My Comments On Your Queries Are Given in Red Fonts Below:-: Prof. Sam
My Comments On Your Queries Are Given in Red Fonts Below:-: Prof. Sam
My Comments On Your Queries Are Given in Red Fonts Below:-: Prof. Sam
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Dear Sir,
You will be pleased to learn that I have received confirmation of
AIQS(affil) membership
Thank you once again for your assistance.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Regards,
Palanivel.V
-----Original Message----From: "Ashfaq MS" <ashfaq.ppm@gmail.com>
Sent: Tuesday, August 13, 2013 4:35pm
To: "Dr. Sam" <drsam@rakfzbc.ae>
Subject: Re: project manager
Hi Sir ,
I was in the class of Nov'12 and remember that you in the lecture have mentioned that contractors
representative on site is by error called as project manager .
can you please explain this.
In the construction industry Project Management is an element in the procurement routes (see the
handout of 10th Session of SCA), and therefore Project Manager is a professional of a different
discipline altogether, providing his services to the project Developer/Client. The correct designation for
the contractor's chief person on site is Contractor's Representative. In recognition of this fact FIDIC
1999 has made this term a defined term as we discuss during the Advanced Class.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Regards
Ashfaq
bin ghalib , dubai
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
bEST rEGARDS,
Alex
----- Original Message ----From: mohamed ifham
To: "sam99@eim.ae" <sam99@eim.ae>
Date: Sun, 28 Jul 2013 09:56:39 +0100 (BST)
Subject: Clarification
Dear Professor,
Hope you doing well.
I am an alumini of SCA from Qatar. Please clarify the below issues.
1. Our project (Design & Build) has a large amount of PS for infrastructure (around 500 million). Can
the contractor claim for materials on site for provisional sum items? Is there any provision in the
contract? (Form of Contract is Ashghal Design and Build 2007 edition). If the instruction to expend the
PS has been issued, and the material approvals have been obtained, then material procured for this
work would be the same as any material procured for the rest of the Works (and could be claimed if
Ashghal contract has a provision for payment for material at site, similar to other standard forms of
contract)
2. In the same contract there is no P&OH percentage is mentioned for PS items. How we can tackle
this issue as a consultant? If the work is instructed on the Contractor, then since it would be valued in
the same manner as Variations are valued, the OH&P % found in the other BOQ rates would be
applicable. If the work is to be done by a Nominated Subcontractor, if there is a % given in the
Appendix to Tender (as in FIDIC forms of contract), it would be applicable, otherwise the parties would
have to establish a % by mutual agreement.
3. Can Contractor request an on-account payment for the said PS works? If yes what is the procedure
and where is mentioned in the Conditions of Contract? If the work is done by the Contractor then the
on-account payment provisions applicable to other scope of Works would be applicable to the PS
work as well. If by nominated Subcontractor, then as and when the Nominated Subcontractor submits
his on-account payment applications pursuant to the provisions in the subcontract, the Contractor can
include them in his monthly payment applications.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Doha - Qatar
Dear Sir,
I am one of your students of SCA Alumni, Please comment about the under recovery of
prelims, We are the subcontractor to the main
contractor.
1) Our BOQ Rate includes prelims. In this case, if the item is omitted, or decrease in the
quanity, how we can recover the prelims for each item which falls under
omission/decrease in quantity.
I have attached conditions of contract of clause 12.3, 12.4. Could you please comment on the
formula, which will be the strong base for our claims.
The under-recoveries of Preliminaries and also the Headoffice overheads resulting from
omitted work can be claimed under Sub-Clause 12.4 (FIDIC 1999), and not under 12.3. What
can be claimed under 12.3 is the under-recovery of direct costs. Both calculations are very
complex and are not possible to be explained in this short Q&A forum. We cover this topic in
great detail with worked examples during the Contract Administration Advanced Class. It
would be very beneficial for your company to send you for the next Advanced Class which
starts on October 4th 2013(which is the last class this year).
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Dear Professor,
Thank you for the Q&A's, it is a big help to further sharpen our skills in contract administration.
I have a case that I would like to refer for your comments.
The project is a franchise of a restaurant chain where my director invested in a branch in the UAE.
The franchisor is contracted by my director to deliver the restaurant ready for occupation. The scope
included the construction of a restaurant in which the franchisor contracted a local contractor to
undertake.
The contract between the franchisor and the contractor is in bespoke form and lumpsum. The
agreement has no reference to any standard form of contract such as FIDIC 4 th Edition. It also has no
reference to the Franchise Agreement between the franchisor and my director.
During the final stage of the project, I was called in by my director to make an independent review of
the final account statement prepared by the contractor and recommended by the franchisor. After
learning that the contract agreement is between the franchisor and the contractor, I advised my
director that we cannot engage or make comment or negotiate directly with the contractor. However, I
told my director that we can recommend our findings for the franchisors consideration.
I have completed my assessment and sent it to the franchisor. The franchisor then coordinated with
the contractor but has failed to agree the figures. In this regard, the franchisor requested us to meet
with the contractor. My director accepted the invitation (as the contractor agreed to meet with us) in
hope that the issue will be resolved. After few meetings, the matter was settled and the final account
agreed.
My questions are the following:
1. Am I correct when I advise my director that we cannot deal directly with the contractor? You
cannot deal with the contractor on contractual / legal matters, but there is no harm in engaging in a
friendly advisory / mediatory role.
2. What will be the implication of us meeting and agreeing the final account with the contractor, can the
contractor deny later on any agreement made between us as my director is not a party to the
contract? Yes.
3. I found lots of inconsistencies with the contractors statement, however the franchisor recommended
it; if the contractor insists on their statement, is there any way of challenging it? This is a matter
between the Franchisor and the Contractor.
4. I am presenting this case in my APC interview and I appreciate if you can give some thoughts on
the same.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Now, I would like to know what is the basis of this formula? Any reason why it has
to be the fifth of the Contract duration?
I appreciate if you could explain this to me since I really need the information
urgently.
There is no standard formula of that nature. LDs per day should be calculated as the pre-estimated loss per day
to the developer and accordingly stated in the Tender Documents.
Where it cannot be estimated (such as for non-completion of a Roads project of a Government Developer)
sometimes formulae of the nature mentioned in your email, is used, but it is solely at the discretion of the parties.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
in any argument that he is carrying out any additional work / tasks that could not be foreseen at the time of
signing the contract.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Best Regards,
Manjula Jayawardana,
Quantity Surveyor
----- Original Message ----From: sanjay dubey
To: "sam99@eim.ae" <sam99@eim.ae>
Date: Mon, 17 Jun 2013 12:36:28 +0800 (SGT)
Subject: quarry
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Regards,
Sanjay Kumar
----- Original Message ----From: Sudheer Edamana
To: "Prof. Sam" <sam99@eim.ae>
Date: Thu, 13 Jun 2013 07:24:37 +0300
Subject: Re: Latest Q&A
Dear Sir,
I have a small issue on a Contractual matter which is as follows:
The contract is Lumpsum, and there is an item for cable intended clearly mentioned in the BOQ discription
up to a stable. We are deleting the stable from the scope of works.
The BOQ quantity for the cable and the actual quantity are different. what quantity to be taken for deletion, based
on BOQ or actual remeasured ?
Actual quantity shown on the contract drawing.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
In one of the other contract it was mentioned that Federal Law of UAE,
for this document we commented as Federal Laws of UAE.
But our Contracts Administrator argue that it should be Federal Law is
only one for UAE thats why it should be Federal Law not Laws.
Federal Laws of the United Arab Emirates and any applicable local laws of
the Emirate of Abu Dhabi, is the correct wording because in addition to
the Federal Laws which are applicable to all the Emirates, each Emirate
has its own Emirati (local) laws.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Shamsundar.Kembhavi
Cost Engineer
----- Original Message ----From: Swaroop Sebastian
To: sam99@eim.ae
Date: Sat, 08 Jun 2013 13:57:32 +0400
Subject: Doubt - Arbitration
Hi Prof Sam,
In one of our Subcontract Agreement we have with a major Contractor in Dubai, the Arbitration clause says "the
place of arbitration shall be the Seat".
What exactly does this mean? If there is a requirement for arbitration, can the arbitration be done in Dubai?
Seat is where the arbitration is conducted and the Award is issued. Check in the Appendix to Tender whether the
Seat is mentioned. If both parties agree, they can select Dubai as the Seat, but remember to state this in the
Arbitration Deed to be signed among the two parties and the arbitrator (i.e. if it is not already mentioned in the
subcontract)
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Best Regards
Swaroop Sebastian
----- Original Message ----From: ayman.el-shaar@strabag.com
To: sam99@eim.ae
Date: Sat, 08 Jun 2013 10:19:39 +0400
Subject: Re: First Set of Questions & Answers
I have a question concerning whether it is a correct practice to apply the retention percentage on the
agreed variations . Yes .
I have worked with different companies and we always apply the retention percentage to the agreed
variation . According to the lecture this is a wrong practice. No, at the lectures we clearly discussed
that Variations are subject to retention (but only up to the limit if Retention).
However, when we read Sub Clause 60.2 (a) of the FIDIC 1987 it states that the retention of the
amount calculated by applying the percentage of retention stated in the Appendix to tender to the
amount to which the Contractor is entitled under paragraphs (a) , (b), (c) and (d) . of Sub Clause
60.1 . Note that (d) is not there it should be (e)
Sub Clause 60.1 (d) states , any other sum to which the Contractor may be entitled under the
Contract . I think you are referring to (e)
The question is , do Variations fall under Sub Clause 60.1(d) , which makes them subject to retention.
Variations are Permanent Works and therefore fall under paragraph (a) and are subject to Retention.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Thank you.
Regards,
Ayman El-Shaar
Dear Sir,
Can you please advice below interpretation is correct or not.
Because I gave my explanation as follows whereas my superior does not agree
with that.
Kindly comment.
Clause 55 (Lump sum ) (OMAN COC)
Your question is not clear and the explanation you are referring to is not apparent from what you have sent.
Both 55 and 56 cannot exist together in a contract. One of them should be deleted. If 55 is deleted, then the
contract is re-measurement type, and therefore all executed work would be re-measured for payment
purposes. If 56 is deleted, then the contract is lump sum type, and therefore only instructed variations would be
measured for valuation purposes, but any errors in the items/quantities would not be corrected as they are at
contractor's risk.
If the Employer forgot to delete one of them, then there is an ambiguity as to whether the contract is lump sum
type or re-measurement type, and therefore the court or the arbitrator would delete the clause which is
unfavourable to the Contractor and declare the contract to be either lump sum type or re-measurement type, as
the case may be, in compliance with the legal requirement of interpreting the ambiguity in favour of the obligor (in
this instance, the contractor).
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Palanivel >V
----- Original Message ----From: Palanivel
To: "'sam99@eim.ae'" <sam99@eim.ae>
Cc: "'palaniqs@gmail.com'" <palaniqs@gmail.com>, "'palanivelvdm@gmail.com'" <palanivelvdm@gmail.com>
Date: Tue, 20 Aug 2013 12:53:54 +0400
Subject: RE: Clause 55 and 56 Oman condition of Contract
Dear Sir,
Estimated
Quantities
55.
(1) The quantities set out in the Bill of Quantities are the
estimated
quantities of the work, but they are not to be taken as the actual and
correct quantities of the Works to be executed by the Contractor in
fulfilment of his obligations under the Contract. The quantities may
vary conforming to the actual site conditions, due to errors or
omissions in the original Bill of Quantities, and on account of
variations. Such errors in, omissions from, or variation to the Bill of
Quantities shall not in any way vitiate or invalidate the Contract, not
shall the Contractor be entitled to any claim whatsoever except as
provided in Clauses 51 and 52 hereof.
Orders for
Variations to be
in Writing
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Kind Regards,
Palanivel .V
From: shakthi
To: sam99@eim.ae
Date: Mon, 06 May 2013 10:44:21 +0400
Subject: Performance secrity
One of the NSC provide the Performance security which is going to expire in another three months time, MC
sent the notification to NSC to extend the Bond for another one year from now because still they are working in
the site (Original Completion date 2nd August 2012) but they refused. To secure the client benefit without facing
any risk as a consultant/MC what are the actions we can take in this situation.
Main Contractor can, after giving the Nominated Subcontractor proper notice to extend, call the Bond on the last day
of its validity and hold that money in an account as security in lieu of the Bond. However it is advisable to obtain
legal advice before taking this action as the type of contract/subcontract and/or the law applicable may or may
not have provisions to do this.
As we discuss in detail during the Advanced Class, under FIDIC 1999 the Employer can call the Bond of the Main
Contractor if it is not extended, and therefore the Main Contractor would use similar remedies on subcontractor.
th
Next Advanced Class starts on October 4 2013(which is the last class this year).
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Kind regards
Siva Shakthi