To: sam99@eim.ae
Date: Mon, 09 Feb 2009 12:11:19 +0400
Subject: RE: Q&A
Dear Sir,
Suppose in a hypothetical project, work started and Final version of the
Agreement has sent to us for the signature. My request for the Varied rates
was rejected during the Draft proposals. There is a provision for Variations
proposed by Contractor but we have to get the approval prior to execution.
The project is involving only the Manpower No material involvement ( say
Software implementation)
My question is we are liable for LDs with the phases of project progress Delay
in any phase leads to LD charges. And our relief is the extension of time with
reasonable effects to mitigate the delay. Claim procedure is silent in the
Contract Agreement.
If we are experiencing delays caused by client. Can we raise a claim for
Idling of our resource staff and acceleration cost when we resume the work
with higher amount of resources than allocated in the Base Line Programme.
There is condition of minimum resource requirement. (1 PMS and 2 Project
Assistants)
Even though contract is silent about the cost impact of the delay arent we
entitle to claim for our reasonable additional cost incurred due to delay.
As we discussed during the 2nd session, it is not necessary for express claim procedure or
references to entitlement to exist in a contract. If the Contractor is not responsible for the
delay, then the Employer cannot levy Liquidated Damages (and therefore time should be
extended). If the Employer is responsible for the delay, then the Contractor can
additionally get his costs reimbursed as damages for breach of contract. If both parties are
not responsible for the delay, still the time should be extended but no cost reimbursement.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Gayantha Abeywardena
Commercial Manager
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
regards
Charles Vince
----- Original Message ----From: rabbay alam alam
To: "Prof.Sam" <sam99@eim.ae>
Date: Thu, 05 Feb 2009 08:03:57 +0000
Subject: Questions
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Thank you.
Regards,
Rabbay Alam
----- Original Message ----From: Moorthy Narayana
To: sam99@eim.ae
Date: Sun, 01 Feb 2009 12:04:46 -0800 (PST)
Subject: Reg.- law clarification -moorthy.
Dear Sir,
Here with I am attaching my question for your comment. I am doing studies related to Bsc qty surveying.for
that I am studying construction law subject for my course. I need your advise and guidance for this question.
thanking you in advance for your kind attention.
truly your`s,
moorthy.
(one of your student)
Question 1.
A detailed response cannot be given in this short answer forum. Suggest you research on
the internet. Some advantages to the Contactor are, awareness of the risk in advance in
order to manage it better, a capped liability, not being penalized etc. Some disadvantages
to the Employer are, inability to recover actual loss during the post contract stage,
inability to fix a higher LD rate or limit in the pre-contract stage (without being held to be
a penalty), etc. (However in the UAE penalties can be included in contracts instead of
LDs.)
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Sackeer Hameem
(TechRICS, MACostE, MAQS, ACIArb)
Contracts Manager
----- Original Message ----From: abdul azeez isma lebbe
To: Prof Sam <sam99@eim.ae>
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Thanks
Buddhika Patikirimudiyanselage
B.Sc (QS) Hons, AAIQS
Quantity Surveyor | Jumeirah Village | PMT | Nakheel PJSC
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Thanks
Weerakoon (1st batch )