Example 1 : ESTIMATE OF RCC ROOF SLAB

Details of Measurements & Calculations of Quantities

Item
No.
1

Particulars of items &


details of works
RCC work 1:2:3
excluding steel & its
bending, but including
centering & shutering &
binding steel
Steel bars including
bending(maild steel in
RCC work- Main bars
12mm dia @ 0.89 kg/m --Straight bars 24cm c/c
(No= ((6.300.80)/0.24)+1=27
Bent up bars 24 cm c/c
(No=((6.30-0.8)/0.24)=26

Distribution bars 6mm


(dia @ 0.22 kg/m)
Bottom bars central
portion 18 cm c/c
(Nos =( 2.00/18 ) + 1=12)
Bottom bars two sides
Top bars two sides

No.

Length Breadth
(m)
(m)

6.3

3.3

Height
or
Quantity
Depth(m)

0.12

2.495
cum

Explanatory notes

No deduction for steel


bars

27

3.44

Side cover 4 cm
L=3.30-2side covers + 2
hooks = 3.300.08+(18x0.12)=3.44m

26

3.52

Adding one depth 8 cm


for two bent ups.

Total

184.4

12

6.33

2x3
2x3

6.33
6.33

@ 0.89
= 184.40

kg/M
*0.89=

164.12
kg

1=6.300.08+(18*0.12)=6.33m

Total

151.92 @
33.42 kg
0.22kg/m
151.92 x
0.22 =
33.42 kg
Total =

197.54
kg
1.975
quintal

Abstract of estimated cost


1

RCC work 1:2:4


exculding steel and its
bending but including
centering and
shuttering and bending
of steel
2.495 cum= 675.00/cum=
RS 1684.12
steel bars including
bending (mild steel ) in
RCC work
1.975 q @ 515.00 per quintel= Rs 1017.13
Total
Rs 2701.25
5% cotige. & WE Rs 135.06
Grand
toatal
2836.31

SCHEDULE OF BARS --- RCC SLAB

Length
Total
Description of
Weight
Shape of Bending Dimensions In cm of each No. Length
bars
(kg)
(m)
(m)
Main straight bars
12 mm. DIA

3.44

27

92.88

Main Bent up bars


12mm dia.

3.52

26
Total

91.52
184.4

Bottom distribution
buting bars
6 mm dia

6.33

18

113.94

Top distributing
Bars 6mm dia

6.33

37.98
151.92

164.12

33.42

EXAMPLE 2
ESTIMATING OF R.C.C BEAM

A detailed estimate of a R.C.C beam of 8m clear span and 75cm x 40cm

Particulars of items
Item No.
& details of works
1

R.C.C. work 1:2:4


excluding steel and
its bending but
including centering
Steel bars including
(mild steel) in R.C.C
work Main bars
22mm dia. Straight

No.

Length Breadth
(m)
(m)

8.6

0.4

8.92

35.68

Height
or
Depth
(m)

Quantity

Explanatory notes

0.75

2.58 cu.m

No deduction for vol. Of


steel bars.

L=8.60-2 end cover + 2


x2.98 kg 106.33 kg hooks= 8.60-(2X4
cm)+(18X22mm) =8.92 m

20 mm dia. bent up
bars @2.47kg/m

9.48

37.92

x 2.47
kg

L=8.60-2 end covers +2


hooks+one depth=8.60-8
93.66 kg
cm +(18X20 mm) +60
cm=9.48 cm

12mm dia top bars


@0.89 kg/m

8.74

17.48

x 0.89
kg

L=8.60-2 end covers +2


15.56 kg hooks = 8.60-8 cm+
(18X12 mm)= 8.74m

Stirrups, 10mm dia.


bars @0.62 kg/m-at
end 12 cm c. to.c.

5x2

2.42

Next at 20 cm c/c

4x2

2.42

18 x

2.42

40.32

14

2.42

14 x

2.42 =

33.88 x

0.22 kg
=

7.45 kg

Total

250.01 kg

Total
Stirrups 6mm dia.
@0.22 kg/m At
central remaining
length of 5.20m at 35
cm c. to c.
Total

2.5 quintal

L=(65X2+32X2 cm)+2
hooks+extra 30 cm = 194
cm + (18X10 mm ) + 30
cm = 2.42m

ABSTRACT OF ESTIMATED COST

Item No.

Particulars of item Quantit


of work
y

Unit

Rate
Rs

R.C.C. work 1:2:4


excluding steel and
its bending but
including centering
and binding of steel

per
P

cost
Rs

2.58

cu.m

675

cu.m

1714.5

2.5

quintal

515

quintal

1287.5

Total

3002

2
Steel bars including
(mild steel) in R.C.C
work Main bars
22mm dia. Straight
bars @ 2.98 kg/m.

Add 3% for contingencies and 2% for workcharged Establishment


Grand Total

3152

Descrip
tion of
bars

Total
Weight(
Length
kg)
(m)

Length of
each (m)

No.

Main
straight
bars 22
mm. DIA

8.92

35.68

106.33

Main Bent
up bars
20mm
dia.

9.48

18.96

46.83

Main Bent
up bars
20mm
dia.

9.48

18.96

46.83

Top
straight
Bars 20
mm dia

8.74

17.48

15.56

Stirrups
10 mm
dia

2.24

18

40.32

25

14

31.36

6.9

Stirrups 6
mm dia

Shape of Bending Dimensions In cm

Note -- (i) If centering and shuttering is paid separately , the area and xost can be found as follows
Area of centering and shuttering = Bottom and two vertical sides x length + two ends
[(40 cm + 2 x 75 cm ) x 8.60 m] + (2 x 40 cm x 75 cm ) = (1.90 x 8.60 ) + ( 2x 0.40 x 0.75 )
:= 16.34 + 0.60 = 16.94 sq

Cost of centering and shuttering @ Rs 20.00 per sq.m = 16.94 x20.00 = 338.80
(ii) For over lapping at joints 5% of the whole steel may be provided in the estimate .

RCC COLUMN WITH FOUNDATION

Example 3: Prepare a detailed estimate of a RCC column with foundation footing

Earth work in excavation in


foundation
1x2.00x2.00x0.83m

Cement concrete 1:4:8 in base


1x2.00x2.00x0.08m= 0.32 cu.m

RCC work 1:2:4 in footing


excluding steel and its bending
but including centering and
shuttering and binding steel
Bottom square portion
1x2.00x2.00x0.25m
Trapezoidal portion vol..
=
h/6(A1+A2+4Am)

3.32 cu.m

1.00 cu.m

0.50/6 {0.22 + 0.352 + 4( 2 + 0.35 )2/ 2} = 0.804 cu.m


Total
4

1.804 cu.m

RCC Work 1:2:4 in column above


G.L excluding steel and its
bending but including centering
and shuttering and binding steel
Square portion below plinth level
1x0.35x0.35x60

0.074cu.m

Cicular portion above plinth level


1x(3.14x0.302)/4x3.30

0.233 cu.m

Total

0.307 cu.m

Steel reinforcing bars including bending -(I) 12 mm Dia bars @ 0.89 kg in base footing
No of bars = (200 cm - 8 cm ) /15cm + 1 = 14 nos one way
L = 200 -2 cover +2 hooks = 200 - 2x4 +18x1.2 = 213.6 = 2.14 cm
(ii) 16 mm dia dowel bars @ 1.58 kgs
..
(L= 0.45+0.75-cover + bend = 1.20 - 0.80 + 0.15 = 1.27m

6 nos x 1.27 x 1.58 = 12.04 kg

..

6 nos x 4.10 x 1.58 = 38.87 kg

(iii) 16 mm dia bars @ 1.58 kgs in column


(L= 3.30 +0.60 +0.10 +0.10 = 4.10m

(iv) 10 mm dia bars @ 0.62 kgs in lateral ties ..


Lateral ties

No = (3.90/0.15) + 1 = 27 nos
L = (3.14 x 0.22) = 0.70 m

27 nos x 0.70 x 0.62 = 11.72 kg


Total

115.96kg
1.16q

ABSTRACT OF COST
Item no
1
2

Name of items and details of


work
Earthwork in excavation in
foundation
Cement concrete 1:4:8 in base
with brick ballast
RCC work 1:2:4 in footing
excluding steel and its bending
but including centering and
shuttering and binding steel

Rate
(Rs.P)
350 per
3.32 cu.m
cu.m
300per
0.32cu.m
cu.m
Quantity

1.804cu.m

11.62
96

625per
cu.m
1127.5

RCC Work 1:2:4 in column above


G.L excluding steel and its
590per
0.307cu.m
bending but including centering
cu.m
and shuttering and binding steel
Steel reinforcing bars including
bending --

Amount
(Rs.P)

1.16q

515per
cu.m
Total

Add 5% for Contingences and Worcharged Establishment


Grand
Total

181.13
597.4
2013.65
100.68
2114.33

Note -- Centering and shuttering if required may be estimated separately as follows


Footing trapezium portion ---

4 nos x (2.00+0.35) / 2 x sloping height


4x1.175xsqrt{ (0.825)2+ 0.522 }
=

4.531 sq.m

Square portion above GL upto plinth level

4 nos x 0.35 x 0.45

0.630 sq.m

Cicular portion above plinth level

(3.14 x 0.30 ) x 3.30

3.109 sq.m

---

Total =

8.27sq.m

Example 4
A detailed estimate of R.C.C.
Staircase

Details of Measurement and calculation of Quantities


Item No.

Particulars of item and


details of works

R.C.C. work 1:2:4


excluding steel and its bending
but including centering and
bending steel-Base of flights in ground floor
slab of flights(inclined)
Landing middle and first floor

No.

length
m

breadth
m

1
2
2

1.2
3.12
2.7

0.5
1.2
1.35

height or depth Quantity


m

0.25
0.15
0.15
total

0.15
1.156
1.094
2.4

Explanatory notes

bearing 15cm
cu m

Brickwork in steps in 1:4


cement mortar(cut brickwork)

1.2

1/2(.25.25)

0.495

cu m

20mm cement plaster 1:6


in steps finfshed neat cement
floating-Tread and rise
Ends of steps

2
2

1.2
1/2(.25.25)

(.25.25)
Total

10.56
0.41
10.97

sq m

2.5cm Nosing in steps


in 1:3 cement mortar

2.5cm c.c floor 1:2:4 finished


neat cement floating in landing
middle and first floor

1.2

28.8

2.7

1.2

6.48

sq m

Item No.
6

Particulars of item and


details of works
steel work
including bending in rinforcement and railing
(i)12mm Dia. bar@0.86kg in
R.C.C work--main bars in
landing
No of bars 120/12=11
main bars in upper fright and
middle and first floor landing

No.

length
m

11

5.22

L=4.10+0.90+0.18

11

6.25

Top bars first floor landing

11

1.8

L=1.3+3.7+1.05+
.18+0.12=6.25m
L=1.08+.61+9.012

Extrs bsrs first floor middle


of each landing

1.49

Total

148.950.86

(ii)8mm Dia distributing bars@


0.39kg in R.C.C work
Lower flight 15nos and
upper flight 14nos

29

1.27

L=1.2-2cover+
2hooks=1.27m

middle landing 9nos and upper


landing 8 nos

17

2.77

L=2.70-2cover+
2hooks=2.77m

(iii) 16mm sq bars in railing@


2.01kg

47

breadth
m

height or depth Quantity


m

L=1.2+.15-2cover+
2hooks=1.49m
132.56kg

83.92

0.39

0.90

2.01

32.73kg

Total

R.C.C 1:2:4 hand rail includive


reinforcement centering and
shuttering finished neat cement
floating with moulding

6.82

R.C.C 1:2:4 Newal posts


including steel reinforcement
and from work finished
Ground floor
first floor

1
1

1
0.9

Caps of Newal post of c.c

Explanatory notes

0.1
0.1

0.1
0.1
Total

85.02kg
250.3kg
2.503q

6.82rm

L=23.21+0.40=6.82

0.01
0.01
0.02

cu m

2 nos

ABSTRACT ESTIMATE
Item No.

Particulars of item and


details of works

Quantity

Unit

Rate
Rs
P

per

cost
Rs
P

2.4

cu m

775

/cu m

1860

Brickwork in steps in 1:4


cement mortar(cut brickwork)

0.495

cu m

365

/cu m

180.68

20mm cement plaster 1:6


in steps finfshed neat cement
floating--

10.97

sq m

9.5

/sq m

104.22

2.5cm Nosing in steps


in 1:3 cement mortar

28.8

rm

5.5

/r m

158.4

2.5cm c.c floor 1:2:4 finished


neat cement floating

6.48

sq m

18

/sq m

116.64

2.503

515

/q

1289.05

R.C.C 1:2:4 hand rail includive


reinforcement centering and
shuttering finished neat cement
floating with moulding

6.82

rm

24

/r m

163.68

R.C.C 1:2:4 Newal posts


including steel reinforcement
and from work

0.02

cu m

675

/cu m

13.5

nos

10

each
Total

20
3905.17
117.18
78.12
4101.47

R.C.C. work 1:2:4


excluding steel and its bending
but including centering and
bending steel--

steel work
including bending in rinforcement and railing

Caps of Newal post of c.c

Add 3%for contingenvies


Add 2% Workcharged Establishment
Grand Total