Is 11223 1985
Is 11223 1985
Is 11223 1985
Whereas the Parliament of India has set out to provide a practical regime of right to
information for citizens to secure access to information under the control of public authorities,
in order to promote transparency and accountability in the working of every public authority,
and whereas the attached publication of the Bureau of Indian Standards is of particular interest
to the public, particularly disadvantaged communities and those engaged in the pursuit of
education and knowledge, the attached public safety standard is made available to promote the
timely dissemination of this information in an accurate manner to the public.
1 +, 1 +
01 ' 5
Jawaharlal Nehru
! $ ' +-
Satyanarayan Gangaram Pitroda
! > 0 B
BharthariNtiatakam
( Reaffirmed 2004 )
IS : 11223- 1985
Indian Standard
GUIDELINES
FIXING SPILLWAY
FOR
CAPACITY
Chairman
SHRI
Irrigation Department,
Gandhinagar
J. F. MISTRY
Government
of Gujarat,
Members
SHRI R.
K.
Irrigation Department,Govemment
Lucknow
AGGARWAI.
of Uttar Pradesh,
CAlternate )
SUPERINTENDING ENGINEER
( DAMS ) ( Afternare )
CHIEF ENGINEER & DIRECTOR
CHIEF ENGINEER ( PWD )
SUPERINTENDING ENGINEER
( DESIGNS ) ( Alternate )
CHIEF ENGINEER/R-CUi?t-DIRECTOR
CHIEF ENGINEER, THEIN DAM
DESIGN
DIRECTOR ( SPILLWAYS &
POWER PLANT ) ( Alternate }
SHRI M. L. DAS
Government
of
Punjab,
IS : 11223- 1985
( Continued from page 1 )
Representing
Members
DR JACDISH NARAIN
SHRI G. RAMAN,
Director ( Civ Engg )
Director
SHRI S. P. JAIN
SHRI J. C. BASUR( Alternate )
Jainrakash Associated Pvt Ltd. New Delhi
SHRI D. G. KADKADE
SHRI A. B. ODAK ( Alternate )
Irrigation Department,
Government
of Haryana,
SHRI H. K. KHOSLA
Chandigarh
SHRI M. L. GUPTA ( Alternate)
Irrigation Department,
Government
of Gujarat,
SHRI M. U. PUROHIT
Gandhinagar
SHRI N. B. DESAI ( Alternate )
Karnataka Power Corporation Ltd, Bangalore
SHRI M. S. RAMA RAO
Irrigation Department, Government of Tamil Nadu,
REPRESENTATIVE
Madras
The Hindustan Construction Co Ltd, Bombay
SHRI D. M. SAVUR
Secretary
SHRI K. K. SHARMA
Deputy Director ( Civ Engg ), IS1
IS : 11223- 1985
Indian Standard
GUIDELINES
FIXING SPILLWAY
FOR
CAPACITY
0. FOREWORD
0.1 This Indian Standard was adopted by the Indian Standards Institution
structure
or property
is
IS : 11223- 1985
e) to economize the dam design by adopting
an appropriate
nation of surcharge storage versus spillway capacity.
combi-
1. SCOPE
1.1 This
2. TERMINOLOGY
2.0 For the purpose of this standard, the following definitions in addition
to those given in IS:4410* shall apply.
2.1 Probable Maximum Flood ( PMF ) - It is the flood that may be
expected from the most severe combination of critical meteorological and
hydrological condition that are reasonably possible in the region and is
computed by using the Probable Maximum Storm which is an estimate of
the physical upper limit to maximum precipitation for the basin. This is
obtained from transposition studies of the storms that have occurred over
the region and maximising them for the most critical atmospheric
conditions.
2.2 Return Period Flood - A flood with a return period of T year (T
year flood) is defined as a flood that is expected, on the average, to be
equalled or exceeded once in T years. Thus the probability of occurrence
of a flood equalling or exceeding the T year flood is l/T.
NOTE - The T year flood should specify the flood element (for example peak
discharge volume, volume above a threshold, etc) which is considered in the probability analysis.
While using this concept in application, the flood element to be used
in the analysis is to be decided with reference to the engineering design requirements.
IS : 11223 - 1985
2.5 Surcharge Storage-It
of resulting performance
a) The highest water level reached in the flood studies, that is, in
particular:
1) Free board available at this level,
2) Clearances of gates available at this level,
3) Upstream submergence corresponding
IS : 11223- 1985
b) Inflow
works -
eficient
operation of energy
dissipation
of extent of down-
3.1.2 The dams may be classified according to size by using the hydraulic
head (from normal or annual average flood level on the downstream to the
maximum water level) and the gross storage behind the dam as given
below. The overall size classification for the dam would be the greater of
that indicated by either of the following two parameters:
Classification
Small
Intermediate
Large
Gross Storage
Hydraulic Head
3.1.3 The inflow design flood for safety of the dam would be as follows:
Size as Determined in 3.1.2
Safety of Dam
Small
Intermediate
SPF
Large
PMF
IS : 11223 - 1985
future human settlements, the PMF should be used. Any departure from
the general criteria as above on account of larger or smaller hazard should
be clearly brought out and recorded.
3.1.4 Inffow design flood for efficient operation of energy dissipation
work - For some dams, inflow design flood for the safety of the dam may
not undermine the dam foundation and endanger its safety. Also for
some dams, breaching sections or auxillary spillways may be provided such
that the breach of this breaching section or operation of the auxillary
spillway also may not undermine the dam foundation and endanger its
safety and in addition these may not lead to uncontrolled widening of the
breach or loss of life. Under these conditions the energy dissipation
arrangements for the main spillway may be designed for best efficiency for
a smaller inflow flood than the inflow design flood for the safety of
the dam.
3.1.5 For the two types of inflow design floods (see 3.1.3 and 3.1.4 )
for intermediate and large dams the design situation would consist of
the flood followed or preceded by a 25 year flood, if two large floods have
occurred in close succession in the region in the past. The period between
the floods, or between the two storms if the bloods are generated through
storm rainfall, may be reasonably small and may be decided after the
analysis of the past data.
The duration of the standard project or maximum probable storm to
be considered depends on the storm characteristics of the region, basin
characteristics and characteristics of the proposed engineering work.
For
attaining the highest possible peak discharge, the rainfall period should
not be less than the base period of the unit hydrograph where a considerable
reduction in the peak through the dam is envisaged, the volume of the
flood in the routed portion becomes important, and longer duration rainfall
would have to be considered.
Where a T year flood is to be used through probability analysis,
any value between and including the expected value of the flood, as
indicated by the analysis to be 95 percent upper confidence band value, may
be used depending on the importance of the structure, length of data, etc.
3.2 Initial Level and Outflow - For routing of the inflow design floods
( see 3.1.3 and 3.1.4 ) following conditions shall be used:
a) The initial level, when the flood impinges, would be the top of
conservation pool level. For ungated spillways this would correspond to the spillway crest or a little above this [ see 3.2 (c) 1.
For reservoirs not having a permanent flood control pool this will
correspond to top of gate level. Where by rule-curve operation,
a part of the conservation capacity is proposed to be used as a
7
IS : 11223 - 1985
joint use capacity towards flood control also, the top of conservation level will be used and not the rule-curve level. For
projects having permanent flood control pool, the actual initial
level may be in between the top of conservation pool and top of
flood pool depending on the flow sequences before the flood.
A
Where
sequence of 25 year and design flood should be adopted.
such sequence is used, it would be admissible to use the top of
conservation
pool as the initial level. However, where the
sequence is not used, the initial level may correspond to the level
at which 50 percent of the permanent flood control storage is
occupied.
IS : 11223- 1985
3.5.2 Whether or not flood control is a stated purpose, rules for operation
under normal floods may initially provide a restrictron on the outflow
or on its rate of change. Only at a later stage of a larger flood, the flood
would be recognized as a large one, and emergency schedule permitting
unrestricted outflow may come into force. These possibilities should be
reflected in the computations of reservoir simulation under both the design
floods ( see 3.1.3 and 3.1.4 ).
3.6 Mechanical
Design Condition III : Under inflow design flood for energy dissipation
works and with inoperative gates as in 3.6.1.
Design Condition IV : Under inflow design Aood for energy dissipation
works and with all gates operative.
4.1 Free-Board and Clearances - The free-board as specified in relevant
Indian Standards ( see IS:6512-1984* and IS: 10635-1983t ) should be
available at FRL as also at MWL which would correspond to Design
Condition II.
4.1.1 A reduced free-board may be acceptable under Design Condition I
assumed as an emergency condition ( like earthquake ).
4.1.2 Similarly, normal clearance from and clearance in the energy dissipation structure should be available for Design Condition II and lower
acceptable clearances for Design Condition I.
*Criteria for design and solid gravity dams (first revision ).
TGuidelines for freeboard requirements in embankment dams,
IS : 11223 - 1985
4.2 Upstream Submergence Consideration - This depends on local condiExcept for very
tion, type of property and effects of its submergence.
important structures upstream like power houses, mines, etc, for which
levels corresponding to SPF or PMF may be used; smaller design floods
and levels attained under these may suffice. In general a 25-year flood for
land acquisition and 50-year flood for built up property acquisition may be
adopted.
4.3 Downstream Submergence Consideration - This depends on local conditions, the type of property and elects of its submergence. Except for very
important facilities like power houses, for which outflows obtained under
condition II or of that order may be relevant. Normally the discharge relevant to check the acceptability of downstream submergence condition may
be smaller than those for power houses at or near the toe of the dam.
Normally damage due to physical flooding may not be allowed for Design
Condition II, but disruption of operation may be allowed.
5. GENERAL CONSIDERATIONS
5.1 Breaching Sections - If a suitable site is available in a separate saddle,
a breaching section may be provided.
The top level of the earth dam
provided in the saddle should be kept lower than the top level of the main
dam so that the earth dam in the saddle gets breached due to overtopping
in the event of high water level. This would relieve the pressure on the
main dam. It should be seen that no habitation or valuable property exists
downstream of the saddle and the damage caused by way of the breach is
minimum.
5.2 Although the primary purpose of the spillway as stated in 0.3, that is
to eliminate or reduce the artificial hazard due to failure of dam forms the
main scope of the standard other purposes as mentioned in 0.4 also require
careful considerations.
5.2.1 It seems preferable to provide at least a small surcharge storage so
that the maximum water level reached even under the design floods with
all gates functioning is higher than the full reservoir level (or the maximum
controlled water level in case surcharging is planned).
This would allow a
moderation of the high floods so that the hydrologic effects of the
reservoir in reducing valley storage and travel times are countered. Such a
margin would also give a slight flexibility in gate operation and reduce the
effects of human failures.
5.2.2 Where flood control downstream of the dam is proposed to be
achieved, it is necessary to have a rigorous study based on simulation of
the reservoir under a number of floods.
5.2.3 Techno-economic studies for sizing of spillway vis-a-vis sizing of
surcharge capacity need to be done for all important dams.
10
$Nl#MENP NO, 1
DECEMBER L990
TO
___
__-._.;
,. ___....
IS 11223
: 1985GUIDELINESFOR FIXING
SPILLWAY CAPACITY
t0 top Of tbil.~
( Puge 6, clause 3.13, fist setuence ) - Substitute the following for the
existing sentence :
The dams may be classified according to size by using the static head at FRL
( from l%L to the minimum tail water level ) and the gross storage behind the
dam as given below :
( Puge 6, clause 3.13,
Hydraulic
Had_
_...______.
line 6 ) _.
A_._
(RVDlO)
,
. .
Reprography hit,