Professional Documents
Culture Documents
Ce Wre 50 MCQ
Ce Wre 50 MCQ
A dam reservoir which is not provided with gate controls on its spillway and other
sluices is called ________________
a) detention dam
b) storage reservoir
c) retarding basin
d) flood control reservoir
View Answer
Answer: c
Explanation: Storage reservoir is the one having gates and valves installed at its
spillway and at its sluice outlets. The retarding basin is the one with uncontrolled and
ungated outlets. The cost of gate installation is saved and there are no gates hence,
the possibility of human error and negligence in their operation is eliminated.
2. A hydel power project has been envisaged to serve the water supply and irrigation
needs of the area at its inception stage. The dam reservoir so constructed is known
as __________________
a) multipurpose reservoir
b) single-purpose reservoir
c) distribution reservoir
d) retarding reservoir
View Answer
Answer: a
Explanation: A reservoir planned and constructed to serve various purposes together
is a multipurpose reservoir. It is designed to protect the downstream areas from
floods, to conserve water, irrigation, industrial needs, hydroelectric purposes, etc.
Bhakra dam and Nagarjuna Sagar dam are important multipurpose dams.
3. A dam reservoir catering to flood control, irrigation, and water supply basically
designed for irrigation alone is a _______________-
a) multipurpose reservoir
b) single-purpose reservoir
c) distribution reservoir
d) retarding basins
View Answer
Answer: b
Explanation: A reservoir planned, designed and constructed for one purpose is
called a single purpose reservoir whereas a reservoir planned and constructed to
serve various purposes together is a multipurpose reservoir. A small storage
reservoir constructed within a city water supply system is called distribution reservoir
4. Which reservoir is also known as Mitigation reservoir?
a) Conservation reservoir
b) Flood control reservoir
c) Multipurpose dam
d) Storage reservoir
View Answer
Answer: b
Explanation: A flood control reservoir protects the downstream areas by storing a
portion of the flood flows to minimize the flood peaks. The entire inflow entering the
reservoir is discharged or gradually released to recover the capacity for the next
flood. It is also called as a mitigation reservoir.
5. A reservoir having gates and valves installation at its spillway and at its sluice
outlets ___________
a) storage reservoir
b) retarding basin
c) both storage and retarding reservoir
d) distribution reservoir
View Answer
Answer: a
Explanation: Storage reservoir is the one having gates and valves installed at its
spillway and at its sluice outlets whereas retarding basin is the one with uncontrolled
and ungated outlets. It provides more flexibility in operation and better control.
6. Which reservoir is helpful in permitting the pumps or the water treatment plants to
work at a uniform rate?
a) Storage reservoir
b) Detention reservoir
c) Multipurpose reservoir
d) Distribution reservoir
View Answer
Answer: d
Explanation: A small storage reservoir constructed within a city water supply system
is called a distribution reservoir. It stores water during hours of no demand or less
demand and supply water from their storage during the critical time of maximum
demand.
7. In which of the following reservoir the flood crest downstream can be better
controlled and regulated properly?
a) Distribution reservoir
b) Multipurpose reservoir
c) Storage reservoir
d) Retarding reservoir
View Answer
Answer: c
Explanation: Storage reservoirs are preferred on large rivers and require better
control. It is provided with gated spillway and sluiceways for more flexibility of
operation, better control and to increase the usefulness of the reservoir.
8. What are the types of flood control reservoirs?
a) Multipurpose reservoir and Single purpose reservoir
b) Storage reservoir and retarding reservoirs
c) Distribution reservoir and Storage reservoir
d) Distribution reservoir and multipurpose reservoir
View Answer
Answer: b
Explanation: There are two basic types of flood-mitigation reservoirs i.e. storage
reservoir and retarding reservoirs. Storage reservoir is the one having gates and
valves installed at its spillway and at its sluice outlets whereas the retarding basin is
the one with uncontrolled and ungated outlets.
9. As the reservoir elevation increases, the outflow discharge increases.
a) True
b) False
View Answer
Answer: a
Explanation: When floods occur the reservoir gets filled and discharges through
sluiceways and the water level goes on rising until the flood has subsided. The inflow
becomes equal or less than the outflow. The water gets completely withdrawn until
the stored water is completely discharged.
10. The maximum discharging capacity of a retarding reservoir should not be equal
to the maximum safe carrying capacity of the channel downstream.
a) True
b) False
View Answer
Answer: b
Explanation: Since the retarding reservoir is not always filled much of the land below
the maximum reservoir level will be submerged only temporarily and occasionally.
The automatic regulation of outflow depends upon the availability of water. The
maximum discharging capacity should be equal to the maximum safe capacity of the
channel d/s.
1. The design annual rainfall for the catchment of a proposed reservoir has been
computed to be 99 cm. The catchment area contributing to the proposed reservoir is
1000 sq.km having a mean annual temperature of 20°C. Calculate the annual design
catchment yield for the reservoir using Khosla’s formula.
a) 89.4 M.m3
b) 8.94 M.m3
c) 894 m3
d) 894 M.m3
View Answer
Answer: d
Explanation: Using Khosla’s formula –
Q = P – 0.48 Tm where, Rainfall (P) = 99 cm and Mean annual temperature (Tm) =
20°C
Q = 99 – 0.48 x 20 = 89.4 cm = 0.894 m
The total yield produced from the given catchment = 0.894 x 1000 x 10 6 = 894 M.m3.
2. The reservoir capacity cannot exceed the catchment yield.
a) True
b) False
View Answer
Answer: a
Explanation: The reservoir capacity is fixed at a value which is lesser of the value of
–
i. The accessed gross storage required to meet the demand
ii. The accessed dependable yield for the reservoir site.
3. With the reduction in reservoir capacity over the passage of time, the trap
efficiency ___________
a) increases
b) decreases
c) remains unaffected
d) may increase or decrease depending upon the reservoir characteristics
View Answer
Answer: b
Explanation: If the reservoir capacity reduces with constant inflow value, the trap
efficiency reduces. Hence, for small reservoirs having small capacity on large rivers
having large inflow rates, the trap efficiency is extremely low.
4. Trap efficiency of a storage reservoir is defined as the ratio of
___________________
a) total annual sediment inflow to the reservoir capacity
b) total sediment deposited in a given period to the total sediment inflow in that
period
c) total annual sediment deposited in the reservoir to the dead storage capacity of
the reservoir
d) reservoir capacity to the total annual sediment
View Answer
Answer: b
Explanation: Trap efficiency of a storage reservoir is defined as the ratio of the total
sediment deposited in a given period to the total sediment inflow in that period. It can
be defined as the percentage of sediment deposited in the reservoir in spite of taking
precautionary control measures.
5. Capacity inflow ratio for a storage reservoir is defined as the ratio of
_______________________
a) reservoir capacity to the average annual flood inflow
b) reservoir capacity to the average annual sediment inflow
c) the dead storage capacity of the reservoir to the average annual sediment
deposited
d) total annual sediment inflow to the reservoir capacity
View Answer
Answer: a
Explanation: Capacity-inflow ratio can be defined as the ratio of the reservoir
capacity to the total inflow of water. The trap efficient is a function of the capacity-
inflow ratio which is represented by a graph between them.
6. The capacity-inflow ratio for a reservoir _________________
a) is a constant factor overtime
b) increases with time
c) decreases with time
d) may increase or decrease with time
View Answer
Answer: c
Explanation: The silting rate in the reservoir will be more in the beginning as its
capacity reduces due to silting, the silting rate will also reduce. The trap efficiency is
a function of capacity. The capacity reduces when trap efficiency reduces and lesser
sediment is trapped.
7. A sequent peak algorithm is a plot between __________________
a) Accumulated flow v/s time
b) Discharge v/s time
c) (Cumulative Inflow – Cumulative Outflow) v/s time
d) Mass outflow v/s time
View Answer
Answer: d
Explanation: It is a plot between time on X-axis and cumulative net flow on Y-axis. It
is an excellent alternative to the mass-curve method of determining reservoir
capacity. The positive value of cumulative net flow indicates a surplus of inflow and a
negative value indicates a deficit of inflow.
8. A flow duration curve is a curve plotted between ________________
a) Accumulated flow v/s time
b) Discharge v/s time
c) (Cumulative Inflow – Cumulative Outflow) v/s time
d) Streamflow v/s Percent of time the flow is equaled or exceeded
View Answer
Answer: d
Explanation: A flow-duration curve is a curve plotted between the streamflow and the
percent of the time the flow is equaled or exceeded. It is also called a discharge-
frequency curve and it represents the cumulative frequency distribution.
9. A steep slope of the flow duration curve indicates a stream with
_________________
a) highly variable discharge
b) small variability of flow
c) considerable base flow
d) large flood plains
View Answer
Answer: a
Explanation: A steep slope represents a stream with highly variable discharge and a
flat slope represents a small variability of flow. The considerable base flow is
indicated by a flat portion on the lower end of the curve and the upper end of the
curve is of river basins having large flood plains.
10. The lowest portion of the capacity-elevation curve of a proposed irrigation
reservoir draining 20 km2 of catchment is represented by the following data:
i. The rate of silting for the catchment = 300 m3 / km2 / year
ii. Life of the reservoir = 50 years
iii. Dead storage = 30
iv. The FSD of the canal at the head = 80 cm
v. The crop water requirement = 250 ha.m
vi. Dependable yield of the catchment = 0.29 m
Calculate the gross capacity of the reservoir.
a) 287.5 ha.m
b) 317.5 ha.m
c) 580 ha.m
d) 37.5 ha.m
View Answer
Answer: b
Explanation: Net water demand = 250 ha.m and Reservoir losses = 15% x 250 =
37.5 ha.m
Live storage to meet the given demand = 250 + 37.5 = 287.5 ha.m
Gross storage required to meet the demand = live storage + dead storage = 287.5 +
30 = 317.5 ha.m
Dependable yield = 0.29 x 20 x 106 = 580 ha.m
The gross capacity is fixed at the lesser value of the gross storage and the
dependable yield. Hence, the reservoir capacity = 317.5 ha.m.
1. As the height of a proposed dam is increased, the cost per unit of storage initially
increases and then decreases.
a) True
b) False
View Answer
Answer: b
Explanation: The cost per unit storage of the dam initially decreases reaches to a
certain minimum value and then increases when the height of the dam is increased.
This lowest point on the curve gives the economical height for which the cost per unit
storage is minimum.
2. The economical height of a dam is that height for which the
____________________
a) cost per unit of storage is minimum
b) benefit-cost ratio is maximum
c) net benefits are maximum
d) benefit-cost ratio is minimum
View Answer
Answer: a
Explanation: The height of the dam corresponding to which the cost of the dam per
unit storage is minimum is the economical height of the dam. The cost per unit
storage of the dam initially decreases reaches to a certain minimum value and then
increases when the height of the dam is increased.
3. If 20% of the reservoir capacity is earmarked for dead storage in a storage
reservoir of 30 M.cum and the average annual silt deposition in the reservoir is 0.1 M
cum, then the useful life of the reservoir will start reducing after ____________
a) 60 years
b) 120 years
c) 240 years
d) 300 years
View Answer
Answer: a
Explanation: Given, Reservoir capacity = 30 M.cum
Dead storage is 20% of the reservoir capacity = 0.2 x 30 = 6 M.cum
Time during which 6 M cum is filled by sediment @0.1 M.cum/yr = 6/0.1 = 60 years.
4. According to the Central Water Commission, the average annual evaporation loss
is estimated to be _____________
a) 100 cm
b) 125 cm
c) 225 cm
d) 250 cm
View Answer
Answer: c
Explanation: The Central Water Commission in 1990 has estimated the average
annual evaporation loss to be 225 cm on the basis of a review conducted on 130
sample reservoirs. The estimated total water loss from all the existing reservoirs to
be 27000 Mm3 per annum.
5. Windbreakers, Integrated operation of reservoirs and Use of underground storage
are all methods of ______________________
a) evaporation control
b) estimation of absorption losses
c) estimation of absorption losses
d) estimation of reservoir leakage
View Answer
Answer: a
Explanation: The following are some of the methods of evaporation control such as
Windbreakers, Reduction in the exposed water surface, Use of underground storage
rather than surface storage, Integrated operation of reservoirs, and Use of chemical
for retarding the evaporation rate from the reservoir surface. Use of Water Evapo-
Retardants (WERs) is considered to be an only practical solution for the
conservation of freshwater in spite of its limitations and disadvantages.
6. Which of the following is not used as WERs?
a) Hexa decanol
b) Octa decanol
c) Docosanol
d) Cyclohexanol
View Answer
Answer: d
Explanation: Fatty alcohols like Cetyl alcohol (popularly known as Hexa decanol),
Stearyl alcohol (also called Octadecanol), and Behenyl alcohol (also called
docosanol) are found to be quite suitable. A mixture of these chemicals have also
been generally used and the chemicals should be 99% pure for getting the desired
properties of the monolayer.
7. Which of the following dam is situated in the seismologically inactive zone in
Peninsular India?
a) Koyna dam
b) Hirakud dam
c) Tehri dam
d) Idukki dam
View Answer
Answer: a
Explanation: A very strange phenomenon has been observed in several dams of the
world, the reservoir basins which were seismologically inactive started showing
seismic activities when the reservoir was filled up with water. Koyna dam
(Maharashtra) is an important example of such a case.
8. Which of the following measure does not prevent or reduce the intensity of the
earthquake?
a) Filling the reservoir up to a limited safe level
b) Draining out water from weaker adjoining rocks
c) Active exploration of the dam site for the absence of inactive faults before
selecting the same
d) Increasing the pore pressure
View Answer
Answer: d
Explanation: Earthquakes occur due to increased pore-pressure in the adjoining
rocks which lowers their shearing strength resulting in the release of tectonic strain.
Draining out water from weaker adjoining rocks actually reduces pore pressure.
9. Which of the following guideline is incorrect for the selection of a suitable site for a
reservoir?
a) The geological formation should be such that it entails minimum leakage
b) The cost of the dam is a controlling factor
c) Too much silt-laden tributaries should be avoided as far as possible
d) The reservoir basin should have a shallow wide opening in the valley
View Answer
Answer: d
Explanation: The site should be such that a deep reservoir is formed because of
lower land cost per unit of capacity, less evaporation loss, and less possibility of
weed growth as compared to shallow ones. The basin should have a narrow opening
so that the length of the dam is minimum.
1. The vertical component of the earthquake wave which produces adverse effects
on the stability of a dam when is acting in ____________________
a) upward direction
b) downward direction
c) both upward and downward direction
d) any direction
View Answer
Answer: b
Explanation: When the vertical acceleration is acting downward the foundation try to
move downward away from the dam body. This reduces the effective weight and the
stability of the dam. It is the worst case for design.
2. The horizontal component of an earthquake wave producing instability in a dam is
the one which acts __________________
a) towards the reservoir
b) towards the dam
c) away from the reservoir
d) away from the dam
View Answer
Answer: a
Explanation: Hydrodynamic pressure and horizontal inertia force are caused by the
horizontal acceleration of an earthquake wave acting towards the reservoir. As the
foundation and dam accelerate towards the reservoir there is an increase in the
water pressure which is resisted by water, the extra pressure is hydrodynamic
pressure.
3. The vertical downward earthquake acceleration av = 0.1g acting on a gravity dam
will ________________________
a) increase the resisting weight of the dam by 10%
b) decrease the resisting weight of the dam by 10%
c) increase the uplift by 10%
d) decrease the uplift by 10%
View Answer
Answer: b
Explanation: The net effective weight of the dam is given as W [1 – Kv] and vertical
acceleration av = Kv.g = 0.1.g i.e 10%
where W is the total weight of the dam and Kv is the fraction of gravity adopted for
vertical acceleration.
This is considered as the worst case for design as the foundation tries to move
downward away from the dam body when there is downward vertical acceleration.
This reduces the effective weight and the stability of the dam.
4. A gravity dam is subjected to hydrodynamic pressure caused by __________
a) the rising waves of the reservoir when a flood wave enters into it
b) the rising waves in the reservoir due to high winds
c) the increase in water pressure momentarily caused by the horizontal earthquake
acting towards the reservoir
d) the increase in water pressure momentarily caused by the horizontal earthquake
acting towards the dam
View Answer
5. In a concrete gravity dam with a vertical upstream face the stabilising force is
provided by the ___________________
a) weight of the dam
b) the water supported against the upstream slope
c) uplift pressure
d) water pressure at the tail end
View Answer
Answer: a
Explanation: The major resisting force is the weight of the dam body and its
foundation. A unit length of the dam is considered in the 2D analysis of a gravity
dam. The resultant of all the downward forces will represent the total weight of the
dam acting on it.
6. What is the value of horizontal destabilizing force caused by the formation of
waves in a storage reservoir having a fetch of 52 km due to high wind of 172 km/h?
a) 30 KN
b) 60 KN
c) 130 KN
d) 180 KN
View Answer
Answer: d
Explanation: When F > 32 km, the wave height is given by h w = 0.032 (V.F)1/2
hw = 0.032 (172 x 52)1/2 = 3.02 m
The force caused by waves is given by the equation – Pw = 19.62 hw2 KN/m run of
the dam
Pw = 19.62 x 3.022 = 179.69 KN.
7. Calculate the value of free-board that should be provided for a reservoir having a
wind velocity of 92 km/h and it extends up to 18 km upstream.
a) 1.2 m
b) 1.6 m
c) 2.25 m
d) 2.5 m
View Answer
Answer: c
Explanation: When F < 32 km, the wave height is given by – Hw = 0.032(V.F)1/2 +
0.763 – 0.271 F1/4
Hw = 0.032(92 x 18)1/2 + 0.763 – 0.271 (18)1/4 = 1.5 m
Free board is generally provided equal to 1.5 Hw = 1.5 x 1.5 = 2.25 m.
8. The upward acceleration of dam due to seismic activity will
________________________
a) increase the base pressure
b) decrease the base pressure
c) not affect the effective weight of the dam
d) increase the horizontal dynamic force
View Answer
Answer: a
Explanation: Vertical acceleration can be resolved in two parts i.e. upward vertical
accelerations and downward vertical accelerations. The effective weight of the dam
increases when there is an upward vertical acceleration as it brings the foundation
closer to the dam. In downward acceleration, the effective weight reduces and is
considered as the worst design case.
9. What is the average value of acceleration that is sufficient for high dams in
seismic zones?
a) 0.1g to 0.15g
b) 0.05g to 0.1g
c) 0.3gs
d) 0.15g (where g is the acceleration due to gravity)
View Answer
Answer: a
Explanation: An average value of acceleration equal to 0.1 to 0.15 g is sufficient for
high dams in seismic zones and for areas not subjected to extreme earthquake a h =
0.1 g and av = 0.05 g may be used. These forces are neglected in areas of no
earthquake or very less earthquake.
10. What is Von Karman’s formula for hydrodynamic force (Pe)?
a) Pe = 0.726 pe H
b) Pe = 0.424 pe H
c) Pe = 0.555 pe H
d) Pe = 0.555.Kh. Yw H2
View Answer
Answer: d
Explanation: According to Von-Karman, the hydrodynamic force is given by –
Pe = 0.555. Kh. ϒw H2 where, ϒw is the unit weight of water, H is the depth of water
and Kh is a fraction of gravity adapted for horizontal acceleration which acts at the
height of 4H/3π above the base. In addition to this, an inertia force is also produced
by the horizontal acceleration into the body of the dam.
This set of Irrigation Engineering Multiple Choice Questions & Answers (MCQs)
focuses on “Gravity Method”.
1. When the reservoir is empty, the single force acting on it is the self-weight of the
dam which acts at a distance of ____________
a) B/2 from the heel
b) B/6 from the heel
c) B/3 from the heel
d) B/4 from the heel
View Answer
Answer: c
Explanation: The only single force on the dam when the reservoir is empty is the
self-weight of the dam acting at a distance of B/3 from the heel. It provides maximum
possible stabilizing moment about the toe without causing tension.
2. When the reservoir is empty, the maximum vertical stress equal to
________________
a) At heel = 2W/B and at toe = 0
b) At heel = 0 and at toe = 2W/B
c) At heel = toe = zero
d) At heel = toe = 2W/B
View Answer
Answer: a
Explanation: The vertical stress distribution at the base when the reservoir is empty
is given as –
Pmax/min = V/B [1 + 6e/B] and V/B [1 – 6e/B] where e = B/6 and V = total vertical force
= weight W
Pmax = 2W/B and Pmin = 0.
The maximum vertical stress at the heel is equal to 2W/B and at the toe is zero.
3. The two-dimensional stability analysis of gravity dams proves better for U-shaped
valleys than for V-shaped valleys.
a) True
b) False
View Answer
Answer: a
Explanation: The transverse joints in the dam body are generally not grouted in U-
shaped valleys but are keyed together in V-shaped valleys. In V-shaped valleys, the
entire length of the dam acts monolithically as a single body. The assumption that
the dam is considered to made up of a number of cantilevers of unit width each may
involve errors here.
4. Calculate the value of minimum base width for an elementary triangular concrete
gravity dam supporting 72 m height of reservoir water and full uplift? (Take specific
gravity of concrete as 2.4 and coefficient of friction as 0.7)
a) 36.28 m
b) 39.77 m
c) 51.5 m
d) 73.5 m
View Answer
Answer: d
Explanation: Using formula –
Case 1: B = H / (Sc – c)1/2 (For full uplift c = 1 and specific gravity of concrete = 2.4 )
= 72/ (2.4 – 1)1/2 = 60.85 m
Case 2: B = H/μ (S – 1) where μ = coefficient of friction taken as 0.7
B = 72 / 0.7 x 1.4 = 73.46 m
The highest among the two base width value is to be selected i.e. B = 73.46 m.
5. For usual values of permissible compressive stress and specific gravity of
concrete, a high concrete gravity is the one whose height exceeds ______________
a) 48 m
b) 70 m
c) 88 m
d) 98 m
View Answer
Answer: c
Explanation: The limiting height is – Hmax = f / (Sc + 1) ϒw Permissible strength of
concrete = 3000 KN/m2, Sc = specific gravity of concrete = 2.4
Hmax = 3000/[(2.4 + 1) x 9.81] = 89.9 m.
6. For triangular dam section of height H for just no tension under the action of water
pressure, self-weight and uplift pressure, the minimum base width required is
_____________
a) H / (S-1)
b) H / S1/2
c) H / (S – 1)-1
d) H / (S-1)1/2
View Answer
Answer: d
Explanation: The minimum base width (B) of a gravity dam having an elementary
profile –
B = H / (S – 1)-1 where S is specific gravity of concrete and H is the height of water.
If uplift is not considered – B = H/S1/2.
7. If the eccentricity of the resultant falls outside the middle third, the ultimate failure
of the dam occurs by ______________
a) tension
b) crushing
c) sliding
d) overturning
View Answer
Answer: a
Explanation: When eccentricity is greater than B/6 (eccentricity falls outside the
middle third), tension may develop. When tension prevails, cracks develop near the
heel and uplift pressure distribution increases reducing the net salinizing force.
8. What is the value of eccentricity for no tension condition in the dam?
a) e < B/6
b) e > B/6
c) e > B/3
d) e < B/3
View Answer
Answer: a
Explanation: The resultant of all the forces i.e hydrostatic water pressure, uplift
pressure and self-weight of the dam should always lie within the middle third of the
base for no tension. When e < B/6, the value of stress intensity at toe and heel are
positive i.e compression on both sides.
9. What is the formula for limiting height of a gravity dam?
a) Hmax = f / (Sc + 1) γw
b) Hmax = f / (Sc – 1) γw
c) Hmax = f / (Sc + C) γw
d) Hmax = f / (Sc – 1) γw
View Answer
Answer: a
Explanation: The critical height or limiting height of a dam having elementary profile
is –
Hmax = f / (Sc + 1) γw where f = allowable stress of the dam material, Sc = Specific
gravity of concrete and γw = unit weight of water.
This limiting height draws a dividing line between a low gravity dam and a high
gravity dam.
10. Calculate the top width of the dam if the height of water stored is 84m.
a) 5 m
b) 2.5 m
c) 5.55 m
d) 7.75 m
View Answer
Answer: a
Explanation: Bligh has given an empirical formula for finding out the thickness of the
dam at top.
A = 0.522 H1/2 = 0.522 x 841/2 = 5.05 m.
As per Creager, the economical top width has been found to be equal to 14% of the
dam height without considering earthquake forces.
1. In high dams, the safety against sliding should be checked only for friction.
a) True
b) False
View Answer
Answer: b
Explanation: The safety against sliding should be checked only for friction in case of
low dams and in high dams, the shear strength of the joint (i.e. an additional shear
resistance) is also considered for economical design. The dam section is given an
extra slope or batter on the U/s or D/s side as per requirements for achieving
stability.
2. For full reservoir condition in a gravity dam, the critical combination of vertical and
horizontal earthquake accelerations to be considered for checking the stability is
________________________
a) vertically upward and horizontally downstream
b) vertically downward and horizontally downstream
c) vertically upward and horizontally upstream
d) vertically downward and horizontally upstream
View Answer
Answer: b
Explanation: Horizontal inertia force should be considered to be acting at the center
of the gravity of the mass regardless of the shape of cross-section and it acts
horizontally downstream in worst cases under full reservoir case. This force would
produce the worst results is it is additive to the hydrostatic water pressure (acting
towards the downstream).
3. The base width of a solid gravity dam is 35 m and the specific gravity of dam
material is 2.45. What is the approximate allowable height of the dam having an
elementary profile without considering the uplift?
a) 64.68 m
b) 54.80 m
c) 164 m
d) 80 m
View Answer
Answer: b
Explanation: The base width at bottom is given by B = H/Sc1/2 (c = 0 since uplift is not
considered).
B = 35 m and Sc = 2.45
Allowable height of the dam H = 35 x 2.451/2 = 54.8 m.
4. A low gravity dam of elementary profile made up of concrete of relative density
2.57 and safe allowable stress of foundation material 4.2 MPa. What is the maximum
height of the dam without considering the uplift force?
a) 120 m
b) 217 m
c) 279 m
d) 325 m
View Answer
Answer: a
Explanation: The maximum possible height of low gravity dam is H = f / ϒw (Sc + 1)
where f = allowable stress of dam material = 4.2 MPa, Sc = 2.57, and ϒw = 9.81
KN/m2.
H = [4.2 / (9.81 x 3.57)] x 1000 = 119.92 m.
5. The vertical stress at the toe was found to be 3.44 MPa at the base of the gravity
dam section. If the downstream face of the dam has a slope of 0.617 horizontal: 1
vertical, the maximum principal stress at the toe of the dam when there is no
tailwater is _______________
a) 1.7 MPa
b) 2.4 MPa
c) 3.6 MPa
d) 4.8 MPa
View Answer
Answer: d
Explanation: The principal stress at the toe is given by Pat toe = Pv. secΦ2 (without
considering the tailwater) where Pv = 3.44 MPa and tan Φ = 0.617/1 i.e.Φ = 31.67°
Pat toe = 3.44 x sec(31.67°)2 = 4.74 MPa.
6. What is the recommended value of shear friction factor against sliding?
a) More than unity
b) Less than unity
c) More than 3 to 5
d) Less than 3
View Answer
Answer: c
Explanation: Shear Friction Factor is given by –
SFF = sliding factor (SF) + B.q / ∑Ph where B = width of joint or section area = B x 1,
q is the shear strength of the joint, and Ph is the sum of horizontal force causing
sliding. SF must be greater than 1 and SFF must be greater than 3 to 5. This
analysis is carried out for a full reservoir case as well as an empty case.
7. The small openings made in the huge body of a concrete gravity dam such as
sluices and inspection galleries can be assumed to be causing only local effects
without any appreciable effect on the distribution of stresses as per the principle
of_____________________
a) Laplace
b) St. Venant
c) Reynold
d) St. Francis
View Answer
Answer: b
Explanation: Small openings made in the dam only produce local effects as per St.
Venant’s principle. They do not affect the general distribution of stresses. This is one
of the most important assumptions made in the two-dimensional analysis of gravity
dams.
8. A concrete gravity dam having a maximum reservoir level at 200 m and the RL of
the bottom of the dam 100 m. The maximum allowable compressive stress in
concrete is 3000 KN/m2 and the specific gravity of concrete is 2.4. Calculate the
height of the dam and check whether it is a high dam or low dam.
a) H = 90 m High gravity dam
b) H = 90 m Low gravity dam
c) H = 214.2 m High gravity dam
d) H = 214.2 m Low gravity dam
View Answer
Answer: a
Explanation: The limiting height of the dam is given by-
H = f / ϒw (Sc + 1) where f = allowable stress of dam material = 3000 KN/m 2, Sc =
2.4, and ϒw = 9.81 KN/m2.
H = 3000 / 9.81 x 3.4 = 89.9 m.
This value is more than the height of the dam so it is a high gravity dam.
9. The axis of a gravity dam is the ______________________
a) line of the crown of the dam on the downstream side
b) line of the crown of the dam on the upstream side
c) centre-line of the top width of the dam
d) line joining mid-points of the base
View Answer
Answer: b
Explanation: The axis of the dam is taken as the reference line which is defined
separately in the plan and in the cross-section of the dam. In plan, it is the horizontal
trace of the U/s edge of the top of the dam. In the cross-section, the vertical line
passing through the U/s edge of the top of the dam is considered as the axis of the
dam.
10. Presence of tail-water in a gravity dam ____________________
a) increases the principal stress and decreases the shear stress
b) increases both the principal stress and the shear stress
c) decreases the principal stress and increases the shear stress
d) decreases both the principal stress and the shear stress
View Answer
Answer: d
Explanation: The principal stress is given by the formula –
P = Pv sec(Φ)2 – p’ tan(Φ)2 where Pv is the intensity of vertical pressure and p’ is the
tail-water pressure
The shear stress on the horizontal plane near the toe is given by –
S = (Pv – p’) tan(Φ)
From both the equations, it is clear that the tail-water pressure is opposite in nature
and it reduces the value of principal stress and shear stress.
< 10 m or
1. Diaphragm-type embankment
< the height of embankment
2. Zoned-type embankment ≥ 10 m
5. The blanket in earth dam is provided ___________________
a) at the ground level on u/s side
b) at the ground level on the d/s side
c) at the ground level of the D/s side of the dam
d) on the D/s slope
View Answer
Answer: a
Explanation: A blanket of relatively impervious material may be placed on the
upstream face. Since homogenous earth dam poses the problems of seepage, a
homogenous section is generally added with an internal drainage system. This
keeps the seepage line well within the body of the dam.
6. Which of the following statement is correct with reference to earthen dams?
a) These dams are very costly as compared to other types
b) Gravity dams are less susceptible to failure as compared to rigid dams
c) These dams are suitable for construction on almost every type of foundation
d) Highly skilled labor is generally not required
View Answer
Answer: c
Explanation: Earthen dams are suitable for any type of foundation but there has to
be a separate provision for the spillway location. The mode of failure is sudden and
requires high maintenance and the overall life is not so long. It requires low to
moderately skilled labors and moderate capital cost.
7. During the construction of an earthen dam by hydraulic fill method, development
of pore pressure becomes important in the __________________
a) central impervious core
b) pervious outer shell
c) transition zone
d) both central core and outer shell
View Answer
Answer: a
Explanation: In this method, an embankment is created by water and earth slurry
which is discharged inwards to form a central pool at site. When water is pumped to
the site it spreads the coarser material drops out first and the finest at last. Thus the
core material settles within the central pool forming a zoned embankment and high
pore pressures develop in the core.
8. The process of laying and compacting earth in layers by power rollers under OMC
for construction of earthen dams is known as ______________________
a) Rolled fill method
b) Hydraulic fill method
c) OMC method
d) Compaction
View Answer
Answer: a
Explanation: In the rolled-fill method, the embankment is constructed by placing
suitable soil materials in thin layers and compacting the layers with rollers. Power-
operated rollers are used for dams and ordinary road rollers can be used for low
embankments. The best compaction can be obtained at the optimum moisture
content (OMC).
9. The central core of the zoned embankment type earth dam
________________________
a) checks the seepage
b) prevents piping
c) gives stability to the central impervious fill
d) distribute the load over a large area
View Answer
Answer: a
Explanation: The central core or hearting is done with fairly impervious material and
it checks the seepage. The transition zone of mediocre permeability prevents piping
through cracks. The outer zone gives stability to the central fill.
10. Which type of dam is suitable on shallow pervious foundations?
a) Zoned embankment type
b) Homogenous embankment type
c) Both Non-homogenous type and homogenous type
d) Diaphragm type
View Answer
Answer: a
Explanation: Zoned earth dam is also called a non-homogenous or heterogeneous
earth dam and it is suitable on shallow pervious foundations. This dam is widely
constructed and the materials of the zone are selected depending upon the
availabilities.
1. What is the U.S.B.R recommended value for freeboard when the height of the
dam is more than 60 m?
a) 2 m to 3 m
b) 2.5 m above the top of gates
c) 3 m above the top of gates
d) More than 3 m
View Answer
Answer: c
Explanation: For controlled spillway, if the height of the dam is less than 60 m, the
minimum recommended freeboard value is 2.5 m above the top of gates. If the
height of the dam is more than 60 m, the minimum freeboard value is 3 m.
2. What is the recommended formula for top width of a very low dam?
a) H + 3
b) 0.2H + 3
c) 0.2 H
d) H + 5
View Answer
Answer: b
Explanation: The top width (A) is generally governed by minimum roadway width
requirements in case of small dams. The top width of the earth dam for very low
dams is given by –
A = H/5 + 3 where H is the height of the dam.
3. What is the Terzaghi’s recommended value of U/s side slope for earth dam of
height less than 15m of homogenous silty clay?
a) 2: 1
b) 2.5: 1
c) 3: 1
d) 3.5: 1
View Answer
Answer: b
Explanation: For earth dams of homogenous silty clay of height less than 15 m, the
recommended u/s slope is 2.5: 1 and d/s slope is 2: 1. For height more than 15 m,
u/s slope value is 3: 1 and d/s slope is 2.5: 1.
4. If the height of the dam is 10 m, then the value of top width (A) according to
Strange’s recommendations is _________________
a) 1.85 m
b) 2.5 m
c) 3.0 m
d) 4.0 m
View Answer
Answer: b
Explanation: If the height of the dam is up to 7.5 m then the top width value
according to Strange’s recommendation is 1.85 and if the height is in between 7.5 to
15 m, then the recommended value is 2.5. If the height is in between 15 to 22.5 m
then the top width is 3.0 m.
5. When the height of the dam is in between 7.5 to 15, the Strange’s recommended
value for maximum freeboard of low earth dams is ______________
a) 1.2 to 1.5
b) 1.5 to 1.8
c) 1.85
d) 2.1
View Answer
Answer: c
Explanation: For the height of the dam up to 4.5 m, the maximum freeboard is 1.2 to
1.5 m and for the height range 4.5 to 7.5 m, the maximum freeboard is 1.5 to 1.8 m.
If the height of the dam is in between 7.5 to 15 m, the maximum value is 1.85 m.
6. Calculate the top width (A) of the earth dam of height 50 m.
a) 5.0 m
b) 4.75 m
c) 6.10 m
d) 3 m
View Answer
Answer: c
Explanation: For dams higher than 30 m, the top width (A) is given by the following
formula-
A = 1.65 (H + 1.5)1/3 where H is the height of the dam.
A = 1.65 (50 + 1.5)1/3 = 6.13 m.
7. A phreatic line in seepage analysis is defined as the line on which pressure is
_______________
a) equal to the atmosphere
b) greater than atmosphere
c) lower than atmosphere
d) varying
View Answer
Answer: a
Explanation: The line which joins the points in a dam section at which pressure is
equal to the atmospheric pressure is called phreatic line. It is also called as line of
seepage or saturation line. There is capillary fringe i.e zone of capillary which has
negative hydrostatic pressure above this line.
8. Provision of horizontal berms at suitable vertical intervals may be provided in the
downstream face of an earthen dam in order to _________________
a) allow the movement of cattle
b) allow the inspection of vehicles to move
c) reduce the erosion caused by the flowing rainwater
d) increase the erosion
View Answer
Answer: c
Explanation: The provision of berms serves the following purposes –
1. It behaves like a good lining for reducing losses and leakage.
2. They provide protection against erosion and breaches due to wave action.
3. They help the channel to attain regime conditions as they help in providing
a wider waterway.
4. It can be used as borrow pits for excavating soil to be used for filling.
9. During seepage through an earthen mass, the direction of seepage is
________________ to the equipotential lines.
a) perpendicular
b) parallel
c) not defined
d) diagonal
View Answer
Answer: a
Explanation: The seepage through a pervious soil material for 2-D flow is given by
Laplacian equation and the graphical solution suggests that the flow through the soil
can be represented by flow-net. It consists of 2 sets of curves equipotential line and
streamlines which is mutually perpendicular to each other.
10. The upstream face of the earth dam is considered as _____________________
a) equipotential line
b) streamline
c) streak line
d) path line
View Answer
Answer: a
Explanation: Equipotential lines are the lines of equal energy. Every point on the
upstream face of an earth dam will be under equal total energy, this line acts as an
equipotential line. Similarly, the upstream floor of a weir acts as an equipotential line.
10. The effects of capillary fringe are on the slightly safer side and are neglected.
a) True
b) False
View Answer
Answer: a
Explanation: When there is appreciable flow through the dam body below the
phreatic line, it reduces the effective weight of the soil and also the shear strength of
the soil due to pore pressure. The capillary tension in water leads to increased
intergranular pressure as the insignificant flow through the fringe leads to greater
shear strength. Hence, the effects are neglected.
11. Which of the following line acts as a dividing line between dry (or moist) and
submerged line?
a) Equipotential line
b) Path line
c) Seepage line
d) Streak line
View Answer
Answer: c
Explanation: The soil above the phreatic line or seepage line will be taken as dry and
the soil below it shall be taken as submerged for computation of shear strength of
the soil. This helps in drawing the flow net.
i. Over-topping failure
v. Gully formation
1. The discharge passing over an ogee spillway per unit length of its apex line is
proportional ___________________
a) H
b) H2
c) H1/2
d) H3/2
View Answer
Answer: d
Explanation: The discharge passing over the ogee spillway is given by the formula –
Q = C. Le. H3/2 where Le is the effective length of the spillway crest, C is the
coefficient of discharge and H is the total head over the crest including the velocity
head.
It is clear from the discharge equation that the discharge is proportional to H3/2.
2. When the crest of an ogee spillway is designed to be in accordance with the lower
nappe of a free-falling water jet over a duly ventilated sharp-crested weir then
theoretically
a) The pressure on the spillway crest will be zero at design head only
b) The pressure on the spillway crest will always be zero
c) The pressure on the spillway crest will always be negative
d) The pressure on the spillway crest will be always positive
View Answer
Answer: a
Explanation: In actual practice development of negative pressure takes place
beneath the nappe due to the removal of air by the falling jet. This causes the danger
of cavitation and induces fluctuation and pulsation effects. To control this aeration
pipes may be provided along spillway face.
3. When the gated sluices are provided through the body of the dam spillway then
the ogee spillway structure shall normally be of Corbel type.
a) True
b) False
View Answer
Answer: b
Explanation: The extra concrete is required for thickening of the section at the d/s
end which can be saved by shifting the curve of the nappe in a backward direction
until it becomes tangential to the d/s face. It can be affected by providing a corbel on
u/s face.
4. The velocity of approach has found to be negligible effect upon discharge if
____________
a) the ratio H/Hd is more than 1.33
b) the ratio H/Hd is less than 1.33
c) the ratio H/Hd is equal to zero
d) the ratio H/Hd is more than 1
View Answer
Answer: a
Explanation: The velocity of approach has been found to have a negligible effect
upon discharge when the height of the weir is more than 1.33 times the design head.
When this ratio is less than 1.33 as in low spillways, the velocity is having an
appreciable effect.
5. If a flood enters a dam reservoir at F.R.L, the efficiency of its ogee spillway will
______________
a) increase with the increasing head
b) reduce with the increasing head
c) remain constant with the increasing head
d) vary with the increasing head
View Answer
Answer: a
Explanation: The coefficient of discharge increases with the increasing head above
the full reservoir level till it becomes about 2.2 at full design head i.e. MRL. Since the
spillway starts working when the water level just crosses FRL, the coefficient of
discharge is about 77% at full design head. As the water level increases from F.R.L
to M.R.L, the efficiency increases from 77% to 100%.
6. The downstream apron of the ogee spillway is found to have a negligible effect on
the coefficient of discharge when the value of ________________
a) (Hd + d) / He is less than 1.7
b) (Hd + d) / He exceeds 1.7
c) (Hd + d) / He is equal to 1
d) (Hd + d) / He is less than 1.33
View Answer
Answer: b
Explanation: The d/s apron is found to have a negligible effect on the coefficient of
discharge when the value of (Hd + d) / He exceeds 1.7. where d is the tailwater
depth, Hd is the design head and He is the Design head including the velocity head.
There can be a decrease in the coefficient due to tailwater submergence.
7. What is the value of the pier abutment coefficient for pointed nose piers?
a) 0.1
b) 0.02
c) 0.01
d) 0.0
View Answer
Answer: d
Explanation: The value of pier contraction coefficient depends upon the shape of the
piers.
2 Rounded nose piers and 900 cut water nosed piers 0.01
1. Which of the following is the simplest type of spillway which can be provided
independently and at low costs?
a) Ogee spillway
b) Trough spillway
c) Siphon spillway
d) Saddle spillway
View Answer
Answer: b
Explanation: The trough or chute spillway is adaptable to any type of foundations
and is the simplest type of spillway. It can be easily provided independently at low
costs but it requires ample room adjacent to the dam.
2. If the spillway is constructed in continuation to the dam at one end, it may be
called as ________
a) saddle weir
b) flank weir
c) waste weir
d) temporary weir
View Answer
Answer: b
Explanation: Saddle weir is the one when the spillway is constructed in a natural
saddle in a bank of the river separated from the main dam by a high ridge. Flank weir
is the one when the spillway is constructed in continuation to the dam at one end.
3. The spillway which can be adopted with ease on gravity as well as earthen dams
is _________________
a) ogee spillway
b) chute spillway
c) both ogee and chute spillway
d) straight drop spillway
View Answer
Answer: b
Explanation: Straight drop spillway is a low weir and simple vertical fall type structure
which may be constructed on thin arch dams or small bunds etc. An ogee spillway is
most suitable for concrete gravity dams. Chute spillway can be provided easily on
earth and rock-fill dams.
4. The famous Bhakra dam of India is provided with ________________
a) trough spillway
b) ogee spillway
c) shaft spillway
d) siphon spillway
View Answer
Answer: a
Explanation: Bhakra Dam is a concrete gravity dam on the Sutlej River in Himachal
Pradesh of the total height of 226 m approximately. It forms the Gobindsagar
Reservoir with controlled overflow chute or trough spillway and four spillway gates
for an emergency.
5. The surplus reservoir water after spilling over the crest of the spillway flows on the
chute is __________________
a) parallel to the crest in a trough spillway
b) parallel to the crest in a side-channel spillway
c) perpendicular to the crest in a side-channel spillway
d) obliquely to the crest in a chute spillway
View Answer
Answer: b
Explanation: In chute spillway, after crossing over the crest of the spillway water
flows at right angle shoots down a channel or a trough to meet the river channel
downstream of the dam. The water after spilling over the crest flows parallel to the
crest in a side-channel spillway.
6. Whenever the slope of chute changes from steeper to milder
____________________ curve shall be provided.
a) a concave vertical curve
b) a convex vertical curve
c) a hyperbolic curve
d) a parabolic curve
View Answer
Answer: a
Explanation: A concave vertical curve is provided whenever the slope changes from
steeper to milder. The radius of this curve should be less than 10 times the depth of
water (in meters).
7. The side slope of approach channel of chute spillway is ___________________
a) 1:1
b) 1:1 12
c) 1:3
d) 1:2.5
View Answer
Answer: a
Explanation: An entrance channel also called as an approach channel is trapezoidal
in shape with side slopes 1:1. It is constructed so as to lead the reservoir water up to
the control structure or low ogee weir.
8. The spillway which may sometimes be called as a waste weir is
______________________
a) an ogee spillway
b) a trough spillway
c) a shaft spillway
d) a siphon spillway
View Answer
Answer: b
Explanation: A chute or trough spillway is sometimes called as a waste weir. It is
called as chute spillway because after crossing over the crest of the spillway water
flow shoots down a channel or trough to meet the river channel downstream of the
dam. The trough is taken straight from the crest to the river.
9. The portion of a chute spillway which is known as its control structure is
________________
a) low ogee weir
b) chute channel
c) approach channel leading the water from the reservoir to the ogee weir
d) silting basin at its bottom
View Answer
Answer: a
Explanation: Low ogee weir is required as a control structure in the chute spillway.
The entire chute spillway is divided into the entrance channel, control structure,
Chute channel or discharge channel, and energy dissipation arrangements in the
form of silting basin at the bottom.
10. The type of spillway which is provided on narrow valleys where no side flanks are
available is ____________________
a) ogee spillway
b) chute spillway
c) side-channel spillway
d) straight drop spillway
View Answer
Answer: c
Explanation: The side channel spillway is suitable when the valley is too narrow.
When there is no room for provision of chute spillway (as side flanks of sufficient
width are required), this type is adopted as it requires limited space. The situation
required for the chute spillway and side-channel spillway is mostly the same.
11. Which of the following curve is provided when the slope of the chute changes
from milder to steeper?
a) Concave vertical curve
b) Hyperbolic curve
c) Convex vertical curve
d) Straight plan
View Answer
Answer: c
Explanation: A convex vertical curve shall have to be provided when the slope of the
chute changes from milder to steeper. The curvature should approximate to a
parabolic shape. A concave vertical curve is provided whenever the slope changes
from steeper to milder.
12. Calculate the freeboard for the top levels of the side walls if the mean velocity of
water in the chute reach is 3.5 m/s and the mean depth of water in the chute reach
under consideration is 4.7 m.
a) 0.60 m
b) 1 m
c) 0.85 m
d) 0.55 m
View Answer
Answer: c
Explanation: The freeboard to be provided above the top nappe of side walls is
generally given by the equation:
F.B = 0.61 + 0.04 Vm. dm1/3 where ‘Vm‘ is the mean velocity of water in the chute
reach and ‘dm’ is the mean depth of water in the chute reach under consideration.
F.B = 0.61 + 0.04 x 3.5 x 4.71/3 = 0.84 m.
13. The minimum slope of the chute is governed by the condition that
_____________
a) the subcritical flow must be maintained
b) the supercritical flow must be maintained
c) a critical flow must be maintained
d) maybe supercritical or subcritical flow is possible
View Answer
Answer: b
Explanation: The water flows through the chute channel after spilling over the control
structure and the minimum slope is governed by the condition that the supercritical
flow must be maintained. The slope should be sufficient to meet the flow requirement
from the crest without endangering the stability or heavy excavations.
14. What is the approximate percentage of light reinforcement that is provided in the
top of the reinforced concrete slabs at the base?
a) 0.50% of the concrete area
b) 0.45% of the concrete area
c) 0.30% of the concrete area
d) 0.25% of the concrete area
View Answer
Answer: d
Explanation: The base of the channel is usually made of reinforced concrete slabs
25 to 50 cm thick and light reinforcement of about 0.25% of the concrete area is also
provided in both the directions. The chute is sometimes narrowed for the economy
and then widened near the end to reduce the discharging velocity.
1. The energy dissipation at the toe of the spillway is affected basically by the use of
hydraulic jump in _______________________
a) roller bucket
b) a ski-jump bucket
c) a sloping apron below the downstream river bed
d) both roller and ski-jump bucket
View Answer
2. The most ideal condition for energy dissipation in the design of spillways is the
one when the tail-water rating curve coincides with the jump rating curve at all
discharge.
a) True
b) False
View Answer
Answer: a
Explanation: The most ideal condition for jump formation is when TWC coincides
with JHC at all discharge. To ensure protection in the region of a hydraulic jump, a
simple concrete apron of apron length 5 (y2 – y1) is provided.
3. When the tail-water depths in the river downstream of a spillway are quite low
such that the tail-water curve at all discharges lies below the post jump depth curve,
then the energy dissipation can be affected best by ___________________
a) a roller bucket
b) a ski-jump bucket
c) either roller or ski-jump bucket
d) a sloping apron
View Answer
Answer: b
Explanation: Energy dissipation bucket called ski-jump bucket is used when the tail-
water depth is insufficient or low at all discharge. It requires sound and rocky river
bed. Water may shoot up out of the bucket and fail harmlessly into the river at some
distance downstream of the bucket.
4. The device which does not help in energy dissipation at the bottom of a hydraulic
structure over which water spills is ________________
a) chute block
b) dentated sill
c) morning glory
d) baffle piers
View Answer
Answer: c
Explanation: A flared inlet called morning glory is often used in large projects. The
horizontal tunnel is either taken through the dam body or below the foundations.
Chute blocks, dentated sills and baffle piers are all auxiliary devices which help in
energy dissipation.
5. The formation of hydraulic jump at the foot of a spillway is one of the common
methods of energy dissipation because ______________________
a) it destroys more than 90% of total energy by the turbulence produced in the jump
b) it reduces the kinetic energy by increasing the depth of flow
c) its action is not understood
d) it reduces the kinetic energy by decreasing the depth of flow
View Answer
Answer: a
Explanation: Hydraulic jump is generally accompanied by large scale turbulence
dissipating most of the kinetic energy of the super-critical flow. It is the most suitable
method because the energy is lost in the impact of the water against water. Most of
the kinetic energy is destroyed by creating a condition suitable for the hydraulic
jump.
6. A ski-jump bucket is also known as _____________________
a) flip bucket
b) solid roller bucket
c) slotted roller bucket
d) flexible bucket
View Answer
Answer: a
Explanation: A ski-jump bucket is also called flip bucket is used for energy
dissipation when tail-water depth is insufficient or low at all discharge. A part of
energy dissipation takes place by impact and some of the energy is dissipated in the
air by diffusion or aeration.
7. The percentage of energy dissipation in a hydraulic jump increases with the
increase in the Froude number.
a) True
b) False
View Answer
Answer: a
Explanation: The energy dissipation in the jump depends upon the Froude number, if
this Froude number is higher, the greater energy dissipation can take place.
1. 2.5 17
2. 4.5 45
3. 9.0 70
8. Which of the following stilling basin help in stabilizing the flow and improve the
jump performance?
a) dentated sills
b) chute blocks
c) baffle piers
d) friction blocks
View Answer
Answer: b
Explanation: Chute blocks are a row of small projections like teeth of saw and are
provided at the entrance of the silting basin. It produces a shorter length of jump and
stabilizes the flow. Hence, they improve jump performance.
9. What is the expected solution for the case when the T.W.C is lying above the
J.H.C curve at all discharges?
a) By providing a simple concrete apron of length 5(Y1 – Y2)
b) By providing a sloping apron above the river bed
c) By providing a sloping apron below the river bed
d) Provision of a ski-jump bucket
View Answer
Answer: b
Explanation: When the TWC is lying above the JHC at all discharges, the problem
can be solved by-
1) By constructing a sloping apron above the river bed
2) By providing a roller bucket type of energy dissipator.
In this case, the jump is formed at the toe will be drowned by the tail-water and little
energy will be dissipated.
10. A sloping apron is provided partly above the river bed and partly below the river
bed in case of ____________________________
a) when TWC coincides with the JHC at all discharges
b) when TWC lies above the JHC at all discharges
c) when TWC lies below the JHC at all discharges
d) when TWC lies above the JHC at low discharges and below the JHC at high
discharges
View Answer
Answer: d
Explanation: At low discharges, the jump will be drowned and at high discharges tail-
water depth is insufficient. When TWC lies above the JHC at low discharges and
below the JHC at high discharges, the solution is the provision of sloping apron
partly above and partly below the river bed. The horizontal apron and end-sill are
also provided.
11. When the TWC lies below the JHC at all discharges, the problem can be solved
by which of the following provisions?
i. Constructing a sloping apron above the river bed
ii. Provision of roller bucket type of energy dissipator
iii. Provision of a ski-jump bucket
iv. A sloping apron below the river bed
v. Construction of a subsidiary dam
vi. A sloping apron partly above and partly below the river bed
a) i, iii and v
b) i, ii and vi
c) iii, iv and v
d) i, iii, iv and v
View Answer
Answer: c
Explanation: When TWC lies below the JHC at all discharges, the expected solution
is –
i. Provision of a ski-jump bucket
ii. A sloping apron below the river bed of length 5 (y2 – y1)
iii. Construction of a subsidiary dam below the main dam.
1. The bar screens used to cover the dam outlets to prevent entry of debris, or ice
into the spillway conduits are called __________________
a) gate controlled ports
b) projecting collars
c) trash racks
d) intakes
View Answer
Answer: c
Explanation: The trash racks are made from steel bars at a spacing of about 5 to 15
cm c/c in both the directions. The floating objects like debris, ice get collected on
these racks and can be removed by manual labor as well as automatic power-driven
system. The spacing depends upon the maximum size of debris required to be
excluded.
2. Projecting collars are provided on sides of a rectangular tunnel of length L made
through an earthen dam to increase the seepage path. Their projection length (X)
and numbers (N) are decided so as to provide increased seepage path equal to 2NX
where 2NX should generally be ______________________
a) greater than L/4
b) greater than L/3
c) greater than L/2
d) greater than L
View Answer
Answer: a
Explanation: The seepage is reduced by increasing the length of the seepage path
by at least 25%. The increase in seepage path must generally be greater than L/4.
3. The outlet provided in a dam body to release water for the downstream water
demand is known as ______________________
a) spillway
b) sluiceway
c) under-sluice
d) waterway
View Answer
Answer: b
Explanation: A sluiceway is a pipe or a tunnel that passes through the body of the
dam or through some hillside at one end of the dam and discharges into the stream
below. The sluiceways are preferred to place outside the limits of the embankments
in case of spillways.
4. A 2 m diameter sluiceway at RL 300 m is provided through a concrete overflow
dam section to release water to the downstream where tail water level is not more
than 275 m. The discharge through this outlet when the water level in the reservoir is
at FRL of 330 m is of the order of_________________
a) 20 cumecs
b) 40 cumecs
c) 50 cumecs
d) 80 cumecs
View Answer
Answer: c
Explanation: The discharge passing through the dam outlet is given by using the
equation-
Q = Cd. A. (2gHL)1/2 where Cd is the coefficient of discharge = 0.62 for free over-fall,
H = Water head over centre line of sluice = 330 – 300 = 30 m and A = π/4 x 4 = 3.14
m2
Q = 0.62 x 3.14 x (2 x 9.81 x 30)1/2 = 47.23 cumecs.
5. A 4 m diameter tunnel has been constructed through an earthen dam with a bell
mouth entry. The water levels on the U/s and D/s sides of the dam are at RL 226 m
and 210 m respectively. What will be the discharge through this outlet?
a) 64 cumecs
b) 104 cumecs
c) 165 cumecs
d) 216 cumecs
View Answer
Answer: c
Explanation: The discharge through the outlet is given by –
Q = Cd. A. (2gHL)1/2 where HL = 226 – 210 = 16 m
Q = 0.8 x (π/4 x 16) x (2 x 9.81 x 16) = 164 cumecs.
6. Which of the following entrance of the sluiceway is most superior?
a) A square-edged entrance
b) A Bell-mouthed entrance
c) A rectangular entrance
d) A circular entrance
View Answer
Answer: b
Explanation: As compared to Bell-mouthed or other entrance, a square edge
entrance is likely to cause more separation of flow and more danger of consequent
cavitation. The shape of the bell-mouthed entrance is generally elliptical and the
extra cost involved I shaping this entrance is usually justified except for small
projects under low heads.
7. What is the correct Douma’s equation for rectangular tunnels or conduits?
a) X2 + 10.4 Y2 = d2
b) 4X2 + 10.4 Y2 = d2
c) 4X2 + 44.4 Y2 = d2
d) X2 – 10.4 Y2 = d2
View Answer
Answer: a
Explanation: Douma has suggested the following equation –
i. For circular conduits: 4X2 + 44.4 Y2 = d2 where d is the diameter of the circular
conduit
ii. For rectangular tunnels or conduits: X2 + 10.4 Y2 = d2 where d is the width or
height of the conduit depending on whether the sides or top and bottom curves are
being designed. Where X and Y are the coordinates of any point on the curve and d
is the width or height of the conduit.
8. What is the value of head loss for the fully open gate and butterfly valves?
a) 0.5 V2 / 2g
b) V2 / 2g
c) 0.2 V2 / 2g
d) 0.04 V2 / 2g
View Answer
Answer: c
Explanation: The head loss depends upon the type of gate and valves. For fully open
gates and butterfly valves, a loss of about 0.2 V2 / 2g (where V is the flow velocity
through the conduit) may be taken and is taken as nil for ring follower gates.
1. As per estimate made by the Central Electricity Authority, the potential of the
country is accessed at 84 GW at load factor value of _________________
a) 40%
b) 60%
c) 80%
d) 20%
View Answer
Answer: b
Explanation: This equivalent to about 440 billion units + KWh of annual energy
generation at a power factor of 0.6. 60% load factor means that the installed
machines are run on an average to give output capacity equal to 60% of the station
capacity. Machines will not always work at the installed capacity but on an average
of 60% of this capacity.
2. The first power station of India was installed at _________________
a) Mysore
b) Bombay
c) Darjeeling
d) Bangalore
View Answer
Answer: c
Explanation: The first hydropower station in India dates back to the year 1897 when
a small power station of 200 KW capacities was constructed in Darjeeling. Then it
was followed by a 50 MW Tata Electric project of Bombay in 1914.
3. What is the correct expansion of DAE?
a) The Department of Atomic Energy
b) The Discipline of Atomic Energy
c) The Division of Atomic Energy
d) The Domain of Atomic Energy
View Answer
Answer: a
Explanation: This department directly runs under the Prime Minister of India with
headquarters in Mumbai, Maharashtra. The main aim of the department is to
increase nuclear power production from 3% to 8% of the total electricity generation in
the next 15 years.
4. In India, the nuclear power generation is about ____________ of the total power
generation.
a) 3%
b) 4%
c) 5%
d) 6%
View Answer
Answer: a
Explanation: The nuclear power generation is only about 3% of the total power
generation including hydropower, thermal power, nuclear power, etc. The Indian
Department of Atomic Energy is planning to boost its generation in the next 15 years
from 3% to 8% of the total electricity generation.
5. Which one is the first nuclear power plant in India?
a) Tarapur atomic power station
b) Kaiga atomic power station
c) Rawatbhata Atomic power station
d) Narora atomic power station
View Answer
Answer: a
Explanation: Tarapur Atomic power station 320 MW is located in Tarapur,
Maharashtra and it was the first commercial nuclear power station. The construction
began in 1961 and went operational in 1969. It has two 160 MW water boiling
reactors.
6. Convert the hydropower potential of 84 GW at 60% load factor into Trillion watts
hour.
a) 441 TWh
b) 735 TWh
c) 553 TWh
d) 345 TWh
View Answer
Answer: a
Explanation: 1 TW (Trillion watt) = 1000 GW (Giga watt)
84 GW is equivalent to = 84 x 365 x 24 = 735,840 GW hour
At 60 % load factor = 735,840 x 0.6 = 441,504 GW hour = 441 TWh or 441 b KWh.
1. The minimum power which a hydropower plant can generate throughout the year
is called as ________________
a) power plant capacity
b) power plant load
c) firm power
d) water power
View Answer
Answer: c
Explanation: The firm power is the net amount of power which is continuously
available from a plant without any break on a guaranteed basis. The consumers can
always be sure of getting this power and this power is available under the most
adverse hydraulic conditions.
2. If the peak load for a power plant equals the plant capacity then the ratio of the
capacity factor to load factor will be _________________
a) 1
b) 0
c) < 1
d) > 1
View Answer
Answer: a
Explanation: Load factor = Average load over a certain period / Peak load during that
period
Capacity factor = Average load over a given time period / Plant capacity
Since, Plant capacity = Peak load
Ratio of CF / LF = 1.
3. If the peak load on a power plant having a capacity of 100 MW is 70 MW during a
given week and the energy produced is 58, 80,000 kWh, the capacity factor for the
plant for the week will be ___________________
a) 35%
b) 50%
c) 70%
d) 65%
View Answer
Answer: a
Explanation: Capacity factor = Average load/ Plant capacity
Average load = Energy produced / Time (in hours) = 58,80,000 / 7 x 24 = 35000 kW
C.F = 35 MW / 100 MW = 0.35 (or 35%).
4. During a certain week a power plant turns out 84,00,000 kWh and the peak load
during the week is 100,000 kW. What is the load factor during the week?
a) 40%
b) 45%
c) 50%
d) 60%
View Answer
Answer: c
Explanation: Load factor can be defined as the ratio of average load to the peak load
over a given period.
Average load = 84,000,000 / (24 x 7) = 50,000 kW
L.F = Average load / Peak load = 50,000 / 100,000 = 0.5 or 50%.
5. A canal drop is 6 meters and discharges available through the turbine is 50
cumec. Find the electrical energy available.
a) 2352 KW
b) 2352 MW
c) 2.352 kW
d) 235.2 kW
View Answer
Answer: a
Explanation: The electrical energy (in kW) = 7.84 Q H (using 80% efficiency) where
H is the design head in meters and Q is the design discharge in cumecs.
Electrical energy = 7.84 x 50 x 6 = 2352 kW.
6. The ratio of maximum power utilised to the maximum power available is
_____________
a) power factor
b) plant use factor
c) reserve capacity
d) capacity factor
View Answer
Answer: b
Explanation: Plant use factor is nothing but utilization factor which can be defined as
the ratio of maximum power utilized to the maximum power available if the water
head is assumed to be constant. The value usually varies from 0.4 to 0.9 for a hydel
plant.
7. The net amount of power which is continuously available from a plant without any
break is known as _____________
a) firm power
b) secondary power
c) power factor
d) utilization factor
View Answer
Answer: a
Explanation: Secondary power is the excess power available over firm power during
peak-off hours. It is supplied to consumers as and when available basis. Power
factor is the ratio of actual power (in kW) to the apparent power (in kilo volt-ampere).
8. The value of power factor is generally _____________________
a) equal to unity
b) less than unity
c) greater than unity
d) equal to zero
View Answer
Answer: b
Explanation: The value of power factor depends upon the relationship between the
inductance and resistance in the load and it can never be greater than unity. The
usual system load has a power factor varying from 0.8 to 0.9. But if various induction
motors are installed in the load, the value will be 0.5.
9. To ensure maximum overall plant efficiency, the rated head should be equal to
______________
a) the design head
b) the gross head
c) the operating head
d) effective head
View Answer
Answer: a
Explanation: The Rated head is the head at which the turbine functioning at full gate
opening will produce a power output. It is nothing but the specified head that is in the
nameplate of the turbine. This is equal to the design head of the turbine so as to
ensure maximum overall plant efficiency.
10. The difference of head at the point of entry and exit of turbine is
_______________
a) design head
b) gross head
c) effective head
d) rated head
View Answer
Answer: c
Explanation: Design head is the net head under which the turbine reaches peak
efficiency. The difference in the water level elevations at the point of diversion of
water for the hydel scheme and the point of return of water back to the river is called
a gross head. The rated head is the head that is specified in the name-plate of the
turbine.
11. The load on a hydel plant varies from a minimum of 10,000 kW to a maximum of
35,000 kW. Two turbo-generators of capacities 20,000 kW each have been installed.
Calculate Plant factor.
a) 50%
b) 51%
c) 56.2%
d) 59.7%
View Answer
Answer: c
Explanation: Plant factor can be defined as the ratio of the energy actually produced
(Average load) to the maximum energy that can be produced at a particular time.
Since two turbo generators are installed, the total installed capacity = 40000 kW
P.F = [(10000 + 35000) / 2] / 40000 = 56%.
12. Calculate utilisation factor if the maximum power utilised is 40,000 kW and two
turbo generators installed each of capacity 23,000 kW.
a) 73%
b) 87%
c) 57.5%
d) 63%
View Answer
Answer: b
Explanation: Utilisation factor = Maximum power utilised / Maximum power available
U.F = 40,000 / (2 x 23000) = 86.9% (since two generators are installed).
13. If the peak load on a power plant having a capacity of 100 MW is 70 MW during
a given week. Calculate the utilization factor.
a) 0.35
b) 0.50
c) 0.70
d) 0.60
View Answer
Answer: c
Explanation: The utilization factor is the ratio of the maximum power utilized to the
maximum power available.
U.F = Max power utilised/ Max power available = 70 / 100 = 0.7.
14. 400 cumecs of water are being released from dam storage to meet the
downstream demand through the turbines of the connected hydro plant. The
effective head of water acting on the turbines is 50 m. The efficiency of the hydro
plant is 0.8. The electrical power generated from this plant is __________________
a) 1,56,800 MW
b) 156.8 M kW
c) 156.8 MW
d) 156.8 kW
View Answer
Answer: c
Explanation: Using 80% efficiency, Electrical energy = 7.84 QH where H is the
design head in meters and Q is the design discharge in cumecs.
Electrical energy = 7.84 x 400 x 50 = 1, 56,800 kW = 156.80 MW.
15. What is the highest elevation of water level that can be maintained in the
reservoir without any spillway discharge either with gated or non-gated spillway?
a) Normal Water level
b) Minimum Water level
c) Weighted average level
d) Operating head
View Answer
Answer: a
Explanation: Minimum water level is that elevation of water level which produces
minimum net head on the power units i.e. 65% of the design head. The weighted
average level is the level above and below which equal amounts of power are
developed during an average year. Operating head is the difference of elevation of
entrance and the tail-race exit.
iv. Higher the specific speed, higher will be the discharge and the head
1. Forebay provides temporary storage before the water goes to the turbine.
Following perform the function of forebay ____________________
a) river
b) tailrace channel
c) reservoir
d) approach channel
View Answer
Answer: c
Explanation: The reservoir itself acts as a forebay when it is constructed by building
a dam. The water is taken to the powerhouse directly from the reservoir through
penstocks. Following are some functions of forebay:
• To temporarily store water and to meet the instantaneous demand
• Absorbs the short interval variations and fluctuations.
2. The surge tank serves which of the following purposes?
a) i and ii
b) ii and iii
c) iii and iv
d) i, ii and iii
View Answer
Answer: c
Explanation: The cylindrical chamber which is connected to the penstocks and open
to the atmosphere is the simplest one. It serves the following functions i.e. to reduce
the pressure fluctuations in the pipe and helps in eliminating additional water
hammer pressure.
3. Identify the correct statement in regard to hydropower.
a) Hydropower stations are generally labour-oriented
b) The gestation period for hydro-power plant is usually small
c) The hydro generators give high efficiency over a wide range of load
d) In a hydropower scheme, the firm power is usually high as compared to tidal
power
View Answer
Answer: c
Explanation: Hydroelectric power plants are the most efficient means of producing
energy and the efficiency of today’s hydroelectric plant is about 90%. Large
hydropower plants usually have a gestation period of about 7 years whereas for
smaller plants it is 2 to 5 years.
4. To avoid the possible damage to the wicket gates and turbine runners
_________________ is provided.
a) trash racks
b) surge chamber
c) floating boom
d) racks and trolley arrangement
View Answer
Answer: a
Explanation: Intakes should be provided with trash racks so as to prevent the entry
of debris into the penstocks or to prevent choking up of the nozzles of the impulse
turbines. Trash racks are made up of thin flat steel bars placed 10 to 30 cm apart
and the permissible velocity of water entering these is 0.6 to 1.6 m/s.
5. In case of long penstocks, ___________________ is generally provided so as to
absorb water hammer pressure.
a) trash racks
b) surge chamber
c) floating boom
d) racks and trolley arrangement
View Answer
Answer: b
Explanation: The surge tank is mostly employed in a water power plant or in a large
pumping plant to control the pressure variations resulting from rapid changes in the
flow. It is done by admitting a large mass of water in the surge tank otherwise it
would have flown out of the pipeline and returns to the tank due to closure of pipe
end.
6. Sharp bends must be avoided in penstocks while designing components of the
hydroelectric scheme.
a) True
b) False
View Answer
Answer: a
Explanation: Sharp bends cause loss of head and requires special anchorages. It
may be buried under the ground or kept exposed. The penstock can be replaced by
constructing a tunnel through a hill if a considerable saving in length can be gained.
7. The retarding and accelerating heads are developed more promptly in
________________
a) simple surge tank
b) restricted orifice surge chamber
c) differential surge chamber
d) multi surge chamber
View Answer
Answer: c
Explanation: The differential surge chamber has a central riser pipe in addition to the
main outer tank and the retarding and accelerating heads are developed more
promptly. The capacity of a different type of surge chamber may be less than that of
a simple elementary type for a given amount of stabilizing effect.
8. The correct sequence in the direction of the flow of water for installations in a
hydropower plant is _______________________
a) Reservoir, Surge tank, Turbine, Penstock
b) Reservoir, Penstock, Surge tank, Turbine
c) Reservoir, Penstock, Turbine, Surge tank
d) Reservoir, Surge tank, Penstock, Turbine
View Answer
Answer: b
Explanation: The main components of a hydropower plant is Forebay, intake
arrangement, Penstock, Surge tank, turbines and generators, powerhouse and
tailrace. The water is taken from a reservoir or forebay and is taken down to the
powerhouse by penstock. A surge tank is fitted at some opening made on a
penstock to receive the rejected flow when the pipe is suddenly closed.
1. What is the minimum depth of water required for safe and economical navigation?
a) 1 m
b) 2 m
c) 2.7 m
d) 4.2 m
View Answer
Answer: c
Explanation: The availability of sufficient water depth in the waterway is the chief
requirement for navigations and for safe and economical navigation, a minimum
depth of 2.7 m is generally required. Lesser depth in the rivers completely eliminates
the possibility of towing the ships and causes an increase in the unit cost of transport
and a depth of 3.7 m is generally desired in the final development.
2. The transit time required by a barge tow moving upstream in a navigable river
increases if the flow velocity is more.
a) True
b) False
View Answer
Answer: b
Explanation: The flow velocities should be low as high velocity causes a substantial
reduction in the true speed for tows moving upstream. This increases the time of
transit and cost of transport per kilometer. The speed of the barge tows in still water
is almost 2.8 m/sec.
3. The belt conveyor forming an essential part of a ladder dredger used for
excavating river sand deposits is used for _______________________
a) excavation of sand
b) transporting excavated sand to the surface over small distances
c) transporting excavated sand to the surface over large distances
d) transporting excavated sand to the surface over all distances
View Answer
Answer: b
Explanation: Ladder dredger has an endless chain of buckets for bringing the
excavated material up to the surface and the cuttings carried by buckets are
discharged on a belt conveyor. The material is then disposed of through a stacker
conveyor at the rear of the dredger which is limited in length to about 100 m or so.
4. The dredger which excavates sand deposits of a river and discharges the
excavated material with water over long distances is called a _________________
a) ladder dredger
b) suction dredger
c) dipper dredger
d) upper dredger
View Answer
Answer: b
Explanation: Dipper dredgers are used on small projects and are merely floating
power shovels. Ladder dredger is used when the excavated materials are to be
discharged at a considerable distance from the dredge. The disadvantage of the
suction dredge is that it cannot operate in rocky or Shoulder River reaches.
5. Lock and dams constructions for creation of a series of slack-water pools along a
river for promoting its navigability is adopted only when
________________________
a) the river is perennial
b) the river carries heavy sediment load
c) the available water in the river is quite less
d) the available water in the river is quite large
View Answer
Answer: c
Explanation: This arrangement is generally adopted where existing site conditions
are not favorable for adopting open channel methods. The water is required for
lockage, sanitary releases, evaporation, percolation, etc and the requirement is
much less than that of open channel procedures. Hence, it is adopted when the
water available is less.
6. Timber is generally transported in our country through ________________
a) rail routes
b) road routes
c) air routes
d) water routes
View Answer
Answer: d
Explanation: Very heavy items like cargo are also packed on wagon trains or trucks
is lifted and transported through water transport. Besides the fact that it is the
cheaper mode of transport, it is also used for recreational boating. The imports and
exports are done by means of water routes.
7. What is the oldest and cheapest mode of transporting cargo?
a) Rail routes
b) Road routes
c) Air routes
d) Water routes
View Answer
Answer: d
Explanation: Water transport is cheaper because the coefficient of friction on the
water is small. On the water, one horsepower can pull 4 tonnes while on road and
rail, it can move approximately 0.15 tonne and 0.5 tonnes respectively.
9. Ships or steamers can pay to carry cargo in Indian waterways extending to about
____________________
a) 500 km
b) 2500 km
c) 10,000 km
d) 40,000 km
View Answer
Answer: b
Explanation: There is about 15,000 km length of navigable waterways in India and
most of them are in bad conditions due to poor silting and maintenance. Most of it is
fit only for boating and the streamers can ply only for about 2500 km length. For the
total navigable length of about 15,000 km, about 8000 km is on rivers and 7000 km
is on canals and backwaters.
10. The alignment of the waterway should be________________
a) straight
b) circular
c) parabola
d) irregular alignment
View Answer
Answer: a
Explanation: A highly irregular alignment increases the circuitry or length in excess pf
airline distance which the barge tow must travel. The existing channels generally
have a length of about 50% greater than the air-line distances. Hence, the alignment
should be as straight as possible.
10. The rivers carrying huge sediment load can be corrected with the help of sal-balli
spurs.
a) True
b) False
View Answer
Answer: a
Explanation: The rivers carrying little sediment load can be corrected by properly
placed impermeable spears or jetties. When the rivers carry heavy sediment load, it
can be corrected by permeable spurs called sal-Balli spurs driven at some suitable
distance center to center in rows across the river currents. This slows down the
current and promotes silting in the dyked area.
11. Which of the following dredger is not suitable for rocky or boulder river reaches?
a) Suction dredger
b) Ladder dredger
c) Dipper dredger
d) Both ladder and dipper dredger
View Answer
Answer: a
Explanation: In suction dredgers, the suction head is provided with jets or rotating
blades so as to cut or loosen the bed material and the suction openings through
which the soil and the water mixture enters into the suction pipe. It cannot operate on
rocky or Boulder River reaches. These dredgers can make cuts of about 10 m width
through sand bars in order to achieve wider cuts.
12. The fuel consumption in water transport decreases as the depth of water
between the bottom of the ship and the bottom of the river increases.
a) True
b) False
View Answer
Answer: a
Explanation: The fuel consumption in water transport also depends on the available
draft. When the clear depth between the barge and the river reduces, an increased
drag force is developed which increases the consumption of fuel. If the clear space is
increased from 0.6 to 1.5 m or so the fuel consumption can be reduced by about
25%.
1. Which of the following forces is the least important in the design of arch dams?
a) Reservoir water force
b) Uplift pressure
c) Temperature stresses
d) Ice load
View Answer
Answer: b
Explanation: The uplift pressure in an arch dam is generally neglected because it is
small due to the narrow base width of its body. Ice load, Temperature stresses and
yield stresses are quite important in such dams and are thoroughly examined.
2. Which of the following theory is the most accurate method to design arch?
a) The thin cylinder theory
b) The theory of elastic arches
c) The trial load method
d) Creep theory
View Answer
Answer: c
Explanation: Thin cylinder theory can only be relied upon for rough estimation of
dimensions of the arches. The Elastic theory does not take into account the
thickness of arch rings and the restrictions at the abutments. The Trial load method
removes the above objections and leads to an accurate estimation of the stresses in
arches.
3. Which among the following is not an assumption of the ‘Trial Load Analysis’
method of design of arch dams?
a) Plane sections normal to the axis remain plane after flexure
b) Any horizontal arch ring is independent of the arch rings below and above
c) Modulus of elasticity of concrete and rock foundation is equal for compression and
tension
d) Stresses are proportional to strains
View Answer
Answer: b
Explanation: In Trial load method, the dam is divided into two systems of elements
i.e. the horizontal arches and the vertical cantilevers. Each element is supposed to
take a percentage of the load due to silt and water pressure. The actual distribution
of the load between these elements is then arrived at by several trials.
4. The thin cylinder theory for designing arch dams is based only on
___________________
a) temperature stresses
b) ice pressures
c) yield stresses
d) hydrostatic water pressure
View Answer
Answer: d
Explanation: In thin cylinder theory analysis, the design is based only on hydrostatic
water pressure. The theory does not take into account the shear and bending
stresses in the arch, temperature stresses, and ice pressures which are quite
important in arch dams.
5. The temperature stresses producing worst effects in the design of arch dams are
caused by ______________
a) rise in temperature
b) fall in temperature
c) both rise and fall
d) no effect in the design
View Answer
Answer: b
Explanation: The dam moves upstream during the summer and downstream during
the winter due to the internal stresses caused by the temperature changes. In stress
analysis, the low temperature becomes quite important since these stresses act
additive to the reservoir water pressure.
6. The stresses due to rib-shortening become quite important in the case of
_____________
a) long thin arch dams
b) thick arch dams of small angle
c) both thin and thick arch dams
d) all types of arch dams
View Answer
Answer: b
Explanation: In the case of an arch dam, the ends being fixed the distance between
them does not change and this restriction of the change in the span causes
additional stresses known as rib-shortening stresses. These stresses are small in a
long thin arch but in the case of a thick arch of small-angle, they are appreciable.
7. Which of the following is not the basis for the design of an arch dam?
a) Thin cylinder theory
b) Trial load theory
c) Unit column theory
d) Elastic theory
View Answer
Answer: c
Explanation: Arch dams are designed on the basis of any one of the following three
methods–
• Thin cylinder theory
• Theory of Elastic arches
• Trial load method
Out of these methods, the trial load method is generally adopted nowadays and it
gives precise results.
8. According to thin cylinder theory, the volume of concrete required for an arch dam
would be minimum if the central angle is ____________
a) 130° 34’
b) 133° 34’
c) 143° 34’
d) 153° 34’
View Answer
Answer: b
Explanation: The most economical central angle is equal to 133°-34’ and such an
angle can be adopted only at one place in constant radius arch dam as there is
considerable variation with height due to narrow V-shape of the valley. It is therefore
considered to keep the economical angle of 133°-34’ at about mid-height for a
minimum value of concrete.
9. The best design of an arch dam is when __________________
a) all horizontal water loads are transferred horizontally to the abutments
b) the dam is safe against sliding at various levels
c) the load is divided between the arches and cantilevers and the deflections at the
conjugal points being equal
d) the deflections of the cantilevers are equal at different points
View Answer
Answer: c
Explanation: In the trial load method, deflections for the arches are calculated at the
points where the cantilevers cross it in each trial. If the deflection calculated at these
points from cantilever elements is within reasonable limits and same, then the
assumed distribution of load is correct. If not, then the calculations are repeated
using a different set of load distribution until the condition is satisfied.
10. At a given elevation, the thickness of the arch ring is proportional to the radius of
the arch.
a) True
b) False
View Answer
Answer: a
Explanation: The thickness of the arch ring (t) under limits is given by –
t = ϒw . h. r / fc where r is the radius of the arch, h is depth, f c is the allowable
compressive stress for the arch material and ϒw is the unit weight of water.
It is clear from the above equation that the thickness of the arch is proportional to the
radius of the arch at a given elevation.