Standard Penetration Test PDF
Standard Penetration Test PDF
Standard Penetration Test PDF
ii
The head of the tube is threaded for connection (via a series of drive rods) to a hammer.
The device is driven into the ground at the base of the borehole with a free falling 63.5 kg
hammer dropping a distance of 760 mm. The standard is much less specific about the
required design of the SPT hammer, stating only that the hammer must have a mass of
140 lbs (63.5 kg) and must drop vertically as freely as possible through 30" (0.76 m)
before hitting the anvil. As a result, different hammer designs have evolved and they vary
considerably. The most commonly used hammer types in North America are the donut,
safety and automatic hammers, as shown in the Figure A2.
iii
iv
Figure A4. Chart to obtain the overburden correction factor as suggested by Peck et al.
(1974)
Figure A5 Chart to obtain angle of internal friction from the corrected SPT N value for
sandy soils.
Uncertainty In The Performance Of The Spt
vi
For example hammer efficiency, borhole diameter, rod length, sampler, Lack of hammer
free fall because of ungreased sheaves, new stiff rope for lifting weight, Use of bent drill
rods etc.
Category D includes sources that are reducible if the test procedure is performed
carefully.
For example Inadequate cleaning of hole, Inadequate head of water in the borehole,
Careless measurement of hammer drop, Sampler driven above bottom of casing, More
than two turns on cathead, Hammer strikes drill rod collar eccentrically, Incomplete
release of rope in each drop, and Careless blow count.
Category E lists irreducible sources in the inves-tigation procedure.
For example Human factor, and Weather and site conditions.
Different researchers tried to correct the field SPT N values due to the errors due to
reducible sources related to the equipment and its maintenance. In this method of the SPT
correction, following corrections are applied.
Overburden correction
Overburden correction factor, CN, is obtained by the following expression.
CN
95.76
/
po
Several investigators have measured the hammer energy in various SPT systems and
found considerable variability. Some investigations
measured blow count was inversely proportional to the energy delivered to the drill rods
for blow counts less than 50. Because of the variable energy input from different SPT
hammer/rod systems, it was suggested that measured blow counts (N-value) be corrected
vii
to reference value of 70% of the potential energy of the SPT hammer. The 70% reference
energy was adopted because energy measurements carried out on different hammer
configurations have indicated an average of about 70% of the theoretical potential energy
of the SPT
If the energy ratio of the SPT set up used is Er then,
Er
70
Similarly, other correction factors due to the rod length, sampler, and borehole diameter
2, 2, and 3 respectively can be obtained from Figure A6.
viii
The corrected SPT N value is referred to as N70/ since the energy ratio is converted to that
corresponding to 70%.
N70 CN1234
/
ix
Example A.1
Five boreholes are driven in a proposed building site to investigate the subsurface
condition for a 20-storey building. The subsurface at the site consists of loose silty sand,
stiff clay, completely weathered rock, and fractured rock. A typical subsurface condition
in a borehole together with the SPT blow counts and rock properties are given in the
following Figure.
If the SPT setup used has an energy ratio of 60% and the borehole diameter is 75 mm,
estimate the soil strength parameters upto the weathered rock layer. (Assume weathered
rock layer consists of coarse grained soil and noliner is used in the SPT sampler).
Depth (m)
SPT
0.00
W. T
1.00
5.00
Stiff clay
12.00
Completely weathered rock
(Coarse sand)
17.00
Fractured rock
1.0
2.0
3.0
4.0
5.0
12
6.0
12
7.0
14
8.0
16
9.0
15
10.0
17
11.0
14
12.0
40
13.0
42
14.0
40
15.0
> 50
16.0
> 50
17.0
> 50
Answer
1
P/o (kPa) CN
Depth
(m)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
16.0
22.2
28.4
34.6
41.8
49.0
56.1
63.3
70.5
77.7
84.9
93.1
101.3
109.5
117.7
125.9
134.0
2.4
2.1
1.8
1.7
1.5
1.4
1.3
1.2
1.2
1.1
1.1
1.0
1.0
0.9
0.9
0.9
0.8
2
0.79
0.79
0.79
0.79
0.79
0.79
0.79
0.79
0.79
0.79
0.79
0.79
0.79
0.79
0.79
0.79
0.79
0.75
0.75
0.85
0.95
0.95
0.95
0.95
0.95
1
1
1
1
1
1
1
1
1
4
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
N/70
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
6
5
5
6
14
13
14
15
14
15
12
32
32
29
c
(kPa)
30
30
30
30
83
75
83
92
83
92
67
43
43
42
Example A2
The subsurface condition at a building site consists of a 3m thick fine sand layer
underlain by a 5m thick normally consolidated clay layer followed by a hard weathered
rock layer. The subsurface condition and the SPT blow counts obtained from the site
investigation program are given in Figure A2. Water table is located at 2.0m below the
ground surface.
Estimate the soil strength parameters of the subsurface using the energy method.
(Assume an energy ratio of 55%, borehole diameter of 90mm and noliner)
CN
95.76
Where
Po/
=
Po
xi
W. T
Depth
(m) 1
SPT
20
22
10
24
12
28
13
25
14
50 <
Bedrock
Figure A2
Answer
Depth (m)
1
2
3
4
5
6
7
8
9
10
12
13
14
SPT (N)
4
3
5
3
4
3
3
20
22
24
28
25
50
P/o (kPa)
15.5
31
37.7
43.9
50.1
52.3
62.5
68.6
75.3
80
95.4
102.1
108.8
N2
0.75
0.75
0.85
0.85
0.95
0.95
0.95
0.95
1
1
1
1
1
xii
N/70
6
3
5
3
4
3
3
17
19
20
22
19
36
/
30
28
29
C (kPa)
12.5
18
12.5
12.5
36
37
38
39
37
45
Question A1
The average subsurface condition of a site is shown in Figure QA.1, together with the
SPT blow counts obtained. As shown in the Figure QA.1, the subsurface consists of a 2m
thick coarse sand layer underlain by a 8.5 m thick normally consolidated clay layer
followed by a weathered rock layer. The bedrock is found at about 18m depth below the
ground surface beneath the weathered rock layer. The water table is located at 2m below
the ground surface.
Estimate the soil strength parameters of the subsurface soil layers using the energy
method for the estimation of the ultimate carrying capacity of the piles. (Assume an
energy ratio of 55%, borehole diameter of 90mm and noliner)
CN
95.76
Where
Po/
=
Po
xiii
Depth
(m) 1
SPT
4.5
7.5
10.5
24
12
22
13.5
25
15
28
16.5
50<
18
50 <