EIAKukulaText Eng PDF
EIAKukulaText Eng PDF
EIAKukulaText Eng PDF
Project Title
Provincial Council
District
Divisional Secretariat Division
Local Authority
: Western
: Kalutara
: Bulathsinhala
: Bulathsinhala Pradeshiya Saba
Installed capacity
: 2.3 MW
Annual Energy
: 11.38 GWh
Rated Flow
: 49.5 m3/s
Weir
Headrace Channel
: Length: 310m
: 0.5 km
: 0.57 ha
Investment
Phone No
Contact Person:
: +94-11-2839656
: Mr. Sarath Hemachandra
: Director
: +94-71-8317129
Name
Designation
Phone
August 2015
TABLE OF CONTENTS
TABLE OF CONTENTS .................................................................................................................................... ii
LIST OF ANNEXES .......................................................................................................................................... v
ABBREVIATIONS ........................................................................................................................................... vi
EXECUTIVE SUMMARY ................................................................................................................................ 1
1.
INTRODUCTION ................................................................................................................................... 6
1.1
Background of the project ...................................................................................................... 6
1.2
Objectives and justification of the project ............................................................................. 6
1.3
Objectives of the EIA report ................................................................................................... 8
1.4
Extent and scope of the study ................................................................................................ 8
1.5
Methodologies adopted in report preparation ...................................................................... 9
1.6
Approvals needed for the proposed development from state agencies ............................. 11
1.7
Any conditions laid down by state agencies ........................................................................ 11
1.8
Compliance with the existing plans of the Area ................................................................... 11
2.
2.4
Project Description ............................................................................................................... 21
2.4.1 Weir ................................................................................................................................. 21
2.4.2 Headrace Channel............................................................................................................ 23
2.4.3 Penstock........................................................................................................................... 24
2.4.4 Power Station .................................................................................................................. 24
2.4.5 Tail race Channel.............................................................................................................. 26
2.4.6 Transmission Line ............................................................................................................ 26
2.4.7 Temporary Structures ...................................................................................................... 27
2.5
Methodology of Construction .............................................................................................. 27
2.5.1 Site preparation ............................................................................................................... 27
2.5.2 Pre and post project construction activities .................................................................... 27
2.5.3 Other construction activities, including temporary structures ....................................... 27
2.5.4 Materials to be used ........................................................................................................ 27
2.5.5 Method of material / equipment transport and installations ......................................... 28
2.5.6 Techniques and equipment to be used ........................................................................... 28
2.6
Number of trees to be felled due to the construction activities .......................................... 28
2.7
Details of any phased development activities and time schedule ....................................... 28
2.8
Any infrastructure facilities required / provided by the project (access road etc.) ............. 28
2.9
Investment and funding sources / state the total cost of the project ................................. 29
2.10 Methodology of operation ................................................................................................... 30
2.10.1 Water utilization schedule, amount to be discharged downstream ............................... 30
2.10.2 Repair and maintenance activities .................................................................................. 30
2.10.3 Desilting requirements / arrangements with frequencies .............................................. 30
2.10.4 Disaster Management Plan (Gate opening / Flood Warning etc.) .................................. 30
EIA of the proposed Bogahahena Kukula MHP
August 2015
ii
3.
4.
August 2015
iii
4.5
Sociological impacts.............................................................................................................. 69
4.5.1 Impacts on existing irrigation systems ............................................................................ 69
4.5.2 Possible impact on the roads ........................................................................................... 69
4.5.3 Impacts on other river uses ............................................................................................. 69
4.5.4 Impacts on existing land use forms due to inundation ................................................... 70
4.5.5 Impacts on existing infrastructure facilities..................................................................... 70
4.5.6 Impacts on commercial activities .................................................................................... 70
4.5.7 Impacts on sand miners ................................................................................................... 70
4.5.8 Impacts due to material transportation .......................................................................... 71
4.5.9 Noise pollution and vibration impacts............................................................................. 71
4.5.10 Impacts on wells & septic tanks in the vicinity due to changes in ground water level ... 72
4.6
5.
6.
7.
August 2015
iv
LIST OF ANNEXES
Annex I
: Terms of Reference
Annex II
: Comments made by the Public, NGOs and Other Agencies during the
Informal Scoping Meetings held by the EIA Team
Annex VI : Complete set of relevant Maps, tables, charts, layout plan and other details
Annex VII : Landslide Investigation Report, NBRO
Annex VIII : Hydrology Report
Annex IX : Hydraulic Study Report
Annex X
August 2015
ABBREVIATIONS
CDM
- Clean Development Mechanism
CEA
- Central Environmental Authority
CEB
- Ceylon Electricity Board
DBH
- Diameter at Breast Height
DS
- Divisional Secretary
DSD
- Divisional Secretariat Division
E&M
- Electrical and Mechanical
EIA
- Environmental Impact Assessment
EIAR
- Environmental Impact Assessment Report
EMC
- Environmental Monitoring Committee
EMoP
- Environmental Monitoring Plan
FDC
- Flow Duration Curve
FSL
- Full Supply Level
GN
- Grama Niladarii
GND
- Grama Niladari Division
GS&MB - Geological Surveys and Mines Bureau
GWh
- Giga Watt Hour
HFL
- High Flood Level
LA
- Local Authority
LKR
- Sri Lanka Rupee
MCM
- Million Cubic Meters
MHP
- Mini Hydropower Project
MSL
- Mean Sea Level
NBRO
- National Building Research Organization
NCRE
- Non-Conventional Renewable Energy
NEA
- National Environmental Act
NWS&DB - National Water Supply and Drainage Board
PAA
- Project Approving Agency
PP
- Project Proponent
PS
- Pradeshiya Saba
rpm
- Revolutions per minute
SEA
- Sustainable Energy Authority
ToR
- Terms of Reference
August 2015
vi
EXECUTIVE SUMMARY
Introduction
Environmental Impact Assessment (EIA) in respect of the proposed Bogahahena - Kukule
Mini Hydropower Project was conducted in order to ensure that the potential adverse
impacts are appropriately addressed in line with the requirements specified in the National
Environmental Act (NEA) and to ensure that proposed project will not pose any significant
negative effect on the environment and socio economic conditions of the people living in
and around the project area.
A team of professionals who are specialists in their respective fields conducted the EIA study
and the EIA Report was prepared as per the Terms of Reference (ToR) issued by the Central
Environmental Authority (CEA) which is the appropriate Project Approving Agency (PAA).
Objective of the Project
The objective of the project is to generate power using a run of river scheme by exploiting
the water head of Kukule Ganga in the downstream of existing Kukule Ganga Reservoir and
connect to the National Grid on an agreement entered into with the Ceylon Electricity Board
(CEB). The installed capacity of the project is 2.3 MW and the expected annual output would
be 11.38 GWh.
Justification of the Project
This renewable energy project would bring about two fold vital benefits to the nation.
Firstly, saving of much valuable foreign exchange by limiting import of fossil fuel required
for generation of equal amount of power. Secondly, it avoids emission of green house gases
to the atmosphere in equivalent amounts generated by burning of fossil fuel. The effort of
the project to prevent emission of green house gases complies with the National Policies on
combating climatic changes and hence eligible for green funding such as CDM. The annual
emissions reduction due from the project is estimated at 8,400 tonnes of CO2 equivalent.
Location of the Project
The project will be located on the right bank of Kukule Ganga in an area within the Paragoda
East Grama Niladhari Division falling within the Bulathsinhala Divisional Secretariat Division
in Kalutara administrative district of the Western Province.
Project Description
The Project is designed to divert the water by constructing a weir with a maximum height of
2.5 m to generate power. The effective catchment area at the weir location is 372 km2 and
the project design flow is 49.5 m3/s. The weir which will be 62 m long with a maximum
height of 2.5 m is designed as a mass concrete structure to be constructed across the Kukule
Ganga. As a result of construction of the weir, river water level will rise up to the weir top
level creating a pond that will extend about 360 m upstream. The entire pond will remain
within the banks and there will be no inundation of any land. The entire Project related
construction will be in the right bank of the river which involves construction of a head race
August 2015
channel about 310 m long, a forebay structure and a power house with two turbines of
1,200 kW each. As it is planned to convey water directly from the headrace channel to the
powerhouse through a forebay structure, no penstock will be required.
The water is finally released back into the river through a tailrace channel (approximately
9m long). The generated power will be connected to the National Grid through a
transmission line (about 500 m long) which will be connected to the existing 33kV
transmission line. Consequently the Project will result in a reduction in the water flow
between the weir and the powerhouse and mandatory discharge which is equivalent to
base flow will be released throughout the Project life to avoid any impact on river
ecosystem.
Bio-Physical Environment
In order to assess and document the baseline conditions in the project area, several studies
were undertaken by the environmental experts, specially related to ecology (terrestrial and
aquatic), hydrology, geology and geomorphology of the area.
In the ecological study, a line transect survey was conducted starting at a point 100 m above
the weir to a point located 50m below the tail race outlet covering 25 m on either side of
the river bank. Terrestrial fauna and flora observed were recorded.
River and riverside vegetation are the only natural habitats observed in the project
impacted area. More than 90% of the project activities will take place in man-made habitats
such as cultivated lands (Oil Palm or Rubber) and abandoned lands.
A total of 33 endemic plants were recorded within the river and riverside vegetation during
the study. Three nationally vulnerable (VU) native plant species and eight nationally near
threatened (NT) native plant species were also recorded within the river and riverside
vegetation.
A total number of 153 plant species recorded from the study area. This included 33
endemics, 15 nationally threatened and 12 nationally near threatened plant species.
Majority of the plant species recorded are trees (72) followed by climbers or creepers (31),
herbaceous species (29) shrubs (20) and epiphytes (1). Further, about 22 % of the recorded
flora is endemic to Sri Lanka and about 23 % of the recoded flora is exotic to the country.
The plant species richness was found to be significantly high in the riverside vegetation
compared to plantations and abandoned lands
Total number of 85 faunal species was recorded in and around the project area representing
land snails, butterflies, dragon flies, freshwater fish, frogs, reptiles, birds and mammals. This
included 9 endemic species and 1 exotic species. Further, one species listed as a nationally
vulnerable and five species including three endemic species listed as nationally near
threatened was recorded among the fauna observed in the direct and indirect impact zone
of the project.
The faunal diversity in these habitats is comparatively low compared to natural riverine
vegetation observed in the indirect impact zone of the project.
Even though, a number of endemic and threatened species has been recorded at the project
site, it does not support any critical habitats. The project will have a temporary impact on
the terrestrial fauna such as disturbance due to noise and vibration and generation of dust.
August 2015
However, these impacts will arise only during the construction phase and can be avoided by
employing best practices during the construction phase. The project will not result in
removal of trees.
As the water will be released back to the river only about 460 m downstream of the weir, it
is proposed to release environmental flow of 0.34m3/s at all times from the weir to meet
the ecological demands of the stretch of the river between the weir and the tail race.
Socio-Economic Environment
The direct project impact area of the proposed mini-hydro power project is confined to
Paragoda East Grama Niladari Division (No 825 A), coming under the Bulathsinhala
Divisional Secretariat (DS) Division in the District of Kalutara. As the power evacuation
system traverses through Molkawa GN division and some indirect impacts of the project
may extend to Paragoda West GN division these two GN divisions were also studied in the
socio- economic considerations. The total population of Paragoda East, Molkawa and
Paragoda West Grama Niladhari divisions is 2,873 as of 2012 which belong to 873 families.
There is an ethnic mix of Sinhala and Tamil in three GN divisions. Other than flooding, no
major social impact is prevailing in this area.
The proposed project land area is owned by the Government of Sri Lanka (Land Reform
Commission) and managed by the privately owned plantation company. The weir, part of
conveyance and part of powerhouse area land falls within the river reservations of the right
bank.
Impacts on the Environment and Proposed Mitigation Measures
The project-related impacts are mainly restricted to construction sites extent of which is less
than 0.6 hectare. These impacts are short term in nature and could be minimized through
good engineering practices during construction period. No significant environmental
impacts are envisaged outside these areas during construction period.
The proposed project will not result in any significant negative impacts on the Socio
Economic Status of the project area. Instead, the Project will bring in positive impacts on
the Socio Economic Status of the area as its construction activities will provide employment
to the people in the suburb during the construction period and additional business to the
suppliers of construction materials.
A hydraulic study was conducted to estimate the possible impact of enhanced flooding due
to the construction of the proposed weir. Floods of 10, 25, 50 and 100 return periods and
sudden opening of flood gates of Kukule Ganga CEB Hydro Power Project were studied. The
study reveals that the impact of the proposed 2.5 m high weir could influence the flood
levels up to a distance of 1,550 m upstream from the proposed weir. Submergence of lands
due to enhanced flooding are very marginal. Only six houses could be affected due to
enhanced flooding and suitable compensation packages are proposed to mitigate those
impacts.
The hydraulic study confirms that there is no enhanced flood impact due to the proposed
weir along the river reach downstream of the weir.
August 2015
There will be no impact on the existing Kukule Ganga Hydropower project during the
construction or operational phases of the proposed mini hydropower project.
Sand mining areas are located downstream of the proposed weir and far from the project
area. Most of locations are now not functioning. However, downstream sand mining will not
be affected due to the project as sufficient sand flushing openings are provided in the weir
and intake designs.
The following Table summarizes the significant environmental and social impacts and
mitigation measures.
Anticipated Impact
Soil Erosion and
Sedimentation
impacts
Increase of Slope
Failures
Flood impacts
Drainage issues
August 2015
Anticipated Impact
River water
pollution during
construction
Reduction in
downstream flow
of the river
Impacts on
terrestrial flora
Impacts on other
river uses
Compensation
packages to the
affected people
Impacts due to
material
transportation
Noise pollution
Vibration impacts /
blasting activities
Conclusion
Implementation of this project will not result in any long term negative environmental and
social impacts. The minor scale negative impacts which are expected during construction
period can easily be mitigated through appropriate engineering practises. Hence, this
project could be recommended for implementation as an environmentally sound and
socially acceptable development activity.
August 2015
1.
1.1
INTRODUCTION
Background of the Project
The Bogahahena-Kukule Mini Hydropower Project plans to exploit the hydro power
potential of Kukule Ganga in the downstream of the existing CEB owned Kukule Ganga
Hydro Power Project. The proposed project is a run-of-the-river and will receive a
consistent water flow for power generation from the Kukule Ganga which comprises with
the turbine discharge of the CEBs Kukule Ganga Hydro Power Project and flow of other
tributaries mainly the Makeli Oya. These two flows converge together at a location about
3.5 km upstream to the proposed weir. The location of the diversion weir, headrace channel
trace, powerhouse and access roads have been carefully investigated after several site
inspections and reconnaissance surveys to form an appropriate layout which is socially and
environmentally complementary and technically feasible. The pre-feasibility study was
conducted along with the hydrology studies and the engineering surveys and obtained the
Letter of Intent from CEB and the provisional approval from SEA.
The project proponent, Zhejiang Young Energy Co. (Pvt) Ltd., is a member of a competent
mini hydropower developing group of companies in Sri Lanka who have been involved in
several hydropower projects including Hapugahakumbura - Walawe Mini Hydro power
project among others.
1.2
August 2015
However, in the past, the electricity demand of the country was mainly supplied by hydro
generation and the contribution from thermal generation was minimal. With the time,
thermal generation has become prominent. At present, thermal generation share is much
higher than that of hydro. Electricity generation during the recent past is graphically shown
in Figure 1.1.
Figure 1.1: National Grids Hydro Thermal Share in the Recent Past
Source: Economic and Social Statistics of Sri Lanka 2014, Central Bank of Sri Lanka
As per the CEB long-term electricity generation expansion plan, countrys energy mix in the
generating system would change from the present oil-dominant status to be coal-dominant,
as shown in Table 1.1. The share of renewable power is estimated to reduce to 20.2%, while
coal-fired and oil-fired thermal generation is estimated to reach 79.8% by 2022. As no more
major hydro power addition other than Broadlands (35 MW), Uma Oya (120 MW),
Moragolla (30 MW) and Gin Ganga (49 MW), CEB encourages the Non Conventional
Renewable Energy (NCRE) generations as a substitute for its highest-cost thermal power
output generated using imported fossil fuels. As a result, the generation mix will be slightly
altered owing to the contribution from NCRE sources, which are targeted to serve 13.3% of
the grids electricity requirement by year 2022.
Table 1.1: Planned Capacity Mix in the Sri Lanka Grid
Type of Plant
2022
2032
MW
MW
Major Hydro
231
6.9
231
3.8
NCRE
445
13.3
720
11.9
Coal
2,300
68.7
4,700
78.0
Gas Turbines
330
9.8
330
5.5
Medium Diesel
44
1.3
44
0.7
3,350
100
6,025
100
Total
August 2015
In this context, the proposed mini hydropower project is a timely intervention, as it will
result in a reduction of anthropogenic emissions of greenhouse gases by displacing an
equivalent amount of electricity that would otherwise be generated by the most expensive
thermal power plants tied into the national grid. The annual emission reduction due to the
proposed Project is estimated at around 8,400 tonnes of CO2 equivalent and is eligible to
attract international carbon finance.
By adding hydropower to the National Grid, the Project contributes to the national economy
by displacing high-cost thermal power by equivalent amount, earning carbon credit and
providing employment. Therefore the project is justified.
1.3
The purpose of the environmental assessment is to ensure that project activities under
consideration are environmentally sound and sustainable. This EIA report is prepared to
facilitate the decisions that are based on understanding the environmental consequences of
this Project and the decisions taken will facilitate to protect, restore and enhance the
environment.
The environment Study specifically aims at the following activities:
assimilate baseline data and information relating to physical, biological and social
environment in and around the project site;
have a series of dialogues with the line agencies, local communities / households
living in and around the project site as well as other stakeholders of the project to
obtain their views;
assess the potential environmental impacts that might emanate during the
construction as well as operation phases of the project;
prepare an Environmental Monitoring Plan (EMoP) so that the Project Proponent can
take timely action to prevent negative environmental impacts before they become
irreversible.
Finally prepare EIA report, which will properly address all the items specified in the
Terms of Reference (ToR) issued by the CEA.
1.4
The ToR issued by the Central Environmental Authority of Sri Lanka, which is the Project
Approving Agency (PAA), defines the scope of the EIA study. The ToR is given in Annex I. The
study area for the assessment is defined in the ToR as follows:
The Project site (weir site to tail race outlet and transmission line trace)
August 2015
The ToR outlines the report structure and the issues to be addressed during the study. The
study covers the existing environmental settings of the Project area (present situation) and
impacts both short-term and long-term in nature. The analysis extends to propose effective
mitigation measures and a monitoring programme too.
1.5
The ToR outlines the extent and scope of the study and the EIA report structure. A
multidisciplinary team of experts were participated in the process of preparation of EIA and
the details of the team of experts for the study is given in Annex IV. A number of
methodologies have been adopted to facilitate the assessment.
The available literature and relevant information was collected, data, information and
reports, survey maps from the feasibility study which is being carried out in parallel with the
EIA study, available topographic maps, geological maps were studied. To supplement the
information derived from desk studies, a number of field surveys and investigations have
been carried out.
Photographs of vital importance and concerns on current situation of the various sites and
the surrounding physical, biotic and social environment were taken using digital cameras to
record empirical evidence.
Data were captured using GPS and maps processed using GIS to identify the administrative
areas, existing status of physical features, drainage network, land use, and infrastructure.
The consultants during their field work visually observed all aspects of physical, biotic and
social environment of the project area. These observations were extremely helpful for the
consultants to identify impacts and propose mitigation measures.
Geological Studies
General geology of the area was studied through secondary sources as well as data
extraction from the Colombo-Ratnapura 1:100,000 scale geology map sheet No. 16
published by the GSMB. Significant geological features of the area, covered by the proposed
civil structures of the project such as geomorphology, bed rock stability, soil erosion, soil
stability and slope failures were studied through field observations. Landslides vulnerability
was studied through a detailed Landslide Hazard investigation in consultation with the
NBRO and recommendations were obtained.
Hydrological Studies
There are a few rain gauges in the catchment, but continuous recent rainfall data are
available only at two locations. Data from three rain gauges were collected to represent
special distribution of the catchment. Selected rain gauges are Deepadine, Dolabodakanda
and Gonapanigala.
The estimated monthly flow volumes were validated with the estimated flow from the MIKE
Basin model developed for Kalu Ganga basin. For the low flow analysis the statistics of the
estimated annual minimum flow rates were obtained. The flood peak analysis was done by
adopting the Snyders flood module in the HEC-HMS model developed by US army Corps of
Engineers.
August 2015
Hydraulic Studies
Back water profiles and its impact along the river due to the proposed weir for MHP was
studied. A numerical hydraulic model was set up to simulate water levels in the river reach
both upstream and downstream of the proposed diversion weir. For this purpose, the
HEC_RAS model developed by the US Army Corps of Engineers, was calibrated.
After calibration of the model, it was simulated without the proposed weir for different
frequencies of natural floods. For simulation flood peaks of 10, 25, 50 and 100 year return
periods were adopted. Then simulations were done for the above scenarios after
introducing the proposed weir to the model. A simulation was also done to understand the
impact of an artificial flood due to possible release of 10,000 year flood by opening the
spillway gates at existing dam of the Kukule Ganga CEB Project.
Ecological Studies
Proposed site
The project will be located in the Molkawa area within the Kalutara District. The weir (2.5 m
tall) will be constructed across Kukule Ganga at. The water diverted at the weir will be
channeled in to a power house located 310 m from the weir site. The water after power
generation will be released back to the Kukule ganga. The stretch of the Kukule ganga
affected by the proposed project can be described as a fast flowing river. The substratum of
the river is made up mainly of large boulders. The area can be classified as an area with land
use patterns dominated by cultivated lands, home gardens as well as abandoned lands.
Riverside vegetation that lies on both sides of the river is the only natural ecosystems found
in the area.
Study period
This study was conducted during the first week of June 2014.
Study methods
Fauna: A Line transect survey was carried out along the proposed ponding area starting at
point 360 m above the weir to a point 120 m below the powerhouse. Terrestrial fauna
observed 25 m either side of the line transect, were recorded. The aquatic fauna present in
the surface and shallow water areas were collected with a hand net and identified.
Flora: Study site was divided into three segments as described below and the plant species
and different habitats present within each of this segment were examined using the line
transect survey method.
Weir and ponding area: The area identified for the construction of the weir and the
area that will be inundated due to the construction of the weir up to 360 m
upstream of the location of the weir
Head race channel, fore bay tank and the Powerhouse: The areas identified for the
construction of head race channel, fore bay tank, powerhouse and the area
immediately downstream of the tail race up to 50 m from the point of release
Riverside and aquatic vegetation: The area examined include about a 460 m stretch
on the two banks of the segment of the river affected by the project.
August 2015
10
All the species observed were recorded with respect to its location and the results were
pooled according to the habitat. In addition to the species, the types of habitats were also
recorded. Species identification and nomenclature of the species present was based on the
latest literature published on the fauna and flora of Sri Lanka (Annex III). The conservation
status of the species was determined according to the Global and National lists of
threatened fauna and flora (Annex III).
Social Impact Assessment
Information required to measure the social impacts within the proposed project area were
collected in the following manner:
Field surveys conducted in the area around 500m from the proposed project to
identify the possible impacts on the existing land use and socio economic status of
the project area.
Discussions with Grama Niladaris of Paragoda East (825 A), Paragoda West (835 C),
Molkawa (825) and Galahitiya (825 B) Grama Niladari Division (GNDs).
Stakeholder consultation meeting held on 10th April 2014, 30th June 2014 and 25th
July 2014 with the GNs and Development Assistants of the area.
Resource profile and other relevant documents maintained at the DSDs and GNDs.
1.6
Approvals from the following agencies are necessary for the implementation of the project.
The approvals and consent letters obtained for various activities during the project
development period are attached in Annex XI.
1.
2.
3.
4.
5.
6.
7.
1.7
Various conditions imposed by the state agencies are included in respective letters of
approval. (Please see Annex XI for details.)
1.8
The project area is a river environment and the construction of the proposed power project
is not in conflict with any development plans of the area.
August 2015
11
2.
2.1
During the course of project planning, many decisions were made concerning the type and
scale of the proposed project, its location and the processes involved. In depth studies and
investigations were carried out in the process of defining best solution by considering all
available alternatives. In this process, design consultants and project developer used their
knowledge, expertise and experience for selecting the best option. Environmental criteria
were also considered at this stage through consultation of experts. The purpose of defining,
evaluating, screening and ultimately selecting feasible project alternative for consideration
in this EIA report included an extensive examinations and discussions between the scientists
and environmental consultants as well as the engineers who designed the project.
Alternatives were evaluated based on how well they meet the overall objectives of the
project in terms of design criteria, environmental, engineering and economic aspects.
2.1.1 No Action Alternative
The countrys expectation is to attain the policy target to generate 20% of power from NCRE
resources and to achieve 100% of electrification of Sri Lanka by the year 2020. The proposed
project will contribute in meeting these targets by adding 2.3 MW which supply 11.38 GWh
annually to the National Grid. In the absence of the Project, the foregone amount of energy
will have to be fulfilled by other means of thermal power options which not only absorb
foreign currency but also the environment will be adversely impacted. Both thermal
alternatives of oil fired and coal fired would result emissions of CO 2, SOx, NOx and
particulates.
In this context, as the Projects social and environmental impacts are minimal and mitigable,
the selection of No action alternative is not a wise option. There are no resource conflicts
as the water of this particular river stretch between the weir and the tailrace is not used for
any other purposes. The decision made to construct the proposed mini hydropower plant is
a good investment in economic terms. It is important and a timely intervention as it
contributes to the increasing countrys alternative environmental friendly power demand
and also supports the call for renewable energy alternatives worldwide.
2.1.2 Alternative Technologies
It is vital to develop its own sources of energy in Sri Lanka as far as possible to meet the
projected demand for electricity. If fossil fuel (coal, oil or natural gas) based energy
generation is considered, it will absorb the countrys net foreign earnings. Substitute NCRE
technologies to this such as converting hydro, wind, dendro, agricultural, industrial and
municipal waste to energy and solar-photo-voltaic energy are certainly important in this
context.
Table 2.1 illustrates a typical comparison of capital and operational cost of alternative NCRE
technologies. When comparing the cost of wind power plants in Sri Lanka, the capital cost
and operation and maintenance (O&M) cost is higher than those of a hydropower plant. The
average plant factor of a wind power plant is only 32% whereas a hydro power plant can go
August 2015
12
beyond 40% making the cost of electricity generated from a wind power in Sri Lanka is
expensive than the cost of electricity generated from hydropower.
Even though the plant factor of dendro power is significantly higher and the capital cost is
almost the same as hydropower, the dendro power technology is yet to be established in Sri
Lanka. The plant factor of other recourses of energy such as agricultural, industrial and
municipal waste is greater than that of hydropower. However, the utilisation of such energy
sources would be possible only when the relevant technologies are adequately developed
and cost effective.
Table 2.1: Typical Comparison of Capital Costs, O&M Costs and Annual Plant Factor
Capital cost
(LKR
Million/MW)
Estimated O&M
cost
(LKR/kWh)
Type of
technology
Annual plant
factor
Mini-hydro
42%
220
1.93
3.0
Wind
32%
243
1.30
1.5
Biomass (dendro)
80%
263
1.501
4.01
1.882
5.02
Agricultural and
industrial waste
80%
263
1.501
4.01
1.882
5.02
Municipal Waste
60%
399
1.753
7.04
Waste Heat
67%
229
0.52
1.33
The solar photo-voltaic (PV) is more widely used in off-grid applications and not yet
considered as a viable option as a grid connected source. When considering the cost, it is 12
times higher than that of hydropower generation.
This gives hydropower a potential edge over the other alternative technologies on the basis
of efficiency and economy.
The proposed Project is a run-of-river hydropower plant system using well established
technologies. Run-of-the-river hydropower facilities are considered one of the best forms of
low impact renewable energy available today which has very low impact on the
environment specially the river flow. The plant capacity of this Project is optimized
considering all vital design parameters. The electro-mechanical equipment have welldemonstrated application around the world and are considered most suitable for this
Project.
2.1.3 Alternative Scales, Design, Technology and Construction Techniques
As far as proposed layout as well as individual components is concerned, several alternative
configurations, designs and technologies were considered and evaluated to provide the
rationale for selection of the preferred design approach. Three such alternatives were
considered during the feasibility study for selection of layout, considering technical /
engineering, social and environmental concerns. Weir and powerhouse locations of all the
August 2015
13
proposals are located inside a 2 km of a river section. The salient features of the proposals
and the conceptual layouts are given below.
Alternative No. 1
Alternative No. 2
: Left Bank Canal Option - 1m high, 75m long weir; 1,840m long
headrace canal Gross head 8.4m; Installed capacity 2.4MW
Figure 2.2: Layout Plan of Alternative No. 2
Alternative No. 3
: Right Bank Canal Option - 2.5m high, 62m long weir; 310m long
headrace canal; Gross head 6.7m; Installed capacity 2.3MW
(Preferred option: This Project)
Figure 2.3: Layout Plan of Alternative No. 3
Comparison of Alternatives
The comparison of the above three alternative configurations is presented in Table 2.2.
Potential power output of the different options have no significant difference and key
considerations in the comparison were their overall financial costs (including diversion
structure, water conveyance mechanism, flood gates and access), simplicity and ease of
construction and their relative environmental and socio-economic implications. Of the
alternatives studied, Alternative No. 3 is recommended.
Figure 2.1: Layout Plan of Alternative No. 1
August 2015
14
Figure 2.3: Layout Plan of Alternative No. 3 (Preferred option: This Project)
August 2015
15
No. 2
Weir: Height - 1m; Length 75m;
Type concrete structure
16.4m MSL
Headrace canal: Length-1,840m; No penstock
required.
8.4m
2.4MW; 11.8GWh
3.15 ha
Length 600m
Fairly high; More than 10 private lands are
involved
Advantage of avoiding massive rock blasting
and resulting physical impacts to the slopes
and the river channel;
Social impacts
Operating level
Water conveyance
Gross head
Capacity; Generation
Land required
Access road
Inundation area
Geological aspects
Construction
No. 1
Dam: Height 8m; Length 34m;
Type concrete structure
16.4m MSL
Directly from weir to powerhouse; No penstock
required.
8.4m
2.6MW; 13.33Wh
0.5ha
Length 600m
High; More than 12 private lands are involved
Possible slope failures, river bank erosions due to
larger ponding area; Excessive rock blasting for dam
construction; River banks to be improved by rubble
lining to have better stability under high flood
conditions
Very large volume of excavation and thereby
destabilizing the slope; Turbines are housed in RC
structures to withstand high flood situations
Environmental Impacts
Excavated soil
Very high volume of excavated soil and loose rock to
handling / Soil erosion be generated due to dam construction; Most likely
river water pollution due to sedimentation
Flooding
Destruction to natural
environment
Construction cost
August 2015
16
6.7m
2.3MW; 11.38GWh
0.57 ha
Existing estate road will be used
Negligible as the inundation area will be confined into
the river banks (rock outcrop)
Advantage of avoiding massive rock blasting and
resulting physical impacts to the slopes and the river
channel;
2.2
Project Location
The proposed MHP site is located at Trafalgar Division of Uskvalley Estate within Paragoda
East GN Division of Bulathsinhala DS Division of Kalutara District. The proposed project is
situated in the Kukule Ganga, about 12 km downstream from the CEBs 70 MW Kukule
Ganga Hydro Power Project. Proposed powerhouse is located at right bank of the river
about 310 m downstream to the proposed weir. The Project Location Maps prepared based
on 1: 50,000 Sheet No. 74 and 1:10,000 Sheet No. 74/15 published by the Survey
Department are given in Figure 2.1 and Figure 2.2.
The site can be reached from Colombo via Horana Bulathsinghala road (B304) and taking a
left turn at Bulathsinhala to reach Paragoda and Molkawa. At Paragoda, there is a bridge
over the Kukule Ganga. There are two alternatives to reach the site; (i) taking left turn
before Paragoda bridge and travelling along Kithulagoda Temple road and then along estate
road within Trafalgar Division and (ii) After passing the bridge, proceed towards Molkawa
old junction and taking left turn at the junction to reach the Kukule Ganga where there is a
ferry service to reach Trafafgar Division.
2.2.1 Administrative Areas within which the Project Components Fall
Provincial Council
Western
District
Kalutara
Bulathsinhala
Bulathsinhala
Village
Following Table shows the administrative areas within which the project components fall in
detail. A map showing the administration divisions of the area is given in Annex VI.1
Table 2.1: Administrative Areas within which the Project Components Fall
Project Component
Pond
Weir
GN Division
(LB)
Molkawa
(RB)
Paragoda East
(LB)
Molkawa
(RB)
Paragoda East
Headrace channel,
Forebay, Powerhouse
Paragoda East
Transmission line
August 2015
DS Division
Local
Authority
District
Bulathsinhala
Bulathsinhala
Pradeshiya
Saba
Kalutara
17
Extents (ha)
0.0400
Headrace channel
0.3325
0.1953
Total
0.5678
Pond
2.7000
August 2015
Ownership
River reservation and Land Reform
Commission (currently managed
by Trafalgar Division, Uskvalley
Estate)
18
August 2015
19
August 2015
20
2.3
Project Layout
Project layout plan drawn on a contour map is presented in Figure 2.2 (on 1:10,000 map),
Figure 2.3 (Auto CAD drawing) and Annex VI.3.
2.4
Project Description
2.4.1 Weir
a.
Location
Weir
b.
Topo Co-ordinate
157477.27 N
141711.44 E
GPS Co-ordinate
0
6 36 57 N
800 14 46 E
As the project is run-of the river type, a minimal storage is required at the weir for
regulating purpose. The weir which will be 62m long with a maximum height of 2.5 m is
designed as a mass concrete structure to be constructed across the Kukule Ganga. Dowels
driven to the bedrock will anchor the weir to the bedrock along its axis and proper
geological investigation programme will be carried out before the construction activities to
see the suitability of the rock for foundations and to study and propose grouting and
foundations treatment requirements. Two flush gates and arrangement for environmental
flow release will be incorporated in to the weir structure. A sand flush gate will also be
provided at the curved section of the intake structure.
The resulting pond will extend up to about 360 m upstream from the weir. Since the river
banks in the pond area are fairly steep, inundation area will be confined only to the river
reservation without any impact on productive lands. Design flow rate was selected as
49.5m3/s which gives nearly 10% exceedance. In other words the river flow at the weir site
will exceed the design flow for about 36 days of the year. Weir will be constructed to
maintain the crest level at 15.0 m MSL. An intake structure has been designed at the right
bank to direct the river flow to the headrace channel. Details of the weir and the intake are
given in Annex VI.4.
c.
The maximum height of the weir from the river bed is about 2.5 m.
d.
August 2015
21
August 2015
22
Weir axis
g.
The Weir Top Level in meters above MSL (Bench mark should be demarcated)
The top level of the weir is 15.0 m above MSL. The location of the benchmark is given in the
Figure 2.3 and Annex VI.3: Project layout plan drawn on a contour map.
2.4.2 Headrace Channel
a.
The headrace channel will be a rectangular reinforced concrete structure which has
dimensions according to the rated flow against installed capacity. The total channel length is
310 m and it comprises with a rectangular cross section with 8.0 m in width and 4.8 m in
height including a free board of 0.3 m. This conveyance channel is located at right bank of
the river along a contour, on a mild slope, and the channel path was so selected in such a
manner that it will need least excavation. Aque-ducts will be provided to sections where
necessary.
Typical land use of the headrace channel route is given in Plate 2.2. The route of the
headrace channel is given in Figure 2.3: Project Layout Plan and typical sections of it are
given in Annex VI.5.
August 2015
23
Headrace
channel route
Estate road
Power House
Location
2.4.3 Penstock
As water conveyed directly from the headrace channel to the powerhouse through a
forebay structure, no penstock will be required.
2.4.4 Power Station
a.
Location
Powerhouse
b.
Topo Co-ordinate
GPS Co-ordinate
157183.22 N
60 36 49 N
141321.31 E
800 14 39 E
Installed Capacity (kW/ MW) and Average Annual Energy Output (MWh /GWh)
The installed capacity of the power plant is 2.3MW and the annual energy output is
11.38GWh.
c.
The powerhouse will be located at the right bank of the river at the end of the forebay
structure considering the site profile and in order to avoid additional conveyance system to
feed the turbines. The powerhouse will facilitate to house all electro mechanical
equipments consisting of Turbines, Generators, Vales Panel boards, crane and all other
associated plant and machinery etc. The powerhouse dimensions will be 8.0 m in width,
21.8 m in length and 13.8 m in height up to the turbine floor. The powerhouse structure will
be a multi storied (Annex VI.6), concrete water-sealed type structure to withstand high
flood situations. The outer wall of the powerhouse will be raised above the high flood level
and will be abutted to the existing natural ground level. The machine floor would be
reinforced concrete.
August 2015
24
Conceptual Design of powerhouse and turbines arrangement is given in Annex VI.6 and the
location of powerhouse is shown in Plate 2.3.
d.
The powerhouse, equipped with 2 similar units of 1200kW vertical shaft Kaplan turbines and
synchronous generators of 1350kVA with built-in exciters. Rated speed of the turbines is
300 rpm. Other powerhouse equipment will include inlet valve, governor oil pressure
system, medium voltage switchgear, low voltage switchboard, control, monitoring and
protection system and the powerhouse overhead hoist. Complete G59 protection system
will be incorporated as per CEB requirements.
The generated energy will be fed in to the National Grid through the switchyard which will
consist of 2 Nos. of 415V/33kV, 1400kVA step-up transformers placed outside the
powerhouse. The terminal tower of the 33 kV transmission line will be located at the switch
yard.
e.
Powerhouse location
August 2015
25
Water is released back to the river immediately after the power generation through the
draft tube and followed by about 9m long tail race channel along the river. The arrangement
of the tail race is shown in the layout plan (Figure 2.3, Annex VI.3 and Annex VI.6).
2.4.6 Transmission Line
a.
Transmission Voltage
The transmission line will be constructed from the switchyard to the existing CEB high
voltage transmission line which routes along Molkawa-Kelinkanda road (Kukule Ganga
Powerhouse access road). The point of interconnection will be the nearest transformer at
the road and the length is approximately 500m from the powerhouse.
The 33kV transmission line will be constructed under the supervision of CEB simultaneously
with the civil works of the project to utilize the resources assigned to the project effectively.
c.
Land Ownership along the Transmission Line (Approved map of the transmission
line should be submitted)
Transmission line started from the switchyard will be crossed the river and routed along the
river access road at Bogahahena villege in Molkawa GND and then along Molkawa
Kelinkanda road to connect the CEBs existing transformer. The route of the transmission
line is shown in Figure 2.2 and Annex VI.3. Photographs of river access road and the existing
transformer is shown in Plate 2.4.
Plate 2.4: River access road and existing transformer at Molkawa-Kelinkanda road
August 2015
26
Methodology of Construction
August 2015
27
Time (Month)
9 10 11 12 13 14 15 16 17 18 19 20
2.8
Any Infrastructure Facilities required / provided by the Project (Access Road etc.)
New Access road will be constructed to the powerhouse and weir and existing village road
will be improved as required.
Two houses form the area will be rented out till permanent facilities are provided at
powerhouse site.
EIA of the proposed Bogahahena Kukula MHP
August 2015
28
2.9
Investment and Funding Sources / state the Total Cost of the Project
The estimated total project cost is LKR 690 Million. During the feasibility study, the
developer has conducted the project financial analysis and the financing structure proposed
and summary of the financial analysis are given in Table 2.4.
Table 2.4: Financial Structure and Summary of Financial Analysis of the Project
(a) Financial Structure
Source of Finance
Equity
Long term loan
Total
%
40
60
100
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
197.9
197.9
197.9
197.9
197.9
197.9
197.9
88.9
88.9
88.9
88.9
88.9
88.9
88.9
59.5
59.5
59.5
59.5
59.5
2.0
2.0
2.0
2.0
2.0
2.0
2.0
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.6
0.6
0.6
0.6
0.6
195.9
195.9
195.9
195.9
195.9
195.9
195.9
88.0
88.0
88.0
88.0
88.0
88.0
88.0
58.9
58.9
58.9
58.9
58.9
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
24.7
171.2
171.2
171.2
171.2
171.2
171.2
171.2
63.3
63.3
63.3
63.3
63.3
63.3
63.3
34.2
34.2
34.2
34.2
34.2
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
27.6
39.7
34.0
27.8
20.9
13.3
4.9
-
103.9
103.9 131.5
109.6
109.6 137.2
115.8
115.8 143.4
122.7
122.7 150.3
130.3 15.6 114.7 142.3
138.7 16.6 122.1 149.7
143.6 17.2 126.4 154.0
35.7
4.3
31.4
59.0
35.7
4.3
31.4
59.0
35.7
4.3
31.4
59.0
35.7
4.3
31.4
59.0
35.7
4.3
31.4
59.0
35.7
4.3
31.4
59.0
35.7
4.3
31.4
59.0
6.6
0.8
5.8
33.4
6.6
0.8
5.8
33.4
6.6
0.8
5.8
33.4
6.6
0.8
5.8
33.4
6.6
0.8
5.8
33.4
Internal Rate of Return (IRR)
98.7
126.3
(449.7)
171.2
171.2
171.2
171.2
171.2
155.6
154.6
154.0
59.0
59.0
59.0
59.0
59.0
59.0
59.0
33.4
33.4
33.4
33.4
33.4
20%
Project
1,900.4
197.0
50.6
55.8
61.5
67.7
74.6
82.2
90.6
-
98.7
Repayment of Loan
44.9
27.6
Cash Flow
Interest on Loan
171.2
Net Profit
Depreciation
24.7
Taxation
Operating Profit
195.9
Net Revenue
2.0
Sales Tax @ 1%
197.9
Revenue
Year
O&M Cost
(135.0)
75.7
75.7
75.7
75.7
75.7
60.1
59.1
154.0
59.0
59.0
59.0
59.0
59.0
59.0
59.0
33.4
33.4
33.4
33.4
33.4
36%
Equity
1,231.9
127.7
IRR
20%
18%
17%
15%
36%
36%
27%
27%
*r - Discount rate
August 2015
29
2.10
Methodology of Operation
August 2015
30
3.
Study Area
The geographic area for the environmental study is defined in the ToR as follows:
The project site (weir site to tail trace outlet and transmission line trace)
The area of influence is often, if not always, variable and dependent on the impacting
factors (both direct and indirect) and the affected resources. It is generally complex and is
rarely limited to specific distance from the project area. Hence, for the purpose of this EIA,
the team of environmental consultants decided to extend the study area by considering the
nature and extent of the impact on the physical, ecological and socio-economical
environments as presented in respective Sections below.
3.1
Physical Environment
3.1.1 Topography
Kukule Ganga stream is one of the main tributaries of Kalu Ganga which enters to the sea at
the western coast of the country. This stream originates from the south western slope of
Sinharaja forest at an elevation of 2000 m above mean sea level (amsl). The proposed mini
hydro power project area is located at an elevation about 8 to 25 m amsl. The source of the
project is Kukule Ganga, which has supplemented by a number of tributaries at its upper
reaches. The take-off point of the project is situated about 2 km upstream to the Paragoda
bridge. The catchment area up to the weir location is about 372km2.
The area is characterized by undulating topography with medium steep ridges and valleys
(Figure 3.1). The relief of the area varies approximately from 25m up to 250m above mean
sea level dominating undulating nature.
The Kukule Ganga flows through a relatively fairly broad and gentle valley, which trends
approximately towards east to west direction at the weir and power house area. All the
project related structures are to be constructed in the right bank slope of the Kukule Ganga.
The continuous nature of this slope has been disturbed by intermittently situated small
scale valleys across the slope and the erosion taken place along them. This is an inherent
feature related to the subsurface geology and structure. The area is characterized by a
dendritic type of drainage network. The inclination of the lower part of left bank slope at the
weir site is about 300. However, slope angles at certain places somewhat deviate as low or
high from the general trend.
August 2015
31
August 2015
32
3.1.2 Geology
General Geology of the Area
Geologically, the proposed project area belongs to the Highland Complex of Sri Lanka (HC)
and consists of granulite grade metamorphic rocks, which are biotite hornblende gneiss,
charnockitic gneiss, charnockitic biotite gneiss, garnet sillimanite biotite gneiss and quartzite
(Figure 3.2). These rocks are trending in NW SE direction, having high dip angles in S-W
direction. These rocks represent the south west limb of an antiform structure. The rocks of
this limb have further been folded into minor folds. Figure 3.2 is the regional geology map
around the project area and is extracted from the Colombo-Ratnapura 1:100,000 scale
geology map sheet No. 16 published by the GSMB.
Due to the complex structural nature of the area, composition of the bed rock is significantly
varied in same outcrop in the project area. Therefore, rock layers of quartzo feldspathic
gneiss can be observed in the area. The rocks are moderately to highly weathered in the
project area. Two fracture systems can be observed in the rocks of the project area. Detail
of the fracture systems, which is widely distributed in the rocks of the project area, is as
follows.
No.
Fracture Direction
/ Dip Angle
0
N60 E/0900
N30 W/0900
Fracture
Density
Remarks
3/m
3/m
Significant geological features of the area, covered by the proposed civil structures of the
project, are described in the following section.
Weir Site
Weir site is located on a near straight section of Kukule Ganga trending N-S direction, just
few meters downstream to a bend (Plate 3.1). Highly foliated moderately to highly
weathered and highly jointed garnetiferous quartzo feldspathic gneiss rock, which has
biotitic layers, is exposed on the river bed and at the bottom of both river banks around the
proposed weir site. Some dislodged and detached boulders (1 m x 1 m x1 m) are observed
on the bed rock exposures around the weir site area. This rock exposure shows a dip of 80 0
towards the south west. The strike of foliation of the rock is N 300W.
August 2015
33
August 2015
34
Weir area
.
The both stream banks can be identified as intermediate slopes. However, the angle
between stream flow direction and the dip direction is 60 0. The angle between the major
joint system and the weir axis is about 300. These fractures are slightly open and show slight
weathering condition. The foliation joint plane is in the flowing direction of the river with an
acute angle. Some blasting may be required during weir construction. The fresh rock is
expected at 1-2 m depth from the surface.
The river channel has a mild gradient towards upstream from the weir site. The bottom of
both river banks are protected by the presence of exposed bedrock. A mixture of silt, sand
and gravel deposit can be observed on the river bed, along which water is flowing.
The both river banks are not very steep at the lower parts at the weir area. Slope angles of
lower parts of right and left banks are about 40 0 and 300 respectively. Next sections of both
slopes are observed less steep than lower parts. On the right river bank slope, red brown
coloured residual soil formation is encountered with an overburden thickness of about 2-4m
(Plate 3.2). On the left river bank slope, dark brown coloured colluvium soil formation is
encountered with an overburden thickness of about 1-2 m. Both river bank slopes are
covered by vegetation (Plate 3.3). The thickness of the overburden deposit is largely
increased towards the upper areas.
Although the exposed bed rock surface is highly fractured and weathered, sound bed rock
can be found at about 1-2 m depth around the weir area. Therefore, proposed weir
structure could be constructed with minimum difficulty. However, the orientation and
weathering conditions of joint planes and the foliation plane may create stability issues for
the weir structure, unless properly treated.
August 2015
35
Plate 3.2: Showing the red brown residual soil at the right bank
Plate 3.3: River bank slopes at the weir and intake area
Weir area
August 2015
36
Ponding Area
As the height of the proposed weir is about 2.5 m, created pond will be extended upto
about 360 m upstream from the weir.
According to the present depth of the ponding area, it is only about 1.5 m deep at the
vicinity of proposed weir structure. The depth of the rest of the ponding area is also
remaining shallow. The proposed ponding area comprises of approximately 75 m average
width across the stream. After implementation of the project, the depth of the ponding area
will be 2.5 m deep near the weir location and gradually decreases towards the tail area of
the pond. The bed rock exposures are observed at most locations along the periphery of the
pond area. A majority of the upper slopes of the pond area are covered by either forest or
rubber lands. Dwelling cannot be observed close to pond area. Submergence of soil, which is
situated above the rock, may not be expected after implementation of the project.
Headrace Channel Route
The entire headrace channel is proposed in the right stream bank, which is covered by 1-2 m
thick residual soil cover. The length of the conveyance channel is about 310 m. The bedrock
is exposed at the intake area and blasting is required (Plate 3.4).The proposed path for the
headrace channel is located a few meters above from the edge of the right river bank. The
slope angle is about 200-300 and covered with newly planted oil palm trees and 2-3 m deep
excavations are expected (Plate 3.5).
Plate 3.4: A view of the intake area
Intake area
August 2015
37
A considerably large section must be excavated at the intake area, where rock blasting is
also required. According to the structural details of the rock, slope can be destabilized along
existing defects. Since the dimension of the channel is 8 m x 4.5 m, exerted pressure on to
the ground is considerable, after implementation of the project. Therefore, rock mass can
be failed along joints unless sound rock is found to lay the foundation.
Forebay Tank
The geological conditions at the proposed forebay tank area are almost similar to that of the
headrace channel path.
Power house and tail race
The power house will be constructed on a valley like land portion, where the bed rock
exposure, which is slightly weathered, is observed (Plate 3.6). The rock has to be blasted to
prepare the location for the power house. A thin soil cover is observed on the rock at the
surrounding area. The expected rock slope cut can be destabilized along existing joint
planes.
August 2015
38
Powerhouse site
Access Road
Existing estate roads can be utilized to access the project area with minor improvements.
Mineral Resources of the Area
Economically viable mineral deposits have not been reported or identified in and around the
area covered by the proposed project, except minor river sand pockets and alluvial clay
deposits.
The entire area covered by the proposed project consists of high grade metamorphic rocks,
having varying proportions (uneconomical) of common rock forming minerals such as
quartz, feldspar, biotite, garnet, hornblende, etc. Therefore, there will be no impact on
mineral resources due to the implementation of the project.
Available fresh rocks in the area could be used as construction materials. However, so far
these rocks have not been used for extraction of construction materials, mainly due to the
presence of number of rock quarries in other parts of the area.
Landslide Potential of the Project Area
A detailed Landslide Hazard investigation report and the clearance have been obtained from
the National Building Research Organisation (Annex VII).
August 2015
39
August 2015
40
August 2015
41
3.1.4 Hydrology
A hydrology study was carried out to reach the objectives mainly to estimate the long term
flow regime of the catchment above the proposed site to assess the availability of water for
the project. A low flow analysis was also carried out. Project Hydrology Report is given in
Annex VIII.
In order to estimate the possible impact of enhanced flooding due to the construction of the
proposed diversion weir, a hydraulic study was also carried out.
Effective Catchment Area
The effective catchment area at the proposed weir location is 372km2. The catchment area
maps are given in Annex VI.7 and Hydrology Report (Annex VIII).
Rainfall Patterns of the Effective Catchment Area
Data from three rain gauges were collected to represent spatial rainfall distribution of the
catchment. Selected rain gauges are Deepadine, Dolabodakanda and Gonapanigala. Due to
inconsistency of rainfall records 18 years of data range from 1992 to 2011 was considered in
the analysis. The annual average rainfall for 18 years at Dolabodakanda rain gauge is
3,633mm and that of Deepadene is 3,349mm respectively. The data for Gonapanigala is
available only up to 2003 with few missing data and the average from 1992 to 2003 is
2,905mm. Table 1 to Table 3 of Annex VIII: Hydrology Report shows the monthly rainfall
data at Deepadine, Dolabodakanda and Gonapanigala respectively. The basin average
rainfall for 18 years from 1992 to 2011 was estimated at 3,447mm. The average monthly
distribution of rainfall is depicted in Figure 3.4. From this figure it is clear that SW monsoon
dominates the catchment rainfall and lowest rainfall occurs in February.
Figure 3.4: Distribution of average basin rainfall-From 1992 to 2011
August 2015
42
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Mean
Mean
33.27 27.71 35.00 22.29 16.67 13.31 17.79 35.44 25.93 32.96 28.53 35.22 27.05
Max
54.69 40.24 53.87 46.08 54.21 29.11 29.74 62.95 37.13 56.60 45.59 59.77 62.95
Min
7.88
6.18
August 2015
6.18
43
% Exceedance
Flow rate (m3/s)
10
20
30
40
50
60
70
80
90
95
50.89
38.52
31.91
26.31
21.78
17.75
13.80
9.98
6.20
3.92
August 2015
44
10
1,297
25
1,561
50
1,771
100
2,069
2,638
August 2015
45
3.2
Biological Environment
August 2015
46
Two out of the 33 endemic plant species observed during the field investigations in the river
side vegetation downstream of the proposed weir location, Aponogeton rigidifolius
(Kekatiya) and Drypetes lanceolata are listed as nationally endangered (EN). Out of these
two species, Drypetes lanceolata that was observed in the riverside vegetation on the left
bank of the river is a very rare plant species. According to the A Revised Handbook to the
Flora of Ceylon it has been recorded from only few locations in Kalutara (exact location
unknown), Ratnapura (Nambapana) and Kandy (Madugoda) districts. As this species was
recorded on the left bank of the river it will not be directly impacted by the project as the
project activities take place in the right bank of the river. A detailed list of plant species
observed within the river and riverside vegetation is given in Annex X.
3.2.4 Flora of the Project Area
Flora of the Proposed Canal Path
The proposed canal trace passes through an Oil palm cultivated land. Few species of weeds
were observed in the area other than the oil palm. None of the plant species observed in
this area are listed as endemic, nationally threatened or nationally near threatened. A
detailed list of plant species observed along the canal trace is given in Annex X.1.
Flora of the Proposed Powerhouse Location
The proposed powerhouse will be located in an abandoned land on the right bank of the
river. A single endemic plant species, Ochlandra stridula (Bata) was observed in the
proposed location. A detailed list of plants recorded within the proposed powerhouse
location is given in Annex X.1.
Flora of the Project Area
A total number of 153 plant species including 33 endemics, 15 nationally threatened and 12
nationally near threatened plant species were recorded during the field survey within the
study area (Table 3.3). Majority of the plant species recorded are trees (72) followed by
climbers or creepers (31), herbaceous species (29) shrubs (20) and epiphytes (1) (Table 3.3).
Further, about 22 % of the recorded flora is endemic to Sri Lanka and about 23 % of the
recoded flora is exotic to the country. A detailed list of plant species recorded in and around
the project affected area is listed in Annex X.1.
Table 3.3: Summary of the Plant Species Recorded During the Study
Total
Species
Plant Type
VU
NT
Endemic
Native
Exotic
Tree
72
1 (1)
7 (5)
7 (3)
21
37
14
Shrub
20
2 (2)
11
Herb
29
1 (1)
15
12
Epiphyte
Climbers/ Creepers
31
4 (3)
3 (1)
21
153
2 (2)
13 (10)
12 (4)
33
85
35
22%
55%
23%
Total
%
August 2015
47
The plant species richness was found to be significantly high in the riverside vegetation
compared to plantations and abandoned lands. Likewise, the endemic species and
threatened species were recorded only in the riverside vegetation while the exotic species
were recorded predominantly in the cultivated lands (Oil palm or Rubber) and abandoned
lands where more than 90% of the project activities will take place (Table 3.4).
Table 3.4: Summary of the Plant Species Recorded in areas identified for different project
activities
Project activity
Total
Species
River banks*
Headrace canal
Power House
142
17
8
Conservation Status
EN
VU
NT
2
13
12
0
0
0
0
0
0
Taxonomic Status
E
N
I
33
79
30
0
7
10
1
3
4
T
70
1
3
S
20
1
1
Habit
H
22
12
2
E
1
0
0
C
29
3
2
* Riverbanks are not significantly impacted (less than 10% of project activities take place in river banks).
However the river banks come within the indirect impact zone and therefore considered in the impact analysis.
Abbreviations used: EN - Endangered, VU - Vulnerable, NT - Near Threatened, E - Endemic, N - Native, I Introduced or Exotic, T - Tree, S - Shrub, H - Herb, E - Epiphyte, C - Climber.
Scientific Name
Strobilanthes spp.
Hydnocarpus venenata
Mangifera zeylanica
Semecarpus gardneri
Semecarpus marginata
Willughbeia cirrhifera
Aponogeton rigidifolius
Lagenandra sp.
Schefflera emarginata
Calamus digitatus
Calamus thwaitesii
Dracaena thwaitesii
Common Name
Nelu
Makulu
Etamba
Badulla
Kiri Wel
Kekatiya
Kethala
Kukulu Wel
Ma Wewel
August 2015
HA
S
T
T
T
T
C
H
H
C
C
C
S
TS NCS RS CA PH
E
LC +
E
LC +
E
LC +
E
LC +
E NT +
E VU +
E EN +
E
LC +
E VU +
E VU +
N VU +
N NT +
48
Family New
Calophyllaceae
Centroplacaceae
Clusiaceae
Cyatheaceae
Dipterocarpaceae
Euphorbiaceae
Euphorbiaceae
Lamiaceae
Lauraceae
Lauraceae
Lauraceae
Marattiaceae
Melastomataceae
Melastomataceae
Moraceae
Moraceae
Myristicaceae
Myrtaceae
Myrtaceae
Pandanaceae
Pandanaceae
Phyllanthaceae
Poaceae
Polygalaceae
Putranjivaceae
Rhamnaceae
Rhamnaceae
Rhizophoraceae
Rubiaceae
Sapotaceae
Sapotaceae
Simaroubaceae
Scientific Name
Calophyllum acidus
Bhesa ceylanica
Garcinia quaesita
Cyathea walkerae
Dipterocarpus zeylanicus
Macaranga digyna
Mallotus fuscescens
Vitex altissima
Cinnamomum zeylanicum
Cryptocarya wightiana
Litsea longifolia
Angiopteris evecta
Lijndenia capitellata
Osbeckia octandra
Artocarpus nobilis
Ficus diversiformis
Horsfieldia iryaghedhi
Cleistocalyx operculatus
Syzygium neesianum
Freycinetia walkeri
Pandanus ceylanicus
Aporusa lanceolata
Ochlandra stridula
Xanthophyllum zeylanicum
Drypetes lanceolata
Gouania microcarpa
Ziziphus rugosa
Carallia brachiata
Gardenia crameri
Madhuca neriifolia
Palaquium canaliculatum
Quassia indica
Common Name
Batu Kina
Pelan
Rat Goraka
Gini Hota
Hora
Gal Ota
Milla
Kurundu
Golu-Mora
Rat Keliya
Wal Meda
Pini Baru
Heen Bowitiya
Bedi Del
Ruk Gedhi
Bata Damba
Panu Kera
Dunu Keyya
Heen Kebella
Bata
Palala
Maha Eraminiya
Dawata
Galis
Gan Mi
Elakirihembiliya
Samadara
HA
T
T
T
T
T
T
T
T
T
T
T
H
T
S
T
C
T
T
T
C
S
T
S
T
T
C
C
T
S
T
T
T
TS NCS RS CA PH
N NT +
E
LC +
E
LC +
E VU +
E NT +
E NT +
E
LC +
N NT +
E VU +
N NT +
E
LC +
N NT +
E VU +
E
LC +
E
LC +
E
LC +
E VU +
E
LC +
E
LC +
E NT +
E VU +
E
LC +
E
LC +
+
E
LC +
E EN +
N NT +
N NT +
N NT +
E VU +
N VU +
E VU +
N VU +
August 2015
49
Table 3.6: Summary of the faunal species recorded in the study area
Threatened species
Total
Species
Endemic
Species
Migrant/ Exotic
Species
CR
EN
VU
NT
Land Snails
Butterflies
14
Dragonflies
Freshwater Fish
Frogs
Reptiles
Birds
34
Mammals
86
Taxonomic Group
TOTAL
Social Environment
August 2015
50
the population and the Muslim community accounts for 4%. Table 3.7 and Table 3.8 show
the ethnic and religious distribution of the population in the DSD respectively.
Table 3.7: Ethnic distribution of the population in Bulathsinhala DS Division
Ethnic Group
Sinhala
Population
57,029
84.5
Tamil
7,938
11.8
Muslim
2,470
3.7
other
24
0.04
Total
67,461
100
Population
56671
84
Hindus
7341
10.9
Islam
2286
3.4
Roman Catholics
754
1.1
Other
409
0.6
Total
67461
100
Buddhists
Since the proposed project falls within Pagoda East GN Division and the power evacuation
system traverses through Molkawa GN division and some impacts of the project may extend
to Paragoda West GN division, it is considered that the Paragoda East, Molkawa and
Paragoda West Grama Niladhari division areas, which are located in the Bulathsinhala
Divisional Secretariat Division (DSD) shall be considered to examine the socio-economic
impacts due to the proposed project.
Background of Paragoda East, Molkawa and Paragoda West Grama Niladhari Divisions
Population characteristics
The total population of Paragoda East, Molkawa and Paragoda West Grama Niladhari
division is 2,873 as of 2012 which belong to 873 families. Table 3.9 shows the number of
families and total population living in the three GN divisions under reference.
Table 3.9: No of families and total population in three GN divisions
GND
No. of Families
Total population
825A
Paragoda-East
282
1020
825
Molkawa
254
816
825C
Paragoda-West
337
1037
873
2873
Total
August 2015
51
Total
Population
Molkawa
Ethnic Distribution
Religious Distribution
816
809
07
798
09
09
Paragoda-East
1,020
1,019
01
1,015
05
Paragoda-West
1,037
1,029
02
06
1,029
02
06
Total
2873
2857
09
07
2842
11
20
Gender
Total
population Female Male
Age
0-5
6-18
Over 70
816
421
395
74
173
229
230
53
57
Paragoda-East
1,020
524
496
100
190
345
223
107
55
Paragoda-West
1,037
525
512
82
168
420
174
117
76
Total
2,873
1,470
1,403
256
531
994
627
277
188
Land Ownership
The total Land area of Paragoda East GN Division is 2729 acres( 11.05 km 2 ) while Molkawa
GN Division is 864 acres (3.5 km2 ) and Paragoda west is 1161 acres ( 4.7 km2).
Land ownership details of the three GN divisions are presents in Table 3.12. It reveals that a
total of 693 acres belong to private owners and 291 acres are owned by the State. There are
95 acres of land given to people on various licences.
August 2015
52
Privately
Owned
Licensed
Religious
properties
Molkawa
66
44
30
05
Paragoda east
168
73
40
Paragoda west
57
576
25
06
Total
291
693
95
11
GND
Toilets
Partly
Land No
Pit
No
Rented Estate
Water seal
Constructed
Owned land
Latrines toilets
Molkawa
20
214
205
02
27
Paragoda East
72
210
243
15
24
ParagodaWest
43
265
02
02
267
01
35
Total
135
689
02
02
715
18
86
August 2015
53
Private
Sector
Agriculture
sector
Self
Employed
Employed
in foreign
countries
Molkawa
18
74
327
77
73
Paragoda-East
38
62
164
48
18
139
86
Paragoda-West
30
44
220
15
10
182
Total
86
180
711
140
28
321
159
GND
Other Unemployed
August 2015
54
Paragoda-East Paragoda-West
Total
141
113
254
508
Unprotected Well
07
42
04
53
02
02
Common Wells
18
15
12
45
River/Streams
41
74
04
119
17
17
Other
01
01
Tube Well
Molkawa
Paragoda-East Paragoda-West
Total
Electricity
Houses with Electricity
203
182
264
649
Other Sources
04
04
No Electricity
31
95
57
183
Land Phone
20
48
55
123
Mobile Phones
171
204
215
590
Telephone
August 2015
55
4.
4.1
Hydrological Impacts
4.2.1 Anticipated Flood Problems in the Area as the Result of the Project
Flood Issue in the Area - An Overview
Intense rainfall received in upper catchments causes floods in downstream river basins
when the rivers cannot hold the flow of water. Flooding also takes place in lowlands when
intense rainfall causes the inflow to exceed the outflow. People living in low-lying areas of
Kalutara District in particular, Bulathsinhala, Madurawala, Dodangoda, Millaniya and
Kalutara DSDs often claimed an increase in occurrences and severity of the flood events
experienced during the recent past. More complaints were recorded from the villagers at
the immediate downstream of the proposed project specially from Molkawa, Paragoda
West and Galahitiya GNDs.
During the EIA study, flood issue faced by the villagers in and around the proposed project
area were investigated in detail. Previously recorded flood data were collected from the
Irrigation Department and literature on the Kukule Ganga, Kuda Ganga and Kalu Ganga
system were studied. Views of officials and villagers were gathered by conducting meetings
and informal discussions etc. An extreme flood event was experienced during the EIA study
period on 04th June, 2014. The flood peak measured at Millakanda river gauging station
(Figure 4.1) was recorded as 869.92m3/s which is equivalent to 10.28m MSL flood level.
Photograph showing the flood level at Molkawa old junction is given in Plate 4.1. Water
levels recorded at Millakanda and Putupaula river gauging stations are shown in Figure 4.2.
August 2015
56
Plate 4.1: Flood Level experienced during the most recent event on 04 th June, 2014
Flood Level
Figure 4.1: River Gauging Stations along the Lower Kalu Ganga System
Naragala bridge
Kalu Ganga
Narthupana bridge
Millakanda
Kuda Ganga
Kukule
Ganga
Putupaula
Kalawellawa bridge
To
Kalutara
Proposed
project area
August 2015
57
Historical flood flows recoded at Millakanda river gauging station is given in Table 4.1.
Flood condition in these areas could be described as a combination of various factors such
as terrain, increase in rainfall intensities which could be due to climate change impacts,
nature of the lower Kalu Ganga river network and man-made activities etc. Some of the
observations related to these factors are discussed below.
Terrain of the Area
Up to the proposed project area, Kukule Ganga flows through narrow parallel valleys. Then
the river enters to a comparatively low lying flood plain with a lower river gradient. Most of
the areas at immediate downstream to the proposed project are at an elevation less than
10m MSL as shown in the Figure 4.3: Google map showing the terrain of the area. Contour
details of this area are given in Figure 3.1: Topography Map.
August 2015
58
Proposed
project area
Millakanda River
Gauging Station
Paragoda East
Paragoda West
Kukule
Ganga
Galahitiya
August 2015
59
Table 4.1: Historical flood flows recoded at Millakanda River Gauging Station
Catchment Area
: 780.29 km2
Gauge Zero
: 0.04m
Water Year
Flood Peaks
m3/s
Date
Water Year
Flood Peaks
m3/s
91/92
537.85
06-06-92
50/51
591.30
92/93
674.16
29-06-93
51/52
571.06
93/94
703.46
28-05-94
52/53
481.02
94/95
425.37
07-06-95
53/54
NA
95/96
458.48
09-10-95
54/55
713.61
96/97
486.64
24-09-97
55/56
512.33
97/98
532.00
20-07-98
56/57
NA
98/99
726.00
21-04-99
57/58
447.55
99/00
569.01
15-10-99
58/59
241.36
00/01
275.44
07-10-00
59/60
275.03
01/02
200.66
14-05-02
60/61
218.12
02/03
1,020.86
18-05-03
61/62
571.06
03/04
380.30
20-09-04
62/63
544.44
04/05
359.50
06-09-05
63/64
438.81
05/06
356.31
23-06-06
64/65
NA
06/07
405.32
28-10-06
65/66
1,166.28
07/08
1,320.45
01-06-08
66/67
1,016.69
08/09
421.77
18-08-09
67/68
NA
09/10
617.85
20-05-10
68/69
1,139.98
10/11
528.14
30-04-11
69/70
392.71
11/12
263.79
13-12-11
70/71
905.69
12/13
536.43
02-11-12
71/72
925.70
13/14
869.92
04-07-14
72/73
271.64
73/74
544.44
74/75
NA
75/76
528.39
76/77
534.72
August 2015
60
According to the studies, it is clearly seen that the southwest monsoon rainfall,
which usually confines to the western and south western parts of the island, is
projected to increase. (Dr. B.R.S.B. Basnayake, Climate change in Sri Lanka)
Studies have revealed a 24 hour heavy rainfall trend in Sri Lanka (1901-2000),
specially a higher increasing trend in south western areas. The increase is mostly due
to south-westerlies (due to monsoon or either due to direct or indirect effect of
cyclonic disturbances)(G.B. Samarasinghe, Long Term Forecast of Climate Change: Sri
Lanka Future Scenario, Meteorological Department).
National Climate Change Adaptation Strategy for Sri Lanka - 2011 to 2016; Water
Sector Vulnerability Profile published by Ministry of Environment, 2012 reports that
the increased intensity of rainfall in the wet zone due to climate change is expected
to increase the tendency for flooding of flood prone rivers. In the regions where
precipitation is generally high, more intense rainfall expected from climate change
scenarios would lead to increase the frequency of floods and landslides.
These studies show the historical trend of increasing rainfall intensities in south west areas
and more frequent and severe flooding from flood prone rivers will exacerbate problems
already faced by these communities in low-lying areas specially, above mentioned GNDs.
Nature of the Lower Kalu Ganga River Network
In general, downstream section of the Kalu Ganga below Ellagawa and up to the Kalutara
outfall is considered as the lower Kalu Ganga. Main Kalu Ganga has a minimum gradient in
this section. Kuda Ganga, one of the main tributaries which joins upstream of Anguruwatota
adds a considerable volume of water in to the Kalu Ganga. The gradient of Kukule Ganga Kuda Ganga drops drastically as elevation between Kukule Ganga existing dam and
proposed dam location at Molkawa area drops from about 190m MSL to 8m MSL between
the river section of 12.5km. Then next 17km section of the river up to Kalawellawa bridge
where the Millakanda river gauge is located, drops only by 5.5m.
During flood situations, increased discharge volumes of rivers converge together at the
confluence. As a consequence, due to the low river gradients and discharge volumes, the
amount of each river discharge decreases, creating a backwater effect for both channels ie
main Kalu Ganga and Kuda Ganga. This phenomenon affects in many low lying areas along
the river.
August 2015
61
Dam
Weir
H-18m; L-110m
H-2.5m; L-62m
342
372
1.6
0.043
88
2.7
No Flood gates
70
2.3
317
11.38
Parameter
Type of diversion structure
Dimensions of the diversion structure
August 2015
62
simulate water levels in the river reach both upstream and downstream of the proposed
weir (Annex IX: Hydraulic Study Report).
For this study, a hydraulic model for the river reach was set up to a distance of about 5.2
km, including the proposed power house, weir up to the confluence of Makeli Oya with
Kukule Ganga near the point where the Kukule Ganga CEB Projects turbine discharge is
released back to the river. The location of the power house in the model is at 1,250 m and
the weir is at 1,750 m. The most upstream location is at 5,200 m near the Makeli Oya
confluence. The distances are measured from downstream to upstream. For modelling, the
river reach, 13 cross sections of the river were obtained to cover the proposed power house
location and Makeli Oya confluence. Locations and the cross sections are given in the Annex
IX: Hydraulics Study Report in Fig. 8 and Fig. 9 respectively.
For simulation, flood peaks of 10, 25, 50 and 100 year return periods were adopted. The
hydraulic model was simulated without the proposed weir for the above scenarios. Then
simulations were done by introducing the proposed weir to the model. Finally a simulation
was done to understand the impact of an artificial flood due to possible release of 10,000
year flood by opening the flood gates at Kukule dam of Kukule Ganga CEB project. The
results of model simulation are shown in Table 4.3.
Return Period
(years)
-500
-340
250
600
Downstream of weir
791
Upstream of weir
without weir
16.73 17.28 17.23 17.42 19.03 19.88 22.47 22.55 22.96 23.55 24.73 26.05
with weir
16.73 17.28 17.23 21.89 21.50 21.60 22.92 22.98 23.29 23.55 24.73 26.05
without weir
16.20 16.71 16.65 16.93 18.52 19.37 21.79 21.90 22.34 22.92 24.03 25.48
with weir
16.20 16.71 16.65 21.41 21.09 21.16 22.30 22.36 22.70 22.92 24.03 25.48
without weir
15.77 16.26 16.19 16.59 18.14 19.01 21.28 21.41 21.90 22.45 23.49 25.01
with weir
15.77 16.26 16.19 21.04 20.77 20.82 21.83 21.91 22.25 22.45 23.49 25.01
without weir
15.19 15.64 15.56 16.12 17.60 18.53 20.61 20.76 21.30 21.82 22.87 24.20
with weir
15.19 15.64 15.56 20.54 20.32 20.35 21.20 21.29 21.66 21.82 22.87 24.20
without weir
with weir
100
50
25
10
Sudden
opening
of Kukule
gates
August 2015
63
August 2015
64
Submergence (ha)
10 year flood
5.130
Map 1
25 year flood
3.353
Map 2
50 year flood
3.188
Map 3
3.370
Map 4
1.884
Map 5
* Map Ref No. as per the Maps 1-5 of Annex XI: Hydraulic Study Report
From Table 4.4 it is clear that the impact of land submergence due to the weir is highest
during a 10 year flood. Even though the flood discharge due to opening of Kukule gates is
large impact of the weir is not so high. This is due to the fact that short weirs are getting
submerged during high floods and impact need not necessarily proportionate to the flood
inflow rates.
(ii) Submergence of Houses
There are about 10 houses on either side of the river which are suspected to be within the
flood plain. The locations of these houses were identified on the inundation maps by
obtaining the GPS coordinates. When the locations of those houses were plotted and only
six houses came within the hatched area in Maps indicating a possible impact. Then plinths
of these houses were surveyed to determine the elevations. This survey confirmed the
elevations of the suspected six houses by a field survey and details are given in Table 4.5.
Table 4.5: Details of suspected houses
House
Ref No.*
Name of owner
Elevation
(m MSL)
G. KusumaRanjani
843.43
22.50
KaurundukarageWijedasa
1148.96
22.00
Somasiri
1075.96
22.75
Kurundukarage Shantha
1113.13
22.50
G.W Samarasinghe
1148.96
22.56
1217.85
23.00
* Ref No. as per the Maps 1-5 of Annex IX: Hydraulic Study Report
According to the findings of the model study, the position of each house given in the above
Table is as below.
a. During a 10 year flood, non of these houses are affected.
b. During a 25 year flood, House Nos. 1, 2 and 5 are affected due to weir. House Nos. 3,
4 and 6 are not affected.
c. During a 50 year flood, House No. 3 is safe. House No.6 is partly affected due to
natural conditions and fully affected due to weir. House Nos. 1, 2, 4 and 5 are
affected due to weir.
August 2015
65
d. During a 100 year flood, House Nos. 4 and 5 are partly affected under natural
conditions even without the weir. However, all six houses are fully affected due to
weir.
e. During the sudden opening of radial gates at Kukule dam, these six houses are
affected even without the weir under natural conditions. Therefore, the weir has no
significant impact on these houses.
4.2.5 Increase in Water Levels Upstream under Normal Discharge due to the Weir
Contour map of the inundating area indicating land use and land ownership should be
provided
As a run-of-the-river type project, only a minimal storage is required at the weir for
regulating purpose. The proposed weir height will only be 2.5 m maximum and the resulted
pond area would be at the level of 15 m MSL, confined to an area between the weir and
slopes at its upstream. Total pond area will be about 2.7 ha and belong to the river and river
reservation. Contour map showing the normal inundation area is given in Figure 4.4 and
detailed drawing is given in Annex VI.10.
Figure 4.4: Normal Inundation Area
August 2015
66
9km
460m
47.5 m3/s
0.3 m3/s
49.5 m3/s
0.34m3/s
According to the Flow Diversion curve at the weir site developed in the detailed hydrological
study, turbines can run at their design flow about 10% of the time in a year. During this
period, the downstream flow will be more than the mandatory environmental flow. If the
river flow is less than the minimum flow required for a turbine, the total flow will be
released from the weir. The minimum flow required for a Kaplan turbine is assumed to be
15% of the design flow which is equal to 3.7m3/s. Flow release for downstream during
operation stage is shown in the following Table 4.7.
Table 4.7: Downstream flow during operation stage
River Flow Class
Higher than design flow of power
plant
(Q> 49.5m3/s)
Downstream
Flow
Probability of
Exceedance
Q - Qd
10%
Qenv
80%
10%
4.2.8 Impacts on River Water Quality due to Waste Discharge and Pollution from Project
Activities
Water pollution risk could arise from sources of pollution during construction including
spillage of fuels, lubricants and other toxic materials at the construction site; discharge of
silt laden run off from sites, and the disposal of waste and wastewater from work sites.
Materials such as oil, diesel fuel, concrete additives, and solvents are likely to be stored and
used on construction sites and lay down areas and in construction traffic and equipment.
August 2015
67
Storage and handling of these materials could lead to spills on site, along roads and in
surrounding areas. Contaminated run-off from spill sites could adversely affect soils and
vegetation and if it reaches the river would have an adverse impact on water quality. The
extent of impact will depend on the size, frequency and timing of spills and the nature of the
materials involved including their toxicity.
The impacts on the water body downstream will include reduction in dissolved oxygen
levels, nutrient loading causing increased algal growth, and the spread of pathogenic
disease vectors. However these adverse effects on water quality due to discharge of waste
will not be anticipated if appropriate measures are put in place.
4.3
Ecological Impacts
4.3.1 Impacts on Aquatic Fauna and Flora due to Reduced Flows in Downstream and
Inundation in Upstream During the Operational Stage
The project will result in impounding and diversion of water from the main river to generate
power. This activity will not have an impact on the quality of the water. Since the
powerhouse is located 350m meters away from the weir site a stretch of about 460m of the
river will be subjected to low flows during the operational phase . Therefore, an
environmental flow of 0.34 m3/s has to be maintained at all times to meet the ecological
demand of this strecth of the river. The ponding area arising due to the weir will be limited
to the banks of the river that does not support any sensitive species and therefore the
impact due to the inundation of the upstream area is not significant.
4.3.2 Impacts on Aquatic Fauna and Flora due to Construction of the Weir with Special
Reference to Migration of Fish Species
The weir will block the movement patterns of aquatic organisms, especially fish. However,
freshwater migrant fish species have not been recorded during the field survey in the
stretch of the river that will be affected by the project. Further the weir will only be 2.5 m
tall and most migratory species will be able to cross the weir especially during wet season
when the water will flow over the dam. Therefore, this impact will not arise and a fish
ladder will not be necessary for this project.
4.3.3 Impacts on Terrestrial Fauna and Flora including Number of Trees to be cut
During the construction phase, noise and vibrations will arise due to activities such as
excavation, cutting, filling and compaction work, as well as operation of construction related
vehicles. This could cause disturbance to both humans as well as the wild animals that
inhabit the area. Further, these activities will also result in emission of dust and other
pollutants that will decrease the quality of air in the project area that will have an impact on
humans and wildlife that inhabits the area. However, this impact is a short term affect and
will not have a significant impact on the terrestrial fauna. As most of the project activities
will be based at the weir site and head race channel which are located at highly man
modified habitats, the impact on indigenous species are minimal.
August 2015
68
4.4
Sociological Impacts
August 2015
69
the families in this regard and the project developer agreed to provide properly constructed
bathing place for them.
4.5.4 Impacts on Existing Land Use Forms due to Inundation
The map depicting the existing land use pattern of the surrounding area of the pond is given
in Figure 3.3. As the ponding area is confined only to the limits of the stream due to steep
river banks (Plate 4.2) and no large scale constructions in the proposed project is expected,
any changes in the existing land use is not envisaged.
Plate 4.2: Steep river banks along the ponding area
Ponding area
August 2015
70
Vehicle movements
Blasting work
Noise levels for some of the common types of heavy construction machinery and equipment
that are likely to be used for the project are given below.
Table 4.8: Noise levels for common types of construction machinery and equipment
Machinery / Equipment
Compactors (rollers)
71-75
Front loaders
70-83
Tractors
78-95
Backhoes/excavators
70-85
Trucks
83-93
Concrete mixers
75-88
Roller vibrator
108
Poke vibrator
113
Compressors
109
During the construction work of the proposed project, the use of construction equipment,
machinery and heavy vehicles are expected and necessary noise abatement measures will
be taken to minimize the noise impacts.
August 2015
71
4.5.10 Impacts on Wells and Septic Tanks in the Vicinity due to Changes in the Ground
Water Level
There are no any wells located in the inundation area. The few wells located outside the
inundation area will have a positive impact as water levels of these wells will rise due to the
ponding effect. There is no remotest possibility of polluting the water of the existing wells as
the project activities will not result in pollution of the river water.
However, if there any septic tanks located closer to the inundation area will be unusable
due to rising of ground water level of the area due to ponding. Such septic tanks and the
toilets will be relocated at suitable locations in consultation of the owners.
4.6
August 2015
72
Figure 4.5: Kukule Ganga CEB Project and Proposed Bogahahena-Kukula MHP
August 2015
73
5.
5.1
The following soil erosion control measures will be applied to minimize the anticipated
impacts;
In all possible occasions the material stockpiles, vehicle service and repair stations,
vehicles parks, labour camps etc., will not be located within the stream reservations
Strip the topsoil immediately after clearing of a site and stockpile the topsoil; Locate soil
stockpiles in cleared areas away from drainage paths.
Excavated unused soil material must be used for filling of necessary areas.
Any balance soil material must be dumped in a pre identified site with a permission of
the local authority.
Any soil dumps within the project area during the construction phase must be properly
covered.
Surface drainage system of slopes over the project area must be properly maintained.
No any perennial or seasonal streams must be disturbed or blocked during construction
and operational phase.
Majority of the excavation works must be planned to carry out during rain free days.
Side drains must be provided to the upper side of the access road.
Temporary soil mound could be used to avoid further soil wash off to the river from
the head race channel area or from the power house area.
5.2
On-site protective measures against sediment transport at all construction sites will be
installed prior to commence construction. The usual measures will include storm water
basins, silt / sediment traps, check dams and sand bag barriers.
Runoff from construction sites will be discharged only through sediment control devices
as mentioned in item above.
Sediment outflow from material stockpiles including fill earth will be prevented by
having cut off drains or bunds to capture the flow leaving the stockpile. Such out flows
will be directed to sedimentation basins before release.
Exposed embankments will be protected using silt control devices including silt fences,
mulch or temporary sheeting covers.
River bank erosion at the weir site could be avoided using rubble pitching or gabion support
as appropriate. The coffer dam will be erected in phases to mitigate impacts. About one half
of the river section will be coffer dammed allowing normal flow through the rest of the
undisturbed river section. The first half of the weir will be completed under the first
August 2015
74
segment of the coffer dam. The rest of the weir will be constructed by making a coffer dam
for the remaining section of the river after demolishing the previously constructed coffer
dam. Steps will be provided in the spill tail to mitigate erosion by dissipating energy.
Using appropriate mechanical and biological methods the banks of the river specially the
ponding area will be protected. River bank protection measures will include:
In places where river banks are stable, vegetative soil conservation measures such as
establishment of deep rooted grasses will be applied. Eg. Establishment of vetivar
grass fences, bamboo trees etc.
In places where the river embankments are weak due to either weathered rocks or
soils, special mechanical measures shall be applied. Such measures may include:
- Placing gabion cubes of suitable width and height
- Arranging larger rock boulders along the bank
- Paving the bank with rubble pitching or rip-rap construction
5.3
5.4
There is no increased downstream erosion expected due to the weir construction. River
banks at both abutments will be protected by suitable measures such as rubble pitching,
gabion support and toe protection by boulders packing and planting protective trees on the
river banks where necessary. The best method will be decided by the detailed design stage
depending on the specific site conditions.
August 2015
75
Design of the weir has been done in such a way to ensured that the excess water to be
spilled over the weir in case of floods. The high velocity of flow over the weir has a tendency
to erode the bed of the river at the base of the weir and thus the stability of the weir may
be in danger. Hence, to dissipate the kinetic energy and to resist the erosion of the river
bed, suitable energy dissipation devices will be adopted in design of the weir.
5.5
Power house discharge will be properly released into the river minimizing bank erosion and
riverbed scouring. Proposed tailrace channel will be widened into broader section for the
purpose of dissipation of energy to spread out to the downstream area to minimize the river
bank erosion. Proper shoring techniques will be used to protect the right bank. Excavated
river banks will be improved by means of gabion walls / retention walls to prevent erosion
effects.
After constructing the tailrace channel, river bed at the discharge point will also be
improved to avoid erosion effects on the river bed by concreting and rock paving on the top
of concrete surface. The bed rock is present at river bed at the discharging point of the
tailrace channel and therefore the area could easily be strengthened without much
difficulty.
5.6
Hydraulic study confirms that, due to proposed weir, there is no enhanced flood impact in
the river reach downstream of the weir.
In the area upstream of the weir, only six houses could undergo possible impacts due to
enhanced submergence. Mitigatory actions proposed are as follows.
Table 5.1: Mitigatory Actions Proposed for the Possible Flood Affected Households
House Ref
No.*
Name of owner
G. KusumaRanjani
KaurundukarageWijedasa
Somasiri
Kurundukarage Shantha
G.W Samarasinghe
* Ref No. as per the Maps 1-5 of Annex IX: Hydraulic Study Report
August 2015
76
5.7
Storm water will be allowed to flow freely to the river without any disturbance or
accumulation.
All natural streamlets, dry valleys and gullies in and around the project area will be
kept free from obstructions by any kind of construction activities or waste dumping
as much as possible.
All existing constructed drainage paths, contour drains, cascade drains if any will not
be disturbed and they will be maintained during the entire life span of the project.
Aque-ducts will be provided to carry water at locations where channel trace crosses
the streamlets.
Provide permanent drainage structures such as culverts for the access road at
suitable locations.
5.8
Vehicular movements to the river bank areas will be restricted to avoid damage to
the banks.
No toilets will be located close to the river. Standard septic tanks (either PVC or
concrete) will be used for all the toilets and there will be at least one toilet for 20
workers.
The water quality of the river will be monitored during construction, especially in dry
seasons.
August 2015
77
5.9
Solid wastes generated in project area will be collected separately using correctly
marked containers (eg. Organic waste, Plastic, Paper, and Glass etc.) and disposed in
an acceptable manner to designated places as follows;
a. Solid waste comprising garbage and organic waste will be composted on site
at a suitable location but sufficiently away from the river.
b. Non biodegradable solid waste such as plastic, polythene, glass etc. will be
separately stored and disposed (re-use / sell)
Provisions to collect waste cement slurry will be provided and disposed outside the
river reservation in consultation with PS.
Wastewater from washing of concrete mixtures and other equipment used for
mixing and transporting of concrete will be disposed outside the river reservation
area.
All discarded and used oil and grease will be collected, properly stored and disposed
(reuse / sell).
All potentially water polluting chemicals and oils will be stored (a) at locations
sufficiently away from watercourses and storm water drainage paths and (b) in a
manner that would minimise chances of spillage.
Minimize the oil and chemical spillages during operation and properly maintain the
equipment and machinery.
Debris and spoil will be disposed only to designated places in such a manner that (i)
waterways and drainage paths are not blocked, and (ii) the disposed material will not
be washed away by floods.
The solid waste comprising of spoil and waste rock material will be disposed of as
land fill material.
5.9.3 Sewage
All toilets will have septic tanks / soakage pits of adequate capacity so that it can
function properly for the entire duration of construction phase
All justifiable measures will be taken to prevent the waste water entering directly
into the river i.e. provision of septic tanks, absorption trenches and settling tanks
constructed minimum of 15m away from streams and water-bodies
August 2015
78
5.10
The project area does not support any critical habitats. However number of endemic and
threatened species has been recorded at the project site. The proposed activities will not
have a significant impact on these species. Therefore, no special mitigation measures are
needed to protect the ecological resources present at the project site.
5.10.1 Mitigation measures on aquatic fauna and flora due to reduced flows in
downstream and inundation in upstream during the operational stage
Water will be released back about 460m downstream of the weir site. An environmental
flow of 0.34m3/s has to be maintained at all times from the weir site to meet the ecological
demands of the stretch of the river between the weir and the tail race.
5.10.2 Mitigation measures on aquatic fauna and flora due to construction of the weir
with special reference to migration of fish species
During the construction of the weir the water quality of the river can be affected due to
contamination by material used for construction of the weir. This can have an adverse
impact on the aquatic fauna and flora. Therefore, mitigation measures should be taken to
avoid such contamination by providing protective bunds to prevent such contaminations.
Migratory fish were not observed in the stretch of the river that will be subjected to low
flows due to the river diversion for power generation.
5.10.3 Mitigation measures on terrestrial fauna and flora including number of trees to be
cut
The project will have a temporary impact on the terrestrial fauna such as disturbance due to
noise and vibration and generation of dust. However, these impacts will arise only during
the construction phase and can be avoided by employing best practices during the
construction phase. The project will not result in removal of trees Therefore, special
mitigatory measures will not be required. However, it is recommended that project
proponent should undertake tree planting in the immediate catchment of the project as a
measure of compensation which will also be beneficial for the project proponent.
5.11
An environmental flow of 0.34m3/s has to be maintained at all times from the weir site to
meet the ecological demands of the stretch of the river between the weir and the tail race.
5.12
There were several public meetings held by the project proponent with Divisional Secretary,
relevant Grama Niladharies and some key stakeholders in the study area on 10 th April 2014,
30th June 2014, and 25th July 2014 to discuss potential impacts and possible mitigatory
measures.
The participants of all the stakeholder consultation meetings perceived that the flood
situation in the area will be aggravated due to the construction of the proposed weir. At the
August 2015
79
meeting held on 25th July 2014, the technical features of the proposed Bogahahena-Kukula
Mini Hydropower Project in comparison with CEBs Kukule Ganga Hydropower project along
with the flood water release mechanisms of both hydropower projects was explained to the
participants; relevant Grama Niladharies and other key officials of the area (Refer Annex V).
5.12.1 Provisions for the River Uses
River water within the project area is not used for any other useful purpose except for
bathing. The bathing places will be re-located to a convenient location with proper access
and safety in consultation with the users.
It is recommended to fence the area between the intake and powerhouse discharge point to
restrict public entrance in order to ensure the safety of people.
5.12.2 Impacts on Sand Miners
Sand mining areas are located downstream of the proposed weir and far from the project
area. Most of locations are now not functioning. However, downstream sand mining will not
be affected due to the project as sufficient sand flushing openings are provided in the weir
and intake designs. Two 1.5 m x 1.5 m flush gates will be provided at the weir section while
another 2.0 m x 2.0 m opening will be provided at the curved section of the intake structure.
These openings will be operated frequently when sufficient river flow is available.
5.12.3 Restoration of damaged Infrastructure Facilities
The only existing infrastructure facility within the project area is estate road. This is in a
dilapidated condition and will be rehabilitated prior to the commencement of the project
construction activities.
5.12.4 Compensation Packages to the Affected People
The project will not result in utilization of large extents of land. A land in extent of 0.57ha in
Trafalgar Division of Uskvalley Estate has already been requested by the developer for the
construction of the power project. The transmission line will be drawn along the existing
river access road until it meets the existing transmission line of the CEB running about 500m
away from the power house.
The project proponent undertakes to pay suitable compensation in respect of any affected
land in consultation of the Divisional Secretary.
5.13
To minimize the impacts due to material transportation following steps will be taken:
Load trucks with soil only to an extent that no spillage will occur while in
transportation.
All construction material / filling materials / excess soil loads will be covered during
transportation.
August 2015
80
Dump trucks / tractors carrying mud (on tyres and body) to travel in the main public
roads is not allowed.
To avoid dust emissions and to ensure the workers and public safety, speed limits
will be set.
Transportation activities during schools opening and closing times will be avoided.
Dust generation along the roads due to construction traffic will be suppressed using
a water truck as required.
5.14
All construction works will be carried out during day time (due to occupational,
health and safety reasons too) as much as possible.
To the extent possible, attempts will be made to use equipment and machinery that
produce low noise levels (for example, concrete / cement mixers and poker
vibrators). Also proper and regular maintenance and/or servicing of equipment and
machinery will be carried out.
August 2015
81
Earplugs or mufflers will be provided for the persons working in the powerhouse
especially those who are exposed to high noise levels exceeding 4 hours (continuous)
of duration.
All blasting activities will be carried out according to the regulations and guidelines of
GS&MB. Kukule Ganga CEB Project will be informed for their consent prior to blasting
activities. Non explosive chemical blasting method shall be used in critical areas, those are
located on potentially unstable slopes or close to dwelling structures. Service of a qualified
Geotechnical / Mining Engineer will be obtained in decision making of blasting
methodologies and supervision for all blasting activities.
Non explosive chemical blasting is encouraged specially for vulnerable areas, however, use
of such chemicals in riverine area should be done only with confirmation from the
manufacturers. It should be confirmed that there are no impact on water quality or aquatic
life through respective Material Safety Data Sheets (MSDS) and internationally recognized
test reports.
General procedure of blasting:
All the required permits and licenses for the purpose of purchasing, explosive transporting
and to use on the project will be obtained from the relevant authorities. ie. GS&MB,
Bulathsinhala Divisional Secretariat, Explosive Controller, Ministry of Defence and Local
Police etc.
Rock and boulders excavation comprising of drilling, charging & blasting, rock mucking,
lording and removal will be carried out concurrently the activities comprising charging and
blasting will be done during daylight hours whereas the other activities (drilling and
mucking) may be done on a multiple shift basis which could also include night work.
All blasting operation carried out showing the time and location of each blast together with
types & quantities of explosive used will be recorded. A summary of these records will be
kept on site.
Drilling will be done using hand-held pneumatic equipment and it is intended to drill the
blast holes to the diameter and to a depth specified in the Blasting Licence. Charge levels for
rock blasting will always be decided by the qualified Geotechnical / Mining Engineer to
August 2015
82
ensure that the combined quantity of explosives detonated at any instantaneous moment
will not produce vibration levels in excess of the maximum permissible limits.
Rock loading and Removal: Mechanized equipment will be used to load and remove blasted
rock from site using equipment such as excavators, dumpers and tipper trucks.
Safety Precautions:
Clearing the site area positioning guards: Prior to any blasts being detonated, guards
will be positioned at safe locations outside the area of the blast deemed to be the
danger area to prevent unauthorized entry by other persons. Also while placing the
guards and prior to detonating any blast/s, the danger area will be searched &
cleared of any persons who are inside this area.
Special care will be taken in the placement and securing of blasting mats to ensure
that fly rock will be contained. These blasts mats will comprise of gabion net and
weighted down with sand bags/ rubber tires or soil.
Initial warning - One siren sounded approximately five (5) minutes before blasting
to warn the site of the impending blasts.
Final Warning - Three (3) short sirens sounded when blasting is imminent.
All Clear Signal - One (1) siren sounded to indicate all clear once fumes and smoke
has cleared.
August 2015
83
6.
All relevant line agencies, local government bodies and interested parties shall take part in
the monitoring activities. An Environmental Monitoring Committee consisting of the
members from the following agencies shall be set up by CEA.
Irrigation Department
Forest Department
August 2015
84
Phase of the
project
Monitoring
parameter / Indicator
Monitoring method
Monitoring
Frequency
Implementation /
Monitoring
Agency
Monitoring of
construction activities;
Site inspections
Weekly
PP, EMC
Site activities
Monitoring of
construction activities;
Site inspections
Weekly
PP, EMC
Strip the topsoil immediately after clearing of a site and stockpile Construction
the topsoil; Locate soil stockpiles in cleared areas away from
drainage paths.
Site activities
Site inspections
Weekly
PP, EMC
Site activities
Site inspections
Regular
PP, EMC
Construction
Site activities
Site inspections
Regular
PP, EMC, PS
Any soil dumps within the project area during the construction Construction
phase shall be properly covered
Site activities
Site inspections
Regular
PP, EMC
Surface drainage system of slopes over the project area must be Design/
properly maintained. No any perennial or seasonal streams must Construction
be disturbed or blocked during construction and operational
phase.
Site activities
Site inspections
Regular
PP, EMC
Site activities
Monitoring of
construction schedule
Regular
PP, EMC
Side drains must be provided to the upper side of the access Design/
road.
Construction
Site activities
Site inspections
Regular
PP, EMC
Temporary soil mound could be used to avoid further soil wash Construction
off to the river from the head race channel area or from the
power house area.
Site activities
Site inspections
As required
PP, EMC
August 2015
85
Proposed Activity
/ Anticipated
Environmental
Impact
Sedimentation
Control
River Bank
Protection
Measures
Phase of the
project
Monitoring
parameter / Indicator
Monitoring
Frequency
Implementation /
Monitoring
Agency
Site inspections
As required
PP, EMC
Sediment outflow from material stockpiles including fill earth will Construction
be prevented by having cut off drains or bunds to capture the
flow leaving the stockpile. Such out flows will be directed to
sedimentation basins before release.
Site inspections
As required
PP, EMC
Site inspections
Regular
PP, EMC
River bank erosion at the weir site could be avoided using rubble Design/
pitching or gabion support as appropriate.
Construction
Once the
design and
weekly during
construction
PP, EMC
Site inspections
Regular
PP
Gabion cubes of
Site inspections
suitable width and
height, larger rock
boulders along the
bank, rubble pitching
or rip-raps are in place
Regular
PP
Vegetation cover and the top soil cover will be carefully removed Design /
within the stretch from the intake area to powerhouse site. This construction
clearance will be limited to the proposed dimensions of
structures. Extra lands must not be disturbed in any case.
Areas need to be
cleared are identified
and marked on
ground. Appropriate
slope protection
measures are design
and implemented
Once during
PP, Design
design then as consultants, EMC
required
Establishment of vegetative soil conservation measures such as Construction / Vetivar grass fences,
deep rooted grasses at stable slopes in places where river banks Operation
bamboo trees etc are
are stable
established.
Slope
Stabilization
Measures
Monitoring method
August 2015
86
Site inspections
Proposed Activity
/ Anticipated
Environmental
Impact
Phase of the
project
Monitoring
parameter / Indicator
Monitoring method
Monitoring
Frequency
Implementation /
Monitoring
Agency
Regular
PP, EMC
Created rock walls at the intake area, along the channel path, and Design /
power house site must be strengthen by sealing all available construction
weak zones. Any weathered/crushed parts of the bed rock must
be removed before the foundation of structures laid.
Foundations must be properly doweled to the firm bed rock.
Regular
PP, Design
consultants, EMC
Any vertical slope cut created due to excavation with a height Design /
greater than 3 m must be protected by a suitable retaining construction
structure. Cut slopes having height less than 3m also shall be
protected based on the geotechnical engineers recommendation
where necessary.
Regular
PP, Design
consultants, EMC
Regular
PP, Design
consultants, EMC
Downstream
erosion at the
weir site
Dissipate the kinetic energy and to resist the erosion of the river Design
bed, suitable energy dissipation devices will be adopted in design
of the weir.
Suitable energy
dissipation facility is
incorporated
Inspection of designs;
Site inspections
Once
EMC/ PP
Downstream
erosion at the
tailrace canal
Widen the tailrace canal into broader section for the purpose of Design
dissipation of energy to spread out to the downstream area to
minimize the river bank erosion.
Suitable energy
dissipation facility is
incorporated
Inspection of designs;
Site inspections
Once
EMC/ PP
River bed at the discharge point will also be improved to avoid Design
erosion effects on the river bed by concreting and rock paving on
the top of concrete surface.
Suitable energy
dissipation facility is
incorporated
Inspection of designs;
Site inspections
Once
EMC/ PP
August 2015
87
Proposed Activity
/ Anticipated
Environmental
Impact
Flood control
measures
Drainage
management
Phase of the
project
Monitoring
parameter / Indicator
Monitoring method
Monitoring
Frequency
Implementation /
Monitoring
Agency
Suitable
compensation
package is paid with
livelihood support
Inspection of progress
Regular
PP, EMC, DS
For any affected land due to enhanced upstream floods, pay Operation
suitable compensation in consultation with the Divisional
Secretary.
Suitable
compensation
package is paid
Inspection of progress
During and
after every
flood event
PP, EMC, DS
Regular
EMC
Storm water will be allowed to flow freely to the river without Construction
any disturbance or accumulation.
Monitoring of
construction activities;
Site inspections
Weekly
PP, EMC
All natural streamlets, dry valleys and gullies in and around the Construction
project area will be kept free from obstructions by any kind of
construction activities or waste dumping as much as possible.
Monitoring of
construction activities;
Site inspections
Weekly
PP, EMC
All existing constructed drainage paths, contour drains, cascade PreAll drainage paths are
drains if any will not be disturbed and they will be maintained construction/ not obstructed
during the entire life span of the project.
Construction /
Operation
Monitoring of
construction activities;
Site inspections
Weekly
PP, EMC
Temporary bunds,
Monitoring of
rubble pitched drains construction activities;
etc. are provided prior Site inspections
to work
commencement
Regular
PP, EMC
Inspection
As required
PP,
Design
Consultant, EMC
Inspection
As required
PP,
Design
Consultant, EMC
August 2015
88
Proposed Activity
/ Anticipated
Environmental
Impact
Phase of the
project
Monitoring
parameter / Indicator
Monitoring method
Monitoring
Frequency
Implementation /
Monitoring
Agency
Water Pollution
Vehicular movements to the river bank areas will be restricted to Construction
Control Measures avoid damage to the banks.
No vehicles are
allowed in vulnerable
areas.
Inspection
As required
PP, EMC
No vehicles are
washed in vulnerable
areas.
Inspection
As required
PP, EMC
Once
PP, EMC
Water quality
Inspect the WQ
monitoring
monitoring results
programme is in place
Monthly
PP, EMC
Proper disposal
practices are adopted
Monitoring of project
area &
accommodations; Site
inspections
Daily
PP, EMC, PS
Waste disposal
routine is in place
Monitoring of routine
disposal; Site
inspections
Daily
PP, EMC, PS
Non biodegradable solid waste such as plastic, polythene, glass Construction / Re-use / re-sell
etc. will be separately stored and disposed (re-use / sell).
Operation
practices are adopted
Monitoring of
separation; inspection
Weekly
PP, EMC, PS
Proper disposal
practices are adopted
Monitoring of
construction sites and
activities; Site
inspections
Daily
PP, EMC, PS
Proper disposal
practices are adopted
Monitoring of
construction sites and
activities; Site
inspections
Daily
PP, EMC
Construction
The water quality of the river will be monitored during Preconstruction, especially in dry seasons.
construction,
construction
Waste disposal
Solid wastes generated in project area will be collected Construction
methods:
separately using correctly marked containers (eg. Organic waste,
Garbage Disposal Plastic, Paper, and Glass etc.)
Solid waste comprising garbage and organic waste will be Construction
composted on site at a suitable location but sufficiently away
from the river.
Waste disposal
methods:
Construction
Waste
August 2015
89
Proposed Activity
/ Anticipated
Environmental
Impact
Waste disposal
methods:
Sewage
Phase of the
project
Monitoring
parameter / Indicator
Monitoring method
Monitoring
Frequency
Implementation /
Monitoring
Agency
All discarded and used oil and grease will be collected, properly Construction
stored and disposed (reuse / sell).
Re-use / re-sell
practices are adopted
Monitoring of
construction sites and
activities; Site
inspections
Weekly
PP, EMC
All potentially water polluting chemicals and oils will be stored (a) Construction
at locations sufficiently away from watercourses and storm water
drainage paths and (b) in a manner that would minimise chances
of spillage.
Proper disposal
practices are adopted
Monitoring of
construction sites and
activities; Site
inspections
Daily
PP, EMC
Minimize the oil and chemical spillages during operation and Operation
properly maintain the equipment and machinery.
Proper disposal
practices are adopted
Monitoring of
Weekly
maintenance works; Site
inspections
PP, EMC
Proper disposal
practices are adopted
Monitoring of
construction sites and
activities; Site
inspections
Daily
PP, EMC
The solid waste comprising of spoil and waste rock material will Construction
be disposed of as land fill material.
Proper disposal
practices are adopted
Monitoring of
construction sites and
activities; Site
inspections
Weekly
PP, EMC
Inspections
Monthly
PP, EMC
Inspections
Once
PP, EMC
All justifiable measures will be taken to prevent the waste water PreDistance between
Inspection
entering directly into the river i.e. provision of septic tanks, construction / toilets and waterways
absorption trenches and settling tanks constructed minimum of Construction
15m away from streams and water-bodies
Monthly
PP, EMC
Weekly
PP, EMC
PreNumber of toilets
construction / provided
Construction
All toilets will have septic tanks / soakage pits of adequate Precapacity so that it can function properly for the entire duration of construction/
construction phase
Construction
August 2015
Capacities of septic
tanks / soakage pits
Number of training
sessions
90
Inspection
Proposed Activity
/ Anticipated
Environmental
Impact
Phase of the
project
Monitoring
parameter / Indicator
Provisions for
minimum
environmental
flow release
Final designs /
Continuous flow
release
Tree planting
Monitoring method
Implementation /
Monitoring
Agency
Once /
Regular
PP, EMC
Tree planting
Inspection
programme is in place
Regular
PP, EMC
Inspection/ Stakeholder
consultation
Frequently as
possible
PS, EMC
Fence the area between intake and powerhouse discharge point Construction
to restrict public entrance.
Fence is constructed
Inspection
Provide sufficient sand flushing openings in the weir and intake Design
designs.
Operate sand flushing openings frequently when sufficient river Operation
flow is available.
Final designs
Review of designs
Once
PP, EMC
Sand flushing
openings are opened
Inspection
During rainy
season
PP, EMC
Compensation
package
Amount of
compensation paid
Inspection of the
documents
Once
Divisional
Secretariat
Material
transportation
Load trucks with soil only to an extent that no spillage will occur Construction
while in transportation.
Site activities
Site inspections
Daily
All construction material / filling materials / excess soil loads will Construction
be covered during transportation.
Site activities
Site inspections
Daily
Site activities
Site inspections
Daily
Dump trucks / tractors carrying mud (on tyres and body) to travel Construction
in the main public roads is not allowed.
Site activities
Site inspections
Daily
To avoid dust emissions and to ensure the workers and public Construction
safety, speed limits will be set.
Site inspections
Daily
Site inspections
Daily
Construction,
operation
Provisions for the affected Bathing places will be relocated to a convenient location Preriver uses
with proper access and safety in consultation with the users.
construction
August 2015
91
Review of designs /
Inspection
Monitoring
Frequency
Proposed Activity
/ Anticipated
Environmental
Impact
Noise control
measures
Vibration control
measures
Protections for
Blasting Impacts
Phase of the
project
Monitoring
parameter / Indicator
Monitoring method
Monitoring
Frequency
Implementation /
Monitoring
Agency
Dust generation along the roads due to construction traffic will Construction
be suppressed using a water truck as required.
Site inspections
Daily
Noise level
Noise measurements
Regular
PP, EMC
Noise level
Noise measurements
Regular
PP
EMC
Inspection
Where
applicable
PP
GS&MB
EMC
Construction
No complains
Inspection
Frequently
PP
GS&MB, EMC
Construction
Private or public
properties are not
impacted.
No complains
Inspection
Frequently
August 2015
92
7.
At a time, when the energy is so precious for the economic and social development of the
country, generation of electricity and adding to the national grid, by exploiting hitherto
unexploited potential of a mini-hydro source will be a blessing to the nation.
Power, a key factor for economic development of the country has been a major concern of
the Government as the increasing demand is yet to be met. Even with several power
development Projects implemented by the Ceylon Electricity Board (CEB) to meet the
increasing demand, the total requirement is yet to be met.
Exploration of all cost effective power generation options has become a timely requirement.
One of the reasonable options in this respect is to identify the mini hydro power Projects
which are environmentally friendly and economically more viable.
The proposed mini hydropower Project will not result in any adverse effects in the existing
socio economic situation of the area coming within the Project. Existing agricultural
practices or farming patterns will not change and no relocation or resettlement will take
place due to the Project.
Also, the proposed Project will not create any significant negative impacts on the ecological
environment of the Project area. The minor impacts that could be caused due to
construction activities can be easily and successfully mitigated.
In conclusion the environmental study team strongly recommends the implementation of
the proposed this Mini Hydropower Project as the power generated by this Project will be
conducive for the economic development of the nation.
7.1
General Conclusions
Negative impacts are mostly construction impacts such as soil erosion, slope failures,
noise, vibration and dust which are temporary and mitigable.
Positive impacts such as socio economic benefits of power generation will outweigh
the negative impacts.
The project activities are compliant with laws and policies and preliminary approvals
have been granted by relevant line agencies such as CEB, Irrigation Department,
Department of Wildlife Conservation and Forest Department etc.
The only social concern observed during the EIA study was the perceived fear of
aggravation of flooding events in the downstream area. Though this is very unlikely
to happen, they feel that another dam (though it is only a small weir of 2.5 m high
and not a dam) may affect their villages during extreme weather conditions.
7.2
Recommendations
August 2015
93
monitoring plan could be used in this regard. Additional cost items for these should
be specified in the bill of quantities for construction works.
August 2015
94