Water Nep
Water Nep
Water Nep
Prepared by:
GHD Pty Ltd., Australia in assn with Integrated Consultants Nepal (ICON) Pvt. Lt. Nepal
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and
ADB and the Government cannot be held liable for its contents. (For project preparatory technical
assistance: All the views expressed herein may not be incorporated into the proposed project’s design.
Government of Nepal
Ministry of Physical Planning & Works
Kathmandu Upatyaka Khanepani Limited
MAY 2010
ADB
Table of Contents
1. Introduction ............................................................................................................................... 1
1.1 General Project Background................................................................................................... 1
1.2 Project Objective..................................................................................................................... 1
1.3 Introduction of the Project Area .............................................................................................. 2
1.4 Structure of Report ................................................................................................................. 3
2. Existing Water Supply and Sanitation Scenario ........................................................................... 4
2.1 Existing Supply and Consumption .......................................................................................... 4
2.2 Operating Period..................................................................................................................... 5
2.3 Customers .............................................................................................................................. 5
2.4 Tariff ....................................................................................................................................... 5
3. Design Standards and Approach ................................................................................................. 5
3.1 General Approach................................................................................................................... 5
3.2 Selecting the Pilot DNI Area ................................................................................................... 6
3.3 Benefits and Impacts of DNI in the Pilot Area ......................................................................... 8
3.3.1 Uniformity and Equity of Service in the Pilot Area......................................................................... 8
3.3.2 Reduction in Unaccounted for Water (UFW) / Non-Revenue Water (NRW) ............................... 8
3.3.3 Services to the poor and under privileged ..................................................................................... 9
3.3.4 Impact in Post Melamchi Scenario ................................................................................................. 9
3.4 Design Parameters and Criteria.............................................................................................. 9
3.4.1 Background...................................................................................................................................... 9
3.4.2 Design Period ......................................................................................................................... 9
3.4.3 Demographic Characteristics .................................................................................................. 9
3.4.4 Growth Trend and Limitation................................................................................................. 10
3.4.5 Population Projection ............................................................................................................ 10
3.5 Engineering Design and Approach ....................................................................................... 14
4. Survey and Investigations ......................................................................................................... 14
4.1 Engineering Survey .............................................................................................................. 14
4.2 Survey Map Preparation ....................................................................................................... 15
4.3 Base Map.............................................................................................................................. 15
4.4 Existing Pipeline Network Verification................................................................................... 15
4.5 Water Quality Survey ............................................................................................................ 15
5. Proposed Distribution Network Improvement .......................................................................... 16
5.1 Distribution Network Configuration ....................................................................................... 16
5.2 Basic DNI Concepts and Approach ...................................................................................... 16
5.3 Demand Projection and Allocation ........................................................................................ 17
5.4 Network Modeling and Design .............................................................................................. 17
Distribution Mains/Lines ................................................................................................ 19
Chambers 19
Bulk Meters and other Valve Chambers ......................................................................... 19
Pipe Valve Chambers ..................................................................................................... 20
Washout Chambers ....................................................................................................... 20
Air Valve Chamber ......................................................................................................... 20
Appendices
List of Acronyms
Page 1
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
6 Under the PPTA, out of 3 identified priority areas, one area was to be selected as the
pilot area for which detailed designs and contract bid documents would be prepared. The
PPTA consultants in close consultation with KUKL identified four priority areas for detail
design of DNI works consideration, taking into account the followings:
existing studies on the water supply and distribution system in Kathmandu Valley
detailed design report for the DNI demonstration project at Baneshwor
reports by the consultants engaged under ADB-assisted projects
condition of water availability, network hydraulics, water pressure in target areas
contribution to achieving the project’s overall objectives
assessment on the implementability of immediate physical works
7 As per the requirements of the TOR, the detailed design should include:
description on the area and scope of works
technical specifications
bill of quantities
drawings
bid documents for implementation of designed works
Page 2
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 3
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 4
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 5
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 6
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
21 The service area of the Pilot area has been delineated in such a way that it can be
easily hydraulically isolated from the overall network system. Coinciding of Pilot service area
boundary to the natural boundary (at least in one side) has been given top priority in order to
clearly define the service area.
Table 3-1: Evaluation of Water Supply Service Areas for DNI Pilot Area Selection
Particulars Identified Priority Areas
Basundhara Kalopool Koteswor Patan
Source of supply Bansbari Mahankal Chaur Sinamangal / Airport Sainbhu
Reservoir Reservoir wells Reservoir
Diameter of main 100 mm 600 mm 150 mm 400 mm
supplying pipe
Total area in Ha 72 100 129 135
Approximate 2009 12,000 40,000 28,000 41,000
population to be
benefitted
No. of household to be 2200 4300 7000 6300
benefitted
Types of population to Homogenous, Heterogeneous, Heterogeneous, Homogenous,
be benefitted (socio- lower middle class mixed (lower to middle class middle class
economic) higher class)
Type of the area Newly developed Mixed area (new and Newly developed Core area
residential area old) area
Present supply Alternative day 6-24 hours supply One hour supply in One hour supply
situation supply in wet depending upon every fourth day in every fourth
season and one location day
hour supply in
every fourth day in
dry seasons
Main reason of Enough water in Enough water fed by Possibility for The hard hit area
selection for piloting wet season but 600 mm dia. improvement as a at present
poor supply due to transmission main but separate system
sloppy network high percentage of once the proposed
leakage and wastage water treatment
due to smaller plant for all the three
diameter of pipes in tube-wells is
the system completed
Location from zoning Kathmandu Metro Kathmandu Metro Kathmandu Metro Kathmandu Metro
aspect (post Melamchi
stage)
Expected improvement Supply service to Improvement in the Improvement in the Improvement in
after pilot project the area will be supply to the selected supply hours as well the supply (one
improved in wet area as well as to as in the quality of hour supply every
season but will successive areas water alternative day)
have little impact downstream
in dry seasons
Easy/difficult for Easy Easy Difficult Very difficult
implementation
Post piloting impact Medium Very high High High
Priority IV I II III
Page 7
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 8
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
controlled and metered local area distribution supply main and household / consumer meters
installed.
30 Reduction in UFW and improved operations and management in the selected pilot
area will also be a benefit to water supply customers downstream of the area, served by the
existing trunk main passing through the area.
3.3.3 Services to the poor and under privileged
31 Generally the urban form of Kathmandu is organic in overall scenario and is not
guided by any land use plan. However, few local areas are exception to this scenario. Due
consideration has been given while selecting the pilot area such that cross-section of local
inhabitants are represented. The selected area includes a wide spectrum of socio-economic
status from squatter settlements to high class households. A techno-socio-economic
household survey was conducted to clearly identify both poor serviced and economically
poor household pockets within the pilot area so that appropriate solutions can be developed
for replication in other service areas.
3.3.4 Impact in Post Melamchi Scenario
32 The proposed zonal approach to water supply asset management makes the
selected pilot DNI area appropriate for both the pre- and post-Melamchi scenarios. The
improved service levels to be achieved through the pilot DNI area will be apparent in both
situations.
33 As the improved water supply system in the pilot area would be fed from the existing
600mm diameter pipe along Ring Road and fed by the existing Mahankal Chaur reservoir in
both pre and post Melamchi scenario, the proposed pipe network for the area would be
same for both the scenarios. Similarly, hydraulic modelling of the proposed pipe network of
the pilot area has been checked for both pre and post Melamchi scenarios.
3.4 Design Parameters and Criteria
3.4.1 Background
34 Primary design parameters are established for commencing the engineering designs.
These parameters are largely based on the choice of technology and the service level. For
the present and future purposes, the following recommended basic design parameters are
discussed in the following sections.
3.4.2 Design Period
35 Design periods have economic and cost implications on investments. Considering
the high growth rates associated with urban areas within the Kathmandu Valley, a design
period of 15 years up to 2025 has been adopted for the project.
36 The population growth rates for various service zones within the KUKL service area
have been determined adopting a two pronged approach, i.e. actual census data and
maximum / ultimate population density of individual zones. The population growth rates in
various urban areas vary from 0% growth for existing densely populated core urban areas to
a maximum of over 18% in highly intensive growth peri-urban areas like Kapan or Dhapasi.
3.4.3 Demographic Characteristics
37 The Pilot Area comprises of 100.11 hectares in Kathmandu Metropolitan City. Out of
this total area, about 89.55% (89.65 hectares) of the land falls under Ward no. 7 and
remaining area of about 10.45% (10.46 hectares) falls under Ward no. 8. As the pilot area
comprises of areas under different wards, population of the area is not available from any
official source. Present population of the area has been estimated from proportionate area
basis using available information on Ward No. 7. The present population of the Pilot area
has been estimated as 42,024 (2009 AD).
Page 9
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 10
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 11
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
42 In addition, allowances have been made for institutional, commercial and industrial
demands. A maximum allowance of 25% has been adopted for unaccounted for water
(UFW) to cover wastage / losses during treatment and distribution leakages.
43 The total daily demand of the Pilot Area has been developed by projecting the
population for the area and per capita demand figures. The household connections have
been divided into private connections, yard connections and public stand post users. It is
expected that the percentage of private house connections fully plumbed will increase from
65% in 2015 to 80% in 2025 – the design year. It is also expected that unaccounted for
water through system leakage and wastage will also decrease with system improvement.
The table below summarizes the water demand scenario for the Pilot Area in 2015 and
2025. Appendix 1 provides additional details.
Table 3-4: Water Demand Projections (2015 – 2025)
Page 12
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
47 The quality of locally available GI pipes is usually not of adequate standard; therefore
use of GI pipes should be avoided. In order to use non metallic pipe for diameter less than
150mm in distribution network of the Pilot area, cost of two commonly used pipes was
compared. As the cost of trench excavation and backfilling for laying of both type of pipes
would be the same, only the cost of pipe (material), laying and joining of pipe and fittings
cost have been compared. The cost involved in each type of pipe with respect to laying cost
and fitting cost have been estimated, in addition to the pipe cost. Material cost and laying
cost of pipes has been estimated as per the Government norms with the help of approved
district rate of current fiscal year. Fittings cost per unit pipe length have been assumed as
25% and 10% of pipe material cost for both uPVC and HDPE pipes. This assumption has
been made based on past experience and prevailing practices. The total cost for per meter
length of pipe of different diameters is compared and shown in table below.
Page 13
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
48 It has been observed that, the unit cost of HDPE is 13% to 23% higher than uPVC
pipe. For the present DNI works in the Kathmandu valley it is recommended that all pipes of
sizes DN 150 and above shall be DI. For smaller diameter pipes including that for house
connections non-metallic pipes, i.e. uPVC, is recommended.
3.4.10 Pressure and Velocity
49 After general assessment of various engineering practices in Nepal and elsewhere in
the region, it has been concluded that a maximum velocity of 3m/s would be allowed in the
major pipelines, while the minimum velocity should generally not be less than 0.5m/s,
especially where tube well water is being transferred which might contain sediment.
3.5 Engineering Design and Approach
50 The primary guiding principle adopted in the engineering design of the Pilot Area has
been to improve the existing water supply situation in the area in conformity with the KUKL
Service License target in a pre-Melamchi scenario with optimum sizing of the improved pipe
network to satisfy the 2025 post-Melamchi scenario. This required striking the right balance
between alleviating the problem now and readying the system for later stages with greater
availability of water.
51 The existing water supply network also needed to be assessed in terms of its
utilization and utility in view of the changed approach being promoted for laying of water
distribution mains and installing house connections. In order to work within this guiding
framework, extensive survey of the area was done and consultation at the operational level
with KUKL and consumers at the household level.
52 Detailed assessment of the existing supply area in terms of constraints and physical
limitations for the implementation of the proposed works has also been done. Effective
measures are required to ease construction and also facilitate the day-to-day activities of the
local residents. Inconvenience to the local residents and businesses needs to be minimized
and alternative measures adopted to maintain traffic flow and continuity of utility services in
the area. All these factors have been taken into account, while approaching the design to
make it not only sound in technical terms but acceptable to the consumers generally.
Page 14
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
plotting of the pilot area boundary, property line to the both sides of existing roads / lanes
and other prominent features. The survey plans have been reproduced at suitable scales.
56 The survey has captured all storm water drains or any other visible utility lines (e.g.
electricity power cables, sewer / drainage manholes, water valves, etc.) along the roads /
lanes which are marked on the drawing. Details of river / drainage channels with respect to
the bed level, width and depth have also been provided. Spot levels have been provided at
20m intervals on the centre lines of the road / lane and at every junction.
57 All roads / lanes in the survey area have been provided a reference code. Length
with average and minimum width of all roads / lanes has been measured. Type of surfacing
and condition of all roads / lanes has also been recorded. Type and number of houses /
residential dwellings or other properties in each road / lane have been recorded.
4.2 Survey Map Preparation
58 The main aim of the projection systems adopted for the study was to present map
data using ACAD and GIS so that required information could be easily accessed. The
selection of a projection system is based on the area (shape, size and orientation) to be
mapped and the accuracy requirement for the intended purpose of the maps. The available
maps from department of Survey (1:25,000), and other map such as prepared by Valley
Mapping project (1:2000) of Kathmandu Valley were in Modified Universal Transverse
Projection (MUTM) system. In order to maintain consistency with the national practices,
MUTM projection system has been adopted for this Pilot area scheme.
4.3 Base Map
59 An initial preliminary planning exercise was carried out with the help of the Valley
map of 1:2000 scale prepared by DHUD under Kathmandu Urban Development Project
during 1999 AD. But. because the map was rather dated, additional information had to be
added from ‘Google’ earth image of the Pilot area.
60 Based on the preliminary base map, field work for survey was planned. A traverse
survey was carried out with the help of Total Station enclosing the Pilot area. Important
details such as road widths, monuments, new lanes or roads have been added to the base
map for the pipe network planning.
4.4 Existing Pipeline Network Verification
61 Verification of existing pipe has been carried out with the help of map prepared by
JICA under "Development Study on Improvement of Water Supply Facilities in Urban
Centers and Kathmandu Valley" project. As these maps were prepared during 2005 AD,
additional information on existing pipe network has been gathered with the help of
technicians from the KUKL Mahankal Chaur Branch office.
4.5 Water Quality Survey
62 It is essential that the quality of water supplied to consumers be of approved
standards. The KUKL service license although mentions adhering to water quality
standards. Therefore, the recently promulgated National Drinking Water Quality Standards
(2062) have been adopted, as prescribed in the Urban Water Supply and Sanitation Policy of
2009. This might require improved treatment of the source water. Some of the major water
quality parameters to be monitored and water quality level established is listed in Table 4-1.
63 Other heavy metals and carcinogenic chemicals should not be present in the water
for drinking and bacteriological contamination should be nil.
Page 15
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 16
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
67 Few of the existing distribution mains have been designed for present or future
population and water demands. In addition, most existing pipes are dilapidated and not
strong enough to meet the WUO license pressure service levels. As a result, most existing
distribution pipes will be found to be either undersized to meet future water demands or of
poor condition and will require replacement with new pipelines based on adopted design
criteria.
68 Many existing consumer connections are directly made to large diameter
transmission and trunk pipelines. These connections are often made by knocking holes in
the pipe which damages the cement lining of DI pipes, causing rusting and weakening of the
pipes, resulting is severe leaking. On some major trunk pipelines there are so many
consumer connections that over 50% of the water to be delivered is lost. It is recommended,
as part of the service management strategy that consumer connections should only be taken
from the service area distribution network within supply zones. All consumer connections to
main trunk serving different supply zones or service networks shall be removed.
69 One of the principles of providing water supply zones is to be able to monitor the
supply service with the use of bulk meters so that problems in the delivery can be identified
and rectified. Usually degradation in a service is progressive and action to remedy the
problem can be planned in advance. Sometimes failures are sudden and sections of the
distribution network need to be isolated in order to carry out repairs. In both cases, disruption
in service should be as little as possible and with a minimum number of customers affected.
70 It has been the normal practice for every household or property to make a separate
consumer connection to the main distribution pipeline, no matter how far the distance. As a
result, side streets and alleys have clusters of ½” GI service pipes. Because nearly every
ferrule connection to the distribution main leaks and because the pressure drop in the small
diameter service pipes is great, the service pressure and consequent water supply to most
properties is very poor. The problem of high pressure drops is exacerbated by the present
intermittent supply regime and consequential high peaking factors due to the constrained
water supply. This has to be remedied and provisions have been made for replacing leaking
pipes and house connections with new pipes and improved connections
71 Rehabilitation of the existing system will not be an easy task. The major problems for
implementation are narrow roads, old buildings (in the core areas), congested traffic and
complicated network of communication, power and drainage lines. Coordination between all
the concerned line agencies during the rehabilitation and improvement work is essential.
5.3 Demand Projection and Allocation
72 As mentioned earlier, the entire Pilot DNI area has been divided into smaller blocks
with different urban growth characteristics based on the potential for growth. The pipe
network layout was overlaid on the base map of the area and nodes identified. Each of the
design nodes was then given a “demand area” for which the individual node has been
earmarked to provide / supply water. The population to be served by each node was
estimated using the population densities and the area to be serviced by the individual nodes.
The base year population at each node was projected using relevant growth rates to
establish the design year population. The demand allocation at each node was then
established using the nodal population and the per capita demand figures. The average
demand flows at each node was then adjusted using the hourly peak factor, which resulted
in design flows to be used for the network analysis.
5.4 Network Modeling and Design
73 Hydraulic network modelling and design has been performed using US EPAnet 2.1.
Once the initial pipe network for pilot area was prepared, the entire network was modelled
using the node and link facilities of EPAnet. All nodes and links were numbered and coded
and the parameters required for modelling the network, i.e. length, elevation, base demand
Page 17
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
and discrete pipe sizes of defined materials, were inserted in the model to calculate residual
head, velocity of flow, etc. (Refer Figure 5-1: Designed Pressure Diagram). Various runs in
a steady state scenario were made. The results of these runs with the optimized results are
given in Appendix 2.
Figure 5-1: Designed Pressure Diagram
Page 18
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
uPVC Pipes
140 mm diameter 1518 m
125 mm diameter 3775 m
110 mm diameter 3509 m
90 mm diameter 9515 m
75 mm diameter 12262 m
Total 30579 m
Chambers
79 All chambers are M-20 Grade RCC Chamber. All the chambers have been designed
as per the India standard Code for heavy traffic load (heaviest axle load of 8 ton) and limiting
cracking width philosophy assuming other design parameter such as depth of pipe, location
of ground water table, soil characteristic, etc. Designs have been made only for estimate
and tendering purposes. It is recommended designs of these chambers should be checked
and revised, if necessary, to suit particular local conditions and loads during implementation.
Bulk Meters and other Valve Chambers
80 Supply of water to the DNI pilot area will be from the existing 600mm diameter
transmission main along Ring Road, at two locations. In order to enhance water auditing
two Bulk meter chambers at these locations has been provided. These chambers comprise
of control valves (Sluice Valve) and other necessary appurtenances to control water from the
transmission main and isolating distribution blocks from maintenance purposes. Similarly,
Page 19
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
other valve chambers have been provided to isolate parts of the distribution system for
maintenance or in case of damage.
Pipe Valve Chambers
81 Wherever, there is lack of space and control valves are of smaller diameter, pipe
valve chambers have been considered for ease in implementation and use.
Washout Chambers
82 Four Washout Chambers have been provided in the Pilot area distribution network.
These washout chambers have been provided along the Dhobi Khola with respect to
reduced level of the area and ease in draining.
Air Valve Chamber
83 Air valve chambers with drain pipe and sluice valve has been provided along with
outlet structure of brick masonry on the bank of the Dhobi Khola. The air valves are single
orifice with throttle of 50ND. Altogether, about 10 air valve chambers are envisaged. The
locations of these chambers are tentative based on elevations, depth of pipe and ground
condition. Exact location and numbers may have to be revised during implementation.
Water Revenue Meter
84 Dry dial volumetric rotary piston type water revenue meter for all house connections
are proposed. These household water meters have 15mm ND and have been
recommended for use in KUKL DNI Demonstration Area of Baneshwor.
House Connection
85 All house connections shall be of non metallic pipe in order to reduce leakage at the
service connection points. Initially four different options as per the pipe material have been
developed. The use of GI, Composite, HDPE and uPVC pipes have been adopted in option
1, 2, 3 and 4, respectively. The implication costs have been assessed. Because the entire
length of roads and lanes would be provided with distribution pipes, a service pipe length of
9m has been adopted for the house connection in the estimate. Table 5-1 illustrates cost
involved in different option.
Table 5-1: Comparative Cost of House Connections with Various Pipe Materials
Description of GI Composite HDPE uPVC
Quantity
Items U. Cost Amount U. Cost Amount U. Cost Amount U. Cost Amount
EW in Excavation
3 4.65 260.59 1210.44 260.590 1210.440 260.59 1,210.44 260.59 1210.44
(m )
EW in Back filling
3 4.65 162.87 756.53 162.870 756.530 162.87 756.53 162.87 756.53
(m )
Pipe (m) 9.00 151.67 1365.03 148.060 1332.540 34.10 306.90 45.29 407.61
Fittings (Set) 1 3134.65 3134.65 4047.340 4047.340 3,391.65 3,391.65 3367.65 3367.65
Water Meter
1 2077.37 2077.37 2077.370 2077.370 2,077.37 2,077.37 2077.37 2077.37
(No.)
Total Cost (NRs.) 8544.02 9424.22 7742.89 7819.60
86 The KUKL Mahankalchaur Branch office estimated that there are about 4,300 private
connections in the Pilot DNI Area, which are expected to increase to about 4,800 by 2012.
Accordingly, 4,800 house connections have been proposed in the project costs. Nominal
15mm diameter pipe have been taken for house connection in case of GI pipe Option. In
case of others, pipe of 20mm outer diameter (OD) has been considered. The cost of fittings
has been lumped to one item as per required number and type of fittings.
Page 20
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 21
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
abstract of the cost has been prepared by identifying the quantity of work and unit rate
analysis. The relevant details of cost estimates are given in the Appendix 3.
95 An additional 10% of the cost is provided for physical contingencies plus 13% VAT in
order to estimate final cost of the scheme. The cost for the scheme has been estimated as
NRs. 183,976,468.00, which is summarized in the Table 6-1.
Table 6-1: Pilot DNI Area – Cost Estimate
S. Rate or Avg. Total Cost
Description of Items Qty Unit
No. Rate (NRs.)
A Preliminary Items 1 Job 3,692,585.00 3,692,585.00
B Provisional Item 1 Job 6,973,064.00 6,973,064.00
C Civil Works
1 Pipeline Trench Excavation & Backfilling 1 Set 10,268,388.88 10,268,388.88
2 Pipe Cost 1 Set 22,563,795.64 22,563,795.64
3 Fittings 1 Set 9,952,215.36 9,952,215.36
4 Dismantling Works 1 Job 7,002,874.17 7,002,874.17
Main Tapping Chambers (at Two Chowks 1.5 mx
5 8 No. 219,230.48 1,753,843.83
2.5m)
6 Valve Chambers (2.25mx2.25m) 2 No. 236,115.53 472,231.05
7 Valve and Washout Chambers (1.5mx1.5m) 14 No. 147,652.93 2,067,140.98
8 Valve and Washout Chambers (1.0mx2.0m) 8 No. 181,240.15 1,449,921.17
9 Air Chambers (1.0mx1.0m) 10 No. 108,020.45 1,080,204.46
10 Pipe Valve Box 8 No. 3,397.88 27,183.04
11 Fire Hydrant 10 Nos. 25,000.00 250,000.00
12 Temporary Re-sealing of the Black topped Road Sq.m 1,577.84 32,158,903.74
20,381.6
13 Re-instate of the Gravel Road Sq.m 650.62 1,760,317.47
2,705.6
14 Re-instate of the Brick Pavement Sq.m 1,516.92 2,380,957.63
1,569.6
15 Re-instate of the Flag Stone Pavement Sq.m 1,602.08 2,330,065.15
1,454.4
16 Re-instate of the Interlocking Block Pavement 64 Sq.m 1,105.45 70,748.80
17 Re-instate of the Concrete Pavement 48 Sq.m 1,039.93 49,916.64
18 Thrust Block 45 Cu.m 8,609.87 387,444.15
19 House Connections 4800 No 7,729.61 37,102,136.16
20 Miscelleneous Work 1 Job 8,379,430.00 8,379,430.00
Sub-Total (A+B+C) 152,173,367.33
D Contingencies for workchart staff and small miscelleneous expenses 5% 7,608,668.37
E Sub total including workchart staff and small miscelleneous expenses 159,782,035.70
F Contingencies for price adjustment 10% 15,978,203.57
G Physical contingencies 10% 15,978,203.57
H Sub-total including contingencies 191,738,442.84
I Value Added Taxes (VAT) 13% 24,925,997.57
J Total Estimated Amount (NRS) 216,664,440.41
Page 22
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Nevertheless, the operation of the distribution system inside the pilot area will be
comparatively much easier. Also, it will not require any maintenance of the system for the
first three years after the completion of the pilot project.
100 The above table shows that the biggest representation in the population is of age
group between 16 to 45 (55.1%) followed by another age group between 46 to 65 (18.2%).
The percentage share of the children below 15 years is about 18%.
101 Out of 219 households interviewed for the survey, 36.1% were female headed
households. Of the total female headed households, about 20.3% were widowed.
7.3 Ethnicity
102 Table 7-2 indicates the different ethnic groups residing in the DNI pilot area. Brahmin
(41%), Newar (34%) and Chettri (11%) are the major ethnic groups. Other prominent ethnic
groups are Gurungs (5%), Rais (3%) and Lamas (3%).
Table 7-2: Ethnic composition of the households
Ethnicity No. Percentage (%)
Brahmin 90 41.10
Newar 75 34.25
Chettri 24 10.96
Gurung 11 5.02
Rai 6 2.74
Lama 3 1.37
Others 10 4.56
Page 23
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Not attending
Kindergarten
no schooling
Grade VI- X
Graduate &
school time
school until
Literate but
Grade I-V
complete
DNI Pilot
Illiterate
above
Infant
10+2
area
Page 24
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 25
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
1
It should be noted that the measurement of income and expenditure by means of questionnaire surveys is
limited. Questions on income may be seen as an invasion of household privacy, and the data collected is entirely
dependent on respondent recall and integrity.
Page 26
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 27
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
117 The study on “Kathmandu Valley Water Distribution, Sewerage and Urban
Development” made by Kanako Kishi during 2008, found that about 50 %, 39 % and 44 %
households of Kathmandu Valley were satisfied with the quantity available, regularity and
water pressure respectively.
7.16 Sewerage and Sanitation
118 When asked about the existence of sewer system in the surveyed area only 12
households reported that there exists some kind of sewerage system. None of them
reported the existence of combined sewer systems in the area. About the problem of
sewerage, only 35 (16%) households reported the clogging of sewerage pipes from time to
time. The household members were also asked about their willingness to pay for improved
Page 28
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
sewerage system in the area. About 46% informed that they want to pay as usual i.e. 50%
of the water tariff or less than Rs 200, where as 11.4% reported that they are willing to pay
up to Rs.250. About 16% were willing to pay more than Rs.500 for the hygienic and regular
supply of 10,000 liters of water. Other households did not want to comment on this question.
119 It was found that different agencies have constructed sewer lines in the study area.
120 It was found that about 57% of the households use water sealed toilet with flush,
whereas 42% use water sealed toilet without flush.
121 About 28% of the household still dispose their solid waste into the septic tank and
majority of them cleaned the tank within 2 to 5 years of period mostly using private firms.
7.17 Gender Issues
122 According to 2001 census, about 15 5 households have been reported as women
headed household. In the urban areas it was a bit more than the country as a whole i.e. 17%
in 2001. The current survey in DNI area indicates that about 36.1% of the households were
women headed households. Of the total female headed households, about 20.3% were
widows.
123 There is still some difference in the literacy between male and female. It has been
found that about 88% of the female were literate in comparison to 97% of male population.
124 About 17% of the women are housewives. Only 11% of the female members of a
family are found to be involved in income generating activities compared to 22% of the male
members. The sectors, in which they are involved, are trade, business and labour related
activities in and outside the country. It has been reported that in addition to the involvement
in income generating activities, women also carry out households activities like cooking,
cleaning, washing clothes, child care, care of elderly members of their family, etc. The
following table shows the household activities by gender.
Table 7-13: Household’s Activities by Gender (%)
Households activities Men Women Boys Girls Women Men, Men & NA
& Girls Women, Women
Boys &
Girls
Fetching drinking 2.7 17.8 - 0.5 2.7 5.5 12.8 58
water
Cooking & cleaning 0.9 67.1 0.5 1.8 5.0 6.4 17.4 0.9
Washing clothes 0.5 68.5 0.5 3.2 5.5 3.7 16.4 1.8
Child care 0.5 21 - 1.8 0.9 3.2 9.6 63
Care of elderly 0.5 12.8 - 0.5 0.9 3.7 3.2 78.5
Source: Field Survey, November 2009
125 Besides, the respondents were also asked about the involvement of women in
decision making of the household matters like in finance, education, health care, purchase of
assets, day to day households matters etc. It has been found that women are involved in the
decision making of almost all household matters. The following table provides the status of
women in decision making process.
Table 7-14: Involvement of women in decision making of the household matters (%)
Household matters Yes No NA
Finance 88.6 10 1.4
Education 76.3 16.9 6.8
Health care of children 75.8 16 8.2
Page 29
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
126 In most of the developing countries, the family land and household assets have been
owned by male population. In some cases both the male and female owned through
inheritance land and assets. However, from last few years, the ownership of women on land
has increased in Nepal due to the Government policy of 20 % rebate/concession on the land
registration fees while purchasing land from other. It is clear from the table below that almost
half of the household’s women own assets like land, house and other structures. Majority of
them are also allowed to keep money separately in banks or other financial institutions.
Table 7-15: Women ownership of assets
Ownership Yes No NA
Land 48.9 28.3 22.8
House & other structures 50.7 27.4 21.9
Keeping money 65.3 15.5 19.2
Others 1.0 2.7 96.3
Source: Field Survey, November 2009
127 The participation of women in social, political, religious, community gatherings has
increased in recent years in Nepal. During the survey in the sampled households, the
respondents were also asked about gender participation in community meetings. The
percentage of female alone in social/religious gatherings was slightly more than the men,
whereas participation of men in community gatherings is much more higher than the female.
However, around 50 % of both male and female together participate in the social/religious
work. The following table shows the participation status of both male and female in different
social activities.
Table 7-16: Participation in the social activities by sex
Social activities Male Female Both Male & NA
Female
Social/Religious work 10 12.3 49.3 28.4
Community gatherings/meetings 17.8 6.8 23.7 51.3
Political gatherings/meetings 11 0.9 8.7 79.4
Charity/club 7.3 1.8 8.2 82.7
Others 3.2 0.9 4.1 95.8
Source: Field Survey, November 2009
Page 30
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 31
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 32
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
141 Mitigation measures are: Cut only trees that are marked and have been agreed by
the Department of Forestry for removal and plant and rear tree saplings at the rate of 25
saplings for each felled tree; prohibit the use of fuel-wood and timber collection; prohibit
hunting, the illegal collection and trade of NTFPs; provide LPG/kerosene to the workforce;
stockpile the felled trees and take permission from concerned authorities for their use;
compensate all private trees and community forests affected. To save the fisheries and
riverbed aquatic ecology, work should be done in the dry season only and river diversions
and bunding-off of sections carried out.
142 Endangered species and protected areas do not fall within the construction areas
and mitigation measures are not required.
8.2.3 Socio-Economic and Cultural Environment
143 As per the approved EIA of 2000 for the Melamchi Water Supply Project,
approximately 1,100 workers were estimated to be employed every day for the construction
and improvement of the Water Supply Networks. About 60% of the workers required for the
project were estimated to be available locally, and at least 30% of the workers should be
local. Women should be given preference for employment as far as feasible and practical
and ensure that at least 15% of the unskilled workforce shall be women (Norplan, 2002).
Compensation and Rehabilitation as per the Resettlement Plan (RP)
144 Contractor’s temporary land use and housing acquisition and compensation to
affected people is one of the most important impacts of any construction project if its
progress is not to be hampered. The mitigation measures are: Avoid involuntary
displacement; compensation resettlement according to agreed Entitlements Policy and RP;
make arrangements for a “grievance redress committee” to look into the grievances; restore
temporary sites to their natural or stable conditions as per agreements with the land owners;
plant exposed areas of temporary sites with endemic vegetation; make sure that the
proponent reports in writing that temporary areas have been vacated and restored to pre-
project conditions before acceptance of the works; provide employment opportunities to the
affected people; provide all possible assistance to the displaced people until they are settled;
provide disturbance and rehabilitation costs; protect the traditional rights of the local people;
compensate for any loss of crops, trees and other natural resources and establish a
technical committee to assess the compensation for damages caused by vibrations of
construction equipment and vehicles.
Reinstatement of Damaged Community Services and Infrastructure
145 Construction activities could have adverse impacts on community services and
infrastructure. To mitigate these impacts, compensate or reinstate/relocate community
assets that are disturbed such as temples, bridges and irrigation canals, electricity poles,
telephone lines, drinking water pipes, sewerage lines, roads, trails, cremation sites etc. to
the satisfaction of the people. Establish a technical committee to assess the compensation
for damages caused by vibrations (photographs of the damaged structures should be taken
and compared to the baseline photographs taken before construction).
Influx of Outside Workforce, Money and Unwanted Activities
146 Alcohol abuse, gambling, prostitution and other social disharmony are likely to arise
in the construction site. There will be an influx of workers from outside to the project site with
their immediate family members, increasing crime and stress. This will create unwanted
congestion and exert pressure on the limited local resources. The mitigation measures to be
carried out are: Prohibit gambling and alcohol consumption in construction camp sites;
instruct the outside workforce to respect the local cultures, traditions, rights etc.; and provide
security in camps.
Page 33
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 34
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 35
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 36
TA 4893 –NEP: Kathmandu Valley Water Supply & Wastewater System Improvement
DNI Detail Design Report
Page 37
TA 4893-NEP
Project Feasibility Study
APPENDIX 1
APPENDIX 2
PIPES Node Length Flow Pipe Ground Elevation Velocity Pressure (m)
ID From To (m) (lps) O.D.(mm) I.D.(mm) Type Rough From To (m/s) From To
P-1 N-332 N-331 32 6.3 200 200 D.I. 0.085 1331.96 1332.00 0.20 4.59 4.54
P-2 N-331 N-329 119 5.32 150 150 D.I. 0.085 1332.00 1332.10 0.30 4.54 4.36
P-4 N-195 N-330 94 1.95 150 150 D.I. 0.085 1331.77 1332.10 0.11 4.67 4.33
P-5 111 N-195 5 4.5 150 150 D.I. 0.085 1331.77 1331.77 0.25 4.67 4.67
P-6 N-138 N-194 174 7.07 200 200 D.I. 0.085 1330.37 1331.77 0.23 6.12 4.67
P-7 1 N-137 9 51.69 200 200 D.I. 0.085 1330.37 1330.37 1.65 6.13 6.01
P-8 N-137 N-132 80 37.48 200 200 D.I. 0.085 1330.37 1329.89 1.19 6.01 5.97
P-9 N-132 N-131 53 36.77 200 200 D.I. 0.085 1329.89 1329.57 1.17 5.97 5.95
P-10 N-131 N-130 8 36.12 200 200 D.I. 0.085 1329.57 1329.57 1.15 5.95 5.90
P-11 N-130 N-129 8 35.88 200 200 D.I. 0.085 1329.57 1329.49 1.14 5.90 5.93
P-12 N-129 N-128 5 33.8 200 200 D.I. 0.085 1329.49 1329.49 1.08 5.93 5.91
P-13 N-128 N-104 168 31.81 200 200 D.I. 0.085 1329.49 1326.48 1.01 5.91 8.10
P-14 N-104 81 3 28.81 200 200 D.I. 0.085 1326.48 1326.48 0.92 8.10 8.09
P-15 N-103 N-102 26 12.82 150 150 D.I. 0.085 1326.48 1326.30 0.73 8.09 8.17
P-16 N-102 N-101 6 12.01 150 150 D.I. 0.085 1326.30 1326.26 0.68 8.17 8.19
P-17 N-101 N-96 261 12.89 140 129.5 UPVC 0.005 1326.26 1322.28 0.98 8.19 10.46
P-18 N-96 N-95 29 11.23 140 129.5 UPVC 0.005 1322.28 1322.30 0.85 10.46 10.30
P-19 N-95 N-8 250 7.99 110 102 UPVC 0.005 1322.30 1304.50 0.98 10.30 25.92
P-20 N-8 20 2 10.88 90 83.2 UPVC 0.005 1304.50 1304.50 2.00 25.92 25.84
P-23 N-6 24 3 9.76 90 83.2 UPVC 0.005 1300.26 1300.26 1.80 28.67 28.57
P-24 N-5 N-4 107 4.63 90 83.2 UPVC 0.005 1300.26 1298.49 0.85 28.44 29.27
P-25 N-4 N-3 51 3.02 90 83.2 UPVC 0.005 1298.49 1299.19 0.56 29.27 28.37
P-26 N-3 N-2 38 2.7 90 83.2 UPVC 0.005 1299.19 1299.71 0.50 28.37 27.72
P-27 N-2 N-1 43 1.15 90 83.2 UPVC 0.005 1299.71 1300.30 0.21 27.72 27.10
P-28 N-1 N-18 87 0.86 75 69.3 UPVC 0.005 1300.30 1296.11 0.23 27.10 31.20
P-29 N-18 N-19 21 0.11 75 69.3 UPVC 0.005 1296.11 1295.79 0.03 31.20 31.52
P-30 N-23 N-19 43 0.18 75 69.3 UPVC 0.005 1297.30 1295.79 0.05 30.02 31.52
P-31 N-24 N-23 13 0.51 75 69.3 UPVC 0.005 1296.38 1297.30 0.14 30.94 30.02
P-32 N-25 N-24 52 1.49 75 69.3 UPVC 0.005 1296.69 1296.38 0.40 30.77 30.94
P-33 N-27 N-25 29 1.88 75 69.3 UPVC 0.005 1296.83 1296.69 0.50 30.76 30.77
P-34 N-55 N-27 148 1.95 75 69.3 UPVC 0.005 1300.00 1296.83 0.52 28.25 30.76
P-42 N-4 N-15 91 0.97 75 69.3 UPVC 0.005 1298.49 1296.49 0.26 29.27 31.16
P-43 N-2 N-17 77 1.14 75 69.3 UPVC 0.005 1299.71 1296.54 0.30 27.72 30.76
P-44 N-18 N-17 70 0.29 75 69.3 UPVC 0.005 1296.11 1296.54 0.08 31.20 30.76
P-45 N-17 N-16 12 0.81 75 69.3 UPVC 0.005 1296.54 1296.64 0.21 30.76 30.65
P-46 N-16 N-20 59 0.48 75 69.3 UPVC 0.005 1296.64 1296.54 0.13 30.65 30.73
P-47 N-20 N-21 27 0.06 75 69.3 UPVC 0.005 1296.54 1296.81 0.02 30.73 30.45
P-48 N-22 N-21 28 0.08 75 69.3 UPVC 0.005 1297.30 1296.81 0.02 29.97 30.45
P-49 N-24 N-22 79 0.66 75 69.3 UPVC 0.005 1296.38 1297.30 0.18 30.94 29.97
P-50 N-38 N-21 189 1.27 75 69.3 UPVC 0.005 1306.93 1296.81 0.34 20.74 30.45
P-51 N-26 N-27 53 0.26 75 69.3 UPVC 0.005 1296.00 1296.83 0.07 31.59 30.76
P-52 N-31 N-26 75 0.99 75 69.3 UPVC 0.005 1300.94 1296.00 0.26 26.76 31.59
P-53 N-47 N-29 42 0.55 75 69.3 UPVC 0.005 1300.49 1298.86 0.15 27.42 29.03
P-54 N-29 N-28 15 0.21 75 69.3 UPVC 0.005 1298.86 1298.26 0.06 29.03 29.63
P-55 N-10 N-14 55 0 75 69.3 UPVC 0.005 1301.65 1298.27 0.00 26.57 29.94
P-56 N-13 N-14 9 0.46 75 69.3 UPVC 0.005 1297.96 1298.27 0.12 30.26 29.94
P-57 N-12 N-13 24 0.74 75 69.3 UPVC 0.005 1297.11 1297.96 0.20 31.13 30.26
P-58 N-9 N-12 41 1.12 75 69.3 UPVC 0.005 1301.07 1297.11 0.30 27.24 31.13
P-59 N-7 N-6 93 5.98 90 83.2 UPVC 0.005 1304.50 1300.26 1.10 25.71 28.67
P-83 N-62 N-61 23 1.57 90 83.2 UPVC 0.005 1307.47 1310.46 0.29 24.54 21.51
P-84 N-61 N-94 78 0.99 90 83.2 UPVC 0.005 1310.46 1320.00 0.18 21.51 11.93
P-85 N-94 N-34 148 2.68 90 83.2 UPVC 0.005 1320.00 1307.60 0.49 11.93 23.85
P-86 N-34 N-35 29 1.19 90 83.2 UPVC 0.005 1307.60 1303.58 0.22 23.85 27.84
P-89 N-56 N-53 39 1.82 90 83.2 UPVC 0.005 1303.68 1310.44 0.34 27.88 21.06
P-90 N-53 N-52 24 1.49 90 83.2 UPVC 0.005 1310.44 1313.61 0.27 21.06 17.86
P-91 N-52 N-51 38 1.15 90 83.2 UPVC 0.005 1313.61 1313.70 0.21 17.86 17.74
P-92 N-51 N-49 50 0.45 90 83.2 UPVC 0.005 1313.70 1307.47 0.08 17.74 23.96
P-93 N-49 N-32 56 0.26 90 83.2 UPVC 0.005 1307.47 1300.94 0.05 23.96 30.49
P-94 N-50 N-49 16 0.08 90 83.2 UPVC 0.005 1308.05 1307.47 0.02 23.38 23.96
P-95 N-34 N-50 72 0.46 90 83.2 UPVC 0.005 1307.60 1308.05 0.09 23.85 23.38
P-96 N-51 N-48 50 0.2 75 69.3 UPVC 0.005 1313.70 1308.00 0.05 17.74 23.44
P-97 N-30 N-46 28 0.21 75 69.3 UPVC 0.005 1300.94 1304.34 0.06 30.50 27.09
P-106 N-40 N-39 32 0.74 75 69.3 UPVC 0.005 1314.89 1306.93 0.20 16.49 24.42
P-107 N-41 N-40 22 1.13 75 69.3 UPVC 0.005 1321.00 1314.89 0.30 10.41 16.49
P-108 N-42 N-41 10 1.45 75 69.3 UPVC 0.005 1322.00 1321.00 0.38 9.44 10.41
P-109 N-95 N-42 303 1.79 75 69.3 UPVC 0.005 1322.30 1322.00 0.47 10.30 9.44
P-110 N-87 N-42 182 1.17 75 69.3 UPVC 0.005 1322.00 1322.00 0.31 9.77 9.44
P-111 N-92 N-87 75 1.77 75 69.3 UPVC 0.005 1322.70 1322.00 0.47 9.35 9.77
P-112 N-88 N-72 185 0.26 75 69.3 UPVC 0.005 1324.31 1324.00 0.07 10.10 10.39
P-113 N-99 N-88 23 0.37 75 69.3 UPVC 0.005 1324.57 1324.31 0.10 9.85 10.10
P-114 N-100 N-99 86 0.35 75 69.3 UPVC 0.005 1325.61 1324.57 0.09 8.83 9.85
P-115 N-102 N-100 55 0.65 75 69.3 UPVC 0.005 1326.30 1325.61 0.17 8.17 8.83
P-116 N-85 N-88 40 0.1 75 69.3 UPVC 0.005 1325.90 1324.31 0.03 8.51 10.10
P-117 N-86 N-99 37 0.3 75 69.3 UPVC 0.005 1326.10 1324.57 0.08 8.32 9.85
P-142 N-197 N-323 71 0.51 75 69.3 UPVC 0.005 1329.13 1331.45 0.14 6.38 4.04
P-143 N-318 N-197 64 1.36 90 83.2 UPVC 0.005 1329.56 1329.13 0.25 6.01 6.38
P-144 N-316 N-318 33 0.15 110 102 UPVC 0.005 1327.15 1329.56 0.02 8.43 6.01
Page 1 of 8
Hydraulic Calculation of Pilot Area
Alternative - II, Connection from Chabahil and Mitra park chowk
PIPES Node Length Flow Pipe Ground Elevation Velocity Pressure (m)
ID From To (m) (lps) O.D.(mm) I.D.(mm) Type Rough From To (m/s) From To
P-146 N-320 N-319 20 0.95 75 69.3 UPVC 0.005 1331.67 1331.54 0.25 4.03 4.13
P-147 N-319 N-318 53 1.93 90 83.2 UPVC 0.005 1331.54 1329.56 0.35 4.13 6.01
P-148 N-326 N-319 78 1.46 75 69.3 UPVC 0.005 1331.53 1331.54 0.39 4.35 4.13
P-149 N-326 N-325 18 2.09 90 83.2 UPVC 0.005 1331.53 1331.67 0.38 4.35 4.17
P-150 N-325 N-324 40 1.68 75 69.3 UPVC 0.005 1331.67 1331.67 0.45 4.17 4.03
P-155 N-330 N-322 111 1.65 125 115.7 UPVC 0.005 1332.10 1331.84 0.16 4.33 4.55
P-156 N-327 N-326 36 3.97 110 102 UPVC 0.005 1331.93 1331.53 0.49 4.04 4.35
P-157 N-327 N-310 32 2.41 90 83.2 UPVC 0.005 1331.93 1329.90 0.44 4.04 5.98
P-158 N-307 N-327 49 3.62 110 102 UPVC 0.005 1330.93 1331.93 0.44 5.14 4.04
P-159 N-328 N-327 71 3.38 90 83.2 UPVC 0.005 1332.57 1331.93 0.62 3.75 4.04
P-160 N-329 N-328 101 5.36 140 129.5 UPVC 0.005 1332.10 1332.57 0.41 4.36 3.75
P-161 N-328 N-309 59 0.73 140 129.5 UPVC 0.005 1332.57 1331.83 0.06 3.75 4.49
P-162 N-309 N-336 15 0.36 140 129.5 UPVC 0.005 1331.83 1331.05 0.03 4.49 5.27
P-163 N-309 N-308 20 0.04 75 69.3 UPVC 0.005 1331.83 1331.00 0.01 4.49 5.32
P-164 N-201 N-200 23 0.95 75 69.3 UPVC 0.005 1326.45 1326.15 0.25 9.05 9.31
P-165 N-200 N-198 39 0.46 75 69.3 UPVC 0.005 1326.15 1327.50 0.12 9.31 7.95
P-192 N-128 N-105 183 3.25 90 83.2 UPVC 0.005 1329.49 1326.82 0.60 5.91 7.73
P-193 N-129 N-111 170 1.69 90 83.2 UPVC 0.005 1329.49 1327.89 0.31 5.93 7.29
P-195 N-106 N-110 19 1 90 83.2 UPVC 0.005 1326.82 1327.89 0.18 7.72 6.64
P-196 N-111 N-114 107 1.17 90 83.2 UPVC 0.005 1327.89 1326.76 0.22 7.29 8.33
P-200 N-110 N-109 20 0.94 90 83.2 UPVC 0.005 1327.89 1327.11 0.17 6.64 7.41
P-201 N-109 N-107 16 0.74 90 83.2 UPVC 0.005 1327.11 1326.60 0.14 7.41 7.91
P-202 N-108 N-112 35 1.08 90 83.2 UPVC 0.005 1326.60 1327.16 0.20 7.91 7.32
P-203 N-112 N-113 67 0.96 90 83.2 UPVC 0.005 1327.16 1326.76 0.18 7.32 7.68
P-210 N-81 N-79 23 0.48 75 69.3 UPVC 0.005 1325.75 1325.94 0.13 8.64 8.44
P-211 N-79 N-78 22 0.28 75 69.3 UPVC 0.005 1325.94 1325.65 0.07 8.44 8.73
P-212 N-77 N-115 94 2.02 90 83.2 UPVC 0.005 1325.55 1325.22 0.37 8.81 8.95
P-213 N-115 N-116 28 1.26 75 69.3 UPVC 0.005 1325.22 1324.19 0.33 8.95 9.92
P-214 N-116 N-117 17 0.59 75 69.3 UPVC 0.005 1324.19 1323.74 0.16 9.92 10.36
P-215 N-119 N-118 42 0.59 75 69.3 UPVC 0.005 1324.84 1324.84 0.16 9.62 9.60
P-224 N-221 N-165 131 1.5 75 69.3 UPVC 0.005 1298.09 1298.50 0.40 33.95 33.17
P-225 N-165 N-164 35 0.71 75 69.3 UPVC 0.005 1298.50 1298.00 0.19 33.17 33.65
P-226 N-164 N-159 27 0.6 75 69.3 UPVC 0.005 1298.00 1297.49 0.16 33.65 34.14
P-227 N-159 N-160 41 0.58 75 69.3 UPVC 0.005 1297.49 1297.20 0.15 34.14 34.41
P-230 N-59 N-163 143 0.67 75 69.3 UPVC 0.005 1300.00 1298.15 0.18 28.72 30.47
P-232 N-160 N-162 45 0.38 75 69.3 UPVC 0.005 1297.20 1298.20 0.10 34.41 33.40
P-233 N-161 N-163 43 0.28 75 69.3 UPVC 0.005 1297.15 1298.15 0.07 31.48 30.47
P-245 N-123 N-154 100 2.24 90 83.2 UPVC 0.005 1320.00 1310.00 0.41 11.90 21.66
P-246 N-154 N-155 16 1.06 90 83.2 UPVC 0.005 1310.00 1309.35 0.20 21.66 22.30
P-247 N-155 N-156 61 0.11 90 83.2 UPVC 0.005 1309.35 1305.00 0.02 22.30 26.65
P-248 N-156 N-157 26 0.48 90 83.2 UPVC 0.005 1305.00 1303.00 0.09 26.65 28.64
P-249 N-157 N-158 43 0.4 75 69.3 UPVC 0.005 1303.00 1300.00 0.11 28.64 31.63
P-250 N-158 N-159 28 0.14 75 69.3 UPVC 0.005 1300.00 1297.49 0.04 31.63 34.14
P-251 N-166 N-157 24 0.43 75 69.3 UPVC 0.005 1298.95 1303.00 0.11 32.70 28.64
P-252 N-166 N-164 71 0.2 75 69.3 UPVC 0.005 1298.95 1298.00 0.05 32.70 33.65
P-253 N-167 N-166 20 0.99 75 69.3 UPVC 0.005 1301.83 1298.95 0.26 29.85 32.70
P-254 N-167 N-165 89 0.19 75 69.3 UPVC 0.005 1301.83 1298.50 0.05 29.85 33.17
P-255 N-168 N-167 17 1.49 75 69.3 UPVC 0.005 1304.37 1301.83 0.39 27.36 29.85
P-256 N-220 N-168 81 1.84 90 83.2 UPVC 0.005 1306.80 1304.37 0.34 25.06 27.36
P-257 N-216 N-220 98 2.96 90 83.2 UPVC 0.005 1307.92 1306.80 0.54 24.32 25.06
P-258 N-217 N-216 9 3.43 90 83.2 UPVC 0.005 1307.92 1307.92 0.63 24.37 24.32
P-259 N-169 N-168 36 0.23 75 69.3 UPVC 0.005 1308.26 1304.37 0.06 23.47 27.36
P-260 N-169 N-156 48 1.13 75 69.3 UPVC 0.005 1308.26 1305.00 0.30 23.47 26.65
P-261 N-170 N-169 10 1.78 90 83.2 UPVC 0.005 1309.02 1308.26 0.33 22.72 23.47
P-262 N-171 N-170 29 2.21 90 83.2 UPVC 0.005 1315.09 1309.02 0.41 16.72 22.72
P-263 N-172 N-171 38 2.55 90 83.2 UPVC 0.005 1318.50 1315.09 0.47 13.43 16.72
P-264 N-174 N-172 23 2.98 90 83.2 UPVC 0.005 1319.31 1318.50 0.55 12.71 13.43
P-265 N-173 N-174 12 3.15 90 83.2 UPVC 0.005 1319.39 1319.31 0.58 12.68 12.71
P-266 N-175 N-173 17 3.31 90 83.2 UPVC 0.005 1319.23 1319.39 0.61 12.92 12.68
P-267 N-176 N-175 31 3.6 90 83.2 UPVC 0.005 1320.63 1319.23 0.66 11.69 12.92
P-268 N-178 N-176 23 1.78 90 83.2 UPVC 0.005 1319.43 1320.63 0.33 12.93 11.69
P-269 N-215 N-178 77 2.24 90 83.2 UPVC 0.005 1309.27 1319.43 0.41 23.28 12.93
P-270 N-177 N-176 40 2.11 90 83.2 UPVC 0.005 1321.72 1320.63 0.39 10.69 11.69
P-271 N-177 N-179 54 0.41 75 69.3 UPVC 0.005 1321.72 1320.00 0.11 10.69 12.40
P-272 N-151 N-177 36 2.94 90 83.2 UPVC 0.005 1323.43 1321.72 0.54 9.13 10.69
P-273 N-151 N-152 57 3.56 90 83.2 UPVC 0.005 1323.43 1321.50 0.66 9.13 10.74
P-274 N-152 N-123 106 2.65 90 83.2 UPVC 0.005 1321.50 1320.00 0.49 10.74 11.90
P-276 N-120 N-150A 129 0.94 90 83.2 UPVC 0.005 1324.40 1324.75 0.17 9.76 9.34
P-277 N-150 N-151 41 7.19 110 102 UPVC 0.005 1324.75 1323.43 0.88 8.10 9.13
P-278 N-180 N-150 104 8.13 110 102 UPVC 0.005 1325.66 1324.75 1.00 8.12 8.10
P-279 N-208 N-180 71 5.11 110 102 UPVC 0.005 1325.00 1325.66 0.62 9.06 8.12
P-280 N-181 N-180 60 4.43 90 83.2 UPVC 0.005 1326.22 1325.66 0.81 8.04 8.12
P-281 N-182 N-181 22 4.94 90 83.2 UPVC 0.005 1326.44 1326.22 0.91 8.04 8.04
P-282 16 N-182 32 5.4 90 83.2 UPVC 0.005 1326.50 1326.44 0.99 8.35 8.04
P-300 N-222 N-224 108 0.16 75 69.3 UPVC 0.005 1298.09 1298.66 0.04 33.96 33.39
P-301 N-225 N-224 10 0.14 75 69.3 UPVC 0.005 1298.66 1298.66 0.04 33.39 33.39
P-302 N-245 N-225 59 0.37 75 69.3 UPVC 0.005 1298.91 1298.66 0.10 33.15 33.39
Page 2 of 8
Hydraulic Calculation of Pilot Area
Alternative - II, Connection from Chabahil and Mitra park chowk
PIPES Node Length Flow Pipe Ground Elevation Velocity Pressure (m)
ID From To (m) (lps) O.D.(mm) I.D.(mm) Type Rough From To (m/s) From To
P-303 N-246 N-245 38 0.96 75 69.3 UPVC 0.005 1299.00 1298.91 0.26 33.11 33.15
P-304 N-276 N-246 118 1.42 75 69.3 UPVC 0.005 1301.85 1299.00 0.38 30.56 33.11
P-315 N-311 N-312 17 0.41 75 69.3 UPVC 0.005 1328.99 1328.00 0.11 6.28 7.27
P-316 N-204 N-313 82 0.76 75 69.3 UPVC 0.005 1326.45 1325.50 0.20 8.79 9.67
P-317 N-205 N-206 47 0.47 75 69.3 UPVC 0.005 1326.43 1326.60 0.12 8.39 8.20
P-318 45 N-221 3 0.9 75 69.3 UPVC 0.005 1298.09 1298.09 0.24 33.96 33.95
P-319 N-276 N-275 42 0.37 75 69.3 UPVC 0.005 1301.85 1300.50 0.10 30.56 31.90
P-320 N-273 N-274 13 0.39 75 69.3 UPVC 0.005 1303.62 1303.62 0.10 28.92 28.92
P-321 N-209 N-238 52 4.3 90 83.2 UPVC 0.005 1319.45 1319.55 0.79 13.58 13.08
P-322 N-238 N-255 62 1.75 90 83.2 UPVC 0.005 1319.55 1315.00 0.32 13.08 17.53
P-323 N-255 N-256 10 1.26 90 83.2 UPVC 0.005 1315.00 1316.34 0.23 17.53 16.19
P-324 N-255 N-254 15 0.24 75 69.3 UPVC 0.005 1315.00 1313.00 0.06 17.53 19.53
P-325 N-256 N-257 20 0.23 90 83.2 UPVC 0.005 1316.34 1315.00 0.04 16.19 17.52
P-326 N-258 N-257 12 0.23 90 83.2 UPVC 0.005 1314.00 1315.00 0.04 18.53 17.52
P-327 N-260 N-258 25 1.41 90 83.2 UPVC 0.005 1317.47 1314.00 0.26 15.08 18.53
P-328 N-297 N-260A 77 3.25 90 83.2 UPVC 0.005 1318.81 1317.00 0.60 14.10 15.52
P-329 N-260 N-261 72 0.72 90 83.2 UPVC 0.005 1317.47 1310.47 0.13 15.08 22.06
P-330 N-265 N-261 69 2.15 90 83.2 UPVC 0.005 1320.00 1310.47 0.40 12.68 22.06
P-331 N-266 N-265 29 2.53 90 83.2 UPVC 0.005 1316.40 1320.00 0.47 16.37 12.68
P-332 N-261 N-262 28 2.35 90 83.2 UPVC 0.005 1310.47 1308.47 0.43 22.06 23.99
P-333 N-262 N-251 55 0.58 75 69.3 UPVC 0.005 1308.47 1306.00 0.15 23.99 26.43
P-334 N-262 N-263 15 1.48 90 83.2 UPVC 0.005 1308.47 1307.47 0.27 23.99 24.97
P-335 N-263 N-250 47 1.31 75 69.3 UPVC 0.005 1307.47 1304.99 0.35 24.97 27.34
P-336 N-264 N-263 17 0.04 90 83.2 UPVC 0.005 1305.47 1307.47 0.01 26.97 24.97
P-337 N-271 N-264 54 1.27 75 69.3 UPVC 0.005 1304.37 1305.47 0.34 28.18 26.97
P-338 N-264 N-276 140 0.55 90 83.2 UPVC 0.005 1305.47 1301.85 0.10 26.97 30.56
P-339 N-258 N-259 21 0.99 90 83.2 UPVC 0.005 1314.00 1312.75 0.18 18.53 19.77
P-340 N-256 N-259 13 0.8 75 69.3 UPVC 0.005 1316.34 1312.75 0.21 16.19 19.77
P-341 N-259 N-252 51 1.59 90 83.2 UPVC 0.005 1312.75 1307.62 0.29 19.77 24.82
P-342 N-253 N-252 15 0.88 90 83.2 UPVC 0.005 1310.47 1307.62 0.16 21.99 24.82
P-343 N-239 N-253 25 1.08 90 83.2 UPVC 0.005 1312.50 1310.47 0.20 19.97 21.99
P-344 N-234 N-239 50 1.38 90 83.2 UPVC 0.005 1317.77 1312.50 0.25 14.75 19.97
P-345 N-238 N-234 62 1.88 90 83.2 UPVC 0.005 1319.55 1317.77 0.35 13.08 14.75
P-346 N-252 N-251 9 2.21 90 83.2 UPVC 0.005 1307.62 1306.00 0.41 24.82 26.43
P-347 N-251 N-250 30 2.59 90 83.2 UPVC 0.005 1306.00 1304.99 0.48 26.43 27.34
P-348 N-250 N-249 8 3.71 90 83.2 UPVC 0.005 1304.99 1304.52 0.68 27.34 27.77
P-349 N-249 N-240 56 0.69 90 83.2 UPVC 0.005 1304.52 1304.00 0.13 27.77 28.27
P-350 N-240 N-232 26 0.33 90 83.2 UPVC 0.005 1304.00 1303.15 0.06 28.27 29.12
P-351 N-233 N-232 46 2.61 90 83.2 UPVC 0.005 1309.55 1303.15 0.48 22.86 29.12
P-352 N-236 N-233 21 2.03 90 83.2 UPVC 0.005 1310.97 1309.55 0.37 21.49 22.86
P-353 N-236 N-235 5 0.11 75 69.3 UPVC 0.005 1310.97 1310.97 0.03 21.49 21.49
P-354 N-237 N-236 11 2.21 90 83.2 UPVC 0.005 1310.65 1310.97 0.41 21.83 21.49
P-355 N-211 N-237 44 2.55 90 83.2 UPVC 0.005 1315.60 1310.65 0.47 17.01 21.83
P-356 N-213 N-233 86 0.9 90 83.2 UPVC 0.005 1312.00 1309.55 0.17 20.45 22.86
P-357 N-214 N-213 25 1.13 90 83.2 UPVC 0.005 1311.00 1312.00 0.21 21.47 20.45
P-358 N-232 N-231 14 2.65 90 83.2 UPVC 0.005 1303.15 1303.00 0.49 29.12 29.22
P-359 N-231 N-230 21 2.4 90 83.2 UPVC 0.005 1303.00 1302.90 0.44 29.22 29.26
P-360 N-230 N-229 43 2.12 90 83.2 UPVC 0.005 1302.90 1300.38 0.39 29.26 31.70
P-361 N-229 N-223 30 0.93 90 83.2 UPVC 0.005 1300.38 1300.00 0.17 31.70 32.06
P-362 N-223 N-224 79 0.29 75 69.3 UPVC 0.005 1300.00 1298.66 0.08 32.06 33.39
P-363 N-229 N-228 15 0.65 90 83.2 UPVC 0.005 1300.38 1300.00 0.12 31.70 32.07
P-364 N-228 N-227 23 0.51 75 69.3 UPVC 0.005 1300.00 1299.50 0.14 32.07 32.56
P-365 N-227 N-226 17 0.35 75 69.3 UPVC 0.005 1299.50 1299.00 0.09 32.56 33.06
P-366 N-226 N-244 59 0.02 75 69.3 UPVC 0.005 1299.00 1299.50 0.01 33.06 32.56
P-367 N-245 N-244 42 0.21 75 69.3 UPVC 0.005 1298.91 1299.50 0.06 33.15 32.56
P-368 N-244 N-243 14 0.13 75 69.3 UPVC 0.005 1299.50 1300.48 0.03 32.56 31.57
P-369 N-242 N-244 76 0.32 75 69.3 UPVC 0.005 1300.47 1299.50 0.09 31.60 32.56
P-370 N-242 N-228 48 0.19 90 83.2 UPVC 0.005 1300.47 1300.00 0.03 31.60 32.07
P-371 N-241 N-242 23 0.96 90 83.2 UPVC 0.005 1300.27 1300.47 0.18 31.81 31.60
P-372 N-248 N-241 49 1.29 90 83.2 UPVC 0.005 1301.99 1300.27 0.24 30.14 31.81
P-373 N-248 N-247 54 0.73 90 83.2 UPVC 0.005 1301.99 1300.80 0.13 30.14 31.30
P-374 N-247 N-246 79 0.04 90 83.2 UPVC 0.005 1300.80 1299.00 0.01 31.30 33.11
P-375 N-249 N-248 51 2.61 90 83.2 UPVC 0.005 1304.52 1301.99 0.48 27.77 30.14
P-376 N-306 N-305 21 14.11 140 129.5 UPVC 0.005 1330.59 1330.00 1.07 5.21 5.64
P-377 N-305 N-303 28 13.85 140 129.5 UPVC 0.005 1330.00 1329.60 1.05 5.64 5.83
P-379 N-334 N-391 74 17.92 140 129.5 UPVC 0.005 1331.96 1328.00 1.36 4.55 7.63
P-380 N-391 N-388 59 12.88 125 115.7 UPVC 0.005 1328.00 1322.00 1.22 7.63 12.97
P-381 N-388 N-384 59 12.13 125 115.7 UPVC 0.005 1322.00 1318.00 1.15 12.97 16.37
P-382 N-384 N-382 97 9.44 110 102 UPVC 0.005 1318.00 1314.00 1.15 16.37 19.23
P-383 N-382 N-378 102 9.16 110 102 UPVC 0.005 1314.00 1308.00 1.12 19.23 24.09
P-384 N-378 N-374 86 3.5 90 83.2 UPVC 0.005 1308.00 1305.00 0.64 24.09 26.64
P-385 N-374 N-373 25 2.45 90 83.2 UPVC 0.005 1305.00 1304.00 0.45 26.64 27.57
P-386 N-373 N-372 37 1.87 90 83.2 UPVC 0.005 1304.00 1303.50 0.34 27.57 28.00
P-387 N-372 N-371 85 1.58 90 83.2 UPVC 0.005 1303.50 1302.00 0.29 28.00 29.40
P-388 N-371 N-362 239 1.43 75 69.3 UPVC 0.005 1302.00 1300.50 0.38 29.40 30.28
P-400 N-361 N-362 59 0.42 75 69.3 UPVC 0.005 1300.91 1300.50 0.11 29.89 30.28
P-401 N-287 N-361 105 2.65 75 69.3 UPVC 0.005 1300.50 1300.91 0.70 31.11 29.89
Page 3 of 8
Hydraulic Calculation of Pilot Area
Alternative - II, Connection from Chabahil and Mitra park chowk
PIPES Node Length Flow Pipe Ground Elevation Velocity Pressure (m)
ID From To (m) (lps) O.D.(mm) I.D.(mm) Type Rough From To (m/s) From To
P-402 N-286 N-287 71 2.12 75 69.3 UPVC 0.005 1300.35 1300.50 0.56 31.62 31.11
P-403 N-280 N-286 113 1.26 75 69.3 UPVC 0.005 1298.56 1300.35 0.33 33.65 31.62
P-404 N-277 N-280 96 1.29 75 69.3 UPVC 0.005 1302.00 1298.56 0.34 30.42 33.65
P-412 N-338 N-304 75 11.96 140 129.5 UPVC 0.005 1330.70 1329.60 0.91 5.12 5.79
P-414 N-340A N-341 60 6.96 125 115.7 UPVC 0.005 1330.46 1329.46 0.78 5.21 5.88
P-418 N-342 N-343 35 0.39 90 83.2 UPVC 0.005 1329.46 1328.00 0.07 5.77 7.23
P-419 N-342 N-344 14 12.11 125 115.7 UPVC 0.005 1329.46 1329.46 1.36 5.77 5.56
P-420 N-344 N-345 67 11.59 125 115.7 UPVC 0.005 1329.46 1322.46 1.31 5.56 11.62
P-421 N-345 N-346 12 10.95 110 102 UPVC 0.005 1322.46 1321.46 1.34 11.62 12.43
P-422 N-346 N-347 20 10.72 110 102 UPVC 0.005 1321.46 1319.96 1.31 12.43 13.64
P-423 N-347 N-348 15 10.25 110 102 UPVC 0.005 1319.96 1318.96 1.25 13.64 14.43
P-424 N-348 N-349 33 9.84 110 102 UPVC 0.005 1318.96 1317.96 1.20 14.43 15.01
P-425 N-349 N-350 53 1.31 90 83.2 UPVC 0.005 1317.96 1317.50 0.24 15.01 15.43
P-426 N-350 N-352 37 0.84 90 83.2 UPVC 0.005 1317.50 1317.40 0.15 15.43 15.51
P-427 N-352 N-351 14 0.63 90 83.2 UPVC 0.005 1317.40 1317.40 0.12 15.51 15.51
P-428 N-351 N-291 33 0.35 90 83.2 UPVC 0.005 1317.40 1320.00 0.06 15.51 12.91
P-429 N-292 N-291 65 0.14 90 83.2 UPVC 0.005 1321.87 1320.00 0.03 11.03 12.91
P-431 N-295 N-294 32 6.25 110 102 UPVC 0.005 1326.30 1325.24 0.76 7.02 7.90
P-432 N-296 N-295 54 6.87 110 102 UPVC 0.005 1327.65 1326.30 0.84 6.02 7.02
P-433 N-299 N-296 68 7.73 140 129.5 UPVC 0.005 1325.25 1327.65 0.59 8.60 6.02
P-434 N-292 N-290 83 4.75 90 83.2 UPVC 0.005 1321.87 1307.90 0.87 11.03 24.25
P-435 N-290 N-289 21 4.04 90 83.2 UPVC 0.005 1307.90 1307.00 0.74 24.25 25.01
P-436 N-289 N-288 54 3.45 90 83.2 UPVC 0.005 1307.00 1306.76 0.63 25.01 24.97
P-437 N-288 N-287 38 2.68 90 83.2 UPVC 0.005 1306.76 1300.50 0.49 24.97 31.11
P-438 N-349 N-353 40 7.8 110 102 UPVC 0.005 1317.96 1316.96 0.95 15.01 15.68
P-439 N-353 N-357 39 7.2 110 102 UPVC 0.005 1316.96 1317.00 0.88 15.68 15.37
P-440 N-356 N-357 30 2.95 90 83.2 UPVC 0.005 1316.70 1317.00 0.54 15.78 15.37
P-441 N-355 N-356 17 3.19 90 83.2 UPVC 0.005 1316.50 1316.70 0.59 16.06 15.78
P-442 N-354 N-355 17 3.56 90 83.2 UPVC 0.005 1316.35 1316.50 0.66 16.30 16.06
P-443 N-383 N-354 82 4.21 90 83.2 UPVC 0.005 1316.00 1316.35 0.77 17.25 16.30
P-444 N-383 N-382 31 1.12 90 83.2 UPVC 0.005 1316.00 1314.00 0.21 17.25 19.23
P-445 N-385 N-383 73 6.14 90 83.2 UPVC 0.005 1320.00 1316.00 1.13 14.31 17.25
P-446 N-384 N-385 39 1.79 90 83.2 UPVC 0.005 1318.00 1320.00 0.33 16.37 14.31
P-447 N-387 N-385 58 5.37 90 83.2 UPVC 0.005 1324.00 1320.00 0.99 10.97 14.31
P-448 N-389 N-387 25 5.93 90 83.2 UPVC 0.005 1327.00 1324.00 1.09 8.31 10.97
P-449 N-389 N-386 40 0.52 75 69.3 UPVC 0.005 1327.00 1328.00 0.14 8.31 7.29
P-450 N-390 N-389 23 6.94 110 102 UPVC 0.005 1329.00 1327.00 0.85 6.46 8.31
P-451 N-340A N-390 100 3.62 110 102 UPVC 0.005 1330.46 1329.00 0.44 5.21 6.46
P-452 N-337 N-338 26 23.22 140 129.5 UPVC 0.005 1331.05 1330.70 1.76 5.26 5.12
P-453 N-391 N-390 71 3.83 110 102 UPVC 0.005 1328.00 1329.00 0.47 7.63 6.46
P-454 N-357 N-358 29 9.7 110 102 UPVC 0.005 1317.00 1314.54 1.19 15.37 17.46
P-455 N-358 N-381 84 1.93 90 83.2 UPVC 0.005 1314.54 1311.00 0.36 17.46 20.85
P-456 N-380 N-381 36 0.73 90 83.2 UPVC 0.005 1309.40 1311.00 0.13 22.46 20.85
P-457 N-379 N-380 17 4.58 90 83.2 UPVC 0.005 1308.40 1309.40 0.84 23.61 22.46
P-458 N-378 N-379 9 4.9 90 83.2 UPVC 0.005 1308.00 1308.40 0.90 24.09 23.61
P-459 N-358 N-359 20 7.39 110 102 UPVC 0.005 1314.54 1312.02 0.90 17.46 19.83
P-460 N-359 N-365 60 1.9 75 69.3 UPVC 0.005 1312.02 1309.81 0.50 19.83 21.79
P-461 N-359 N-366 46 4.91 110 102 UPVC 0.005 1312.02 1308.95 0.60 19.83 22.73
P-462 N-366 N-365 33 1.46 75 69.3 UPVC 0.005 1308.95 1309.81 0.39 22.73 21.79
P-463 N-365 N-363 32 2.8 75 69.3 UPVC 0.005 1309.81 1303.97 0.74 21.79 27.36
P-464 N-363 N-360 69 2.21 75 69.3 UPVC 0.005 1303.97 1305.77 0.59 27.36 25.17
P-465 N-360 N-361 100 1.01 75 69.3 UPVC 0.005 1305.77 1300.91 0.27 25.17 29.89
P-466 N-364 N-363 18 0.15 75 69.3 UPVC 0.005 1303.32 1303.97 0.04 28.01 27.36
P-467 N-381 N-366 96 1.85 90 83.2 UPVC 0.005 1311.00 1308.95 0.34 20.85 22.73
P-468 N-366 N-367 35 4.77 110 102 UPVC 0.005 1308.95 1306.34 0.58 22.73 25.22
P-469 N-367 N-364 53 3.21 90 83.2 UPVC 0.005 1306.34 1303.32 0.59 25.22 28.01
P-470 N-364 N-362 101 2.17 75 69.3 UPVC 0.005 1303.32 1300.50 0.58 28.01 30.28
P-471 N-368 N-367 42 0.38 90 83.2 UPVC 0.005 1307.00 1306.34 0.07 24.57 25.22
P-472 N-375 N-368 54 0.64 90 83.2 UPVC 0.005 1305.50 1307.00 0.12 26.08 24.57
P-473 N-367 N-369 39 1.44 90 83.2 UPVC 0.005 1306.34 1304.97 0.27 25.22 26.55
P-474 N-376 N-369 62 1.21 90 83.2 UPVC 0.005 1305.50 1304.97 0.22 26.07 26.55
P-475 N-376 N-373 75 0.14 75 69.3 UPVC 0.005 1305.50 1304.00 0.04 26.07 27.57
P-476 N-375 N-376 8 1.72 90 83.2 UPVC 0.005 1305.50 1305.50 0.32 26.08 26.07
P-477 N-377 N-375 12 2.6 90 83.2 UPVC 0.005 1306.21 1305.50 0.48 25.41 26.08
P-478 N-374 N-377 64 0.41 75 69.3 UPVC 0.005 1305.00 1306.21 0.11 26.64 25.41
P-479 N-380 N-377 72 2.71 90 83.2 UPVC 0.005 1309.40 1306.21 0.50 22.46 25.41
P-480 N-369 N-370 32 1.92 90 83.2 UPVC 0.005 1304.97 1303.00 0.35 26.55 28.46
P-481 N-370 N-371 56 0.93 75 69.3 UPVC 0.005 1303.00 1302.00 0.25 28.46 29.40
P-482 N-298 N-283 154 3.52 90 83.2 UPVC 0.005 1323.27 1318.83 0.65 10.20 13.82
P-483 N-282 N-283 62 1.3 90 83.2 UPVC 0.005 1313.00 1318.83 0.24 19.70 13.82
P-484 N-268 N-282 64 2.08 90 83.2 UPVC 0.005 1312.64 1313.00 0.38 20.20 19.70
P-485 N-283 N-284 20 3.9 90 83.2 UPVC 0.005 1318.83 1318.16 0.72 13.82 14.36
P-486 N-284 N-285 79 3.25 90 83.2 UPVC 0.005 1318.16 1306.00 0.60 14.36 26.15
P-487 N-285 N-286 54 1.62 75 69.3 UPVC 0.005 1306.00 1300.35 0.43 26.15 31.62
P-488 N-285 N-281 88 0.62 75 69.3 UPVC 0.005 1306.00 1309.00 0.16 26.15 23.10
P-489 N-272 N-279 87 1.69 75 69.3 UPVC 0.005 1304.37 1301.00 0.45 28.20 31.26
P-490 N-279 N-280 58 0.78 75 69.3 UPVC 0.005 1301.00 1298.56 0.21 31.26 33.65
Page 4 of 8
Hydraulic Calculation of Pilot Area
Alternative - II, Connection from Chabahil and Mitra park chowk
PIPES Node Length Flow Pipe Ground Elevation Velocity Pressure (m)
ID From To (m) (lps) O.D.(mm) I.D.(mm) Type Rough From To (m/s) From To
P-491 N-279 N-278 14 0.26 75 69.3 UPVC 0.005 1301.00 1301.00 0.07 31.26 31.26
P-275 N-155 N-153 47 0.43 75 69.3 UPVC 0.005 1309.35 1313.50 0.11 22.30 18.13
1 MC-01 N-333 1000 207.39 600 600 D.I. 0.085 1337.00 1331.96 0.73 0.25 4.60
4 N-338 N-340A 30 10.94 140 129.5 UPVC 0.005 1330.70 1330.46 0.83 5.12 5.21
6 N-59 N-161 123 0.7 75 69.3 UPVC 0.005 1300.00 1297.15 0.19 28.72 31.48
7 N-58 N-59 45 2.48 75 69.3 UPVC 0.005 1301.88 1300.00 0.66 27.15 28.72
12 N-293 N-292 15 5.36 110 102 UPVC 0.005 1324.44 1321.87 0.66 8.53 11.03
13 N-294 N-293 35 5.65 110 102 UPVC 0.005 1325.24 1324.44 0.69 7.90 8.53
2 44 N-334 15 24.81 200 200 D.I. 0.085 1331.96 1331.96 0.79 4.59 4.55
3 N-333 2 450 84.24 600 600 D.I. 0.085 1331.96 1330.37 0.30 4.60 6.13
14 2 1 10 84.24 600 600 D.I. 0.085 1330.37 1330.37 0.30 6.13 6.13
15 1 N-138 6 11.5 200 200 D.I. 0.085 1330.37 1330.37 0.37 6.13 6.12
17 1 3 55 17.06 250 250 D.I. 0.085 1330.37 1328.26 0.35 6.13 8.21
18 3 4 52 17.06 250 250 D.I. 0.085 1328.26 1326.50 0.35 8.21 9.94
19 4 5 75 17.06 200 200 D.I. 0.085 1326.50 1325.62 0.54 9.94 10.72
20 5 6 27 17.06 200 200 D.I. 0.085 1325.62 1325.67 0.54 10.72 10.62
21 6 7 17 17.06 200 200 D.I. 0.085 1325.67 1325.71 0.54 10.62 10.56
22 7 8 60 17.06 200 200 D.I. 0.085 1325.71 1325.82 0.54 10.56 10.36
23 44 S-335 70 86.34 350 350 D.I. 0.085 1331.96 1331.50 0.90 4.59 4.92
24 S-335 42 50 86.34 350 350 D.I. 0.085 1331.50 1331.05 0.90 4.92 5.27
25 42 41 30 48.63 300 300 D.I. 0.085 1331.05 1330.93 0.69 5.27 5.35
26 41 40 20 48.63 300 300 D.I. 0.085 1330.93 1330.59 0.69 5.35 5.66
27 40 39 60 48.63 250 250 D.I. 0.085 1330.59 1329.90 0.99 5.66 6.14
28 39 38 35 48.63 200 200 D.I. 0.085 1329.90 1328.00 1.55 6.14 7.65
29 38 61 25 25.06 200 200 D.I. 0.085 1328.00 1327.15 0.80 7.65 8.43
30 61 N-317A 25 28.66 200 200 D.I. 0.085 1327.15 1326.80 0.91 8.43 8.68
31 N-317A 59 45 28.66 200 200 D.I. 0.085 1326.80 1326.45 0.91 8.68 8.85
32 59 58 10 28.66 200 200 D.I. 0.085 1326.45 1326.45 0.91 8.85 8.82
59 N-304 99 50 5.84 140 129.5 UPVC 0.005 1329.60 1329.46 0.44 5.79 5.85
61 110 115 25 2.12 125 115.7 UPVC 0.005 1329.72 1329.88 0.20 6.67 6.50
62 116 115 85 1.07 125 115.7 UPVC 0.005 1331.45 1329.88 0.10 4.94 6.50
63 N-322 116 25 1.07 125 115.7 UPVC 0.005 1331.84 1331.45 0.10 4.55 4.94
65 115 N-190C 40 2.46 110 102 UPVC 0.005 1329.88 1329.07 0.30 6.50 7.27
66 N-190C 113 20 2.09 110 102 UPVC 0.005 1329.07 1328.62 0.26 7.27 7.70
67 113 112 100 0.59 90 83.2 UPVC 0.005 1328.62 1326.50 0.11 7.70 9.80
83 81 82 60 13.25 200 200 D.I. 0.085 1326.48 1326.82 0.42 8.09 7.69
84 82 83 25 13.25 200 200 D.I. 0.085 1326.82 1326.60 0.42 7.69 7.89
85 83 84 45 13.25 200 200 D.I. 0.085 1326.60 1326.10 0.42 7.89 8.35
86 84 85 20 13.25 200 200 D.I. 0.085 1326.10 1325.90 0.42 8.35 8.53
87 85 87 20 18.5 200 200 D.I. 0.085 1325.90 1325.71 0.59 8.53 8.68
88 87 88 20 18.5 200 200 D.I. 0.085 1325.71 1325.75 0.59 8.68 8.61
89 88 89 10 18.5 200 200 D.I. 0.085 1325.75 1325.70 0.59 8.61 8.64
90 89 90 10 18.5 200 200 D.I. 0.085 1325.70 1325.65 0.59 8.64 8.67
91 90 91 25 18.5 200 200 D.I. 0.085 1325.65 1325.55 0.59 8.67 8.73
92 91 92 10 18.5 150 150 D.I. 0.085 1325.55 1325.50 1.05 8.73 8.71
93 92 93 10 18.5 150 150 D.I. 0.085 1325.50 1325.42 1.05 8.71 8.72
94 93 94 5 18.5 150 150 D.I. 0.085 1325.42 1325.42 1.05 8.72 8.68
95 94 95 35 18.5 150 150 D.I. 0.085 1325.42 1324.75 1.05 8.68 9.09
96 95 96 15 18.5 150 150 D.I. 0.085 1324.75 1324.00 1.05 9.09 9.73
97 96 97 5 18.5 150 150 D.I. 0.085 1324.00 1324.00 1.05 9.73 9.69
98 97 98 10 18.5 150 150 D.I. 0.085 1324.00 1323.50 1.05 9.69 10.12
99 98 12 70 18.5 150 150 D.I. 0.085 1323.50 1323.00 1.05 10.12 10.11
129 10 11 25 17.06 150 150 D.I. 0.085 1322.15 1321.13 0.97 12.45 13.31
130 9 10 75 17.06 150 150 D.I. 0.085 1324.50 1322.15 0.97 10.57 12.45
131 67 9 75 17.06 150 150 D.I. 0.085 1325.60 1324.50 0.97 9.94 10.57
132 66 67 20 17.06 150 150 D.I. 0.085 1325.86 1325.60 0.97 9.81 9.94
133 8 66 80 17.06 150 150 D.I. 0.085 1325.82 1325.86 0.97 10.36 9.81
139 120 N-58 20 2.77 75 69.3 UPVC 0.005 1301.00 1301.88 0.73 28.20 27.15
140 N-333 44 15 123.15 600 600 D.I. 0.085 1331.96 1331.96 0.44 4.60 4.59
141 44 N-332 15 12 300 300 D.I. 0.085 1331.96 1331.96 0.17 4.59 4.59
142 N-194 111 6 4.5 150 150 D.I. 0.085 1331.77 1331.77 0.25 4.67 4.67
143 118 N-321 50 0.28 75 69.3 UPVC 0.005 1331.67 1331.93 0.07 4.03 3.76
144 81 N-103 2 15.56 200 200 D.I. 0.085 1326.48 1326.48 0.50 8.09 8.09
5 42 N-337 5 34.81 300 300 D.I. 0.085 1331.05 1331.05 0.49 5.27 5.26
8 42 N-336 5 2.9 200 200 D.I. 0.085 1331.05 1331.05 0.09 5.27 5.27
10 N-336 N-308 10 0.11 75 69.3 UPVC 0.005 1331.05 1331.00 0.03 5.27 5.32
78 N-341 99 5 6.81 125 115.7 UPVC 0.005 1329.46 1329.46 0.77 5.88 5.85
79 99 N-342 5 12.65 125 115.7 UPVC 0.005 1329.46 1329.46 1.43 5.85 5.77
156 38 N-315 5 23.56 150 150 D.I. 0.085 1328.00 1328.00 1.33 7.65 7.60
157 N-316 61 5 3.6 200 200 D.I. 0.085 1327.15 1327.15 0.11 8.43 8.43
173 N-222 45 3 0.9 75 69.3 UPVC 0.005 1298.09 1298.09 0.24 33.96 33.96
187 12 N-69 5 5.46 90 83.2 UPVC 0.005 1323.00 1323.00 1.00 10.11 10.05
219 20 N-7 3 10.88 90 83.2 UPVC 0.005 1304.50 1304.50 2.00 25.84 25.71
220 24 N-5 4 9.76 90 83.2 UPVC 0.005 1300.26 1300.26 1.80 28.57 28.44
255 N-190 115 5 0.06 125 115.7 UPVC 0.005 1329.88 1329.88 0.01 6.50 6.50
259 N-324 118 9 1.43 110 102 UPVC 0.005 1331.67 1331.67 0.18 4.03 4.03
260 118 N-320 6 1.15 110 102 UPVC 0.005 1331.67 1331.67 0.14 4.03 4.03
Page 5 of 8
Hydraulic Calculation of Pilot Area
Alternative - II, Connection from Chabahil and Mitra park chowk
PIPES Node Length Flow Pipe Ground Elevation Velocity Pressure (m)
ID From To (m) (lps) O.D.(mm) I.D.(mm) Type Rough From To (m/s) From To
68 N-11 N-6 95 4.11 90 83.2 UPVC 0.005 1302.70 1300.26 0.76 26.90 28.67
272 N-7 N-11 70 4.67 90 83.2 UPVC 0.005 1304.50 1302.70 0.86 25.71 26.90
276 N-47 N-31 70 2.62 90 83.2 UPVC 0.005 1300.49 1300.94 0.48 27.42 26.76
112 N-33 N-35 65 0.25 90 83.2 UPVC 0.005 1301.56 1303.58 0.05 29.87 27.84
113 N-32 N-33 30 0.49 90 83.2 UPVC 0.005 1300.94 1301.56 0.09 30.49 29.87
114 N-30 N-32 15 0.43 90 83.2 UPVC 0.005 1300.94 1300.94 0.08 30.50 30.49
115 N-54 76 60 0.88 90 83.2 UPVC 0.005 1300.00 1300.49 0.16 31.49 30.97
116 N-55 N-47 60 3.62 90 83.2 UPVC 0.005 1300.00 1300.49 0.67 28.25 27.42
117 76 N-30 60 0.88 90 83.2 UPVC 0.005 1300.49 1300.94 0.16 30.97 30.50
118 N-35 N-37 110 1.07 90 83.2 UPVC 0.005 1303.58 1306.93 0.20 27.84 24.42
119 N-37 N-39 15 0.66 90 83.2 UPVC 0.005 1306.93 1306.93 0.12 24.42 24.42
120 N-38 N-36 75 0.16 90 83.2 UPVC 0.005 1306.93 1304.46 0.03 20.74 23.20
121 N-31 N-36 135 0.62 90 83.2 UPVC 0.005 1300.94 1304.46 0.11 26.76 23.20
208 21 N-8 70 3.45 90 83.2 UPVC 0.005 1302.70 1304.50 0.63 28.08 25.92
209 N-39 21 110 3.45 90 83.2 UPVC 0.005 1306.93 1302.70 0.63 24.42 28.08
210 17 N-38 115 2.93 90 83.2 UPVC 0.005 1302.70 1306.93 0.54 25.41 20.74
211 N-43 N-39 50 2.36 90 83.2 UPVC 0.005 1311.18 1306.93 0.43 20.30 24.42
212 N-10 17 30 2.93 90 83.2 UPVC 0.005 1301.65 1302.70 0.54 26.57 25.41
213 N-9 N-10 20 3.23 90 83.2 UPVC 0.005 1301.07 1301.65 0.59 27.24 26.57
214 N-5 N-9 45 4.59 90 83.2 UPVC 0.005 1300.26 1301.07 0.84 28.44 27.24
108 N-69 N-92 85 5.46 90 83.2 UPVC 0.005 1323.00 1322.70 1.00 10.05 9.35
109 N-68 N-90 85 5.72 110 102 UPVC 0.005 1323.00 1322.70 0.70 9.89 9.79
110 N-92 N-43 135 3.11 90 83.2 UPVC 0.005 1322.70 1311.18 0.57 9.35 20.30
111 N-91 N-45 105 0.58 75 69.3 UPVC 0.005 1322.70 1323.00 0.15 9.75 9.40
123 N-45 N-44 15 0.26 75 69.3 UPVC 0.005 1323.00 1313.92 0.07 9.40 18.48
125 N-44 78 15 0 75 69.3 UPVC 0.005 1313.92 1311.18 0.00 18.48 21.22
126 N-90 N-91 10 4.6 110 102 UPVC 0.005 1322.70 1322.70 0.56 9.79 9.75
127 N-90 N-93 120 0.62 90 83.2 UPVC 0.005 1322.70 1320.00 0.11 9.79 12.46
128 N-91 N-94 120 3.16 90 83.2 UPVC 0.005 1322.70 1320.00 0.58 9.75 11.93
199 N-68 N-65 75 6.86 125 115.7 UPVC 0.005 1323.00 1318.52 0.65 9.89 14.11
200 N-65 N-62 120 5.98 110 102 UPVC 0.005 1318.52 1307.47 0.73 14.11 24.54
201 N-66 N-64 135 10.49 125 115.7 UPVC 0.005 1321.13 1311.53 1.00 13.16 21.72
202 N-64 N-63 25 9.46 110 102 UPVC 0.005 1311.53 1308.92 1.16 21.72 24.03
203 N-63 N-57 90 8.92 90 83.2 UPVC 0.005 1308.92 1303.68 1.64 24.03 26.72
204 N-62 N-60 50 3.69 90 83.2 UPVC 0.005 1307.47 1304.68 0.68 24.54 27.04
205 N-60 N-56 30 3.43 90 83.2 UPVC 0.005 1304.68 1303.68 0.63 27.04 27.88
206 N-56 N-54 75 1.35 90 83.2 UPVC 0.005 1303.68 1300.00 0.25 27.88 31.49
207 N-57 120 45 8.58 90 83.2 UPVC 0.005 1303.68 1301.00 1.58 26.72 28.20
215 120 N-55 30 5.81 75 69.3 UPVC 0.005 1301.00 1300.00 1.54 28.20 28.25
217 N-127 N-125 20 5.18 125 115.7 UPVC 0.005 1326.21 1326.12 0.49 8.57 8.61
218 N-125 N-124 15 4.9 125 115.7 UPVC 0.005 1326.12 1326.12 0.47 8.61 8.58
273 N-135 N-126 85 0.79 125 115.7 UPVC 0.005 1326.50 1326.21 0.07 8.59 8.88
274 N-134 N-133 30 5.95 125 115.7 UPVC 0.005 1326.50 1326.40 0.57 8.50 8.52
275 N-133 N-127 55 5.59 125 115.7 UPVC 0.005 1326.40 1326.21 0.53 8.52 8.57
277 N-114 N-126 160 0.33 125 115.7 UPVC 0.005 1326.76 1326.21 0.03 8.33 8.88
279 N-113 N-84 50 0.71 125 115.7 UPVC 0.005 1326.76 1325.90 0.07 7.68 8.54
280 N-124 N-83 165 4.45 125 115.7 UPVC 0.005 1326.12 1325.90 0.42 8.58 8.53
71 N-104 N-105 58 2.35 125 115.7 UPVC 0.005 1326.48 1326.82 0.22 8.10 7.73
72 N-105 N-106 5 4.84 125 115.7 UPVC 0.005 1326.82 1326.82 0.46 7.73 7.72
73 N-106 N-107 21 3.79 125 115.7 UPVC 0.005 1326.82 1326.60 0.36 7.72 7.91
74 N-107 N-108 5 4.48 125 115.7 UPVC 0.005 1326.60 1326.60 0.43 7.91 7.91
75 N-108 N-84 65 3.28 125 115.7 UPVC 0.005 1326.60 1325.90 0.31 7.91 8.54
76 N-86 N-85 20 1.68 110 102 UPVC 0.005 1326.10 1325.90 0.21 8.32 8.51
101 N-103 N-86 134 2.48 110 102 UPVC 0.005 1326.48 1326.10 0.30 8.09 8.32
102 N-85 N-80 50 1.23 110 102 UPVC 0.005 1325.90 1325.70 0.15 8.51 8.70
103 N-80 N-76 45 0.84 110 102 UPVC 0.005 1325.70 1325.50 0.10 8.70 8.89
104 N-76 N-72 65 0.21 110 102 UPVC 0.005 1325.50 1324.00 0.03 8.89 10.39
105 N-84 N-83 6 3.62 110 102 UPVC 0.005 1325.90 1325.90 0.44 8.54 8.53
106 N-83 N-82 18 2.62 110 102 UPVC 0.005 1325.90 1325.71 0.32 8.53 8.70
107 N-82 N-81 20 2.43 110 102 UPVC 0.005 1325.71 1325.75 0.30 8.70 8.64
122 N-81 N-78 20 1.8 110 102 UPVC 0.005 1325.75 1325.65 0.22 8.64 8.73
124 N-78 N-77 25 1.91 110 102 UPVC 0.005 1325.65 1325.55 0.23 8.73 8.81
189 N-75 N-77 20 0.49 110 102 UPVC 0.005 1325.42 1325.55 0.06 8.94 8.81
190 N-74 N-75 5 0.72 110 102 UPVC 0.005 1325.42 1325.42 0.09 8.94 8.94
191 N-73 N-74 35 0.91 110 102 UPVC 0.005 1324.75 1325.42 0.11 9.62 8.94
192 N-70 N-73 30 1.41 110 102 UPVC 0.005 1323.50 1324.75 0.17 10.88 9.62
193 N-67 N-70 95 1.91 110 102 UPVC 0.005 1321.13 1323.50 0.23 13.31 10.88
194 N-137 N-136 55 13.79 125 115.7 UPVC 0.005 1330.37 1328.26 1.31 6.01 7.43
195 N-136 N-135 50 13.24 125 115.7 UPVC 0.005 1328.26 1326.50 1.26 7.43 8.59
216 N-135 N-134 10 11.91 125 115.7 UPVC 0.005 1326.50 1326.50 1.13 8.59 8.50
221 N-138 N-139 105 3.21 125 115.7 UPVC 0.005 1330.37 1326.50 0.31 6.12 9.89
222 N-139 N-140 12 3.26 125 115.7 UPVC 0.005 1326.50 1326.50 0.31 9.89 9.88
224 N-134 N-142 73 5.62 125 115.7 UPVC 0.005 1326.50 1325.62 0.53 8.50 9.20
225 N-142 N-143 27 5.23 125 115.7 UPVC 0.005 1325.62 1325.67 0.50 9.20 9.08
226 N-140 N-144 117 1.98 110 102 UPVC 0.005 1326.50 1325.71 0.24 9.88 10.59
227 N-144 N-146 58 1.18 110 102 UPVC 0.005 1325.71 1325.82 0.14 10.59 10.46
228 N-143 N-145 75 4.38 125 115.7 UPVC 0.005 1325.67 1325.82 0.42 9.08 8.81
Page 6 of 8
Hydraulic Calculation of Pilot Area
Alternative - II, Connection from Chabahil and Mitra park chowk
PIPES Node Length Flow Pipe Ground Elevation Velocity Pressure (m)
ID From To (m) (lps) O.D.(mm) I.D.(mm) Type Rough From To (m/s) From To
229 N-145 N-148 80 3.91 125 115.7 UPVC 0.005 1325.82 1325.86 0.37 8.81 8.67
230 N-148 N-149 20 3.27 125 115.7 UPVC 0.005 1325.86 1325.60 0.31 8.67 8.90
231 N-149 N-119 70 2.56 125 115.7 UPVC 0.005 1325.60 1324.84 0.24 8.90 9.62
232 N-119 N-121 25 1.67 125 115.7 UPVC 0.005 1324.84 1324.40 0.16 9.62 10.06
233 N-121 N-67 75 1.21 125 115.7 UPVC 0.005 1324.40 1321.13 0.12 10.06 13.31
235 N-146 N-184 85 0.55 90 83.2 UPVC 0.005 1325.82 1326.50 0.10 10.46 9.76
237 N-147 N-183 60 0.3 110 102 UPVC 0.005 1326.04 1326.50 0.04 8.08 7.62
238 N-66 N-122 25 4.56 125 115.7 UPVC 0.005 1321.13 1322.15 0.43 13.16 12.10
239 N-122 N-120 72 3.77 125 115.7 UPVC 0.005 1322.15 1324.40 0.36 12.10 9.76
240 N-120 N-147 200 1.32 125 115.7 UPVC 0.005 1324.40 1326.04 0.13 9.76 8.08
241 N-202 N-199 55 6.14 125 115.7 UPVC 0.005 1326.45 1326.09 0.58 8.78 8.97
242 N-199 16 85 5.69 125 115.7 UPVC 0.005 1326.09 1326.50 0.54 8.97 8.35
243 N-201 N-185 140 0.26 75 69.3 UPVC 0.005 1326.45 1326.50 0.07 9.05 8.97
244 N-202 N-208 130 15.38 140 129.5 UPVC 0.005 1326.45 1325.00 1.17 8.78 9.06
245 N-208 N-210 62 9.38 125 115.7 UPVC 0.005 1325.00 1319.45 0.89 9.06 14.22
246 N-210 N-215 110 8.71 110 102 UPVC 0.005 1319.45 1309.27 1.07 14.22 23.28
247 N-215 N-217 20 5.71 90 83.2 UPVC 0.005 1309.27 1307.92 1.05 23.28 24.37
248 N-217 N-221 175 1.68 90 83.2 UPVC 0.005 1307.92 1298.09 0.31 24.37 33.95
249 N-204 N-205 58 13.68 140 129.5 UPVC 0.005 1326.45 1326.43 1.04 8.79 8.39
250 N-205 55 70 12.76 125 115.7 UPVC 0.005 1326.43 1325.00 1.21 8.39 9.05
251 55 N-209 50 12.76 110 102 UPVC 0.005 1325.00 1319.45 1.56 9.05 13.58
262 N-209 N-211 52 7.62 110 102 UPVC 0.005 1319.45 1315.60 0.93 13.58 17.01
263 N-211 N-212 12 4.78 110 102 UPVC 0.005 1315.60 1315.00 0.58 17.01 17.57
264 N-212 N-214 30 4.65 110 102 UPVC 0.005 1315.00 1311.00 0.57 17.57 21.47
265 N-214 N-218 75 3.15 110 102 UPVC 0.005 1311.00 1304.92 0.39 21.47 27.42
266 N-218 N-219 30 2.72 90 83.2 UPVC 0.005 1304.92 1301.92 0.50 27.42 30.32
267 N-219 N-222 110 1.9 90 83.2 UPVC 0.005 1301.92 1298.09 0.35 30.32 33.96
281 N-140 N-141 30 0.89 125 115.7 UPVC 0.005 1326.50 1327.17 0.08 9.88 9.21
282 N-141 N-190 95 0.43 125 115.7 UPVC 0.005 1327.17 1329.88 0.04 9.21 6.50
283 N-191 N-139 120 0.76 125 115.7 UPVC 0.005 1329.72 1326.50 0.07 6.68 9.89
284 N-194 N-191 105 1.87 125 115.7 UPVC 0.005 1331.77 1329.72 0.18 4.67 6.68
285 N-195 110 105 2.12 125 115.7 UPVC 0.005 1331.77 1329.72 0.20 4.67 6.67
33 N-267 N-269 45 4.68 125 115.7 UPVC 0.005 1312.64 1306.37 0.45 20.04 26.23
34 N-269 N-270 10 4.44 125 115.7 UPVC 0.005 1306.37 1305.37 0.42 26.23 27.21
35 N-270 N-271 15 4.31 125 115.7 UPVC 0.005 1305.37 1304.37 0.41 27.21 28.18
36 N-271 N-273 10 2.81 110 102 UPVC 0.005 1304.37 1303.62 0.34 28.18 28.92
37 N-268 N-272 70 5.09 110 102 UPVC 0.005 1312.64 1304.37 0.62 20.20 28.20
38 N-272 N-277 135 2.49 110 102 UPVC 0.005 1304.37 1302.00 0.31 28.20 30.42
39 N-273 N-276 140 2.27 110 102 UPVC 0.005 1303.62 1301.85 0.28 28.92 30.56
40 N-277 N-276 25 0.42 75 69.3 UPVC 0.005 1302.00 1301.85 0.11 30.42 30.56
41 N-297 N-266 30 7.91 125 115.7 UPVC 0.005 1318.81 1316.40 0.75 14.10 16.37
42 N-266 N-267 45 5.01 125 115.7 UPVC 0.005 1316.40 1312.64 0.48 16.37 20.04
43 N-298 N-268 130 8.08 125 115.7 UPVC 0.005 1323.27 1312.64 0.77 10.20 20.20
44 N-299 N-298 35 12.7 125 115.7 UPVC 0.005 1325.25 1323.27 1.21 8.60 10.20
52 N-332 N-336 120 4.86 125 115.7 UPVC 0.005 1331.96 1331.05 0.46 4.59 5.27
53 N-336 N-307 30 7.73 110 102 UPVC 0.005 1331.05 1330.93 0.95 5.27 5.14
54 N-307 N-310 80 3.87 110 102 UPVC 0.005 1330.93 1329.90 0.47 5.14 5.98
55 N-337 N-306 50 16.48 140 129.5 UPVC 0.005 1331.05 1330.59 1.25 5.26 5.21
56 N-306 N-314 95 2.01 110 102 UPVC 0.005 1330.59 1328.00 0.25 5.21 7.74
57 N-310 N-316 60 5.91 110 102 UPVC 0.005 1329.90 1327.15 0.72 5.98 8.43
11 N-203 N-204 15 8.42 140 129.5 UPVC 0.005 1326.45 1326.45 0.64 8.84 8.79
58 N-316 15 25 1.65 90 83.2 UPVC 0.005 1327.15 1326.80 0.30 8.43 8.74
60 15 N-201 45 1.47 90 83.2 UPVC 0.005 1326.80 1326.45 0.27 8.74 9.05
69 N-315 14 50 8.89 140 129.5 UPVC 0.005 1328.00 1326.80 0.67 7.60 8.63
70 14 N-203 45 8.7 140 129.5 UPVC 0.005 1326.80 1326.45 0.66 8.63 8.84
147 N-314 N-303 110 1.5 75 69.3 UPVC 0.005 1328.00 1329.60 0.40 7.74 5.83
148 N-315 N-311 40 14.42 140 129.5 UPVC 0.005 1328.00 1328.99 1.09 7.60 6.28
149 N-311 N-301A 70 13.75 140 129.5 UPVC 0.005 1328.99 1329.60 1.04 6.28 5.16
151 11 N-66 5 15.85 110 102 UPVC 0.005 1321.13 1321.13 1.94 13.31 13.16
152 11 N-67 5 1.21 110 102 UPVC 0.005 1321.13 1321.13 0.15 13.31 13.31
153 12 N-68 10 13.04 110 102 UPVC 0.005 1323.00 1323.00 1.60 10.11 9.89
155 N-334 N-335 70 6.35 140 129.5 UPVC 0.005 1331.96 1331.50 0.48 4.55 4.88
160 N-335 N-337 50 5.18 140 129.5 UPVC 0.005 1331.50 1331.05 0.39 4.88 5.26
162 18 N-204 5 6.47 200 200 D.I. 0.085 1326.45 1326.45 0.21 8.80 8.79
163 18 N-202 5 22.19 200 200 D.I. 0.085 1326.45 1326.45 0.71 8.80 8.78
164 58 18 5 28.66 200 200 D.I. 0.085 1326.45 1326.45 0.91 8.82 8.80
165 N-304 N-299 98 20.92 140 129.5 UPVC 0.005 1329.60 1325.25 1.59 5.79 8.60
9 N-301A N-297 180 12.28 125 115.7 UPVC 0.005 1329.60 1318.81 1.17 5.16 14.10
16 N-83 85 5 5.25 200 200 D.I. 0.085 1325.90 1325.90 0.17 8.53 8.53
45 N-332 N-331 32 0.6 90 83.2 UPVC 0.005 1331.96 1332.00 0.11 4.59 4.54
46 N-331 N-329 119 0.69 75 69.3 UPVC 0.005 1332.00 1332.10 0.18 4.54 4.36
48 N-195 N-330 94 0.24 75 69.3 UPVC 0.005 1331.77 1332.10 0.06 4.67 4.33
49 N-194 N-195 11 0.58 75 69.3 UPVC 0.005 1331.77 1331.77 0.15 4.67 4.67
50 N-138 N-194 174 0.41 75 69.3 UPVC 0.005 1330.37 1331.77 0.11 6.12 4.67
51 N-122 N-123A 30 0.41 75 69.3 UPVC 0.005 1322.15 1320.00 0.11 12.10 14.24
64 1 N-128 165 4 90 83.2 UPVC 0.005 1330.37 1329.49 0.74 6.13 5.91
77 N-128 N-101 205 1.98 75 69.3 UPVC 0.005 1329.49 1326.26 0.53 5.91 8.19
Page 7 of 8
Hydraulic Calculation of Pilot Area
Alternative - II, Connection from Chabahil and Mitra park chowk
PIPES Node Length Flow Pipe Ground Elevation Velocity Pressure (m)
ID From To (m) (lps) O.D.(mm) I.D.(mm) Type Rough From To (m/s) From To
80 N-303 N-304 5 15.06 140 129.5 UPVC 0.005 1329.60 1329.60 1.14 5.83 5.79
47 N-23 N-23A 55 0.2 75 69.3 UPVC 0.005 1297.30 1298.00 0.05 30.02 29.31
81 N-25 N-25A 65 0.2 75 69.3 UPVC 0.005 1296.69 1297.25 0.05 30.77 30.21
82 N-21 N-21A 45 0.8 75 69.3 UPVC 0.005 1296.81 1297.00 0.21 30.45 30.22
100 N-64 N-64A 75 0.53 75 69.3 UPVC 0.005 1311.53 1311.29 0.14 21.72 21.93
134 N-154 N-154A 55 0.64 75 69.3 UPVC 0.005 1310.00 1310.00 0.14 21.66 21.63
135 N-131 N-131A 100 0.35 75 69.3 UPVC 0.005 1329.57 1329.02 0.09 5.95 6.48
136 N-132 N-132A 35 0.41 75 69.3 UPVC 0.005 1329.89 1329.23 0.11 5.97 6.61
137 N-136 N-136A 53 0.3 75 69.3 UPVC 0.005 1328.26 1328.10 0.08 7.43 7.58
138 N-124 N-124A 115 0.25 75 69.3 UPVC 0.005 1326.12 1326.00 0.07 8.58 8.69
145 N-73 N-73A 100 0.25 75 69.3 UPVC 0.005 1324.75 1325.00 0.07 9.62 9.35
146 N-127 N-127A 75 0.21 75 69.3 UPVC 0.005 1326.21 1326.00 0.06 8.57 8.77
150 N-133 N-133A 30 0.2 75 69.3 UPVC 0.005 1326.40 1326.00 0.05 8.52 8.91
154 N-142 N-142A 35 0.2 75 69.3 UPVC 0.005 1325.62 1325.00 0.05 9.20 9.81
158 N-149 N-149A 70 0.4 75 69.3 UPVC 0.005 1325.60 1326.55 0.11 8.90 7.93
159 N-180 N-180A 75 0.7 75 69.3 UPVC 0.005 1325.66 1324.53 0.19 8.12 9.20
161 N-170 N-170A 85 0.23 75 69.3 UPVC 0.005 1309.02 1309.00 0.06 22.72 22.74
166 N-223 N-223A 50 0.34 75 69.3 UPVC 0.005 1300.00 1300.00 0.09 32.06 32.05
167 N-190C N-190CA 80 0.2 75 69.3 UPVC 0.005 1329.07 1329.00 0.05 7.27 7.33
168 N-260 N-260A 55 0.61 75 69.3 UPVC 0.005 1317.47 1317.00 0.16 15.08 15.52
169 N-288 N-288A 60 0.4 75 69.3 UPVC 0.005 1306.76 1306.00 0.11 24.97 25.71
170 N-290 N-290A 100 0.4 75 69.3 UPVC 0.005 1307.90 1307.00 0.11 24.25 25.12
171 N-270 N-270A 40 0.08 75 69.3 UPVC 0.005 1305.37 1305.00 0.02 27.21 27.57
172 N-352 N-352A 60 0.11 75 69.3 UPVC 0.005 1317.40 1317.00 0.03 15.51 15.91
174 N-335 N-335A 75 0.67 75 69.3 UPVC 0.005 1331.50 1331.25 0.18 4.88 5.08
Page 8 of 8
TA 4893-NEP
Detailed Design Report
APPENDIX 3
S. Rate or Avg.
Description of Items Qty Unit Unit Total Cost (NRs.)
No. Rate
A Preliminary Items 1 Job 3,692,585.00 Job 3,692,585.00
B Provisional Item 1 Job 6,973,064.00 Job 6,973,064.00
C Civil Works
1 Pipeline Trench Excavation & Backfilling 1.0 Set 10,268,388.88 No. 10,268,388.88
2 Pipe Cost 1.0 Set 22,563,795.64 No. 22,563,795.64
3 Fittings 1.0 Set 9,952,215.36 Set 9,952,215.36
4 Dismantling Works 1.0 Job 7,002,874.17 Job 7,002,874.17
5 Main Tapping Chambers (at Two Chowks 1.5 mx 2.5m) 8.0 No. 219,230.48 No. 1,753,843.83
6 Valve Chambers (2.25mx2.25m) 2.0 No. 236,115.53 No. 472,231.05
7 Valve and Washout Chambers (1.5mx1.5m) 14.0 No. 147,652.93 No. 2,067,140.98
8 Valve and Washout Chambers (1.0mx2.0m) 8.0 No. 181,240.15 No. 1,449,921.17
9 Air Chambers (1.0mx1.0m) 10.0 No. 108,020.45 No. 1,080,204.46
10 Pipe Valve Box 8.0 No. 3,397.88 Set 27,183.04
11 Fire Hydrant 10.0 Nos. 25,000.00 Nos. 250,000.00
12 Temporary Re-sealing of the Black topped Road 20,381.6 Sq.m 1,577.84 Sq.m 32,158,903.74
13 Re-instate of the Gravel Road 2,705.6 Sq.m 650.62 Sq.m 1,760,317.47
14 Re-instate of the Brick Pavement 1,569.6 Sq.m 1,516.92 Sq.m 2,380,957.63
15 Re-instate of the Flag Stone Pavement 1,454.4 Sq.m 1,602.08 Sq.m 2,330,065.15
16 Re-instate of the Interlocking Block Pavement 64.0 Sq.m 1,105.45 Sq.m 70,748.80
17 Re-instate of the Concrete Pavement 48.0 Sq.m 1,039.93 Sq.m 49,916.64
18 Thrust Block 45.0 Cu.m 8,609.87 Cu.m 387,444.15
19 House Connections 4,800 No 7,729.61 No 37,102,136.16
20 Miscelleneous Work 1 Job 8,379,430.00 Job 8,379,430.00
Sub-Total (A+B+C) 152,173,367.33
D Contingencies for workchart staff and small miscelleneous expenses 5% 7,608,668.37
E Sub total including workchart staff and small miscelleneous expenses 159,782,035.70
F Contingencies for price adjustment 10% 15,978,203.57
G Physical contingencies 10% 15,978,203.57
H Sub total including contingencies 191,738,442.84
I Value Added Taxes (VAT) 13% 24,925,997.57
J Total Estimated Amount (NRS) 216,664,440.41
COST ESTIMATE
Preliminary and General Works
Item Description of Works Quantity Unit Rate Amount
No. (NRs.) (NRs.)
Included in Unit
1 Material and construction testing and quality control programme
Price
2 Site Photographic Records 840 Nos 15 12,600.00
3 Engineer's Site Office
Provide furnishing of Site Office for the Engineer or his representative at
3.1 1 LS 150,000.00 150,000.00
Work Site with furniture and equipped as specified.
Maintain the Engineer's Site Offices (Service for the Engineer),
equipments, office premises, with payment of rents, fee and charges for
3.2 services, provision of one cleaner, peon or guard in a office including 14 months 70,000.00 980,000.00
regular supply of stationary and office consumables as per Technical
Specification
4 Supply of Vehicles
Provide following vehicles with fuel, lubricant and including maintenance
during construction period on monthly cost basis for Engineer or his staffs
4.1 Four Wheel Drive Jeep at least 2300 CC with driver. (One Nos.) 14 months 80,000.00 1,120,000.00
4.2 Motorbikes of at least 110 CC (2 Nos) 28 months 5,000.00 140,000.00
4.3 Vehicle Operation (including fuel, lubricant & maintenance) 14 months 16,427.50 229,985.00
5 Survey Assistance and Equipments
Provide Survey equipments and manpower for verification of
topographical survey and executive design of Pipe network and other 1 Job 150,000.00 150,000.00
related structures.
6 Construction Safety Equipments
Provide Safety equipments for the Engineer at site office of type and
14 months 5,000.00 70,000.00
number specified in Technical Specification for the contract period.
7 Performance Security and Insurance
7.1 Provide insurance to permanent works 0.20 % LS 160,000,000.00 320,000.00
7.2 Provide insurance to plant, equipment and vehicles 0.10 % LS 160,000,000.00 160,000.00
7.3 Provide third party insurance 0.10 % LS 160,000,000.00 160,000.00
8 Others
Preparing GIS Data base and as built-drawings locating newly laid
8.1 pipes, house connection points, existing pipe lines, sewerage 1.00 LS 200,000.00 200,000.00
connection, etc.
Included in Unit
8.2 Prepare and undertake the Environmental Management Plan.
Price
Total Amount 3,692,585.00
COST ESTIMATE
Provisional Items
1 Temporary provision of water supply for the disconnected pipelines 2700 Cu.m 120 324,000.00
Provide canopy type Mobile Diesel Generator Set (not having less
than 5KV ) with necessary accessories lamps, lamp stands and
5 cables, fuel, lubricant, generator operator including maintenance 50 Night 4000 200,000.00
during construction period on daily cost basis for illumination of
stretches during Night-shift construction as per specification.
6 Permanent reinstatement of asphalt roads during DLP 2000 Sqm 927.22 1,854,440.00
7 Diversion of utilities and provision of temporary services
Provide payments to other statutory undertakers for diverting
7.1 1 LS 1000000 1,000,000.00
electricity, telecommunication and other services
I. uPVC FITTINGS
REDUCER
Reducer (90 x 75) 119.00 No. 87.66 8.77 96.43 11,475.17
Reducer (110 x 75) 3.00 No. 87.66 8.77 96.43 289.29
Reducer (110 x 90) 97.00 No. 113.96 11.4 125.36 12,159.92
Reducer (125 x 90) 3.00 No. 148.15 14.82 162.97 488.91
Reducer (125 x 110) 50.00 No. 192.60 19.26 211.86 10,593.00
Reducer (140 x 110) 2.00 No. 350.00 35 385.00 770.00
Reducer (140 x 125) 25.00 No. 350.00 35 385.00 9,625.00
CROSS
Cross 75 mm 2.00 No. 282.90 28.29 311.19 622.38
Cross 90 mm 1.00 No. 371.56 37.16 408.72 408.72
Cross 110 mm 6.00 No. 460.22 46.02 506.24 3,037.44
Cross 125 mm 3.00 No. 644.31 64.43 708.74 2,126.22
Cross 140 mm 3.00 No. 1288.62 128.86 1417.48 4,252.44
UN-EQUAL TEE
UN-Equal Tee 90x75 mm 43.00 No. 176.40 17.64 194.04 8,343.72
UN-Equal Tee 110x90 mm 4.00 No. 294.00 29.4 323.40 1,293.60
UN-Equal Tee 110x75 mm 13.00 No. 294.00 29.4 323.40 4,204.20
UN-Equal Tee 125x90 mm 2.00 No. 490.00 49 539.00 1,078.00
UN-Equal Tee 125x75 mm 11.00 No. 490.00 49 539.00 5,929.00
UN-Equal Tee 140x125 mm 5.00 No. 700.00 70 770.00 3,850.00
UN-Equal Tee 140x75 mm 4.00 No. 700.00 70 770.00 3,080.00
All (EQUAL) TEE
Equal Tee 75 mm 62.00 No. 94.71 9.47 104.18 6,459.16
Equal Tee 90 mm 91.00 No. 176.40 17.64 194.04 17,657.64
Equal Tee 110 mm 36.00 No. 294.00 29.4 323.40 11,642.40
Equal Tee 125 mm 31.00 No. 490.00 49 539.00 16,709.00
Equal Tee 140 mm 12.00 No. 700.00 70 770.00 9,240.00
ELBOW
Elbow 75 mm 7.00 No. 72.33 7.23 79.56 556.92
Elbow 90 mm 18.00 No. 120.54 12.05 132.59 2,386.62
Elbow 110 mm 7.00 No. 120.64 12.06 132.70 928.90
Elbow 125 mm 7.00 No. 168.90 16.89 185.79 1,300.53
Elbow 140 mm 5.00 No. 236.46 23.65 260.11 1,300.55
Y-BRANCH
Y 140 mm 1.00 No. 1470.00 147 1617.00 1,617.00
NIPPLE
Nipple 75 mm 10.00 No. 89.27 8.93 98.20 982.00
Nipple 90 mm 125.00 No. 128.99 12.9 141.89 17,736.25
Nipple 110 mm 96.00 No. 187.00 18.7 205.70 19,747.20
Nipple 125 mm 57.00 No. 248.15 24.82 272.97 15,559.29
Nipple 140 mm 27.00 No. 308.89 30.89 339.78 9,174.06
BEND
DN 75 BEND OF 22.50 20.00 No. 58.54 5.85 64.39 1,287.80
0
DN 75 BEND OF 45 20.00 No. 58.54 5.85 64.39 1,287.80
DN 90 BEND OF 22.50 15.00 No. 79.21 7.92 87.13 1,306.95
0
DN 90 BEND OF 45 15.00 No. 79.21 7.92 87.13 1,306.95
DN 110 BEND OF 22.50 8.00 No. 99.87 9.99 109.86 878.88
0
DN 110 BEND OF 45 6.00 No. 99.87 9.99 109.86 659.16
1/3
COST ESTIMATE
PIPE FITTINGS
S.No. DESCRIPTION OF ITEM Quantity Unit Rate (NRs.) Amount
Material Fitting Total (NRs.)
MALE THREADED ADOPTER WITH THREADED FLANGE
Flange Set 65 mm 15.00 Set 1141.00 114.1 1255.10 18,826.50
Flange Set 80 mm 14.00 Set 1349.00 134.9 1483.90 20,774.60
Flange Set 100 mm 11.00 Set 1703.00 170.3 1873.30 20,606.30
Flange Set 125 mm 30.00 Set 1873.30 187.33 2060.63 61,818.90
Flange Set 140 mm 1.00 Set 2060.63 206.06 2266.69 2,266.69
END CAP
End Cap of 75mm Dia. 94.00 No. 120.00 12.00 132.00 12,408.00
End Cap of 90mm Dia. 8.00 No. 160.00 16.00 176.00 1,408.00
End Cap of 110mm Dia. 3.00 No. 300.00 30.00 330.00 990.00
MECHANICAL COUPLING WITH RUBBER RINGS (MC)
MC 75 mm 36.00 Set 1141.00 114.10 1255.10 45,183.60
MC 90 mm 30.00 Set 1349.00 134.90 1483.90 44,517.00
MC 110 mm 19.00 Set 1703.00 170.30 1873.30 35,592.70
MC 125 mm 19.00 Set 2043.60 204.36 2247.96 42,711.24
MC 140 mm 12.00 Set 2452.32 245.23 2697.55 32,370.60
II. D.I. FITTINGS
DI FLANGED SOCKET
DN 350 2.00 No. 42225.00 1698.52 43923.52 87,847.04
DN 300 4.00 No. 34627.13 1330.12 35957.25 143,829.00
DN 250 1.00 No. 27029.25 1051.50 28080.75 28,080.75
DN 200 1.00 No. 16875.75 792.76 17668.51 17,668.51
DN 150 1.00 No. 11391.00 622.27 12013.27 12,013.27
FLANGED CROSS WITH FLANGED BRANCH
DN 350 x 350 x 200 x 200 1.00 No. 69242.00 1698.52 70940.52 70,940.52
DN 200 x 200 x 125 x 125 1.00 No. 24393.00 792.76 25185.76 25,185.76
DOUBLE FLANGED TEE WITH FLANGED BRANCH
DN 600 x 600 x 350 2.00 No. 116845.00 5732.51 122577.51 245,155.02
DN 300 x 300 x 200 4.00 No. 23081.00 1330.12 24411.12 97,644.48
DN 200 x 200 x 200 4.00 No. 12197.00 792.76 12989.76 51,959.04
DN 200 x 200 x 150 1.00 No. 12197.00 792.76 12989.76 12,989.76
DN 200 x 200 x 125 7.00 No. 12197.00 792.76 12989.76 90,928.32
DN 200 x 200 x 100 1.00 No. 12197.00 792.76 12989.76 12,989.76
DN 200 x 200 x 80 2.00 No. 12197.00 792.76 12989.76 25,979.52
DN 200 x 200 x 65 1.00 No. 12197.00 792.76 12989.76 12,989.76
DN 150 x 150 x 150 3.00 No. 10478.00 622.27 11100.27 33,300.81
DN 150 x 150 x 125 2.00 No. 10478.00 622.27 11100.27 22,200.54
DN 150 x 150 x 100 1.00 No. 10478.00 622.27 11100.27 11,100.27
DN 150 x 150 x 80 1.00 No. 10478.00 622.27 11100.27 11,100.27
DN 150 x 150 x 65 1.00 No. 10478.00 622.27 11100.27 11,100.27
DOUBLE FLANGED CONCENTRIC TAPER
DN 350 x 300 4.00 No. 57134.00 1698.52 58832.52 235,330.08
DN 300 x 250 2.00 No. 31640.00 1330.12 32970.12 65,940.24
DN 250 x 200 2.00 No. 14699.00 1051.50 15750.50 31,501.00
DN 200 x 150 3.00 No. 9307.00 792.76 10099.76 30,299.28
DN 200 x 100 2.00 No. 9307.00 792.76 10099.76 20,199.52
DN 200 x 125 6.00 No. 9307.00 792.76 10099.76 60,598.56
DN 150 x 125 6.00 No. 6348.00 622.27 6970.27 41,821.62
2/3
COST ESTIMATE
PIPE FITTINGS
S.No. DESCRIPTION OF ITEM Quantity Unit Rate (NRs.) Amount
Material Fitting Total (NRs.)
SINGLE FLANGED TAIL PIECE
Single Flanged Tail Piece DI 600 8.00 No. 25200.00 5095.56 30295.56 242,364.48
Single Flanged Tail Piece DI 350 8.00 No. 18300.00 1698.52 19998.52 159,988.16
Single Flanged Tail Piece DI 300 8.00 No. 15750.00 1330.12 17080.12 136,640.96
Single Flanged Tail Piece DI 250 3.00 No. 12300.00 1051.50 13351.50 40,054.50
Single Flanged Tail Piece DI 200 50.00 No. 9300.00 792.76 10092.76 504,638.00
Single Flanged Tail Piece DI 150 17.00 No. 6750.00 622.27 7372.27 125,328.59
DI MECHANICAL COUPLING WITH RUBBER RINGS
DN 600 6.00 No. 128678.00 5733 134410.51 806,463.06
DN 350 8.00 No. 47902.00 1698.52 49600.52 396,804.16
DN 300 7.00 No. 16438.00 1330.12 17768.12 124,376.84
DN 250 7.00 No. 11029.00 1051.50 12080.50 84,563.50
DN 200 57.00 No. 11441.00 792.76 12233.76 697,324.32
DN 150 23.00 No. 9170.00 622.27 9792.27 225,222.21
DI DOUBLE FLANGED BEND WITH RUBBER GASKETS
DN 150 BEND OF 11.250 2.00 No. 5749.50 622.27 6371.77 12,743.54
0
DN 150 BEND OF 22.5 1.00 No. 5749.50 622.27 6371.77 6,371.77
0
DN 150 BEND OF 45 1.00 No. 5749.50 622.27 6371.77 6,371.77
DN 150 BEND OF 900 1.00 No. 5749.50 622.27 6371.77 6,371.77
DN 200 BEND OF 11.250 4.00 No. 9351.00 792.76 10143.76 40,575.04
DN 200 BEND OF 22.50 3.00 No. 9351.00 792.76 10143.76 30,431.28
0
DN 200 BEND OF 45 2.00 No. 9351.00 792.76 10143.76 20,287.52
0
DN 200 BEND OF 90 1.00 No. 9351.00 792.76 10143.76 10,143.76
DN 250 BEND OF 11.250 2.00 No. 14811.00 1051.50 15862.50 31,725.00
DN 250 BEND OF 22.50 1.00 No. 14811.00 1051.50 15862.50 15,862.50
DN 250 BEND OF 450 1.00 No. 14811.00 1051.50 15862.50 15,862.50
0
DN 250 BEND OF 90 1.00 pc 14811.00 1051.50 15862.50 15,862.50
0
DN 300 BEND OF 11.25 1.00 pc 25167.75 1330.12 26497.87 26,497.87
DN 300 BEND OF 22.50 1.00 No. 25167.75 1330.12 26497.87 26,497.87
DN 350 BEND OF 11.250 1.00 No. 37751.63 1698.52 39450.15 39,450.15
0
DN 350 BEND OF 45 5.00 No. 37751.63 1698.52 39450.15 197,250.75
III VALVES
AIR VALVE
Air Valve 50mm (single Orifice) 10.00 No. 35160.00 242.79 35402.79 354,027.90
3/3
COST ESTIMATE
Chambers (Per Unit Cost)
S. Description of Works Unit Unit Rate Per Unit Cost
No. Quantity (NRs.) (NRs.)
A MAIN CHAMBERS At INLET POINTS (1.5m x 2.5m)
1 Earthwork in Excavation 63.740 Cu.m. 260.59 16,610.01
2 Earth Work in Back Filling 25.500 Cu.m. 162.87 4,153.19
3 Flat Brick Soling 11.030 Sq.m. 537.21 5,925.43
4 M-10 Grade Concreting Work for Lean Concrete in Foundation 1.110 Cu.m. 7325.36 8,131.15
5 M-20 Grade Concreting Work for RCC 6.630 Cu.m. 10572.21 70,093.75
6 Formwork 44.830 Sq.m. 429.28 19,244.62
7 Reinforcement Bar for RCC 769.000 Kg 85.72 65,918.68
8 12.5 mm thick cement plaster in 1:4 C/M 34.340 Sq.m. 208.02 7,143.41
9 Safety Iron Rung 7.000 Sets 200.00 1,400.00
10 Manhole Cover (28")of Locable Arrangments 1.000 Sets 17566.25 17,566.25
11 250 mm thick Plain G.I. Sheet of 16 to 18 SWG water-stopper 22.000 m 102.00 2,244.00
12 Valve Operating Cast Iron Cap with Frame 2.000 Nos. 400.00 800.00
Sub Total 219,230.48
1/2
COST ESTIMATE
Chambers (Per Unit Cost)
S. Description of Works Unit Unit Rate Per Unit Cost
No. Quantity (NRs.) (NRs.)
D VALVE And WASHOUT CHAMBER (1.0m x2.0m)
1 Earthwork in Excavation 50.990 Cu.m. 260.59 13,287.48
2 Earth Work in Back Filling 20.400 Cu.m. 162.87 3,322.55
3 Flat Brick Soling 9.840 Sq.m. 537.21 5,286.15
4 M-10 Grade Concreting Work for Lean Concrete in Foundation 0.980 Cu.m. 7325.36 7,178.85
5 M-20 Grade Concreting Work for RCC 4.220 Cu.m. 10572.21 44,614.73
6 Formwork 33.320 Sq.m. 429.28 14,303.61
7 Reinforcement Bar for RCC 569.000 Kg 85.72 48,774.68
8 12.5 mm thick cement plaster in 1:4 C/M 26.840 Sq.m. 208.02 5,583.26
9 Safety Iron Rung 7.000 Set 200.00 1,400.00
10 Manhole Cover (28")of Locable Arrangments 1.000 Set 17566.25 17,566.25
11 250 mm thick Plain G.I. Sheet of 16 to 18 SWG water-stopper 17.000 m 102.00 1,734.00
12 Valve Operating Cast Iron Cap with Frame 2.000 Nos. 400.00 800.00
13 Brick Work in 1:4 C/S 2.050 Cu.m. 8482.24 17,388.59
Sub Total 181,240.15
2/2
COST ESTIMATES
Road Re-instatement and Re-sealing
Total 7,002,874.17
COST ESTIMATES
House Connection (With UPVC Pipe) Total Number of Connection = 4800
S. Description of Works Unit Unit Rate Per Unit Cost Total Total Cost
No. Quantity (NRs.) (NRs.) Quantity (NRs.)
1/1
COST ESTIMATE
PIPES (Material & Laying Cost)
B DI PIPES
Designed 350 mm Dia. DI Pipe 132.00 Mts. 9177.70 293.29 9470.99 1,250,170.68
Designed 300 mm Dia. DI Pipe 77.00 Mts. 7829.12 211.61 8040.73 619,136.21
Designed 250 mm Dia. DI Pipe 184.00 Mts. 6117.20 168.25 6285.45 1,156,522.80
Designed 200 mm Dia. DI Pipe 1262.00 Mts. 4635.90 125.49 4761.39 6,008,874.18
Designed 150 mm Dia. DI Pipe 766.00 Mts. 3418.41 104.73 3523.14 2,698,725.24
Sub total 2421.00 Mts. 11,733,429.11
1/1
COST ESTIMATE
Miscelleneous Works
S. Description of Works Unit Unit Rate Per Unit Cost
No. Quantity (NRs.) (NRs.)
APPENDIX 4
Quantity Estimations
QUANTITY ESTIMATES
TRENCH EXCAVATION & BACKFILLING FOR PIPE LAYING
DI PIPE
DI Pipe of 350 mm Dia. 1 120.00 0.90 1.00 10.80 108.00
DI Pipe of 300 mm Dia. 1 70.00 0.90 1.00 6.30 63.00
DI Pipe of 250 mm Dia. 1 167.00 0.90 1.00 15.03 150.30
DI Pipe of 200 mm Dia. 1 1147.00 0.60 1.00 68.82 688.20
DI Pipe of 150 mm Dia. 1 696.00 0.60 1.00 41.76 417.60
Sub Total = 2200.00 1427.10
Total Excavation = 32779.00 17939.76
4 M 10 Cement Concrete work for PCC 1 1.760 1.760 0.100 0.31 Cu.m
6 Formwork
Foundation 1 7.040 0.300 2.11
Outer side of Wall 1 5.440 2.200 11.97
Inner side of wall 1 4.000 2.000 8.00
bottom face of Slab 1 1.000 1.000 1.00
Total 23.08 Sq.m.
7 Reinforcement
12 Dia. M Bar in Base Slab in S. Dir. (Top) 7 2.560 Unit Wt. 0.899 16.11
12 Dia. M Bar in Base Slab in S. Dir. (Bot) 7 2.560 Unit Wt. 0.899 16.11
12 Dia. D Bar in Base Slab in Long Dir. (Both Face) 14 2.560 Unit Wt. 0.899 32.22
12 Dia. Vertical Wall (Long) in Earth face 12 3.060 Unit Wt. 0.899 33.01
12 Dia. Vertical Wall (Long) in Water face 12 2.600 Unit Wt. 0.899 28.05
12 Dia. Vertical Wall (Short) in Earth face 12 3.060 Unit Wt. 0.899 33.01
12 Dia. Vertical Wall (Short) in Water face 12 2.600 Unit Wt. 0.899 28.05
12 Dia Horizontal Bar 8 10.880 Unit Wt. 0.899 78.25
12 Dia. Main Bar in Roof Slab 6 2.740 Unit Wt. 0.899 14.78
12 Dia. Mainor Bar in Roof Slab 6 2.740 Unit Wt. 0.899 14.78
12 Dia Chair Bar 20 1.300 Unit Wt. 0.899 23.37
Extra for Lapping, Chair, etc. 20% 63.55
Total 381.00 Kgs.
9 Plaster (1:4) 12.5mm
Wall of Main Chamber 1 Same as Inner Form Work 8.00
Base of Main Chamber 1 1.000 1.000 1.00
Total 9.00 Sq.m
1 E/W in Excavation
Main Chamber 1 4.960 3.960 2.350 46.16
Outlet Structure 1 2.110 2.110 0.600 2.67
Outlet pipe 1 9.000 0.400 0.600 2.16
Total 50.99 Cu.m
7 Reinforcement
12 Dia. M Bar in Base Slab in S. Dir. (Top) 12 2.760 Unit Wt. 0.899 29.77
12 Dia. M Bar in Base Slab in S. Dir. (Bot) 18 2.760 Unit Wt. 0.899 44.66
12 Dia. D Bar in Base Slab in Long Dir. (Both Face) 18 3.760 Unit Wt. 0.899 60.84
12 Dia. Vertical Wall (Long) in Earth face 18 3.060 Unit Wt. 0.899 49.52
12 Dia. Vertical Wall (Long) in Water face 18 2.700 Unit Wt. 0.899 43.69
12 Dia. Vertical Wall (Short) in Earth face 12 3.060 Unit Wt. 0.899 33.01
12 Dia. Vertical Wall (Short) in Water face 12 2.700 Unit Wt. 0.899 29.13
12 Dia Horizontal Bar 8 14.880 Unit Wt. 0.899 107.02
12 Dia. Main Bar in Roof Slab 10 2.740 Unit Wt. 0.899 24.63
12 Dia. Mainor Bar in Roof Slab 5 4.240 Unit Wt. 0.899 19.06
12 Dia Chair Bar 28 1.300 Unit Wt. 0.899 32.72
Extra for Lapping, Chair, etc. 20% 94.81
Total 569.00 Kgs.
8 Plaster (1:4) 12.5 mm thk
Wall of Tank Same as Inner Form Work 12.00
Base & Celing of Tank 2 2.000 1.000 4.00
Other 4 1.000 3.960 15.84
Total 31.84 Sq.m
4 M 10 Cement Concrete work for PCC 1 2.460 2.460 0.100 0.61 Cu.m
7 Reinforcement
12 Dia. M Bar in Base Slab in S. Dir. (Top) 13 3.260 Unit Wt. 0.899 38.10
12 Dia. M Bar in Base Slab in S. Dir. (Bot) 10 3.260 Unit Wt. 0.899 29.31
12 Dia. D Bar in Base Slab in Long Dir. (Both Face) 20 3.260 Unit Wt. 0.899 58.61
12 Dia. Vertical Wall (Long) in Earth face 16 2.760 Unit Wt. 0.899 39.70
12 Dia. Vertical Wall (Long) in Water face 14 2.400 Unit Wt. 0.899 30.21
12 Dia. Vertical Wall (Short) in Earth face 14 2.760 Unit Wt. 0.899 34.74
12 Dia. Vertical Wall (Short) in Water face 16 2.400 Unit Wt. 0.899 34.52
12 Dia Horizontal Bar 8 14.880 Unit Wt. 0.899 107.02
12 Dia. Main Bar in Roof Slab 8 3.490 Unit Wt. 0.899 25.10
12 Dia. Mainor Bar in Roof Slab 8 3.490 Unit Wt. 0.899 25.10
12 Dia Chair Bar 36 1.300 Unit Wt. 0.899 42.07
Extra for Lapping, Chair, etc. 20% 92.90
Total 557.00 Kgs.
1 E/W in Excavation
Main Chamber 1 5.500 4.500 2.380 58.91
Outlet Structure 1 2.110 2.110 0.600 2.67
Outlet pipe 1 9.000 0.400 0.600 2.16
Total 63.74 Cu.m
7 Reinforcement
12 Dia. M Bar in Base Slab in S. Dir. (Top) 14 3.360 Unit Wt. 0.899 42.29
12 Dia. M Bar in Base Slab in S. Dir. (Bot) 18 3.360 Unit Wt. 0.899 54.37
12 Dia. D Bar in Base Slab in Long Dir. (Both Face) 20 4.360 Unit Wt. 0.899 78.39
12 Dia. Vertical Wall (Long) in Earth face 22 3.090 Unit Wt. 0.899 61.11
12 Dia. Vertical Wall (Long) in Water face 22 2.730 Unit Wt. 0.899 53.99
12 Dia. Vertical Wall (Short) in Earth face 14 3.090 Unit Wt. 0.899 38.89
12 Dia. Vertical Wall (Short) in Water face 14 2.730 Unit Wt. 0.899 34.36
12 Dia Horizontal Bar 8 19.200 Unit Wt. 0.899 138.09
12 Dia. Main Bar in Roof Slab 13 3.550 Unit Wt. 0.899 41.49
12 Dia. Mainor Bar in Roof Slab 7 5.050 Unit Wt. 0.899 31.78
12 Dia Chair Bar 54 1.360 Unit Wt. 0.899 66.02
Extra for Lapping, Chair, etc. 20% 128.16
Total 769.00 Kgs.
8 Plaster (1:4) 12.5 mm thk
Wall of Tank Same as Inner Form Work 16.00
Base & Celing of Tank 2 2.500 1.500 7.50
Other 4 1.000 2.710 10.84
Total 34.34 Sq.m
4 M 10 Cement Concrete work for PCC 1 3.250 3.250 0.100 1.06 Cu.m
7 Reinforcement
12 Dia. M Bar in Base Slab in S. Dir. (Top) 29 4.110 Unit Wt. 0.899 107.15
12 Dia. M Bar in Base Slab in S. Dir. (Bot) 13 4.110 Unit Wt. 0.899 48.03
12 Dia. D Bar in Base Slab in Long Dir. (Both Face) 26 4.110 Unit Wt. 0.899 96.07
12 Dia. Vertical Wall (Long) in Earth face 20 2.790 Unit Wt. 0.899 50.16
12 Dia. Vertical Wall (Long) in Water face 20 2.430 Unit Wt. 0.899 43.69
12 Dia. Vertical Wall (Short) in Earth face 26 2.790 Unit Wt. 0.899 65.21
12 Dia. Vertical Wall (Short) in Water face 26 2.430 Unit Wt. 0.899 56.80
12 Dia Horizontal Bar 7 21.200 Unit Wt. 0.899 133.41
12 Dia. Main Bar in Roof Slab 13 4.975 Unit Wt. 0.899 58.14
12 Dia. Mainor Bar in Roof Slab 13 4.975 Unit Wt. 0.899 58.14
12 Dia Chair Bar 64 1.360 Unit Wt. 0.899 78.25
Extra for Lapping, Chair, etc. 20% 159.01
Total 954.00 Kgs.
APPENDIX 5
Description of Item : Earthwork in excavation in Hard clay & soils mixed with soft moorum stones (upto 40 cm size) incl. disposal up to 10 m lead & lift of 1.5m
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
2-2 U.L. pd 0.800 275.00 220.00 Tools and Plants 3% of Labour charge 6.60
Labour Component (A) 220.00 Material & Equipment Component (B) 6.60
RATE PER
Total = A+B = NRs. 226.60
Overhead Misc. Expenditure of 15 % = NRs. 33.99
Grand Total = NRs. 260.59
Rate per cubic meter = NRs 260.59
Description of Item : Back filling with ordinary soil in 15 cm thick layers and hand compaction (haulage distance of 10 m) with sprinkling water.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
2-25-a U.L. pd 0.500 275.00 137.50 Tools and Plants 3% of Labour charge 4.13
Labour Component (A) 137.50 Material & Equipment Component (B) 4.13
RATE PER
Total = A+B = NRs. 141.63
Overhead Misc. Expenditure of 15 % = NRs. 21.24
Grand Total = NRs. 162.87
Rate per cubic meter = NRs 162.87
Description of Item : Filling medium soils in pipeline trenches in 20 cm thick layers including hand compaction and water sprinkling
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
2-39-c U.L. pd 0.550 275.00 151.25 Tools and Plants 3% of Labour charge 4.54
Labour Component (A) 151.25 Material & Equipment Component (B) 4.54
RATE PER
Total = A+B = NRs. 155.79
Overhead Misc. Expenditure of 15 % = NRs. 23.37
Grand Total = NRs. 179.16
Rate per cubic meter = NRs 179.16
Description of Item : Sand filling work in trenches and floor including watering and compacting by ramming all complete
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
2-42 U.L. pd 0.700 275.00 192.50 Sand m3 1.100 882.19 970.41
Tools and Plants 3% of Labour charge 5.78
Labour Component (A) 192.50 Material & Equipment Component (B) 976.18
RATE PER
Total = A+B = NRs. 1,168.68
Overhead Misc. Expenditure of 15 % = NRs. 175.30
Grand Total = NRs. 1,343.99
Rate per cubic meter = NRs 1,343.99
1/24
RATE ANALYSIS :
Description of Item : Back filling by Clean Graded Sand filling in filter as filter material including watering and compacting by ramming all complete
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
2-42+3-12 U.L. pd 2.700 275.00 742.50 Sand (40%) m3 0.440 882.19 388.16
Adjusted Aggregate (60%) m3 0.660 1614.41
Labour Component (A) 742.50 Material & Equipment Component (B) 388.16
RATE PER
Total = A+B = NRs. 1,130.66
Overhead Misc. Expenditure of 15 % = NRs. 169.60
Grand Total = NRs. 1,300.26
Rate per cubic meter = NRs 1,300.30
Description of Item : Brick masonry works with supplying bricks, making C/S mortar of 1:4 & construction of brick walls of chimney bhatta complete works.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
5-1-b-2 S.L. pd 1.500 400.00 600.00 Bricks Nos. 530.000 8.50 4505.00
U.L. pd 2.200 275.00 605.00 Cement Bag 2.000 610.62 1221.24
Sand m³ 0.280 1587.94 444.62
Labour Component (A) 1205.00 Material & Equipment Component (B) 6170.86
RATE PER
Total = A+B = NRs. 7,375.86
Overhead Misc. Expenditure of 15 % = NRs. 1,106.38
Grand Total = NRs. 8,482.24
Rate per cubic meter (m³) = NRs 8,482.24
Description of Item : Brick masonry works with supplying bricks, making C/S mortar of 1:6 & construction of brick walls of chimney bhatta complete works.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
5-1-b-3 S.L. pd 1.500 400.00 600.00 Bricks Nos. 530.000 8.50 4505.00
U.L. pd 2.200 275.00 605.00 Cement Bag 1.400 610.62 854.87
Sand m³ 0.300 1587.94 476.38
Labour Component (A) 1205.00 Material & Equipment Component (B) 5836.25
RATE PER
Total = A+B = NRs. 7,041.25
Overhead Misc. Expenditure of 15 % = NRs. 1,056.19
Grand Total = NRs. 8,097.44
Rate per cubic meter (m³) = NRs 8,097.44
Description of Item : Rubble masonry works incl. supply of hard stone, cement mortar of 1:3 and construction of wall upto 5m high for haulage distance of 10 m
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
6-1-a S.L. pd 1.500 400.00 600.00 Cement Bag 3.880 610.62 2369.21
U.L. pd 5.000 275.00 1375.00 Block Stone m³ 1.000 1288.00 1288.00
Bund Stone m³ 0.100 1235.06 123.51
Sand m³ 0.420 1587.94 666.93
Labour Component (A) 1975.00 Material & Equipment Component (B) 4447.64
RATE PER
Total = A+B = NRs. 6,422.64
Overhead Misc. Expenditure of 15 % = NRs. 963.40
Grand Total = NRs. 7,386.04
Rate per cubic meter (m³) = NRs 7,386.04
2/24
RATE ANALYSIS :
Description of Item : Rubble masonry works incl. supply of stone, preparing C/S mortar of 1:4 & construction of wall upto 5m high for haulage distance of 10 m.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
6-1-b S.L. pd 1.500 400.00 600.00 Cement Bag 3.180 610.62 1941.77
U.L. pd 5.000 275.00 1375.00 Block Stone m³ 1.000 1288.00 1288.00
Bund Stone m³ 0.100 1235.06 123.51
Sand m³ 0.450 1587.94 714.57
Labour Component (A) 1975.00 Material & Equipment Component (B) 4067.85
RATE PER
Total = A+B = NRs. 6,042.85
Overhead Misc. Expenditure of 15 % = NRs. 906.43
Grand Total = NRs. 6,949.27
Rate per cubic meter (m³) = NRs 6,949.27
Description of Item : Rubble masonry works incl. supply of stone, preparing C/S mortar of 1:6 & construction of wall upto 5m high for haulage distance of 10 m.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
6-1-c S.L. pd 1.500 400.00 600.00 Cement Bag 2.120 610.62 1294.51
U.L. pd 5.000 275.00 1375.00 Block Stone m³ 1.000 1288.00 1288.00
Bund Stone m³ 0.100 1235.06 123.51
Sand m³ 0.470 746.33
Labour Component (A) 1975.00 Material & Equipment Component (B) 3452.35
RATE PER
Total = A+B = NRs. 5,427.35
Overhead Misc. Expenditure of 15 % = NRs. 814.10
Grand Total = NRs. 6,241.45
Rate per cubic meter (m³) = NRs 6,241.45
Description of Item : Rubble masonry works incl. supply of stone blocks & construction of dry wall upto 5m high for haulage distance of 30 m.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
6-2-a S.L. pd 1.000 400.00 400.00 Block Stone 1.000 1288.00 1288.00
U.L. pd 2.000 275.00 550.00 Bund Stone 0.100 1235.06 123.51
Labour Component (A) 950.00 Material & Equipment Component (B) 1411.50
RATE PER
Total = A+B = NRs. 2,361.50
Overhead Misc. Expenditure of 15 % = NRs. 354.23
Grand Total = NRs. 2,715.73
Rate per cubic meter (m³) = NRs 2,715.73
Description of Item : Stone masonry works of side ditch in 1:3 cement mortar including preparation of mortar, hauling stones & mortar.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
6-6-a S.L. pd 1.430 400.00 572.00 Cement Bag 3.060 610.62 1868.50
U.L. pd 5.720 275.00 1573.00 Block Stone m³ 1.000 1288.00 1288.00
Bund Stone m³ 0.100 1235.06 123.51
Sand m³ 0.321 1587.94 509.73
Labour Component (A) 2145.00 Material & Equipment Component (B) 3789.73
RATE PER
Total = A+B = NRs. 5,934.73
Overhead Misc. Expenditure of 15 % = NRs. 0.00
Grand Total = NRs. 5,934.73
Rate per cubic meter = NRs 5,934.73 For Pitching 0f 20cm thk 1186.95 per Sq.m
3/24
RATE ANALYSIS :
Description of Item : Stone masonry works of side ditch in 1:6 C/S mortar incl. preparation of mortar, hauling stones & mortar upto 30 m distance & construction
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
6-6-b S.L. pd 1.430 400.00 572.00 Cement Bag 1.500 610.62 915.93
U.L. pd 5.720 275.00 1573.00 Bund Stone m³ 1.000 1288.00 1288.00
Block Stone m³ 0.100 1235.06 123.51
Sand m³ 0.306 1587.94 485.91
Labour Component (A) 2145.00 Material & Equipment Component (B) 2813.34
RATE PER
Total = A+B = NRs. 4,958.34
Overhead Misc. Expenditure of 15 % = NRs. 743.75
Grand Total = NRs. 5,702.09
Rate per cubic meter (m³) = NRs 5,702.09
Description of Item: M10 Grade (1:3:6 mix by volume) concrete work in foundation, vertical walls incl. supply of materials & haulage upto 30 m.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
7-2-c S.L. pd 1.000 400.00 400.00 Cement Bag 4.400 610.62 2686.73
U.L. pd 4.000 275.00 1100.00 Aggregate cum 0.890 1614.41 1436.82
Sand cum 0.470 1587.94 746.33
Labour Component (A) 1500.00 Material & Equipment Component (B) 4869.88
RATE PER
Total = A+B = NRs. 6,369.88
Overhead Misc. Expenditure of 15 % = NRs. 955.48
Grand Total = NRs. 7,325.36
Rate per cubic meter (m³) = NRs 7,325.36
Description of Item: M15 Grade (1:2:4 mix by volume) concrete work in foundation & vertical walls incl. supply of materials & haulage upto 30 m.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
7-2-d S.L. pd 1.000 400.00 400.00 Cement Bag 6.400 610.62 3907.97
U.L. pd 4.000 275.00 1100.00 Aggregate cum 0.850 1614.41 1372.24
Sand cum 0.445 1587.94 706.63
Labour Component (A) 1500.00 Material & Equipment Component (B) 5986.85
RATE PER
Total = A+B = NRs. 7,486.85
Overhead Misc. Expenditure of 15 % = NRs. 1,123.03
Grand Total = NRs. 8,609.87
Rate per cubic meter (m³) = NRs 8,609.87
Description of Item: M15 Grade (1:2:4 mix by volume) concrete work in super structures, slabs, beams & walls incl. supply of materials & haulage upto 30 m.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
7-4-a S.L. pd 0.800 400.00 320.00 Cement Bag 6.400 610.62 3907.97
U.L. pd 7.000 275.00 1925.00 Aggregate cum 0.850 1614.41 1372.24
Sand cum 0.445 1587.94 706.63
Labour Component (A) 2245.00 Material & Equipment Component (B) 5986.85
RATE PER
Total = A+B = NRs. 8,231.85
Overhead Misc. Expenditure of 15 % = NRs. 1,234.78
Grand Total = NRs. 9,466.62
Rate per cubic meter (m³) = NRs 9,466.62
4/24
RATE ANALYSIS :
Description of Item : M20 Grade (1:1.5:3 mix) concrete work upto 3m height, foundation, beam, slabs & walls incl. supply of materials & haulage upto 30 m.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
7-4-b S.L. pd 0.800 400.00 320.00 Cement Bag 8.000 610.62 4884.96
U.L. pd 7.000 275.00 1925.00 Aggregate m3 0.860 1614.41 1388.39
3
Sand m 0.425 1587.94 674.87
Labour Component (A) 2245.00 Material & Equipment Component (B) 6948.22
RATE PER
Total = A+B = NRs. 9,193.22
Overhead Misc. Expenditure of 15 % = NRs. 1,378.98
Grand Total = NRs. 10,572.21
Rate per cubic meter = NRs 10,572.21
Description of Item : Cutting, bending, placing in position & binding by GI Wire of reinforcement steel bars for RCC incl. supply of materials & haulage upto 30 m
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
7-5 S.L. pd 12.000 400.00 4800.00 Steel Bars MT 1.050 62500.00 65625.00
For 1 ton U.L. pd 12.000 275.00 3300.00 Binding wire Kg 10.000 81.00 810.00
Labour Component (A) 8100.00 Material & Equipment Component (B) 66435.00
RATE PER
Total = A+B = NRs. 74,535.00
Overhead Misc. Expenditure of 15 % = NRs. 11,180.25
Rate per Ton = NRs. 85,715.25
Description of Item : Making wooden forms for building incl. supply & selection of material, fixing, nailing placing separators, dismantling forms for lead upto 30m
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
8-2 -a S.L. pd 1.720 400.00 688.00 Timber m³ 0.526 3969.85 2088.14 6 times use
U.L. pd 2.570 275.00 706.75 Nails Kg 2.500 100.00 250.00 of Wood
Labour Component (A) 1394.75 Material & Equipment Component (B) 2338.14
RATE PER
Total = A+B = NRs. 3,732.89
Overhead Misc. Expenditure of 15 % = NRs. 559.93
Grand Total = NRs. 4,292.82
Rate per square meter = NRs. 429.28
Description of Item : Making open wooden forms for trench Cutting for deeper depth incl. supply, fixing, placing separators, dismantling, etc for complete work.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
8-13 -a S.L. pd 1.000 400.00 400.00 Timber m³ 2.030 3969.85 8058.79 6 times use
For 100 Sq.m U.L. pd 1.750 275.00 481.25 Plank Sq.m. 33.330 99.25 3307.88 of Wood
Labour Component (A) 881.25 Material & Equipment Component (B) 11366.67
RATE PER
Total = A+B = NRs. 12,247.92
Overhead Misc. Expenditure of 15 % = NRs. 1,837.19
Grand Total = NRs. 14,085.11
Rate per square meter = NRs. 140.85
Description of Item: 1:2:4 cement concrete floor casting of 50 mm thick including finishing by cement rubbing.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
11-1 -c S.L. pd 1.250 400.00 500.00 Cement Bag. 3.400 610.62 2076.11
For 10 Sq.m. U.L. pd 2.500 275.00 687.50 Sand m³ 0.230 1587.94 365.23
Aggregate m³ 0.460 1614.41 742.63
Labour Component (A) 1187.50 Material & Equipment Component (B) 3183.96
RATE PER
Total = A+B = NRs. 4,371.46
Overhead Misc. Expenditure of 15 % = NRs. 655.72
Grand Total (for 10 Sq. m) = NRs. 5,027.18
Rate per square meter = NRs. 502.72
5/24
RATE ANALYSIS :
Description of Item: 1:2:4 cement concrete floor casting of 75 mm thick including finishing by cement rubbing.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
11-1 -d S.L. pd 1.250 400.00 500.00 Cement Bag. 5.200 610.62 3175.22
For 10 Sq.m. U.L. pd 3.000 275.00 825.00 Sand m³ 0.340 1587.94 539.90
Aggregate m³ 0.680 1614.41 1097.80
Labour Component (A) 1325.00 Material & Equipment Component (B) 4812.92
RATE PER
Total = A+B = NRs. 6,137.92
Overhead Misc. Expenditure of 15 % = NRs. 920.69
Grand Total (for 10 Sq. m) = NRs. 7,058.61
Rate per square meter (m²) = NRs. 705.86
Description of Item: Flooring of 60 to 70 mm thick Interlocking Concrete Block on sand bed including fine finishing with all lead & lift.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
2
11-8-b-Adj S.L. pd 1.000 400.00 400.00 I. L Blck m 11.00 527.16 5798.78
For 10 Sq.m. U.L. pd 6.000 275.00 1650.00 Crusher Dust m³ 1.260 657.82 828.85
Adjusted
Labour Component (A) 2050.00 Material & Equipment Component (B) 6627.63
RATE PER
Total = A+B = NRs. 8,677.63
Overhead Misc. Expenditure of 15 % = NRs. 1,301.64
Grand Total (for 10 Sq. m) = NRs. 9,979.28
Rate per square meter = NRs. 997.93
Description of Item: Flooring of Flag Stone of 50 mm thick thick on sand bed & rule pointing by 1:4 Cement sand mortar incl. fine finishing with all lead & lift.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
2
11-8-a S.L. pd 2.000 400.00 800.00 Flag Stone m 11.00 484.13 5325.41
For 10 Sq.m. U.L. pd 4.500 275.00 1237.50 Cement Bag 1.26 610.62 769.38
Sand m³ 0.710 1587.94 1127.44
Labour Component (A) 2037.50 Material & Equipment Component (B) 7222.23
RATE PER
Total = A+B = NRs. 9,259.73
Overhead Misc. Expenditure of 15 % = NRs. 1,388.96
Grand Total (for 10 Sq. m) = NRs. 10,648.69
Rate per square meter = NRs. 1,064.87
Description of Item: Flooring of Flag Stone of 60 mm thick thick on sand bed & rule pointing by 1:4 Cement sand mortar incl. fine finishing with all lead & lift.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
11-8-a S.L. pd 2.000 400.00 800.00 Flag Stone m2 11.00 774.60 8520.65
For 10 Sq.m. U.L. pd 4.500 275.00 1237.50 Cement Bag 1.26 1,755.82 2212.33
Sand m³ 0.710 60.00 42.60
Labour Component (A) 2037.50 Material & Equipment Component (B) 10775.59
RATE PER
Total = A+B = NRs. 12,813.09
Overhead Misc. Expenditure of 15 % = NRs. 1,921.96
Grand Total (for 10 Sq. m) = NRs. 14,735.05
Rate per square meter = NRs. 1,473.50
6/24
RATE ANALYSIS :
Description of Item : Single Layer Flat brick soling in base with sand
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
11-15 -a S.L. pd 0.500 400.00 200.00 Bricks Nos. 420.000 8.50 3570.00
For 10 Sq.m. U.L. pd 1.000 275.00 275.00 Sand m³ 0.710 882.19 626.35
Labour Component (A) 475.00 Material & Equipment Component (B) 4196.35
RATE PER
Total = A+B = NRs. 4,671.35
Overhead Misc. Expenditure of 15 % = NRs. 700.70
Grand Total = NRs. 5,372.06
Rate per square meter = NRs 537.21
Description of Item : Brick on Edge Paving with specified pattern laying on sand bed, filling of voids by sand and flush rule pointing by 1:3 C/S mortar
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
11-17 S.L. pd 2.000 400.00 800.00 Bricks Nos. 750.000 8.50 6375.00
For 10 Sq.m U.L. pd 4.000 275.00 1100.00 Cement Bag 0.400 610.62 244.25
Sand m³ 0.100 1587.94 158.79
Labour Component (A) 1900.00 Material & Equipment Component (B) 6619.25
RATE PER
Total = A+B = NRs. 8,519.25
Overhead Misc. Expenditure of 15 % = NRs. 1,277.89
Rate per square meter = NRs. 979.71
Description of Item: 3 mm thick fine cement rubbing works (Neat Cement Punning)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
11-20 S.L. pd 1.000 400.00 400.00 Cement Kg 53.200 12.21 649.70
For 10 Sq.m. U.L. pd 1.000 275.00 275.00
Labour Component (A) 675.00 Material & Equipment Component (B) 649.70
RATE PER
Total = A+B = NRs. 1,324.70
Overhead Misc. Expenditure of 15 % = NRs. 198.70
Grand Total = NRs. 1,523.40
Rate per square meter = NRs 152.34
7/24
RATE ANALYSIS :
Description of Item: 12.5 mm thick plastering works with 1:3 cement Sand mortar on Wall and Floor
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
12-1-b S.L. pd 12.000 400.00 4800.00 Cement Bag 12.500 610.62 7632.75
For 100Sq.m. U.L. pd 16.000 275.00 4400.00 Sand m³ 1.280 1587.94 2032.56
Labour Component (A) 9200.00 Material & Equipment Component (B) 9665.31
RATE PER
Total = A+B = NRs. 18,865.31
Overhead Misc. Expenditure of 15 % = NRs. 2,829.80
Grand Total = NRs. 21,695.11
Rate per square meter = NRs 216.95
Description of Item: 12.5 mm thick plastering works with 1:4 cement Sand mortar on Wall and floor
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
12-1-c S.L. pd 12.000 400.00 4800.00 Cement Bag 10.760 610.62 6570.27
For 100Sq.m. U.L. pd 16.000 275.00 4400.00 Sand m³ 1.460 1587.94 2318.39
Labour Component (A) 9200.00 Material & Equipment Component (B) 8888.66
RATE PER
Total = A+B = NRs. 18,088.66
Overhead Misc. Expenditure of 15 % = NRs. 2,713.30
Grand Total = NRs. 20,801.96
Rate per square meter = NRs 208.02
Description of Item: 12.5 mm thick plastering works with 1:6 cement Sand mortar on Wall and floor
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
12-1-d S.L. pd 12.000 400.00 4800.00 Cement Bag 7.640 610.62 4665.14
For 100Sq.m. U.L. pd 16.000 275.00 4400.00 Sand m³ 1.570 1587.94 2493.07
Labour Component (A) 9200.00 Material & Equipment Component (B) 7158.20
RATE PER
Total = A+B = NRs. 16,358.20
Overhead Misc. Expenditure of 15 % = NRs. 2,453.73
Grand Total = NRs. 18,811.93
Rate per square meter = NRs 188.12
Description of Item: 20 mm thick plastering works with 1:3 cement Sand mortar on Wall and floor For 100 Sq.m.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
12-4 -a S.L. pd 14.000 400.00 5600.00 Cement Bag 19.200 610.62 11723.90
For 100Sq.m. U.L. pd 19.000 275.00 5225.00 Sand m³ 1.950 1587.94 3096.48
Labour Component (A) 10825.00 Material & Equipment Component (B) 14820.39
RATE PER
Total = A+B = NRs. 25,645.39
Overhead Misc. Expenditure of 15 % = NRs. 3,846.81
Grand Total = NRs. 29,492.19
Rate per square meter = NRs 294.92
Description of Item: 20 mm thick plastering works with 1:6 cement Sand mortar on Wall and floor For 100 Sq.m.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
12-4 -c S.L. pd 14.000 400.00 5600.00 Cement Bag 11.400 610.62 6961.07
For 100Sq.m. U.L. pd 19.000 275.00 5225.00 Sand m³ 2.350 1587.94 3731.66
Labour Component (A) 10825.00 Material & Equipment Component (B) 10692.73
RATE PER
Total = A+B = NRs. 21,517.73
Overhead Misc. Expenditure of 15 % = NRs. 3,227.66
Grand Total = NRs. 24,745.39
Rate per square meter = NRs 247.45
8/24
RATE ANALYSIS :
Description of Item Prepared enamel paint application of double coat on top of single coat of primer
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
13-5(a+b+c) S.L. pd 12.000 400.00 4800.00 Metal Primer Lt 8.100 188.00 1522.80
For 100Sq.m. U.L. pd 8.000 275.00 2200.00 Enamel paint Lt 16.000 285.00 4560.00
Labour Component (A) 7000.00 Material & Equipment Component (B) 6082.80
RATE PER
Total = A+B = NRs. 13,082.80
Overhead Misc. Expenditure of 15 % = NRs. 1,962.42
Grand Total (for 100 m2) = NRs. 15,045.22
Rate per square meter = NRs. 150.45
Description of Item: Flush Pointing work with 1:3 cement Sand mortar in brick wall including supply of materials complete work
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
14-1-c S.L. pd 10.500 400.00 4200.00 Cement Bag 3.100 610.62 1892.92
For 100 Sq.m. U.L. pd 12.000 275.00 3300.00 Sand m³ 0.320 1587.94 508.14
Labour Component (A) 7500.00 Material & Equipment Component (B) 2401.06
RATE PER
Total = A+B = NRs. 9,901.06
Overhead Misc. Expenditure of 15 % = NRs. 1,485.16
Grand Total = NRs. 11,386.22
Rate per square meter = NRs 113.86
Description of Item: Flush Rule Pointing work with 1:3 C/S mortar in boulder stone masonry wall incl. supply of materials, mortar preparation, etc complete wor
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
14-2-c S.L. pd 10.000 400.00 4000.00 Cement Bag 6.120 610.62 3736.99
For 100 Sq.m. U.L. pd 14.000 275.00 3850.00 Sand m³ 0.630 1587.94 1000.40
Labour Component (A) 7850.00 Material & Equipment Component (B) 4737.40
RATE PER
Total = A+B = NRs. 12,587.40
Overhead Misc. Expenditure of 15 % = NRs. 1,888.11
Rate per square meter = NRs. 144.76
Description of Item : Laying Sub-base course of sand mixed gravel (150mm thk.), including loading, transportation of material & spraying, leveling of surface
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
15-9c S.L. pd 0.000 400.00 0.00 C. Aggregate m³ 0.192 1235.06 237.13
Depth=15cm U.L. pd 0.190 275.00 52.25 Road Roller Hrs 0.013 500.00 6.50
Labour Component (A) 52.25 Material & Equipment Component (B) 243.63
RATE PER
Total = A+B = NRs. 295.88
Overhead Misc. Expenditure of 15 % = NRs. 44.38
Rate per square meter = NRs. 340.26
9/24
RATE ANALYSIS :
Description of Item : Laying of solid base (250mm Thk) for the foundation of crushed stone & crusher dust incl. supply of material at site, roller compaction & le
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
15-10-c-adj C. Aggregate m³ 0.3375 1235.06 416.83
Depth =25cm U.L. pd 0.320 275.00 88.00 Scrng. m³ 0.1050 1614.41 169.51
Binding Mat m³ 0.0250 1587.94 39.70
Compactor Hrs 0.070 300.00 21.00
Labour Component (A) 88.00 Material & Equipment Component (B) 647.05
RATE PER
Total = A+B = NRs. 735.05
Overhead Misc. Expenditure of 15 % = NRs. 110.26
Rate per square meter = NRs. 845.30
Description of Item : Laying Base course of sand & clay of 100 to 150mm thick including loading, transportation of material and spraying Leveling of surface
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
15-12.1-d S.L. pd 0.000 400.00 0.00 C. Aggregate m³ 0.1333 1235.06 164.63
Depth =10cm U.L. pd 0.150 275.00 41.25 Scrng. m³ 0.0266 1614.41 42.94
Binding Mat m³ 0.0120 1587.94 19.06
Road Roller Hrs 0.004 500.00 2.00
Labour Component (A) 41.25 Material & Equipment Component (B) 228.63
RATE PER
Total = A+B = NRs. 269.88
Overhead Misc. Expenditure of 15 % = NRs. 40.48
Rate per square meter = NRs. 310.36
Description of Item : Tack Coat application including supply of materials including heating, mixing, spraying, leveling & compaction
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
15-17-b S.L. pd 0.000 400.00 0.00 Bitumen Kg 12.200 58.40 712.48
For 10 Sq.m. U.L. pd 0.200 275.00 55.00 Kerosene Lit 2.000 60.00 120.00
Firewood kg 30.000 7.00 210.00
Roller Hrs 0.000 500.00 0.00
Bitumin Distributor Hrs 0.040 1300.00 52.00
Labour Component (A) 55.00 Material & Equipment Component (B) 1094.48
RATE PER
Total = A+B = NRs. 1,149.48
Overhead Misc. Expenditure of 15 % = NRs. 172.42
Rate per square meter = NRs. 132.19
10/24
RATE ANALYSIS :
Description of Item : Seal Coat including material, heating, mixing, spraying, leveling & compaction complete
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
15-23-1 S.L. pd 0.000 400.00 0.00 C. Aggregate m³ 0.120 1235.06 148.21
For 10 Sq.m. U.L. pd 0.450 275.00 123.75 Bitumen Kg 15.000 58.40 876.00
Kerosene Lit 1.500 60.00 90.00
Firewood kg 36.000 7.00 252.00
Roller Hrs 0.040 500.00 20.00
Sprayer Hrs 0.040 1300.00 52.00
Labour Component (A) 123.75 Material & Equipment Component (B) 1438.21
RATE PER
Total = A+B = NRs. 1,561.96
Overhead Misc. Expenditure of 15 % = NRs. 234.29
Rate per square meter = NRs. 179.63
Description of Item: Making gabion boxes including cutting wire, netting, assembling in position of hexagonal mesh (size of 10cm x 12cm) complete work
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
16(5a+6a) S.L. pd 0.450 400.00 180.00 Mesh Wire Kg. 25.300 76.00 1922.80 MW=10SWG
2 x 1 x 1m U.L. pd 0.600 275.00 165.00 Selvedge Wire Kg. 3.150 75.00 236.25 SW=7SWG
Labour Component (A) 345.00 Material & Equipment Component (B) 2159.05
RATE PER
Total = A+B = NRs. 2,504.05
Overhead Misc. Expenditure of 15 % = NRs. 375.61
Rate per cubic meter = NRs. 1,439.83
Description of Item: Making gabion boxes including cutting wire, netting, assembling in position of hexagonal mesh (size of 10cm x 12cm) complete work
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
16(5b+6b) S.L. pd 0.630 400.00 252.00 Mesh Wire Kg. 36.700 76.00 2789.20 MW=10SWG
3 x 1 x 1m U.L. pd 0.880 275.00 242.00 Selvedge Wire Kg. 4.100 75.00 307.50 SW=7SWG
Labour Component (A) 494.00 Material & Equipment Component (B) 3096.70
RATE PER
Total = A+B = NRs. 3,590.70
Overhead Misc. Expenditure of 15 % = NRs. 538.61 4129.31 1376.44
Rate per cubic meter = NRs. 1,376.44
Description of Item: Making gabion boxes including cutting wire, netting, assembling in position of hexagonal mesh (size of 10cm x 12cm) complete work
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
16(5e+6e) S.L. pd 0.260 400.00 104.00 Mesh Wire Kg. 14.200 76.00 1079.20 MW=10SWG
2 x 1 x 0.3m U.L. pd 0.240 275.00 66.00 Selvedge Wire Kg. 2.250 75.00 168.75 SW=7SWG
Labour Component (A) 170.00 Material & Equipment Component (B) 1247.95
RATE PER
Total = A+B = NRs. 1,417.95
Overhead Misc. Expenditure of 15 % = NRs. 212.69
Rate per cubic meter = NRs. 2,717.74
Description of Item: Making gabion boxes including cutting wire, netting, assembling in position of hexagonal mesh (size of 10cm x 12cm) complete work
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
16(5f+6f) S.L. pd 0.370 400.00 148.00 Mesh Wire Kg. 20.850 76.00 1584.60 MW=10SWG
3 x 1 x 0.3m U.L. pd 0.350 275.00 96.25 Selvedge Wire Kg. 3.000 75.00 225.00 SW=7SWG
Labour Component (A) 244.25 Material & Equipment Component (B) 1809.60
RATE PER
Total = A+B = NRs. 2,053.85
Overhead Misc. Expenditure of 15 % = NRs. 308.08
Rate per cubic meter = NRs. 2,624.36
11/24
RATE ANALYSIS :
Description of Item: Packing and filling of gabion crates with boulder stones
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
16-11 U.L. pd 0.500 275.00 137.50 Rubble Stone m³ 1.100 1288.00 1416.80
Labour Component (A) 137.50 Material & Equipment Component (B) 1416.80
RATE PER
Total = A+B = NRs. 1,554.30
Overhead Misc. Expenditure of 15 % = NRs. 233.14
Rate per cubic meter = NRs. 1,787.44
Description of Item : Laying, RCC Pipe of 25cm Ø of NP3 Class & its accessories with 1:2 cement sand mortar, jute, etc. including Haulage up to 100 m
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-1-(b+C)/2 Cement Bag 1.350 610.62 824.34
For S.L. pd 5.000 400.00 2000.00 Hume Pipe m. 32.000 2008.82 64282.24
32m Pipe U.L. pd 21.000 275.00 5775.00 Jute Kg. 3.015 80.00 241.20
Bitumen Kg. 1.000 58.40 58.40
Sand m³ 0.105 882.19 92.63
Labour Component (A) 7775.00 Material & Equipment Component (B) 65498.81
RATE PER
Total = A+B = NRs. 73,273.81
Overhead Misc. Expenditure of 15 % = NRs. 10,991.07
Grand Total for 32 m = NRs. 84,264.88
Rate per RM = NRs. 2,633.28
Description of Item : Laying, RCC Pipe of 30cm Ø of NP3 Class & its accessories with 1:2 cement sand mortar, jute, etc. including Haulage up to 100 m
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-1-c Cement Bag 1.660 610.62 1013.63
For S.L. pd 6.000 400.00 2400.00 Hume Pipe m. 32.000 2886.50 92368.00
32m Pipe U.L. pd 22.000 275.00 6050.00 Jute Kg. 3.630 80.00 290.40
Bitumen Kg. 1.250 58.40 73.00
Sand m³ 0.130 882.19 114.68
Labour Component (A) 8450.00 Material & Equipment Component (B) 93859.71
RATE PER
Total = A+B = NRs. 102,309.71
Overhead Misc. Expenditure of 15 % = NRs. 15,346.46
Grand Total for 32 m = NRs. 117,656.17
Rate per RM = NRs. 3,676.76
Description of Item : Laying, RCC Pipe of 45cm Ø of NP3 Class & its accessories with 1:2 cement sand mortar, jute, etc. including Haulage up to 100 m
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-1-(d+e)/2 Cement Bag 2.260 610.62 1380.00
For S.L. pd 7.000 400.00 2800.00 Hume Pipe m. 32.000 4142.30 132553.60
32m Pipe U.L. pd 26.000 275.00 7150.00 Jute Kg. 4.515 80.00 361.20
Bitumen Kg. 1.500 58.40 87.60
Sand m³ 0.175 882.19 154.38
Labour Component (A) 9950.00 Material & Equipment Component (B) 134536.78
RATE PER
Total = A+B = NRs. 144,486.78
Overhead Misc. Expenditure of 15 % = NRs. 21,673.02
Grand Total for 32 m = NRs. 166,159.80
Rate per RM = NRs. 5,192.49
12/24
RATE ANALYSIS :
Description of Item : Laying, RCC Pipe of 60cm Ø of NP3 Class & its accessories with 1:2 cement sand mortar, jute, etc. including Haulage up to 100 m
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-1-f Cement Bag 4.360 610.62 2662.30
For S.L. pd 9.000 400.00 3600.00 Hume Pipe m. 32.000 5475.38 175212.16
32m Pipe U.L. pd 35.000 275.00 9625.00 Jute Kg. 7.000 80.00 560.00
Bitumen Kg. 2.000 58.40 116.80
Sand m³ 0.300 882.19 264.66
Labour Component (A) 13225.00 Material & Equipment Component (B) 178815.92
RATE PER
Total = A+B = NRs. 192,040.92
Overhead Misc. Expenditure of 15 % = NRs. 28,806.14
Grand Total for 32 m = NRs. 220,847.06
Rate per RM = NRs. 6,901.47
Description of Item: 20 to 25 mm Ø (external diameter) HDPE Laying works (with butt welded joints) including jointing of pipe
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-2a-1 S.L. pd 1.000 400.00 400.00 EG & MJ LS 1000.00 E. Generator,
For 1000m U.L. pd 3.000 275.00 825.00 Fuel Lt. 0.250 60.00 15.00 Mech. Jack
Misc. expenses @ 2.51 % of Labour cost 30.75
Labour Component (A) 1225.00 Material & Equipment Component (B) 1045.75
RATE PER
Total = A+B = NRs. 2,270.75
Overhead Misc. Expenditure of 15 % = NRs. 340.61
Grand Total for 1000 m. = NRs. 2,611.36
Rate per meter (m) = NRs. 2.61
Description of Item: 32 mm Ø (external diameter) HDPE Laying works (with butt welded joints) including jointing of pipe
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-2a-2 S.L. pd 1.000 400.00 400.00 EG & MJ LS 1000.00 E. Generator,
For 1000m U.L. pd 4.000 275.00 1100.00 Fuel Lt. 0.250 60.00 15.00 Mech. Jack
Misc. expenses @ 2.51 % of Labour cost 37.65
Labour Component (A) 1500.00 Material & Equipment Component (B) 1052.65
RATE PER
Total = A+B = NRs. 2,552.65
Overhead Misc. Expenditure of 15 % = NRs. 382.90
Grand Total for 1000 m. = NRs. 2,935.55
Rate per meter (m) = NRs. 2.94
Description of Item: 40 and 50 mm Ø (external diameter) HDPE Laying works (with butt welded joints) including jointing of pipe
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-2a-3 S.L. pd 1.500 400.00 600.00 EG & MJ LS 1000.00 E. Generator,
For 1000m U.L. pd 4.500 275.00 1237.50 Fuel Lt. 0.370 60.00 22.20 Mech. Jack
Misc. expenses @ 2.51 % of Labour cost 46.12
Labour Component (A) 1837.50 Material & Equipment Component (B) 1068.32
RATE PER
Total = A+B = NRs. 2,905.82
Overhead Misc. Expenditure of 15 % = NRs. 435.87
Grand Total for 1000 m. = NRs. 3,341.69
Rate per meter (m) = NRs. 3.34
13/24
RATE ANALYSIS :
Description of Item: 63 , 75 and 90 mm Ø (external diameter) HDPE Laying works (with butt welded joints) including jointing of pipe
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-2b-1 S.L. pd 1.000 400.00 400.00 EG & MJ LS 50.00 E. Generator,
For 50m U.L. pd 3.000 275.00 825.00 Fuel Lt. 0.050 60.00 3.00 Mech. Jack
Misc. expenses @ 2.51 % of Labour cost 30.75
Labour Component (A) 1225.00 Material & Equipment Component (B) 83.75
RATE PER
Total = A+B = NRs. 1,308.75
Overhead Misc. Expenditure of 15 % = NRs. 196.31
Grand Total for 50 m. = NRs. 1,505.06
Rate per meter (m) = NRs. 30.10
Description of Item: 110 and 125 mm Ø (external diameter) HDPE Laying works (with butt welded joints) including jointing of pipe
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-2b-1 S.L. pd 1.500 400.00 600.00 EG & MJ LS 50.00 E. Generator,
For 50m U.L. pd 4.500 275.00 1237.50 Fuel Lt. 0.500 60.00 30.00 Mech. Jack
Misc. expenses @ 2.51 % of Labour cost 46.12
Labour Component (A) 1837.50 Material & Equipment Component (B) 126.12
RATE PER
Total = A+B = NRs. 1,963.62
Overhead Misc. Expenditure of 15 % = NRs. 294.54
Grand Total for 50 m. = NRs. 2,258.16
Rate per meter (m) = NRs. 45.16
Description of Item: 140 and 160 mm Ø (external diameter) HDPE Laying works (with butt welded joints) including jointing of pipe
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-2b-1 Adj S.L. pd 2.000 400.00 800.00 EG & MJ LS 100.00 E. Generator,
For 50m U.L. pd 6.000 275.00 1650.00 Fuel Lt. 1.000 60.00 60.00 Mech. Jack
Misc. expenses @ 2.51 % of Labour cost 61.50
Labour Component (A) 2450.00 Material & Equipment Component (B) 221.50
RATE PER
Total = A+B = NRs. 2,671.50
Overhead Misc. Expenditure of 15 % = NRs. 400.72
Grand Total for 50 m. = NRs. 3,072.22
Rate per meter (m) = NRs. 61.44
Description of Item: Laying and jointing of G.I. Pipe (socket joint type) of 15 & 20 mm internal diameter.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4a-1 S.L. pd 0.500 400.00 200.00 Red lead, hemp etc. @ 10% of Labour Cost 75.00
For 30m. U.L. pd 2.000 275.00 550.00 Misc. expenses @ 2.5 % of Labour cost 18.75
Labour Component (A) 750.00 Material & Equipment Component (B) 93.75
RATE PER
Total = A+B = NRs. 843.75
Overhead Misc. Expenditure of 15 % = NRs. 126.56
Grand Total for 30 m. = NRs. 970.31
Rate per meter (m) = NRs. 32.34
14/24
RATE ANALYSIS :
Description of Item: Laying and jointing of G.I. Pipe (socket joint type) of 25 & 32 mm internal diameter.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4a-1 S.L. pd 0.500 400.00 200.00 Red lead, hemp etc. @ 10% of Labour Cost 102.50
For 30m. U.L. pd 3.000 275.00 825.00 Misc. expenses @ 2.5 % of Labour cost 25.63
Labour Component (A) 1025.00 Material & Equipment Component (B) 128.13
RATE PER
Total = A+B = NRs. 1,153.13
Overhead Misc. Expenditure of 15 % = NRs. 172.97
Grand Total for 30 m. = NRs. 1,326.09
Rate per meter (m) = NRs. 44.20
Description of Item: Laying and jointing of G.I. Pipe (socket joint type) of 40 & 50 mm internal diameter.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4a-1 S.L. pd 0.750 400.00 300.00 Red lead, hemp etc. @ 10% of Labour Cost 140.00
For 30m. U.L. pd 4.000 275.00 1100.00 Misc. expenses @ 2.5 % of Labour cost 35.00
Labour Component (A) 1400.00 Material & Equipment Component (B) 175.00
RATE PER
Total = A+B = NRs. 1,575.00
Overhead Misc. Expenditure of 15 % = NRs. 236.25
Grand Total for 30 m. = NRs. 1,811.25
Rate per meter (m) = NRs. 60.38
Description of Item: Laying and jointing of G.I. Pipe (socket joint type) of 65 & 80 mm internal diameter.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4a-1 S.L. pd 1.250 400.00 500.00 Red lead, hemp etc. @ 10% of Labour Cost 187.50
For 30m. U.L. pd 5.000 275.00 1375.00 Misc. expenses @ 2.5 % of Labour cost 46.88
Labour Component (A) 1875.00 Material & Equipment Component (B) 234.38
RATE PER
Total = A+B = NRs. 2,109.38
Overhead Misc. Expenditure of 15 % = NRs. 316.41
Grand Total for 30 m. = NRs. 2,425.78
Rate per meter (m) = NRs. 80.86
Description of Item: Laying and jointing of G.I. Pipe (socket joint type) of 100 mm internal diameter.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4a-1 S.L. pd 1.750 400.00 700.00 Red lead, hemp etc. @ 10% of Labour Cost 235.00
For 30m. U.L. pd 6.000 275.00 1650.00 Misc. expenses @ 2.5 % of Labour cost 58.75
Labour Component (A) 2350.00 Material & Equipment Component (B) 293.75
RATE PER
Total = A+B = NRs. 2,643.75
Overhead Misc. Expenditure of 15 % = NRs. 396.56
Grand Total for 30 m. = NRs. 3,040.31
Rate per meter (m) = NRs. 101.34
Description of Item: Laying and jointing of G.I. Pipe (socket joint type) of 125 mm internal diameter.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4a-1 S.L. pd 2.000 400.00 800.00 Red lead, hemp etc. @ 10% of Labour Cost 286.25
For 30m. U.L. pd 7.500 275.00 2062.50 Misc. expenses @ 2.5 % of Labour cost 71.56
Labour Component (A) 2862.50 Material & Equipment Component (B) 357.81
RATE PER
Total = A+B = NRs. 3,220.31
Overhead Misc. Expenditure of 15 % = NRs. 483.05
Grand Total for 30 m. = NRs. 3,703.36
Rate per meter (m) = NRs. 123.45
15/24
RATE ANALYSIS :
Description of Item: Laying and Jointing of 125 mm D.I. Pipes (Tyton Joint)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-3-c S.L. pd 1.000 400.00 400.00 Hemp Kg. 1.800 80.00 144.00
For 30 m. U.L. pd 6.000 275.00 1650.00 Contingencies @ 1% of the labour cost 20.50
Labour Component (A) 2050.00 Material & Equipment Component (B) 164.50
RATE PER
Total = A+B = NRs. 2,214.50
Overhead Misc. Expenditure of 15 % = NRs. 332.18
Grand Total for 30m. = NRs. 2,546.68
Rate per meter (m) = NRs. 84.89
Description of Item: Laying and Jointing of 150 mm D.I. Pipes (Tyton Joint)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-3-d S.L. pd 1.250 400.00 500.00 Hemp Kg. 1.800 80.00 144.00
For 30 m. U.L. pd 7.500 275.00 2062.50 Contingencies @ 1% of the labour cost 25.63
Labour Component (A) 2562.50 Material & Equipment Component (B) 169.63
RATE PER
Total = A+B = NRs. 2,732.13
Overhead Misc. Expenditure of 15 % = NRs. 409.82
Grand Total for 30m. = NRs. 3,141.94
Rate per meter (m) = NRs. 104.73
Description of Item: Laying and Jointing of 200 mm D.I. Pipes (Tyton Joint)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-3-e S.L. pd 1.500 400.00 600.00 Hemp Kg. 2.100 80.00 168.00
For 30 m. U.L. pd 9.000 275.00 2475.00 Contingencies @ 1% of the labour cost 30.75
Labour Component (A) 3075.00 Material & Equipment Component (B) 198.75
RATE PER
Total = A+B = NRs. 3,273.75
Overhead Misc. Expenditure of 15 % = NRs. 491.06
Grand Total for 30m. = NRs. 3,764.81
Rate per meter (m) = NRs. 125.49
Description of Item: Laying and Jointing of 250 mm D.I. Pipes (Tyton Joint)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-3-e S.L. pd 2.000 400.00 800.00 Hemp Kg. 3.100 80.00 248.00
For 30 m. U.L. pd 12.000 275.00 3300.00 Contingencies @ 1% of the labour cost 41.00
Labour Component (A) 4100.00 Material & Equipment Component (B) 289.00
RATE PER
Total = A+B = NRs. 4,389.00
Overhead Misc. Expenditure of 15 % = NRs. 658.35
Grand Total for 30m. = NRs. 5,047.35
Rate per meter (m) = NRs. 168.25
Description of Item: Laying and Jointing of 300 mm D.I. Pipes (Tyton Joint)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-3-e S.L. pd 2.500 400.00 1000.00 Hemp Kg. 4.300 80.00 344.00
For 30 m. U.L. pd 15.000 275.00 4125.00 Contingencies @ 1% of the labour cost 51.25
Labour Component (A) 5125.00 Material & Equipment Component (B) 395.25
RATE PER
Total = A+B = NRs. 5,520.25
Overhead Misc. Expenditure of 15 % = NRs. 828.04
Grand Total for 30m. = NRs. 6,348.29
Rate per meter (m) = NRs. 211.61
16/24
RATE ANALYSIS :
Description of Item: Laying and Jointing of 350 mm Ø D.I. Pipes (Tyton Joint)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-3-g-Adj. S.L. pd 4.000 400.00 1600.00 Hemp Kg. 6.000 80.00 480.00
For 30 m. U.L. pd 20.000 275.00 5500.00 Contingencies @ 1% of the labor cost 71.00
Labour Component (A) 7100.00 Material & Equipment Component (B) 551.00
RATE PER
Total = A+B = NRs. 7,651.00
Overhead Misc. Expenditure of 15 % = NRs. 1,147.65
Grand Total for 30m. = NRs. 8,798.65
Rate per meter = NRs. 293.29
Description of Item: G.I. Pipe fitting & fixing works of size 15 and 20 mm for metal valve, meter and 15 mm ferrule for all types of fitting.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-1 (1) S.L. pd 0.056 400.00 22.22 R. L.paint, Hemp, T&P etc. required for jointing @1% 10m pipe
U.L. pd 0.222 275.00 61.11 length pipe cost (Rate per m of pipe) = 119.33 11.93
Labour Component (A) 83.33 Material & Equipment Component (B) 11.93
RATE PER
Total = A+B = NRs. 95.27
Overhead Misc. Expenditure of 15 % = NRs. 14.29
Grand Total (per no) = NRs. 109.56
Description of Item: G.I. Pipe fitting & fixing works of size 25 and 32 mm for metal valve and meter for all types of fitting.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-1 (2) S.L. pd 0.056 400.00 22.22 R. L.paint, Hemp, T&P etc. required for jointing @1% 10m pipe
U.L. pd 0.333 275.00 91.67 length pipe cost (Rate per m of pipe) = 331.00 33.10
Labour Component (A) 113.89 Material & Equipment Component (B) 33.10
RATE PER
Total = A+B = NRs. 146.99
Overhead Misc. Expenditure of 15 % = NRs. 22.05
Grand Total (per no) = NRs. 169.04
Description of Item: G.I. Pipe fitting & fixing works of size 40 and 50 mm for metal valve and meter for all types of fitting.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-1 (3) S.L. pd 0.083 400.00 33.33 R. L.paint, Hemp, T&P etc. required for jointing @1% 10m pipe
U.L. pd 0.444 275.00 122.22 length pipe cost (Rate per m of pipe) = 555.67 55.57
Labour Component (A) 155.56 Material & Equipment Component (B) 55.57
RATE PER
Total = A+B = NRs. 211.12
Overhead Misc. Expenditure of 15 % = NRs. 31.67
Grand Total (per no) = NRs. 242.79
Description of Item: G.I. Pipe fitting & fixing works of size 65 and 80 mm for metal valve and meter for all types of fitting.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-1 (4) S.L. pd 0.139 400.00 55.56 R. L.paint, Hemp, T&P etc. required for jointing @1% 10m pipe
U.L. pd 0.556 275.00 152.78 length pipe cost (Rate per m of pipe) = 893.67 89.37
Labour Component (A) 208.33 Material & Equipment Component (B) 89.37
RATE PER
Total = A+B = NRs. 297.70
Overhead Misc. Expenditure of 15 % = NRs. 44.66
Grand Total (per no) = NRs. 342.36
17/24
RATE ANALYSIS :
Description of Item: G.I. Pipe fitting & fixing works of size 100 mm for metal valve and meter for all types of fitting.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-1 (5) S.L. pd 0.194 400.00 77.78 R. L.paint, Hemp, T&P etc. required for jointing @1% 10m pipe
U.L. pd 0.667 275.00 183.33 length pipe cost (Rate per m of pipe) = 1323.17 132.32
Labour Component (A) 261.11 Material & Equipment Component (B) 132.32
RATE PER
Total = A+B = NRs. 393.43
Overhead Misc. Expenditure of 15 % = NRs. 59.01
Grand Total (per no) = NRs. 452.44
Description of Item: G.I. Pipe fitting & fixing works of size 125 mm for metal valve and meter for all types of fitting.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-1 (6) S.L. pd 0.222 400.00 88.89 R. L.paint, Hemp, T&P etc. required for jointing @1% 10m pipe
U.L. pd 0.833 275.00 229.17 length pipe cost (Rate per m of pipe) = 1809.17 180.92
Labour Component (A) 318.06 Material & Equipment Component (B) 180.92
RATE PER
Total = A+B = NRs. 498.97
Overhead Misc. Expenditure of 15 % = NRs. 74.85
Grand Total (per no) = NRs. 573.82
Description of Item: Bend, elbow, union, reducer, flange connection, tap, etc of size 15-20 mm of G.I. Fitting and fixing works.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-2 (1) S.L. pd 0.028 400.00 11.11 Misce. Expenses, T&P etc. required for jointing @0.5% of 10m pipe
U.L. pd 0.111 275.00 30.56 length pipe cost (Rate per m of pipe) = 119.33 5.97
Labour Component (A) 41.67 Material & Equipment Component (B) 5.97
RATE PER
Total = A+B = NRs. 47.63
Overhead Misc. Expenditure of 15 % = NRs. 7.14
Grand Total (per no) = NRs. 54.78
Description of Item: Bend, elbow, union, reducer, flange connection, tap, etc of size 25-32 mm of G.I. Fitting and fixing works.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-2 (2) S.L. pd 0.028 400.00 11.11 Misce. Expenses, T&P etc. required for jointing @0.5% of 10m pipe
U.L. pd 0.167 275.00 45.83 length pipe cost (Rate per m of pipe) = 331.00 16.55
Labour Component (A) 56.94 Material & Equipment Component (B) 16.55
RATE PER
Total = A+B = NRs. 73.49
Overhead Misc. Expenditure of 15 % = NRs. 11.02
Grand Total (per no) = NRs. 84.52
Description of Item: Bend, elbow, union, reducer, flange connection, tap, etc of size 40-50 mm of G.I. Fitting and fixing works.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-2 (3) S.L. pd 0.042 400.00 16.67 Misce. Expenses, T&P etc. required for jointing @0.5% of 10m pipe
U.L. pd 0.222 275.00 61.11 length pipe cost (Rate per m of pipe) = 555.67 27.78
Labour Component (A) 77.78 Material & Equipment Component (B) 27.78
RATE PER
Total = A+B = NRs. 105.56
Overhead Misc. Expenditure of 15 % = NRs. 15.83
Grand Total (per no) = NRs. 121.40
18/24
RATE ANALYSIS :
Description of Item: Bend, elbow, union, reducer, flange connection, tap, etc of size 65-80 mm of G.I. Fitting and fixing works.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-2 (4) S.L. pd 0.069 400.00 27.78 Misce. Expenses, T&P etc. required for jointing @0.5% of 10m pipe
U.L. pd 0.278 275.00 76.39 length pipe cost (Rate per m of pipe) = 893.67 44.68
Labour Component (A) 104.17 Material & Equipment Component (B) 44.68
RATE PER
Total = A+B = NRs. 148.85
Overhead Misc. Expenditure of 15 % = NRs. 22.33
Grand Total (per no) = NRs. 171.18
Description of Item: Bend, elbow, union, reducer, flange connection, tap, etc of size 100 mm of G.I. Fitting and fixing works.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-2 (5) S.L. pd 0.097 400.00 38.89 Misce. Expenses, T&P etc. required for jointing @0.5% of 10m pipe
U.L. pd 0.333 275.00 91.67 length pipe cost (Rate per m of pipe) = 1323.17 66.16
Labour Component (A) 130.56 Material & Equipment Component (B) 66.16
RATE PER
Total = A+B = NRs. 196.71
Overhead Misc. Expenditure of 15 % = NRs. 29.51
Grand Total (per no) = NRs. 226.22
Description of Item: Bend, elbow, union, reducer, flange connection, tap, etc of size 125 mm of G.I. Fitting and fixing works.
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4-b-2 (6) S.L. pd 0.111 400.00 44.44 Misce. Expenses, T&P etc. required for jointing @0.5% of 10m pipe
U.L. pd 0.417 275.00 114.58 length pipe cost (Rate per m of pipe) = 1809.17 90.46
Labour Component (A) 159.03 Material & Equipment Component (B) 90.46
RATE PER
Total = A+B = NRs. 249.49
Overhead Misc. Expenditure of 15 % = NRs. 37.42
Grand Total (per no) = NRs. 286.91
Description of Item: Fixing of Fitting of 80 mm D.I. or G.I. Sluice Valve with Flanged Tail piece or Flanged Tee
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-1+17-3a S.L. pd 0.125 400.00 50.00 Misce. Expenses, T&P etc. required for jointing @1% 15m pipe
U.L. pd 0.750 275.00 206.25 length pipe cost (Rate per m of pipe) = 893.67 134.05
Labour Component (A) 256.25 Material & Equipment Component (B) 134.05
RATE PER
Total = A+B = NRs. 390.30
Overhead Misc. Expenditure of 15 % = NRs. 58.55
Grand Total (per no) = NRs. 448.85
Description of Item: Fixing of Fitting of 100 mm D.I. or G.I. Sluice Valve with Flanged Tail piece or Flanged Tee
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-1+17-3b S.L. pd 0.167 400.00 66.67 Misce. Expenses, T&P etc. required for jointing @1% 15m pipe
U.L. pd 0.875 275.00 240.63 length pipe cost (Rate per m of pipe) = 1323.17 198.48
Labour Component (A) 307.29 Material & Equipment Component (B) 198.48
RATE PER
Total = A+B = NRs. 505.77
Overhead Misc. Expenditure of 15 % = NRs. 75.87
Grand Total (per no) = NRs. 581.63
19/24
RATE ANALYSIS :
Description of Item: Fixing of Fitting of 125 mm D.I. or G.I. Sluice Valve with Flanged Tail piece or Flanged Tee
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-1+17-3c S.L. pd 0.167 400.00 66.67 Misce. Expenses, T&P etc. required for jointing @1% 15m pipe
U.L. pd 1.000 275.00 275.00 length pipe cost (Rate per m of pipe) = 1809.17 271.38
Labour Component (A) 341.67 Material & Equipment Component (B) 271.38
RATE PER
Total = A+B = NRs. 613.04
Overhead Misc. Expenditure of 15 % = NRs. 91.96
Grand Total (per no) = NRs. 705.00
Description of Item: Fixing of Fitting of 150 mm D.I. or G.I. Sluice Valve with Flanged Tail piece or Flanged Tee
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-1+17-3d S.L. pd 0.208 400.00 83.33 Misce. Expenses, T&P etc. required for jointing @1% 15m pipe
U.L. pd 1.167 275.00 320.83 length pipe cost (Rate per m of pipe) = 3418.41 512.76
Labour Component (A) 404.17 Material & Equipment Component (B) 512.76
RATE PER
Total = A+B = NRs. 916.93
Overhead Misc. Expenditure of 15 % = NRs. 137.54
Grand Total (per no) = NRs. 1,054.47
Description of Item: Fixing of Fitting of 200 mm D.I. or G.I. Sluice Valve with Flanged Tail piece or Flanged Tee
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-1+17-3e S.L. pd 0.250 400.00 100.00 Misce. Expenses, T&P etc. required for jointing @1% 15m pipe
U.L. pd 1.500 275.00 412.50 length pipe cost (Rate per m of pipe) = 4635.90 695.39
Labour Component (A) 512.50 Material & Equipment Component (B) 695.39
RATE PER
Total = A+B = NRs. 1,207.89
Overhead Misc. Expenditure of 15 % = NRs. 181.18
Grand Total (per no) = NRs. 1,389.07
Description of Item: Fixing of Fitting of 250 mm D.I. or G.I. Sluice Valve with Flanged Tail piece or Flanged Tee
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-1+17-3f S.L. pd 0.333 400.00 133.33 Misce. Expenses, T&P etc. required for jointing @1% 15m pipe
U.L. pd 2.000 275.00 550.00 length pipe cost (Rate per m of pipe) = 6117.20 917.58
Labour Component (A) 683.33 Material & Equipment Component (B) 917.58
RATE PER
Total = A+B = NRs. 1,600.91
Overhead Misc. Expenditure of 15 % = NRs. 240.14
Grand Total (per no) = NRs. 1,841.05
Description of Item: Fixing of Fitting of 300 mm D.I. or G.I. Sluice Valve with Flanged Tail piece or Flanged Tee
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-1+17-3f S.L. pd 0.042 400.00 16.67 Misce. Expenses, T&P etc. required for jointing @1% 15m pipe
U.L. pd 0.250 275.00 68.75 length pipe cost (Rate per m of pipe) = 7829.12 1174.37
Labour Component (A) 85.42 Material & Equipment Component (B) 1174.37
RATE PER
Total = A+B = NRs. 1,259.78
Overhead Misc. Expenditure of 15 % = NRs. 188.97
Grand Total (per no) = NRs. 1,448.75
20/24
RATE ANALYSIS :
Description of Item: Fixing of Fitting of 350 mm D.I. or G.I. Sluice Valve with Flanged Tail piece or Flanged Tee
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-1+17-3g S.L. pd 0.667 400.00 266.80 Miss.. Expenses, T&P etc. required for jointing @1% 15m pipe
Adjusted U.L. pd 3.333 275.00 916.58 length pipe cost (Rate per m of pipe) = 9177.70 1376.66
Labour Component (A) 1183.38 Material & Equipment Component (B) 1376.66
RATE PER
Total = A+B = NRs. 2,560.03
Overhead Misc. Expenditure of 15 % = NRs. 384.00
Rate per number = NRs. 2,944.03
Description of Item : Fixing and Fitting of 80 mm D.I./G.I. Pipe fittings (Flanged bend, bell mouth, elbow, duck foot bend, water meter, reducer, etc)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-3+17-3a S.L. pd 0.083 400.00 33.33 Misce. Expenses, T&P etc. required for jointing @0.5% 15m pipe
U.L. pd 0.500 275.00 137.50 length pipe cost (Rate per m of pipe) = 893.67 67.03
Labour Component (A) 170.83 Material & Equipment Component (B) 67.03
RATE PER
Total = A+B = NRs. 237.86
Overhead Misc. Expenditure of 15 % = NRs. 35.68
Grand Total (per no) = NRs. 273.54
Description of Item : Fixing and Fitting of 150 mm D.I./G.I. Pipe fittings (Flanged bend, bell mouth, elbow, duck foot bend, water meter, reducer, etc)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-3+17-3d S.L. pd 0.139 400.00 55.56 Misce. Expenses, T&P etc. required for jointing @0.5% 15m pipe
U.L. pd 0.833 275.00 229.17 length pipe cost (Rate per m of pipe) = 3418.41 256.38
Labour Component (A) 284.72 Material & Equipment Component (B) 256.38
RATE PER
Total = A+B = NRs. 541.10
Overhead Misc. Expenditure of 15 % = NRs. 81.17
Grand Total (per no) = NRs. 622.27
Description of Item : Fixing and Fitting of 200 mm D.I./G.I. Pipe fittings (Flanged bend, bell mouth, elbow, duck foot bend, water meter, reducer, etc)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-3+17-3e S.L. pd 0.167 400.00 66.67 Misce. Expenses, T&P etc. required for jointing @0.5% 15m pipe
U.L. pd 1.000 275.00 275.00 length pipe cost (Rate per m of pipe) = 4635.90 347.69
Labour Component (A) 341.67 Material & Equipment Component (B) 347.69
RATE PER
Total = A+B = NRs. 689.36
Overhead Misc. Expenditure of 15 % = NRs. 103.40
Grand Total (per no) = NRs. 792.76
Description of Item : Fixing and Fitting of 250 mm D.I./G.I. Pipe fittings (Flanged bend, bell mouth, elbow, duck foot bend, water meter, reducer, etc)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-3+17-3f S.L. pd 0.222 400.00 88.89 Misce. Expenses, T&P etc. required for jointing @0.5% 15m pipe
U.L. pd 1.333 275.00 366.67 length pipe cost (Rate per m of pipe) = 6117.20 458.79
Labour Component (A) 455.56 Material & Equipment Component (B) 458.79
RATE PER
Total = A+B = NRs. 914.35
Overhead Misc. Expenditure of 15 % = NRs. 137.15
Grand Total (per no) = NRs. 1,051.50
21/24
RATE ANALYSIS :
Description of Item : Fixing and Fitting of 300 mm D.I./G.I. Pipe fittings (Flanged bend, bell mouth, elbow, duck foot bend, water meter, reducer, etc)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-3+17-3g S.L. pd 0.278 400.00 111.11 Misce. Expenses, T&P etc. required for jointing @0.5% 15m pipe
U.L. pd 1.667 275.00 458.33 length pipe cost (Rate per m of pipe) = 7829.12 587.18
Labour Component (A) 569.44 Material & Equipment Component (B) 587.18
RATE PER
Total = A+B = NRs. 1,156.63
Overhead Misc. Expenditure of 15 % = NRs. 173.49
Grand Total (per no) = NRs. 1,330.12
Description of Item : Fixing and Fitting of 350 mm D.I./G.I. Pipe fittings (Flanged bend, bell mouth, elbow, duck foot bend, water meter, reducer, etc)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4c-3+17-3g S.L. pd 0.444 400.00 177.60 Miss.. Expenses, T&P etc. required for jointing @0.5% 15m pipe
Adjusted U.L. pd 2.222 275.00 611.05 length pipe cost (Rate per m of pipe) = 9177.70 688.33
Labour Component (A) 788.65 Material & Equipment Component (B) 688.33
RATE PER
Total = A+B = NRs. 1,476.98
Overhead Misc. Expenditure of 15 % = NRs. 221.55
Grand Total (per no) = NRs. 1,698.52
Description of Item : Supply & Fixation of 16mm Dia. Iron Rod for the Safety Lung Purpose including breaking and embedding in RCC/B/W Walls
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
17-4a-3 (Adj) S.L. pd 0.500 400.00 200.00 Iron Bar (16mm dia) Kg 53.760 62.50 3360.00
For 30. Nos. U.L. pd 1.000 275.00 275.00 Iron Plates & Welding Kg 13.331 120.00 1599.75
Created Misc. expenses @ 5% of Labour cost 23.75
Labour Component (A) 475.00 Material & Equipment Component (B) 4959.75
RATE PER
Total = A+B = NRs. 5,434.75
Overhead Misc. Expenditure of 15 % = NRs. 815.21
Grand Total for 30 m. = NRs. 6,249.96
Rate per Running meter = NRs. 208.33
Description of Item : Dismantling of B/W in Cement Sand Mortar including disposal of material from the construction area
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
19-2 U.L. pd 2.120 275.00 583.00
For 1 Cq.m.
Labour Component (A) 583.00 Material & Equipment Component (B) 0.00
RATE PER
Total = A+B = NRs. 583.00
Overhead Misc. Expenditure of 15 % = NRs. 87.45
Rate per cubic meter = NRs. 670.45
Description of Item : Dismantling of RCC Works including disposal of material from the construction area
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
19-3 U.L. pd 11.000 275.00 3025.00
For 1 Cq.m.
Labour Component (A) 3025.00 Material & Equipment Component (B) 0.00
RATE PER
Total = A+B = NRs. 3,025.00
Overhead Misc. Expenditure of 15 % = NRs. 453.75
Rate per cubic meter = NRs. 3,478.75
22/24
RATE ANALYSIS :
Description of Item : Dismantling of PCC Works including disposal of material from the construction area
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
19-4 U.L. pd 4.000 275.00 1100.00
For 1 Cq.m.
Labour Component (A) 1100.00 Material & Equipment Component (B) 0.00
RATE PER
Total = A+B = NRs. 1,100.00
Overhead Misc. Expenditure of 15 % = NRs. 165.00
Rate per cubic meter = NRs. 1,265.00
Description of Item : Dismantling of Flag Stone/Interlocking cement Pavement Works incl. disposal of non-usable material from the construction area
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
19-7 U.L. pd 5.290 275.00 1454.75
For 10 Sq.m. 0.706 400.00 282.40
Labour Component (A) 1737.15 Material & Equipment Component (B) 0.00
RATE PER
Total = A+B = NRs. 1,737.15
Overhead Misc. Expenditure of 15 % = NRs. 260.57
Rate per cubic meter = NRs. 199.77
Description of Item : Dismantling of Blacktopped Pavement Works including disposal of material from the construction area
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
19-8 U.L. pd 10.000 275.00 2750.00
For 10 Sq.m.
Labour Component (A) 2750.00 Material & Equipment Component (B) 0.00
RATE PER
Total = A+B = NRs. 2,750.00
Overhead Misc. Expenditure of 15 % = NRs. 412.50
Rate per cubic meter = NRs. 316.25
Description of Item: Lifting of Pre cast RCC (slab) unit from casting yard and placing in position (average Distance = 30m)
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
22-1-g (Adj) U.L. pd 1.838 275.00 505.45 Tools and Plants 5% of Labour charge 25.27
For 1 m ton
Labour Component (A) 505.45 Material & Equipment Component (B) 25.27
RATE PER
Total = A+B = NRs. 530.72
Overhead Misc. Expenditure of 15 % = NRs. 79.61
Rate per Ton = NRs. 610.33
Description of Item: Disposal of surplus excavated earth piled at site beyod the premisses within 8 km distance
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
21-1 S.L. pd 0.000 400.00 0.00 Truck Hr 1.800 1003.79 1806.82
5 cu.m U.L. pd 1.000 275.00 275.00
Labour Component (A) 275.00 Material & Equipment Component (B) 1806.82
RATE PER
Total = A+B = NRs. 2,081.82
Overhead Misc. Expenditure of 15 % = NRs. 312.27
Grand Total = NRs. 2,394.10
Rate per m3 = NRs. 478.82
23/24
RATE ANALYSIS :
Description of Item: Supply and Installation of 28" Dia. water tight Heavy Manhole cover in specified location and position includig all lead and lift
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
1150 S.L. pd 0.500 400.00 200.00 Cir. M. Cover of 24" Sq.m 1 14,800.00 14800.00 Taken from
Adjusted U.L. pd 1.000 275.00 275.00 DUDBC
475.00 Material & Equipment Component (B) 14800.00
RATE PER
Total = A+B = NRs. 15,275.00
Overhead Misc. Expenditure of 15 % = NRs. 2,291.25
Rate per Set = NRs. 17,566.25
Description of Item: Supply and Installation of GI Sheet of 1.1mm thick as a Water-Stopper in Concrete Chambers and Tank
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
Created S.L. pd 0.250 400.00 100.00 GI Sheet of 1.1mm thk. Sq.m 1 689.36 689.36 Taken from
12m U.L. pd 1.000 275.00 275.00 DUDBC
Labour Component (A) 375.00 Material & Equipment Component (B) 689.36
RATE PER
Total = A+B = NRs. 1,064.36
Overhead Misc. Expenditure of 15 % = NRs. 159.65
Rate per Ton = NRs. 102.00
Description of Item: Supply and Installation of Pipe Valve Box complete Work
Item Labour (A) Material & Equipment (B)
No. Type Unit Qty. Rate (Rs) Amount (Rs) Type Unit Qty. Rate (Rs) Amount (Rs) Remarks
1167 S.L. pd 0.100 400.00 40.00 Valve Operation Cap Set 1.000 400.00 400.00
For Set U.L. pd 0.500 275.00 137.50 CI Pipe (100 mm) m 1.000 1000.00 1000.00
Created Brick Soling Sq 0.360 953.94 343.42
M-20 Concrete Cum 0.054 10572.21 570.90
Other Missceleneous % of tota 2,314.32 20% 462.86
Labour Component (A) 177.50 Material & Equipment Component (B) 2777.18
RATE PER
Total = A+B = NRs. 2,954.68
Overhead Misc. Expenditure of 15 % = NRs. 443.20
Rate per meter (m) = NRs. 3,397.88
24/24
TA 4893-NEP
Project Feasibility Study
APPENDIX 6
Table of Contents
1. Background.................................................................................................................................... 2
2. Construction Work Involved ........................................................................................................ 2
3. Guiding Principles for TMP around the DNI Construction Sites .............................................. 2
4. Operating Policies for TMP ......................................................................................................... 3
4.1 Review the construction schedules and methods .................................................................... 5
4.2 Identify preliminary traffic re-circulation................................................................................ 5
4.3 Traffic diversions ....................................................................................................................21
4.4 Analyse the impact due to street closure ...............................................................................26
4.5 Temporary parking ..................................................................................................................26
4.6 Coordination with other utility agencies................................................................................29
4.7 Public awareness and notifications ........................................................................................30
4.8 Public Redress Mechanism.....................................................................................................30
4.9 Install traffic control devices at the work zones and traffic diversion routes ......................31
5. Tentative Costs for Traffic Control Devices & Enforcements.................................................34
Conceptual Traffic Management Plan for the Pilot DNI Area Page i
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
1. Background
1. This Project proposes a pilot project for the distribution network improvements (DNI)
along a portion of the Study Area. The Study Area for this pilot DNI i.e. the area bounded
between the Kathmandu Ring Road (Dhumbarahi- Gausahala section), Pashupati
Sadak(Ratopul Bridge – Gaushala section) and the Dhobikhola Link Road (Ratopul Bridge-
Gopi Krishna Bridge) was selected based on a prioritisation criteria outlined in the Draft Capital
Investment Asset Management Plan (CIAMP) prepared by the Consultants on 16th October
2009.
2. The Guideline on Utility Management Coordination was included in the CIAMP Final
Report submitted in February 2010. This document guides the Kathmandu Upatyaka Khanepani
Limited (KUKL) to initiate utility management throughout the Project's cycle (feasibility to defect
liability period) but this document itself is open to further amendments if deemed necessary by
the custodian of the same i.e. the Utility Management Coordination Sub-Committee set up by
the Project Implementing Directorate (PID) recently as experience builds up. The traffic
management plan (TMP) is a component of the utility management coordination.
3. This document outlines a conceptual TMP for the pilot DNI works and will evolve as
more data are available during the construction phase of the pilot DNI works. The refinement of
this conceptual TMP is evident given the fact that a detailed TMP for a construction project is
still a new concept in Nepal.
4. This document concentrates on DNI works with special focus to the pilot area conditions
but the general principles are valid for the other components, if, customised accordingly.
Conceptual Traffic Management Plan for the Pilot DNI Area Page 2
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Conceptual Traffic Management Plan for the Pilot DNI Area Page 3
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Police
Coordination
Conceptual Traffic Management Plan for the Pilot DNI Area Page 4
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Conceptual Traffic Management Plan for the Pilot DNI Area Page 5
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
14. Currently, as-built plans of the utilities within the pilot area are not available and
therefore it is not possible to precisely identify those streets where traffic movements can be
maintained, albeit in a controlled manner, even when the constructions for the pilot works takes
in such streets. This exercise will take place on a case by case basis during the construction
itself when the daily work schedule is definite and as-built plan of the utilities are available (refer
to the Guideline for the Utility Management Coordination).
15. While overhead electric cables invariably exist on both sides of the street in the built-up
areas, the location of collector sewer pipe is not known at this stage. These aspects including
further constraints such as presence of two or more utilities in the street concerned will further
constrain the space available for the traffic circulation during the pilot constructions. Figure 2
and 3 illustrate the carriageway available for traffic movements along streets of different widths
(single and four lane), subjected to typical constraints, when the constructions take place at
such streets. Both the examples assume the following conditions for evaluating the carriageway
available for traffic movements along the pilot area.
Two layouts of collector sewers in the streets – (i) case 1: sewer located at the centre
and (ii) case 2: sewer at the edge of the street.
2.5 m wide sidewalks at both sides of the street.
Most of the pilot alignment complies with the minimum setback required from various
utility agencies with exception to the requirements from buildings. .
Compliance to the minimum setback between the DNI pipe and buildings not feasible in
most of the built-up locations. Therefore, protection measures necessary are assumed to
be in place to ensure the structural integrity of the buildings.
Two-way traffic movements under controlled conditions (slow speeds, on-site
enforcement and patrol) are provided as far as possible.
All traffic movements are under controlled conditions (slow speeds, on-site enforcement
and patrol).
Traffic Police enforce pedestrians to use the sidewalks on the far-side of the DNI trench
along the narrow streets under Case 2 conditions (refer to Figure 2). Traffic Police can
permit pedestrians to use the space available at the near side of the trench under strict
control and when it is safe to do so.
All the electrical poles are laterally offset 600 mm from the kerb
The effective carriageways outlined in this report represent the typical condition existing
at the pilot area. .
Excavations take place at only one side of the street at a time and installation comprise
only single pipes.
Connections to the individual households take place only at one side of a street at a time
and all the traverse trenches for these connections are decked up with steel plates of
adequate strength to withstand the anticipated traffic loads.
Access to buildings are decked up with wooden planks or steel plates of required widths
and strength based on the type of access existing i.e. wide or narrow entry, at all times
during the constructions.
The collector sewers for the case 2 conditions are assumed to lie right adjacent to the
kerbs.
All the trenches in the layout pertain to manual excavations.
Conceptual Traffic Management Plan for the Pilot DNI Area Page 6
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Case 1: Collector
Sewer at the
centre of the
road
Case 2:
Collector
Sewer at
the edge of
the road
Conceptual Traffic Management Plan for the Pilot DNI Area Page 7
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Figure 3 Available Carriageway During DNI Constructions (4-lane road with Sidewalks)
Case 1: Collector
Sewer at the
centre of the
road
Case 2:
Collector
Sewer at
the edge of
the road
Conceptual Traffic Management Plan for the Pilot DNI Area Page 8
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
16. From the perspective of pedestrian safety, it is not preferable to construct the DNI
trenches in the sidewalks as shown in Figure 2 as one of the sidewalks is closed to the
pedestrians. However, this practice is often in many countries where the street is narrow.
Therefore, as far as possible, the DNI trench along the narrow roads (single or intermediate
lane) will use one side of the sidewalks or shoulder, if available, to permit traffic movements on
the far side of the trench. In addition, for the streets, two lane or wider, the shoulder or sidewalk
will be preserved unless two-way traffic movements at the far side of the trench is no longer
feasible.
17. Figure 3 also shows that for the pilot works, controlled ONE-WAY movements (speeds
less than 10 kph) restricted to motor-cycles and bicycles may be feasible along the near side of
the trench in a wide street under Case 2 conditions. Based on the Figure 2 and 3, the effective
carriageway is most constrained under the Case 2 conditions.
18. Table 1 to 10 summarise the effective carriageway available at the far-end of the trench
for different streets subjected to various constraints during the pilot DNl works. On a
conservative estimate, the following options are available for managing the traffic circulation
when the pilot constructions take place along particular streets.
Option 1: Two way movements for all vehicles:
At four lane streets (14 m), under both manual and mechanised excavations.
Three lane streets (10 .5 m), under manual excavations, pipe installations up to 150 mm in
diameter and if there are no collector sewers.
Option 2: Two-way movements at two lane streets (7 m) restricted to certain vehicles:
Up to micro-buses if no collector sewer/high transmission lines and pipes installations
limited to 90 mm diameter.
Restricted up to tempos if no collector sewer and pipe installations limited to 200 mm
diameter.
Option 3: Controlled ONE-WAY movements for small vehicles
At intermediate-lane streets (5.5 m) for up to cars under manual excavations, pipe
installations do not exceed 200 mm diameter and there is no high transmission/r sewer
lines.
Option 4: Full street closure and traffic diversion in advance from both directions
Option 5: Maintaining existing traffic flow with construction confined to night-time.
19. In contrast to the above choices, there is more flexibility for maintaining the traffic flow
along the various streets when the existing shoulders or sidewalks are used as well. However,
compliance with the minimum setback between the DNI trench and the high transmission lines
or underground electricity lines is not feasible unless the shoulder or sidewalk is at least 1.65 m.
Therefore, necessary insulation cover against electrical shocks is necessary in the narrow
streets if the pipes are installed under the shoulder or sidewalk.
20. Normally, the use of the shoulders or sidewalks for traffic circulation along wide streets
are not recommended due to safety implications to pedestrians at such roads due to higher
vehicle speeds as well as pedestrian traffic. However, the Utility Management Coordinator can
re-assess this issue in consultation with the proposed Utility Management Sub-committee or
one-on-one discussions with the Traffic Police and the Department of Roads if directed to do so.
Conceptual Traffic Management Plan for the Pilot DNI Area Page 9
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
The following options are therefore available during DNI constructions when the shoulder and
sidewalks are used in the narrow streets.
Option 2: Two-way movements restricted to certain types of vehicles
At intermediate-lane streets, restricted up to micro-buses if no sewer lines and pipe
installations do not exceed 500 mm diameter and the latter insulated from existing electricity
poles or high transmission lines.
At single lane streets, for motor-cycles only if no sewer lines and pipe installations do not
exceed 150 mm diameter.
Option 3: ONE-WAY movements confined to smaller vehicles
At single lane streets for up to micro-buses if no sewer lines, manual excavations and pipe
installations do not exceed 200 mm diameter.
21. While it is the intention of the TMP to ensure minimum disruptions to the traffic mobility,
the same including the pedestrians will invariably be affected during the constructions.
Therefore, public awareness well in advance about these situations is very important so that
commuters and pedestrians can plan their travel accordingly.
Conceptual Traffic Management Plan for the Pilot DNI Area Page 10
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Table 1 Available Carriageway at Single-Lane Streets during Manual Excavations for the Pilot DNI Works
Equipment (m)
Trenching
Space for
(m)
No UG elect. High
No utilities UG elect. Utility, w High transm.,
utilities, with 1 m Utility, no 1m transm., w1m Sewer, no Sewer, 1
Pipe Dia. no SH/SW SH/SW SH/SW SH/SW* no SH/SW SH/SW* SH/SW m SH/SW
FULL FULL FULL FULL
(i) 75 mm Ø 0.23 1.00 2.40 1.38 2.38 CLOSURE 2.38 CLOSURE 2.38 CLOSURE CLOSURE
FULL FULL FULL FULL
(ii) 90 mm Ø 0.27 1.00 2.40 1.33 2.33 CLOSURE 2.33 CLOSURE 2.33 CLOSURE CLOSURE
FULL FULL FULL FULL FULL
(iii) 110 mm Ø 0.33 1.00 2.40 CLOSURE 2.27 CLOSURE 2.27 CLOSURE 2.27 CLOSURE CLOSURE
FULL FULL FULL FULL FULL
(iv) 125 mm Ø 0.38 1.00 2.40 CLOSURE 2.23 CLOSURE 2.23 CLOSURE 2.23 CLOSURE CLOSURE
FULL FULL FULL FULL FULL
(v) 140 mm Ø 0.42 1.00 2.40 CLOSURE 2.18 CLOSURE 2.18 CLOSURE 2.18 CLOSURE CLOSURE
FULL FULL FULL FULL FULL
(i) 150 mm Ø 0.45 1.00 2.40 CLOSURE 2.15 CLOSURE 2.15 CLOSURE 2.15 CLOSURE CLOSURE
FULL FULL FULL FULL FULL
(ii) 200 mm Ø 0.60 1.00 2.40 CLOSURE 2.00 CLOSURE 2.00 CLOSURE 2.00 CLOSURE CLOSURE
FULL FULL FULL FULL FULL
(iii) 300 mm Ø 0.90 1.00 2.40 CLOSURE 1.70 CLOSURE 1.70 CLOSURE 1.70 CLOSURE CLOSURE
FULL FULL FULL FULL FULL
(iv) 400 mm Ø 1.20 1.00 2.40 CLOSURE 1.40 CLOSURE 1.40 CLOSURE 1.40 CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(v) 500 mm Ø 1.50 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(vi) 600 mm Ø 1.80 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
Conceptual Traffic Management Plan for the Pilot DNI Area Page 11
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Table 2 Available Carriageway at the Single-Lane Streets during Mechanised Excavations for the Pilot DNI Works
Equipment (m)
Trenching
Space for
(m)
High
No No utilities UG elect. UG elect. High transm., w
utilities, with 1 m Utility, no Utility, w 1 transm., 1m Sewer, no Sewer, 1 m
Pipe Dia. no SH/SW SH/SW SH/SW m SH/SW* no SH/SW SH/SW* SH/SW SH/SW
FULL FULL FULL FULL FULL FULL FULL FULL
(i) 75 mm Ø 0.23 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(ii) 90 mm Ø 0.27 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(iii) 110 mm Ø 0.33 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(iv) 125 mm Ø 0.38 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(v) 140 mm Ø 0.42 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(i) 150 mm Ø 0.45 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(ii) 200 mm Ø 0.60 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(iii) 300 mm Ø 0.90 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(iv) 400 mm Ø 1.20 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(v) 500 mm Ø 1.50 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
FULL FULL FULL FULL FULL FULL FULL FULL
(vi) 600 mm Ø 1.80 1.00 2.40 CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE CLOSURE
Conceptual Traffic Management Plan for the Pilot DNI Area Page 12
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Table 3 Available Carriageway at Intermediate-Lane Streets during Manual Excavations for the Pilot DNI Works
Equipment (m)
Trenching
Space for
(m)
High
No No utilities UG elect. UG elect. High transm., w
utilities, with 1 m Utility, no Utility, w 1 transm., 1m Sewer, no Sewer, 1 m
Pipe Dia. no SH/SW SH/SW SH/SW m SH/SW* no SH/SW SH/SW* SH/SW SH/SW
FULL
(i) 75 mm Ø 0.23 1.00 2.40 3.38 4.38 2.13 4.38 1.83 4.38 CLOSURE 1.38
FULL
(ii) 90 mm Ø 0.27 1.00 2.40 3.33 4.33 2.08 4.33 1.78 4.33 CLOSURE 1.33
FULL FULL
(iii) 110 mm Ø 0.33 1.00 2.40 3.27 4.27 2.02 4.27 1.72 4.27 CLOSURE CLOSURE
FULL FULL
(iv) 125 mm Ø 0.38 1.00 2.40 3.23 4.23 1.98 4.23 1.68 4.23 CLOSURE CLOSURE
FULL FULL
(v) 140 mm Ø 0.42 1.00 2.40 3.18 4.18 1.93 4.18 1.63 4.18 CLOSURE CLOSURE
FULL FULL
(i) 150 mm Ø 0.45 1.00 2.40 3.15 4.15 1.90 4.15 1.60 4.15 CLOSURE CLOSURE
FULL FULL
(ii) 200 mm Ø 0.60 1.00 2.40 3.00 4.00 1.75 4.00 1.45 4.00 CLOSURE CLOSURE
FULL FULL FULL
(iii) 300 mm Ø 0.90 1.00 2.40 2.70 3.70 1.45 3.70 CLOSURE 3.70 CLOSURE CLOSURE
FULL FULL FULL FULL
(iv) 400 mm Ø 1.20 1.00 2.40 2.40 3.40 CLOSURE 3.40 CLOSURE 3.40 CLOSURE CLOSURE
FULL FULL FULL FULL
(v) 500 mm Ø 1.50 1.00 2.40 2.10 3.10 CLOSURE 3.10 CLOSURE 3.10 CLOSURE CLOSURE
FULL FULL FULL FULL
(vi) 600 mm Ø 1.80 1.00 2.40 1.80 2.80 CLOSURE 2.80 CLOSURE 2.80 CLOSURE CLOSURE
Conceptual Traffic Management Plan for the Pilot DNI Area Page 13
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Table 4 Available Carriageway at the Intermediate-Lane Streets during Mechanised Excavations for the Pilot DNI Works
Equipment (m)
Trenching
Space for
(m)
High
No No utilities UG elect. UG elect. High transm., w
utilities, with 1 m Utility, no Utility, w 1 transm., 1m Sewer, no Sewer, 1 m
Pipe Dia. no SH/SW SH/SW SH/SW m SH/SW* no SH/SW SH/SW* SH/SW SH/SW
FULL FULL FULL FULL
(i) 75 mm Ø 0.23 1.00 2.40 2.20 3.20 CLOSURE 3.20 CLOSURE 3.20 CLOSURE CLOSURE
FULL FULL FULL FULL
(ii) 90 mm Ø 0.27 1.00 2.40 2.20 3.20 CLOSURE 3.20 CLOSURE 3.20 CLOSURE CLOSURE
FULL FULL FULL FULL
(iii) 110 mm Ø 0.33 1.00 2.40 2.20 3.20 CLOSURE 3.20 CLOSURE 3.20 CLOSURE CLOSURE
FULL FULL FULL FULL
(iv) 125 mm Ø 0.38 1.00 2.40 2.20 3.20 CLOSURE 3.20 CLOSURE 3.20 CLOSURE CLOSURE
FULL FULL FULL FULL
(v) 140 mm Ø 0.42 1.00 2.40 2.20 3.20 CLOSURE 3.20 CLOSURE 3.20 CLOSURE CLOSURE
FULL FULL FULL FULL
(i) 150 mm Ø 0.45 1.00 2.40 2.20 3.20 CLOSURE 3.20 CLOSURE 3.20 CLOSURE CLOSURE
FULL FULL FULL FULL
(ii) 200 mm Ø 0.60 1.00 2.40 2.20 3.20 CLOSURE 3.20 CLOSURE 3.20 CLOSURE CLOSURE
FULL FULL FULL FULL
(iii) 300 mm Ø 0.90 1.00 2.40 2.20 3.20 CLOSURE 3.20 CLOSURE 3.20 CLOSURE CLOSURE
FULL FULL FULL FULL
(iv) 400 mm Ø 1.20 1.00 2.40 2.20 3.20 CLOSURE 3.20 CLOSURE 3.20 CLOSURE CLOSURE
FULL FULL FULL FULL
(v) 500 mm Ø 1.50 1.00 2.40 2.10 3.10 CLOSURE 3.10 CLOSURE 3.10 CLOSURE CLOSURE
FULL FULL FULL FULL
(vi) 600 mm Ø 1.80 1.00 2.40 1.80 2.80 CLOSURE 2.80 CLOSURE 2.80 CLOSURE CLOSURE
Source: Consultant's estimate CWY = carriageway SH= shoulder SW = side-walk NA = not available
Conceptual Traffic Management Plan for the Pilot DNI Area Page 14
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Table 5 Available Carriageway at the Two-Lane Streets during Manual Excavations for the Pilot DNI Works
Equipment (m)
Trenching
Space for
(m)
High
No No utilities UG elect. UG elect. High transm., w
utilities, with 1 m Utility, no Utility, w 1 transm., 1m Sewer, no Sewer, 1 m
Pipe Dia. no SH/SW SH/SW SH/SW m SH/SW no SH/SW SH/SW SH/SW SH/SW
(i) 75 mm Ø 0.23 1.00 2.40 4.88 5.88 3.63 4.63 3.33 4.33 1.88 2.88
(ii) 90 mm Ø 0.27 1.00 2.40 4.83 5.83 3.58 4.58 3.28 4.28 1.83 2.83
(iii) 110 mm Ø 0.33 1.00 2.40 4.77 5.77 3.52 4.52 3.22 4.22 1.77 2.77
(iv) 125 mm Ø 0.38 1.00 2.40 4.73 5.73 3.48 4.48 3.18 4.18 1.73 2.73
(v) 140 mm Ø 0.42 1.00 2.40 4.68 5.68 3.43 4.43 3.13 4.13 1.68 2.68
(i) 150 mm Ø 0.45 1.00 2.40 4.65 5.65 3.40 4.40 3.10 4.10 1.65 2.65
(ii) 200 mm Ø 0.60 1.00 2.40 4.50 5.50 3.25 4.25 2.95 3.95 1.50 2.50
FULL
(iii) 300 mm Ø 0.90 1.00 2.40 4.20 5.20 2.95 3.95 2.65 3.65 CLOSURE 2.20
FULL
(iv) 400 mm Ø 1.20 1.00 2.40 3.90 4.90 2.65 3.65 2.35 3.35 CLOSURE 1.90
FULL
(v) 500 mm Ø 1.50 1.00 2.40 3.60 4.60 2.35 3.35 2.05 3.05 CLOSURE 1.60
FULL
(vi) 600 mm Ø 1.80 1.00 2.40 3.30 4.30 2.05 3.05 1.75 2.75 CLOSURE 1.30
Source: Consultant's estimate CWY = carriageway SH= shoulder SW = side-walk NA = not available
Conceptual Traffic Management Plan for the Pilot DNI Area Page 15
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Table 6 Available Carriageway at the Two-Lane Streets during Mechanised Excavations for the Pilot DNI Works
Equipment (m)
Trenching
Space for
(m)
High
No No utilities UG elect. UG elect. High transm., w
utilities, with 1 m Utility, no Utility, w 1 transm., 1m Sewer, no Sewer, 1 m
Pipe Dia. no SH/SW SH/SW SH/SW m SH/SW no SH/SW SH/SW SH/SW SH/SW
FULL
(i) 75 mm Ø 0.23 1.00 2.40 3.70 4.70 2.45 3.45 2.15 3.15 CLOSURE 1.70
FULL
(ii) 90 mm Ø 0.27 1.00 2.40 3.70 4.70 2.45 3.45 2.15 3.15 CLOSURE 1.70
FULL
(iii) 110 mm Ø 0.33 1.00 2.40 3.70 4.70 2.45 3.45 2.15 3.15 CLOSURE 1.70
FULL
(iv) 125 mm Ø 0.38 1.00 2.40 3.70 4.70 2.45 3.45 2.15 3.15 CLOSURE 1.70
FULL
(v) 140 mm Ø 0.42 1.00 2.40 3.70 4.70 2.45 3.45 2.15 3.15 CLOSURE 1.70
FULL
(i) 150 mm Ø 0.45 1.00 2.40 3.70 4.70 2.45 3.45 2.15 3.15 CLOSURE 1.70
FULL
(ii) 200 mm Ø 0.60 1.00 2.40 3.70 4.70 2.45 3.45 2.15 3.15 CLOSURE 1.70
FULL
(iii) 300 mm Ø 0.90 1.00 2.40 3.70 4.70 2.45 3.45 2.15 3.15 CLOSURE 1.70
FULL
(iv) 400 mm Ø 1.20 1.00 2.40 3.70 4.70 2.45 3.45 2.15 3.15 CLOSURE 1.70
FULL
(v) 500 mm Ø 1.50 1.00 2.40 3.60 4.60 2.35 3.35 2.05 3.05 CLOSURE 1.60
FULL
(vi) 600 mm Ø 1.80 1.00 2.40 3.30 4.30 2.05 3.05 1.75 2.75 CLOSURE 1.30
Source: Consultant's estimate CWY = carriageway SH= shoulder SW = side-walk NA = not available
Conceptual Traffic Management Plan for the Pilot DNI Area Page 16
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Table 7 Available Carriageway at the Three-Lane Streets during Manual Excavations for the Pilot DNI Works
Available CWY at the Far-end of the DNI Trench under Case 2: Collector Sewer Located at the Side
Equipment (m)
High
No No utilities UG elect. UG elect. High transm., w
utilities, with 1 m Utility, no Utility, w 1 transm., 1m Sewer, no Sewer, 1 m
Pipe Dia. no SH/SW SH/SW SH/SW m SH/SW no SH/SW SH/SW SH/SW SH/SW
(i) 75 mm Ø 0.23 1.00 2.40 8.38 8.38 7.13 7.13 6.83 6.83 5.38 5.38
(ii) 90 mm Ø 0.27 1.00 2.40 8.33 8.33 7.08 7.08 6.78 6.78 5.33 5.33
(iii) 110 mm Ø 0.33 1.00 2.40 8.27 8.27 7.02 7.02 6.72 6.72 5.27 5.27
(iv) 125 mm Ø 0.38 1.00 2.40 8.23 8.23 6.98 6.98 6.68 6.68 5.23 5.23
(v) 140 mm Ø 0.42 1.00 2.40 8.18 8.18 6.93 6.93 6.63 6.63 5.18 5.18
(i) 150 mm Ø 0.45 1.00 2.40 8.15 8.15 6.90 6.90 6.60 6.60 5.15 5.15
(ii) 200 mm Ø 0.60 1.00 2.40 8.00 8.00 6.75 6.75 6.45 6.45 5.00 5.00
(iii) 300 mm Ø 0.90 1.00 2.40 7.70 7.70 6.45 6.45 6.15 6.15 4.70 4.70
(iv) 400 mm Ø 1.20 1.00 2.40 7.40 7.40 6.15 6.15 5.85 5.85 4.40 4.40
(v) 500 mm Ø 1.50 1.00 2.40 7.10 7.10 5.85 5.85 5.55 5.55 4.10 4.10
(vi) 600 mm Ø 1.80 1.00 2.40 6.80 6.80 5.55 5.55 5.25 5.25 3.80 3.80
Source: Consultant's estimate CWY = carriageway SH= shoulder SW = side-walk NA = not available
Conceptual Traffic Management Plan for the Pilot DNI Area Page 17
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Table 8 Available Carriageway at the Three-Lane Streets during Mechanised Excavations for the Pilot DNI Works
Equipment (m)
High
No No utilities UG elect. UG elect. High transm., w
utilities, with 1 m Utility, no Utility, w 1 transm., 1m Sewer, no Sewer, 1 m
Pipe Dia. no SH/SW SH/SW SH/SW m SH/SW no SH/SW SH/SW SH/SW SH/SW
(i) 75 mm Ø 0.23 1.00 2.40 7.20 7.20 5.95 5.95 5.65 5.65 4.20 4.20
(ii) 90 mm Ø 0.27 1.00 2.40 7.20 7.20 5.95 5.95 5.65 5.65 4.20 4.20
(iii) 110 mm Ø 0.33 1.00 2.40 7.20 7.20 5.95 5.95 5.65 5.65 4.20 4.20
(iv) 125 mm Ø 0.38 1.00 2.40 7.20 7.20 5.95 5.95 5.65 5.65 4.20 4.20
(v) 140 mm Ø 0.42 1.00 2.40 7.20 7.20 5.95 5.95 5.65 5.65 4.20 4.20
(i) 150 mm Ø 0.45 1.00 2.40 7.20 7.20 5.95 5.95 5.65 5.65 4.20 4.20
(ii) 200 mm Ø 0.60 1.00 2.40 7.20 7.20 5.95 5.95 5.65 5.65 4.20 4.20
(iii) 300 mm Ø 0.90 1.00 2.40 7.20 7.20 5.95 5.95 5.65 5.65 4.20 4.20
(iv) 400 mm Ø 1.20 1.00 2.40 7.20 7.20 5.95 5.95 5.65 5.65 4.20 4.20
(v) 500 mm Ø 1.50 1.00 2.40 7.10 7.91 5.85 6.66 5.55 6.36 4.10 4.91
(vi) 600 mm Ø 1.80 1.00 2.40 6.80 7.61 5.55 6.36 5.25 6.06 3.80 4.61
Source: Consultant's estimate CWY = carriageway SH= shoulder SW = side-walk NA = not available
Conceptual Traffic Management Plan for the Pilot DNI Area Page 18
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Table 9 Available Carriageway at the Four-Lane Streets during Manual Excavations for the Pilot DNI Works
Equipment (m)
Trenching
Space for
(m)
High
No No utilities UG elect. UG elect. High transm., w
utilities, with 1 m Utility, no Utility, w 1 transm., 1m Sewer, no Sewer, 1 m
Pipe Dia. no SH/SW SH/SW SH/SW m SH/SW no SH/SW SH/SW SH/SW SH/SW
(i) 75 mm Ø 0.23 1.00 2.40 11.88 11.88 10.63 10.63 10.33 10.33 8.88 8.88
(ii) 90 mm Ø 0.27 1.00 2.40 11.83 11.83 10.58 10.58 10.28 10.28 8.83 8.83
(iii) 110 mm Ø 0.33 1.00 2.40 11.77 11.77 10.52 10.52 10.22 10.22 8.77 8.77
(iv) 125 mm Ø 0.38 1.00 2.40 11.73 11.73 10.48 10.48 10.18 10.18 8.73 8.73
(v) 140 mm Ø 0.42 1.00 2.40 11.68 11.68 10.43 10.43 10.13 10.13 8.68 8.68
(i) 150 mm Ø 0.45 1.00 2.40 11.65 11.65 10.40 10.40 10.10 10.10 8.65 8.65
(ii) 200 mm Ø 0.60 1.00 2.40 11.50 11.50 10.25 10.25 9.95 9.95 8.50 8.50
(iii) 300 mm Ø 0.90 1.00 2.40 11.20 11.20 9.95 9.95 9.65 9.65 8.20 8.20
(iv) 400 mm Ø 1.20 1.00 2.40 10.90 10.90 9.65 9.65 9.35 9.35 7.90 7.90
(v) 500 mm Ø 1.50 1.00 2.40 10.60 10.60 9.35 9.35 9.05 9.05 7.60 7.60
(vi) 600 mm Ø 1.80 1.00 2.40 10.30 10.30 9.05 9.05 8.75 8.75 7.30 7.30
Source: Consultant's estimate CWY = carriageway SH= shoulder SW = side-walk NA = not available
Conceptual Traffic Management Plan for the Pilot DNI Area Page 19
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Table 10 Available Carriageway at the Four-Lane Streets during Mechanised Excavations for the Pilot DNI Works
Equipment (m)
Trenching
Space for
(m)
Sewer, 1 No No utilities UG elect. UG elect. High High Sewer, 1
m utilities, with 1 m Utility, no Utility, w 1 transm., transm., w Sewer, no m
Pipe Dia. SH/SW no SH/SW SH/SW SH/SW m SH/SW no SH/SW 1 m SH/SW SH/SW SH/SW
(i) 75 mm Ø 0.23 1.00 2.40 8.88 10.70 10.70 9.45 9.45 9.15 9.15 7.70 7.70
(ii) 90 mm Ø 0.27 1.00 2.40 8.83 10.70 10.70 9.45 9.45 9.15 9.15 7.70 7.70
(iii) 110 mm Ø 0.33 1.00 2.40 8.77 10.70 10.70 9.45 9.45 9.15 9.15 7.70 7.70
(iv) 125 mm Ø 0.38 1.00 2.40 8.73 10.70 10.70 9.45 9.45 9.15 9.15 7.70 7.70
(v) 140 mm Ø 0.42 1.00 2.40 8.68 10.70 10.70 9.45 9.45 9.15 9.15 7.70 7.70
(i) 150 mm Ø 0.45 1.00 2.40 8.65 10.70 10.70 9.45 9.45 9.15 9.15 7.70 7.70
(ii) 200 mm Ø 0.60 1.00 2.40 8.50 10.70 10.70 9.45 9.45 9.15 9.15 7.70 7.70
(iii) 300 mm Ø 0.90 1.00 2.40 8.20 10.70 10.70 9.45 9.45 9.15 9.15 7.70 7.70
(iv) 400 mm Ø 1.20 1.00 2.40 7.90 10.70 10.70 9.45 9.45 9.15 9.15 7.70 7.70
(v) 500 mm Ø 1.50 1.00 2.40 7.60 10.60 11.41 9.35 10.16 9.05 9.86 7.60 8.41
(vi) 600 mm Ø 1.80 1.00 2.40 7.30 10.30 11.11 9.05 9.86 8.75 9.56 7.30 8.11
Source: Consultant's estimate CWY = carriageway SH= shoulder SW = side-walk NA = not available
Conceptual Traffic Management Plan for the Pilot DNI Area Page 20
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Conceptual Traffic Management Plan for the Pilot DNI Area Page 21
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
None at
15 Chabahil Ganesh Marg 6.25 Chabahil side 110 ~ 125 Option 5 - Night Constructions
16 Navasudhar Galli 2.55 ? 75 Option 4: Full closure
Option 2 - two-way for motor-
shoulder/side- cycles only or Option 4 - Full
17 Natyashwori Marg 3.25 walk varies 90 ~ 140 Closure
18 Muse Ganesh Marg 4.45 ? 125 Option 4: Full closure
19 Charumati Marg 3.50 ? 125 Option 4: Full closure
Option 3: ONE-WAY for cars &
motor-cycles if no sewer or
Check for Option 4 - Full closure at the
20 Budhang Marg 5.15 footpath 125 narrow section
21 Bajkhala Galli 2.80 90 Option 4: Full closure
22 Shanumishra Galli 2.35 75 Option 4: Full closure
Option 3: ONE-WAY for cars &
23 Charu Galli 3.75 none 90 ~ 110 motor-cycles if no sewer
24 Kutubahal Galli 3.00 none 90 Option 4: Full closure
Option 2: Two-way for motor-
25 Panahitti Marg 4.55 none 90 cycles if no sewer
31 Jayabageshwori Marg 6.05 Paved 110 ~ 125 (1) Option 4: Full closure or (2)
shoulder of Option 5: night constructions
varying
Conceptual Traffic Management Plan for the Pilot DNI Area Page 22
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
43 Punya Marg
4.00 none 90 Option 4: Full closure
none for most
44 Paneku Marg 90
4.42 part Option 4: Full closure
GR shoulder (1) Option 3: ONE-WAY for cars,
of varying tempos and motor-cycles under
widths in manual excavations or (2) Option
45 Lamapokhari Marg 5.3 some section 75 ~ 140 4: Full closure
Conceptual Traffic Management Plan for the Pilot DNI Area Page 23
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Conceptual Traffic Management Plan for the Pilot DNI Area Page 24
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
27. The design capacity is the traffic volume which offers reasonable degree of freedom for
drivers to negotiate through the streets and is 45 percent of the theoretical capacity of the street.
Based on the analysis above, the existing traffic along the Gaushala – Dhumbarahi section of
the Ring Road is oversaturated during the peak hour periods (morning and evening) implying
that the vehicles during these times are at a stand-still. Therefore, the preliminary options for
traffic circulation at this street during the pilot constructions in this street (refer to Table 11)
should be confined to the off-peak periods. By contrast, the preliminary traffic circulation
identified for other streets during the pilot constructions taking place in these streets (Pashupati
Sadak, Rudramati Marg, Chandrabinayak Marg, Dharmabhakta Marg, etc,) are still valid.
28. Within the pilot area, the following streets will form part of the route for the traffic
diversion either independently or in combination with other road networks throughout the
construction period.
Rudramati Marg (Dhobi Khola Link Road)
Chandrabinayak Marg
Chabahil Ganesh Marg
Natyashwori Margly
Dharmabhakta Marg
Jayabageshwori Marg
Pashupati Sadak (Ratopul –Gausahala section)
Ring Road (Gauhala – Chabahil section)
Conceptual Traffic Management Plan for the Pilot DNI Area Page 25
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
The working hours and daily work schedule along the pilot area will dictate the period up to
which the traffic diversion should be in place.
29. It may be necessary to carry the pilot constructions at Rishi Bhadra Marg during the
night-time as it is the access road to both Medicare National Hospital and Om Hospital. In any
event, ambulance and serious patients to these hospitals should have access to these
hospitals. Therefore, the traffic police at the site will need to regulate the traffic to allow ONE-
WAY access to such emergency vehicles from the opposing direction when construction is
taking place at this street.
30. Owing to the heavy pedestrian traffic, pilot constructions along the Chandra Ganesh
Marg should take place during the night-time only.
31. During the construction phase, peak hour traffic counts at strategic locations of the pilot
area are necessary to accurately assess the capacity of the strategic streets in the pilot area to
finalise the traffic circulation measures identified in the preliminary assessment in tandem to the
coordination process.
Conceptual Traffic Management Plan for the Pilot DNI Area Page 26
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
should negotiate with the concerned property-owner regarding compensation for the use of their
property. It is premature at this stage to predict the compensation that will be necessary in this
regard. Moreover, it is the prerogative of the property owner whether to or not permit the use of
his or her land for temporary parking.
36. The Project's financial obligation in terms of providing off-street parking would include
land rentals, salary for the parking attendants, necessary fencing of the property and
compensation to roadside vendors for loss of businesses. Some of these issues also relate to or
pertain to resettlement activities for this Project. As per discussions with the Project, the
average compensation for each affected vendor is around NRs. 1,130, which is equivalent to
the average profit estimated by the Consultant. A certain budget have been set aside for
compensation to vendors in terms of lost business during the pilot construction in the social and
resettlement assessment for this Project. It is however worthwhile to mention that the period of
rental of the parking areas could be varied from short to long duration depending on the speed
of the constructions which will determine the duration when the road-block is lifted.
37. Figure 4 shows the potential locations for both off-street and on-street parking on
temporary basis as result of the reconnaissance survey.
Conceptual Traffic Management Plan for the Pilot DNI Area Page 27
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Figure 4 Potential Areas for Temporary Parking During the Pilot DNI Constructions
Handigaon Bridge
Chabahil Vegetable
Market
Pashupati Sadak
Conceptual Traffic Management Plan for the Pilot DNI Area Page 28
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
38. The following (refer to Figure 4) are potential areas for temporary parking in the pilot
area.
Off-street Parking:
A Area bounded between Ring Road (Chabahil- Dhumbarahi section), Rudramati (DKLR)
and Chabahil Ganesh Marg
(1) Open fields along the right side of Rudramati Marg from Handigaon Bridge (all
private properties)
(2) Open field between the Dhobi Khola (River) meander and DKLR further north from
Handigaon Bridge (public but usable during dry season only)
(3) Open ground inside the Chabahil vegetable market (public, area is enclosed with
gate for access; temporary relocation of some of the vegetable stalls may be
necessary).
B Area bounded between the Ring Road (Chabahil - Gaushala section), DKLR,
Dharmbhakta Marg and Jayabageshwori Marg
(1) Open lands (two plots) bordering east from DKLR and south from Lamopokhari
Marg
C Area bounded between DKLR, Dharmbhakta -Jayabageshwori Marg and Ring Road
(Mitra Park- Gaushala section) and the Pashupati Sadak
(1) Siphal public ground
(2) Bhadarkhal forest (public)
(3) Fenced land bounded between the Y-junction at Paneku Marg and the western
border of Bhadharkhal Forest
On-street Parking:
D The following are potential locations for temporary on-street parking during the pilot
constructions, provided there is easy access to these areas.
(1) Wide shoulder adjacent to the Nepal Electricity Authority Office at Natyashwori Marg
(2) Wide shoulder adjacent to Office of the Nepal Electricity & Electricity Committee at
Charumati Marg
(3) Wide building setback space near Jagar Mandir High School and the Agricultural
Veterinary Service Office at Katubahal Galli
(4) Wide building setback space, 78 m west from Gaushala junction along Pashupati
Sadak
39. It is necessary to confirm the ownership of these lands and begin negotiation for
establishing temporary parking areas during the pilot constructions. Once this is formalised, the
detailed parking management can take place.
Conceptual Traffic Management Plan for the Pilot DNI Area Page 29
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Conceptual Traffic Management Plan for the Pilot DNI Area Page 30
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Grievance Officer to collect the complaints daily with power-of-attorney to resolve minor issues.
The Project Steering Committee will regularly supervise this Unit.
47. As the resolution of the public complaint emerging as result of the traffic management for
the pilot works need urgent actions, this Unit should be in a position to process such complaints
quickly during the pilot works. Therefore, this Unit will coordinate with the Utility Management
Coordinator, Consultant, Contractor, UMC Sub-committee members representing the Traffic
Police and Department of Roads, to resolve the complaints pertaining to traffic circulation, TMP.
If necessary, this Unit may call for an urgent meeting of the Sub-committee for resolving the
problem.
48. The Safeguard Unit will fix time-limits to address public complaints and strictly adhere to
them. The Unit will widely circulate flyers to the residents of the pilot area to inform the latter
how they can lodge complaints pertaining to the Project works and who to contact in this aspect.
This Unit will also pick up grievances regarding the traffic management in the pilot area
appearing in the newspaper or articles. In addition, this Unit will also publicise about lodging
complaints in the print and audio-visual media as well. The full detail of the Public Redress
Mechanism is beyond the scope of this TMP and should be drafted separately.
4.9 Install traffic control devices at the work zones and traffic diversion routes
49. The purpose of installing traffic control devices at the work zones is to delineate these
areas to warn, inform and direct the road-users about a hazard ahead and protect the former
including the workers. As proper delineation is a key to achieve the above objective, it is
important to install good traffic signs at the work zones.
50. Procedures for installing traffic control devices at any work zone vary depending on road
configuration, location of the work, construction activity, duration, traffic speed and volume and
pedestrian traffic. At the pilot area, the work area will take place both at the minor streets and
the major streets such as Pashupati Sadak and the Dhumbarahi – Chabahil section of Ring
Road. As such, the traffic volumes and road geometry varies with the latter qualifying for more
elaborate settings. However, regardless where the pilot constructions take place, all the work
zones should be cordoned off and traffic should be shifted away at least with traffic cones,
barricades and temporary signs (temporary STOP and GO). The pilot works will closely follow
the guidelines outlined in the DOR Traffic Sign Manual 1997 (which includes DOR 1996
document “Safety at Roadwork”) and other literature available in this respect.
51. Figure 5 illustrates a typical set-up for installing traffic control devices at the work-zone
of the pilot area.
Conceptual Traffic Management Plan for the Pilot DNI Area Page 31
TA 4893- NEP: Kathmandu Valley Water Supply and Wastewater System Improvement
Source: DOR Traffic Sign Manual; Volume I; August 1997; Kathmandu, Nepal.
52. The work zone should take into consideration the space required for buffer zone
between the workers and the traffic (lateral and longitudinal) and the transition space required
for delineation, as applicable. For the DNI works, a 30 cm clearance between the traffic and the
temporary STOP and GO signs should be provided. In addition, at least 60 cm space is
necessary to install the temporary traffic signs and cones. Figure 5 clarifies that the "ROAD
NARROWS" warning-sign is only necessary at the DNI works zones along Pashupati Sadak
and the Ring Road section, where, high traffic speeds is likely during the off-peak and night-
time. All the temporary traffic signs should be reflectorised, especially for the works to be
conducted during the night-time as per the DOR Traffic Sign Manual 1997.
53. All the traffic diversions should be properly delineated through proper "DIVERSION
AHEAD" and "ROADWORK AHEAD" signs as indicated in Figure 6. In addition, the "B46"
temporary warning sign for sharp bends used at temporary diversion should be in place after the
start of the taper of the traffic cones. Flashing beacons should be installed at the entry to the
work zone and traffic diversion for night constructions or if backfilling of the DNI trench does not
take place after the completion of a day shift.
Conceptual Traffic Management Plan for the Pilot DNI Area Page 32