Project Definition Report: Lions Gate Secondary Wastewater Treatment Plant
Project Definition Report: Lions Gate Secondary Wastewater Treatment Plant
Project Definition Report: Lions Gate Secondary Wastewater Treatment Plant
Dear Laurie:
We are pleased to submit 11 copies of our Final Project Definition Report for the referenced project.
We greatly appreciate the opportunity to work with you, your project team, and with many other
stakeholders on this exciting assignment. We look forward to working with you on the next phase of
the project in the near future.
Sincerely,
AECOM Canada Ltd.
Encl.
LGSWWTP_PDR_Covltr_2014-02-28_Final.Docx
Project Definition Report
Prepared by:
AECOM
3292 Production Way, Floor 4 604.444.6400 tel
Burnaby, BC, Canada V5A 4R4
CH2M HILL
Metrotower II, Suite 2100, 4720 Kingsway 604.684.3282 tel
Burnaby, BC, Canada V5H 4N2
Prepared for:
Metro Vancouver
4330 Kingsway 604.432.6200 tel
Burnaby, BC, Canada V5H 4G8
Project Number:
60272810 (AECOM)
456928 (CH2M HILL)
Date:
February 2014
Distribution List
Revision Log
Signatures
Table of Contents
page
Acknowledgements .............................................................................................................................xiii
Acronyms and Abbreviations ..............................................................................................................xv
1. Indicative Design Summary Report ....................................................................................... 1-1
2. Project Background ................................................................................................................ 2-1
2.1 Section Description .......................................................................................................................... 2-1
2.2 Project Need .................................................................................................................................... 2-2
2.3 Project Objectives, Organization, and Integrated Design Process .................................................. 2-3
2.3.1 Metro Vancouver’s Key Project Objectives ........................................................................ 2-3
2.3.2 Secondary Wastewater Treatment ..................................................................................... 2-3
2.3.3 Sustainability – Environmental, Social, and Economic ....................................................... 2-3
2.3.4 Integrated Resource Recovery ........................................................................................... 2-4
2.3.5 Community Integration ........................................................................................................ 2-4
2.3.6 Integrated Design Process ................................................................................................. 2-4
2.4 Structured Decision-making Process ............................................................................................... 2-5
2.4.1 Framework for Selecting the Preferred Option ................................................................... 2-5
2.5 Creation and Evaluation of Nine Integrated Thematic Concepts .................................................... 2-8
2.6 Development of Three Build Scenarios ......................................................................................... 2-10
2.6.1 Summary of Three Build Scenarios .................................................................................. 2-10
2.6.2 Build Scenario A – Resource ............................................................................................ 2-10
2.6.3 Build Scenario B – Community ......................................................................................... 2-11
2.6.4 Build Scenario C – Natural ............................................................................................... 2-12
2.6.5 Liquid Treatment Discussion of Trade-offs ....................................................................... 2-20
2.6.6 Solids Management Discussion of Trade-offs .................................................................. 2-20
2.7 Recommendation for Liquid Treatment and Solids Management at LGSWWTP ......................... 2-21
2.8 Resource Recovery Opportunities ................................................................................................. 2-21
2.8.1 Biogas Utilization .............................................................................................................. 2-22
2.8.2 District Energy................................................................................................................... 2-23
2.9 Reclaimed Water Opportunities ..................................................................................................... 2-23
2.10 Nutrient Recovery Opportunities .................................................................................................... 2-24
3. Wastewater Flow and Load Projections ................................................................................ 3-1
3.1 Section Description .......................................................................................................................... 3-1
3.2 Population Projections ..................................................................................................................... 3-1
3.3 Flow and Loads Projection for North Shore Sewerage Area ........................................................... 3-1
4. Regulatory Permitting and Approvals.................................................................................... 4-1
4.1 Section Description .......................................................................................................................... 4-1
4.2 Federal ............................................................................................................................................. 4-1
4.2.1 Wastewater Systems Effluent Regulations ......................................................................... 4-1
4.2.2 Canadian Environmental Protection Act ............................................................................. 4-2
4.2.3 Canadian Environmental Assessment Agency ................................................................... 4-3
4.3 Provincial ......................................................................................................................................... 4-3
4.3.1 Integrated Liquid Waste and Resource Management Plan ................................................ 4-3
4.3.2 Operational Certificate ........................................................................................................ 4-3
456928_WBG103013092847VBC iii
Table of Contents
iv 456928_WBG103013092847VBC
Table of Contents
456928_WBG103013092847VBC v
Table of Contents
vi 456928_WBG103013092847VBC
Table of Contents
456928_WBG103013092847VBC vii
Table of Contents
List of Figures
Figure 2-1. Metro Vancouver’s Wastewater Treatment Plants .................................................................................. 2-2
Figure 2-2. Metro Vancouver’s Key Project Objectives ............................................................................................. 2-3
Figure 2-3. Timeline of Integrated Design Process Workshops ................................................................................ 2-5
Figure 2-4. Structured Decision-making Process Steps ............................................................................................ 2-6
Figure 2-5. Objectives Hierarchy ............................................................................................................................... 2-7
Figure 2-6. Example of Consequence Table ............................................................................................................. 2-8
viii 456928_WBG103013092847VBC
Table of Contents
456928_WBG103013092847VBC ix
Table of Contents
List of Tables
Table 2-1. Summary of Thematic Concepts .............................................................................................................. 2-8
Table 3-1. North Shore Sewerage Area Population Projections ............................................................................... 3-1
Table 3-2. Flow and Load Projections for North Shore Sewerage Area ................................................................... 3-1
Table 4-1. Draft List of Substances ........................................................................................................................... 4-4
Table 4-2. Municipal Effluent Quality Requirements for Reclaimed Water (MWR) ...................................................4-5
Table 5-1. District of North Vancouver Flood Construction Level.............................................................................. 5-4
Table 7-1. Outfall Calculation Summary .................................................................................................................... 7-1
Table 8-1. Review of Freeboard ................................................................................................................................ 8-3
Table 8-2. Possible Technology Migration Pathways for Liquid Treatment Stream ..................................................8-6
Table 9-1. Summary of Project Characteristics .......................................................................................................9-29
Table 10-1. Odour Control Systems Design Parameters ........................................................................................10-3
Table 13-1. Summary of Projected Energy Use for LGSWWTP .............................................................................13-1
Table 13-2. Summary of Greenhouse Gas Emissions from LGSWWTP ................................................................13-3
Table 16-1. Capital Costs ........................................................................................................................................16-1
Table 16-2. Annual Operations and Maintenance Costs .........................................................................................16-2
Appendixes
2 Project Background Technical Brief
2A Notes from Integrated Design Process Workshops
2B Structure Decision-making Process Technical Memorandum
2C Liquid Treatment Technologies Long List Technical Memorandum
2D Biosolids Technologies Long List Technical Memorandum
2E Thematic Concept Development Technical Memorandum
2F Thematic Concept Evaluation Technical Memorandum
2G Conceptual Development of Three Build Scenarios Technical Memorandum
2H Integrated Processing of Source-separated Organics Technical Memorandum
2I Remote SSO Facility on North Shore Technical Memorandum
2J Coastal Wetland Enhancement Opportunities Technical Memorandum
2K Evaluation of Three Build Scenarios Technical Memorandum
2L Build Scenarios B and C Modified Technical Memorandum
2M Supporting Calculations for Key Tradeoffs for Liquid Treatment and Solids Management
Alternatives
2N Integrated Resource Recovery Opportunities Long List Technical Memorandum
2O Biogas Utilization Technical Memorandum
2P Heat Recovery Conceptual Design Capital Costing Basis
2Q Heat Recovery Pro Forma Cash Flow Analysis
2R Water Reuse Technical Memorandum
3 Flow and Load Projections Technical Brief
4A Response from the Canadian Environmental Assessment Agency (CEAA)
4B Potential Effluent Discharge Objectives for the Proposed North Shore Wastewater Treatment Plant –
August 2012
4C Potential Effluent Discharge Objectives for the Proposed North Shore Wastewater Treatment Plant – First
Update, October 2013
5A Community Enhancement Opportunities Technical Memorandum
5B Minutes of Meeting with Metro Vancouver on March 27, 2013
5C Minutes of Meeting with Metro Vancouver on June 28, 2013
5D PowerPoint Slides Presented at Meeting with Metro Vancouver on August 30, 2013
5E PowerPoint Slides Presented at Meeting with Metro Vancouver on September 6, 2013
5F PowerPoint Slides Presented at Meeting with Metro Vancouver on November 5, 2013
x 456928_WBG103013092847VBC
Table of Contents
456928_WBG103013092847VBC xi
Acknowledgements
Acknowledgements
Engineering Team
AECOM
CH2M HILL Canada Limited
Golder Associates Ltd.
FVB Energy Inc.
WPC Solutions Inc.
Matson Peck and Topliss
Cost Consultant
BTY Group
Additional Contributors
7group – Integrative Design Process Facilitator
KPMG – Business Advisor
Maple Reinders – Construction Advisor
Dr. Alan Russell, Dr. George Tchobanoglous, Gordon Culp – Expert Advisors
456928_WBG103013092847VBC xiii
Acronyms and Abbreviations
°C degree Celsius
µm micrometre
24/7/365 24 hours per day, 7 days per week, 365 days per year
AA annual average
AAF average annual flow
ACH air change per hour
ACI American Concrete Institute
ADWF average dry weather flow
AiP Approval in Principle
AP approved professional
AS activated sludge
AV audio visual
AWWA American Water Works Association
BC British Columbia
BC Gov Government of British Columbia
BCBC BC Building Code
BD+C Building Design and Construction
BEAM Biosolids Emissions Assessment Model
BNR biological nutrient removal
Board Metro Vancouver Board of Directors
BOD biochemical oxygen demand
BOD5 5-day biochemical oxygen demand
BTY BTY Group
CAS conventional activated sludge
cBOD5 5-day carbonaceous biochemical oxygen demand
CCME Canadian Council of Ministers of the Environment
CDAC computerized data acquisition and control
CEAA Canadian Environmental Assessment Agency
CEPA Canadian Environmental Protection Act, 1999
CEPT chemically enhanced primary treatment
CFU colony forming unit
CH2M HILL CH2M HILL Canada Limited
CH4 methane
CHP combined heat and power
CN Canadian National Railway Company
456928_WBG103013092847VBC xv
Acronyms and Abbreviations
xvi 456928_WBG103013092847VBC
Acronyms and Abbreviations
456928_WBG103013092847VBC xvii
Acronyms and Abbreviations
xviii 456928_WBG103013092847VBC
Acronyms and Abbreviations
OC operational certificate
OMRR Organic Matter Recycling Regulation (18/2002)
PDWF peak dry weather flow
PE primary effluent
PGH power generation and heating
Piteau Piteau Associates
PLC programmable logic controller
PRAH permeability-reducing admixture for hydrostatic conditions
PS primary sludge
PWWF peak wet weather flow
QC quality control
RAP remediation action plan
RDT rotary drum thickener
RFP Request for Proposal
ROW right-of-way
RSS return secondary sludge
SDM structured decision-making
SE secondary effluent
SITES Sustainable Sites Initiative
SLR sea-level rise
Sources Sources Archaeological & Heritage Consultants
SRT solids retention time
SSO source-separated organics
St. street
Stantec Stantec Consultants Ltd.
SWD side water depth
t CO2e/y tonne of carbon dioxide equivalent per year
t tonne
TAD thermophilic anaerobic digestion
TBL triple-bottom line
TKN total Kjeldahl nitrogen
TM technical memorandum
TN total nitrogen
TP total phosphorous
TPS thickened primary sludge
tpy tonne per year
TSS total suspended solids
TWSS thickened waste secondary sludge
456928_WBG103013092847VBC xix
Acronyms and Abbreviations
xx 456928_WBG103013092847VBC
LIONS GATE SECONDARY WASTEWATER TREATMENT PLANT
INDICATIVE DESIGN SUMMARY REPORT October 2013
© 2013, Greater Vancouver Sewerage and Drainage District. All Rights Reserved.
The preparation of this feasibility study was carried out with assistance from
the Green Municipal Fund, a fund financed by the Government of Canada and
administered by the federation of Canadian Municipalities. Notwithstanding this
support, the views expressed are the personal views of the authors, and the
Federation of Canadian Municipalities and the Government of Canada accept no
responsibility for them.
LIONS GATE SECONDARY WASTEWATER TREATMENT PLANT
INDICATIVE DESIGN SUMMARY REPORT
The Integrative Design Process model dissolves traditional discipline oriented
silos, thereby allowing the project team to discover opportunities that emerge from
the design process which would otherwise be unrealized. The integrative process
provides a robust framework for the team to work across disciplines to develop
concepts consistent with Metro Vancouver’s four key objectives, simultaneously
fostering exploration of the interdependencies between key project objectives.
Involvement of all disciplines throughout the design process resulted in an
indicative design that is more responsive to a range of criteria.
1 EXECUTIVE SUMMARY
2 PROJECT BACKGROUND
3 PROJECT OBJECTIVES
4 KEY DESIGN CRITERIA
5 SITE CHARACTERIZATION
6 INDICATIVE DESIGN
7 PROJECT IMPLEMENTATION SCHEDULE
1 EXECUTIVE SUMMARY
1. EXECUTIVE SUMMARY
The Lions Gate Secondary Wastewater Treatment Plant presents an opportunity to simultaneously provide a needed upgrade
to an essential service, protect the local environment and contribute to development on the North Shore. Located on former
BC Rail lands, the intent of this Indicative Design is to define the scope of the work required for the delivery of a twenty first
century wastewater treatment plant.
The Lions Gate Secondary Wastewater Treatment Plant will occupy much of its 3.5 hectare site, employing best practices
for wastewater treatment and providing maximum flexibility for future treatment technology upgrades. The Indicative Design
included in this report was developed specifically to fulfill Metro Vancouver’s four goals for the project, including:
The project team has worked together in a highly collaborative way with a large number of stakeholder groups including
businesses, residents, technical experts, local government and First Nations in order to integrate these objectives with the
project design. The outcome is a facility that is resilient and future proof; belongs to the place; is secure but visually open
to the community; has the potential to be a net producer of energy; and that can be used to teach future generations about
sustainable building, wastewater treatment and environmental stewardship.
This Indicative Design Summary Report provides a brief overview of the defined project. It describes the recommended
treatment technology, architectural character, and community integration opportunities present in the Lions Gate Secondary
Wastewater Treatment Plant.
In early 2014, Metro Vancouver will assess its construction procurement options and funding structures. Following the Board
decision on procurement and funding, the design and construction phase is expected to commence with a project completion
date of December 31, 2020.
2. PROJECT BACKGROUND
1. PROJECT NEED
The existing Lions Gate Wastewater Treatment Plant serves the North Shore
municipalities of West Vancouver, the City of North Vancouver and the District of North
Vancouver as well as the Squamish Nation and Tsleil-Waututh Nation. The plant was
commissioned in 1961 and has provided primary level treatment on the North Shore for
the past 50 years. The existing plant will continue in full operation until the new Lions Gate
Secondary Wastewater Treatment Plant (LGSWWTP) is commissioned and operating.
The existing treatment plant is one of five treatment plants owned and operated by Metro
Vancouver in the region.
The Lions Gate Secondary WWTP will be the fourth secondary treatment plant
2. DEVELOPMENT OF ALTERNATIVES
Three build scenarios were considered and focused on enhancing different characteristics and potentials of
the indicative design: resource, community, and sustainability.
The design process for the LGSWWTP has utilized the IDP methodology in order to
explore potential synergies between the technical and community aspects of the project.
This process has been elaborated through seven Integrative workshops and several
collaboration meetings were held throughout the Project Definition phase. These
workshops have brought the interdisciplinary team together to collaboratively explore the
project’s potential and had substantial impact on the form, character and deployment of
technologies for the project.
3. PROJECT OBJECTIVES
Grounding all IDP exchanges have been four project goals established prior to the project commencement by Metro
Vancouver. These are: Robust Secondary Wastewater Treatment; the Use and Demonstration of Sustainable Design
Principles; the implementation of Integrated Resource Recovery Strategies, and strong Community Integration.
2. SUSTAINABILITY
The project will optimize the generation and capture of valuable materials to be
repurposed for fuel, water, fertilizer and heat, helping Metro Vancouver in reducing
its energy costs, carbon footprint, potable water use and environmental impact. Metro
Vancouver has an opportunity through this project to demonstrate its commitment to
sustainability, to provide leadership, and to build a model facility, while fulfilling its mandate
of providing of a core service. In working to achieve this goal, business cases were
developed in line with the following objectives:
DISTRICT ENERGY
SITE STORMWATER MANAGEMENT
DAYLIGHTING
• Minimize energy use and maximize energy recovery from plant operations
EFFLUENT-SOURCE HEAT
• Minimize the generation of waste and maximize reuse and recycling of waste
PASSIVE VENTILATION
during construction, operation, and deconstruction/decommissioning.
• Minimize the region’s contribution to climate change.
• Minimize off-site impacts of stormwater and effluent discharge.
• Provide a facility that is an asset to the community.
• Develop and apply decision-making processes that are transparent, inclusive,
and respectful of the interests of all affected parties.
• Demonstrate Metro Vancouver’s values and commitment to sustainability
through the creation of a model facility for others to emulate.
• Provide a facility that is financially sustainable and provides value for money for
Metro Vancouver rate payers.
4. COMMUNITY INTEGRATION
The site is between active commercial, industrial, and residential zones, and thus its
character and urban integration are crucial. By exploring community partnerships, mutual
interests, education opportunities and public engagement positions, Metro Vancouver
aims to provide a positive influence to the urban character rather than only minimizing the
community impact. Working with residents, businesses and interested parties allowed for
the exploration of potential community assets.
The estimated wastewater flows and organic loads that will be treated by LGSWWTP, based on the
projected population of 254,000 in year 2051 is summarized below:
Wastewater Flows & Loads Year 2051
Population 254,000
Flow
Average Dry Weather (ADWF), ML/d 102
Average Annual (AAF), ML/d 120
Maximum Day Flow (MDF), ML/d 245
Peak Wet Weather (PWWF), ML/d 320
Average Annual Loads
BOD, kg/d 19,050
TSS, kg/d 21,590
The new plant’s capacity of 320 ML per day will accommodate peak flows associated with wet weather flow.
MLD X1000
MLD
MLD
MLD
MLD
MLD
MLD
Metro Vancouver’s existing Operational Certificate for the Lions Gate Wastewater
Treatment Plant will be amended to reflect the requirements of the regulations.
The requirement for disinfection is seasonal between May 1 and September 30. Also,
treated effluent from LGSWWTP must not be acutely toxic to aquatic organisms.
5. SITE CHARACTERIZATION
1. PROPOSED SITE
The Lions Gate Secondary Wastewater Treatment Plant site is approximately 2kms east
of the Lions Gate Bridge and the existing Lions Gate Wastewater Treatment Plant. The
land uses immediately surrounding the project site and along Pemberton Avenue are
classified as industrial under the District of North Vancouver current zoning bylaw, and are
classified as “employment lands” under the 2011 Official Community Plan. The character
of the neighbourhood beyond the site varies widely:
PROJECT
SITE
FUTURE DEVELOPMENT
• Heavy industrial uses (port and rail)
are expected to intensify.
• Harbourside waterfront redevelopment
is planned to east of site.
• Seaspan will add 800 jobs in coming
decade.
• Vehicular/pedestrian overpass being
planned at Philip Ave just west of site,
closing Pemberton Ave at grade.
NATURAL HAZARDS
• The project site is in an area of
overlapping natural hazards including:
liquefaction, flooding, tsunami and sea
level rise due to climate change.
• Plant design will mitigate these natural
hazards, including locating all critical
equipment and functions at elevation
of +6.0m above sea level to address
projected 100 year sea level rise.
2. GEOTECHNICAL CONSIDERATIONS
SOIL LIQUEFACTION DESCRIBES A Geotechnical considerations are a important element of this project given that the underly-
PHENOMENON WHEREBY A SATURATED ing native soil is known to be prone to liquefaction during an earthquake. The upper
OR PARTIALLY SATURATED SOIL several metres of soil beneath the site is fill material that was placed in the early part of
SUBSTANTIALLY LOSES STRENGTH AND the 20th century when the intertidal area was developed for industrial use. The fill material
STIFFNESS IN RESPONSE TO AN APPLIED is underlain by a layer of coarse granular sediments to a depth of 15 metres, typical of
STRESS, USUALLY EARTHQUAKE SHAKING
Capilano River Sediment deposits on the North Shore. The soil below this material is silty/
OR OTHER SUDDEN CHANGE IN STRESS
sand in the upper layers and gravel/sand with interbedded fine material at lower elevations
CONDITION, CAUSING IT TO BEHAVE LIKE
from glacial deposits. Groundwater is known to be close to the surface, while bedrock is
A LIQUID
more than 100 metres deep.
3. ARCHAEOLOGICAL CONSIDERATIONS
The north shore of Burrard Inlet lies within the asserted traditional territories of the
Tsleil Waututh, Musqueam, Squamish Nations as well as other Sto:lo First Nations.
The shoreline of this inlet is known historically as the host of numerous village and
seasonal camps sites utilized by First Nations people long before European contact. In
addition to this history, significant archaeological sites within the Burrard Inlet have been
registered with the British Columbia Archaeology Branch in compliance with British
Columbia’s Heritage Conservation Act. Given this context and to comply with jurisdictional
requirements, Metro Vancouver has undertaken an archaeological investigation of the site.
These studies have utilized soil core samples extracted for geotechnical investigations,
and were reviewed in controlled conditions in the geotechnical engineer’s facilities.
The likelihood of finding cultural material on the site is not high, based on the specific
location of the project site, the extent of previous disturbance and the results of recent field
tests. Further samples from across the site will be screened in order to determine if the
area contains material of archaeological origin.
A long history of industrial activity has led the present site to have low ecological value.
Most of the site area is covered by unvegetated gravel or asphalt but lack of recent use
has allowed some areas to become colonized by weedy species, including butterfly
bush, black cottonwood and other early successional vegetation. No species at risk
or ecological communities at risk are known to use the site. In addition, there are no
watercourses or areas of standing water on the site at any time of year.
5. SITE CONTAMINATION
The BC Ministry of Environment (MOE) has issued a Certificate of Compliance (CoC) for
the site, based on its past use for rail freight storage and as a passenger station. The
eastern portion of the site near Pemberton Ave has been remediated with clean fill and
a groundwater cut-off barrier on the south side of the property adjacent to the rail tracks.
The remaining contamination has been fully characterized and includes hydrocarbons and
metals, which will be managed during construction.
The configuration of Lions Gate Secondary Wastewater Treatment Plant is a result of collaborative design efforts between
design team disciplines to develop a compact, contextual addition to the diverse zoning in the neighbourhood. Given the
visibility of the site to arterial traffic, the Spirit Trail and the cycle route bounding its northern perimeter great care has been
taken with the project massing. A translucent “gallery” reduces the apparent height of the facility from the street level while
extensive planting and site grading rise up from 1st St. to modulate the scale of the plant.
Intensive activities are focused at the west end of the site, with digesters, solids handling, headworks and dewatering
clustered to facilitate the robust odour control system and efficient operations. Primary and secondary treatment occur mid
block, with a transparent cantilevered Operations and Maintenance building at the corner of 1st St. and Pemberton Avenue.
These treatment plant functions portray a clean, architectural form balanced against the industrial scale of neighbouring
industries. Translucent and glazed walls at the west end also allow selected views from the street into the plant, making the
invisible visible.
What emerges is a project characterized by a diverse range of urban experiences across the site, a pedestrian scaled public
entrance and outdoor open space at the foot of Pemberton, a highly visible energy centre, and several other spaces indoors
and out that support public education and outreach in water use and sustainable water infrastructure.
(top) View of Operations and Maintenance building from corner of Pemberton and 1st St
(bottom left) View of Southwest end of plant from McKeen Rd
(bottom right) View of digesters and screening building from further west along 1st St
DEVELOP CLEAN,
UNIFIED EXPRESSION
• Integrate design of main building and
treatment plant
• Tighten up buildings and equipment at
intensive end of site
v. Energy Centre
Space has been allocated within the Operations and Maintenance Building for an Energy
Centre to serve district energy systems in close proximity to LGSWWTP. The new Energy
Centre will produce green energy by extracting low grade heat from treated effluent and
upgrading the heat to a higher temperature using heat pump technology, then distributing
GROUND LEVEL 1 El. 4.1m the heat to district energy systems using an underground piping system. Once delivered
DISTRICT ENERGY to a district energy system, the heat will be transferred and used by residential and
PLANT LOBBY commercial customers for hydronic space heating and hot water.
PUBLIC LOBBY AND MEETING
The first phase of the Energy Centre is planned to include space for a 5 Megawatt heat
pump capable of provide space heating and hot water for approximately 3,000 homes on
the North Shore. The capacity of the Energy Centre may be expanded in the future near
development nodes within the community, as opportunities present themselves.
2. SITE DEVELOPMENT
i. General
The development is responsive to the linear procession of the treatment process. Intensive
processes are focused at the west end, with linear, stacked clarifiers midblock concluding
in the Operations and Maintenance building and public open space at Pemberton. The
volume of the plant is held back from 1st St. to allow a 15m-25m deep buffer between the
street edge and the wall of the plant, allowing for vegetation, landforms and water features
to integrate the plant into the neighbouring context. The public enter the facility through the
public lobby on the north side of the Operations and Maintenance building. Plant staff will
enter the facility at the plant lobby on the south side of the Operations and Maintenance
building.
Traffic will enter the facility along the east side of the facility via Pemberton, following a
one way drive along the south property line and exit the plant midblock onto 1st St. Public
parking will be provided at Pemberton, with plant staff parking inside the security gate
along the south side of the plant. Trucks will exit the plant headed eastbound on 1st St. All
internal roadways are elevated to 4.1m and separated from public right of way by security
gates or perimeter fencing 2m above grade.
Pemberton Ave
Philip Ave
Vehicle
Entry
Pedestrian Parking
circulation
*
Bike route 1st Street West
Administration
Vehicle Building
Exit Entries
* Rail Crossing
Emergency
Employee Parking Vehicles Only
ion
c ulat
y cir
-wa
One
Plant circulation will be one-way with vehicles entering to the east at Pemberton Ave and exiting to the west
onto 1st St
The public space at the foot of Pemberton Ave. is largely characterized by a water
feature surrounding the Operations and Maintenance building with naturalized landscape
edges. The public space in combination with the Operations and Maintenance building
establishes an inviting presence within the community. Public functions within the
Operations and Maintenance building are at grade and integrate with the activities in the
public space. These include the water feature, an arrival plaza, public gathering space,
education space and a visible district energy centre.
The water feature will display water in a variety of forms including: cascades, flowing water
through channels and reflective water in pools. The planting throughout the site will reflect
the character of the temperate rainforests of the north shore. Additionally, the development
of a public art strategy and other site amenities can further support the creation of a
meaningful public space at the foot of Pemberton and will inspire a dialog surrounding the
importance of water. Such interpretive elements on the site illustrate the methods Metro
Vancouver is implementing to conserve this important public resource.
The area at the foot of Pemberton Avenue is the natural public face for the facility and
provides the most opportunity to establish a positive identity for the facility within the
community.
RAIL
MIXED INDUSTRIAL
Vegetation and a water feature screen the north side of the plant and flow east into a public area at the foot
of Pemberton Ave.
A range of treatment technologies will be used at the LGSWWTP to treat wastewater from the North Shore, manage
various sludge streams generated on the site and treat odours, as depicted in the process flow schematic.
1st STAGE
ODOUR CONTROL
TREATMENT
HIGH ODOUR
POTENTIAL SOURCES
COARSE
SCREENING
LIQUID, BIOSOLIDS & RESOURCE RECOVERY
COMPACTED DEWATERED
SCREENINGS GRIT TO
TO DISPOSAL DISPOSAL
WASTE
SECONDARY
RETURN STREAMS
SLUDGE
PRIMARY THICKENING
SLUDGE
THICKENING
DILUTION
WATER
AIR
ANAMMOX
REACTORS
3. TREATMENT TECHNOLOGY
3A. LIQUID TREATMENT
The liquid treatment train includes the following six major components:
1. Influent pumping
2. Preliminary treatment
3. Primary treatment
4. Secondary treatment
5. High rate clarification
6. Disinfection
i. Influent Pumping
Wastewater will be conveyed to LGSWWTP in trunk sewers to the Influent Pump Station.
The Influent Pump Station will pump the wastewater directly above to the preliminary
treatment process. LGSWWTP has been designed to allow wastewater to flow through
the entire liquid treatment train and outfall to Burrard Inlet by gravity without additional
pumping.
Activated sludge will then flow to the stacked secondary clarifiers, which will be used to
settle the activated sludge and produce a clear effluent (secondary effluent) that will flow
to the disinfection process. Activated sludge settled in the bottom of the tanks will be
returned to the deep tank activated sludge process and a small amount will be removed
and pumped to the solids treatment train.
Both deep tank activated sludge and stacked secondary clarifiers are small footprint
technologies, as these tanks are twice as deep as conventional technologies and reduce
space requirements for LGSWWTP.
vi. Disinfection
The requirement for disinfection is seasonal and when required, ultraviolet light will be
used. Disinfected treated effluent will be conveyed to the existing outfall and discharged to
Burrard Inlet.
i. Thickening
Mechanical thickening will be used to remove water from the primary and secondary
sludge streams to reduce their volume and minimize the size and footprint of solids
treatment processes. After thickening, the sludge streams will be blended, pre-heated and
pumped to the digestion process.
ii. Digestion
Thermophilic anaerobic digestion will be used for stabilizing FOG, primary and secondary
sludge streams. The microorganisms in the digester tanks are able to degrade the FOG
and sludge streams under anaerobic conditions (in the absence of oxygen) and high
temperature (55°C) to stabilize the final product and produce a “biogas”, which will be
collected at the top of the digester tanks. The biogas contains 50 to 60% methane, which
will be recovered and used to produce electricity and heat for the digestion process and
space heating within the plant.
Containment
All potential sources of odour will be contained by physical covers and the air within the
containment barriers will be discharged to the odour treatment system. An additional
level of secondary containment will be provided with enclosures around all components of
LGSWWTP. The air within the secondary containment system will also be discharged to
the odour treatment system.
Treatment
STAGES OF TREATMENT: LGSWWTP will be equipped with a two stage odour treatment system. High odour
1. BIOTOWERS potential sources, including those within the preliminary treatment and primary treatment
2. ACTIVATED CARBON POLISHING areas, as well as those within the solids treatment areas will be first treated in biotowers.
Biotower treatment technology uses plastic media to provide surfaces for bacteria to grow
and degrade odorous compounds. The towers utilize a countercurrent configuration in
which foul air is introduced at the bottom and water at the top.
Contained air from low and medium odour potential sources together with air from all
secondary enclosures will be treated directly in the activated carbon polishing units.
Dispersion
The treated air from the activated carbon polishing units will be discharged through a stack
to disperse the treated air into the atmosphere.
The treated air at the top of the biotowers will be discharged to activated carbon units for final polishing.
4. RESOURCE RECOVERY
The following three resource recovery options have been integrated into the design of the
LGSWWTP:
In addition, space has been allocated on the site for a struvite recovery system should
market conditions change and the business case for this opportunity improves.
5. CONVEYANCE
The majority of wastewater generated on the North Shore will discharge to LGSWWTP
via the North Vancouver Interceptor on West 1st Street. The North Vancouver Interceptor
will be diverted to the Influent Pump Station when the new infrastructure is ready to be
put into service. Infrastructure improvements will be required to convey wastewater from
the District of West Vancouver, Squamish Nation and the District of North Vancouver to
LGSWWTP. Also, a pipeline will be required to convey treated effluent to the existing
outfall at First Narrows. The final siting and alignment of this infrastructure is to be
determined.
Procurement for the design and construction phase should commence in 2014.
Construction and commissioning is to take place between 2017 and the end of 2020.
Once the plant is in operation, the existing Lions Gate primary treatment plant will be
decommissioned and deconstructed.
CONSULTANT PROCUREMENT
CONSTRUCTION PROCUREMENT
CONVEYANCE UPGRADES
2. Project Background
2.1 Section Description
This section provides background on the project and an overview of the structured decision-making (SDM) process
that was formulated and used by the Integrated Design Team (IDT) to develop and evaluate integrated wastewater
treatment schemes for the Lions Gate Secondary Wastewater Treatment Plant (LGSWWTP) and ultimately select a
preferred build scenario to carry forward for Indicative Design. This section includes the following topics:
• Project Need
• Project Objectives, Organization, and Integrated Design Process
• SDM Process
• Creation of Thematic Concepts and Build Scenarios
• Selection of Preferred Build Scenario for Liquid Treatment and Solids Management
• Resource Recovery Opportunities
456928_WBG103013092847VBC 2-1
Project Background
2-2 456928_WBG103013092847VBC
Project Background
Sustainability
Environmental, Social, Economic
Community Integration
Figure 2-2. Metro Vancouver’s Key Project Objectives
• Minimize energy use, and maximize energy recovery from Metro Vancouver’s operations
• Minimize the generation of waste, and maximize reuse and recycling of waste that remains during construction,
operation, and deconstruction/decommissioning
• Minimize the region’s contribution to climate change
• Minimize offsite impacts of stormwater and effluent discharge
• Provide a facility that is an asset to the community
• Develop and apply decision-making processes that are transparent, inclusive, and respectful of the interests of
all affected parties
• Demonstrate Metro Vancouver’s values and commitment to sustainability through the creation of a model
facility for others to emulate
• Provide a facility that is financially sustainable and provides value for money for Metro Vancouver ratepayers
456928_WBG103013092847VBC 2-3
Project Background
2-4 456928_WBG103013092847VBC
Project Background
456928_WBG103013092847VBC 2-5
Project Background
The overarching framework provided a means to start with a full range of opportunities encompassing treatment
technologies, resource recovery, sustainable development, and community; gradually, through a series of steps
and key decision points, the opportunities were narrowed to a preferred option that informed the Indicative Design.
Key tools developed by the IDT to support the SDM process were an objectives hierarchy and a consequence
table. The objectives hierarchy consisted of a series of criteria developed by the IDT with input from stakeholders to
measure how well each option achieved Metro Vancouver’s key project objectives based on a measurement scale
and corresponding score. The objectives hierarchy is shown in Figure 2-5. The consequence table was a summary
matrix showing the scores for each option by criterion and used colour coding to identify how well each option
achieved each objective, as compared to other options. An example consequence table, complete with colour
coding, is illustrated in Figure 2-6.
These two tools were fundamental to the SDM process and allowed the IDT to explore desirable and undesirable
aspects of options with stakeholders and consider ways to combine features into improved hybrid alternatives. This
approach also allowed the IDT to explore trade-offs inherent in the selection of an option with project stakeholders.
2-6 456928_WBG103013092847VBC
Project Background
Objectives Hierarchy
1. Provide Robust Secondary Wastewater Treatment for the North Shore
1A. Operational risks
1B. Risks to operators associated with O&M activities
1C. Total solids requiring management
1D. Risk of odour nuisances
1E. Partnership complexity
1F. Ability to adapt to future legal or regulatory changes such as nutrient and microconstituent
removal
2. Enhance Local Community Integration of the Project
2A. Quality and diversity of offsite community experiences
2B. Educational opportunities
2C. Potential for public amenities
2D. Narrative potential
2E. Risk that community integration objectives would not be met
3. Promote Metro Vancouver’s Sustainability Policy Objectives
3A. Ecological service provision (habitat potential)
3B. BOD Loading to Burrard Inlet
3C. Greenhouse gas emissions (plant construction and operations less emissions avoided elsewhere)
3D. Criteria Air Contaminants (plant operations less emissions avoided elsewhere)
4. Promote Integrated Resource Recovery
4A. Beneficial use of energy (heating, cooling, electricity) to displace other fuel sources (including
offsite uses)
4B. Nutrient beneficial reuse
4C. Robustness/flexibility of IRR product markets
4D. Risk of securing source separated organics feedstocks
5. Minimize Costs to Ratepayers
5A. Expected ratepayer cost (net present value of long-term revenue and expenses)
5B. Ratepayer cost risk
Figure 2-5. Objectives Hierarchy
456928_WBG103013092847VBC 2-7
Project Background
Concept Description
1 Intertidal Wetland
2 Luminous Breathing Organism
3 Network
4 Ant Colony
5 Flea Market
6 Perpetual Motion Machine
7 Urban Farm
8 Urban Rainforest
9A Dragon’s Den (small footprint)
9B Dragon’s Den (buried)
The nine thematic concepts were illustrated in a series of boards and presented to stakeholders for their review and
input. The concepts were then evaluated by the IDT using the SDM process, which informed Workshop 4.
2-8 456928_WBG103013092847VBC
Project Background
456928_WBG103013092847VBC 2-9
Project Background
This build scenario transforms resources into valuable commodities that reduce the demand on existing
infrastructure, provide development opportunities, and maximize revenues to offset ratepayer costs. This build
scenario is testing the potential of the project to maximize revenue-generating potential to offset ratepayer costs
through IRR and comprehensive urban development. Opportunities include:
2-10 456928_WBG103013092847VBC
Project Background
• Specialty fabrication and production (three-dimensional printing, computer numerical control/ automated
production, digital fabrication)
• Leasable high-bay incubator space for sustainability-focused new industries (resource reuse, energy
development, materials research)
• Highest level of IRR, integrating liquid and solid waste streams
Build Scenario A’s technological foundation is inclusion of a second site for the construction of an Energy Centre to
receive and process residuals from LGSWWTP and biomass in solid waste streams from the North Shore,
including food waste and clean wood waste. Furthermore, there is the potential to integrate the Energy Centre with
a district energy initiative involving the DNV and various utility and industrial partnerships.
A secondary foundation of this concept is to keep LGSWWTP’s footprint small to allow for the potential for unused
portions of the site to be developed for retail, light-industrial, and commercial uses, as envisaged in the site’s
current zoning designation.
This build scenario engages the community in an active partnership so that mutually beneficial opportunities for
Metro Vancouver and the community are created and realized. This build scenario is testing the potential of the
project to act as a catalyst to strengthen social connections and build strong community partnerships. Opportunities
include:
• Urban rooftop greenhouses (for example, restoration agriculture, research, medicinals, or urban food
production with rainwater irrigation)
456928_WBG103013092847VBC 2-11
Project Background
• Conservatory with exotics and tropicals (for example, orchids and epiphytes) for sale or exhibition
• Leasable, available spaces for art space or farm stalls
• Saturday/weekly market booths/galleries/farmers market (for example, Granville Island, Pike Place Market) at
the foot of Pemberton Avenue; exterior covered and interior/exterior spaces
• Skate park (covered or partially covered) 1.9-square metre (m2) minimum size (regional skate park examples
include Louisville, Gleneagles, White Rock skate parks)
• Granular, pedestrian feel at Pemberton Avenue and along 1st Street (St.).
• Highest adaptability over time
Build Scenario B’s technological foundation is that infrastructure constructed in the first phase will have low
mechanical intensity and large tank volumes. The technology migration pathway will entail the installation of more
mechanically intensive equipment in the tanks in the future. Implicit in this concept is the notion that deep and
expansive tanks provide the most flexibility to adapt to future technologies, most particularly those that have not yet
been conceived and will be commercially available in the future.
This build scenario incorporates advanced treatment technologies and transforms a damaged site into one that is
ecologically restored in a sustainable and regenerative manner. This build scenario is testing the potential of the
project to achieve ecological restoration through advanced treatment and site naturalization. Opportunities include:
• Constructed wetland / forest / weirs, including tule, sedges, and indigenous / native vegetation
• Visible WWTP functions
2-12 456928_WBG103013092847VBC
Project Background
Build Scenario C’s technological foundation is that treated effluent from the new LGSWWTP will be of high quality,
suitable for discharge to the pocket estuaries at the southern ends of Philip and Pemberton Avenues, and possibly
other existing receiving waters near the site, such as the MacKay Wetland and MacKay Creek. Also, the effluent
will be suitable for most reclaimed water applications (other than those required to meet extremely high-quality
standards), such as boiler feed water and other industrial applications.
Should discharging high-quality treated effluent to the pocket estuaries and other receiving waters as envisaged
prove feasible, it may be possible to deconstruct the existing outfall and eliminate the associated conveyance
infrastructure needed to return treated effluent flow from the new LGSWWTP to the existing site.
456928_WBG103013092847VBC 2-13
Project Background
2-14 456928_WBG103013092847VBC
Project Background
456928_WBG103013092847VBC 2-15
Project Background
2-16 456928_WBG103013092847VBC
Project Background
456928_WBG103013092847VBC 2-17
Project Background
2-18 456928_WBG103013092847VBC
Project Background
456928_WBG103013092847VBC 2-19
Project Background
• Key trade-offs for provision of tertiary quality effluent (Build Scenario C) or secondary quality effluent (Build
Scenarios A and B) include:
− Capital costs for tertiary treatment are approximately $50 million more than for secondary treatment, and
operations and maintenance (O&M) costs are approximately $2 million more per year.
− Approximately 50 percent more electricity is required for tertiary treatment, and there are significantly more
greenhouse gas (GHG) emissions from electricity and more required chemical addition.
− Tertiary treated effluent reduces the overall biochemical oxygen demand (BOD) loading to the Burrard Inlet
beyond that achieved by upgrading to secondary treated effluent. Secondary effluent (SE) will be fully
protective of the Burrard Inlet receiving waters.
− Implementation of tertiary treatment now will provide future-proofing against potential future regulatory
changes.
− Tertiary treated effluent has the potential to be discharged at the foot of Pemberton or Philip Avenues,
creating estuary conditions and associated habitat, and could eliminate the need to use the existing outfall.
• Between the secondary treated effluent alternatives, installation of an ultra-compact, mechanically intensive
process (Build Scenario A), when compared to the larger, less mechanically intensive processes (Build
Scenario B) provides the following advantages and disadvantages:
− Leaves more land available for potential alternative development of portions of the site.
− Has a lower initial capital cost ($20 million), and higher O&M costs of approximately $1.8 million per year,
due to significantly higher chemical and electricity consumption.
− More GHG emissions (approximately 8 times more), primarily due to required chemical addition.
− Is less adaptable to future regulatory changes. Build Scenario B, by design, is adaptable over time, by
increasing the type and ‘intensity’ of the unit processes used, as compared to expanding the overall size
and tankage.
• Onsite digestion of biosolids (Build Scenario B) results in significantly lower life-cycle costs than digesting
biosolids at a second site (Build Scenario A) or using thermal reduction (Build Scenario C).
• Conveyance of undigested biosolids, drying, thermal hydrolysis, and addition of food waste increases the risk of
odours (at either site) (Build Scenario A).
• Codigestion of preprocessed SSOs at the treatment plant site results in the lowest overall life-cycle cost of the
alternatives considered (Build Scenario B). However, prior to further development, the following items require
additional consideration:
− Life-cycle costs do not include the cost of implementing a source-separated organics (SSO) program within
the North Shore municipalities; in particular, the separate collection of food waste and yard waste. Current
practice is to collect comingled food waste and yard waste.
2-20 456928_WBG103013092847VBC
Project Background
− There are few examples of codigestion of food waste and biosolids at the scale proposed. Food waste
could account for approximately 40 percent of the solids loading at the new wastewater treatment facility.
− Local end-use markets for biosolids are limited, and the addition of food waste will increase the quantity of
material that must be managed. As well, by codigesting the two materials, the end product would be
restricted to uses available to biosolids, which may be more limited than that of independently digested/
composted food waste.
− The required tipping fee for SSOs (food waste) may not be acceptable.
− Metro Vancouver may need to implement additional flow control measures to secure the SSO waste
stream. The current organics disposal ban is set for 2015, but the plant would not be operational for
another 5 years.
− All three approaches used facilities scaled to accommodate the capacity of the waste generated on the
North Shore. This could result in higher unit prices due to economies of scale for larger, regional facilities.
• Thermal reduction of solids has the highest potential GHG emissions (Build Scenario C).
• Creation of dried biosolids pellets has the highest associated energy value and potential for reduction of
regional GHG emissions if they are used to displace fossil fuels (Build Scenario A). However, it is important to
note that the relatively small quantities of dried biosolids that would be generated by the North Shore facility
would not necessarily be sufficient to justify the investment needed at facilities to receive and use biosolids
pellets. A regional biosolids-drying facility would be able to generate more material, at less unit costs, than the
LGSWWTP.
Digestion of biosolids onsite provides the lowest capital and operating costs of the solids processing options (Build
Scenario B). In addition, onsite digestion offers a variety of options for utilization of the biogas produced, for either
direct heating within the treatment plant, electricity and heat generation from biogas cogeneration engines, or
generation of renewable natural gas by upgrading the biogas to pipeline quality.
The Indicative Design was presented to the Utilities Committee at a special meeting on September 24, 2013, followed
by presentations to Metro Vancouver Council of Councils and North Shore Councils and community groups; and was
endorsed at the Utilities Committee regular meeting on November 7, 2013, and the Board regular meeting on
November 15, 2013.
1. Biogas utilization
2. District energy
456928_WBG103013092847VBC 2-21
Project Background
3. Reclaimed water
4. Nutrient recovery
The following paragraphs describe the outcome of the TBL business cases developed by the IDT.
The purpose of this TBL business case was to evaluate the following options:
• Alternative 1: Digester gas for in-plant process and facility-heating requirements, and flare the remaining gas.
• Alternative 2: Cogeneration (combined heat and power [CHP]) using two reciprocating engine-generator units
and waste-heat recovery to supply hot water for both process and facility heating within the plant. All energy is
used in-plant for this alternative.
• Alternative 2A: Cogeneration (CHP) using one reciprocating engine-generator unit (no redundancy) and waste-
heat recovery to supply hot water for both process and facility heating within the plant. All energy is used
in-plant for this alternative.
• Alternative 3A: Digester gas for in-plant process and facility-heating requirements, and upgrade the remaining
gas to biomethane for injection into the utility pipeline.
• Alternative 3B: Digester gas for in-plant process and facility-heating requirements, and upgrade the remaining
gas to biomethane for vehicle fuelling.
Other alternatives were conceptually screened, but eliminated for further evaluation for technology and
implementation reasons. These alternatives include:
• Fuel cells: This technology is in the developmental stage and has not been adequately demonstrated at full
scale for sufficient time to support its application for this project.
• Local distribution of biogas: After consulting with surrounding industrial users, it was determined that a local
district energy provider is interested in using biogas for their district energy system, but the energy available in
the biogas is much lower than their demand; however, the demand could be met by recovery of effluent heat,
which was explored instead.
On the basis of the TBL business case, Alternative 2, including cogeneration with two engines, is included in the
Indicative Design for the following reasons:
• The life-cycle costs of Alternatives 2 and 3A are essentially the same based on the conceptual level of detail
used in the analysis; however, Alternative 2 has the following advantages over Alternative 3A:
− Metro Vancouver’s existing experience with the technology
− Less market risk
• Cogeneration of electricity and heat onsite provides a high level of energy self-sufficiency for LGSWWTP and
enhances power reliability.
• Alternative 2 is preferred over Alternative 2A (single unit) owing to O&M benefits of having multiple installed
units, rather than a single unit.
The Indicative Design includes two reciprocating engine-generator units and waste-heat recovery to supply hot
water for both process and facility heating within the plant and the Energy Centre.
2-22 456928_WBG103013092847VBC
Project Background
• The estimated capital cost is approximately $19 million (Year 2020), and the annual operating cost is on the
order of $2 million. This would be improved by sizing the distribution piping for the short-term capacity only.
• The system will require the cost of renewable energy to be in the order of $20/ gigajoule (GJ) by the end of the
decade in order for the system to pay for itself in 25 years, and be cash-flow positive in 8 years. Fortis BC is
currently offering Metro Vancouver $13.40/GJ for renewable natural gas from the Lulu Island WWTP.
• The use of effluent heat for the assumed base load demand (if displacing natural gas use) would result in a
regional GHG emission reduction equivalent to 5,300 tonnes of carbon dioxide equivalent per year (t CO2e/y).
• By recovering energy from the effluent and applying it to a district energy system, all build scenarios become
net energy producers.
• There is potential to direct any surplus heat from cogeneration to the Energy Centre, which would reduce the
electricity required for heat pump operation and would improve the annual operating cost.
There is a reasonable opportunity to recover energy from the treatment plant effluent for district energy use, and
there has been considerable interest from stakeholders. The final business case will depend on the future market
value of green energy, cost of energy such as natural gas and electricity, availability of funding, and the allocation
of risk in the development of assets. Exploration of markets and funding, and further discussion with potential
partners, is warranted.
The Indicative Design includes space on the ground floor of the Operations and Maintenance Building for an
Energy Centre based on heat pump technology.
• Internal non-potable functions within the WWTP such as seal-water, tank washdown, landscape irrigation,
make-up water for chemicals, toilet flushing, and interpretative water features
• Nearby industrial users for dust control, washdown, and vehicle washing
• Nearby parks for summer irrigation
• Large water-consuming industries near the collection system, but not adjacent to the WWTP, through the
installation of a small satellite reclaimed water facility.
456928_WBG103013092847VBC 2-23
Project Background
A significant component of the costs associated with water reuse is the installation of a separate pressurized water
distribution system to transport the reclaimed water to potential users. The best opportunity for the use of reclaimed
water is within the WWTP itself, to offset potable water for non-potable uses. If incorporated at the project outset,
the reclaimed water system can be fully integrated within the overall treatment plant non-potable water system.
Metro Vancouver currently uses a variety of reclaimed water use strategies at its wastewater treatment facilities to
reduce overall potable water consumption.
Assuming that external water users would be willing to pay half of the cost of potable water for reclaimed water, the
business case with today’s rates is not cost-effective. However, in the future, if the drivers for reclaimed water
change, the reclaimed water system could be expanded to include other users and potentially satellite facilities.
The Indicative Design includes a reclaimed water system, which has been sized for internal non-potable uses with
provisions to expand the system in the future for other offsite uses. Also, provisions have been included for a truck
fill station near the Ultraviolet (UV) Disinfection Building.
• Total production is about 500 tonnes per year (tpy), with an estimated capital expenditure of $6.3 million and
annual O&M cost of $150,000.
• Estimated revenue from the product is $230,000 per year, and the estimated O&M savings are approximately
$110,000 per year, plus a reduced risk of dewatering mechanical equipment failure.
• Overall, the business case is extremely sensitive to the market price of the recovered product. For the business
case, the product has been estimated at $460 per tonne (t); however, the retail market price is considerably
higher.
The Indicative Design includes space for a struvite recovery facility on the top floor of the Solids Building that could
be installed at a later date, when market conditions improve.
2-24 456928_WBG103013092847VBC
Wastewater Flow and Load Projections
The following supporting document is included in the Appendixes volume: Appendix 3 – Flow and Load Projections
Technical Brief.
3.3 Flow and Loads Projection for North Shore Sewerage Area
The flow and load projections for the NSSA catchment in years 2035, 2051, and 2101 are summarized in Table 3-2.
Table 3-2. Flow and Load Projections for North Shore Sewerage Area
Component Year 2035 Year 2051 Year 2101 Notes
456928_WBG103013092847VBC 3-1
Wastewater Flow and Load Projections
Table 3-2. Flow and Load Projections for North Shore Sewerage Area
Component Year 2035 Year 2051 Year 2101 Notes
TSS Loads
Per Capita TSS Loads
AA, g/c/d 85 85 85
MM, g/c/d 101.5 101.5 101.5
MW, g/c/d 153 153 153
AA TSS Load, kg/d 19,975 21,590 24,990
MM TSS Load, kg/d 23,853 25,781 29,841
MW TSS Load, kg/d 35,955 38,862 44,982
BOD5 Loads
Per Capita BOD5 Loads
AA, g/c/d 74.5 74.5 74.5
MM, g/c/d 87.5 87.5 87.5
MW, g/c/d 101 101 101
AA BOD5 Load, kg/d 17,625 19,050 21,903
MM BOD5 Load, kg/d 20,563 22,225 25,725
MW BOD5 Load, kg/d 23,735 25,654 29,694
COD Loads
Per Capita COD Loads
AA, g/c/d 166.8 166.8 166.8
MM, g/c/d 187.8 187.8 187.8
MW, g/c/d 266.6 266.6 266.6
AA COD Load, kg/d 38,928 42,076 49,039
MM COD Load, kg/d 45,563 49,247 55,213
MW COD Load, kg/d 62,651 67,716 78,380
TKN Loads
Per Capita TKN Loads
AA, g/c/d 13.5 13.5 13.5
MM, g/c/d 15.0 15.0 15.0
AA TKN Load, kg/d 3,173 3,429 3,969
MM TKN Load, kg/d 3,525 3,810 4,410
Notes: AA – annual average kg/d – kilogram per day MMF – maximum month flow
AAF – annual average flow L/c/d – litre per capita per day MW – maximum week
ADWF – average dry weather flow MDDWF – maximum day dry PDWF – peak dry weather flow
weather flow
BOD5 – 5-day biochemical oxygen demand PWWF – peak wet weather flow
MDF - maximum day flow
COD – chemical oxygen demand TKN – total Kjeldahl nitrogen
ML/d – megalitre per day
g/c/d – gram per capita per day TSS – total suspended solids
MM – maximum month
From 2006 to 2011, the ratio of influent sBOD:BOD5 averaged 0.16, and the ratio of ammonia (NH3):TKN is
estimated to be 0.66 based on influent NH3 data and assumed TKN per capita loads.
3-2 456928_WBG103013092847VBC
Regulatory Permitting and Approvals
3. Appendix 4C – Potential Effluent Discharge Objectives for the Proposed North Shore Wastewater Treatment
Plant – First Update, October 2013
4.2 Federal
The minimum national effluent quality standards for wastewater treatment facilities of a size similar to the
LGSWWTP are:
• cBOD5 less than or equal to 25 milligrams per litre (mg/L) (monthly average of at least five samples per week)
• TSS less than or equal to 25 mg/L (monthly average of at least five samples per week)
• Total residual chlorine less than or equal to 0.02 mg/L (testing is required only if chlorine is used as a
disinfectant in the treatment facility; testing to be done three times per day if required)
• Un-ionized ammonia 1.25 mg/L maximum, expressed as nitrogen (N) at 15 degrees Celsius (°C) ± 1°C
Under the WSER, toxicity testing of effluent can now be conducted using a modified procedure: with or without the
add-on pH stabilization procedure.
The WSER stipulates the following with respect to toxicity: Acute lethality of effluent means that the effluent at
100 percent concentration kills more than 50 percent of the rainbow trout subjected to it during a 96-hour period.
The acute lethality of the effluent must be determined in accordance with Reference Method EPS 1/RM/13 or
Reference Method EPS 1/RM/13 used with Procedure for pH Stabilization EPS 1/RM/50. Nontoxic effluent is
defined by passing the acute toxicity test using rainbow trout.
The WSER also defines unionized ammonia as a deleterious substance. The maximum concentration of unionized
ammonia in the effluent must be less than 1.25 mg/L, expressed as N, at 15°C ± 1°C. The concentration of
unionized ammonia in the effluent is defined in accordance with the formula
456928_WBG103013092847VBC 4-1
Regulatory Permitting and Approvals
The concentration of total ammonia in the effluent is determined using an aliquot of the effluent from which the pH
of the effluent is determined.
The CEPA takes a risk-based approach to decision-making regarding the entry of substances into the environment,
exposure conditions, and inherent toxicity to human health. 1 Implementation of the CEPA integrates risk
assessment, risk management, compliance promotion, and enforcement of the Act, as well as research and
monitoring. The CEPA addresses preventative and remedial measures for the protection of the environment and
human health.
Under the CEPA legislation, when a substance is identified that may be toxic to the environment or human health,
Environment Canada and Health Canada develop a plan to assess and manage the substance, under the New
Substances Notification Regulations. For some substances, the plan is to stop using the chemical; for others, the
plan is to regulate the use; and for others, the plan is to manage the chemical in the correct fashion.
The CEPA is administered by Environment Canada and Health Canada according to their Memorandum of
Understanding, 1990, and uses several tools, including:
Substances Lists. These lists control the importation, trade, evaluation, and use of almost any chemical used in
Canada. These lists also contain items of environmental concern (for example, certain effluents). For each item in a
specific list, there is a defined course of action required.
Regulations. The CEPA currently includes 55 regulations (plus 10 proposed regulations). These cover a range of
activities, from pulp mills, to ocean disposal, solvent handling, gasoline content, renewable fuels, and phosphorus
concentration in detergent.
Guideline and Code of Practice: The CEPA currently includes 47 guidelines, 26 codes of practice, 1 provisional
code of practice, and 9 guidance documents/objectives covering a range of activities.
Ammonia dissolved in water is a substance specified in the List of Toxic Substances in Schedule 1 of the CEPA.
On December 4, 2004, Environment Canada published additional requirements under the CEPA related to
preparation of pollution prevention plans for chlorinated municipal effluents, as well as the Guideline for the
Release of Ammonia Dissolved in Water Found in Wastewater Effluents. The intent of the guideline is to maintain
the concentration of ammonia to less than nonacutely lethal levels in municipal wastewater effluents. The maximum
allowable ammonia concentration is calculated in accordance with the formula:
Where:
1 Toxicity or harm to wildlife is addressed through separate pieces of legislation, including the Fisheries Act, Species at Risk Act, Canada Wildlife Act,
Migratory Birds Convention Act (1994), and Wild Animal and Plant Protection and Regulation of International and Interprovincial Trade Act.
4-2 456928_WBG103013092847VBC
Regulatory Permitting and Approvals
4.3 Provincial
Approval of Metro Vancouver’s ILWRMP (2010) under the BC Environmental Management Act authorizes
discharges to the environment – water, air, and land – associated with the management of liquid waste according to
the criteria set out in the plan and facility-specific OC. The ILWRMP was approved by the MoE on May 30, 2011.
Metro Vancouver’s ILWRMP identifies that Metro Vancouver and municipalities will maintain and operate their liquid
waste infrastructure, make improvements, and reduce risks to the environment that may be identified through
ongoing monitoring and assessment programs. Metro Vancouver and municipal actions include the provision of
basic sewer service levels, and quantifying and managing air emissions, including odours and GHGs, associated
with operating and maintaining wastewater collection and treatment systems. The ILWRMP further identifies that
Metro Vancouver will operate its secondary treatment WWTPs (of which LGSWWTP will be one) to meet
requirements specified in each facility’s OC. The effluent discharge limits specified in the OC are generally
consistent with the WSER. The ILWRMP identifies the intended site for the NSSA secondary treatment facility as
the Metro Vancouver-owned property between Pemberton, Philip, and McKeen Avenues, and 1st St. in the DNV,
and that the existing outfall will be retained as part of the upgraded facility.
Effluent quality requirements for the new LGSWWTP will be set out in an amended OC to be issued by the MoE
under the provisions of the BC Environmental Management Act, Municipal Wastewater Regulation 87/2012.
Discussions with the MoE indicate the following:
• cBOD5 and TSS should be less than or equal to 25 mg/L based on monthly averages.
• Wastewater flows exceeding the capacity of the secondary treatment works may bypass those works when
flows are greater than two times measured dry weather flow, provided that primary treatment effluent standards
are maintained for the effluent not receiving secondary treatment.
• Primary treatment standard required for flow bypassing secondary is 130/130 mg/L.
• The effluent will be disinfected between May 1 and September 30. The biological indicator for disinfection was
still under discussion with the MoE at the time of publication but will be either Enterococci or E. coli. If chlorine
is used, the effluent will be dechlorinated to less than 0.02 mg/L total residual chlorine before discharge.
456928_WBG103013092847VBC 4-3
Regulatory Permitting and Approvals
sector across Canada. An element of the strategy was the development of effluent discharge objectives (EDOs) to
protect water users.
In an August 2012 report, Tri-Star Environmental Consulting undertook an initial evaluation of EDOs for the new
LGSWWTP based on effluent data obtained from the existing primary plant. This initial report was subsequently
updated in October 2013 to provide additional monitoring data and address comments received by the MoE. The
August 2012 report is included in Appendix 4B and the October 2013 report in Appendix 4C. A draft list of potential
substances developed is summarized in Table 4-1.
Substance
Fluoride
Cadmium – total
Chromium
Copper – total
Polychlorinated biphenyls
Permethrin
Biosolids from LGSWWTP will be integrated with Metro Vancouver’s existing regional beneficial reuse program.
4-4 456928_WBG103013092847VBC
Regulatory Permitting and Approvals
Table 4-2. Municipal Effluent Quality Requirements for Reclaimed Water (MWR)
Exposure Potential
Fecal coliform Median < 1 CFU or Median < 1 CFU or Median 100 CFU; Median 200 CFU;
(per 100 mL) < 2.2 MPN < 2.2 MPN; maximum maximum 400 CFU maximum 1,000 CFU
14 CFU
Section 113 of the MWR lists the following requirements for the disinfection of reclaimed water:
4.4 Municipal
• Any noises or sounds continuing for any period of time created by earth-moving equipment exceeding a
maximum sound level of 80 decibels (acoustic) (dBA), or any noises or sound continuing for any period of time
created by earth-moving equipment that causes the daytime average sound level to exceed 65 dBA (equivalent
noise level [Leq]) at the point of reception.
456928_WBG103013092847VBC 4-5
Regulatory Permitting and Approvals
• Any continuous sound that exceeds the following sound levels at the point of reception:
− In a Quiet Zone during the day 55 dBA
− In a Quiet Zone during the night 45 dBA
− In an Activity Zone during the day 60 dBA
− In an Activity Zone during the night 55 dBA
• Any noncontinuous sound that exceeds the following sound levels at the point of reception:
− During the day 80 dBA
− During the night 75 dBA
• Any construction noise that exceeds a sound level of 80 dBA at the point of reception
The bylaw defines “day” as the period of time from 7:00 am to 8:00 pm each week day or Saturday, and from
9:00 am to 8:00 pm on a Sunday or holiday. “Night” is defined as all other time periods.
• No net increase in the rate and volume of stormwater runoff from existing to developed conditions up to the
mean annual rain event (MAR) (2-year return period)
• If existing imperviousness is greater than 50 percent, no net increase in the rate and volume of stormwater
runoff beyond a maximum 50 percent effective imperviousness up to the MAR (2-year return period).
4-6 456928_WBG103013092847VBC
Community Acceptance and User Requirements
Metro Vancouver’s Public Involvement Division led community engagement for the project. Throughout the project
definition phase, the IDT met with representatives from the community on several occasions to present and solicit
feedback on the design concepts as they were developed. Related documents (available for download from the
project website http://www.metrovancouver.org/services/wastewater/engagement/lionsgate/Pages/default.aspx )
include:
1. Engagement and Consultation Results: Project Definition Phase for Lions Gate Secondary Wastewater
Treatment Plant. Prepared by the Metro Vancouver Public Involvement Division (October 23, 2013)
2. Lions Gate Public Advisory Committee (LGPAC) report on Indicative Design (October 21, 2013)
At these meetings, the following concerns and opportunities were identified by the community.
Concerns
• Odour Control. Odour control and its impact on surrounding properties is a primary issue for the community.
This issue has been raised in all meetings with the community.
• Air Quality. The community has also raised concerns about air quality, which is related to odour control and air
pollution. Community members want facility emissions to be regularly monitored and reported.
• Traffic Impacts. There is concern that the plant will result in additional truck traffic in the neighbourhood.
• Aesthetics. The community accepts that the site is industrial. The site is currently nondescript and does not
contribute positively to the community. The height and scale of the proposed treatment facility and its site
design are important considerations, and it is important that they are appropriate to the neighbourhood context.
• Noise. It was identified that the primary source of noise in the neighbourhood is the Canadian National Railway
Company (CN) railway. Some community members see the plant as a potential noise barrier, though any effect
456928_WBG103013092847VBC 5-1
Community Acceptance and User Requirements
of the plant on CN rail noise is considered to be incidental. It is expected that the plant will not contribute to
additional noise levels in the community.
• Environmental Impacts and Long-term Planning. There is an understanding that the new facility will
represent an improvement in current environmental standards related to wastewater treatment. This includes
nutrient recovery, energy recovery, and water treatment to secondary standards. The community expressed a
desire for wastewater to be treated to higher standards where feasible.
• Cost. The cost of the facility and the impact on rates is a concern. The community wants to receive good value
for money.
• Public Health and Safety. Avoiding a negative impact on public health and safety for the neighbouring
residents and businesses is an important issue. This is closely related to the other sensory issues, including
odour, air quality emissions, and noise.
• Construction Impacts. Given that construction is expected to take place over several years, residents are
concerned about the impacts of construction on the neighbourhood.
Opportunities
• Community Amenities. The IDT identified that the LGSWWTP should improve the community. Some potential
opportunities for amenities include making the site a public destination, providing community space,
incorporating water features, and ensuring high-quality plant aesthetics.
• Educational Opportunities. The plant provides an important opportunity to educate the community about the
issues of water use, water treatment, water consumption, and waste recovery.
• IRR. The community desires that resources should be recovered from the wastewater where possible, including
energy, nutrients, and water.
5-2 456928_WBG103013092847VBC
Community Acceptance and User Requirements
• Goods handling
• Detailed treatment-area programming requirements
• Centralized storage requirements
• Layout and security requirements for non-treatment spaces
• Use and sizing of non-treatment spaces
• Shipping and receiving requirements
• Flood protection requirements
• Key functional adjacencies
Commissioning
• Commissioning procedures
• Commissioning handover plan
These discussions had a substantial influence on the Indicative Design. Specific strategies incorporated into the
Indicative Design include:
456928_WBG103013092847VBC 5-3
Community Acceptance and User Requirements
HHWLT 1.9 m
Freeboard 0.6 m
5-4 456928_WBG103013092847VBC
Site Characterization
6. Site Characterization
6.1 Section Description
The local and regional context of the project site (see Figure 6-1) has been integral to the design of the new
LGSWWTP. Investigations began by seeking to understand how the site fits within the broader geological,
ecological, and First Nations context of the North Shore, and how the site has been shaped by dynamic physical
and ecological processes over time. Site analysis also focused on understanding the modern day land-use,
circulation, and geographic patterns surrounding the site, and the projected changes to these activities over the
coming decades. Soil conditions, drainage patterns, circulation connections, and experiential qualities of the site
were documented at the parcel level.
456928_WBG103013092847VBC 6-1
Site Characterization
6.2.1 Climate
The site is within the Coastal Western Hemlock dry maritime (CWHdm) biogeoclimatic zone, which is characterized
by cool summers and mild winters (BC Gov, 1991). The average total annual precipitation at the site is
1,772 millimetres (mm) (Environment Canada, 2013). Figures 6-2 and 6-3 provide further climate details.
6-2 456928_WBG103013092847VBC
Site Characterization
The project site is generally flat, at an elevation of around 2.5 to 3 masl. Stormwater catch basins are located
around the perimeter of the site, and drain stormwater from the western portion of the site to the Philip Avenue tidal
channel, and stormwater from the eastern portion of the site to the Pemberton Avenue tidal channel. There are no
watercourses or areas of standing water on the site at any time of year. Figure 6-6 shows drainage pattern details.
456928_WBG103013092847VBC 6-3
Site Characterization
6-4 456928_WBG103013092847VBC
Site Characterization
A discontinuous row of five Douglas fir trees are located on the eastern-central portion of the site (Figure 6-7).
Immature black cottonwood trees with an understory of non-native butterfly bush and Himalayan blackberry occur
along the eastern property boundary. Most of the site area is covered by unvegetated gravel or asphalt, but the lack of
recent use has allowed some areas to become colonized by weedy species, including butterfly bush, black
cottonwood (1 to 3 years old; less than 5 m in height), red clover, St. John’s Wort, and other early successional plant
species. These shrub thickets are used by bird species tolerant of urban areas, including spotted towhee, song
sparrow, and northern flicker. No species at risk or ecological communities at risk are known to use the site.
456928_WBG103013092847VBC 6-5
Site Characterization
Pemberton Avenue, to the east of the site, is currently classified as a major arterial route, but the DNV’s Official
Community Plan (2011) re-classifies it as a minor arterial route. It has two travel lanes in both directions and
parking on both sides of the street. Pemberton Avenue north of 1st St. has a more pedestrian feel, with continuous
sidewalks on both sides of the street, small lot frontages, and narrow building setbacks.
Philip Avenue, to the west of the site, is currently a short section of street that runs between Welch Street to the
north and the railway tracks to the south.
Under a proposal for port upgrades, the at-grade rail crossing at the foot of Pemberton Avenue will be closed to
non-emergency vehicles and replaced with a pedestrian-only overpass. A multi-use overpass (vehicle, bike,
pedestrian) will be built at the foot of Philip Avenue, and the intersection of Philip Avenue and 1st St. will become
signalized.
There is currently no public transit service in the immediate vicinity of the site. The closest transit service is along
Harbourside Drive, east of the Mackay Creek estuary, and along Marine Drive, 750-m north of the site.
The North Shore Spirit Trail, an active multi-use transportation route, passes 1 block north of the project site. It
currently extends east toward the Mosquito Creek estuary, and west through Ambleside Park. Figures 6-8 through
6-10 illustrate current local circulation patterns in the immediate vicinity of the project site.
6-6 456928_WBG103013092847VBC
Site Characterization
456928_WBG103013092847VBC 6-7
Site Characterization
6-8 456928_WBG103013092847VBC
Site Characterization
456928_WBG103013092847VBC 6-9
Site Characterization
6-10 456928_WBG103013092847VBC
Site Characterization
Figure 6-12. Extensive Intertidal Marsh and Mud Flats East of Lions Gate Bridge in 1947
The shoreline of North Vancouver between the Capilano and Seymour Rivers has been extensively modified in the
past century, with much of the intertidal marshes converted to industrial land uses between the 1940s and 1960s.
Remnant intertidal wetlands are now rare on the North Shore and include the Lions Gate salt marsh immediately
east of the Lions Gate Bridge, and Maplewood Flats salt marsh east of the Seymour River.
While the site itself has few features of ecological value, there are several ecologically important areas in the
vicinity of the project site, including:
• Mackay Creek is an important salmon-bearing stream in North Vancouver and crosses 1st St. approximately
375 m east of the site. Mackay Creek is surrounded by a substantial forested riparian corridor that connects
Burrard Inlet with the forested upper watershed.
• Mackay Creek Wetlands are located one block east of the project site, and consist of a mix of forested swamp
and seasonally flooded, open water areas. The wetlands provide some seasonal value for fish and other
wildlife, but they are affected by low summer water level and high invasive species cover.
456928_WBG103013092847VBC 6-11
Site Characterization
• Pemberton Avenue tidal channel is a narrow (15- to 20-m wide by 275-m long) tidal channel that follows the
western side of the Pemberton Avenue ROW. It is a remnant intertidal habitat created by the filling of adjacent
sites for industrial development.
• Philip Avenue tidal channel is a smaller tidal channel located southwest of the project site with a similar
history to the Pemberton Avenue tidal channel.
• Welch Strip Park is a linear park area separating the industrial lands to the south from the residential area of
Norgate to the north. It is a largely manicured landscape with some mature conifer and deciduous trees along
its southern edge.
Figure 6-13 shows the existing local vegetation and ecosystems.
6-12 456928_WBG103013092847VBC
Site Characterization
The character of the neighbourhood beyond the site varies widely, as follows:
Community space in the Norgate area is somewhat limited, but likely proportional to the relatively low population
density of the area. A number of community functions operate out of the Norgate Community School, north of the
project site. Some additional community services take place at the Capilano House and the Anglican Church. Other
nearby schools include Capilano Little Ones School (Xwemelch'stn Etsímxwawtxw) at Squamish Nation, Bodwell
High School (private), and Lions Gate Christian Academy (private).
Active recreation space is provided at Welch Strip Park, Norgate Community School, Norgate Park, Squamish
Nation, and the Grant Connell Tennis Centre. A section of the Spirit Trail passes through Welch Park, extending
east toward Mosquito Creek and west to Ambleside Park.
The high-density, mixed-use development planned for Lower Capilano Marine Village will incorporate a community
centre, and the CNV’s Harbourside development is anticipated to incorporate other community amenities
(childcare, community gardens, Spirit Trail connections).
• CN: An intensification of port activities is prompting the closure of the Pemberton Avenue rail crossing to
vehicle access (with the exception of emergency vehicles), and the establishment of a vehicular-pedestrian
overpass at the south end of Philip Avenue.
• Seaspan Marine: A major expansion of ship-building activities will take place at Seaspan over the next 5 to
10 years, with a corresponding increase of up to 1,000 new jobs (Vancouver Sun, 2013). Vehicular access to
Seaspan will be via the Philip Avenue Overpass. Pedestrian access will be via the Pemberton Avenue
pedestrian overpass or the Philip Avenue Overpass.
456928_WBG103013092847VBC 6-13
Site Characterization
• Harbourside development: This new multi-use development, east of the Mackay Creek estuary on CNV
waterfront property, is projected to have 800 new homes and 1,500 new full-time jobs (Concert, 2013). This
large-scale redevelopment will likely increase pedestrian activity and demand for transit connections in the
vicinity of the project site.
• Lower Capilano/Marine Village Centre: The DNV has started transforming the Marine Drive and Lower
Capilano area into a future Town Centre, which will lead to a large increase in population density, jobs, and
community amenities.
Figure 6-14 illustrates land use and community amenities.
• Liquefaction;
• River flooding (that is, within Mackay Creek floodplain)
• Tsunami
• SLR due to climate change.
Refer to Section 8 for the ways that the LGSWWTP Indicative Design mitigates these risks.
6-14 456928_WBG103013092847VBC
Site Characterization
6.5 Archaeological
456928_WBG103013092847VBC 6-15
Site Characterization
Following inspection of all cores obtained from geotechnical drilling, results indicated that there were no layers with
a high potential of encountering subsurface cultural materials. Detailed results can be found in the Archeological
Report prepared by Sources (2013) in Appendix 6A.
6.6 Utilities
Existing utilities and services data in the vicinity of the proposed LGSWWTP site bounded by Philip Avenue, 1st St.,
Pemberton Avenue, and the CN railway ROW was collected via BC OneCall and from the DNV. Third-party-owned
services are as follows:
• BC Hydro – Overhead three-phase power on 1st St., with an underground duct bank west of Philip Avenue
• Telus – Overhead telephone line on 1st St. and underground fibre-optic cable on Philip Avenue
• Fortis – 60-mm distribution pressure gas main on 1st St. and on Philip Avenue, and 88-mm distribution pressure
main on Pemberton Avenue
The DNV has a 300-mm ductile iron water main on 1st St. There is an abandoned 250-mm asbestos cement water
main crossing the LGSWWTP site within the historical 1st St. ROW.
6-16 456928_WBG103013092847VBC
Site Characterization
The DNV’s storm sewer system on 1st St. currently crosses the LGSWWTP site with a 600-mm storm sewer that
ties into the system on Philip Avenue and discharges via a storm outfall to Burrard Inlet. As part of the DNV’s
Philip Avenue Overpass project, the storm system on Philip Avenue will be modified and will include a 600-mm stub
connection east of the intersection of Philip Avenue and 1st St. The future intent is to relocate the 600-mm sewer
crossing the site into 1st St. and connect it to the new stub. Refer to Drawing X-C10-002 for site utilities information.
Additional information on existing site geology is provided in Golder Associates’ (Golder’s) geotechnical reports in
Appendixes 8B and 8C.
A Certificate of Compliance (CofC) was issued by the MoE for the site on March 23, 2011. This CofC was
completed to meet Contaminated Sites Regulation standards for industrial land soil use and marine water aquatic
life water use. Remediation in soil and groundwater was to meet both numerical standards and risk-based
standards.
The risk-based CofC indicates that in its current configuration and use (vacant, fences, limited access industrial
property), the site does not pose an unacceptable risk; however, there is still contamination that exceeds numerical
standards present on the site. Material determined to meet the classification of hazardous waste is also present
onsite. The CofC is essentially only valid for the existing site and land uses.
The majority of the remaining contamination is located on the western third of the site. Light extractable petroleum
hydrocarbon, heavy extractable petroleum hydrocarbon, polycyclic hydrocarbons, and metals were identified in soil
and groundwater. There is also a small area near the centre of the southern boundary with impacts of copper in
water and a small area near the northeastern corner where impacts of cadmium in water is present. Contamination
also exists offsite, and a cut-off wall was installed along the southeast property boundary to prevent ingress of
contaminated water from offsite.
6.9 Noise
Several of the surrounding industrial land uses generate a moderate amount of noise that can be heard at the
project site. Traffic noise along 1st St. is projected to increase with intensifying port activity.
BRC Acoustics & Audiovisual Design (2012) conducted a Baseline Sound Analysis for the LGSWWTP site.
Sources of existing sound levels received onsite and in the Norgate community include moderate traffic (including
456928_WBG103013092847VBC 6-17
Site Characterization
buses) on 1st St., traffic on Welch Street, and train manoeuvres on the CN rail tracks and spurs serving industrial
and shipping facilities to the south. Sound from train manoeuvres was clearly audible at all measurement locations.
The sound levels measured during the daytime were generally consistent with the DNV noise limits, with a minor
exception, which exceeded the noise limits due to the location’s proximity to arterial traffic on Welch Street. Existing
sound levels during the nighttime generally exceed the nighttime noise limit as established by the DNV Noise
Bylaw.
The results of this analysis suggest that the DNV noise limits are valid design criteria for sound levels from the
project, and also constitute appropriate criteria for preventing significant increases in sound levels at the receiver
locations due to the project. Detailed results of the sound analysis can be found in the Baseline Sound Analysis
(BRC Acoustics & Audiovisual Design, 2012) in Appendix 6C.
6-18 456928_WBG103013092847VBC
Evaluation of Existing Outfall
There are 10 diffuser ports positioned along the crown of the 1.37-m conduit at 30.5 m (100 ft) from the
downstream end before flow is released into the First Narrows. The estimated losses and required inlet hydraulic
grade line (HGL) elevation are summarized in Table 7-1.
456928_WBG103013092847VBC 7-1
Indicative Design – Wastewater Treatment
The design horizon for the LGSWWTP site is to the end of the century. Major infrastructure, including the digesters
and primary and secondary treatment tanks, were sized to accommodate projected population growth on the North
Shore to Year 2051. The sizing of most equipment, which has a typical life of 15 to 20 years, is based on the
projected flows and loads in Year 2035.
The following recommendations are put forward as post-disaster seismic objectives for LGSWWTP:
• All buildings and structures that will be occupied on a full- or part-time basis should be designed for immediate
occupancy, as described in the NBC and reflected in Metro Vancouver’s current seismic design criteria for
Immediate Occupancy and Life Safety Performance Levels.
• All tanks should be designed in accordance with American Concrete Institute (ACI) ACI 350 – Code
Requirements for Environmental Engineering Concrete Structures or American Water Works Association’s
(AWWA) D110 Wire- and Strand-Wound, Circular, Prestressed Concrete Water Tanks, as appropriate, and
using ground motion parameters stipulated in the NBC. Of note is that both the ACI and AWWA documents use
an Importance Factor (I) of 1.25 for “tanks that must remain usable to provide emergency service after an
earthquake or that are part of lifeline systems.” Additionally, both ACI and AWWA acknowledge the potential for
some structural damage and insignificant repairable leakage.
• A detailed study should be carried out, as recommended in the User’s Guide – NBC 2010 Structural
Commentaries (UGNBC) (NRCC, 2010) and in consultation with the MoE and other appropriate regulatory
authorities and stakeholders to establish post-disaster wastewater treatment objectives for the LGSWWTP.
• Standby power should be provided for all life- and building-safety systems at a minimum, and the LGSWWTP
Indicative Design should include provisions to provide standby power to the following additional treatment
processes:
− Influent pumping
− Preliminary treatment
456928_WBG103013092847VBC 8-1
Indicative Design – Wastewater Treatment
− Primary treatment
− Disinfection
− Primary sludge (PS) pumping
• Good design practices should be followed consistent with good industry practice.
8.2.2 Flooding
Structures and buildings that house essential process and equipment will be flood-protected to an FCL of 6.0 m, as
discussed in Section 5.5. Flood-proofing of buildings and structures will include the following:
• All doors and openings into buildings and structures that house essential processes will be at or above
elevation 6.0 m, or if not feasible, then flood-protected.
• Access into manholes and wet wells below elevation 6.0 m will be through sealed and bolted hatches or
manhole lids.
• Truck bays will be at elevation 4.1 m and will not house essential equipment below elevation 6.0 m. Truck bay
structures will be designed to resist water to elevation 6.0 m, and doorways can be sealed using sand bags.
The truck bay building will be designed to bring the structure back quickly into service after flooding above
elevation 4.1 m. Loading docks and general storage floors will be at elevation 5.3 m.
• Sumps with pumps will be provided to collect drainage water in process areas. There will be no direct
connection of building drains to sewers and process drains below elevation 6.0 m.
8.2.3 Wind
All building, structures, stacks, piping, and equipment that is exposed to wind forces will be designed to meet the
requirements of the BC Building Code (BCBC), Section 4.1.7, Wind Load, as post-disaster structures. Important
factors from BCBC, Table 4.1.7.1 for post-disaster situations will be used in the design of structures and
components.
• Design buildings for immediate occupancy post-disaster, as described in the current BCBC and UGNBC.
• UGNBC Commentary J, Paragraph 225: “The design of free-standing tanks is outside the scope of the NBC.”
• ACI 350.3-06 and AWWA design standards for seismic design of tanks intended to remain usable for
emergency purposes after an earthquake, or tanks that are part of lifeline systems.
• ACI 350.3-06 and BCBC to verify the structure has exceeded BCBC post-disaster requirements.
8-2 456928_WBG103013092847VBC
Indicative Design – Wastewater Treatment
• ACI 350.3-06, Chapter 7, Freeboard, using an I of 1.5. Table 8-1 provides a summary of the freeboard required
for the major liquid treatment processes.
8.3 Geotechnical
Golder carried out the geotechnical field investigations and prepared the factual and interpretive reports for this
project, which are provided in Appendixes 8B, 8C, and 8D. This section presents recommendations from Golder’s
reports.
Based on the results of the geotechnical investigation, portions of the soils underlying the site are considered to be
susceptible to liquefaction, with resulting liquefaction-induced settlements. Given these conditions and the loads
and settlement tolerances of the proposed structures, combined with the seismic hazard, the use of shallow
foundations without ground improvement is considered very unlikely to be feasible. The various options for ground
improvement have advantages and disadvantages, and several are considered marginally feasible or would have
undesirable impacts on nearby residents and facilities, and are, therefore, not recommended. Among the options
considered, compaction grouting targeting the upper and lower zones of potential liquefaction is considered the
most feasible (Golder, 2013).
It bears repeating that even with adequate ground improvement, it is not technically feasible to support the heavily
loaded digesters on shallow foundations, and it may also be challenging to achieve the desired performance for
some of the other structures using shallow foundations. Consequently, it is recommended that the digesters be pile-
supported. The depth to the underside of the digester footing and those of other structures is considerable and
would result in the need for excavation and dewatering for both piled and shallow foundation options. However, the
challenges associated with suitable subgrade preparation under these conditions would be more critical for shallow
foundations and present the risk of compromised subgrade preparation, with resulting unsatisfactory performance
(Golder, 2013).
The technically preferred, lowest-risk, and most reliable option for foundation support at this conceptual stage is
driven non-displacement (open-ended) steel pipe piles, followed by closed-ended steel pipe piles driven to suitable
bearing in the underlying sand to a depth of between 25 and 30 m below the existing ground surface (elevation -22
to -27 m). While other options may ultimately be proven feasible based on appropriate engineering analysis, they
are unlikely to be considered unless there is significant cost or time saving, or to address environmental or
neighbourhood impacts (Golder, 2013).
Further engineering analysis and onsite testing would be required to evaluate specific technical and constructability
issues and costing identified during this current phase of the project. In particular, evaluation of the rest and effects
of liquefaction within the deeper strata, in particular, would benefit from more detailed numerical analysis, with the
potential to demonstrate that this risk is low within the highly permeable soils at the site. This finding would have a
significant impact on foundation option selection and cost. Pile driveability and load testing also offers the potential
for significant cost, schedule, and environmental impact benefits, and would be recommended regardless of the
procurement options ultimately selected. The following recommendations for additional work are provided for
Metro Vancouver’s consideration:
456928_WBG103013092847VBC 8-3
Indicative Design – Wastewater Treatment
• Pile driveability testing to confirm the drivability of steel pipe piles, both closed- and open-ended. Pile dynamic
analyzer testing is recommended during driving.
• Pile load testing to evaluate the capacity of driven piles. This is particularly important for open-ended piles,
since the formation of a suitable soil plug is an uncertain factor.
• Additional engineering analysis of the liquefaction potential and its impact on foundation options and
performance. The analysis should comprise an effective stress analysis that accounts for the cyclic behaviour
and drainage of the soil in order to evaluate whether sufficient excess porewater pressure develops under
cyclic loading to cause liquefaction. The potential impact of various scenarios on various foundation support
options should be considered (Golder, 2013).
It is expected that all groundwater extracted from the site during dewatering activities will require treatment prior to
discharge, and additional cut-off walls along the southern property boundary may be warranted to prevent ingress
of contaminated water from offsite. A cutoff wall was installed along the southeastern property boundary to prevent
ingress of contaminated water from offsite.
Further investigations on the DNV property immediately east of the LGSWWTP site and at the foot of Pemberton
Avenue, which is intended in the Indicative Design to be used as a public plaza, may be required, as such
investigations were beyond the scope of this project.
The requirement for a site profile submission(s) to the MoE will be triggered by applications for zoning,
development permits, and/or soil removal and demolition permits; and one of the following is required for the
approving authority (DNV) to release the application (MoE, 2010):
1. The approving authority is not required to forward a copy of the site profile to a Director.
2. The authority has received a final determination that the site is not a contaminated site.
3. The authority has received an Approval in Principle (AiP) or CoC with respect to the site.
4. The authority has received notice from the Director indicating he or she has entered into a Voluntary
Remediation Agreement with respect to the site.
5. The authority has received notice from the Director that site investigation is not required.
6. The authority has received notice from the Director that it may approve an application because the site would
not present significant threat or risk if the application were approved.
7. The authority has received notice from the Director that the Director has received and accepted a notice of
independent remediation with respect to the site.
Given the LGSWWTP site is known to be contaminated and a CoC has already been issued by the MoE, Item 3 is
the preferred pathway for allowing the approving authority to proceed with any land-use and development related
applications. Both AiP and CoC are recognized in the Environmental Management Act and Local Government Act
as legal instruments. The AiP pathway requires the submission of a remediation action plan (RAP) prepared by an
8-4 456928_WBG103013092847VBC
Indicative Design – Wastewater Treatment
approved professional (AP) and approval by the Director; and the CoC pathway requires the site to meet numerical
or risk-based standards, which may require a risk assessment and possibly remediation.
Between the AiP and CoC pathways, AiP would appear to have the following advantages:
• Remediation work is likely not required in advance of an AiP being issued; whereas, it may be required for a
CoC. Therefore, it would be possible to include any remediation work within the scope of work of the main
construction contract rather than have separate construction contracts for remediation and construction.
• The preparation of a RAP may be more amenable to procuring LGSWWTP using design-build-finance-operate-
maintain (DBFOM) or design-build (DB) delivery models, as the plan could provide more flexibility for
proponents to innovate and meet performance-based specifications, rather than binding them to specific
conditions prescribed in a CoC.
Based on the foregoing discussion, the following two-step pathway is recommended for Metro Vancouver’s
consideration:
• Step 1 – Apply to MoE for AiP to use as legal instrument to support land-use and development applications to
the DNV.
456928_WBG103013092847VBC 8-5
Indicative Design – Wastewater Treatment
Table 8-2. Possible Technology Migration Pathways for Liquid Treatment Stream
A significant contributing factor to the selection of thermophilic anaerobic digestion (TAD) as the anchor biosolids
technology is its ability to produce Class A biosolids and consistency with stabilization practices at
Metro Vancouver’s wastewater treatment facilities, including Annacis Island, Iona Island, and Lulu Island, which will
allow biosolids from LGSWWTP to be readily adapted to whatever beneficial reuse opportunities may be pursued
by Metro Vancouver in the future.
In the event additional digestion capacity is required, the technology migration pathway is to optimize solids loading
rates, based on full-scale operational experience, recuperative thickening, and enhanced volatile solids destruction
technologies.
HRC will be used to provide primary treatment to wet weather flows. High-rate clarifiers have an extremely small
footprint and are ideally suited for intermittent use in wet weather applications. Effluent from the HRC process will
be blended with SE and flow to the disinfection process.
8-6 456928_WBG103013092847VBC
Indicative Design – Wastewater Treatment
The requirement for disinfection is seasonal, and when required, UV light will be used. The disinfection process will
include two channels equipped with bulbs that transmit UV-wavelength light to the treated effluent to destroy
pathogens. Disinfected treated effluent will be conveyed to the existing outfall and discharged to Burrard Inlet.
The Indicative Design also includes deammonification of centrate produced by the anaerobic digestion and
dewatering processes to reduce effluent toxicity. A reclaimed water system is provided to offset in-plant potable
water use.
The stabilized product from the digestion process will be pumped to a dewatering process employing centrifuges to
remove excess water, which will significantly reduce the volume of the final product and give it the consistency of
solid material. The final dewatered biosolids cake will be loaded in trucks and included as part of
Metro Vancouver’s biosolids beneficial reuse program.
456928_WBG103013092847VBC 8-7
Indicative Design – Wastewater Treatment
456928_WBG103013092847VBC 8-9
Indicative Design – Wastewater Treatment
Dry well-mounted, submersible pumps are selected for the LGSWWTP, as they are best suited for trench wet well
applications and meet post-disaster requirements when installed below the FCL established for the site. Each pump
has a maximum flow rate of 110 ML/d at a total design head of 20 m, and a rated power of 340 kilowatt (kW).
Screenings removed by both the coarse and fine screens are conveyed to a screenings handling area where they
are washed and compacted prior to discharge into screenings hoppers. The hoppers discharge the compacted
screenings into storage containers for removal to an approved offsite disposal facility.
The double-bottomed target tank has an active volume of approximately 20 cubic metres (m3), and is equipped with
a drop box, two knife gates, and a flushing water system. The drop box discharges wet screenings onto two
screenings conveyors that transport the material to two washer/compactors. The two washer/compactors wash and
compact the screenings from the two duty coarse screens and the two duty fine screens, and discharge the
compacted screenings into a 3-m3 screenings hopper. Screenings fall by gravity from the hopper into a 10-m3
screenings container for removal to offsite disposal.
456928_WBG103013092847VBC 8-11
Indicative Design – Wastewater Treatment
The operator sets the number of units required to match the average daily flow to the plant at the time. For
example, during dry weather when the average daily flow to the plant is between 80 and 100 ML/d, only one or two
units need to be in operation. During wet weather flow events when the average daily flow to the plant is between
200 and 240 ML/d, a minimum of three units need to be in operation. The in-service grit concentrators work
continuously. Grit removed in the degritters is pumped to grit handling units where it is washed and classified to
remove the organics, and dewatered prior to discharge to storage containers for removal to offsite disposal.
Each unit has a dedicated slurry pump that continuously pumps the separated grit to a dedicated grit washing/
classification unit. These units separate the inert grit from the organic solids and very fine inert solids. The grit
washing/classification units are fully enclosed, stainless steel, vortex-type units. The four grit washing/classification
units have a design flow of between 18 and 25 litres per second (L/s) per unit, and are capable of removing
95 percent of grit particles greater than 75 micrometres (µm) in size with this flow range. Each unit is 0.8 m in
diameter and has an average design flow of 18.9 L/s (1,600 cubic metres per day [m 3/d]). The grit slurry drains by
gravity from the bottom of the grit washing/classification units to two dewatering conveyors. There are two grit
dewatering units, with each unit being dedicated to two washing/classification units. The two dewatering conveyors
have a capacity of 2.3 cubic metres per hour (m3/h) per unit. Each unit has a 1.8-m by 1.8-m clarifier and 0.5-m-
wide belt. The dewatered grit is discharged to a grit hopper and then into storage containers for removal to offsite
disposal.
Primary clarifiers separate out the easily settleable solids, and the material is collected and removed for further
processing. Primary clarifiers remove 50 to 70 percent of influent suspended solids and 25 to 40 percent of the
influent BOD. There are three (two duty and one standby) primary clarifiers, each having dimensions of 37-m long
by 12-m wide by 5.0-m side water depth (SWD). The tanks are fitted with lamella plate packs over much of the
settlement area, which increases the hydraulic loading rate that the units can handle. Two of the primary clarifiers
are capable of handling flows up to 204 ML/d (twice the ADWF).
Wet weather flows exceeding 204 ML/d (twice the ADWF) are bypassed around the primary clarifiers and treated in
two HRC units.
8-12 456928_WBG103013092847VBC
Indicative Design – Wastewater Treatment
The system consists of two HRC units, each with a capacity of 60 ML/d. The system consists of the following four
tanks in series: coagulation, polymer injection, maturation, and clarification. The clarifier is a high-rate settling tank
equipped with lamella plate settlers and a scraper mechanism.
The total bioreactor volume is 20,000 m3, which is divided into four individual bioreactors that operate in parallel.
Each bioreactor has three passes, 28-m long, 6-m wide, and 10-m SWD, for a total volume of 5,000 m3. Each of the
12 passes has an unaerated (anoxic) zone, followed by an aerated zone. The anoxic zones are mechanically mixed
using bridge-mounted, 1.125-kW hyperboloid mixers. The aerobic zones are mixed and aerated using a fine-bubble
aeration system with floor-mounted membrane diffusers. Process air to the membrane diffusers is supplied by four
duty and one standby high-efficiency turbo blowers. Three of the turbo blowers have a capacity of 7,576 normal
cubic metres per hour (nm3/h) and a power rating of 263 kW. The remaining two turbo blowers have a capacity of
3,674 nm3/h and a power rating of 113 kW.
ML from the four bioreactors flows over effluent weirs into a degassing channel, where it is stripped of the dissolved
nitrogen and other gases that may cause sludge flotation in the secondary clarifiers. Both the ML channel and the
degassing channel have a SWD of 5 m and are equipped with a coarse-bubble aeration system that agitates the
ML and prevents solids deposition in the channels.
Return secondary sludge (RSS) from the secondary clarifiers is distributed to the four bioreactors from the RSS
channel. A portion of the RSS, referred to as waste secondary sludge (WSS), is continuously wasted from the end
of the RSS channel to the WSS thickeners in order to maintain the bioreactor solids retention time (SRT) at
between 4 and 6 days.
Each secondary clarifier has a dedicated RSS pump capable of withdrawing about 1 x AAF from the clarifier. The
RSS pumps are screw centrifugal pumps equipped with variable frequency drives (VFDs), and are located in a
456928_WBG103013092847VBC 8-13
Indicative Design – Wastewater Treatment
pump galley between the two sets of clarifiers. Each pair of clarifiers is served by a secondary scum sump. Scum
collected in the sumps is pumped to the rotary drum thickeners (RDTs) for thickening together with the WSS.
8.7.11 Disinfection
UV light is used to disinfect the treated effluent by inactivating pathogenic bacteria, viruses, and other
microorganisms so that they can no longer replicate. In UV disinfection systems, the UV light is produced by lamps
that are submerged in wastewater channels. Next-generation UV technology is used as a representative
technology for LGSWWTP.
The requirement for disinfection is seasonal, between May 1 and September 30, and the design assumption is that
effluent is required to meet enterococci or escherichia coli (E. coli) limits of 20 MPN/100 mL at the edge of the initial
dilution zone. The UV disinfection system is sized for the entire PWWF of 320 ML/d at a UV transmittance of
40 percent to reflect a blended effluent comprising effluent from both the secondary treatment process and HRCs.
The UV disinfection system is designed to operate continuously and is controlled by a vendor-supplied system
control centre with very little operator assistance required.
The filtrate from the PS thickening process is returned to the front end of the plant for further treatment. Progressing
cavity pumps transfer the thickened primary sludge (TPS) into the sludge blending tank. The piping configuration
upstream of the pumps will allow the operator to use either pump with either RDT.
The filtrate from the thickening process is returned to the front end of the plant for further treatment. Progressing
cavity pumps transfer the thickened waste secondary sludge (TWSS) into the sludge blending tank. The piping
configuration upstream of the pumps will allow the operator to use either pump with either RDT.
There are two thermophillic anaerobic digesters that can operate in parallel or in series. The digesters are large,
concrete tanks with fixed-cover, concrete roofs, and are sized to provide an SRT of approximately 17 days at
8-14 456928_WBG103013092847VBC
Indicative Design – Wastewater Treatment
maximum month sludge flow and load with one unit out of service. The digesters are tall, cylindrical units with a
steep, conical bottom to eliminate solids deposition, and have a partially submerged, inverted cone roof. The sludge
in the digesters is mixed using a pumped mixing system to promote the digestion process and to minimize
deposition of solids within the digester tanks. A digester heating system based on spiral heat exchangers is
selected for the Indicative Design.
The two digesters have conical bottoms with a floor slope of 1 to 1. The inverted cone roof of the digester is sloped
at about 1 in 4 toward the centre. Almost all of the roof is submerged, with the design liquid level being just below
the top of the cone. In this arrangement, mixing energy causes rising currents that are deflected by the underside of
the roof toward the centre of the digester. Each digester has two horizontal chopper pumps (one duty and one
standby), each with the capacity to pump the entire mixing flow. The mixing pumps are located in the pump gallery
under the cone of the digesters. The pumps withdraw digested sludge (DS) from a low point in the centre of the
digester cone and distribute the sludge back into the digester through fixed nozzles mounted within the digester.
The two duty digester feed pumps operate continuously at a constant speed. The digester hydraulic mixing system
is designed to operate continuously. However, these systems can be run intermittently with no impact on gas
production or sludge stabilization effectiveness. Intermittent operation of the hydraulic mixing system results in
significant mixing power cost savings.
The gas management system provides the equipment and controls necessary to collect, distribute, and control the
biogas produced in the anaerobic digesters. The biogas management system includes several major components,
including the digester gas domes and safety-relief equipment, low-pressure gasholder, moisture removal system,
and waste-gas burners.
The biogas system operates at a pressure that is normally about 250 mm of water (H2O). When the biogas
pressure increases above this point, it will be directed to flare, and at a high-high pressure (at about 300-mm H2O),
pressure-relief valves on the digesters will open. At low-low pressure (about -50-mm H2O), vacuum-relief valves will
open. The biogas conveyance system will be designed to minimize pressure losses.
8.7.17 Dewatering
Sludge dewatering can be accomplished using a variety of mechanical devices and generally raises the solids
content of sludge to between 15 and 35 percent. The reduction in moisture content decreases the volume and
mass of the DS, making the sludge easier to handle and more cost-effective to haul, especially over a long
distances.
For Indicative Design, centrifuges are selected because the equipment is compact and enclosed, with low odour-
generating potential. Centrifuges are also capable of producing dewatered sludge with high solids content, which
reduces dewatered sludge storage requirements and lowers hauling costs. Metro Vancouver currently uses
centrifuges at the existing LGWWTP, as well as at other Metro Vancouver’s wastewater treatment facilities; thus, is
familiar with the O&M of centrifuges.
456928_WBG103013092847VBC 8-15
Indicative Design – Wastewater Treatment
Two centrifuges (one duty and one standby) are included in the Indicative Design to provide equipment
redundancy. Each centrifuge is sized to handle the maximum month sludge production rate, assuming 8 hours per
day of centrifuge operation. Polymer is added to the dewatering process to increase the solids capture rate. Typical
polymer dosage is 6 to 12 kg/t of sludge.
The centrifuges are designed to operate 8 hours per day, 5 days per week. Dewatered sludge hauling can be
scheduled 3 to 5 times a week, depending on the daily sludge production rate. A dedicated classifying conveyor is
mounted below the discharge chute of each centrifuge to divert poor-quality dewatered sludge (mostly in liquid
form) produced during the first 15 to 30 minutes of starting a centrifuge to the process drain. Once stable operation
is achieved after each centrifuge startup, the classifying conveyor will discharge dewatered sludge to a distribution
conveyor located above the sludge storage hoppers. Centrate from the dewatering centrifuges can either be
returned to the plant’s headworks or sent to the deammonification units for sidestream treatment.
The dewatering equipment is housed inside a four-storey dewatering building, where centrifuges are located on the
top level, classifying and distribution conveyors are on the third level, dewatered sludge storage hoppers are on the
second level, and a truck loading bay is on the ground level. This four-storey arrangement minimizes the footprint
required for the dewatering building and eliminates the need for dewatered sludge pumping.
Total nitrogen (TN) and total phosphorus (TP) concentrations in the dewatering centrate at the new LGSWWTP are
predicted to be in the order of 1,500 and 250 mg/L, respectively. These high concentrations of nitrogen and
phosphorus present both operational challenges and nutrient recovery opportunities. The following paragraphs
provide a description of (a) struvite recovery as a nutrient recovery opportunity, (b) struvite control measures that
can be employed to alleviate operational problems, and (c) a deammonification system as a nitrogen removal
option.
An analysis using a TBL approach was conducted to evaluate the feasibility of implementing a struvite recovery
process at the LGSWWTP. The business case for struvite recovery was not strong enough to justify the installation
of a struvite recovery system during initial build of the plant because the facility is mostly a carbonaceous plant.
However, space is reserved onsite for the implementation of struvite recovery should market conditions become
more favourable in the future.
8-16 456928_WBG103013092847VBC
Indicative Design – Wastewater Treatment
8.8 Structural
The section describes the functional requirements of the main structural elements included in the LGSWWTP
Indicative Design, including discussion about the following topics:
• Design criteria
• Post-disaster considerations
• Coatings and liners for concrete structures
• Description of buildings and structures
Foundation structures systems will comprise a common raft slab support from driven steel pipe piles, with an
assumed minimum thickness of the concrete raft slab of 900 mm, and some areas with a thickness of 3,000 mm.
Assumed piles are 610 to 760-mm-diameter steel piles driven to a depth of 25 to 30 m and with an allowable
capacity of 1,600 to 2,200 kilonewtons (kN). The buildings and structures will be designed for a minimum service
life of 100 years.
Structural elements will be designed to carry all superimposed loads, including dead loads, live loads, snow and
rain, wind, seismic loads, earth pressure, flooding, fluid loads, thermal loads, crane and monorail loads, and
operational loads. In addition, where the effects of differential settlement, creep, shrinkage, or temperature change
are significant, these loadings will be included in the design.
456928_WBG103013092847VBC 8-17
Indicative Design – Wastewater Treatment
8.8.3.4 Bioreactors
The bioreactors are deep concrete tanks with a water depth of 10 m bearing on the concrete raft slab. The roof of
the tanks will provide lateral support at the top of the wall. Concrete struts with internal baffle walls will provide
lateral support to help resist the loading caused by the 10-m water depth. The roof of the structure will be designed
for future public use. Future use of the roof may include a greenhouse or public plaza deck. Concrete exposure
classifications will be A-1. Concrete tank exterior walls, channel walls, and elevated channel floors will contain a
self-healing PRAH, as indicated by ACI 212.3R-10.
8-18 456928_WBG103013092847VBC
Indicative Design – Wastewater Treatment
The digester foundation will be a concrete base mat supported by driven piles. The base mat will be concrete,
approximately 3-m thick, to transfer the load from the centre ring into the piles. Assumed piles are 610 to 760-mm-
diameter steel piles driven to a depth of 25 to 30 m and with an allowable capacity of 1,600 to 2,200 kN.
The use of large cantilevers in the design of the building will require steel-framed structures, including multi-storey
trusses. The steel construction is chosen to reduce the weight of the cantilever.
• Design criteria
• Ventilation requirements
• Heating loads and plant heat supply system
• Air conditioning systems
• Natural gas utility service
• Fuel delivery and storage systems
• Plumbing
• Fire protection
• Heat recovery
• Controls
456928_WBG103013092847VBC 8-19
Indicative Design – Wastewater Treatment
The inside design conditions vary, depending on the type of building being served and whether it is air conditioned
in summer. As a general rule, the following design conditions will form the basis of design:
Process area heating loads will depend greatly on the ventilation rates required by the odour control system and
those dictated by NFPA 820. The peak process building heating load is approximately 4.5 MW. Process cooling
loads are estimated to be a maximum of 100 kW.
The peak heating loads for the digestion system are estimated to be 147 gigajoules per day (GJ/d) or
approximately 2 MW.
The Indicative Design includes two heating plants: (1) one heating/cooling plant dedicated for the Operations and
Maintenance Building, which will be located in the building, and (2) one heating plant dedicated for process
buildings, which will be located in the PGH Building.
The Operations and Maintenance Building will be heated using a total of two effluent-to-water heat pumps and one
natural-gas-fired condensing boiler.
The process area heating system will have one heating loop dedicated for process heating (100 percent hot water)
and one loop dedicated for space heating (30 percent ethylene glycol by volume).
The primary source of process heating will be one of two dual-fuel (digester gas/natural gas) CHP units, which will
use the majority of the digester gas produced by the digestion process.
8-20 456928_WBG103013092847VBC
Indicative Design – Wastewater Treatment
localized cooling will be provided. Individual cooling units will be located in the space with remote direct-expansion
condensers located in the galleries.
There will be two cooling plants: one cooling/heating plant dedicated to the Operations and Maintenance Building,
which will be located in the building, and one cooling plant dedicated to process areas located in the PGH Building.
The total Operations and Maintenance Building cooling load is estimated to be 300 kW. The Operations and
Maintenance Building will be cooled using a total of two effluent-to-water heat pumps. One standby effluent-to-
water heat pump will be installed to generate cooling in the case of failure of any of the duty effluent-to-water heat
pumps.
The total process building cooling load is estimated to be 100 kW. The process building will be cooled using a heat
pump system.
Based on preliminary estimated heating requirements, the gas service size will be based on a connected load of
approximately 7.81 MW.
8.9.7 Plumbing
Plumbing fixtures will be of commercial quality throughout the LGSWWTP. The primary source of domestic hot
water in the Operations and Maintenance Building will be a domestic hot water tank. Domestic hot water will be
preheated using heat from a heated water buffer tank or reheated using a natural-gas-fired condensing boiler. Hot
water in process areas will be provided by gas-fired water heaters, where practical, or localized electric heaters in
remote areas.
Effluent water will be used to supply toilets and urinals installed in the Operations and Maintenance Building.
Dual-flush toilets and waterless or low-flow (0.6 L/flush) urinals will be used throughout the plant where practical.
Emergency showers and eyewashes will be provided, where required. Tempered water will be provided to the
emergency fixtures by a thermostatic mixing valve.
Hot and cold hose bibs will be located in the process areas where required. The sanitary system will be set up to
take drainage back to the IPS.
456928_WBG103013092847VBC 8-21
Indicative Design – Wastewater Treatment
8.9.10 Controls
The computerized data acquisition and control (CDAC) system will monitor, control, and alarm HVAC, plumbing,
and fire protection systems. During the next stage of design development a business case will be prepared to
assess direct digital control versus CDAC control of the HVAC system at LGSWWTP.
8.10 Electrical
The section describes the functional requirements of the electrical power system included in the LGSWWTP
Indicative Design. This section includes discussion on the following topics:
• Preliminary load prediction
• Electrical supply
• Power distribution
• Standby power
• Onsite cogeneration
• Arc-flash hazards
• Grounding and lightning protection
• Lighting
A second feeder is included for the Energy Centre in the Operations and Maintenance Building.
The primary feed will enter the site underground from 1st St. along the access roadway under the primary clarifiers
to the transformers on the roof of the PGH Building. A power reliability assessment was undertaken to evaluate a
number of secondary feeder configuration options. For the purposes of the Indicative Design, the following is
assumed for electrical supply and onsite power generation:
8-22 456928_WBG103013092847VBC
Indicative Design – Wastewater Treatment
A dedicated 4,160-V feed will be provided for the Energy Centre to serve the heat pumps and associated equipment.
Two standby diesel generators are included in the Indicative Design, each sized at 1.6 MW.
• Limiting the transformation capacity on all distribution stations to a maximum of 2 MVA, as required by
Metro Vancouver electrical, instrumentation, and control (EIC) standards
Specific arc-flash hazard control measures for special cases, such as 4,160-V loads, will be defined during
subsequent stages of design development.
Lightning protection systems will be designed according to CAN/CSA B72-M87: Installation Code for Lightning
Protection Systems.
8.10.8 Lighting
Lighting will be designed in accordance with latest Metro Vancouver EIC standards.
456928_WBG103013092847VBC 8-23
Indicative Design – Wastewater Treatment
The system and, therefore, the five subsystems, provide a common and consistent technology (hardware, software,
and configuration) and integration approach, which facilitates effective O&M, replacement, expansion, and risk
management. The LGSWWTP CDAC system must adhere to this philosophy and the WWTP Principles of
Automation. The system must provide full integration so that any console at any site can control any or all the five
WWTPs. In addition, engineering configuration must be performed from any site to all five WWTPs.
The Bailey Infi-90 DCS interfaces with various PLCs, mainly Allen Bradley. Other interfaces include DeviceNet,
data highway plus (DH+), Modbus, Modbus TCP, Gateways, and other vendor packages and third-party controllers
and devices (as approved by Metro Vancouver on a case-by-case basis).
Metro Vancouver’s CDAC system migration plan was not available at time of writing this PDR; however, the new
CDAC system for LGSWWTP must communicate with the centralized system at Annacis Island WWTP, and the
system designs/configurations will conform to the migration plan, including system architecture, process control
philosophy, device communication technologies, and other applicable standards. Logic configuration for process
units requires Metro Vancouver’s input to conform to Wastewater Treatment Division CDAC-wide standards and
control philosophies.
8-24 456928_WBG103013092847VBC
Indicative Design – Architectural
The LGSWWTP, however, requires a civic architectural approach that provides an effective community integration
response to the diverse project context (see Figures 9-1, 9-2, and 9-3). The design of the new treatment plant
draws upon the adjacent context in scale, form, and siting, simultaneously serving the role of necessary civic
infrastructure and a symbol of Metro Vancouver’s commitment to clean water. Through site configuration, massing,
and open space integration, the architecture and overall form of the treatment facility was designed to communicate
the durability, technological advances, and presence of this important public service.
The LGSWWTP was laid out with the intention of illustrating the flow through the treatment process. The larger,
intensive treatment processes are located at the western end of the site. The more refined processes and the O&M
functions are located at the eastern end of the site, with a more modest scale being developed to address the low
height and pedestrian scale of Pemberton Avenue.
While active treatment processes are located within secure areas, the exterior walls of the plant are integrated to
the north and east within the public context. Public space, water, plants, and landforms as described in Section 9.4
were designed to create a unique place and identify for the facility.
456928_WBG103013092847VBC 9-1
Indicative Design – Architectural
9-2 456928_WBG103013092847VBC
Indicative Design – Architectural
The project site is located in an industrial context with few distinguishing features. The site is bordered on the
southern edge by the CN railway, the western edge by Philip Avenue (future Philip Avenue Overpass), along 1st St.
by a light industrial district, and on the eastern edge by Pemberton Avenue. The southern and western boundaries
will be inaccessible to both vehicles and pedestrians when the plant becomes operational. Pemberton Avenue
currently provides a connection to the Port of Metro Vancouver south of the site. Once the Philip Avenue Overpass
is built, the DNV intends to close this connection to vehicles, with the exception of emergency vehicles. Early in the
design process, it was identified that use of the DNV ROW at the foot of Pemberton Avenue, if used for community
purposes (directly east of the project site), represented the best opportunity to connect the site with the surrounding
neighbourhood. The establishment of this connection was a major driver in the overall organization of the facility
(see Figure 9-4).
456928_WBG103013092847VBC 9-3
Indicative Design – Architectural
The facility has a distinct organization in both plan and elevation. The elevation of the plant takes the form of a
low-slung building along 1st St., with more intensive plant uses located at the western end of the site. As the
wastewater moves west to east, the treatment program becomes more passive, transitioning from the headworks
and primary clarifiers through to the secondary clarifiers. The plant is anchored on the eastern boundary by the
Operations and Maintenance Building, with public amenities on the ground floor. Publicly accessible space and
secure space within the plant are clearly separated, and this strategy is clearly expressed on the building’s exterior
(see Figure 9-5). The northern wall of the plant serves as the primary dividing line between secure plant spaces
and freely accessible spaces at ground level to the north and east of the facility.
Figure 9-5. Site Organization, Northern Elevation Looking South from 1st St.
9-4 456928_WBG103013092847VBC
Indicative Design – Architectural
The site layout is designed to provide as much public space along 1st St. and at the foot of Pemberton Avenue as
possible, given the large footprint of the treatment technology (see the following figures). Along 1st St., this provides
a setback that ranges from 15 to 25 m. The design uses this setback to slope up against the long concrete wall of
the bioreactors and secondary clarifiers to break down the scale of the facility along 1st St. This will be further
enhanced by plantings that recall the historical ecosystems that once occupied this site.
456928_WBG103013092847VBC 9-5
Indicative Design – Architectural
Figure 9-7. Public Space Serves as a Transition between Plant and Community
9-6 456928_WBG103013092847VBC
Indicative Design – Architectural
9.3.1 Buildings
The tallest built structures will be the digesters at the western end of the site. Next to the digesters is the
Dewatering Building, Solids Facility, and primary clarifiers. These are the largest components within the
LGSWWTP, and they are concentrated in a small portion of the site, with the greatest depth north to south (see
Figure 9-8). The remainder of the facility east of the primary clarifiers is consistent in form and appearance,
terminating in the Operations and Maintenance Building, which brings some articulation and presents a public face
to the community.
9.3.3 Parking
Parking is provided for plant staff, visitors, and the general public. Twenty spaces of employee parking are provided
just inside the security checkpoint on the southern side of the plant, off the access roadway. Up to 10 visitor parking
spaces are provided on the eastern side of the vehicular circulation in the Pemberton Avenue ROW. These spaces
are separated by planting islands every three spaces in order to minimize the visual impact of the parking while
456928_WBG103013092847VBC 9-7
Indicative Design – Architectural
integrating the parking with the public space. The final configuration of this parking is still to be determined in
consultation with DNV and may change. It is anticipated that this area will be developed in two phases. Additional
public parking is currently available as parallel parking along 1st St. All parking is being designed to incorporate
Leadership in Energy and Environmental Design (LEED) standards for parking areas, including criteria for
carpooling, accessible parking, electric charging stations, and provision of bicycle parking.
A bus drop-off is located on 1st St. adjacent to the front entry of the Operations and Maintenance Building.
9-8 456928_WBG103013092847VBC
Indicative Design – Architectural
Zone 1: Planting along 1st St. between facility and the street.
The planting in Zone 1 is located within a landscape setback
between the northern side of the plant and 1st St. The proposed
planting recalls a temperate rainforest (see Figure 9-11) and is
composed of plants indigenous to the North Shore (CWHdm
biogeoclimatic zone). The planting is proposed as a simple
composition of large masses of understory plants and
coniferous trees to create a sculptural quality to the landscape,
contrasting with the linear massing of the concrete walls of the
plant.
456928_WBG103013092847VBC 9-9
Indicative Design – Architectural
9-10 456928_WBG103013092847VBC
Indicative Design – Architectural
9.3.7 Lighting
Onsite roadways, walkways, and the parking area will be lit at night to provide safe vehicle and pedestrian
movement (see Figure 9-16). Lighting will be used to highlight the Operations and Maintenance Building and
dramatic industrial features. The water features will also be highlighted through illumination. Site lighting is to be in
the colour temperature range of 3,000 to 5,000 Kelvin (K) and be composed of highly efficient lighting fixtures.
Lighting will follow LEED requirements for dark sky compliance and be designed prevent light spill into
neighbouring sites.
456928_WBG103013092847VBC 9-11
Indicative Design – Architectural
9.3.8 Fencing
The perimeter of the plant must remain secure; however,
the adjacency of community, circulation, and public
context mandates a refined approach to perimeter
treatment. Massing and configuration makes the plant
secure and inaccessible to the public along the northern
property line, and offers accessibility at the public entry
and open space at Pemberton Avenue. Southern,
western, and northwestern perimeters are treated with a
minimum 2-m-high enclosure, measured above adjacent
grade or retaining walls to limit climbing or intrusion into
the facility. This important architectural feature is faced
with formed aluminum ‘reeds’ that provide a
characteristic element to the plant while simultaneously
interrupting the flat surface of retaining walls that might Figure 9-17. Aluminum Reed Installation
attract unwanted graffiti (see Figure 9-17). Security
gates are provided at the roadway entry and exit points.
9-12 456928_WBG103013092847VBC
Indicative Design – Architectural
Figure 9-19. Typical Section through the Landform along 1st St.
In contrast to the public space at the foot of Pemberton Avenue, there is less opportunity for people to engage with
this space. Its primary function is to provide a friendlier edge for the community by reducing the apparent height of
the building. Additionally, the width of the setback provides an opportunity to restore habitat for indigenous birds
and small mammals, while enhancing the character of 1st St. This public space is connected to the foot of
Pemberton Avenue via a water feature that originates at the junction of the building walls in the middle of the site,
and cascades down terraced pond cells to an open water pond north of the Operations and Maintenance Building.
The program for this space will be primarily passive in nature. It is anticipated that this space will offer a place for
neighbouring industrial workers to have a refuge for lunch, and a mustering place for school groups and plant tours,
as well as incorporate some interpretive opportunities in relation to the water feature treatment system. An
integrated, educational public art strategy or installation will occupy this space.
This open space is contained primarily within the DNV ROW. Once the construction of the Philip Avenue Overpass
is completed, the Pemberton Avenue crossing will be closed to vehicle traffic apart from emergency vehicle access.
As a result, the roadway can be reduced considerably from its current width. Additionally, the DNV is considering a
pedestrian overpass at the foot of Pemberton Avenue. This pedestrian overpass is outside of the scope of the
LGSWWTP.
456928_WBG103013092847VBC 9-13
Indicative Design – Architectural
The major considerations for the design of this public space are described in the following subsections.
9-14 456928_WBG103013092847VBC
Indicative Design – Architectural
Setting the mass of the treatment plant south from the 1st St. property line reduced the overall mass of the facility.
The resulting elongated planting and landform along the northern wall of the LGSWWTP creates a layered
foreground, with digesters and the building mass of the Solids Building beyond. Windows enclose the eastern and
western ends of the Dewatering Building, allowing views into the structure atypical of wastewater treatment
facilities.
Translucent cladding covers the UV and grit screening functions along the southern wall of the plant. Emitting a
glow at night from lighting within, the southern elevation of the plant is an architectural gesture toward the southern
side of the CN rail tracks. Stair towers punctuate the southern side of the secondary clarifier, breaking down the
mass of the long concrete wall.
An articulated, vertical, metal slat fence surrounds the southern and western property lines. Providing security first,
the minimum 2-m-high slats provide a dynamic and humanizing texture along the rail line, while also interrupting a
long, smooth surface that would attract graffiti. Digesters are clad with a similar, vertical metal slat cladding. A
splayed top creates a tall element that is visible from downtown Vancouver, transforming the tallest building on the
site into a public art asset.
The LGSWWTP was developed as a complete composition, with scale, function, form, and texture investigated to
design a plant that is an integration of engineering, architecture, landscape, and community context.
456928_WBG103013092847VBC 9-15
Indicative Design – Architectural
9-16 456928_WBG103013092847VBC
Indicative Design – Architectural
9.7.1 General
Given the constraints of a small site, the facility is configured with intensive operations at the western end of the site
and less-intensive operations at the eastern end of the site. The Operations and Maintenance Building is located at
the eastern end of the property in order to optimize the space available for plant processes and to support the
project vision of using the DNV land at Pemberton Avenue. Taller, active processes, such as grit removal, solids
handling, dewatering, and truck loading, are located at the western end of the site, adjacent to the land mass of the
proposed Philip Avenue Overpass. Diminishing the perceived height of digesters and solids handling, the Philip
Avenue Overpass serves as a screen and common scale element in the industrial and commercial context. The
middle section of the site is occupied at grade by the secondary treatment processes with a translucent, enclosed
circulation level extending the length of the plant.
9.7.6 Circulation
Internal circulation and egress of O&M functions is provided by two stairs, one person elevator, and one freight
elevator. From the plant lobby on Level 1, staff proceed to Levels 2, 3, or 4. Egress from each floor proceeds to
456928_WBG103013092847VBC 9-17
Indicative Design – Architectural
grade via a fire-rated path. The northern elevator provides access to the roof by the public from Level 1, with no
access to Levels 2 and 3. The egress stair associated with this vertical core is redundant. However, it provides a
separate access for the public through the secure levels of the building, eliminating any opportunity for inadvertent
contamination or security breach.
9-18 456928_WBG103013092847VBC
Indicative Design – Architectural
456928_WBG103013092847VBC 9-19
Indicative Design – Architectural
Energy Centre, and a multipurpose room for meetings, exhibitions, and other uses are provided. The multipurpose
room faces east, with views of the exterior space and demonstration water feature developed on the DNV’s ROW
at the foot of Pemberton Avenue.
The multipurpose room was designed to accommodate a variety of functions, including short-term exhibitions,
public outreach activities, educational activities, special events, and public meetings. Moveable chairs, tables,
ample storage space for other equipment and educational materials, and integrated wiring for AV equipment will be
provided. Details can be found in the room data sheets included in Appendix 9G.
The IDT reviewed and considered all potential sustainable strategies simultaneously to identify connections
amongst them, and to arrive at comprehensive sustainability strategies that could achieve multiple project goals.
Finally, the IDT screened strategies according to whether they could be applied immediately into the Indicative
Design process, should be recommended for incorporation into later phases of the project, or were not feasible for
inclusion at all. The resultant information has helped to produce an Indicative Design that holds the potential to
become a project that is a potent symbol for regenerative design and local community spirit.
Air Quality
Outdoor public spaces will be surrounded by native vegetation and trees to help buffer and filter surrounding air
contaminants. To mitigate potential odours originating from the plant, a robust two-stage odour control system will
be used to treat foul air prior to dispersion.
Liquid Waste
A reclaimed water feature will serve as a feature educational piece that will tie into a bigger narrative that also
includes how treated water is being used for site infiltration and irrigation. To capitalize on IRR, the warmth of
incoming wastewater will contribute to heating the Operations and Maintenance Building. For the most effective,
ecological use of rainwater, it will be captured for internal reuse, irrigation of planting areas, and to supply the water
feature.
Solid Waste
A construction waste management plan should be created, outlining how waste will be diverted from landfills by
90 percent or more. Once the project is operational, reducing ongoing waste production should remain a priority.
Recycling strategies should be transparent and communicated effectively to all staff and visitors.
9-20 456928_WBG103013092847VBC
Indicative Design – Architectural
Ecological Health
The revitalized landscape will create potential habitat for target species; thereby, creating ecological connections to
adjacent green patches and corridors. Creating the opportunity for visitors to experience and learn about local
ecology also facilitates Metro Vancouver’s goal for community integration with the project.
Water
Treated wastewater will replace potable water for in plant non-potable use and other non-potable uses (such as
toilet flushing). Part of the education curriculum will support dialogues on the subject of water.
Food Systems
The incorporation of food systems into the project will likely focus on educational opportunities related to habitat,
water conservation, and nutrient and energy recovery.
The project is being designed with the goal of reinvigorating the area, and will be indirectly encouraging recreational
walkers and cyclists by creating a friendlier environment for all. The generous landscape will create a point of
interest along the Spirit Trail, and will facilitate linkages with existing parks. Educational curriculum will include the
role the project plays in the ecology of the site, the North Shore, and the larger region.
Regional Growth
Using the Energy Centre, the project will provide green energy to service new community developments. The
project will serve as a catalyst for positive change, encouraging business growth and an enthusiasm for the
diversity of the neighbourhood.
Housing
One of the project’s contributions to Metro Vancouver’s sustainable housing strategy is in its provision of various
types of accessible amenities for surrounding residential populations, including the outdoor plaza, educational
programs, and flexible interior community gathering spaces. The unique urban location of the facility, close to a
diverse and engaged population, will allow it to be an integral part of a growing residential community.
9.10.2 Conclusion
By achieving its four project goals, the LGSWWTP is also supporting the larger Metro Vancouver Sustainability
Framework, and contributing to the nine strategic priorities outlined in the Metro Vancouver Sustainability
Roadmap. While all of the nine sustainability priorities will not necessarily be represented equally in this project, it
was important for the project definition phase to consider each one so that the project achieves the highest level of
sustainability possible. The priorities of Liquid Waste, Solid Waste, Ecological Health, and Water are closely allied
with the programmatic requirements of this project and with the capacity of the site.
The site has historically been, and will continue to be, a witness to various exchanges, such as those between
natural and industrial processes, and those between community members and other ecosystems.
456928_WBG103013092847VBC 9-21
Indicative Design – Architectural
During the periods of less precipitation, the system will use the reclaimed water produced for use in plant
operations. This effluent is discharged via sheet flow over the green roof flowing from southern side wall and
collected along the northern edge of the roof. The approximate area of the green roof is 5,500 m 2.
This water is then collected and fed to the upper containment cell of the water feature in the middle of the public
space along 1st St. This water is supplemented with recirculated water from the pond to increase the flow of water
through the water feature. The water cascades down a series of containment cells planted with submerged plants
to remove nutrients from the treated water. At the bottom of the cascade, the water is directed into a channel that
leads to the pond surrounding the Operations and Maintenance Building as identified in Figure 9-24.
The pond is an important part of the site water system. It serves an important aesthetic role as foreground for the
Operations and Maintenance Building. It also serves an important functional role for the stormwater system. The
soils in the vicinity are very porous, and to hold water in the pond, a liner or impervious layer will need to be
constructed. The elevation of the pond is designed to fluctuate depending on the season. This will be controlled by
having two adjustable overflow elevations. Prior to the wet season, the elevation of the water will be lowered so that
the pond will be able to function as a stormwater detention basin. The ‘soft’ margins of the water feature will be
planted with emergent plants. This planted zone of the water feature will not be lined to allow for infiltration along
the pond edges. Along the southern side of the water feature, a concrete wall is proposed with an integrated water
feature. This provides an important edge to the public space and screens the vehicular traffic circulation along the
southern side of the property. The source for this feature will be recirculated water from the pond. Figure 9-25
provides more details.
9-22 456928_WBG103013092847VBC
Indicative Design – Architectural
456928_WBG103013092847VBC 9-23
Indicative Design – Architectural
Zone 1
With the majority of intensive treatment plant activities located at the western end of the site, there is a risk of
potential spills in this area, and these will need to be contained. Thus, stormwater runoff from this part of the site
will be collected in a containment area in the southwestern corner of the property, and then conveyed to an
infiltration gallery below the landform along 1st St. In the event of a chemical spill or treatment plant leak, diversion
valves will be activated to collect runoff and direct it through the wastewater treatment process.
Zone 2
Water collected at grade along the southern property line will be collected into catch basins, passed through oil/grit
separators, and conveyed by gravity or pumped (depending on final grades) to the infiltration gallery along 1st St.
Zone 3
The rooftop of the facility is the largest collection zone on the project site. During the winter months, rainwater can
be collected for plant functions and used as a source for the water feature. During the summer months and dry
periods, the green roof will be used to filter nutrients from plant effluent before feeding the water into the water
feature.
Zone 4
The public zone along the northern and eastern ends of the property is primarily a vegetated zone with a water
feature as its main focus. An infiltration gallery will occupy the area under the landform along 1st St. This site was
selected as it appears to have little or no soil contamination. This area will receive and infiltrate the runoff from
9-24 456928_WBG103013092847VBC
Indicative Design – Architectural
Zones 1 and 2. Water elevations in the water feature will fluctuate seasonally to allow it to receive and store
stormwater. The edges away from the building will be naturalized and planted with emergent vegetation to provide
some ecological values.
Figure 9-27. Concrete Finish Examples: Clyfford Still Museum, Denver Allied Works Architecture
456928_WBG103013092847VBC 9-25
Indicative Design – Architectural
9.13.1 Introduction
The public art framework for the LGSWWTP project is focused on identifying opportunities for public art within the
context of an operating wastewater treatment facility. Approached as a strategic development similar to a master
plan, an art strategy that explores the themes of water use at the local, regional, and global scales and the sensual
and cultural aspects of water is proposed. Possible locations for public art, as well as an example of what might be
produced, are included in this section.
A number of possible opportunities for public art are identified in Figure 9-28, which include the following:
9-26 456928_WBG103013092847VBC
Indicative Design – Architectural
Many of the statistics will reference water and energy use, not just for the treatment plant, but extended to statistical
facts relating to the Greater Vancouver region, and even further to the entire world. The gamut of statistics will be
further supplemented by a number of factoids, such as world population or global desertification rates and more,
such that the viewer is presented with a wall of constantly changing visual numbers that represent measurements
of scientific inquiry and social life in general.
The wall will be canted forwards slightly to permit greater proximity of the higher and farther-located factoids so that
they are more legible and to enhance the viewer’s immersive experience within the work.
An overhanging roof structure for rain protection and glare control that would shelter the viewer from weather will
also be included. This overhang permits greater legibility during days of sunshine, as well as rain and snow. The
overhang would channel water runoff, such that the viewer enters a kind of ‘al fresco tunnel,’ flanked by the
mirrored wall on one side and a curtain of water (waterfall) on the other, creating an intense sensual experience
grounded in Ken’s earlier works.
“This proposal pays homage to utopian science fiction films in which scientists are immersed in an
environment of flickering coloured lights. Movies such as 2001: A Space Odyssey used such
environments to convey technological complexity but advancement. My proposal would ground
such ideas in terms of the viewer’s relationship to the world. Moreover, the viewer’s understanding
of self is conditioned upon a reflection, both literal and speculative, of his or herself a subject in a
changing ecological, technological and social environment.”
456928_WBG103013092847VBC 9-27
Indicative Design – Architectural
• Direct pedestrian (stair) access should be considered from the corner of Pemberton Avenue and 1st St.
• Structural design and roof loading should consider assembly occupancies and industrial loading for
greenhouses.
• Fire separations between the plant and rooftop spaces should contemplate assembly and industrial
occupancies.
• Water and power points should be located at frequent (approximately 25-m) intervals.
• Metro Vancouver’s Operational Plan should consider the potential of the rooftop being occupied by an external
subcontractor, and Health and Safety procedures should be designed accordingly.
9.14.3 Recommendations
In conclusion, the use of rooftop space presents a substantial opportunity for the development of a public amenity,
be it for public use (such as a skate park or tennis court), or for public benefit (such as a commercial greenhouse or
solar panel farm). In order to realize the full potential of this opportunity, the IDT recommends the following:
• The funding sources and generic operational model for this amenity should be clarified prior to the next phase
of procurement.
• The infrastructure, code, and access requirements should be clarified further prior to procurement of the plant
so that a comprehensive list of requirements is provided in any Request for Proposal (RFP) document.
9-28 456928_WBG103013092847VBC
Indicative Design – Architectural
• A procurement method (either stand-alone RFP or a part of the whole project) for this amenity should be
clarified prior to the next phase of procurement.
The occupancy of any rooftop amenity should be postponed until following plant commissioning.
Using the process building distinctions identified by the IDT, project characteristics are summarized in Table 9-1.
Major
Occupied Area No. of Occupancy Sprinklers Construction Code
No. Building Name (m2) Storeys Classification Requireda. Type Reference
Notes: a. Sprinkler requirement is based on prescriptive requirement of BCBC 2012, Sections 3.2.2.20 to 3.2.2.88.
It should be noted that sprinklers located in unconditioned spaces are required to be of the ‘dry’ type, which are not
subject to freezing.
456928_WBG103013092847VBC 9-29
Indicative Design – Architectural
9.15.4.1 Access
Direct access is required:
3. From the floor below to all roofs with a slope less than 1 in 4 by either a stairway or a hatch and ladder
• Use of wired or laminated glass and sprinklered water curtains to provide equivalent spatial separation in
selected areas of the project to maintain visibility between functional areas.
• Possible modification of requirements for automatic sprinkler systems based on the specific project
characteristics and engineering judgement, due to the project function.
• Selective use of increased travel distances in technical spaces not generally accessed by the public.
• Reduction of exit capacity for the exterior publically accessible roof based on timed exit analysis and the
protection of exits to verify the correct sizing of exits based on actual use.
• Use of safe exterior exit routes on Metro Vancouver property to a public ROW to provide safe exiting from all
sides of the project.
9-30 456928_WBG103013092847VBC
Indicative Design – Architectural
1. Include a Building Code Consultant on the IDT in an integrated way during the design and project
documentation phases, including leading preparation of a more detailed building code assessment.
2. Conduct a review of the foundational building code assumptions (including applicable code) with the authorities
having jurisdiction.
3. Conduct a review of the project with the Fire Department to confirm firefighting requirements.
4. Use the services of an independent Code Consultant (certified professional) to provide inspection services
during the construction period that would typically be offered by the municipality given the complicated and
unusual nature of the design.
456928_WBG103013092847VBC 9-31
Indicative Design – Odour Control
• Surrounding neighbours
• Odour sources and odorous air loads
• Odour control technology selection and recommendation
• Odour control process description
The following supporting document is included in the Appendixes volume: Appendix 10 – Odour Control Technical
Brief.
Figure 10-1. Aerial Rendering Location Concept for the LGSWWTP and Vicinity
The new plant location is farther from the Lions Gate Bridge and related elevated commuter traffic than the existing
plant, but very close to businesses, neighbours, and adjacent thoroughfares. 1st St., Philip Avenue,
McKeen Avenue, and Pemberton Avenue bound the new plant property just outside the future fence line. Because
of this proximity, odour control is a key priority and a challenge. As such, options in this evaluation assume all
odour sources will be contained, treated, and dispersed in a controlled manner.
456928_WBG103013092847VBC 10-1
Indicative Design – Odour Control
Given the odour sensitivity of the areas surrounding the LGSWWTP, low-level covers will be employed throughout
the facility to contain foul air. This approach minimizes the foul-air flow requiring high levels of treatment, and in
many instances, provides two levels of protection: the contained space is exhausted to the odour control system, as
well as the general space above.
1. High priority – More-intense sources with the greatest potential for negatively impacting neighbours; in general,
these odour sources include process tankage or processing equipment
The basis of this evaluation is to capture and treat all priorities of odour sources: high, medium, and low. Higher-
priority sources will receive more aggressive odour treatment than medium-priority sources, but all sources will be
captured and treated to remove odours before being released through a stack discharge. Odour ventilation rates
are based on the following basic guidance:
• Vent occupied spaces at 6 to 12 ACH, except the biosolids truck loading bay, which is based on a more
aggressive 20 ACH
• Provide a capture velocity greater than 60 metres per minute (m/min) or enough to maintain a slight negative
pressure on the contained spaces, assuming that containment covers and doors are closed
• Outrun process air or air displacement due to tank filling by at least 10 percent
All odour sources will be captured and vented to odour control, whether they are process tanks, process
equipment, or general buildings housing process equipment. In most instances, the tanks and equipment will be
contained and vented at the source inside a secondary building. The building space will also be vented to odour
control in case the building space is mildly odorous.
Figure 10-2 illustrates the general concept of air reuse and provision of multiple-stage treatment for the high-priority
sources, with provision of single-stage treatment for medium- and low-priority sources.
10-2 456928_WBG103013092847VBC
Indicative Design – Odour Control
Sky
Multiple Fans
Moderate Source
403,800 m3/h
with partial reuse Minor Source
from Minor Sources Aeration Basin Building
reused air from
Fan Fan Secondary Clarifier Fan
Building
Minor Source Minor Source
112,100 m3/h to Building
Centrifuge Floor reuse Secondary Clarifier
+ 20,200 m3/h reuse air Building
air to Conveyor Floor
to aeration tanks
16,200 m3/h total 132,300 m3/h
132,300 m3/h total
Parameter Value
First-stage Treatment
456928_WBG103013092847VBC 10-3
Indicative Design – Odour Control
Parameter Value
Recirculation Pumps 1 duty and 1 standby per 5 biotowers, 5 hp rated at 7.57 L/s
(Optional, depending on the system. BioAir uses a recirculation pump for startup
only, and then the biotower becomes a once-through spray system without use of
long-term recycle pumps.)
Nutrient Supply and Water Cabinet To supply nutrients to biological process (requirement to be confirmed by
vendors). FRP or stainless cabinet rated for outdoor service if needed and with
necessary heat protection against freezing.
Second-stage Treatment
Carbon Design Criteria 0.035 m/s maximum superficial velocity through the carbon
Minimum carbon H2S capacity 0.15 g/cm3
Maximum pressure loss 0.075 m-wc/m of carbon bed
10-4 456928_WBG103013092847VBC
Conveyance
11. Conveyance
11.1 Section Description
The section outlines the options for conveying wastewater and treated effluent to and from the LGSWWTP,
evaluates these options, and provides recommendations to Metro Vancouver. The conveyance system upgrade
involves routing wastewater from the North Shore communities to the LGSWWTP site, and routing treated effluent
back to the existing LGWWTP outfall.
The following supporting document is included in the Appendixes volume: Appendix 11 – Conveyance Alternatives
Technical Brief.
1. 1,200-mm deep-gravity sewer from the HI: This option eliminates the need for pumping flows from the DWV
and is based on a deep gravity sewer from the termination of the HI at the existing prechlorination manhole.
The DNV trunk sewer and the Squamish Nation services can be tied into this sewer.
2. 1,200-mm shallow-gravity sewer from the HI: This option requires a lift station near the existing LGWWTP to lift
the HI flows to an elevation near the ground surface, from where the wastewater flows by gravity to the
LGSWWTP. The DNV trunk sewer and the Squamish Nation services can be tied into this sewer.
3. 1,050-mm forcemain from the HI: This option is based on a new pump station near the existing LGWWTP that
pumps wastewater to the new plant headworks via a forcemain. The DNV trunk sewer and the
Squamish Nation services would need to be collected and conveyed separately to either the pump station or
the plant.
The following two effluent conveyance options include a gravity forcemain from the LGSWWTP plant to the existing
LGWWTP outfall:
2. Cured-in-place pipeline at the 1,650-mm North Vancouver Interceptor (NVI), and add a parallel 1,050-mm main.
This option would require a temporary bypass of all effluent flows from the LGSWWTP to the outfall while the
NVI is lined.
The NVI is located within an existing, 4.6-m-wide ROW crossing Squamish Nation IR5. Depending on the pipe
depth and installation methodology for the wastewater and effluent conveyance options, the additional ROW and
working space requirements vary considerably for the different combinations of possible options. For all options
requiring a pump station to convey DWV wastewater to the LGSWWTP, the pump station would be located near
the existing LGWWTP.
456928_WBG103013092847VBC 11-1
Conveyance
11.3.1 Geotechnical
Till with cobbles and boulders will be challenging for deep excavations, and sheet piling may not be a feasible
approach. Alternatives such as a jet-grouted wall are more expensive. The dewatering of deep excavations below
the tide line will present challenges and premium construction costs.
11.4 Recommendation
Based on the IDT’s findings, the preferred conveyance alternatives are the 1,200-mm deep-gravity influent and
1,800-mm steel effluent (option Influent 1 + Effluent 1), and the HI pump station/1,050-mm slip-lined forcemain and
1,800-mm steel effluent (option Influent 3B + Effluent 1) options.
The first recommended option has the lowest estimated capital and life-cycle costs of all of the options, including
gravity and pump station and forcemain options. There are, however, geotechnical risks associated with the deep
excavation and property acquisition risks related to the large ROW requirement. It is, therefore, recommended that
additional geotechnical investigations be undertaken to assess the risk, and that the cost estimates be updated to
reflect the requirements of the Squamish Nation and the Province once negotiations are complete.
The second recommended option has the lowest estimated capital and life-cycle costs for the pump station and
forcemain options, and requires the least amount of additional ROW; thus, carrying a lower magnitude of property
acquisition risk. As the influent forcemain would be slip-lined into the NVI, and the effluent pipe is relatively shallow,
the geotechnical risks are reduced when compared to the other recommendation, as well.
11-2 456928_WBG103013092847VBC
Education and Partnerships
The following supporting documents are included in the Appendixes volume: Appendix 12 – Education and
Partnerships Technical Memorandum.
12.2.1 Introduction
In all stakeholder engagement activities, education has been identified as a priority for the project. This aligns with
goals identified in Metro Vancouver’s Sustainability Framework and Integrated Waste and Resource Management
Plan. Working together with Metro Vancouver, the IDT has identified a number opportunities for the LGSWWTP to
meet these goals or provide opportunities to achieve them. Through identification of educational audiences,
requirements, and strategies, a comprehensive approach to education and outreach is described in the following
subsections.
12.2.2 Audiences
Metro Vancouver typically considers two types of education: active, or programmed education (inside the fence),
and passive, or self-directed activities (outside the fence). Typically, active audiences will be those arriving with
pre-arranged visits, and include groups from school districts, community partners, and BC teacher associations.
Passive audiences will be spontaneous visitors, such as the public, local neighbours, North Shore residents, and
the general population from Metro Vancouver. In addition, Metro Vancouver staff will continue to pursue outreach
education on the topic of liquid waste.
Within this context, it is important to note that local audiences, including residents and the staff and students of
nearby schools such as Norgate Community Elementary School, Capilano Elementary School, Bodwell High
School, and the Lions Gate Christian Academy, have the potential to be not only audiences but also partners in
ongoing education initiatives.
456928_WBG103013092847VBC 12-1
Education and Partnerships
Public guided tours are also conducted on a by-request basis, and the facility provides opportunity to enhance this
program, as well.
In relation to this, an opportunity that has emerged during the Project Definition Phase is the potential to develop
more targeted and robust partnerships with local schools. Specifically, it was suggested during a community
meeting that an ongoing relationship with Norgate Community Elementary School could be developed, which would
result in the following benefits:
• Encouraging students to develop a deeper understanding of issues surrounding water use and conservation
• Improving the school’s science programming through experiential and real world connected learning activities,
such as water sampling and monitoring
• Working effectively with a number of local constituencies, all of whom participate in the life of the school
• Organization of the plant in a way that illustrates the flow through the treatment process
• A publically accessible roof deck for direct sight lines to the Burrard Inlet, effluent discharge, McKay Creek, and
onsite water features
• A public art strategy that illustrates water use locally, nationally, and internationally
• Interior and exterior mustering points at which to start and end plant tours
• A clearly marked internal tour route to explain the wastewater treatment process
12-2 456928_WBG103013092847VBC
Education and Partnerships
• A highly visible Energy Centre to demonstrate resource recovery from the effluent stream
• The use of educational materials to demonstrate plant performance for both indoor and outdoor spaces
• Maximize the visibility of functioning facility components through oversized glazed walls
• Use the services of an Education / Communications Consultant when laying out equipment to make the
systems visible and easily understandable by various audiences, and so that the plan meets identified
audience/program priorities
• Use the services of an Education / Communications Consultant to develop effective signage and branding to
maximize the understanding of the systems on display.
• Explain the role of any visible technologies in the larger system with display panels.
12.2.7 Requirements
Meetings with Metro Vancouver School Programs staff revealed a number of specific requirements that should be
incorporated into the next phases of design, as follows:
• Space within facility for safety orientation and safety equipment as required for tour groups
• Meeting room with flexible space for pre- and post-facility tour activities to support teaching, learning, and
inquiry into wastewater treatment, management, and related sustainability challenges; and equip with chairs,
whiteboards, AV equipment, classroom equipment, projector, and a laptop
• Facilities for onsite storage of personal protective equipment for tour groups
• Ample opportunities for experiential learning, which could include opportunities to use sample equipment (such
as hoses or valves) and full-sized mock-ups of equipment, or actual equipment (such as pipe sections to
establish scale)
456928_WBG103013092847VBC 12-3
Education and Partnerships
• Participate in all key project workshops during the next phases of design
• Engage North Shore educators in an ongoing dialogue to explore opportunities for partnerships and create
project champions, as part of an Education Advisory Committee involving key school education stakeholders
from North Shore municipalities, school districts, Metro Vancouver Education staff, school education partner
organizations, and individuals interested in contributing to the project’s educational strategies
• Identify and develop tour routes with specific thematic focus during the design phase (for example, IRR, water
treatment and conservation, and community issues) in partnership with design consultants, Metro Vancouver
educational staff, and local teachers
• Develop stopping points along tour routes with appropriate technical support (that is, lighting, acoustics, and
displays)
This exercise was intended to be preliminary in nature, and participants were chosen based on a diversity of needs
and sectors. As such, this study is not exhaustive. These interviews were informal and exploratory, and no
commitments were promised or discussed. The participants included environmental and educational organizations,
local government, and private companies with a focus on sustainability programs and services.
In general terms, all participants expressed interest at the potential of the project and indicated a general
willingness to be involved through further discussions. During the interviews, it also became apparent that the
typical planning time horizons for the project (that is, 2020 startup) exceeded the typical planning time horizons of
most of the participants.
Based on feedback from market sounding participants, the greatest opportunities for partnerships seem to occur
where a potential partner's involvement mutually reinforces shared values with Metro Vancouver, which could
include:
• An emphasis on environmental stewardship (as outlined in Metro Vancouver's Ecological Health Action Plan)
• GHG reduction
• Food security (as outlined in Metro Vancouver's Regional Food System Strategy)
• Educational partnerships and integration with Metro Vancouver's internal education and outreach initiatives that
affect positive behaviour change among the region's residents on issues such as water consumption, waste
management, and urban biodiversity
The space needs identified by participants varied considerably, from indoor classrooms to outdoor roof space.
Several participants emphasized that outdoor space, particularly natural outdoor space, is preferred to support
educational initiatives.
12-4 456928_WBG103013092847VBC
Education and Partnerships
Given the long-term nature of Metro Vancouver's planning horizon for this project, the design of community and
partner spaces will need to be reasonably flexible to accommodate a potential change of tenancy throughout the
life of the project. Some issues to consider during the next phases of the project include:
• For project resilience, Metro Vancouver should consider designing for a diversity of uses for their spaces.
• Individual space types should be adaptable to multiple uses because Metro Vancouver's project completion
(2020) exceeds typical planning horizons for businesses and the involvement of specific partners could change
as the project advances.
• Potential partners (beyond office uses) often have access requirements and loading criteria that can be defined
functionally, and will need to be provided for.
All participants in the market sounding had the expectation that they would be required to make a funding
commitment to the project for hard costs or operational costs as appropriate. Additionally, participants also
expressed the desire to commit time and personnel resources to further define the project with Metro Vancouver
should there be a real opportunity for inclusion in the final project.
Specific issues that were identified during market sounding interviews included:
• Early stage agreements or memoranda of understanding with Metro Vancouver are appealing to a number of
possible partners, as they see this as an exciting initiative, and they would be willing to contribute some time up
front to shaping the project potential. In other words, they would consider a relationship beyond the typical
landlord/tenant contract that might be expected from a typical market tenant.
• Social Enterprise and Not-for-Profit sector partners do see themselves as bringing value to the project, so might
have an expectation that this would be acknowledged through competitive market rates (that is, they may not
want to pay a premium to be included in this project).
• Several participants expressed a willingness to share space with a number of other uses.
• Several participants suggested that an additional advantage that the Not-for-Profit and Social Enterprise
sectors bring to the project is access to a broad network of partnerships with a diverse range of organizations
that pursue similar goals.
456928_WBG103013092847VBC 12-5
Performance Indicators
Energy Value
Notes: a. Refer to power and energy consumption values in Appendix 13A GJ/y – gigajoule per year
b. GJ/y is converted to kWh/y by multiplying by 278 kWh – kilowatt-hour
c. Power use by odour control equipment is assumed to be 750 kW kWh/y – kilowatt-hour per year
d. Net power produced by District Energy is assumed to be 3,333 kW
(5,000 kW total output with assumed coefficient of performance of 3)
Metro Vancouver is a founding partner of the National Water and Wastewater Benchmarking Initiative (NWWBI),
which was developed as a means for Canadian municipal water and wastewater utilities to measure, track, and
report on their utility performance. NWWBI now has an extensive database of operations data and metrics.
Figure 13-1 shows metrics extracted from the database for 18 secondary WWTPs that have an AAF of greater than
50 ML/d. The group average total energy use, not including any in-plant reuse of biogas, is 845 kilowatt-hours per
456928_WBG103013092847VBC 13-1
Performance Indicators
megalitre (kWh/ML) treated. The estimated 2021 AAF for LGSWWTP is 98 ML/d, so using the group average total
energy use benchmark of 845 kWh/ML treated, LGSWWTP is estimated to have a total energy use of
30,226,000 kWh/y (AECOM, 2013). This calculated value is close to the projected total energy use for LGSWWTP
of 29,000,000 kWh/y (Total A of Table 13-1). However, the Indicative Design includes a much higher level of odour
control than found at most Canadian WWTPs; therefore, the projected total energy use without odour control of
22,400,000 kWh/y (Total A – B in Table 13-1) is considered to be a more representative benchmark.
The cogeneration system is projected to produce 7,304,000 kWh/y of electricity and 6,950,000 kWh/y of usable
heat energy for a total energy production indicator of 14,000,000 kWh/y (Total C in Table 13-1).
The Indicative Design includes space for an Energy Centre in the Operations and Maintenance Building, based on
heat pump technology to recover low-grade heat in the treated effluent. If a 5-MW heat pump is installed, and the
unit performs at an average coefficient of performance of 3, two-thirds of the output energy, or a net of
approximately 3.3 MW of green energy, will be produced (5 MW output and 1.67 MW input). This is equivalent to
almost 29,200,000 kWh/y of green energy. If this net energy produced is included in the energy balance for
LGSWWTP, the facility would be a net positive energy generator, at a total amount of 14,200,000 kWh/y (Total A +
C + D in Table 13-1).
Figure 13-1. Energy Use Data Extracted from NWWBI Database (AECOM, 2013)
13-2 456928_WBG103013092847VBC
Performance Indicators
Notes: BEAM – The Biosolids Emissions Assessment Model (BEAM): A Method for Determining Greenhouse Gas Emissions from Canadian Biosolids
Management Practices
CO2e – carbon dioxide equivalent
dt/y – dry tonne per year
FeCl3 – ferric chloride
kg – kilogram
km/y – kilometre per year
wt – wet tonne
y – year
456928_WBG103013092847VBC 13-3
Performance Indicators
• Internal non-potable functions within the WWTP, such as seal-water, tank washdown, landscape irrigation,
make-up water for chemicals, toilet flushing, and interpretative water features
• Nearby industrial users for dust control, washdown, and vehicle washing
• Large water-consuming industries near the collection system, but not adjacent to the WWTP, through the
installation of a small satellite reclaimed water facility
The Indicative Design includes a reclaimed water system, which has been sized for internal non-potable uses with
provisions to expand the system in the future for other offsite uses. Also, provisions have been included for a truck
fill station near the UV Disinfection Building. The firm capacity is 11 ML/d, and provisions are included to expand
the system to a firm capacity of 22 ML/d.
The performance indicator for reclaimed water use for LGSWWTP is to provide a system sized for a firm capacity of
11 ML/d, with provisions to expand to 22 ML/d.
The performance indicator for onsite stormwater management for LGSWWTP is no net increase in the rate and
volume of stormwater runoff from existing to developed conditions up to the MAR (80 mm) (2-year return period),
based on the North Vancouver Municipal Hall weather station.
13.6.1 Introduction
To assist with the selection of an appropriate environmental rating system to help guide, assess, and reward the
LGSWWTP project’s sustainability agenda, the IDT reviewed numerous environmental rating systems with varying
scales and also various degrees of market acceptance. Ultimately, four systems were selected for a more detailed
review: LEED, Living Building Challenge, Sustainable Sites Initiative (SITES), and Envision. To gauge the
applicability of these four rating systems for the LGSWWTP, they were first assessed according to their ability to act
as a set of holistic key performance indicators (KPIs) for the design, construction, and occupancy phases of the
project. Following this assessment, each rating system was subjected to a detailed scorecard review to more fully
understand how the project might align with point achievement and certification award. These scorecards, and the
project assumptions made to complete them, are included in the Green Rating Systems TM, located in
Appendix 13B.
The LGSWWTP project’s schedule will result in the work being governed by the upcoming LEED V4: Building
Design and Construction (BD+C) (LEED V4), which will be released in Canada in 2014 or 2015. The main changes
in this upcoming version are in the shifting of focus from prescriptive ratings to performance-based solutions
13-4 456928_WBG103013092847VBC
Performance Indicators
through the use of more holistic evaluations for materials, and by placing more emphasis on water and energy
metering. This shift of emphasis towards rewarding long-term performance means that LEED is becoming more
aligned with the traditional role of a KPI, so with a judicious choice of targeted credits, will provide a solid set of
metrics by which to evaluate the Operations and Maintenance Building.
The preliminary LEED scorecard, attached in the Green Rating Systems TM in Appendix 13B, indicates that the
Operations and Maintenance Building could target Gold certification. The project’s progressive approach to water
management and energy-use reduction results in target point levels very close to Platinum. Additionally, it is likely
that as the project achieves greater design resolution, the IDT will also identify additional innovative measures that
could increase the score.
Although not applicable for the infrastructure portion of the LGSWWTP, achievement of LEED certification for the
Operations and Maintenance Building will provide Metro Vancouver with a readily understood marketing and
assessment tool. LEED is well-established and will be easily understood by the IDT, contractors, and the public. It
is a rating system that will provide more specific details for establishing exceptional indoor air quality, implementing
life-cycle analyses, and creating material specifications that reflect the most current standards in green technology.
LEED will also assess the project for its already established aggressive approach to reducing energy use and
potable water consumption. Pursuing LEED certification is a low-risk, high-reward strategy for increasing the
project’s green profile, integrating additional sustainable strategies, and accessing progressive information about
new environmental performance benchmarks.
The rating system has a range of achievement levels, with restorative design and construction practices ranking the
highest, and industry standard practices ranking the lowest. The preliminary scorecard completed for the
LGSWWTP indicates that the project could target a Gold certification level. Many Envision credits are similar in
scope to those of LEED V4 and SITES, with a focus on energy-use reduction, material responsibility, site selection,
and innovation. Because the rating system is still in its infancy, and because the system is performance based,
rather than prescription based, some point tallies will also not be determined until final life-cycle, energy, or water
audits are conducted. The system does offer a comprehensive set of KPIs to assess the project.
While each of the assessed rating systems has some level of applicability to the scale and scope of a large
infrastructure project, Envision is the most holistic tool for evaluating the entirety of the LGSWWTP project. The
credits available within the Envision rating system contain a fundamental alignment with Metro Vancouver’s project
objectives. Envision’s credit metrics align extremely well with Metro Vancouver’s Integrated Solid Waste and
Resource Management Plan, and will also tie into their Air Quality Management Plan and Regional Growth
Strategy. The Envision rating system could evaluate, grade, and give recognition to this project’s integrated
approach to design.
456928_WBG103013092847VBC 13-5
Performance Indicators
13.6.4 Conclusion
The IDT recommends that Metro Vancouver pursue LEED certification for the project’s Operations and
Maintenance Building and surrounding public outdoor spaces. Additionally, the IDT recommends that
Metro Vancouver continue to consider Envision as a comprehensive assessment tool for the next phases of the
project, and that ultimately, Metro Vancouver consider Envision certification.
Using an established environmental rating system as a set of KPIs will allow the IDT to gauge the LGSWWTP
project’s comparative ecological footprint, assess its technical performance, and determine its contribution to the
community. Environmental rating systems go far beyond what is typically provided with an infrastructure project’s
KPIs, by providing exhaustive accompanying written guidelines, educational tools, and technical support to project
teams at every phase of their project. These systems’ guidelines, credits, and accompanying point rankings are
created by leaders in their respective fields, and are typically vetted first through industry reviews and then by pilot
projects. The use of one or more of these environmental rating systems as a set of KPIs is recommended for the
LGSWWTP.
13.7.1 Introduction
The objective of this section is to present an overview of building performance strategies for the Operations and
Maintenance Building, and an associated list of sustainable KPIs for the LGSWWTP facility that align with
Metro Vancouver’s and the North Shore municipalities’ environmental goals.
The overriding principle guiding Metro Vancouver’s Integrated Solid Waste and Resource Management Plan is the
avoidance of waste through an aggressive waste-reduction campaign, and through the recovery of materials and
energy from the waste that remains. Furthermore, they have established that any new infrastructure projects must
be resilient, be adaptable to climate change, lessen the region’s dependence on nonrenewable energy sources,
and protect the environment.
To support these goals, the LGSWWTP IDT has incorporated a wide range of strategies, and is proposing many
more be incorporated into later phases of design. The LGSWWTP project captures valuable materials to be
repurposed for fuel, water, fertilizer, and heat, helping Metro Vancouver, and all its member municipalities, in
reducing energy costs, carbon footprints, potable water use, and environmental impact. The Indicative Design is
aggressively targeting dramatically reduced energy and potable water consumption, it is advancing concepts of life-
cycle thinking, and it is poised to become an example for restorative community design. The sustainable building
performance strategies identified in this section are divided into five distinct categories, each of which is introduced
with explanatory text that outlines proposed green design strategies.
As the project moves forward, the IDT recommends that this substantive list of KPIs be adopted, ideally through
registration with their related Green Building Rating System, to strengthen the project’s commitment to ecological
and social health.
13-6 456928_WBG103013092847VBC
Performance Indicators
The landscape at the eastern end of the project will provide a native, temperate rainforest habitat that will both help
to moderate heat gain on the building’s eastern facade and will introduce biodiversity to the site. This area will
serve as a place of refuge from the industrial neighbours, a welcoming entrance to the facility, and a hub for
community education and outreach efforts. A proposed green roof over the majority of the facility’s roof mitigates
the heat island effect and provides potential habitat area. These strategies, combined with efforts to minimize
paved-surface parking areas and reduce light pollution, will create an integrated landscape that supports a healthy
neighbourhood and will increase ecological values on the site.
The following are KPI categories for Sustainable Sites and Community Enhancement. A more detailed description
of each item can be found in the Building Performance TM in Appendix 13C.
The following are KPI categories for Water Conservation and Reuse. A more detailed description of each item can
be found in the Building Performance TM in Appendix 13C.
456928_WBG103013092847VBC 13-7
Performance Indicators
from radiant panels provided to meet desired room temperatures. To augment this efficient energy system, passive
design strategies will include the use of high-performance glass and the strategic use of architectural shading
devices on all facades. Despite these comprehensive systems, the IDT recognizes that user behaviour remains a
primary factor in energy performance. Commissioning and advanced monitoring feedback will help the energy
systems achieve and maintain a high level of performance over the life of the project.
The following are KPI categories for Climate and Energy. A more detailed description of each item can be found in
the Building Performance TM in Appendix 13C.
This project is designed to reduce the total consumption of construction and repair material required over the
project's full life cycle. Materials specified were carefully selected for their durability and contribution to reducing net
embodied energy over the project’s lifespan. Concrete was chosen for its durability, heating and cooling properties,
and local availability. Many other building materials will be required to have a publicly available, critically reviewed,
life-cycle assessment or an International Organization for Standardization (ISO)-conforming Environmental Product
Declaration so that their environmental, social, and economic impacts are aligned with Metro Vancouver’s
sustainability goals. Additionally, a growing concern with the chemical components of some products has resulted
in the specification of products that disclose their ingredients.
The following are KPI categories for Material Procurement and Building Life Cycle. A more detailed description of
each item can be found in the Building Performance TM in Appendix 13C.
13-8 456928_WBG103013092847VBC
Performance Indicators
The following are KPI categories for Indoor Quality of Life. A more detailed description of each item can be found in
the Building Performance TM in Appendix 13C.
13.7.3 Conclusion
The sustainable design strategies in place to achieve optimal performance, and the methodology for measuring the
success of those strategies, were strategically developed to provide a durable, low-maintenance, restorative facility
to Metro Vancouver and the residents of the North Shore. The IDT recommends using these sustainable KPIs to
provide accountability for the project’s sustainability agenda, and to assure adherence to this agenda for the lifetime
of the LGSWWTP. The KPIs should be formally adopted into the next phase of the project through certification with
a green rating system. This will help incorporate rigorous, thorough sustainable performance concepts into early
editions of specifications and drawings. A separate Green Rating Systems TM (Appendix 13B) provides detailed
reviews and recommendations for applicable rating systems.
456928_WBG103013092847VBC 13-9
Construction Sequencing and Site Development Phasing
• Contract packaging
• Site security and access
• Site offices, laydown areas, and warehousing
• Excavation spoils and dewatering
• Delivery of concrete and reinforcing steel
• Neighbours and nuisance issues
• Project schedule
An image showing an aerial photograph of the site and summarizing key construction considerations is provided in
Figure 14-1.
456928_WBG103013092847VBC 14-1
Construction Sequencing and Site Development Phasing
• Contract 1 – LGSWWTP
• Contract 2 – Conveyance Upgrades
• Contract 3 – Deconstruction of Existing LGWWTP
Consideration may be given to including an early works construction package to allow any required ground
improvements to be completed in advance of the main LGSWWTP construction contract (Contract 1). This
approach would allow construction of the main LGSWWTP contract to be accelerated, if desired by
Metro Vancouver. Also, the Conveyance Upgrades (Contract 2) may be split into additional contracts once the
scope of work and alignments are finalized.
The rationale for parceling the LGSWWTP into a single construction contract is due to onsite space constraints and
the fact that the vertical nature of the project does not lend itself to having multiple general contractors on the site at
the same time. The construction value of Contract 1, although significant, is within the capabilities of the
construction industry in Metro Vancouver, and a competitive pricing environment is expected. The preferred model
for delivering Contract 1 will be confirmed by Metro Vancouver in early 2014.
Equipment prepurchase contracts may be a consideration for Contract 1; however, that will be confirmed in early
2014, together with Metro Vancouver’s preferred delivery model.
The required Conveyance Upgrades (Contract 2) are essentially independent of construction activities on the
LGSWWTP site and the construction trades required are different than those required in the plant; hence, the
rationale for including this work as a separate construction package(s). This construction package(s) will be
delivered using the conventional design-bid-build (DBB) delivery model.
The deconstruction of the existing LGWWTP (Contract 3) will occur sometime after the new LGSWWTP is
commissioned and put into service. Also, the trades required for this work will be different than the trades required
for the plant work. The separation in time, area, and trade requirements provide the rationale for separating this
work into a separate contract. This construction package will be delivered using an RFP process.
The DNV intends to construct a new vehicle overpass at Philip Avenue over the railway lines to provide better
access from 1st St. to businesses in the Port of Metro Vancouver. DNV also plans to close Pemberton Avenue
immediately south of 1st St. (north of the railway lines) and provide access only for oversize vehicles unable to use
the overpass and emergency vehicles.
Presently, the LGSWWTP site is secured with fencing, which will need to be maintained or replaced, as required
during construction. Multiple access gates will need to be provided at the northern and eastern sides of the site to
suit construction staging. Access will not be available on the western side of the site at Philip Avenue, as the
overpass will be constructed and in service by the time LGSWWTP is under construction.
There will be conflicts with traffic on 1st St. and construction traffic entering the site, especially before and after shift
work at nearby businesses (including Fibreco Export Inc., Seaspan, and Kinder Morgan). An option to reduce
14-2 456928_WBG103013092847VBC
Construction Sequencing and Site Development Phasing
conflicts during peak traffic is to re-direct traffic along Welch Street temporarily during the peak traffic flow Monday
through Friday, and this should be reviewed in further detail with DNV.
As construction progresses, there will be limited space for trucks to place concrete at higher storeys of the
LGSWWTP and deliver equipment and supplies to the site; therefore, the possibility of closing one lane on 1st St.
should be reviewed with DNV. Also, construction will be required along 1st St. to upgrade the NVI and install
conveyance infrastructure from west of the site and a pipeline to the existing outfall near the Lions Gate Bridge. It
may be necessary to close 1st St. at times when the new conveyance infrastructure is under construction, while
providing temporary access to the business on the northern side of 1st St.
Areas required for offices, meetings, and lunchrooms will become an issue as construction progresses. An offsite
project office near the construction site could be rented for the duration of the construction period and could be
used by the contractor, consultant, and Metro Vancouver.
As construction progresses, it may be possible to move management staff from site trailers used in the initial
phases of construction to other finished or partially finished areas, such as space available below the primary
clarifiers or within the bioreactors and secondary clarifiers.
Parking requirements for staff will also become an issue as construction progresses and parking areas need to be
identified. Early in construction, there will be parking areas available onsite and along 1st St. and McKeen Avenue;
however, as construction progresses, additional parking will be required. If additional space cannot be located near
the site, it may be necessary to find additional space offsite and shuttle staff to and from the site.
There will be significant volumes of deliveries to the site beyond concrete, including reinforcing steel, piping, valves,
HVAC and electrical equipment, and a range of other supplies and equipment. Staging the delivery of this material
and equipment will become critical, and leasing an offsite warehouse or equipment laydown area should be
considered. Double-handling equipment may become unavoidable. Identifying office space and warehousing
options prior to tendering construction of LGSWWTP will reduce risk and should be considered by
Metro Vancouver.
There are a few deeper excavations for the influent sewer, influent pumping station, digesters, RSS pumping
station, and effluent line that will require careful sequencing. Identifying the correct sequence for these excavations
and the concrete forming, and placing the foundations is critical to the schedule. Also, trains running along the
railway lines south may impact both slope stability during the excavations and shoring requirements, so should be
evaluated during subsequent stages of design development.
The number of trucks and trailers required to remove 90,000 m3 of excavated materials is approximately
6,000 trips, or equivalent to 100 trips per day (one truck every 6 minutes) for 3 months early in the construction
456928_WBG103013092847VBC 14-3
Construction Sequencing and Site Development Phasing
schedule. Reviewing the feasibility of using rail or barging for relocation of the excavated materials may offer some
advantages, but the logistics of loading and unloading the cars/barges at the disposal site needs to be considered.
This option may also require the construction of a rail spur into the site or refurbishing the existing tracks.
Groundwater levels are expected to be about 1.2 to 1.9 m below existing ground surface, and the level is expected
to fluctuate with changes in precipitation and sea level. As the foundation elevations for most structures included in
the Indicative Design of LGSWWTP are below the groundwater level, dewatering will be required. It is expected
that all groundwater extracted from the site during dewatering activities will require treatment prior to discharge, and
additional cutoff walls along the southern property boundary may be warranted to prevent ingress of contaminated
water from offsite. A cutoff wall was installed along the southeastern property boundary to prevent ingress of
contaminated water from offsite.
If deep pile foundations or other ground improvement methods that have similar offsite impacts are used, noise and
vibration will be a concern, and measures to mitigate these impacts will need to be reviewed. A test pile program
could be performed to provide clarity on issues associated with advancing piles through the upper granular layers
below the site, as well as assess the practicality and benefit of noise mitigation measures.
Vibration would also be of concern for settlement at adjacent buildings and the railway line to the south.
Preconstruction surveys of these structures should be completed prior to construction activities. There may be
requirements for shoring along the southern and western sides of the site to mitigate any issues with settlement at
the railway lines and the overpass piles, and ground improvement infrastructure.
There will be significant truck traffic added to the current vehicle traffic levels. Engine emissions will be greater than
current background levels at the site; however, these emissions are temporary only during the construction period.
There should not be any significant dust issues during construction. Dust generation during excavation and hauling
can be managed using water suppression. The use of smoke eaters is recommended to capture any smoke
generated during welding onsite.
Separate to the construction of the new plant, the upgrades for the conveyance lines will be completed by the time
the plant is ready for startup testing. There will be significant traffic issues associated with this work between the
new plant site and the existing plant site.
14-4 456928_WBG103013092847VBC
Construction Sequencing and Site Development Phasing
There is some slack time in the schedule for construction of the conveyance upgrades, and these upgrades will
need to be complete and operational before the Owner Commissioning phase of Contract 1. The project schedule
shows this work being complete at the end of 2019.
Decommissioning of the existing LGWWTP is scheduled to occur in 2021 once LGSWWTP is operational.
• Ground improvements
• Excavation
• Structural slabs
• Structural concrete
• Equipment installation: process, HVAC, electrical, piping, ducting, cable trays, and cable pulls
• Building finishing: roofs, doors, stairs, painting, coatings, and architectural finishes
• Conveyance tie-ins
• Startup, testing, and commissioning
There is overlap between all of these major phases, and the construction sequence will need to be developed to
minimize critical path activities and maximize parallel activities to reduce schedule risk.
456928_WBG103013092847VBC 14-5
Construction Sequencing and Site Development Phasing
Once the mud mat is complete, forming and rebar placement for the raft foundation will commence. Sequencing
this work so that multiple crews work in different areas across site will maximize progress. The foundation for the
inlet pumping station, digesters, and RSS pumping station require deeper excavation and foundations slabs. There
could be crews working on the solids facility building, primary clarifiers, bioreactors, and secondary clarifiers at the
same time. Generally, there will be more activity on the western side of site, which will then move east towards the
Operations and Maintenance Building for each phase of construction. Once these areas are complete, the ancillary
buildings, digesters, and Operations and Maintenance Building could be completed. These activities may take up to
24 months to complete.
The installation of the influent sewer and effluent line tie-ins to and from 1st St. should be completed early and be
backfilled to allow construction access around the buildings.
Due to the amount of equipment required in the Solids Building, this building should be prioritized for completion
early in the schedule to allow equipment installation to be accelerated. There will need to be laydown areas for
pipefitters, electricians, and sheet metal subtrades. These areas will be located within the plant itself. The pipefitters
will have onsite welding shops that will need to be properly ventilated. These activities could take up to 18 months
to complete.
Startup and testing of equipment could overlap with equipment installation and finishing trades as work progresses
in other buildings. Owner commissioning by Metro Vancouver will require substantial completion of LGSWWTP,
including the Operations and Maintenance Building and conveyance infrastructure. These activities may take up to
12 months to complete.
Final grading and landscaping for the plant could be completed during the owner commissioning phase.
14-6 456928_WBG103013092847VBC
Operations Plan
The following supporting document is included in the Appendixes volume: Appendix 15 – Operations Plan
Technical Brief.
A more refined estimate of staffing levels for LGSWWTP is 31 FTE. The proposed level of O&M staff is less than
that developed using the guide owing to the high level of automation that will be employed at LGSWWTP. The
proposed staffing level has an allowance for an increased level of effort for maintenance due to the vertical layout
of the plant. This estimate does not include corporate Human Resources, Occupational Health and Safety,
Training, CDAC, or Information Technology/Security support, nor subcontracted janitorial or landscaping services.
Lulu Island WWTP uses a one-plus shift for plant staffing, and a typical schedule is one shift Monday through
Friday, with on-call coverage for the off-hours and the weekend. A similar staffing concept is envisaged for
LGSWWTP.
All preventative maintenance tasks will be performed onsite, including lubrication, changing of seals and gaskets,
instrumentation calibration, exercising valves, standby and electrical equipment inspection, and other like activities.
Some major overhaul maintenance may be performed offsite due to size of equipment or specialist requirements
for the maintenance activities. These activities include major overhauls on influent pumps, centrifuges, and process
456928_WBG103013092847VBC 15-1
Operations Plan
air blowers and gas compressors. The majority of the remaining large equipment can be overhauled in situ, such as
the screens, boilers, and UV reactors. Major tank refurbishments and capital upgrades will be performed by
subcontractors and budgeted for in the annual maintenance work plans. This work will be managed by the plant
superintendent/maintenance supervisor.
The following O&M activities at the existing LGWWTP are typically subcontracted by Metro Vancouver, and a
similar approach is envisaged for LGSWWTP:
• Janitorial services
• Landscaping services
• Maintenance and inspection services for other equipment items such, as roll-up doors, high-voltage equipment,
fire extinguishers, and HVAC systems
The following items are identified as new O&M activities that will be required for LGSWWTP:
• UV disinfection reactor maintenance, including lamp sleeve cleaning, lamp replacement, and ballast
replacement. This activity could be subcontracted for the first 2 years of operation to allow the O&M staff to
gain the knowledge required to perform this activity in-house.
• Activated carbon media replacement. This activity could be subcontracted to the activated carbon supplier.
• Centrifuge maintenance, including lubrication, belt tensioning, and replacement of worn components. These
activities will be performed in-house. Major overhaul activities could be subcontracted to a specialist shop
approved by the vendor to do the refurbishment work.
• Passenger and freight elevator maintenance and inspection. For regulatory compliance, these activities will be
subcontracted to the elevator vendor for certification.
Laboratory staff are responsible for sample collection and preparation, analysis, data certification and QC, and
sample preservation for shipping to other laboratories. The onsite laboratory at LGSWWTP will be used for
compliance monitoring and process optimization. Laboratory activities will include physical tests, such as pH and
temperature; and suspended solids, alkalinity, and some organic analysis, such as COD. BOD, nitrogen species,
and metals samples will be collected and transferred to the Annacis Island WWTP Process Laboratory for analysis,
and coliform samples will be collected and transferred to Metro Vancouver’s microbiology laboratory.
• Environmental Operators Certification Program (EOCP) training to become certified WWTP Operators
15-2 456928_WBG103013092847VBC
Operations Plan
Figure 15-1 provides a summary overview schedule for the various components of training required for the new
LGSWWTP.
Detailed Design
Field Guides
456928_WBG103013092847VBC 15-3
Operations Plan
• Pre-operational Checkout
• Equipment and System Performance Testing
• Owner Commissioning
Overall, the testing and commissioning period is expected to last 12 to 18 months, which allows 6 months for
Pre-operational Checkout, 4 to 6 months for Equipment and System Performance Testing, and 3 to 6 months for
Owner Commissioning.
In order to cover the staffing gap created by operating both plants during the transition period, Metro Vancouver
should hire operators on a temporary basis to operate the existing plant while existing staff rotates through the plant
commissioning team at LGSWWTP. There is a requirement to increase the overall staff complement at LGWWTP,
and the transition period would provide an opportunity to assess temporary hires for moving to the new plant on a
full-time basis. Existing operations supervisors and senior operators will need to provide supervision of new staff to
continue to operate the existing plant while the new plant comes online.
Owner commissioning will also have additional staffing requirements due to increased daily coverage during
commissioning. The plant will require 24-hour operating staffing coverage and increased laboratory staffing for the
first few months to ensure the process is optimized and effluent criteria are met.
15-4 456928_WBG103013092847VBC
Operations Plan
The CDAC configuration, process, and CDAC startup testing and commissioning; optimization; and integration
requires careful consideration for LGSWWTP. Metro Vancouver’s Wastewater Treatment CDAC is a highly
customized system and beyond what many ‘boilerplate’ configurations in industry are familiar with. Close
coordination, including embedding CDAC configuration resources in the design team and use of a CDAC auxiliary
team, is warranted.
In addition to the commissioning activities, there is significant documentation that needs to be prepared for this
project. This documentation, including MTAs, elearning modules, asset attribute data, and maintenance manuals,
will be required before the commissioning team is fully chartered.
O&M Documentation
Commissioning Manager
eLearning MV Senior Project Manager
MV Operations Specialist
MTA’s MV Lions Gate Plant Superintendent
Deputy Commissioning Manager
Asset Attribute Data MV Lions Gate Maintenance Supervisor
MV Operations Supervisor
O&M Documents
456928_WBG103013092847VBC 15-5
Operations Plan
15-6 456928_WBG103013092847VBC
Operations Plan
• The lifting/handling of equipment and materials during construction and initial installation do not form part of this
strategy. The rated lifting capacities will not be exceeded under any circumstances.
• The majority of equipment is unlikely to require lifting operations for general maintenance, such as greasing,
filter changes, cleaning, and similar activities.
• The majority of equipment is unlikely to require complete removal during its working life.
• Lifting equipment will be used for all plant items heavier than 25 kg and for items less than 25 kg where location
constraints or nature of the equipment could result in any manual lifting being deemed unsafe.
• In areas where there are numerous pieces of equipment, a common lifting device, such as a gantry crane, is
provided as the most suitable lifting equipment.
• Where common lifting facilities pass over expansion joints, spliced joints to crane rails and runway beams will
be designed into the installation to allow up to 15 mm of movement without affecting the operation of the lifting
unit or its ability to travel the full length of the rails or beams without jamming.
• Safe person-lifting apparatus to be incorporated into tank access/hatch design and included as part of the lifting
equipment provided. Safe working area around hatches to be provided with items such as guard rails and tie-off
points.
456928_WBG103013092847VBC 15-7
Operations Plan
Due to the various locations and nature of plant equipment or materials, various types of lifting facilities are
required. The use of bridge cranes, gantry cranes, jib cranes, monorails, and truck-mounted cranes have been
identified for each piece of equipment and material handling. The use of forklifts and pallet jacks are also identified.
15-8 456928_WBG103013092847VBC
Cost Estimates
Cost ($)
Land Cost 0 0 0 0
Taxes 0 0 0 0
456928_WBG103013092847VBC 16-1
Cost Estimates
Utilities 2.1
Consumables 0.7
Other 0.1
Total 10.8
16-2 456928_WBG103013092847VBC
References
17. References
7group and Bill Reed. 2009. The Integrative Design Guide to Green Building. Washington, DC: U.S. Green Building
Council.
AECOM. 2013. “NWWBI Database.” National Water & Wastewater Benchmarking Initiative.
http://www.nationalbenchmarking.ca/index.htm. Accessed December 18, 2013.
BC Ministry of the Environment (MoE). 2004. Lions Gate Wastewater Treatment Plant, Operational Certificate
ME-00030.
BC Ministry of Environment (MoE). 2010. “Site Profile Freeze and Release Provisions.” 37 Facts on Contaminated
Sites. Version 2. June. http://www.env.gov.bc.ca/epd/remediation/fact_sheets/pdf/fs37.pdf. Accessed March 10,
2014.
BC Ministry of Environment (MoE). 2011. Certificate of Compliance – 1311, 1321, 1350. West 1st St., North
Vancouver, BC. Site ID: 9769. March 23.
BC Ministry of Environment (MoE). 2013. B.C. Best Practices Methodology for Quantifying Greenhouse Gas
Emissions.
BRC Acoustics & Audiovisual Design. 2012. Baseline Sound Analysis. December 17.
Canadian Council of Ministers of the Environment (CCME). 2009. Canada-wide Strategy for the Management of
Municipal Wastewater Effluent. February 14. http://www.ccme.ca/assets/pdf/cda_wide_strategy_mwwe_final_e.pdf.
Accessed December 4, 2013.
Clemen, R.T. 1991. Making Hard Decisions: An Introduction to Decision Analysis. Belmont: Duxbury Press.
Concert Realty Services Ltd. (Concert). 2013. An Evolving Vision for the Future of Harbourside.
http://harboursidewaterfront.com/. Accessed December 2, 2013.
Environment Canada. 2004. Guideline for the Release of Ammonia Dissolved in Water Found in Wastewater
Effluents. December 4.
Environment Canada. 2013. Vancouver Wharves climate station. 1971-2000 climate normals database.
Golder Associates (Golder). 2013. Lions Gate Secondary Wastewater Treatment Plant, Geotechnical Design Brief.
December 18.
Greater Vancouver Sewage and Drainage District (GVS&DD). 1997. 1995 Wastewater Inventory.
Gregory, R., L. Failing, M. Harstone, G. Long, T. McDaniels, and D. Ohlson. 2012. Structured Decision-making: A
Practical Guide to Environmental Management Choices. New York: Wiley-Blackwell.
Kerr Wood Leidal Associates Ltd. (KWL). 2012. District of North Vancouver – Creek Hydrology, Floodplain Mapping
and Bridge Hydraulic Assessment (Draft Report).
Lions Gate Public Advisory Committee (LGPAC). 2013. Community Values and Interests for the Design of the
Lions Gate Secondary Wastewater Treatment Plant. October 21.
456928_WBG103013092847VBC 17-1
References
Metro Vancouver. 2010. Integrated Liquid Waste and Resource Management Plan.
Metro Vancouver. 2011. Metro Vancouver Drinking Water Management Plan. June.
http://www.metrovancouver.org/about/publications/Publications/DWMP-2011.pdf. Accessed November 22, 2013.
Metro Vancouver. 2013. Engagement and Consultation Results: Project Definition Phase for Lions Gate Secondary
Wastewater Treatment Plant. October 23.
National Research Council Canada (NRCC). 2010. User’s Guide – NBC 2010 Structural Commentaries.
Piteau Associates (Piteau). 2010. Confirmation of Remediation – Former North Vancouver Freight Shed and
Passenger Station 1311, 1321 and 1350 West 1st Street North Vancouver, B.C. February.
Province of British Columbia (BC). 2008. Living Water Smart – BC’s Water Plan.
Sources Archaeological & Heritage Consultants (Sources). 2013. Archeological Summary Letter Report.
November.
Stantec Consultants Ltd. (Stantec). 2005. Iona Island and Lions Gate WWTP Summary Report. Final Report.
Project No. RFP 03-005. August.
SYLVIS. 2013. The Biosolids Emissions Assessment Model (BEAM): A Method for Determining Greenhouse Gas
Emissions from Canadian Biosolids Management Practices. Prepared for Canadian Council of Ministers of the
Environment. http://www.ccme.ca/assets/pdf/beam_final_report_1432.pdf. Accessed December 18, 2013.
U.S. Environmental Protection Agency (USEPA). 1973. Estimating Staff for Municipal Wastewater Treatment
Facilities.
Vancouver Sun. 2013. “$3.3-billion contract for Coast Guard ships will bring up to 1,000 jobs to Vancouver
Shipyards.” October 7.
http://www.vancouversun.com/news/billion+contract+Coast+Guard+ships+will+bring+jobs+Vancouver+Shipyards/9
006862/story.html. Accessed December 19, 2013.
Von Winterfeldt, D., and W. Edwards. 1986. Decision Analysis and Behavioural Research. Cambridge, UK:
Cambridge University Press.
Water Board of Sydney. 1993. Energy/Greenhouse Life Cycle Analysis. The Clean Waterways Program. Australia
17-2 456928_WBG103013092847VBC