CH 07
CH 07
Chapter 7
Monitoring and Controlling the Project
This chapter addresses issues related to monitoring and controlling the project. Monitoring
refers to collecting, recording and reporting information about the project while controlling uses
this information to bring actual performance into agreement with the plan. The chapter begins
with an overview of the plan-monitor-control cycle. Emphasis is given to the importance of
designing the planning-monitoring-controlling process. Next the issue of data collection and
reporting is discussed including the topics of data collection and types of data, data analysis,
types of reports, and meetings. Following this, the earned value approach is presented. As the
chapter notes, earned value represents a way to capture both in-process performance and cost on
a certain date as measured against budget or schedule. Finally the chapter concludes with a
discussion of project control, the design of the control system, and scope creep.
80
81
82
83
84
85
86
87
88
89
Solutions to Problems
25.
90
Actual cost of work performed (ACWP) = $400 + 180 + 300 + 400 + 200
= $1480
Budgeted cost of work performed (BCWP) = $300 + 200 + 250 + .2(600) + .
2(400) = $950
Budgeted cost of work scheduled (BCWS) = 300 + 200 + 250 + .8(600) +
.5(400) = $1430
Cost/spending variance = BCWP ACWP = $950 1,480 = -$530
Schedule variance = BCWP BCWS = 950 1,430 = -$480
Schedule Performance Index (SPI) = BCWP/BCWS = $950/1,430 = 0.664
Cost Performance Index (CPI) = BCWP/ACWP = $950/1,480 = 0.642
In this instance, more has been spent than the baseline plan and, given
what has been spent, less progress has been made than should have
been.
91
92
28.
Students should begin by inputting the original planned project data into
MSPs entry table as it appears in the problem. Only the activity names,
predecessors, durations, can be entered in the Entry table.
The Gantt chart would look as follows:
The budgeted cost data is entered using the Cost Table. To enter this data
you select the View menu, then Tables, then select Cost from the drop
down list. Enter the budgeted cost information under the Fixed Cost
section of the table. Fixed costs are assigned by activities as opposed to
by resources. This problem is concerned about a cost of activity not a
resource cost. The table will look as follows:
Once the original data is in the action plan format, the students should
save the Baseline data so that a comparison to actual can be calculated
by MSP. To do this you need to go to the Tools menu, select Tracking, then
select Save Baseline, then click OK so that you are saving the baseline for
the entire project.
Once the baseline has been saved, students need to enter the actual data
provided in the problem. You next need to create a table to enter the
actual costs and percent complete. By default MSP automatically
calculates actual costs based on the percent an activity has been
completed. In this example we need to turn off this feature. To do this
you must select the Tools menu, then the Options line, then you select
Calculations Tab. Next you deselect the option Actual costs are
calculated by MSP. Once the automatic cost calculation is turned off, you
select Table from the View menu and then select the Tracking table from
93
the drop down menu to enter the information that you have on actual
costs and percent complete. Enter the information that is provided in the
case. The software will calculate the rest. Your spreadsheet/table should
look as follows:
Note: The start and finished dates will be based on the dates that you
start the project, in this example the project was started on January 15,
2001. If you choose not to enter a start date, MSP will default to using
todays date.]
Once you have entered the actual data, MSP will calculate the information
needed to answer questions #27 based on the date of comparison, in this
problem, that is the end of the sixth week. Using the start date of January
15th, the end of the sixth week would be February 23, 2001. (No matter
what your start date is, it is easy to see in MSP when the end of the sixth
week would be.)
You must first enter that date for the comparison, to do that you go to the
Project Menu, select Project Information and enter the date under Current
Date. Next, you are ready to view the earned value information for this
project. Select the View menu, then Table, then More Tables, from this
drop down menu select Earned Value table and click Apply. The following
is the chart that should appear:
By adding or subtracting the totals of the columns you can determine the
total project variances as outlined in Problem #26. Note: Please recall
that MSP reverses the calculations.
94
adjustments to the steps in the action plan in a timely fashion so that the
entire project is not affected. This would also allow Alex to monitor the
project more closely.
96
The company should also develop a change control system for their work
with clients. Such a system will minimize the impact of the scope creep that
appears to happen at J. Z. Smith. They need a formal process to deal with
changes to the original project plan. Jeremy can design this system to
include his input. He can make sure that the budget and estimate of
completion dates are adjusted if he and the client both agree on the cost and
duration of any changes the client wants in the scope of the project.
Cable Tech, Inc.
Question: Does the monitoring and control method seem adequate?
No, the monitoring and control method is not adequate. Jean will not be able
to take effective action from headquarters, being removed from the site.
What are the potential problems?
Among some of the potential problems:
o Jean is located at headquarters and any delays in getting reports to her
will leave too long a period between occurrence of the attendance
problem and a response.
o The policies themselves are also in question. There is no flexibility in the
policies for differences in reasons between sites. In many cases the
problem may be the companys fault, beyond the control of the employee.
o The employees were never consulted on the design of these policies and
may reject their enforcement.
o Although punishment is provided for, rewards for good attendance are not
recognized so no positive motivation is being considered.
Additional Incidents for Discussion
97
98
This is a good control system for improving the user responsiveness of IS but may be
unresponsive to the larger needs of the firm, particularly if later activities depend on the
completion of ISs tasks. An external PM would be concerned about the delay on the IS
activities as they strive for meeting internal quality requirements.
99
100
Question #4: Develop an action plan and draw a Gantt chart for the
Parking Lot phase of the project. Answer Freds questions.
If everything goes as scheduled the Gantt chart for the Parking Lot
construction would look as follows:
If St. Dismus did not hear from the city until May 1, 2001, the Gantt chart
would be adjusted as follows: (New end date for the project would be
6/12/01.)
The latest date to be notified by the city to meet the June 15th deadline is
May 7th. This would make the end date of the project June 15th.
Question 5: What information does Fred need to make a decision
about building a hair salon?
This is an example of scope creep. The building of the hair salon was not in
the original project plan. Fred must determine, first if he wants to build a
hair salon for residents, he should have the COO and VP of marketing do a
complete business plan with a cost benefit analysis/return on investment for
this endeavor. After that is done, Fred must determine the impact that this
would have on the construction project. He must identify the additional
costs, changes necessary to the design and schedule.
101
102
103