The document discusses project budgeting and cost estimating. It covers topics like top-down versus bottom-up budgeting, work breakdown structures, estimating direct and indirect costs, and dealing with budget uncertainty. Budgeting involves forecasting resource needs, quantities, costs, and timing. Top-down uses manager experience, while bottom-up involves task owners. Costs include direct materials, labor, and overhead. Uncertainty comes from errors, changes, and new information.
The document discusses project budgeting and cost estimating. It covers topics like top-down versus bottom-up budgeting, work breakdown structures, estimating direct and indirect costs, and dealing with budget uncertainty. Budgeting involves forecasting resource needs, quantities, costs, and timing. Top-down uses manager experience, while bottom-up involves task owners. Costs include direct materials, labor, and overhead. Uncertainty comes from errors, changes, and new information.
The document discusses project budgeting and cost estimating. It covers topics like top-down versus bottom-up budgeting, work breakdown structures, estimating direct and indirect costs, and dealing with budget uncertainty. Budgeting involves forecasting resource needs, quantities, costs, and timing. Top-down uses manager experience, while bottom-up involves task owners. Costs include direct materials, labor, and overhead. Uncertainty comes from errors, changes, and new information.
The document discusses project budgeting and cost estimating. It covers topics like top-down versus bottom-up budgeting, work breakdown structures, estimating direct and indirect costs, and dealing with budget uncertainty. Budgeting involves forecasting resource needs, quantities, costs, and timing. Top-down uses manager experience, while bottom-up involves task owners. Costs include direct materials, labor, and overhead. Uncertainty comes from errors, changes, and new information.
Download as PPTX, PDF, TXT or read online from Scribd
Download as pptx, pdf, or txt
You are on page 1of 32
ENGINEERING PROJECT
MANAGEMENT DAF - 211
Dr. Khin Marlar Maung
Professor Department of Commerce Meiktila University of Economics Meredith, J. R., Shafer, S. M., & Mantel, S. J. Jr. (2017). Project Management in Practice (6th ed.). John Wiley & Sons, Inc. Chapter 4 Budgeting the Project Introduction Once the budget is developed, it acts as a tool for upper management to monitor and guide the project. Appropriate data must be collected and accurately
reported in a timely manner or the value of the
budget to identify current financial problems or anticipate upcoming ones will be lost. This collection and reporting system must be as
carefully designed as the initial project plans
because late reporting, inaccurate reporting, or reporting to the wrong person will negate the main purpose of the budget. 4.1 Methods of Budgeting Budgeting is simply the process of forecasting what resources the project will require, what quantities of each will be needed, when they will be needed, and how much they will cost. Most businesses and professions employ experienced estimators who can forecast resource usage with amazingly small errors. Top-Down Budgeting The top‐down approach to budgeting is based on the collective judgments and experiences of top and middle managers concerning similar past projects. These managers estimate the overall project
cost by estimating the costs of the major
tasks, which estimates are then given to the next lower level of managers to split up among the tasks under their control, and so on, until all the work is budgeted. Top-Down Budgeting The advantage of this approach is that overall budget costs can be estimated with fair accuracy, though individual elements may be in substantial error. Another advantage is that errors in funding small
tasks need not be individually identified because
the overall budget allows for such exceptions. Similarly, the good chance that some small but
important task was overlooked does not usually
cause a serious budgetary problem. The experience and judgment of top management
are presumed to include all such elements in the
overall estimate Bottom-Up Budgeting In bottom‐up budgeting, the WBS identifies the elemental tasks, whose resource requirements are estimated by those responsible for executing them (e.g., programmer‐hours in a software project). This can result in much more accurate estimates, but it
often does not do so for reasons.
The resources, such as labor and materials, are then
converted to costs and aggregated to different levels of
the project, eventually resulting in an overall direct cost for the project. The PM then adds, according to organizational policy,
indirect costs such as general and administrative, a
reserve for contingencies, and a profit figure to arrive at a final project budget. Bottom-Up Budgeting Bottom‐up budgets are usually more accurate in the detailed tasks, but risk the chance of overlooking some small but costly tasks. Such an approach, however, is common in
organizations with a participative
management philosophy and leads to better morale, greater acceptance of the resulting budget, and heightened commitment by the project team. Work Breakdown Structure (WBS) Work Breakdown Structure (WBS) 4.2 Cost Estimating Work Element Costing The task of building a budget is relatively
straightforward but tedious. Each work
element is evaluated for its resource requirements, and its costs are then determined. 4.2 Cost Estimating Direct material cost Direct labor cost Overhead cost 4.2 Cost Estimating For example, suppose a certain task is expected to require 16 hours of labor at $10 per hour, and the required materials cost $235. In addition, the organization charges overhead for the use of utilities, indirect labor, and so forth at a rate of 50 percent of direct labor. Then, the total task cost will be
$235 + [(16hr * $10/hr) * 1.5] = $475
Activity versus Program Budgeting Traditional organizational budgets are typically activity oriented and based on historical data accumulated through an activity‐based accounting system. Individual expenses are classified and assigned
to basic budget lines such as phone, materials,
fixed personnel types (salaried, exempt, etc.), or to production centers or processes. These lines are then aggregated and reported by
organizational units such as departments or
divisions. Activity versus Program Budgeting Table4-3 Typical Monthly Budget for a Real Estate Project (pg. 118) 4.3 IMPROVING COST ESTIMATES 4.4 BUDGET UNCERTAINTY AND PROJECT RISK MANAGEMENT Budget uncertainty Perceptually, the PM sees the uncertainty of
the budget like the shaded portion of Figure
4-3, where the actual project costs may be either higher or lower than the estimates the PM has derived. Three Causes for Change There are three basic causes for change in projects and their budgets and/or schedules. Some changes are due to errors the cost estimator made about how to achieve the tasks identified in the project plan. Such changes are due to technological uncertainty: a building’s foundation must be reinforced due to a fault in the ground that wasn’t identified beforehand; a new innovation allows a project task to be completed easier than was anticipated, and so on. Three Causes for Change The third source of change is the mandate: A new law is passed, a trade association sets a new standard, a governmental regulatory agency adopts a new policy. These changes alter the previous “rules of conduct” under which the project had been operating, usually to the detriment of the budget. Three Causes for Change Other changes result because the project team or client learns more about the nature of the scope of the project or the setting in which it is to be used. This derives from an increase in the team’s or client’s knowledge or sophistication about the project deliverables. The medical team plans to use a device in the field as well as in the hospital. The chemists find another application of the granulated bed process if it is altered to include additional minerals. Project Budgeting in Practice To determine a project budget, the project manager (PM) starts with the project plan or WBS to determine the various steps required in the project, the resource needs, labor hours, and associated costs. This cost estimate, plus a “contingency” of up to 25
percent added to either the labor hours or total
cost, is then used as the project budget for both obtaining approval for the project and as a placeholder in the department’s budget so the funds will be encumbered and unavailable for other purposes. Project Budgeting in Practice However, top management is also responsible for constructing a budget for the company and may have also calculated some cost for this project, or the department that will be funding it. In the process, they will be using their own
methods, such as the budget or cost of a previous
but similar project, the amount of money the department was budgeted for last year, the amount of monies available for them to spend, the amount the project manager or department spent last year, gut‐feel, and other such approaches. Thank you.