CH 04
CH 04
Chapter 4
Budgeting the Project
This chapter continues the topic of project planning and focuses specifically on project
budgeting. With the technical aspects of project planning discussed in the previous
chapter, this chapter addresses the need to develop a budget in order to obtain the
resources needed to accomplish the project’s objectives. The chapter begins with an
overview of budgeting methods and discusses both the top-down and bottom-up
approaches. In comparing these approaches, it is noted that top-down budgeting is
usually accurate overall but may include significant errors for low-level tasks. Bottom-
up budgeting, on the other hand, is usually accurate for low-level tasks but risks
overlooking tasks. Following this overview of budgeting methods, the chapter next
addresses the issues of cost estimation and improving cost estimates. The need for PMs
to thoroughly understand the organization’s accounting system is emphasized. Also the
issue of budget cuts is addressed. In terms of improving cost estimates, techniques such
as the use of learning curves and tracking signals are presented. Finally, the chapter
concludes with a discussion of budget uncertainty and risk management.
Harvard: 9-193-071 Porsche AG This 20-page case illustrates how traditional cost
measurement systems operate in an R&D department but offer little information for
managing projects.
Harvard: 9-690-051 Campbell Soup Co. This 23-page case describes the cost-
justification of a new engineering project to develop a microwavable package and
product for the growing convenience foods market segment. A 28 page teaching note (5-
690-094) is available for this case.
39
4/Budgeting the Project
1. The main disadvantages of top-down budgeting are that significant errors may be
made for low-level tasks, a lower level of budget acceptance is likely due to limited
participation, and it provides little training opportunities in budgeting for junior
managers. The main disadvantage of bottom-up budgeting is the risk of overlooking
tasks.
2. Charging administrative costs based on total project completion time is based on the
assumption that administrative costs increase in proportion to the length of the
project. In other words, longer projects are expected to require more administrative
resources than shorter projects.
3. The learning rate corresponds to the reduction in time or cost as output doubles.
Therefore, a lower learning rate actually translates into a faster rate of learning.
Generally speaking, people have the ability to learn while machines do not. Thus, if
we assume by complex we mean automated, then the plant would have a slower
learning rate of perhaps 95 percent. On the other hand, if by complex it is assumed
that workers need a great deal of skill to operate the equipment, then a faster learning
rate of 70 percent would be expected.
4. Tracking signals can help identify systematic biases in cost and other estimates.
Knowledge of such biases can be used in preparing future estimates. Knowledge of
biases also allows estimators to understand and correct their biases.
5. The three basic causes listed in Section 4.4 would appear to capture the vast majority
of change in projects. As the question hints, however, two or more of these causes
may occur at the same time. For example, new knowledge of a competitor’s new
product may change the performance goal of a project and also require a change in
how the tasks are achieved.
7. The accountant would likely assume that the $3,000,000 is to be allocated evenly
over the six month duration of the task or $500,000 per month. However, most of the
$3,000,000 will likely be incurred at the beginning of the task when the equipment
must be acquired and paid for. The problem for the PM is that the accountant will
expect a $500,000 charge in the first month of this task but will see an expenditure of
40
4/Budgeting the Project
close to $3,000,000! Based on this the accountant and top management may become
alarmed in terms of the project being completed on budget.
8. A straight-line project life cycle means that the impact of a budget cut would be
constant throughout the project’s life. A slope greater (less) than 45 degrees means a
change in the budget would have a proportionally larger (smaller) impact on the
project’s completion. Of course it is unlikely in reality to observe a straight-line life
cycle.
10. According to the “mythical man month” the three new engineers hired would
probably not hit the ground running and would require training. This training would
likely take time away from other members of the project team. Thus, the extra
capacity created by adding these three engineers was likely more than used up by the
other engineers who spent some of their time now training the new team members.
11. The purchasing manager’s assistant’s solution only addressed the symptom of the
problem and not the cause for why the company was short in the first place. In this
case the solution created another problem, namely, that the organization is no longer
cost competitive.
12. The managers should consider both the average cost and variance of the cost for each
plan. Often the tendency is to focus solely on the average cost. However, depending
on an organization’s need to avoid risk, in some situations it might be better to
sacrifice and select a project with a higher average cost but a smaller variance. By
selecting a project with a lower variance, the probability of the actual cost greatly
exceeding the average cost is reduced.
A Budgeting Novice: Since the precedent has been set that a top-down approach to
budgeting is used at this company, Alex should do the same. Alex could approach his
boss with sound estimates and assure the boss that he has involved all the experts in
preparing the budget. Most likely, the boss will still re-work the numbers, but he should
be more comfortable that Alex did his homework in preparing it. Alex must make timely
communications to the boss on the project status, including thorough budget reports.
In the past, Alex has had autonomy to manage both performance and schedule, but has
not been permitted to develop the budget. Thus, it might be helpful for Alex to share
documents with his boss that demonstrate his competency in handling both schedule and
performance (assuming his boss is not familiar with these). In addition to documenting
41
4/Budgeting the Project
his previous experience, it would be useful for Alex to share with the boss his WBS and
demonstrate how this drove his cost estimates. Finally, Alex might find it useful to share
with his boss how having responsibility for only schedule and performance and not
budget, limits his effectiveness as a project manager. Another advantage for Alex’s boss
is that more of his or her time would be freed up if Alex were permitted to work on
budget issues with clients.
Major Dynamic Ground Systems: Careful monitoring of all costs is critical for the
success of this project. The PM must monitor waste, scrap, and spoilage costs. These
should be tied to performance so that low numbers do not hide low levels of progress.
The controller must be able to identify all of the costs, such as those listed above, so that
nothing can be hidden or rolled up under such things as “work-in-process inventory” and
a true assessment can’t be ascertained until the end of the project.
General Sensor Company: The most relevant factors are the seriousness of the error,
Justin’s experience, and the fact that only one stage is affected, but it represents 50% of
the cost. Justin should combine the top-down approach with selected bottom-up inputs
and checks on the 50% of cost stage. He is experienced and comfortable with a top-down
approach and this makes sense for the majority of the project. Selective inputs from
lower level workers involved in the tasks would confirm his estimates, or indicate where
more information is needed.
Teaching Purpose: This installment of the St. Dismas case requires students to address
issues related to identifying and dealing with cost uncertainty
1. The cost per square foot for the units is given in the text together with its standard
deviation. What other areas of cost or revenue are likely to have cost uncertainty?
How should these uncertainties be handled?
Other areas of cost and revenue that are likely to be uncertain are the contingency
allowances, marketing costs, personnel replacement, resource costs, GS&A, overhead
allocation to budget, influences such as weather on the construction, cost increases for
equipment or furniture, and labor cost increases.
To handle the uncertainty, the estimators need to gain more knowledge of the areas of
uncertainty and clearly define all the assumptions that were used to determine the
budget. Furthermore, they need to review the project plans thoroughly to identify
areas of risk. Finally, instituting a change order process, in case there is a change
during the project would also be worthwhile.
Assuming cost or revenues are normally distributed, statistical and probability theory
could be used to gain additional insights. Of course, it is important that the PM,
working with the accounting department, closely monitors all of the project costs.
42
4/Budgeting the Project
2. How would you suggest the team handle the issue of Dr. Link’s supposedly inflated
medical equipment costs?
Since these are costly items, the CFO should recommend using a bottom-up approach
to budgeting. The CFO should facilitate a team with experts and the differing doctors
to determine the actual equipment needs and costs. This would enable buy-in from
both parties. This would also ensure a more accurate estimate of needs. If there is
sufficient data, the CFO can also include a tracking signal to identify if bias is in the
estimates.
Photstat Inc.
Teaching Purpose: This case provides students with an opportunity to analyze the risk of
a project with several uncertain parameters. Students are asked to simulate the
completion of this project 100 times and create a risk profile for the project. Based on
this, students are asked to comment on the implications of using an average value versus
the risk profile. Case can also be analyzed using Crystal Ball.
2. Simulate this project 100 times and compute the average profit over the 100
replications. Plot a histogram of the outcomes of the 100 replications.
A portion of a spreadsheet that was created to simulate this project 500 times is
shown on the following page. There are two major differences between this
spreadsheet and the one discussed earlier to calculate the expected value of the
project. First, the values in columns B-I (beginning in row 20) were generated
randomly using Excel’s Random Number Generation tool. Secondly, a conditional
formula was entered to calculate the NPV based on the useful life randomly generated
in column I. For example, the NPV for the first replication (cell T20) was calculated
as:
=IF(I20=3,NPV(T$18,J20:L20),IF(I20=6,NPV(T$18,J20:O20),IF(I20=8,NPV(T$18,J20:Q20),NPV(T$18,J20:S20))))
43
4/Budgeting the Project
44
4/Budgeting the Project
Q R S T
1 7 Cash Flow Cash Flow Cash Flow
18 Year Year Year 1 1 .1 1 %
19 1 1 11 NPV
2 0 $522 ,373 $590 ,082 $666,567 $851 ,709
2 1 $879 ,837 $1 ,053,604 $1 ,261 ,691 $298 ,689
2 2 $595,390 $653,833 $718 ,013 $1 ,244,393
2 3 $767,066 $896 ,592 $1 ,047,990 $1 ,208 ,590
2 4 $576,161 $642,457 $716 ,380 $1 ,100 ,677
2 5 $586,834 $661 ,218 $745,032 $1 ,574,923
2 6 $424,472 $489 ,715 $564,985 $888 ,853
2 7 $520 ,389 $574,310 $633,819 $272 ,259
2 8 $572,449 $638,226 $711 ,562 $1 ,119 ,011
2 9 $358,745 $393,010 $430,548 $617 ,600
Histogram
1 00
Frequency
80
60
40
20
0
e
, 5 51
, 0 51
, 4 51
, 9 51
, 3 51
, 8 51
, 3 51
51
2 1
, 0 51
or
$ 6 , 25
$1 5 ,2
$2 5,2
$2 5 ,2
$2 5,2
$3 5 ,2
$3 5,2
$4 5,2
,2
$1 5 ,2
M
05
65
8
4
8
2
$1
Bin
3. How does the average of the simulation compare to the expected value you
calculated? What are the managerial implications of this difference?
The average of the simulation was $1,423,668 which is relatively close to the
expected value. However, the range of values observed in the simulation experiment
varied from a loss of almost $65,000 to a profit of over $4.5 million. Thus, the
simulation experiment demonstrates the uncertainty of the actual outcome of this
project.
Using Crystal Ball: The use of Crystal Ball can greatly speed up the development and
analysis of the simulation model for this case. To illustrate this, the spreadsheet shown
on the following page was created. With Crystal Ball, values for the random parameters
are generated by defining cells as Assumption Cells rather than using Excel’s Random
45
4/Budgeting the Project
Number Generation tool. In this particular case, cells B5 to I5 were defined as assumption cells. For example, cell B5
corresponds to the market size in the first year of the product’s introduction. From the case, it is estimated that the market size
follows a normal distribution with a mean of 100,000 units and standard deviation of 10,000 units. To define cell B5 as an
assumption cell, first the cursor was placed in this cell. Next, the Define Assumption button was selected. Then the Normal
distribution was selected from the Distribution Gallery that appeared. In the next window, 100,000 was entered in the Mean
field and 10,000 was entered in the Std Dev field and the OK button selected. Cells C5 to H5 were specified in a similar
fashion.
Cell I5 was a little different in that the useful life of the equipment does not follow a continuous distribution. In this case, the
Custom distribution was selected from the Distribution Gallery. Next 3 was entered in the Value field and .1 entered in the
Prob. field and the Enter button clicked. In a similar fashion, 6 was then entered in the Value field, .8 in the Prob. field and
the Enter button clicked. This was repeated for the probabilities of 8 year and 10 year useful lives, respectively. After all this
information was entered, OK was clicked.
Finally, cell P5 was defined as the Forecast Cell. NPV was entered as a descriptive name in the Forecast Name field and
Dollars in the Units field. The formulas in cells J5:O5 are the same as was previously discussed. To run the simulation, the
Start Simulation button was selected.
The Frequency Chart and Statistics views are shown below. The average cost of the project is within 1 to 2 percent of the
results obtained using Excel’s Random Number Generation tool. Additional details about the use of Crystal Ball can be found
in Appendix C.
46
4/Budgeting the Project
47
4/Budgeting the Project
Test Questions
F 1. ___ The project’s budget is merely the sum of its resource costs.
F 4. ___ Because project budgeting is for a special case and the organization’s budgeting
process is for routine work, the project manager need not be familiar with the
organization’s accounting system.
F 6. ___ Activity budgets show expenses by task, time period, and expense category.
F 7. ___ There is no way other than guessing to estimate the impact of learning on a
project’s task.
T 8. ___ Calculating the Tracking Signal can not only reveal if estimates are biased, it
can also tell how severe the bias is.
F 9. ___ By very careful planning, a project manager can do away with cost uncertainty.
F 11. ___ Traditional organizational budgets are task-oriented, rather than activity-
oriented.
F 12. ___ Learning curve theory states that performance of labor per unit will improve
by a percentage each time production increases by the same percentage.
T 13. ___ Learning curve theory states that performance of labor per unit will improve
by a fixed percentage each time production doubles.
T 14. ___ Individual elements of project budgets are generally more accurate in bottom-
up budgeting.
F 17. ___ Individual budgets are constructed using the work breakdown structure in the
top-down budgeting method.
48
4/Budgeting the Project
T 18. ___ Budgetary gaming is a fact of life using either or both the bottom-up and
top-down method.
49
4/Budgeting the Project
b 25. ___ The budget strategy based on collecting information from middle managers
based on their prior experience is called.
a. bottom-up budgeting
b. top-down budgeting
c. earned value budgeting
d. zero-based budgeting
e. none of the above
d 26. ___ The name given to the budget process that aggregates income and expenditures
across projects is:
a. activity-oriented budget
b. top-down budget
c. bottom-up budget
d. program-oriented budget
e. activity-based costing
Short Answer
28. List some reasons why you would take on a project that was forecast to lose money.
Allow for a follow-up project, improve competitive position, acquire knowledge, get
firm’s name out, broaden a product line.
32. List some of the factors commonly left out of cost estimation.
Inflation, Learning curve, Waste and spoilage, Risk, Potential delays.
50