Method Statement - Piling Work
Method Statement - Piling Work
Method Statement - Piling Work
A. OBJECTIVE
1) To outline the sequence of work or construction methodology
for Piling Works at Sg Jempol, Sg Pelangai and Sg Jemapoh
.Methodology starts from survey setting out until excess pile
cutting until as-built drawing submission for Consultant
review.
2) To outline preparation or coordination required before start
work
3) To outline quality plan or inspection test required during
project implementation.
4) To perform safe working environment and compliance to the
safety requirements.
B. SCOPE OF WORK
In general scope of work for this work method statement cover the
following:Scope of Works
Piling Works (Drop
hammer method)
Methodology starts
from pile position
setting out until asbuilt preparation for
Consultant review.
Descriptions / Details
Piling Works (Drop Hammer Method) consist
of the following items;
Soil Investigation
Survey Setting Out
Pile Driving and Pile Jointing
(welding)
Piling Records
Pile Cutting
As-built (Actual Piles Position)
Prepared by Surveyor
C. REFERENCES
BS 8004- Foundation
D. RECOURCES PLANNING
Material Planning
Item
Material Descriptions
1
R.C Pile (250 x 250)
2
Pile Head / Pile Toe for pile joints
Manpower Planning
Ite
m
1
2
3
4
Manpower Descriptions
Project Manager
Project Engineer / Supervisor / Surveyor
Machine Operator
Skilled and Semi Skilled Workers
RC Pile
(Square/
Spun) and
others
accessories
Method of
Inspection
Visual
Check &
Random
Sampling
G. WORK METHODOLOGY
1) Soil Investigation
2) Survey Setting Out (Pile Position)
The surveyor will set out the alignment of the pipe by means
of EDM using the marking on the piles and the pump house
as a reference point.
Lower down the pile into position as in above step by using
crane mounted piling frame and adjust the position and
vertically of the pile with the aid of the surveyor.
Liaise with Consultant or Client representative to conduct
joint inspection.
3) Pile Driving and Pile Jointing
The steel pipe piles will be sand blast to removed dirt &
grease on the pipe then a layer of hot bitumen coating will be
apply on the body of the piles.
Piles shall be driven by using 1.5 tonne drop hammer type by
follow the Calculation of Setting.
Positioning Pile Machine: Piling base machine shall be placed
manoeuvre to align with the piling points.
Placement of the Pile: the initial pile segment is pitched using
a low speed hydraulic winch and then the pile is placed into
the guide or chamber of the piling machine.
Pile is driven into the ground by the drop hammer.
The driven pile should be maintained straight in line at all the
times.
Piles should not deviate more than 75mm from their designed
positions as at the working level of the piling rig.
Extension Pile: When the initial pile segment is driven close to
ground, operator shall stop driving and install the second
piles into the position for jointing.
Pile shall be jointed by using welding the mild steel plate
between piles.
Continue Pile Driving Process until Set.
Pile driving process repeated until the required resistance to
pile penetration is achieved, or the required pre-determined
penetration depth is reached. The setting is achieved when
the set taken for the final 10 blows of the hammer is within
the set as calculated. (Refer calculation attach)
4) Piling Records
All the pile reading shall be recorded in the Pile Record
Form.
All pile records shall be checked correct and signed by
relevant C&S consultant or Client representative.
5) Pile Cutting
Excess piles length shall be cut according to the piling CutOff-Level.
4
Stage of
Work
Material
Selection
Sample
Submissio
n
(If
applicable
)
Material
Delivery
Survey
Setting
Out
(Boundary
/ pile
position
pegs)
Pile Jacked
In ( Drop
Hammer
Method)
Frequency
Once
Once
Checking Required
Check material to
be used (Grade/
Size): RC Piles either
square piles or
spun piles
Material Product
Brochure
submission
approved by Client
Method
Acceptance
Review
Catalogue
or relevant
test
certificate
Material as
per Project
Specification/
Requirements
Sample
Submission
Form /
Letter
Approved by
Client
Material as
per spec,
good
conditions
and no
damaged.
Every
Delivery
Material delivered
as per material
order, No Damaged
(Quantity, Quality &
Spec)
During
Survey
Setting
Out
Visual Check
Pegs per
& Random
construction
Measureme
drawing
nt
Before Pile
Jacked In
Process
Pile driving as
per
construction
Visual Check drawing and
visually
straight
alignment
During Pile
Jacked In
and Pile
Jointing
Random
Sampling
Check
Visually
straight
alignment
Visual Check and pile joint
was
satisfactory
done
Visual Check Proper
& Recorded records with
authorized
signature
Upon
completio
n of piling
works
Pile
Cutting
As-Built:
Data &
Info:
plotting
and
Consultant
submissio
n
Upon
completio
n of pile
cutting
Check the
following: All the piles shall
be cut follow the
marked CutOff-Level
Suitable
machine
Surveys pick up info
and data for AsBuilt drawing
preparation and
submission.
As-built review by
C&S Design
Consultant
Visual &
Measured
Field Survey
and plotting
Review AsBuilt
Drawing
Pile cutting as
per Cut-OffLevel and
suitable pile
cutter
machine, No
pile damaged.