Work Method Statement For PILING WORKS (Injection Method) : - Your Project Title

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 8

Document Reference : Your_Company/WMS/PLG(IM) Document Date : Date_Order

WORK METHOD STATEMENT FOR


PILING WORKS (Injection Method) for
common residential and medium size commercial buildings

--YOUR PROJECT TITLE--


COMPANY ACTIVITY NAME SIGNATURE DATE
Your_Company Prepare By
Name

Remarks / Comments:

COMPANY ACTIVITY NAME SIGNATURE DATE


Your_Design Review By
Consultant
(If applicable)
Approved By
Please tick ( )which
relevant
Remarks / Comments:

COMPANY ACTIVITY NAME SIGNATURE DATE


Your_Client Review By
Name
Approved By
Please tick ( )which
relevant
Remarks / Comments:

STATUS:
Approved Approved with Comments Rejected as per comments
Doc. Date: Doc. Reference:
Your_Company_Name Date Order Your_Com/WMS/PLG(IM)
Work Method Statement for Piling Works (Injection Method)
Your_Project_ Title

Table of Contents
Section Titles / Subtitles Page
1.0 Objective 3 of 8

2.0 Scope of Work 3 of 8

3.0 References 3 of 8

4.0 Resources Planning 3 of 8


4.1 Material Planning
4.2 Manpower Planning
4.3 Machinery & Equipment Planning

5.0 Material Handling & Delivery Inspection 4 of 8


5.1 Material Handling
5.2 Material Delivery Inspection: Checking Methodology

6.0 Coordination between Other Trades 4 of 8


6.1 Coordination between Others Architecture Trades
6.2 Coordination between Others C&S Trades
6.3 Coordination between Others M&E Trades

7.0 Work Methodology 5 of 8


7.1 Survey Setting Out
7.2 Pile Driving and Pile Jointing (Injection Method)
7.3 Piling Records
7.4 Pile Cutting
7.5 As-built (Actual Pile Position) Prepared By Surveyor

8.0 Quality: Inspection and Test Plan 7 of 8


8.1 Inspection Test Plan
8.2 Relevant Construction Standard & References
8.3 QC Documents or Relevant Checklist

9.0 Health, Safety, Security and Environment 8 of 8

10.0 Attachment 8 of 8

www.kontraktorQualitytools.com.my 2
Doc. Date: Doc. Reference:
Your_Company_Name Date Order Your_Com/WMS/PLG(IM)
Work Method Statement for Piling Works (Injection Method)
Your_Project_ Title

1.0 OBJECTIVE
 To outline the sequence of work or construction methodology for
Piling Works (Injection Method). Methodology starts from survey setting
out until excess pile cutting until as-built drawing submission for
Consultant review.
 To outline preparation or coordination required before start work
 To outline quality plan or inspection test required during project
implementation.
 To perform safe working environment and compliance to the safety
requirements.

2.0 SCOPE OF WORK


In general scope of work for this work method statement cover the following:-

Scope of Works Descriptions / Details


Piling Works (Hydraulic Piling Works (Hydraulic Hammer Method) consist of
Hammer Method) the following items;
Methodology starts from  Survey Setting Out
pile position setting out  Pile Driving and Pile Jointing (Injection)
until as-built preparation  Piling Records
for Consultant review.  Pile Cutting
 As-built (Actual Piles Position) Prepared by
Surveyor

3.0 REFERENCES
NIL

4.0 RECOURCES PLANNING


4.1 Material Planning
Item Material Descriptions
1 RC Square Pile/ RC Spun Pile (Brand/Grade as per contract/ specification)
2 Pile Head / Pile Sheet for pile joints
4.2 Manpower Planning
Item Manpower Descriptions
1 Project Manager
2 Project Engineer / Supervisor / Surveyor
3 Machine Operator
4 Skilled and Semi Skilled Workers
4.3 Machinery & Equipment Planning
Item Machinery & Equipment Descriptions
1 Injection Pile Machine (Model: XXXXXXXXXX)
2 Hydraulic Power Jack (Model: XXXXXXXXXX)
3 Pile Cutter Machine
4 Mobile Crane
5 Welding Machine with welding consumable

5.0 MATERIAL HANDLING & DELIVERY INSPECTION


5.1 Material Handling

www.kontraktorQualitytools.com.my 3
Doc. Date: Doc. Reference:
Your_Company_Name Date Order Your_Com/WMS/PLG(IM)
Work Method Statement for Piling Works (Injection Method)
Your_Project_ Title

 RC Pile (Square/ Spun Piles) All material shall be loaded and


unloaded with care by mobile crane or other type of suitable
machinery to avoid pile damaged. Materials shall be placed where the
materials are not obstructing the main road access in order to prevent
material double handlings.
 All material shall be stacked on top of the piece of timber with proper
timber shim to prevent material damaged or easy material lifting.

5.2 Material Delivery Inspection: Checking Methodology

Method of
Material Items to be Checked or Inspected
Inspection
RC Pile (Square Pile/ Spun Pile) shall be:-
 Correct Specification/ Grade
 Correct Size and Pipe Diameter
RC Pile (Square/ Visual
 Material delivered in good condition,
Spun) and Check &
no damaged.
others Random
 All accessories shall be available
accessories Sampling
and ready for use.
 Pile material: Date of casting shall
over than 28 days

6.0 COORDINATION BETWEEN OTHER TRADES


6.1 Coordination between Others Architecture Trades (NOT APPLICABLE)

6.2 Coordination between Others C&S Trades (NOT APPLICABLE)

6.3 Coordination between Others M&E Trades (where applicable)


 Check if any underground M&E services at the area, check if require
any underground services relocation prior start any excavation works.
Services relocation shall be carried upon receiving approval from
consultant or local authority.

www.kontraktorQualitytools.com.my 4
Doc. Date: Doc. Reference:
Your_Company_Name Date Order Your_Com/WMS/PLG(IM)
Work Method Statement for Piling Works (Injection Method)
Your_Project_ Title

7.0 WORK METHODOLOGY


7.1 Survey Setting Out (Pile Position)
 Surveyor shall pegs the pile position according to Approved
Construction Drawing.
 Liaise with Consultant or Client representative to conduct joint
inspection (subject to project requirements).
 QUICK CHECK: During setting out, check the following:-
 Random inspection shall be carried out to confirm pile
pegs position correct as per specified in the Approved
Construction Drawings.

7.2 Pile Driving and Pile Jointing


 Piles shall be driven by using hydraulic hammer type by follow the
Calculation of Setting for Pile Injection – Please attached the calculation
with this submission.
 Positioning Pile Machine: Piling base machine shall be placed
manoeuvre to align with the piling points.
 Placement of the Pile: the initial pile segment is pitched using a low
speed hydraulic winch and then the pile is placed into the guide or
chamber of the piling machine.
 Pile Jacked Hydraulically into the Ground: When the pile ready to
start, pile jacked in to the ground hydraulically.
 The pile injection should be maintained straight in line at all the times.
In common soil condition, every single stroke will able to jack in
penetration of 6 metres.
 Extension Pile (Mild Steel Sleeve): When the initial pile segment
jacked in reached close to ground, operator shall stop jacked in and
re-opened chamber door to place the second piles into the chamber.
 Pile shall be jointed by using mild steel pile sleeve; where the sleeve is
placed on to the top end of the installed pile. An extension pile is lifted
up and placed into the chamber, which is then properly aligned in a
vertical axis with the installed pile.
 The piston rod will jacked the two piles into the sleeve until both ends
meet at the centre plate.
 Continue Pile Jacking Process until Set: Resume jacked in after
checking the pile joint completed and satisfactory done.
 Pile jacking process repeated until the required resistance to pile
penetration is achieved, or the required pre-determined penetration
depth is reached. The setting load registered through the pressure
gauge mounted on the control panel.
 The jack-in pile is said to have achieved the 'set' when it has visually
ceased to penetrate further under the required jacking load and
maintaining period.
 AQUICK CHECK: During pile driving (hydraulic hammer), check the following:-
 Check the pile position always in the correct alignment
 Check the pile joints satisfactorily done
 Check and monitor gauge mounted on the control panel
and stop when it achieved “set” and reached to the hard
strata

www.kontraktorQualitytools.com.my 5
Doc. Date: Doc. Reference:
Your_Company_Name Date Order Your_Com/WMS/PLG(IM)
Work Method Statement for Piling Works (Injection Method)
Your_Project_ Title

7.3 Piling Records


 All the pile reading shall be recorded in the “Pile Record Form”.
 All pile records shall be checked correct and signed by relevant C&S
consultant or Client representative.
 a QUICK CHECK: During pile driving (Hydraulic Hammer Method) in the
process, check the following:-
 Check and ensure all the data shall be recorded in “Pile
Record Form” for every blow.

7.4 Pile Cutting


 Excess piles length shall be cut according to the piling Cut-Off-Level.
 Suitable type of pile cutter machine shall be used to ensure pile not
damaged during pile cutting process.
 All the excess piles shall be collected and removed away from site.
 A
QUICK CHECK: During excess pile cutting, check the following:-
 Check pile Cut-Off-Level is correct before allow for pile
cutting or hacking.
 Check suitable type of pile cutter machine shall be used
to cut the piles. No damages to the cut piles.

7.5 As-built (Actual Piles Position) Prepared by Surveyor


 Actual piles position shall be recorded by surveyor in the survey book.
 From the actual data taken at site, surveyor will plot the Pile As-built
Drawing for C&S Design Consultant review.
 If any piles out of construction tolerance, rectification shall be carried
out according to C&S Design Consultant instructions.

www.kontraktorQualitytools.com.my 6
Doc. Date: Doc. Reference:
Your_Company_Name Date Order Your_Com/WMS/PLG(IM)
Work Method Statement for Piling Works (Injection Method)
Your_Project_ Title

8.0 QUALITY: INSPECTION & TEST PLAN


8.1 Inspection & Test Plan
Stage of
No Frequency Checking Required Method Acceptance
Work
Check material to be
Review Material as per
used (Grade/ Size):-
Material Catalogue or Project
1 Once  RC Piles either
Selection relevant test Specification/
square piles or
certificate Requirements
spun piles
Sample Material Product Sample
Approved by
2 Submission Once Brochure submission Submission
Client
(If applicable) approved by Client Form / Letter
Material ordered as Order Form / As per specified
Material
3 Every Order per Project Spec. / Purchase in Spec/Client
Order
Client Approval Order Approval
Material delivered as Material as per
Random
Material Every per material order, No spec, good
4 Sampling
Delivery Delivery Damaged conditions and
Check
(Quantity, Quality & Spec) no damaged.
Survey Mark and Check:-
Setting Out During Visual Check Pegs per
 Building Boundary
5 (Boundary/ Survey & Random construction
 Pile Position
pile position Setting Out Measurement drawing
pegs)  Pile (Cut-Off –Level)
Check initial piles
Pile driving as
 Correct Size
Before Pile per construction
Jacked In  Correct Grade Visual Check drawing and
Process  Correct Positions visually straight
 Straight Alignment alignment
Pile Jacked (Pile/Helmet/Hammer)
6 In (Injection Visually straight
Method) Check the all in alignment and
During Pile straight alignment and Visual Check pile joint was
Jacked In joint satisfactorily done satisfactory
and Pile done
Jointing Proper records
Ensure all pile records Visual Check
with authorized
in “Pile Records Form” & Recorded
signature
Check the following:- Pile cutting as
Upon  All the piles shall per “Cut-Off-Level”
completion be cut follow the Visual & and suitable pile
7 Pile Cutting
of piling marked “Cut-Off- Measured cutter machine,
works Level” No pile
 Suitable machine damaged.
As-Built: Surveys pick up info
All piles within
Data & Info: Upon and data for As-Built Field Survey
construction
plotting and completion drawing preparation and plotting
8 tolerances/
Consultant of pile and submission.
Acceptable by
submission cutting As-built review by C&S Review As-
Consultant
Design Consultant Built Drawing

8.2 Relevant Construction Standard & References

www.kontraktorQualitytools.com.my 7
Doc. Date: Doc. Reference:
Your_Company_Name Date Order Your_Com/WMS/PLG(IM)
Work Method Statement for Piling Works (Injection Method)
Your_Project_ Title

NIL
8.3 QC Documents or Relevant Checklist

Please refer Attachment A: Inspection Checklist for “Pile Records Form”

9.0 OCCUPATIONAL SAFETY AND HEALTH (OSH)


All occupational safety and health (OSH) measures shall be as per
FACTORY AND MACHINERY ACT 1967 under:-
 Building Operation and Works of Engineering Construction” (BOWEC)
Safety Regulations 1986. Relevant Regulations – further details please
refer to the following regulations:-
 Part II : General Provision
 Part XII : Excavation Work
 Part IX : Material Handling and Storage, Use and Disposal
 Part XVI : Hand and Power Tools

10.0 ATTACHMENT

 Attachment A: Inspection Checklist for “Pile Records Form”

www.kontraktorQualitytools.com.my 8