Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

MOS Open Cut

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3
At a glance
Powered by AI
The open cut trench method involves excavating down to and exposing the existing pipe so that it can be repaired or replaced and then backfilled. Traffic management measures like signboards, flagmen and speed limits will be implemented.

The steps include preparation work like studying drawings and checking site conditions, surveying work, excavating the road, lowering the pipeline and backfilling, and road restoration as per original structures.

Equipment that will be used includes excavator, road cutting machine, dump truck, sludge pump and generator set. Machinery includes watering cart.

METHOD STATEMENT: OPEN CUT

1) Introduction
The open cut trench method involves excavating down to and exposing the existing
pipe so that it can be repaired or replaced and then backfilled.
The detail method and length of road crossing should be subjected to construction
drawing.
2) Scope

Existing underground piping crossing the road (Refer Attached Drawing).

3) Tools/Machinery

Excavator
Road Cutting Machine
Dump Truck
Sludge Pump
Generator set
Watering Cart

4) Safety, Health & Environment

Workers will be supplied with necessary PPE.


Sufficient warning tape and barrier shall be installed on working site.
Visible direction and warning sign shall be provided away from excavation point.
Battery or genset powered lights should be deployed during the hours of darkness
around barricades.
Flagmen will be on site to guide the traffic flow during the process.
During the process of soil disposal, should arrange some specially-assigned person
to clean the soil falling on the road.
Watering the transportation road continuously to avoid raise dust.

5) Traffic Management

According to the actual situation, Contractor will close one side road to ensure
vehicle and people safety will go smoothly.
Set signboard and flagmen to guide vehicle to pass through the point. A speed limit
was set and a flagmen was assigned at the exit point to prevent a traffic jam or
accident.
Contractor HSE representative will monitor the compliance of this plan and to take
correct actions where observed.
6) Procedure

a. Preparation work
To study all relevant drawings, depth of crossing, check whether equipment
and materials for construction are delivered at site.

Check the site condition, whether any other facilities was buried near the
crossing location. If it has, the facilities shall be exposed by hand tools firstly.
Any trial holes excavated in roads or adjacent verges to locate services or
apparatus will be properly protected by appropriate traffic signs and barriers.

b. Surveying work
Formal layout survey of the road crossing will be undertaken noting centre line
and crossing limits by Contractor.

The centreline will be established along the crossing central axis according to
the control stakes and centreline stakes arranged by pre-construction survey.

c. Road excavation
Contractor shall mark out the boundary line of the trench according to the
crossing axis and the design width of the trench.

Contractor shall use cutting machine to cut the two sides of section road, and
then make small cuts on the road surface with excavator to break the adhesion
of the road.

d. Pipeline lower-in and backfill


After completion of ditching, Contractor shall level off the ditch bottom
according to the design requirement.

Then, the pipeline shall be lowered in the trench to its proper position, sand
bedding materials as per design specification will be installed to specified
minimum depth, below and above pipeline.

Pipes will be installed by soft slings or by methods that does not incur surface
damage. On final placement, all exterior surfaces of the pipes will be tested to
verify no damages where such has occurred all repairs will be undertaken and
re-tested prior to any backfilling.

The sub-base and base course layer for open cut crossing road with concrete
slab shall be reinstated as per existing and these layer shall be compacted,
tested and witnessed by client/consultant.
If the soil under trench is over excavated, the over excavated shall be backfilled
and compacted.

e. Road restoration
Road restoration will be undertaken as per the original road base structures
and surfacing referenced in design specification or as per existing road surface.

Contractor will compile all documentation necessary for perusal and handover
to clients/consultant.

You might also like