METHOD
STATEMENT
FOR CONSTRUCTION
ACTIVITIES
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
INDEX
DESIGN STATEMENTS.
SHUTTERING DRAWINGS.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
The setting out works is the most important activity in any execution work. It is called out in the
following way
1.The Points, which are forming the base line having certain defined references from
certain permanent structure, are established and protected from any disturbances.
2.
A theodolite having-at least count of one second is set at one of the points and is sited to any
other point to form a base line from where the offset and the angle to any point to the
proposed structure is considered.
3.
A point at a comfortable distance from the building grid which falls in the line showing the
distance from the base line is established and marked on masonry pillars is protected.
4.
Now from the above operation we have established a reference point for the structure.
5. The theodolite is then shifted to the above point and the first point is sited and is turned
to the defined angle to form a: lone parallel the grid line.
6. The above line is established and the point which from this line are marked on
pillars constructed in the above line.
7. The survey pillars are constructed at point's from where the distancelo the main point
can be measured by turning a line perpendicular to the line parallel to the grid line.
8. In the above' line, the distance to the points are measured and marked with paint so
that these points are nor removed easily.
9. The theodolite is the'set at a point established at a point from where the line already
established and the points in the other grid line, which is at a defined angle from the
previous line, Can be sited.
10. Now the new line is established and points. are marked as described earlier.
11. The theodolite is then shifted to the next point and the setting of the theodolite
establishing the points are continued till the starting point is sited and measured.
12. There, can be closing error and the error is distributed to all the points as a corrective
measure.
13. All the above points established which the reference for the proposed structure are
given due respect and are preserved undisturbed till the structure has come up to the
defined shape with the required accuracy.
,
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
The excavation works of wall foundation are carried out in the following manner.
1. The area to be excavated is marked with lime powder giving due allowance for
working space.
2. The excavation is carried out manually by using hand tools.
3. The excavated earth which is good for filling works is spread at places required filling and
the unwanted earth is disposed off.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
The surface to receive concrete is made wet and cement slurry is poured above the starter, which
is a construction junction. The- RMC received is unloaded tray made out of MS plates. The
concrete is then
mixed well properly to' form a uniform concrete free from segregation of
bigger aggreg-ates. It is then poured inside the forms manually to a layer of concrete to a
depth of 600mm. It is then consolidated, by using needle vibrator. Then the second layer of
concrete is poured and is vibrated. Similarly concreting is done to the required height. It is
cured 'for at least seven days by keeping the Hessian cloth wrapped around the column wet.
2. PLINTH BEAM
The SM surface above which the plinth beams rests are to be made wet. The RMC unloaded
over the MS span is mixed .well and is poured inside the forms. It is then consolidated by
means of a needle vibrator. Concrete is cured by keeping the Hessian cloth covering the beam
wet.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Stones of required sizes and river sand are stacked near the place of work
2.The surface of
PCC over which the masonry is to be done made clean and damp.
3.Cement sand mortar of specified proportion is prepared over a clean metal sheet.'
4.The area and -size of the masonry are marked by lying strings, which forms a guideline
for the mason working on this.
5.
A layer of sand mortar is placed is placed over the PCC the stones are laid in a staggered
manner to form a coarse of masonry.
6.
The voids are then packed with the mortar and the stone surfaces are made clean,
7.
A layer of sand mortar is again laid over the first layer of masonry and a course of masonry is
constructed.
8.
Similarly required courses of a masonry is build as per drawing and kept clean to received the
next day's works.
9.
Care is taken to provided through Stones (Header or Bond Stone) in each layer in a staggered
manner in such a way that one header comes in one square meter area.
10. The second stage of construction is started next day and if the final height of the same
section comes within
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
13.The locations not satisfying the standard are treated as required to achieve the specified
standards.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Safety works will be always be ensured. All workers working at the top of the columns during
concerting will be provided with helmets, gloves and safety belts. A platform will prepared all
around the top of the column for easy movement of concreting/vibrating team.
Detailed Procedure
Reinforcement
Bars of specified diameter will be straightened. Cut bend and placed in position as per
the approved construction drawings and bar bending Schedule. The steel will be lapped at
specified locations adequately. Care will be taken not to lap the bars at mid height of the
columns after erection of reinforcement in place stirrups will be prepared and positiOned cover
blocks will then be bound to the sides of stirrups.
Casting of Starters
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Concrete will be placed manually, in steel pans or with crane buckets, and properly vibrated
continuously. Concreting will be done in layer Care will be taken to pour the concrete slowly,
so that the concrete does not accumulate heavily at the base of column. One supervisor will be
deputed at the base with wooden mallet to check any voids in concreting.
After concreting is complete, plumb and diagonals of the column will be again checked.
Post concreting
Deshuttering will be done after .24 hours of concreting. Any making good of the concrete surface
will be carried out as soon as forms are stripped. However approval will be requested prior to
making good of any defect in concreting.
-
After this the column will be wrapped fully ,with wet Hessian cloth for curing purpose. One
labour will be deputed full time for curing, to ensure that the concrete surface is always wet.
Curing will be done for at least seven days, after which Hessian will be removed.
As a final completion work, layout mortar, Concrete/mortar droppings at the base of the column
will be removed and finished smooth and clear.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Detailed of Procedure.
As soon as the column reaches the required beam bottom level the activity of slab form work
will start.
Site at the ground floor will be made clean and no object will be their other then shuttering
material.
For first floor level slab ground will be made uniform/level and proper compact will be made
there to erect the staging for form work.
Staging will be erect at slab/beam area up to required height level.
At beam position M.S. span will be fix to the required length of the beam & it will be rest on
the staging made for that.
The above same exercise wily be made whenever beam is coming shown on the slab form
work drawing.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Reinforcement
Bars of -specified diameter will be straightened cut bend and placed in
position as per the approved construction drawing and bar bending schedule.
The reinforcement will lap at the specified location adequately,
While fixing the reinforcement at site first beam main reinforcement fixing
will be done after that the stirrups of required die and dimension will be
positioned.
Cover block will be then kept at position
After binding the beam reinforcement slab reinforcement will be fix there.
Concretin
On the approval of concrete will start with necessary equipment.
Concrete first will be placed at the column beam junction and then in
the beam position. While concreting vibrator will be used.
Concreting will be done in layer..
After pouring the concrete in the beam concrete will be done in slab
area. at slab. One supervisor and one engineer will always be there while concreting
Post concreting
bottom 14 days.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Description
Weight
Load carrying
capacity when
placed
1.8Kgs.
15Kgs.
55 Kgs.
12 Kgs.
1.65 Tons
Acrow san
MS Shuttering sheet
with Angie frame.
4.
10.
11.
20 Kgs.
1.80 Tons
Horizontal
Position
Total load
carrying
capacity
Total weight
of steel &
concrete.
89.10 T
. 46.80 T
100.0 T
100 M2
PI
.
Wooden Battens/
8kgs/rmt 2 . 4 x 1 . 2
100.M
Runners 4"x3"/2"x3"
5.5kg/m
200 M
Nails 4",3" & 2" long
80 kgs.
1.050 T
Steel
for
Beam 1.050.
Tons
300x750x9.0x3 Nos.
0.700
0.700 T
Tons
Steel for Slab 9.0x8.0
1.665 T
1.665 EF 2.3
Concrete Beam
22.39 T
750x750x8.0x2 Nos.
Concrete Beam
15.11 T
300x750x9.0x3 Nos.
Concrete Slab
35.82 T
9.0x80M
23.44 T
15.81 T
37.49 T
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Formwork
Formwork activity will start the next day of pouring of starters. Prior to erection of
formwork, the starter layout will be again cross-checked by the deputed engineer.
Any discrepancy, error, mistake in operation quality, alignment (Le. the column
starter should not get skewed) will be informed immediately to the clients Engineerin-charge, who will advise necessary action
Column forrnwork will be made of 12mrn shuttering plywood. The ply face will be
stiffened with 3" x 2" wooden battens all around at the edges. And internal supportstiffeners with 3" x 2" wooden battens (horizontal & vertical). Spacing of internal
stiffeners will be as per the formwork design drawings. Care will be taken to ensure
that the battens "sit" on the face of the plywood to prevent bulging.
The joint at the junction of two-ply pieces will be strengthened with an additional
batten.
The surfacing of ply (inner face) will be applied with form releasing oil of approved
make,
The column will then be tightened with tie rods fixed at regular intervals. Props
jacks will be supported at regular intervals on sides to keep the formwork in exact
position. Verticality and alignment will then be checked. After this the client's
Engineer-in-charge will be requested to review and approve the column, and sign on
the pour card.
Concreting
On approval of column form work, access platform will be. created up to'the top to
allow workmen to stand on top proceed with concreting. 1 No of vibrator with 40
mm diameter needle will be deputed on top of the access tower. 1 No. of vibrator
will be kept at the base as a standby.
Prior to placing of concrete, rich cement slurry will be poured into the column for
better bonding of new and old concrete.
Regional Office: 4th floor, West Wing, Soul Space Paradigm, Near Innovative Multiplex, Outer Ring Road, Bangalore 560 037
Corporate Office: B-1/E-23, Extension, Mohan Co-op, Industrial Estate, Mathura Road, New Delhi 110044.
Note:Any need arises for construction joint, the some shall be discussed with consultant's
site team and such location shall be provided with offset runners, which will give
proper key for the subsequent concrete.