PTI Current Trends in PT Design and Construction San Diego Handou...
PTI Current Trends in PT Design and Construction San Diego Handou...
PTI Current Trends in PT Design and Construction San Diego Handou...
Current Trends
in PT Design and Construction
in North America
Miroslav Vejvoda, MBA, P.E.
Technical Director
Post-Tensioning Institute
Credits
PTI seminars are developed in collaboration with
several PTI committees.
Special recognition to long time PT designers:
Cary Kopczynski, Ken Bondy, Brian Allred, Don Kline,
and others for their contributions.
What is PTI?
A non-profit organization for the advancement
of prestressed post-tensioned concrete
Established in 1976
Activities
Technical committees (15)
Specifications and technical documents
Certification committees (8)
Certification programs for materials fabrication
and field personnel certification
Marketing and promotional activities
PTI JOURNAL
Research projects and scholarships
Overview
General
Structural systems
Restraint to shortening
Common design issues
Quality and Durability
General
PT Applications & History
PT Basics
PT Systems & Protection
Reasons to Consider PT
Post-Tensioned slabs are typically 2 to 3 thinner than a rebar
deck and use less reinforcement providing financial savings.
Thinner slabs also benefit foundations, columns and seismic
design
The slab can be stressed when concrete reaches 3000 psi and the
forms pulled after that
The shoring and re-shoring times are reduced when using posttensioning
Deflections and Long-term creep problems are significantly
reduced by load balancing
Deck moment of inertia approaches I (gross) as opposed to I
(effective) resulting in reduced deflections
Sustainability
Copyright Post-Tensioning Institute. All rights reserved
Post-Tensioned Concrete
Advantages
Photo Courtesy of Cary Kopczynski & Company
Sustainability
10
Post-Tensioning Applications
2013 North American
Post-Tensioning Tonnage
Earthwork
6%
Bridges
10%
S-O-G
45%
Buildings
37%
Misc.
2%
11
Landmarks in PT Buildings
Introduction of strand systems (1962)
Replaced button-head tendon system
wires
Bearing
plate
Shims
Stressing
washer
Coldformed
buttons
Innovations in post-tensioning
Structural Steel
Prestressed Concrete
Post-Tensioned
Pre-Tensioned
Bonded Strands
Reinforced
Concrete
Bonded Tendons
Unbonded Tendons
Internal
External
Prestressed Concrete
What is Prestressing?
Prestressing is a method of reinforcing concrete, actively
resisting applied loads.
Pre-Tensioning
Steel tendons are stressed prior to concrete placement,
usually at a precast plant remote from the construction site.
Post-Tensioning
Steel tendons are stressed after the concrete has been
placed and gained sufficient strength at the construction
site
Tendon Configurations
Constant
Harped
Parabolic
Load Balancing
M1 = P e = Primary Moment
P wbal l
8e
Load W
P tan
CGC
Tendon
Wbal
P tan
P
Moment Diagram
Tension
No net
eccentricity
Tension
No net
eccentricity
Post-Tensioning Losses
Sources of Loss:
Initial
Losses
Friction, F
Elastic shortening, ES
Anchor set (wedge seating), A
Long Term
Losses
Concrete shrinkage, S
Concrete creep, C
Post-tensioning steel relaxation, R
Types of Prestressing
Tendons
Bare Strand
Monostrand
Multistrand
STRAND
Wedge Close-up
Extrusion Process
Photo Courtesy of GSI Post-Tension
Plastic Hopper
Extruder
Grease Injector
Cooling Trough
Bare Strand
Extruded Strand
27
28
Fixed-End Anchor
Photo Courtesy of G. Chacos
Pull Installation
Push Installation
Field Installation
29
Tendon Identification
Photo Courtesy of G. Chacos
Identification Tag
Color Coding
30
10
Shipping of Tendons
Photo Courtesy of VSL
31
Corrosive environments
Decks exposed and/or near salt water
Decks where de-icing salts will be used
(Northern areas)
PTI initiated change (PTI M10.2-00,
Addendum #3 December 2011):
Fully encapsulated PT systems for all
ACI 318 applications
ACI 318-14 refers to ACI 423.7-14; this
makes it a code requirement
32
Applicable Specifications
11
End Anchorages
ENCAPSULATED
ANCHOR
STANDARD ANCHORS
ENCAPSULATED
ANCHOR
WEDGES
34
Encapsulated Tendons
Photo Courtesy of General Technologies, Inc.
Encapsulated Tendons
Photo Courtesy of General Technologies, Inc.
12
Encapsulated Tendons
Photo Courtesy of Hayes Industries, Inc.
Bonded Post-tensioning
Ducts for Post-Tensioning
Multistrand Anchorages
13
Bonded Tendon
Photo Courtesy of VSL
Permanent
Grout Cap
Seal
Plastic Duct
Positive Mechanical
Coupling of Duct
40
41
Structural Systems
Two-way Systems
One-way Systems
Preliminary Design
14
Two-Way Slabs
Photo Courtesy of Suncoast Post-Tension Ltd.
44
Two-Way Slabs
15
Two-Way Slabs
Banded Direction Tendons bundled together to
create a pseudo beam A final effective force in
the band is specified on the plans; similar to beams.
Uniform Direction Tendons groups equally spaced
perpendicular the bands A kip per foot force is
specified on the plans; similar to one way slabs.
Analysis method is the same for both directions.
BANDEDFLATPLATE
16
TENDONLAYOUTPLANS
Band Beams
Typical Dimensions
1 = 36 48 ft
= 20 28 ft
2 = 20 30 ft
b = 48 120 in.
h = 12 18 in.
17
54
18
Load Balancing:
60% to 70% of DL for one- and two-way slabs
70% to 80% of DL for beams
100% for spandrel beams supporting ext. cladding
56
Variations to Estimations
End bays may require more PT for the same
span (higher moments, reduced drape,
unrestrained condition)
Heavy exterior skin loads that must be
supported by the slab
Parking slab PT quantity will increase due to
increased clear cover requirements in
aggressive regions
19
Preliminary Design
Span/Depth Ratio
Source: Design of
Post-Tensioned
Slabs With
Unbonded
Tendons; 3rd Ed.,
PTI
*These values apply
for members with
LL/Dl ratios < 1.0
Concrete Cover
20
Restrained Vs Unrestrained
A span is considered to be restrained when it
can resist the horizontal forces developed
during a fire
61
PreliminaryDesignTables
PTI DC20.9-11:
Guide for Design of Post-Tensioned Buildings
PreliminaryDesignTables
Two-way parking structures (flat plate or flat slab)
Basic design parameters and assumptions:
Loading: DL = self-weight + 5 lb/ft2 (0.2 kN/m2) (SDL); LL = 40 lb/ft2
(1.9 kN/m2)
Slab minimum F/A = 125 psi (0.9 MPa)
Three-span condition assumes a 62 ft (19 m) typical parking garage span
Concrete: fc = 5000 psi (34 MPa); fci = 3000 psi (21 MPa)
Assumed final effective force per 0.5 in. (12.7 mm) strand tendon = 27 kips
(120 kN)
Tendon CGS: Slab 1.5 in. (38 mm) top; 1 in. (25 mm) bottom interior span;
1.75 in. (44 mm) bottom exterior span
Cover to nonprestressed reinforcement: Slab 1.25 in. (32 mm) top; and
0.75 in. (19 mm) bottom
Column size: 14 x 28 in. (355 x 710 mm)
21
PreliminaryDesignTables
Two-way parking structures (flat plate or flat slab)
PreliminaryDesignTables
Two-way parking structures (flat plate or flat slab)
Restraint to Shortening
Shear wall arrangement
Pour strips / slip joints
22
67
RTS Cracking
69
23
% Of Total
Elastic
7%
Creep
9%
Shrinkage
56%
Temperature
28%
Total
100.0%
.
.
.
.
190 PSI
3000 PSI
30 F
.042%
.07
.14
.20
1.01
____
1.42
71
100
80
60
40
20
10
100
1000
10000
Time in Days
72
24
Restraint Cracking
Photo Courtesy of Merrill Walstad
73
Slab Movement
74
Closure Strip
CSs are used to reduce creep and shrinkage
effects
CSs must remain open for a specific amount
of time (until creep and shrinkage has taken
place)
They are 3 to 4 ft wide temporary
separations between two
regions stressed separately
3 to 4 ft.
CS
75
25
Closure Strip
Slab is temporarily allowed
to cure in smaller segments
Can locate the lateral system
in the middle of the
individual pour
Allows for internal stressing
may be critical on
subterranean projects
Typically remain open for 30
to 60 days. Deck will still
move for many months/years
76
Closure Strip
Movement Joints
78
26
Slip Detail
Slip Detail
Slip Connection
27
Facts about PT
Common design issues
Constructability
ACI 318-14
Facts About PT
PT concrete is not crack free
PT concrete is not water proof
You can drill / make openings in PT slab
If you drill into a tendon, it will not fly out
of the building
It is possible to upgrade / repair a PT
structure
PT structures are durable
83
Structural modeling
DO NOT use simplified analysis using
coefficients (Direct Design Method)
Use the Equivalent Frame Method, EFM
Sec. 13.7 of ACI 318-08, excluding Sec. 13.7.7.4
and 13.7.7.5
DO NOT use middle/column strip concept
Apply total moment to entire bay section when
using EFM
28
Incomplete design
Specify all PT requirements:
Final effective force, or the number of
tendons and corresponding final effective
force
Tendon profile
29
30
Review
Review
31
Cantilever Tendons
One-Way
Slab
Construction
95
96
32
98
Band Anchorage
99
33
Transfer Girders
Photo Courtesy of DYWIDAG Systems International
Podium Slab
102
34
103
104
Conduit Layout
Photo Courtesy of Cary Kopczynski & Company
105
35
Eccoduct Layout
Photo Courtesy of Cary Kopczynski & Company
106
Eccoduct Layout
Photo Courtesy of Cary Kopczynski & Company
107
36
UNIFORMTENDONSATCOLUMN
Top Rebar
111
37
Typical Re-Shoring
Pour Strip
38
Typical Re-Shoring
Pour Strip
For most two way slab applications the pour strip
is not designed to be a cantilever
The pour strip edges NEED to be fully re-shored to
the foundation
Without adequate re-shores pour strip deflections
and flexural cracking can occur.
ACI 318-14
Published in late 2014
Member based code
No Chapter 18 on prestressing
Prestressing requirements in chapters as
applicable
Refers to referenced standard 423.7-14 in 20.6.3.3
for corrosion protection of unbonded tendons.
New requirements for two-way slabs with bonded
tendons 8.6.2.2. and 8.6.2.3;
ACI 318-14
39
Elongations
Measured elongation needs to be within 7% of
calculated value (ACI 318-08, 18.20.1); change
in wording in 318-14, 26.10.2 in an attempt to
clarify requirement not achieved.
For tendons outside the 7%, the EOR shall
ascertain and correct the problem.
Timing for elongation approval is critical.
120
40
Elongation Discrepancy
Causes of Improper Elongation
Poor marking procedures
Inaccurate measurements
Inaccurate gauge reading
Improper stressing procedure
Math errors
Excessive seating loss
Equipment malfunction
121
Placement Inspection
Requirements
Check for damage to sheathing and
encapsulation items. Record the repairs
Verify number of tendons and CGS from
structural drawings
Verify that minimum number of tendons pass
through column in both directions
Remove/move excessive conduit, penetrations,
etc., especially by the anchors and columns
Look for tendons with extreme bends or odd
configurations
Conduit in the slab and penetrations too close
to the anchorages
Copyright Post-Tensioning Institute. All rights reserved
123
41
Inspection of Finishing
Tendon tails to be cut within one working
day after approval of elongations (ACI 301).
Tail cuts to be made between in. to a
distance specified by system supplier
proper lock in of encapsulation cap.
End caps to be installed within 8 hours of
cutting of the tails (ACI 301).
124
Tendon Finishing
Filling of Stressing Pockets (PTI FAQ 11)
Protruding tendon end of proper length
to accommodate end cap
Surface preparation: free from PT
coating, grease, form release agent, dirt,
loose concrete, etc.
Bonding agent
High quality premixed cementitious
chloride-free low-shrinkage repair grout
Proper mixing and application
125
Certification
Post-Tensioning
Material Producers
Certification of plants producing single strand
unbonded tendons (PTI Certified Plants)
42
Certification
Field Personnel
Slab-on-Ground Installer-Stressor
Level 1 Unbonded PT Field Installation
Level 2 Unbonded PT Ironworker
Level 2 Unbonded PT Inspector
Level 1 Bonded PT Field Installation
Level 2 Bonded PT Field Specialist
Thank You!
Questions ?
Copyright Post-Tensioning Institute. All rights reserved
128
43