ISSM Introduction
ISSM Introduction
ISSM Introduction
Summary
PART 1
PART 1
The BQ
The BQ is a standard pricing document for use in competitive tenders
The purpose of a BQ
The primary purposes of our Bills of Quantities are :
The Benefits of a BQ
A consistent detailed BQ :
Saves considerable time and cost of several contractors
measuring the same design in order to calculate their bids for
competition;
Provides a consistent basis for obtaining competitive tenders
Provides a clear statement of the scope of work
Allows for easy comparisons and analysis of tenders received.
Provides a strong basis for budget control and cost reporting
including:
- the preparation of cash flow forecasts,
- a basis for valuing variations
- a basis for the preparation of progress payments
It provides one of the best sources of real-time cost data, which
can be used for estimating the cost of future building projects
PART 1
10
11
That means that when a package is tendered the estimator has to read and
fully understand the rules of the MOM
These takes time during a tight tender period
It can lead to misunderstandings and mistakes in pricing
The lack of a standard can lead to misinformation when discussing unit rates
12
The solution
All developed countries have their own adopted SMMs
Australia, UK, HK, Singapore all have their own standard methods
13
14
PART 2
15
PART 2
16
17
18
19
20
The Bahasa Indonesia version is the document that IQSI have adopted
as the standard Method of Measurement for use by IQSI members
21
PART 2
22
B. General Principles
1. Introduction
23
B. General Principles
2.
2.1 The rules in this document are set out in tabular form. Each table is
split into three parts:
a) Information to be provided : which lists any information which is
required to support the Bill of Quantities
b) Classification table : where the main components of the
description are set out
24
MEASUREMENT RULES
DEFINITION RULES
COVERAGE RULES
C1 Work is held to
include:
(a) all cutting including
cutting holes and
perforations
(b) notching, drilling and
countersinking
(c) welds, rivets and
ordinary bolts with
associated nuts and
washers
1
2
3
4
5
6
Columns
King posts
Beams
Purlins
Cladding rails
Strutting and
bracing
7 Members of
roof
trusses,
number
stated
8 Members of
portal frames,
number stated
1 Cross sectional
shape and
dimensions stated
kg
EXAMPLE
Grade 40 fabricated structural steel with hot dip galvanize finish, all as specified
To Canopy as shown on drawing S 12-401 complete with all holes, perforations, notching, drilling,
counterinking, welds, rivets and bolts
Beam
size ..
(. Kg / m)
4000 kg
25
B. General Principles
2.3 The lists in each column are not intended to be exhaustive and
should be supplemented where necessary.
26
B. General Principles
2.4 Within the classification table, where more than one unit of
measurement is shown against one item, the units of measurement
given may be used as alternatives. The alternative selected must
be consistent with the corresponding description or rules.
27
B. General Principles
2.6 Measurement rules set out when work shall be measured and the
method by which quantities shall be computed.
2.7 Definition rules define the extent and limits of the work represented
by a word or expression.
2.8 Coverage rules draw attention to particular incidental work which
is held to be included within the item.
28
B. General Principles
3.
Quantities
29
B. General Principles
3.
Quantities
3.4 Unless otherwise stated, where minimum deductions for voids are
dealt with in this document they shall refer only to openings or
block-outs which are within the boundaries of measured areas.
Openings or block-outs which are at the boundaries of measured
areas shall always be the subject of deduction irrespective of size.
3.5 The requirement to measure separate items for widths or girths not
exceeding a stated limit shall not apply where these widths are
caused by voids.
30
B. General Principles
4.
Descriptions
31
B. General Principles
4.
Descriptions
32
B. General Principles
4.
Descriptions
33
B. General Principles
4.
Descriptions
4.6 Work is held to include for fixing through any types of finishes
applied to the surface of the base including glass, stone, ceramic
and any other vulnerable material.
34
B. General Principles
4.
Descriptions
4.8 Unless otherwise specifically stated in the Bill of Quantities, the following
shall be held to be included with all items :
(a) Labour and all costs in connection therewith
(b) Goods, materials and plant and all costs in connection therewith
(c) Assembling, hoisting, fitting and fixing goods, materials and plant in
position
(d) Contractors equipment and all costs in connection therewith
(e) Consumables
(f) Wastage, cutting, laps, breakage, loss and any other contingency
(g) Design to the extent required by the specification and drawings
(h) Protection throughout the construction period
(i) Taxes and duties (other than PPN)
(j) Establishment charges, overhead charges and profit
35
B. General Principles
4.
Descriptions
(b) All permanent work in supports, fixings and the like which may not be
designed but are required to correctly install the item
(c) Working in confined spaces
36
B. General Principles
5.
37
B. General Principles
6.
38
B. General Principles
7.1 Where work can be described and given in items in accordance with
these rules but the quantity of work required cannot be accurately
determined, an estimate of the quantity shall be given and identified as
a provisional quantity.
Example : Mpa 30 Concrete to housekeeping
pads (PROVISIONAL)
10 m3
7.2 Where work cannot be described and given in items in accordance
with these rules it shall be given as a provisional sum
39
B. General Principles
40
B. General Principles
8.2 Item codes are taken from the classification tables and are given in the
form :
Section Number
Example:
02200.2.4.1.
02200 Earthwork
Excavation
Pile caps
Depth
Number
.from first column
Number
.from second column
Number
.from third column
8.3 The digit 0 within an item code indicates no entry in the column of the
classification table to which it refers.
41
02200 Earthworks
INFORMATION TO BE PROVIDED
MEASUREMENT RULES
P2 Excavation by top down or other special method shall be given under a separate
heading
DEFINITION RULES
COVERAGE RULES
D1 Trenches include
excavation for thickenings to
slab on grade, beds and the
like
CLASSIFICATION TABLE
1 Excavation
1 Topsoil
2 Excavation,
commencing level
stated
1 To reduce levels
m3
2 Basements
3 Trenches
4 Pile caps
5 Pits
42
B. General Principles
9. Definitions
9.1 Where the ISMM rules describe work as designed or specifically required
9.2 Where the ISMM rules describe "labours" they are defined as work in
cutting, bending, drilling, shaping and the like
43
B. General Principles
9. Definitions
9.4 The term by others shall mean works to be carried out by other
contractors, statutory authorities or other parties.
9.5 The term or equal and approved shall mean materials or equipment
equal or better in quality or performance criteria to that shown on the
drawings or described in the specification and subject to the approval
of the project manager
B. General Principles
9. Definitions
9.6 The term extra over or extra over for preceding any item description
shall mean additional work over and above what is already provided. It
is deemed to exclude the item to which the term extra over or extra
over for applies
0.3m
Pipe
1m
44
BQ Description
Tee
Quantity
Unit Rate
1m
1 no
45
B. General Principles
the rules of the appropriate Section or included in the coverage of allin items at the discretion of the quantity surveyor