Project Risk Analytic Assessment Using The Hierarchy Process
Project Risk Analytic Assessment Using The Hierarchy Process
Project Risk Analytic Assessment Using The Hierarchy Process
I. INTRODUCTION
ONSTRUCTION, like many other industries in a free-enterprise system, has sizeable risk built into its profit structure [3]. From beginning to end, the construction process is
complex and characterized by a number of uncertainties. For
example, uncertainty about weather conditions, subcontractor
failure, and diffemt site conditions are typical risk variables that
exist in every construction project. As a result, many construction projects fail to achieve their time, cost and quality goals.
Most contractors, however, have developed a series of rules
of thumb to analyze and assess risk. These rules generally rely
on the contractors experience and intuition. Rarely do contractors quantify uncertainty and systematically assess the risks
involved in a project [l]. One reason might be the lack of a
rational, straightforward approach to combine all the facets of
risk systematically into a prioritized and manageable scheme.
However, as construction projects become more uncertain and
complex, intuition and tested rules of thumb often fail to anticipate and respond effectively to the extent of uncertainty and risk
in construction projects. Therefore, the need for a logical and
rational risk assessment procedure rather than tested rules of
thumb has increased [ 11.
Recently, a number of systematic models have been proposed
for use in the risk evaluation phase of the risk management
process. Kangari and Riggs [8] classify these methods into two
overall categories: 1) classical models (i.e., probabilistic analysis); and 2) conceptual models (i.e., fuzzy set analysis). Examples of classical models include Monte Carlo simulation [l] and
influence diagrams [4], [l]. An example of conceptual models is
fuzzy sets [8]. Kangari and Riggs [8] note that probabilistic
models suffer from two major limitations:
1) Some of these models require detailed quantitative inforManuscript received September 25, 1989; revised January 23, 1990. The
review of this paper was processed by Editor D. F. Kocaoglu.
The authors are with Tecno-Economics Division, Kuwait Institute for
Scientific Research, P.O.Box 24885, 13109 Safat, Kuwait.
IEEE Log Number 9037562.
11. THEANALYTIC
HIERARCHY
PROCESS
The AHP developed by Saaty [16] is a robust and flexible
multi-criteria decision analysis methodology. Formulating the
decision problem in a hierarchical structure is the first and
probably the most important step. The hierarchy should be
constructed so that elements at the same level are of the same
order of magnitude and must be capable of being related to some
or all elements in the next higher level. In a typical hierarchy,
the top level reflects the overall objective (focus) of the decision
problem. The elements affecting the decision are represented in
MUSTAFA
111. IDENTIFICATION
AND CLASSIFICATION
OF PROJECT
RISKS
-7
47
Njture
naM,
n
1
Environment
Society
Physical Risks
The typical risks that fall under this category are associated
with damage of a property or asset that the contractor owns or
has under his possession. Such risks include: damage to structure or property; damage to equipment and material; labor
injuries and death; and forcible prevention of work or access to
work.
48
23
I1
Acts of God
Financial B
Economic
Physical
Flood
Earthquake
Landslide
Fire
Wind Damage
. Lighting
- Weather
Damage to
Structure
Damageto
Equipment
Labor Injuries
Material and
Equipment Fire
and Theft
Risk Categories In a
Construction Project
Inflation
Availability of
Funds From
Client
Exchange
Rate
Fluctuation
Financial
Default of
Subcontractor
NonConvertibility
,
. Changesin
l a w s and
Regulations
War and
Civil Disorder
- Requirement
for Permits
and Their
Approval
Pollution and
Safety Rules
. Expropriation
- Embargoes
Incomplete
Design Scope
Defective
Design
- Errorsand
Omissions
- Inadequate
Specifications
- Design
Changes
Labor Dispute
and Strike
Labor
Productivity
Different Site
Conditions
Defective
Work
Equipment
Failure
Design Risks
Risks normally incurred by the design professional include
defective design, ambiguous specifications and plans, errors and
omissions in design, inaccurate geological and geotechnical exploration, and interaction of design with methods of construction.
IV . APPLICATION
We now give an application of the AHP to assess the riskiness
of an international construction project: The Jamuna Multipurpose Bridge in Bangladesh [I].
Project Background
The project involves constructing a 4 760-m long span across
the Jamuna river. The bridge will have multiple purposes: 1)
MUSTAFA AND AL-BAHAR: PROJECT RISK ASSESSMENT USING ANALYTIC HIERARCHY PROCESS
49
50
Assess the R
I
Constructing a Bridge
Project
GOAL
FACTORS
LEVEL OF
RISK
Total Risk
Legend
F1 : Financialand Economic Risks
F2 : Political Risks
F21 : Embargoes / expropriation
~ 2 :2Changes in Local ~ W S
F31:Eanhquakes
F32 : Water Damage and Floads
F33 : Soil Subsidence and
Collapse
TABLE I
JUM~MENTS MATRIX
AND WEIGHTS
OF FACTORS
With
Respect
to Goal
F1
F2
F3
Relative
Importance
F1
F2
F3
1
113
116
3
1
115
6
5
1
0.635
0.287
0.078
PRIORITIES
OF FACTORS.
SUB-FACTORS.
AND LEVELS
OF RISK
Factors
F1
F2
F3
Sub-factors
High
Levels of Risk
Medium
Low
0.099
0.031
0.020
0.041
0.121
0.271
0.005
0.017
0.030
0.008
0.019
0.055
0.040
0.147
0.018
0.005
0.015
0.002
0.035
0.010
0.004
0.002
0.005
0.001
0.235
0.364
0.401
0.635
F11
0.150
F12
0.433
F13
0.052
0.287
F2 1
0.082
F22
0.205
0.078
F3 1
0.022
F32
0.049
F33
0.007
V. SUMMARY
AND DISCUSSION
In this paper, we have investigated the subject of risk assessment in construction projects. A scheme of classifying the
variuos sources of risk has been developed. The AHP has been
introduced and applied in assessing the riskiness of constructing
The Jamuna Multipurpose Bridge. Risk factors significant to this
project are identified and incorporated in this assessment. Results show that the project is an overall low risk project.
51
MUSTAFA AND AL-BAHAR: PROJECT RISK ASSESSMENT USING ANALYTIC HIERARCHY PROCESS
1.oo
0.90
0.80
0.10
0.001
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8 0.9
Financial Risks
REFERENCES
[l] J. F. AI-Bahar, Risk management in construction projects: A
systematic analytical approach for contractors, Ph.D. dissertation, Department of Civil Engineering, University of California,
Berkeley, 1988.