Comparison Cost Concreting
Comparison Cost Concreting
Comparison Cost Concreting
S. NO. DESCRIPTION
UNIT QUANTIT
IRCON
Y FROM Accepted
C.H-(111RATE
117KM)
562
3440
1173
3767
5913
6022
56962.1
CUM
341.44
CUM
1115.58
CUM
898.87
CUM
1399.55
CUM
279.23
RMT
149.09
1933280
2760.6
1551457
2933
1648121
4418691
3023.018
3546000
3211
3766934
35608086
4832.655
28575489
5134
30355893
41960057
33672946
35770949
0.00
0.00
0.00
0.00
0.00
Shutteri Departm
ng
ental
Placing
Rate
(Labour (Rs/M3)
) Cost
(Rs/M3)
G=A+B+
C+D+E+F
2284
365
176
100
105
120
2854
2624
365
176
150
800
120
3939
3051
365
176
150
600
120
4166
reak up
AMOUNT AS
PER DEPT
RATE
1603817
2283
365
176
175
270
4620139
2623
365
176
125
270
24635760
3051
365
176
125
825
30859716
AMOUNT AS
PER Contractor
RATE
T=P+Q+R+S
+T+U
3093
1738266
3383
3968259
4366
25816158
31522683
Rate analysis as
sr. no.
1
Sand
Consu
mption
component
labour
PCC M-15
Mass CC M-20
RCC M-30
RCC M-35
RCC M-40
Machinaries
PCC M-15
Mass CC M-20
RCC M-30
RCC M-35
RCC M-40
shuttering placing
PCC M-15
Mass CC M-20
RCC M-30
RCC M-35
RCC M-40
Admixture
RCC M-30
RCC M-35
RCC M-40
Sand 0.48 cum /per cum con. Ave. lead 10 kms. (to & fro)
Rate loader Rs. 4025 for one day (4025/ 4x 7 tripx14 cum per trip= Rs. 10.26 per cum)
Diesel for loader = 15 lit per hr. x10 hrs. = 150 litx Rs.58 per lit/
4x7x14 = Rs. 22.19 /- cum
+ Royalti Rs. 35 per cum
+ Hywa 4 nos. (4 hywa @ rs.1725 per day = rs.6900 per day, 7 trips , = 6900/4 x7x14 = 17.60 /- per
cum + diesel ave. 10 km lead @ 2km/lit.= 4 nos. x7 trip x 5 lit diesl @ rs. 58 = Rs.8120 /7x4x14 cum =
Rs.20.71 per cum. Total Rs. 105.76 cum ) ( 105.76/35.24 = Rs.3.00 cft) )
PCC M-15
@ 0.434 cum /per cum of CC Rs. 140.52 per cum
Mass CC M-20 @ 0.468 cum /per cum CC Rs. 140.52 per cum
RCC M-30 @ 0.47 cum per cum Rs. 148.84 per cum
RCC M-35 @ 0.51 cum/ per cum of cc Rs. 148.84 per cum
RCC M-40 @ 0.51 cum/ per cum of cc Rate Rs. 148.84 per cum
For Aggregate 20 mm at crusher @ Rs.18 per cft ( rs. 635.18) royalti - Rs.120 per cum, transportation
Rs.13 per cft (Rs. 458.77 cum) + CST 5 % = Rs. 1274.65 per cum ( Rs.36.17 per cft )
For Aggregate 40 mm - Rs.16 per cft ((Rs.563.84 cum) +120 royalti+ Rs.458.77 carting +5%CST
(rs.57.13)= Rs.1199.74 per cum
For Aggregate 10 mm Rs. 16 per cft i.e. Rs. 1199.74 per cum
For Aggregate 6 mm Rs. 6 per cft i.e.Rs. Rs.211.44 per
cum
PCC M-15
@ 0.89 cum /per cum of CC Rs. 1199.75 per cum
Mass CC M-20 20 mm @ 0.59 cum @ Rs.1274.65 + 10 mm - 0.28cum @ 1199.74
RCC M-30 20 mm @ 0.59 cum @ Rs.1274.65 + 10 mm - 0.28cum @ 1199.74
RCC M-35 20 mm @ 0.59 cum @ Rs.1274.65 + 10 mm - 0.28cum @ 1199.74
RCC M-40 20 mm @ 0.59 cum @ Rs.1274.65 + 10 mm - 0.28cum @ 1199.74
water 12000 lit in Rs.1000. reqd 42 lit per cum so in rate is 1000/12000*42
add Cement for M-15 i.e. 275 kg i.e. 5.5 bag @ Rs.210 per bag = Rs. 1155
add Cement for M-20 i.e. 350 kg i.e. 7 bag @Rs. 210 bag = Rs.1470
add Cement for M-30 i.e. 405 kg i.e. 8.1 bag@210 = Rs. 1701
add Cement for M-35 i.e. 420 kg i.e. 8.4 bag @210 = Rs.1764
add Cement for M-40 i.e. 435 kg i.e. 8.7 bag @210 = Rs.1827
for back to back - add (3%deptt+ 3%Estb+ 5%profit+2%WCT+2 %Itax+1 % cess +2.25%Gawar
Then
in foundation
In foundation
Above foundation
supersturture bed block, deck slab etc.
qty
amount to be
paid by IRCON
as discussed
others
cum
cum
cum
cum
cum
100
150
150
150
150
cum
cum
cum
cum
cum
364.17
364.17
364.17
364.17
364.17
cum
cum
cum
cum
cum
120
715
715
715
1200
cum
cum
cum
119.07
123.49
127.89
cum
60.98568
65.76336
69.9548
75.9084
75.9084
1067.7775
1087.9707
1087.9707
1087.9707
1087.9707
3.5
12705
23100
1365
41475
3439.83
3767.38
6022.31
6271.25
43703040.15
87026478
8220453.15
260100093.75
2871.43318
3856.40406
4210.6655
4284.0391
4836.4391
399050065.05
+1 % cess +2.25%Gawar+1%add.gawar+ 0.55% bankchargesetc.= 19.75%)
Mix
Qty as
Rate accepted amount
design per LOA as per LOA
A
M-15
M-20
M-30
M-35
M-35
M-40
B
12705
23100
565
800
40975
500
C
D=BXC
3439.83 43703040.15
3767.38
87026478
6022.31
3402605.15
6022.31
4817848
6271.25 256964468.75
6271.25
3135625
399050065.05
over head
expenditure as
above 19.75%
E = C*19.75%)
679.366425
744.05755
1189.406225
1189.406225
1238.571875
1238.571875
F = (C- E)
2760.463575
3023.32245
4832.903775
4832.903775
5032.678125
5032.678125
as worked out
for pck1
amount
458.12
634.32
0.5963
0.2937
36481558.5519
89082933.786
5747558.4075
177680521.673
2284
2624
3051
308992572.42
45576404.4316
354568976.85
add for extra for
M-35 and M-40
as IRCON
mentioned
common rate
G
0
0
0
73.3736
0
552.4
construction
7% contrctors
cost as worked profit +1 % Itax
out above
J
2871.43318
3856.40406
4210.6655
4284.0391
4284.0391
4836.4391
K =J*8%
229.7146544
308.5123248
336.85324
342.723128
342.723128
386.915128
Expected offer
rates from
Contractors
amount
L=J+K
M
3101.1478344 39400083.24
4164.9163848 96209568.49
4547.51874 2569348.088
4626.762228 3701409.782
4626.762228 189581582.3
5223.354228 2611677.114
334073669
O=BXN
176.36
176
2A-1-a
1.5 KM LEAD
4025 day
Disel
150 lit
HYWA-2NOS
Disel
3450 day
1.5
500.00
59.00
500.00
59.00
DEWATERING
BACKFILLING
LOADING JCB
DISEL
HYWA-2NOS
Disel
1.5 KM LEAD
1150
500.00
0.0875
59.00
3450 day
1.5
Total
500.00
59.00
2A-1-B
1.5 KM LEAD
4025 day
150 lit
HYWA-2NOS
Disel
3450 day
1.5
300.00
59.00
300.00
59.00
DEWATERING
Total
2A-1-c
DISEL
Pocklen
Disel
1.5 KM LEAD
1150
200.00
0.0875
59.00
4025 day
150 lit
HYWA-2NOS
Disel
3450 day
1.5
200.00
59.00
200.00
59.00
DEWATERING
Total
PLANT
DG
500
100.00
0.28
59.00
DISEL
9200 day
TM -4 NOS
100.00
Disel
885 RS
6.00
HANDY
250
6.00
1666.667
100.00
0.35
59.00
LOADING JCB
DISEL
2A-2
P.C.C M15
Item name
Unit
Rate
5.500
Bags
240.00
40MM
31.440
cft
35.87
SAND
0.434
CUM
239.99
labour cost
1.00
CUM
100.00
SHUTTERING cost
1.00
CUM
110.00
1.00
CUM
365.00
CEMENT
Total
2A-3
R.C.C M20
Item name
qty.
Unit
Rate
7.000
Bags
240.00
20MM
28.287
cft
36.92
SAND
0.468
cum
239.99
labour cost
1.00
CUM
200.00
SHUTTERING cost
1.00
CUM
800.00
1.00
CUM
365.00
CEMENT
Total
BOX CULVERT/ROB/RUB
2A-4
GRADE M-35
QTY.
UNIT
CEMENT
8.70 Bags
SAND
0.47 cum
RATE
240.00
239.99
20MM
19.07 cuf
36.92
10MM
12.72 cuf
31.67
ADMIXTURE
labour cost
3.05 LIT.
1 CUM
42.00
200.00
SHUTTERING cost
1 CUM
600.00
1 cum
365.00
2A-5
GRADE M-40
QTY.
UNIT
CEMENT
8.92 Bags
SAND
0.51 cum
RATE
240.00
239.99
20MM
18.31 cuf
36.92
10MM
10.95 cuf
31.67
ADMIXTURE
3.12 LIT.
42.00
labour cost
1 CUM
150.00
SHUTTERING cost
1 CUM
1,200.00
1 cum
365.00
2A-6
QTY.
UNIT
CEMENT
8.70 Bags
SAND
0.51 cum
RATE
240.00
239.99
20MM
18.31 cuf
36.92
10MM
10.95 cuf
31.67
ADMIXTURE
3.05 LIT.
42.00
labour cost
1 CUM
SHUTTERING cost
1 CUM
1 cum
365.00
1 RMT
5800
1.13 CUM
3726.09
2B-1a/b/c
STEEL STRUCTURE
QTY.
UNIT
RATE
STEEL
1.00 MT
40,000.00
DESIGNING
1.00 MT
4,000.00
1.00 MT
15,000.00
ERECTION
1.00 MT
PAINTG
1.00 MT
5,000.00
2000
FINAL AMOUNT
2B-5
FE500
QTY.
UNIT
RATE
STEEL
1000.00 KG
40.00
CUTTING/ BENDING
1000.00 KG
5.00
10.00 KG
67.00
GI BINDING WIRE
TOTAL FOR BASIC RATE
FINAL AMOUNT
2C-2
FILTER MEDIA
QTY.
UNIT
RATE
METAL
0.50 CUM
1,214.36
SAND
0.35 CUM
239.99
MOOROM
0.15 CUM
#REF!
COMPACTION
1.00 CUM
12.00
FINAL AMOUNT
2C-4
STONE PITCHING
QTY.
UNIT
RATE
STONE
1.00 CUM
585.00
MORTAR 1:4
0.16 CUM
2,060.00
LABOUR
1.00 CUM
100.00
FINAL AMOUNT
2C-8
SAND RATE
QTY.
UNIT
RATE
SAND
3.26 CUM
700.00
ROYALTY
1.00 CUM
25.00
LABOUR
FINAL AMOUNT
IN CUM
IN CFT
METAL
20MM
AGGRIGATE
1 CUM
883
ROYALTY
1 CUM
155
HYWA-1NOS
1000 TRIP
14.00
Disel
1855
14.00
TAX
METAL
5 PERCENT
10 MM
AGGRIGATE
1 CUM
706.4
ROYALTY
1 CUM
155
HYWA-1NOS
1000 TRIP
14.00
Disel
1855
14.00
TAX
METAL
5 PERCENT
40 MM
AGGRIGATE
1 CUM
847.68
ROYALTY
1 CUM
155
HYWA-1NOS
1000 TRIP
14.00
Disel
1855
14.00
TAX
METAL
5 PERCENT
DUST
AGGRIGATE
1 CUM
282.56
ROYALTY
1 CUM
155
HYWA-1NOS
1000 TRIP
14.00
Disel
1855
14.00
TAX
5 PERCENT
500 CUM
PC RENT
500
17.70
6.90
8.85
4025 DAY
15 lit/h
10 h
HYWA
2 NOS
10 CUM
2 KM/Lit
RENT
1.5 Km
10.00
2.30
500
5.16
6.90
8.85
5 LIT/HOUR
HYWA
2 NOS
10 CUM
2 KM/Lit
7
RENT
1.5 Km
74.71
DAY
PER CUM
13.42
300 CUM
PC RENT
300
29.50
11.50
8.85
4025 DAY
15 lit/h
10 h
HYWA
2 NOS
10 CUM
2 KM/Lit
RENT
1.5 Km
10.00
73.27
M3/day
PER CUM
200
5.16
20.13
5 LIT/HOUR
PC RENT
44.25
17.25
8.85
10.00
100.48
200 CUM
4025 DAY
15 lit/h
HYWA
10 CUM
200
10 h
2 NOS
2 KM/Lit
RENT
1.5 Km
25.00
200 CUM
5.00
16.52
92.00
147.50
41.67
7 HOUR
hywa nos
4
59.00
2300 RS/DAY
2 KM/Lit
2.5 LIT/HOUR
15
2
16.67
20.65
365.00
IN FOUNDATION
Amount
1320.00
1127.76
104.16
100.00
110.00
365.00
3126.92
Amount
1680.00
1044.36
112.32
200.00
800.00
365.00
4201.68
T/ROB/RUB
AMOUNT
2,088.00
112.80
704.07
402.85
127.89
200.00
5 HOUR
600.00
365.00
4600.61
4600.61
RUCTURE
AMOUNT
2,140.80
122.40
676.01
346.79
131.12
150.00
1,200.00
365.00
5132.12
5132.12
AMOUNT
2,088.00
122.40
676.01
346.79
127.89
365.00
3726.09
3726.09
5800.00
4210.48
10010.48
AMOUNT
40,000.00
4,000.00
15,000.00
5,000.00
2,000.00
66000.00
AMOUNT
40,000.00
5,000.00
670.00
45670.00
45.67
AMOUNT
607.18
84.00
#REF!
12.00
#REF!
AMOUNT
585.00
329.60
100.00
-
1014.60
AMOUNT
214.99
1 TRACTOR
115 CFT
25.00
-
###
6.79
883
155
25 PER CFT
883 CUM
###
700
71.43
HYWA
132.50
1 NOS
14 CUM
2 KM/Lit
RENT
35 Km
62.10
1304.03
36.92
706.4
20 PER CFT
706.4 CUM
155
71.43
HYWA
132.50
1 NOS
14 CUM
2 KM/Lit
RENT
35 Km
53.27
1118.60
31.67
847.68
24 PER CFT
847.68 CUM
155
71.43
132.50
HYWA
###
1 NOS
14 CUM
2 KM/Lit
RENT
35 Km
60.33
1266.94
35.87
282.56
8 PER CFT
282.56 CUM
155
71.43
132.50
32.07
673.56
19.07
HYWA
14 CUM
1 NOS
2 KM/Lit
RENT
35 Km
1725
HOUR
1725
1725
HOUR
1725
Km
Km
HOUR
Km
3000
3000
3000
3000
0.002
0.003
0.6
0.067
0.9
3.6
8.478
5.68026
14.15826
7850
7850
MS PLATE SHUTTERING
L
Thick
weight
Kg/cum
total weight
in kg
1.2
0.002
7850
11.30
1.6
7.68
MS SHEET 2MM
0.6
at border - ISA
35X35X3
4.8
Total wt.
18.98
cost of material
(steel )
18.98
36.05
684.37
18.98
132.89
817.26
REPEATATION
( can be used )
30
TIMES
0.72
SQM
SQM
1 PLY
ISA 35X35X3
NUT BOLT
MAKING CHARGE
REPEATATION
RATE FOR (1.2x2.4)
RATE FOR
27.24
Rs. Per Sqm
PLY SHUTTERING
1.2
2.4
12.4
1.6
19.84
27.24
37.84
1549.44
715.232
50
158.72
2473.39
494.68
494.68
538
36.05
5 TIMES
2.88 SQM
1 SQM
171.76
Say
172
1
LENGHTH
WIDTH
DEPTH
WALL
BOTTOM SLAB
TOP SLAB
M-15 PCC
LENGTH OF PCC
WIDTH OF PCC
CONCRETE
SHUTTERING
SHUTTERING PER CUM
SHUTTERING COST PER
COST SHUTTERING PER
SAY RS PER CUM
M-35 FOR RAFT
CONCRETE
SHUTTERING
SHUTTERING PER CUM
SHUTTERING COST PER
COST SHUTTERING PER
SAY RS PER CUM
M-35 FOR WALL
CONCRETE
SHUTTERING
SHUTTERING PER CUM
SHUTTERING COST PER
COST SHUTTERING PER
SAY RS PER CUM
M-35 FOR TOP SLAB
CONCRETE
SHUTTERING
SHUTTERING PER CUM
SHUTTERING COST PER
COST SHUTTERING PER
SAY RS PER CUM
SQM
CUM
SQM
CUM
SQM
CUM
SQM
CUM
3X3
2X2
5X5
4X4.5
23.85
4
4
0.45
0.45
0.45
0.15
24.15
5.2
18.84
8.81
0.47
200
93.49
19.85
3
3
0.35
0.35
0.35
0.15
20.15
4
12.09
7.25
0.60
200
119.85
15.85
2
2
0.35
0.35
0.35
0.15
16.15
3
7.27
5.75
0.79
200
158.10
27.85
5
5
0.5
0.5
0.5
0.15
28.15
6.3
26.60
10.34
0.39
200
77.70
25.85
4
4.5
0.45
0.45
0.45
0.15
26.15
5.2
20.40
9.41
0.46
200
92.22
94.00
121.00
159.00
79.00
93.00
0.45
52.59
25.88
0.49
200
98.40
0.35
25.71
16.49
0.64
200
128.26
0.35
14.98
12.99
0.87
200
173.38
0.5
83.55
33.85
0.41
200
81.03
0.45
57.00
27.68
0.49
200
97.11
99.00
129.00
174.00
82.00
98.00
0.45
66.54
295.74
4.44
200
888.89
0.35
31.96
182.62
5.71
200
1142.86
0.35
14.42
82.42
5.71
200
1142.86
0.5
111.40
445.60
4.00
200
800.00
0.45
83.75
372.24
4.44
200
888.89
801.00
890.00
0.45
52.59
121.28
2.31
250
576.52
0.35
25.71
76.04
2.96
250
739.47
0.35
14.98
44.69
2.98
250
745.83
0.5
83.55
173.10
2.07
250
517.95
0.45
57.00
131.08
2.30
250
574.90
578.00
740.00
747.00
519.00
576.00
171.72
442.89
2.58
83.37
275.14
3.30
44.38
140.09
3.16
278.50
652.55
2.34
197.75
530.99
2.69
TOE WALL
LENGTH
STEM HEIGHT
TOE/ HEEL
TOE/HEEL THICK
STEM WIDTH
200
660.05
200
631.32
200
468.62
200
537.02
517.00
661.00
632.00
470.00
538.00
1
1.05
1.35
0.3
0.45
200
515.83
0.41
0.6
1.48
200
296.30
297.00
0.47
2.10
4.44
200.00
888.89
890.00
1
0.6
1
0.15
0.2
SQM
CUM
0.18
0.4
2.22
200
444.44
445.00
SQM
CUM
0.30
4.00
13.33
200.00
2666.67
2668.00
WING WALL
LENGTH
STEM HEIGHT
TOE/ HEEL
TOE/HEEL THICK
STEM WIDTH
1
3
1.8
0.45
0.45
0.81
0.9
1.11
200
222.22
223.00
1.35
6.00
4.44
200.00
888.89
890.00
3.52
14.00
3.98
200.00
796.02
797.00
12.3
8.7
1.8
192.62
75.6
0.39
200.00
78.50
79.00
12.3
8.7
1.8
CONCRETE
SHUTTERING
SHUTTERING PER CUM
SHUTTERING COST PER SQM
COST SHUTTERING PER CUM
SAY RS PER CUM
192.62
75.6
0.39
200.00
78.50
79.00
ing + deshuttering
6X4
23.85
6
4
0.55
0.55
0.55
0.15
24.15
7.4
26.81
9.47
0.35
200
70.62
72.00
103.00
0.55
93.13
34.05
0.37
200
73.11
74.00
109.33
0.55
76.08
276.66
3.64
200
727.27
728.00
932.83
0.55
93.13
177.15
1.90
250
475.51
477.00
262.35
487.85
1.86
606.17
200
371.91
373.00
531.83
S. DESCRIPTION
NO.
1A
Earth work in
excavation by
mechanical means
(Hydraulicexcavator) in
cutting, in formation,
trolley refuges, side
drains, yard drains,
catchwater drains, etc.
including leading
usable cut spoils and
making formation in
filling using the cut
spoils (as per
specifications of Item 2
below ), site
Soil
excluding
rock out
clearances,
setting
and
demarcation,
Rock not requiringlift,
descent,
blasting loading,
unloading,
tools &
Hard Rock requiring
plants,
all
taxes,
blasting, but blasting
bailing/
pumping
out to
of
not permitted
hence
water
and
all
incidental
be excavated by
charges
chisellingas per
specifications of Item 1
above, disposing off
surplus unusable cut
Earth work in filling
spoils with all lead as
in Embankment Fill
per directions of the
and Top Layer off or
engineer, and top and
mation including trolley
side dressing to provide
refuges, etc with earth
final formation as per
of approved quality as
designed profile. The
per RDSO Guidelines
rate shall not include
and specifications for
cutting of trees with
Design of Formation For
girth
above
30CM ,
a)With
contractor's
Heavy Axle
Load, Nov
which
shall
be
paid
earth
of approved
2009 for
25T Axle Load
separately.
quality
and SQ2/ SQ3
(using SQ1/
Note-1.Rock
spoilsout
such
specification
soil with CBR from
value of 3
asstones
,boulders,
side
railway
land
or
more
in Lower
pebbles, gravels etc
Embankment Fill and
available from
using either SQ1 soil
excavation, if are found
with CBR value of 4 or
suitable for use in
more generally but not
works as per required
less than 3 in isolated
specification seven
cases in Top Layer of1
after modification set
meter thickness or
c.,can be used free of
SQ2/SQ3 soil with CBR
cost but the legally
value of 6 or more
payable royalty and
generally but not less
taxes are to be paid by
than 5 in isolated cases
the contractor to the
in Top Layer of 0.5
concerned authorities.
a)
b)
c)
a)
UNIT
QUANTIT
Y
RATE
AMOUNT
RATE
CUM
903151
104.4
94288964.40
38.50
CUM
541891
154.14
83527078.74
90.00
CUM
361261
328.61
118713977.21
130.00
CUM
4903218
126.12
618393854.16
80.00
EACH
RMT
452
271.16
122564.32
271.16 SOR
27300
13.31
363363.00
6 L.S.
15750
257.15
4050112.50
267.87
Turfing /planting,
including all lead and
lift ,and watering as
required until properly
rooted, with
Note-Initially payment
of only 40% will be
made. Balance 60% will
be paid only after
3months of
maintenance period if
the turfing is properly
rooted.
a)
a)
a)With GJ - Type 1
b)With GJ - Type 2
c)With GJ - Type 3
TOTAL SCHEDULE
"1A" =
SCHEDULE -1B
BLANKETTING WORK
838530
14.01
11747805.30
60 NADEEM
SQM
3150
26.62
83853.00
26.62 SOR
SQM
2100
28.73
60333.00
28.73 SOR
SQM
1050
37.84
39732.00
37.84 SOR
931391637.63
415152
373.46
155042665.92
404.02
155042665.92
291900
208.46
60849474.00
70.59
4725
220.4
1041390.00
69.37
15225
346.07
5268915.75
95.08
12705
3559.43
45222558.15
3320.93
23100
3898.37
90052347.00
4041.11
1365
6231.69
8506256.85
4077.34
41475
6489.29
269143302.75
4898.83
1575
7894.5
12433837.50
9956
42
7894.5
331569.00
9956
500
2869.11
1434555.00
2000
14
2869.11
40167.54
2000
2 431646.12
863292.24
250000 pandey
96460.97
192921.94
250000 pandey
50267.48
100534.96
125000 pandey
56
2060.88
115409.28
3000 pandey
NOS.
Conducting Dynamic
Load test in
NOS.
gonselected piles of
routine pile loadtest, all
as
per specifications
TOTAL
SCHEDULE
and
"2A"the
= direction of
Engineer-in-charge.
CSHEDULE -2B:
BRIDGE WORK
(STEEL ITEM)
Providing, Fabricating,
Trial
Assembly,Transporting
and launching in
position on piers/
abutments as per
drawing-duly applying
protective coating on
all parts of structural
steel of bridge
structure; complete
with contractor's own
steel (Confirming to
IS2062:
2011,E250(B0Quality),
all materials,
machineries, tools &
tackles, consummables,
energy/ power, all leads
and lifts, labour etc.
complete in all respect
(incluiding s hear studs
etc)except concrete
(incluiding its
reinforcement) item as
per approved drawings
& specifications,
relevant clauses of the
contract and RDSO
Guidelines. The
fabrication & erection
cost shall include all
the types of
stiffeners ,packings
,diaphragm, T&F bolts,
steel drifts, shop welds,
shop and field
rivets/bolts, templates,
jigs, fixtures, back up
supports, accessories
etc.The job includes
preparation of
fabrication drawings,
fabrication of steel
girders, erection of
girder sand launching in
position on
piers/abutments as per
drawing. The elements
should be Aluminium
metalized (aspercl. :
39.2.1 of RDSO ; B1
60397.59
120795.18
495717327.14
70000 pandey
Therateshallincludeallm
aterialtestings,preparati
onofQAPandgettingitap
provedbyRDSOoranyoth
eragencyasdecidedbyth
eclient.Nopartofthework
shallbepaintedorcoated,
packedordispatchedunti
lithasbeenfinallyinspect
edandapprovedbythein
spectingofficerasperQA
PTherateshallalsoinclude
thecostofapprovalbyRD
SO/anyotheragency as
decided by the client.
All other relevant guide
lines of (RDSO;B-1)
shall be followed. Rate
shall include all
activities for delivering
the end product except
bearings & RCC
(incluiding its reinfor
cement) which shall be
paid separately.
Note: Payment to be
made in stages as per
Technical
Specifications.
a)
b)
c)
MT
56
83502.09
4676117.04
66000.00
560
83502.09
46761170.40
66000.00
135
83502.09
11272782.15
66000.00
MT
Providing POT/POT-PTFE
bearing on piers and
abutments conforming
to relevant standard
codes including design,
manufacture, supply,
testing and fixing in
position true to line and
level as per drawing for
steel girders
a)
b)
MT
BEARING
CAPACIT
Y
7040
426.86
3005094.40
426.86 SOR
MT
BEARING
CAPACIT
Y
2640
426.86
1126910.40
426.86 SOR
230400
0.64
147456.00
0.8
2.228
86077.61
191780.92
86077.61 SOR
Elastomeric Bearings:
Providing, fitting and
fixing in position true to
line and level complete
CUCM
as per drawing and
approved Technical
specifications incluiding
all steel plates, fittings,
fixtures,
Rocker &scaffolding,
roller bearing:
material,
Supplying,labour
fitting&and
machineries,
fixing in position true in
transporting,
line and level loading.
complete
unloading,
storing,
etc.,
as per relevant
RDSO
as
a
complete
drawing and approved
job.Elastomeric
Techical Specifications
bearings
incluidingas
allper RDSO
drawings
scaffolding, material,
labour & machineries
etc.,
4515
56962.1
257183881.50
45670.00
324365192.81
55650
341.44
19001136.00
267.87
Providing Boulder
Backing/ Filter media
behind wing wall, return
wall, retaining wall with
hand packed boulders
& cobbles with smaller
size boulders toward
the back including
contractor's all
materials, lead, lift,
labour & other
CUM
incidental charges as
complete work in all
respect as per drawing
and specification as
directed by the
Engineer.
3150
1115.58
3514077.00
710.52
2625
898.87
2359533.75
685.00
AMOUNT OF
SCHEDULE "2C" =
2625
1399.55
3673818.75
1014.60
7875
279.23
2198936.25
267.87
12600
149.09
1878534.00
81
32626035.75
executed
SCHEDULEfor
"3A" =
successful
completion of the
work as deemed
necessary by the
Engineer, will be as
per USSOR- 2010 of
SECRailway.
105000000
105000000.00
105000000 SOR
ADD 32 %
QUOTED RATE
TENDER
DAVIATION
RATE
AMOUNT
50.82
50.82
45898133.82
-3.36
100.89
118.80
118.80
64376650.8
-3.36
148.96
171.60
171.60
61992387.6
-3.36
317.57
105.60
105.60
517779820.8
-3.36
121.88
271.16
122564.32
-3.36
262.05
7.92
7.92
216216
-3.36
12.86
353.58
353.58
5568940.46739131
-3.36
248.51
79.20
79.20
66411576
-3.36
13.54
26.62
83853
-3.36
25.73
28.73
60333
-3.36
27.76
37.84
39732
-3.36
36.57
762550207.81
533.30
533.30
221401607.927441
-3.36
360.91
221401607.93
93.18
93.18
27197928.45
-3.36
201.46
91.56
91.56
432639.9
-3.36
212.99
125.50
125.50
1910722.275
-3.36
334.44
4383.62
4383.62
55693941.5901896
-3.36
3439.83
5334.27
5334.27
123221590.95834
-3.36
3767.38
5382.09
5382.09
7346558.27561523
-3.36
6022.31
6466.45
6466.45
268196120.814438
-3.36
6271.25
13141.92
13141.92
20698524
-3.36
7629.24
13141.92
13141.92
551960.64
-3.36
7629.24
2640.00
2640.00
1320000
-3.36
2772.71
2640.00
2640.00
36960
-3.36
2772.71
330000.00
330000.00
660000
-3.36
417142.81
330000.00
330000.00
660000
-3.36
93219.88
165000.00
165000.00
330000
-3.36
48578.49
3960.00
3960.00
221760
-3.36
1991.63
92400.00
92400.00
184800
508663506.90
-3.36
58368.23
87120.00
87120.00
4878720
-3.36
80696.42
87120.00
87120.00
48787200
-3.36
80696.42
87120.00
87120.00
11761200
-3.36
80696.42
426.86
3005094.4
-3.36
412.52
426.86
1126910.4
-3.36
412.52
1.06
1.06
243302.4
-3.36
0.62
86077.61
191780.92
-3.36
83185.4
60284.40
60284.40
272184066
-3.36
55048.17
-3.36
329.97
342178274.12
353.58
353.58
19676922.9847826
937.89
937.89
2954345.09771739
-3.36
1078.1
904.20
904.20
2373525
-3.36
868.67
1339.27
1339.27
3515589
-3.36
1352.53
353.58
353.58
2784470.23369565
-3.36
269.85
106.92
106.92
1347192
-3.36
144.08
32652044.32
105000000.00
105000000.00
105000000
WORKING
WORKING AMOUNT
RATE ON SITE
AMOUNT
SAVING
91118904.39
51.60
46606204.204
44512700.19
80720083.36
119.70
64864352.7
15855730.66
114725655.77
172.90
62462026.9
52263628.87
597604209.84
86.45
423883196.1
173721013.74
118446.6
360.64
163010.5456
0.00
351078
7.98
217854
133224.00
3914032.5
356.26
5611129.41032609
0.00
11353696.2
33.25
27881122.5
0.00
81049.5
35.40
111524.49
0.00
58296
38.21
80242.89
0.00
38398.5
50.33
52843.56
0.00
631933507.30
286486297.46
900083850.66
149832508.32
537.34
149832508.32
223078892.835982
0.00
223078892.84
0.00
58806174
93.88
27403973.3625
31402200.64
1006377.75
119.70
565582.5
440795.25
5091849
199.50
3037387.5
2054461.50
43703040.15
4030.68
51209766.7934586
0.00
87026478
5460.11
126128579.76454
0.00
8220453.15
5990.68
8177275.01137746
43178.14
260100093.75
6697.60
277782807.726737
0.00
12016053
13169.16
20741419.6804472
0.00
320428.08
13169.16
553104.524811926
0.00
1386355
1596.00
798000
588355.00
38817.94
1596.00
22344
16473.94
834285.62
332500.00
665000
169285.62
186439.76
332500.00
665000
0.00
97156.98
166250.00
332500
0.00
111531.28
3990.00
223440
0.00
116736.46
479062269.92
93100.00
186200
0.00
518492380.86
34714750.09
4518999.52
87780.00
4915680
0.00
45189995.2
87780.00
49156800
0.00
10894016.7
87780.00
11850300
0.00
2904140.8
567.72
3996775.552
0.00
1089052.8
567.72
1498790.832
0.00
142848
1.06
245145.6
0.00
114483.22
255068.6170564
0.00
185337.0712
248542487.55
60741.10
313466877.64
18362830.5
356.26
274246066.5
0.00
346164627.10
0.00
19825990.5831522
0.00
3396015
944.99
2976726.49997283
419288.50
2280258.75
911.05
2391506.25
0.00
3550391.25
1349.42
3542222.25
8169.00
2125068.75
356.26
2805564.70516304
0.00
1815408
107.73
1357398
458010.00
32899408.29
885467.50
31529972.25
1873975478.79
1752568816.39
243616812.242856
89013835
197658137
2282857600.63198
322086515.04
EXCESS
DIFFERENCE
0.00
0.00
0.00
0.00
65
44563.95
271.16
0.00
1697096.91
267.866304348
16527426.30
25
26.62
28.73
37.84
30474.99
21946.89
14445.06
18335954.10
268150343.36
73246384.52
404.01706087
73246384.52
-73246384.52
0.00
70.5875
0.00
90
0.00
150
7506726.64
3030.58512831
39102101.76
4105.3471264
0.00
4504.26892031
17682713.98
5035.7867132
8725366.68
9901.62056591
232676.44
9901.62056591
0.00
1200
0.00
1200
0.00
250000
478560.24
250000
125000
235343.02
111908.72
3000
69463.54
70000
74144861.03
-39430110.94
396680.48
66000
3966804.80
66000
956283.30
66000
1092634.75
426.86
409738.03
426.86
102297.60
0.8
69731.55
86077.61
25703578.95
45670
32697749.46
-32697749.46
1463160.08
267.866304348
0.00
710.520706522
111247.50
685
0.00
1014.6
680495.96
267.866304348
0.00
81
2254903.54
-1369436.04
200679852.64
121406662.40