Api 510 Q&a
Api 510 Q&a
Api 510 Q&a
Note: Choose only one answer which you think is most appropriate. Write your
answers in a separate answer sheet.
1.
a.
b.
c.
d.
Improvement in ductility
Increase of tensile strength
Increase of strength and ductility
None of the above
2.
a.
b.
c.
d.
Vessel engineer
Authorised inspector
Repair organisation
Operating personnel
3.
Vessels that are known to have a remaining life of over __________ years or
that are protected against external corrosion need not have insulation
removed for the periodic external inspection.
a.
b.
c.
d.
10
15
5
20
4.
a.
b.
c.
d.
5.
a.
b.
c.
d.
6.
a.
b.
c.
d.
7.
What climatic area may require a very active program for corrosion under
insulation?
Cooler dry locations.
Very cold locations with year round temperature less than 25F
Warmer, wet locations
Warmer dry locations
a.
b.
c.
d.
8.
a.
b.
c.
d.
Soil-to-air (S/A) interfaces for partially buried vessels are a location where
localized corrosion may take place. If the buried part is excavated for
inspection, how deep should the excavation be to determine if there is
hidden damage?
12 to 18 inches
6 to 12 inches
12 to 24 inches
6 to 18 inches
9.
a.
b.
c.
d.
10.
a.
b.
c.
d.
12.
a.
b.
c.
d.
1
2
3
All 4
13.
What type of repairs and procedures may the inspector give prior general
authorisation to continue (provided the inspector is satisfied with the
competency of the repair organization)?
Major repairs and minor procedures
Limited or routine repairs
Major alterations and re-ratings
Minor re-ratings and alterations
a.
b.
c.
d.
14.
a.
b.
c.
d.
a.
b.
c.
d.
16.
a.
b.
c.
d.
17.
a.
b.
c.
d.
18.
a.
b.
c.
d.
Oxygen
Water (i.e., Wet H2S)
Sulphur
a and c above
19.
a.
b.
c.
d.
20.
a.
b.
c.
d.
21.
a.
b.
c.
d.
The leak tightness of the relief valves is tested on the test block at a
pressure equal to:
Same as set pressure
90% of the set pressure
Same as reseat pressure
None of the above
The principal reason for inspecting a pressure relief device is to determine:
Condition of pressure relief device and if it is functioning properly
The remaining life of pressure relief device.
The spring coil diameter.
The body thickness.
Which of the following tests must be conducted on a valve as soon as it has
been received in the shop for inspection?
Visual inspection
Hydrotesting of valve body
Radiographic testing
Check set-pressure
22.
a.
b.
c.
d.
23.
a.
b.
c.
d.
24.
On the basis of this information, the long-term corrosion rate for the location
is:
Thickness
0.500
0.425
0.400
a.
b.
c.
d.
25.
a.
b.
c.
d.
26.
a.
b.
c.
d.
27.
a.
b.
c.
d.
28.
Year
0
5
10
A certain C.S. vessel which required impact testing was required to have
PWHT initially according to code requirement. After 10 years when repaired
by welding PWHT is to be carried out. Performing PWHT is found to be
impracticable. Which of the following is relevant (as per API-510)?
PWHT may be exempted, if proper NDE is carried out.
Carry out temper-bead welding as alternative to PWHT.
Carry out both hydro-testing and pneumatic testing in lieu of the PWHT.
Carry out preheating to minimum 200F
A cylindrical shell with thickness = 4.0, ID=96, S=17100 and E=0.85 and
C.A. = 1/8 showed metal loss of 1/4 in areas 8 on either side of the
longitudinal welds. You analysis of situation is:
Recalculate shell thickness tminimum considering E=1.0
The thinned area is on or within weld area hence (a) above can not be
adopted
Prepare repair procedure and restore the metal loss as per API -510
b and c above
Materials used for making repair by welding in carbon steel vessels shall
have the following limitations?
They shall meet the requirements stipulated in NACE Standard.
The carbon content shall not be over 0.35%
Welding repair shall be done by using only the GTAW process
All of the above
For non-continuous corrosive service with remaining life 25 years, external
inspection shall be performed not later than:
a.
b.
c.
d.
10 years
12.5 years
5 years
None of above
29.
a.
b.
c.
d.
For carrying out temper bead welding technique in lieu of PWHT, apart
from other requirements, which of the following is acceptable?
a.
The root and final pass of weld shall be radiographed.
Weld metal shall be deposited for second pass while the first pass below the
second pass is still not cooled down and its cooling rate is retarded due to
the heat of second pass
c.
After depositing each layers of the weld, the weld shall be DP checked.
d.
Both b and c
b.
31.
Calculate the remaining life and external insp. interval of a vessel given the
following data:
Actual thickness = 0.955 inch
Minimum thickness required = 0.755 inch
Thickness at previous inspection 5 years prior to present inspection = 1.025
inch
a.
20 years, 10 years
b.
14 years, 5years
c.
28 years, 10 years
d.
None of the above
32.
d.
a.
Spot radiography (RT-3)
b.
Full length radiography (RT-1)
c.
No radiography (RT-4)
Penetrant is sufficient if radiography testing is not available
33.
a.
b.
c.
d.
34.
a.
b.
c.
d.
35.
a.
b.
c.
d.
36.
A vessel which was inspected six years ago and had shell thickness =
0.870. As on today the thickness as reported by filed inspection is 0.786.
What was the corrosion rate over last six years?
10 mpy
12 mpy
14 mpy
none of above
If the vessel in above question has minimum permissible thickness = 0.618
for the present design conditions. What will be estimated remaining life of
the vessel if corrosion rate remains same?
10 years
12 years
14 years
None of above
For a vessel, remaining life is estimated as 22 years from now, next planned
internal and external inspection shall not be later than:
11 Years, 5 Years
10 Years, 5 Years
5 Years, 5 Years
None of the above
What is the maximum defect permitted on the convex surface of a welder
qualification bend test after bending?
a.
b.
c.
d.
37.
a.
b.
c.
d.
38.
inch
1/8 inch
1/16 inch
3/16 inch
b.
c.
d.
39. For Ammeter calibration for magnetizing equipment, the allowable tolerance
is:
a.
b.
c.
d.
40.
+5%
+10%
+15%
+20%
Which of the following are commonly preferred to know the process side
degradation of pressure vessels?
a.
b.
b.
c.
On stream inspection.
Internal inspection
External inspection as alternative to internal inspection
Any of above is OK
41.
For MT examination by Prod technique the magnetizing current
required depends on:
b.
42.
a.
b.
c.
d.
a.
Prod Spacing
Thickness of item under Inspection
c.
a & b above
d.
None of above
While deciding the governing thickness for crown portion for corroded 2:1
ellipsoidal head, API 510 stipulates that & crown thickness shall be
calculated:
According to relevant ellipsoidal dished head formula
According to code formula for spherical heads with head radius equal to 0.9
D, where D is shell dia meter.
Thickness of crown shall be same as knuckle thickness.
None of the above.
43.
For a vertical column, Int. dia. = 48'' and height (T-T) = 80ft, The vessel
MAWP is 60 psi. The vessel part MAWP for bottom dished head (2:1 Ellip
type) will be:
a.
b.
c.
94.6 psi
82.8 psi
95.5 psi
d.
44.
a.
b.
c.
d.
45.
None of above
How is hammer testing utilized?
As a preliminary survey for thinned areas.
As a independent test method for which ASNT Certification in NDT is available
As a important tool in the hands of the Authorized inspection only
To carry out Carpy impact test
Which of the following represent grouping of weld-metals in ASME
a.
b.
46.
a.
b.
c.
d.
47.
a.
b.
c.
d.
48.
a.
b.
c.
d.
49.
IX?
P Nos.
F Nos.
c.
S Nos.
d.
A Nos.
a.
b.
c.
d.
10 mm
8 mm
7 mm
9 mm
50.
a.
b.
c.
d.
51.
a.
b.
c.
d.
52.
a.
b.
c.
d.
53.
a.
b.
c.
d.
Less than 7
Greater than 7
It is 7
Greater than 10
54.
55.
a.
b.
c.
d.
56.
a.
b.
c.
d.
ANS.
A
2
3
4
5
6
7
8
9
10
11
12
B
A
C
B
D
C
D
C
B
B
C
13
14
15
B
C
C
16
17
REFERENCE
General
Knowledge
API 510, 4.4
API 510, 6.3
API 510, 6.4
API 510, 6.7
API 510, 6.2
API 572, 8.2.1
API 572, 8.2.9
IRE II, 202.064
API 510, 5.2
API 510, 5.7 (d)
ASME VIII, UG
16 (c)
API 510, 7.11
API 510, 5.2
IRE, Ch. II,
202.023
IRE, Ch. II, Page
12
API 572, Page 29
Q.
18
46
19
47
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
ANS.
C
REFERENCE
API 510, 5.7 (e)
B
B
B
C
B
C
B
C
B
B
B
B
B
C
20
21
22
23
24
25
26
27
28
A
D
C
B
C
B
D
B
C
API
API
API
API
API
API
API
API
API
576,
576,
576,
572,
510,
510,
570,
510,
510,
6.1
6.28
Scope
10.3.5
6.4
7.2.3.2
5.7 (d)
7.2.8
6.3
48
49
50
51
52
53
54
55
56
D
C
B
C
C
A
B
A
C
(b)
ASME VIII, UG - 99
BOK, 10 x 0.7 = 7 mm
API 572, 10.38
IRE II, 203.02
API 572, Page 31
IRE II, Page 10
API 572, 10.4.6
API 572, 10.3.2
API 572, 10.4.3