Quality Control Manual v2
Quality Control Manual v2
This is one of the two most important aspects of good Engineering construction. It is also
where unscrupulous Contractors usually want to cut corners or make fast deals. Little is it
realized that the cheapest cost they pay on a job is when the job is well done. Cutting
corners inevitably lead to loss of revenue to the Contractor, delayed completion and hand
over to the client.
Whatever the Contractors view on this, it is the primary duty of the Supervising Consultants
to see that good quality of materials and workmanship is achieved in every part
of the construction.
1.1 At Borrow pits - Sampling Of Materials from Borrow Pit (Gen Spec Clause
1041)
Trial pits in proposed borrow pit areas shall be dug from original ground level. Trial pits shall
be at least one metre by one metre in size, dug to such a depth that the full extent of the
material intended for incorporation in the works is exposed.
Materials for testing shall not be taken from the spoil of the trial pit but shall be made up
of increments taken from each face of the pit, each increment to be a representative sample
of the entire depth of a horizon. The four increments shall be mixed three times and
quartered or riffled down to the size required for testing. Visual examination will be made to
ensure that sampling more than one horizon in any sample is avoided.
Borrow pits may not be opened unless tests performed on samples from them meet
relevant standards. The usual tests are:
Liquid limit Tests
Plasticity Tests
Classification Tests
Compaction CBR Tests at BS or WAS, AASHO/AASTO
Intended materials are:
Lateritic Fill Materials
Dredged Sand Fill Material
Trouble areas which may or not be reflected on the drawings are identified visually by
experience. These areas are swamps, unsuitable materials, rock outcrops, fissures etc.
Appropriate advice mostly from Quality Control Laboratory/Material Engineer must be given
to the Contractor on each of these areas. Any instructions given must be carefully
considered as they are likely to have cost consequences.
Experience also may show when fills are well compacted, but not in all cases they must be
cross checked by the tests to determine relative densities. Some of these tests include
but are not limited to:
Relative Densities in case of sub-grade, sub base, base course, dredged sand and or
stone base
Atterberg Limit
Unconfined Compression Test
Total voids of less than 12% if crushed stone (Note that Relative Density is no longer
acceptable for crushed stone as a method of determining the state of compaction)
Tensile Test in case of reinforcement
Concrete Cube Tests, Cement Tests, Slump Tests
Progress to the next layer must be prevented until approval is given by satisfactory test
results on a previous layer. Even when a layer passes the prescribed tests, attention must be
given to other often over sighted/ignored defects such as flaking, shaking, wheel-tracking,
roughness etc. The most pungent of Contractors excuse against the performance of tests is
the testing time. They usually do not want to be delayed until the results are out, especially
as the determination of moisture content in the laboratory takes about 24hrs. The answer
to this is to employ a speedy moisture tester, crossed checked later by actual moisture
content determination using oven method. On the other hand, a calibration curve may be
produced for the Speedy Moisture Tester. The Contractor may proceed on the basis of the
result of a Speedy Moisture Content Tester, but he owns the risk of removing the new layer
to re-compact the previous layer if the test subsequently fails. The Contractor MUST NEVER
be allowed to bring to the work materials that are below specification. To refuse them, from
experience from both International and Indigenous Contractors subsequently brings rancour
and uncharitable name calling.
2.3 Laboratory
To this end, If any Contractor is not able to provide the service, we have identified
reputable laboratories that can offer the required services. These are;
i. Lagos State Materials Testing Laboratory, Ojodu Berger.
ii. The University of Lagos Civil Engineering Department. and
iii. SPOAK Nigeria Limited; 23 Ibironke Crescent, Maryland, Lagos State.
3.1 INTRODUCTION
Simply explained, the topic means ensuring strict compliance with the relevant specifications
relating to the construction works so that an acceptable standard job is delivered at a
desirably minimum cost to the Client. To this end the oficer charged with the assignment of
controlling the quality must be knowledgeable about geotechnics and materials testing
procedure inclusive of related construction technology.
3.2 PRELIMINARIES/EARTHWORKS
Payment shall be made under this clause for any material removed as unsuitable soil only on
the written direction of the Engineers Representative provided such unsuitable material
could not have been discovered during the tendering period.
Measurement for this item shall be on the compacted backfill only and payment for this work
will be at the rates entered in the bill of quantities for earthworks.
3.2.5 Sub-grade/Filling
Having addressed areas confirmed to be either unsuitable or need to be cut to spoil, the
subsequent resultant replacement (i.e filling) will have to be carried-out with APPROVED
appropriate good-quality material and accorded adequate compaction. In case of high water
table sections, the use of granular materials (e.g sand) is advised for construction of
sub- grade.
2 2
than 55MN/m and the base course not be less than 60MN/m .
The acceptable equipment for this test is the Light Weight Deflectometer (LWD) machine
(i.e 300mm/10kg).
Conformit Remark
Ite Test Applie Support Approval
Reque Frequen y s
m Descriptio d Tools Documen DN
st cy
No n Officer ts C A NA
C
1 BS RE Confir Lab Every Gen Spec
Proctor/ m Test 2000m 6124
B.B. QC/ME
Heavy
Compacti Tech
on Suppo
2 Plasticity rt Confir Lab Every 6125,
m Test 2000m 6127,
Others 6180
3 Grading Confir Lab Every 6125,
m Test 2000m 6127,
6180
4 WAS/ Confir Lab Every 6181
AASHTO/ m Test 2000m
Compacti
on
5 CBR Confir Lab Every 6124,
m Test 2000m 6127
6 Field Confir Dynami Every 6127,
Density m Test c Plate/ 50m 6162
DCP/
Speedy
Moistur
e Tester
The relative density of hydraulics sand fill placed in embankment shall be as follows:
Table 2: Relationship between Compaction Plant and Laboratory Test: MDD and
OMC
Soil Types
Compact Gravelly
Heavy Clay Silty Clay Sandy Clay Sand
ion Sandy Clay
MDD OMC MDD OMC MDD OMC MDD OMC MDD OMC
B.S 2.5Kg 1554 26 1666 21 1842 14 1938 11 2067 9
B.S. 1810 17 1922 14 2051 11 2083 9 2211 7
Heavy
4.5Kg
2800KG 1522 21 1762 17 1826 16 2034 10 2147 8
S. W.
Rolle
Note!
B.S British Standard
S. W Roller Steel Wheel Roller
Sand fill placed by any method other than the hydraulic shall be compacted in layers by a
method approved by the Engineers Representative to a density of not less than 100% of
the maximum dry density obtained in the British Standard Compaction Test Vibrative system
of compaction is recommended.
In the case of hydraulic sand fill the Contractor shall construct all drains, ditches, spillways,
marginal bunds necessary for the proper protection of the works. Such drains, marginal
bonds etc., shall be constructed sufficiently in advance of the deposit of the sand fill, so as to
efectively drain and retain the sand fill and to prevent any of the material from flowing into
any harbours, creeks, canals, drains etc or from causing any damage or nuisance to persons
or property. The Contractor shall be responsible for any slip or settlements which may occur
during the construction of the sand fill or the bunds, chains, etc., and shall also be
responsible for same during the maintenance period. The Contractor shall make good such
slips and settlements to the satisfaction of the Engineers Representative.
The Contractor shall be responsible for the full and efficient drainage of water resulting from
the hydraulic sand fill operation and shall construct such open drains as may be necessary
to drain all surface and rainwater, so as to avoid all ponding. The Contractor shall make due
allowance for settlement and drying-out of the sand-fill and for the making good of same.
Before any hydraulic sand fill is commenced, the Contractor shall, in conjunction with the
Engineers Representative, survey the site and mutually agree on the surface levels, and
such agreement shall be recorded in writing by both parties. The levels shall be taken on a
grid with points at not exceeding 15 metres centres and the Contractor shall construct
concrete pilot- pillars to the satisfaction of the Engineers Representative to enable the grid
lines to be located during the filling operations. The Contractor shall construct sufficient
tell-tales, consisting of
50mm x 50mm x 10mm angle of adequate length with a flange of 900mm in diameter
fixed at one end, all in non-corrosive metal, to the satisfaction of the Engineers
Representative, to enable any subsidence of the original ground level to be measured. The
method of measurement of hydraulic sand fill shall be on the basis of the volume of
material placed as determined from the area filled and the depth of fill to the finished level
from the original ground level or the subsided original ground level, as applicable.
Hydraulic sand fill shall be done in layers as directed by the Engineer, but in any case
the thickness of such layers shall not exceed the limits stipulated as follows:
The finished level shall be as shown on the drawings or as directed by the Engineer, and
shall be agreed as the result of a joint survey carried out by the Contractor and the
Engineers Representative. A tolerance of 75mm above or below the finished level may be
permitted during pumping operations, but the same shall be made good by subsequent
grading or dozing to the satisfaction of the Engineers Representative and to the tolerances
stipulated for the sub-grade. Without limiting his commitments under the terms of the
contract, the Contractor shall be required to make good any normal expected settlement of
the original ground levels after completion of the sand fill. The Contractor shall be deemed
to have allowed for all the foregoing provisions in his rates and prices for sand filling.
Should the Engineer so desire the Contractor shall place stock piles of material in quantities
and areas as directed.
1. CLASSIFICATION TESTS
2 NO. LIQUID LIMIT TESTS
2 NO. PLASTIC LIMIT TESTS
2 NO. SIEVE ANALYSES TESTS
4 NO. BRITISH STANDARD COMPACTION TESTS
2 NO. LABORATORY C.B.R.TESTS AT THE SPECIFIED DENSITY AND MOISTURE CONTENT.
2. CONTROL TESTS
20 No In-situ Dry Density Tests.
Except where otherwise stated to the contrary, these tests shall be carried out as described,
or where no such description is given in accordance with the appropriate British Standard,
AASHTO and ASTM Standards.
The sieve analysis shall be carried out in accordance with the standards laid down in the
latest amended report of the Lagos Materials Testing Conference a copy of which shall be
made available to the Contractor on request, or as per the latest B.S 1377.
Normally, the minimum strength of such grade course materials shall not be less than
80% CBR value being determined at maximum dry density and optimum moisture content
un- soaked with either West African or Modified AASHTO compaction. However, where the
Engineers Representative considers it necessary on account of perched water-table or any
other reasons, he may specify that a C.B.R. value of 80% be obtained after at least 24 hours
soaking.
The tests listed below will normally be required to be carried out for each 2 kilometres of
Sub- grade course. The actual number and type of tests which will be carried out during the
construction of the works will be entirely at the discretion of the Engineers Representative
The Percent by weight passing the No 75 m sieve shall be less than but not greater than
35%. The material passing the 425 m sieve shall have a liquid limit of not more than 35%
and a plasticity index of not more than 12, as determined by American Society for Testing
Materials methods, serial designation D 432-39 and 424-39 respectively or as determined by
test No 2 or 2A and test Nos. 3 of B.S 1377 (1975). Prior to approval of the sub-base
material, a test section shall be constructed to the thickness shown on the typical pavement
section and compacted to 100 percent of maximum density. When the test section is
compacted to 100 percent maximum density at optimum moisture content, the sub-base
material shall be of such quality that it shall have the minimum CBR of 30% after at least 24
hours soaking. Once established that the sub-base meets the CBR quality requirement at
100 percent maximum density it shall be placed and compacted in the field to that density.
Modifie
Type of Liquid Plastic Insitu C.B.R Grading Remark
WASC d
Tests Limit Limit Density [%] s s
AASHTO
Classificati 4 4 2 2 - 4 2 Carry out
on either of
item 1 or
2
Laborator
y results
to be
Control - 4 - - 20 4 -
used as
control
values
3.3.17 Test for the Selection Of Laterite Sub-Base Course And Base Course
Materials
The following tests shall be carried out on all material proposed for use as sub-base
course and base course:
1. Plasticity Test.
2. Grading Test.
3. Density/Moisture Content Compaction Test.
4. Laboratory C.B.R. Test.
These tests shall be carried out as described in Section 1 of this specification.
The tests listed above will normally be required to be carried out for each 2 kilometres of
sub- base course and base course. The numbers and types of tests listed are, however,
given only as a guide to the Contractor for tender purposes and the actual number and
type of tests which will be carried out during the construction of the works will be entirely at
the discretion of the Engineers Representative:
V. Fine Aggregates
Fine aggregate known as binder material shall be materials passing sieve 5mm and
retained on 75m sieve. It may be sourced from river bed at location approved by the
Engineers Representative or the fines from crushed stone. It shall be free from vegetation or
other objectionable matter. Fine aggregate shall be clean without any clay content,
strong and
sharp. It shall be of such grading characteristic that when combined with coarse
aggregate, the composite material shall conform to the gradation and other requirements
specified in clause 2004 (1-3). Liquid limit and Plasticity Index requirements stated
herein shall apply to any aggregate component that is blended to meet the required
gradation and also to the aggregate in the compacted base course. The portion of fine
aggregate passing the 75 m sieve shall be either non-plastic or shall have liquid limit not
greater than 30% and Plasticity Index not greater than
6. This index test will only be applicable to materials for wet laying.
IX. The grading of crushed stone for use in crushed stone base course shall be
as follows:
Dry Process
75 mm to 12 mm or 50 mm -12 mm herein after referred to as coarse stone.
12 mm to dust hereinafter referred to as screening
Wet Process
The composite mixture of coarse aggregate and binder material proceed as hereinafter
specified shall conform to one of the applicable gradations shown in Table and shall not vary
from the low limit on one sieve to the high limit on adjacent sieve or vice versa, but shall be
uniformly graded from coarse to fine.
Gradation requirement specified herein shall apply to the completed base course after
undergoing the mixing placing compacting and other operations. The portion of the
aggregate passing No 75m sieve shall not be greater than one-third of the portion passing
the No. 425
m sieve. The aggregates shall continuously be well graded within the limits of Gradation A,
B. C, D or E as specified below. The methods of test used will be ASTM Standards C117.
C127, C128, C136 and D422. Sieves shall conform to ASTM Standard E.11 or BS sieve.
Table VI: Grading Envelope for Stone Base Course Wet Method (Gen Spec Clause 6252)
Sieve Percentage by weight passing square mesh sieve
Designation Grading A Grading B Grading C Grading D Opening
Grading E
75 mm 100 100 100 100 50 mm 100
Note: - The table is based on aggregate of uniform specific gravity, and the
percentages passing the various sieves may require appropriate correction by the
Engineer when aggregates of varying specific gravities are used.
The coarse stone shall then be regulated and compacted by not less than three passes of an
approved roller.
Successive uniform layers of screening 12mm to dust shall then be applied over the
surface and shall be vibrated into the interstices of the coarse stone by means of an
approved
vibrating plate compactor or other approved means. Screening may be spread by hand
shovel using a sweeping motion or by approved tailboard spreader attached to lorries. In
no case shall screenings be dumped on the surface in piles and spread there from. Great
care shall be taken to ensure that the screening are not applied either so quickly or so
thickly as to CAKE or bridge on the surface in a manner which prevents the filling of the
interstices or causes the vibrating or compacting equipment bearing directly on the coarse
stone. The addition of screenings and vibrating into the interstices of the coarse stone
shall continue until all the voids are filled in.
The surface of the crushed stone shall then be checked transversely and longitudinally
for level and camber and any indicated variations adjusted. The surface shall then be
sprinkled with water from a water browser and rolled with a smooth wheel roller having a
weight of roll of not less than 58 kilograms per centimetre. Voids in the Base-course which
occur during this process shall be filled by sweeping screenings into them.
The sprinkling, sweeping and rolling shall continue until all voids are filled with grout to the
satisfaction of the Engineers Representative.
The final surface shall be smooth and even, free from irregularities or loose material and
true to line and level having regard to the tolerances for base course finish specified
elsewhere herein.
3.3.21 Crushed Stone Base Course Laid By The Wet Process (Gen Spec Clause
6253)
When crushed stone Base course is to be laid by the dry or wet process the method of laying
and compacting shall be as follows:
The approved crushed stone, graded as specified shall be mixed with between 3% and 5% of
water as directed in a mixer of a type approved by the Engineers Representative.
The mixed material shall be protected from the rays of the sun during transit from the
mixer to the site in order to prevent loss of moisture due to evaporation and shall be laid by
a self- propelled asphalt finisher or other approved plant in layers of not less than 75mm
or more than 150mm thickness after compaction. During this operation care shall be
taken to avoid segregation.
Water can only be added to any wet laid stone base if it was discovered that evaporation
had taken place during rolling. The finished rolled stone base shall not have moisture less
than 3% or more than 5% by weight of dry aggregate.
Should any patchiness appear during compaction, areas deficient in fines shall be blinded
with screenings, watered, and rolled and areas showing an excess of fines shall be
removed and reconstructed with graded material to the satisfaction of the Engineers
Representative
The final surface shall be smooth and even free from irregularities or loose material and
true to line and level having regards to tolerances for Base-courses specified elsewhere
herein.
3.3.22 Preparation Of Crushed Stone Base Course To Receive Bituminous
Surfacing (Gen Spec
Clause 6258)
Crushed stone Base course laid by either the dry or wet shall be prepared for the addition
of bituminous surfacing as specified under the relevant parts of this section of the
specification. COMPACTION. Compaction of crushed stone Base Course shall be to the
satisfaction of the Engineers Representative
Thereafter, sharp sand or an equivalent crushed rock quarry fines is to be used to blind the
surface. A 2.5 tons roller is to be brought in to press down the grains of the fine aggregates.
Thereafter, this surface must either be brushed-clean or washed before applying tack-coat in
case of surface-dressing. Priming performs three major functions. It water-proofs the
surface, makes it dust-proof and provides a bonding surface.
Usually the tray-test exposes any related short-coming. The single-sized coarse
aggregate, that will have to come on board, must have undergone both sieve analysis and
aggregate crushing value (ACV) plus ten percent fines suitability tests and approved before
use.
The services of a chipping spreader, if engaged, will offer a good quality surface. Thereafter,
a
6 ton roller will have to press the grains of aggregates into the bitumen. The surface
is allowed to mature and not to be opened to trafic earlier than 24 hours.
II. Material
The materials used shall be those prescribed for the several parts which constitute
the finished work and shall conform with all the required for such materials as set out herein.
Aggregate
Coarse aggregate shall be the portion of the aggregate retained on the No. 5mm
opening sieve and shall be hard, clean and durable crushed igneous rock from a source to
be approved by the Engineer. The crushed stone shall be free from dirt or other
objectionable matter.
The coarse aggregate when tested by the methods described in B. S.812 shall have
properties not exceeding the following values.
Table VII: Aggregate Specification for Dense Bitumen Macadam, Asphaltic Base & Wearing
Courses
Pavement Course Aggregate Flakiness Absorptio
Crushing Index n
Dense Bitumen Macadam Base Value
30 35 Factor
1.5
Dense Bitumen Macadam Wearing30 35 0.5
Asphaltic Concrete Base course 30 35 0.5
course
Asphaltic Concrete Wearing Course 30 35 0.5
Fine aggregate shall be the portion of the aggregate passing the No. 5mm opening sieve and
shall be quarry fines produced from the crushing of igneous rock. They shall be composed of
clean, tough, rough surfaced and angular particles, free from lump or ball of clay, loam and
other deleterious substances.
Mineral filler shall consist of finely ground particles of hydrated lime, Portland cement or
other non mineral matter approved by the Engineer. It shall be free from foreign or other
objectionable material, and shall meet the following grading requirements:
Bitumen emulsion for tack coat shall be emulsion quick breaking type containing 30-
50% bitumen.
Suitable sizes of aggregate shall be stored in bins at each point where bituminous
materials are mixed. The bins shall be in such numbers and of such capacities as to ensure
that an uninterrupted supply of all the necessary sizes of aggregates are available at the
mixer.
If aggregates are stockpiled prior to their transference to the bins, the stockpiles shall be
formed on concrete floors laid to falls suficient to permit drainage at the base of
the stockpiles. Aggregates shall be handled to and from the stockpiles in a manner such that
they are not contaminated by the ground or by extraneous matter and also in a manner such
that segregation is prevented. In as much as possible the bins shall be covered to
prevent dampness of aggregate by rain.
Coarse and fine aggregates and aggregates from different sources shall be
stockpiled separately and if aggregates of different grading or from different sources are
stockpiled in close proximity the stockpiles shall be separated by partitioning.
All aggregates produced or handled by hydraulic methods and all washed aggregates shall
be stockpiled under cover for draining for at least 24 hours before use.
Material used as filler shall be stored in dry conditions to the satisfaction of the
Engineers Representative.
No material shall be used until it has been approved by the Engineer. Permission to use
material shall not be construed as an approval of its source nor any acceptance as continued
acceptance.
IV. Sampling
The Contractor shall provide equipment, labour and such trained staf as may be required by
the Engineer for carrying out the following tests on materials to be used in the manufacture
of hot asphaltic concrete in accordance with the following standards:
Grading tests on aggregates in accordance with the latest B. S. 812 - Sampling and testing
of mineral aggregate and fillers.
Hot extraction method BT 1 described in B.S. 598 (1974) - Sampling and examination of
bituminous road mixtures. The Contractor is to comply with the requirements of B.S. 598:
and to the need of providing results in duplicate.
Or
By reflux extractor method.
Aggregates shall be sampled and tested on delivery to the mixing plant and after each
extraction test and the result of each test shall be submitted to the Engineer or his
Representative within 24 hours of the sample being taken.
The number of such tests shall be adequate for proper control of the materials and shall
not be limited to those made on specified instructions of the Engineer or his Representative.
Samples of mixed materials shall be taken and tested during the first days mixing and
throughout the work to confirm that the grading and binder contents are as specified. Such
samples shall be taken either at the place and time of mixing or at the place of laying as
directed by the Engineer or his Representative. Samples for testing shall also be cut from the
surfacing as laid when directed by the Engineer or his Representative.
The frequency of sampling mixed materials shall be at least once per day or once for each
90 tonne of material mixed whichever is the more frequent. The result of each test on mixed
materials shall be submitted to the Engineer or his representative within 24 hours of the
sampling and any adjustment shown to be necessary shall be made immediately. Until such
adjustment have been made and until a certificate to the effect has been forwarded to
the Engineer or his representative no further batches or mixed material shall be made.
Independent sampling and testing may be carried out by the Engineer throughout the
contract period and for this purpose the contractor shall grant free access to the mixing
plant and storage depots, supply materials and provide every facility for the Engineer or his
representative to take sample whenever required.
In particular, throughout the contract, the Engineer will carry out control test on the plant
mix material using the marshal test apparatus.
A certificate is to be obtained from the supplier with each consignment of bitumen delivered;
stating the grade of material being supplied, and these certificates are to be handed to
the Engineers Representative.
If the Engineer so requires, the Contractor shall arrange for the testing in an approved
manner of all materials used throughout the contract to ensure that they are up to the
standard specified, i.e. aggregates, bitumen and such other materials as specified or decided
by the Engineer. The Contractor shall arrange for the testing of materials incorporated in
the works to ensure that they have been manufactured as specified, or as ordered by the
Engineer.
Whenever the Contractor intends to carry out any of the above tests, he shall give the
Engineers Representative sufficient notice to enable him, should he so wish, to be present
during the test.
Whenever the Contractor takes samples for testing, and where so directed he is to take
duplicate samples and hand them to the Engineers Representative. Such samples are to be
properly packed and labelled as directed.
The Engineers Representative shall be given the results in writing of all tests, as soon as
they are available, and in any case not later than 24 hours after samples have been taken.
The Engineer shall be supplied with all necessary equipment, material and labour to perform
any additional tests he may wish to carry out himself.
The cost of these tests including the provision of samples will be deemed to have been
included in the bill of quantities under the appropriate item.
V. Composition of Mixes
Asphaltic concrete prepared under these specifications shall be composed of
graded aggregate and asphalt cement within the limits set forth below. When plotted
graphically the aggregate grading shall lie on a smooth curve within the envelope.
The exact job-mix formula will depend on the nature and grading of the aggregate and
the grade of bitumen and will be determined by the Engineer using the marshall method of
mix design. For this purpose the Contractor shall supply to the Engineer without charge
adequate samples (in separate containers) of coarse and fine aggregates and bitumen
which he intends to use. The Engineer will, after testing, furnish the Contractor with the
exact job-mix formula, which will be within the specified limits.
Before any a concrete is laid, the Contractor shall produce sufficient dry mixes in the plant
and carry out sieve analysis to ensure that the correct grading is being obtained. In addition,
he shall produce a number of trial mixes to which the specified quality of bitumen has
been added. He will then carry out extraction tests on this material and further sieve analysis
on the aggregate in accordance with clause 6373 of the specification. The results of these
tests on both the dry and wet mixes shall be approved by the Engineer before any
surfacing is laid in the permanent works.
The job mix formula is liable to alternation by the Engineer Throughout the progress of
the work but at all times it will be within the specified limits.
XIII. Compaction
After spreading, the mix shall be thoroughly and uniformly compacted by rolling.
The initial breakdown rolling shall be done with three wheel smooth roller, followed by
intermediate rolling with high- pressure tyred pneumatic roller. During the rolling wheels
shall be kept moist with only sufficient water to avoid picking up material.
Heavy equipment or roller shall not be permitted to stand on finished surface until it has
thoroughly cooled. In the initial rolling the three-wheel smooth roller shall proceed on to the
fresh material with the rear or driven wheels leading. The rolling shall start as soon after
laying as conditions permit and when the material is still at a temperature of not less than
99C. The weight per unit width of the rear wheel shall be between 45-65 Kg per centimetre
width.
After the longitudinal joints and edges have been compacted rolling shall start
longitudinally at the sides and gradually progress towards the centre of the pavement,
except on super- elevated curves where rolling shall begin on the low side and progress to
the high side. Each pass of the roller shall overlap the preceding one by about one width of
the rear wheel. The roller should move at a slow but uniform speed not exceeding 8
kilometres per hour. The roller shall be in good condition, and capable of being reversed
without back lash, and the line of rolling shall not be suddenly changed or the direction or
rolling suddenly reversed, thereby displacing the mix. If rolling causes displacement of the
materials the affected areas shall be loosened at once with shovels or rakes and restored
to the original grade of loose material before being re-rolled.
The intermediate rolling shall be done with a pneumatic roller exerting compactive ground
pressures between 5.6-8.4 kg per sq. cm. The Contractor shall furnish to the Engineer
charts or tabulations showing the contact areas and contact pressures for the full range of
type inflation pressures and for the full range of tyre loadings for each type and size
compactor tyre furnished. The intermediate rolling shall follow the break down rolling as
closely as possible and while the mix is still at a temperature of 70C - 85C. Rolling shall be
continuous until the mix is thoroughly compacted and the density specified in clause 6381 is
achieved. Turning of pneumatic roller on the hot mix which causes undue displacement shall
not be permitted.
XIV. Joints
All joints shall be vertical, properly formed to the correct line and level; if necessary they
shall be cut back to achieve this. A template made to the shape of the true line and width
may be placed at each end of the construction joint line and width may be placed at each
end of the construction joint to create vertical straight finish. Joints in the surface course
should be staggered with those in the binder course and must be kept straight, when the
abutting lane is not placed the same day or if the edge of the first strip has been distorted
by trafic the joint shall be cut back to an even line and then be coated with bitumen before
laying the adjoining strip. All joints on completion are to present the same texture, density
and smoothness as other sections of the course.
When an approved rolling procedure has been established, each course will be sampled in
accordance with the above at the rate of one sample area for each 84 square metres placed
or one sample area every 2 hours (whichever is more frequent). Material which does not
achieve the required density will either be cut out and replaced or be further compacted
until the required density is obtained.
Accurate thermometer shall be incorporated in the heater to give a clear indication of the
bitumen temperature. Should the temperature be in excess of that specified, the
Engineers Representative may direct that this overheated bitumen be disposed of at the
Contractors expense.
Or
Alternatively rate of spray may be checked as follows: -
Check the initial and final quantity of cut back and record. The difference between initial
reading divided by the area sprayed can he used to check compliance with approved rate of
spraying.
Note: - Initial and final reading shall take place at same position.
The rate of spray of the bitumen shall be determined according to the type of base, type and
size of chippings which are to be used as detailed in the table given below, and the
Contractor shall carry out trial sections, as directed by the Engineers Representative to
determine the most appropriate rate of application of bitumen.
Table XVI: Size of Chipping and Rate of Spray of Bitumen
Immediately after spraying the surface shall be blinded with approved single size chipping
as specified. The chipping shall be distributed on the sprayed surface by means of
mechanical spreader or tailboard gritters so that a single layer of closely packed chipping is
obtained any bare or lean areas shall be made good by follow-on gang using hand blinding.
Rolling shall be carried out immediately after the chippings have been spread with
an approved roller weighing not less than 3,629 kilograms or more than 5,443 kilograms.
The minimum number of passes of the roller shall be used to press the chippings into the
film of bitumen. Two passes of the roller should generally be sufficient. Pneumatic tyred
rollers are preferable to smooth wheeled rollers.
Prior to the commencement of spraying a section of the road for the first coat a 2 metres
wide paper strip shall be laid over the end of the previous section. The bitumen sprayer shall
then commence its run from over this paper strip.
Final Surface Dressing
The finished surface of the carriageway shall be left as smooth as possible and the accuracy
of finish in the longitudinal direction shall not vary at any point by more than 6mm from
a 3 metre straight edge, placed in any position on the finished surface parallel to the centre
line. The transverse profile shall conform to the same accuracy, using a correctly shaped
template instead of the straight edge. The surface shall be evenly textured and show no
lean or fat areas and shall not have any low or flat spots where water will collect.
Wet Weather
No surfacing work shall be done in wet weather or when rain is imminent. Only dry chippings
shall be used.
Job-Mix Formula
The exact job mix formulae will depend on the nature and grading of the aggregate and the
type of bitumen. The exact job-mix formulae for the respective courses will be determined
by the Engineer.
Table XVII: PRIME COAT & TACK COAT [MC1 & S125]
For Priming Base M C-O or M C-I shall be used at the rate of 1.0 - 2.0
Litres/ sq.m
For Applying
emulsion
Tack Coat quick breaking type applied at the rate of 0.25 - 0.70
Litres/sq.m
Tack coat shall be applied in areas to take the binder
course if warranted by surface conditions and directed
by the Engineer Representative.
XVIII. Tests for Bitumen
The Contractor shall produce manufacturers test certificate if requested, otherwise the
Engineer may require the Contractor to carry out the following tests as described in
standard methods for testing petroleum and its products published by the Institute of
Petroleum, 26
Portland Place, London W.1. Penetration of bitumen IP.49/56
Soluble bitumen content: bitumen and asphalt IP.47/55
Flash-point by means of the elevated apparatus IP.36/55
Specific gravity IP.59/57. Method C
Specific gravity of liquids or solids pycnometer method. Specific gravity of liquids or solids
method F.
The determination of viscosity by the standard tar viscosimeter or the furol viscosimeter
may
also be required by the Engineer.
The cost of carrying out these tests if required by the Engineer shall be deemed to be
included
in the tendered rates and prices.
Workmanship
XXVI. Bitumen Macadam Mixing plant
The material shall be mixed in an approved mixer of batch or continuous type from which
mixed materials can be delivered and laid hot the mixing plant shall be maintained in
good working condition and shall be subject to inspection by the Engineers Representative.
The weighing measuring and recording apparatus shall be checked at frequent intervals and
maintained in perfect adjustment throughout the contract.
The asphaltic concrete shall be laid in two courses surface and binder courses with or
without wedge of levelling course or any combination of these as shown on the drawings.
Unless specified in volume-III or on the drawing, the compacted thickness or each course
shall not be less than 60mm for the binder and 40mm for the surface course. The
compacted thickness of any single constructed course shall not exceed 75mm binder or
levelling course or 60mm for surface course.
Table XX: Aggregate Specification for Dense Bitumen Macadam, Asphaltic Base and
Wearing Courses
rse Aggregate Crushing Value Flakin Absorption Factor
ess
Index
Dense Bitumen Macadam Base 30 35 1.5
Dense Bitumen Macadam Wearing 30 35 0.5
course
Asphaltic Concrete Base course 30 35 0.5
Asphaltic Concrete Wearing Course 30 35 0.5
Fine aggregate shall be the portion of the aggregate passing the No. 5mm opening sieve and
shall be quarry fines produced from the crushing of igneous rock. They shall be composed of
clean, tough, rough surfaced and angular particles, free from lump or ball of clay, loam and
other deleterious substances.
Mineral filler shall consist of finely ground particles of hydrated lime, Portland cement or
other non mineral matter approved by the Engineer. It shall be free from foreign or other
objectionable material, and shall meet the following grading requirements:
Suitable sizes of aggregate shall be stored in bins at each point where bituminous
materials are mixed. The bins shall be in such numbers and of such capacities as to ensure
that an uninterrupted supply of all the necessary sizes of aggregates is available at the
mixer.
If aggregates are stockpiled prior to their transference to the bins, the stockpiles shall be
formed on concrete floors laid to falls sufficient to permit drainage at the base of
the stockpiles. Aggregates shall be handled to and from the stockpiles in a manner such that
they are not contaminated by the ground or by extraneous matter and also in a manner such
that segregation is prevented. In as much as possible the bins shall be covered to
prevent dampness of aggregate by rain.
Coarse and fine aggregates and aggregates from different sources shall be
stockpiled separately and if aggregates of different grading or from different sources are
stockpiled in close proximity the stockpiles shall be separated by partitioning.
All aggregates produced or handled by hydraulic methods and all washed aggregates shall
be stockpiled under cover for draining for at least 24 hours before use.
Material used as filler shall be stored in dry conditions to the satisfaction of the
Engineers
Representative.
No material shall be used until it has been approved by the Engineer. Permission to use
material shall not be construed as an approval of its source nor any acceptance as continued
acceptance.
XLI. Sampling
The Contractor shall provide equipment, labour and such trained staf as may be required by
the Engineer for carrying out the following tests on materials to be used in the manufacture
of hot asphaltic concrete in accordance with the following standards:
Grading tests on aggregates in accordance with the latest B. S. 812 - Sampling and testing
of mineral aggregate and fillers.
Determination of binder content of mixed materials in accordance with either:
Hot extraction method BT 1 described in B.S. 598 (1974) - Sampling and examination of
bituminous road mixtures. The Contractor is to comply with the requirements of B.S. 598:
and to the need of providing results in duplicate Or By reflux extractor method.
Aggregates shall be sampled and tested on delivery to the mixing plant and after each
extraction test and the result of each test shall be submitted to the Engineer or his
Representative within 24 hours of the sample being taken.
The number of such tests shall be adequate for proper control of the materials and shall
not be limited to those made on specified instructions of the Engineer or his Representative.
Samples of mixed materials shall be taken and tested during the first days mixing and
throughout the work to confirm that the grading and binder contents are as specified. Such
samples shall be taken either at the place and time of mixing or at the place of laying as
directed by the Engineer or his Representative. Samples for testing shall also be cut from the
surfacing as laid when directed by the Engineer or his Representative.
The frequency of sampling mixed materials shall be at least once per day or once for each
90 tonne of material mixed whichever is the more frequent. The result of each test on mixed
materials shall be submitted to the Engineer or his representative within 24 hours of the
sampling and any adjustment shown to be necessary shall be made immediately. Until such
adjustment have been made and until a certificate to the effect has been forwarded to
the Engineer or his representative no further batches or mixed material shall be made.
Independent sampling and testing may be carried out by the Engineer throughout the
contract period and for this purpose the contractor shall grant free access to the mixing
plant and storage depots, supply materials and provide every facility for the Engineer or his
representative to take sample whenever required.
In particular, throughout the contract, the Engineer will carry out control test on the plant
mix material using the marshal test apparatus.
A certificate is to be obtained from the supplier with each consignment of bitumen delivered;
stating the grade of material being supplied, and these certificates are to be handed to
the Engineers Representative.
If the Engineer so requires, the Contractor shall arrange for the testing in an approved
manner of all materials used throughout the contract to ensure that they are up to the
standard specified, i.e. aggregates, bitumen and such other materials as specified or decided
by the Engineer. The Contractor shall arrange for the testing of materials incorporated in
the works to ensure that they have been manufactured as specified, or as ordered by the
Engineer.
Whenever the Contractor intends to carry out any of the above tests, he shall give the
Engineers Representative sufficient notice to enable him, should he so wish, to be present
during the test.
Whenever the Contractor takes samples for testing, and where so directed he is to take
duplicate samples and hand them to the Engineers Representative. Such samples are to be
properly packed and labelled as directed.
The Engineers Representative shall be given the results in writing of all tests, as soon as
they are available, and in any case not later than 24 hours after samples have been taken.
The Engineer shall be supplied with all necessary equipment, material and labour to perform
any additional tests he may wish to carry out himself.
The cost of these tests including the provision of samples will be deemed to have been
included in the bill of quantities under the appropriate item.
The exact job-mix formula will depend on the nature and grading of the aggregate and
the grade of bitumen and will be determined by the Engineer using the marshall method of
mix design. For this purpose the Contractor shall supply to the Engineer without charge
adequate samples (in separate containers) of coarse and fine aggregates and bitumen
which he intends to use. The Engineer will, after testing, furnish the Contractor with the
exact job-mix formula, which will be within the specified limits.
Before any asphalt concrete is laid, the Contractor shall produce sufficient dry mixes in
the plant and carry out sieve analysis to ensure that the correct grading is being obtained. In
addition, he shall produce a number of trial mixes to which the specified quality of
bitumen has been added. He will then carry out extraction tests on this material and further
sieve analysis on the aggregate in accordance with clause 6373 of the specification. The
results of these tests on both the dry and wet mixes shall be approved by the Engineer
before any surfacing is laid in the permanent works.
Job Mix Formula The job-mix formula is the single definite percentage of aggregate
passing each required sieve size, a single definite bitumen content to be added to the
aggregate, a single definite temperature at which the mixture is to be emptied from the
mixer and a single definite temperature at which the mixture is to be delivered on the road.
Unless specifically changed in writing by the Engineer, the maximum variation from the
job- mix formula shall be as follows:
Table XXV: Permissible Variation Percent by Weight of Total Mix
Material Passing Permissible Variation % By Weight of
Total Mix Passing Sieve 9.5 mm and layer
5% Passing Sieve 9.5 mm
600 m 4% Passing Sieve 600 m
150 m 3% Passing Sieve 150 m
75 m 0.1% Bitumen Content
0.3%
Notes:
Temperature of Mixture when emptied from mixer 145C 5C
Temperature of Mixture on delivery on the road 130C 5C
The job mix formula is liable to alternation by the Engineer Throughout the progress of
the work but at all times it will be within the specified limits.
Preparation
XLIII. Preparation of Aggregates
The coarse and fine aggregate shall be separately fed by feeder to the cold elevator
or elevators in their proper proportions and at a rate to permit correct and uniform
temperature control of the heating and drying operation.
The aggregate shall be heated before entering the mixer to a temperature range of 120C
-
149C. All aggregates in the bins of a temperature that will produce a mix outside the limits
stated above or that contain moisture or expanding gases to cause Foaming in the
mixture, shall be removed and replaced in their respective stock piles. All aggregates that
have been overheated shall be cooled before being deposited in the feeder. All unsuitable
aggregates that may be in the weigh box or that become combined in the process of
Pulling the bins shall be discarded.
The screening efficiency shall be maintained within the limits set forth in Clause 6383. When
these limits are exceeded, the material shall be discarded and the cause for such
condition skill be corrected
When a paver laying base material approaches an expansion joint at a bridge or viaduct it
shall be taken out of use as soon as there is a danger of the material being laid fouling the
joint. In laying the remainder of the pavement up to the joint and the corresponding area
beyond it by hand, the joint or joint cavity shall not be fouled with surface material.
Hand-raking of wearing course material which has been laid by a paver and the addition
of such material by hand-spreading to the paved area for adjustment of level will only be
permitted at the edges of the layers of materials or where otherwise directed by the
Engineer. Where hand spreading and tamping is permitted, the mixed material is to be
dumped on delivery upon existing hard clean surface or on approved metal sheets outside
the area where it is to be spread and shall be distributed in to place immediately by means
of hot shovels. It shall be spread with hot rakes in a uniformly loose layer to the full depth
required.
Materials are to be laid to the depths necessary to give the required thickness after
compaction and they are to be finished true to profile.
The Contractor shall break out and remove at his own expense any asphaltic concrete laid in
trial areas if such asphaltic concrete fails to meet the specified requirements for asphaltic
concrete surfacing.
If for any reason the quality, grading or supply source of aggregates or the quality or source
of bitumen is changed, or at any time the cause of variations outside the permissible
limits cannot be corrected for reasons beyond the Contractors control, the Engineer may
require the Contractor to carry out additional laboratory tests and/or the construction of
additional trial areas depending on the extent of the change or variation.
XLIX. Compaction
After spreading, the mix shall be thoroughly and uniformly compacted by rolling.
The initial breakdown rolling shall be done with three wheel smooth roller, followed by
intermediate rolling with high- pressure tyred pneumatic roller. During the rolling wheels
shall be kept moist with only sufficient water to avoid picking up material.
Heavy equipment or roller shall not be permitted to stand on finished surface until it has
thoroughly cooled. In the initial rolling the three-wheel smooth roller shall proceed on to the
fresh material with the rear or driven wheels leading. The rolling shall start as soon after
laying as conditions permit and when the material is still at a temperature of not less than
99C. The weight per unit width of the rear wheel shall be between 45-65 Kg per centimetre
width.
After the longitudinal joints and edges have been compacted rolling shall start
longitudinally at the sides and gradually progress towards the centre of the pavement,
except on super- elevated curves where rolling shall begin on the low side and progress to
the high side. Each pass of the roller shall overlap the proceeding one by about one width of
the rear wheel. The roller should move at a slow but uniform speed not exceeding 8
kilometres per hour. The roller shall be in good condition, and capable of being reversed
without back lash, and the line of rolling shall not be suddenly changed or the direction or
rolling suddenly reversed, thereby displacing the mix. If rolling causes displacement of the
materials the affected areas shall be loosened at once with shovels or rakes and restored
to the original grade of loose material before being re-rolled.
The intermediate rolling shall be done with a pneumatic roller exerting compactive ground
pressures between 5.6-8.4 kg per sq. cm. The Contractor shall furnish to the Engineer
charts or tabulations showing the contact areas and contact pressures for the full range of
type inflation pressures and for the full range of tyre loadings for each type and size
compactor tyre furnished. The intermediate rolling shall follow the break down rolling as
closely as possible and while the mix is still at a temperature of 70C - 85C. Rolling shall be
continuous until the mix is thoroughly compacted and the density specified in clause 6381 is
achieved. Turning of pneumatic roller on the hot mix which causes undue displacement shall
not be permitted.
L. Joints
All joints shall be vertical, properly formed to the correct line and level; if necessary they
shall be cut back to achieve this. A template made to the shape of the true line and width
may be placed at each end of the construction joint line and width to create vertical straight
finish. Joints in the surface course should be staggered with those in the binder course and
must be kept straight, when the abutting lane is not placed the same day or if the edge of
the first strip has been distorted by traffic the joint shall be cut back to an even line and
then be coated with bitumen before laying the adjoining strip. All joints on completion
are to present the same texture, density and smoothness as other sections of the course.
LII. Priming of untreated base and application of tack coat existing paved surfaces
shall be done as follows:
All materials and method of preparation and construction shall conform with
the requirements of these specifications. The finished pavement shall conform in all respects
with the hues, grades, dimensions and cross sections shown on the drawings or as
may be otherwise specified or directed by the Engineer
LIII. Equipments
The type of equipment used should be the appropriate equipment for specific operation and
should not create any hazard to the adjoining properties along the project areas
most especially plants that can induce vibration. Notwithstanding that all test, piece of
equipment or apparatus is not specifically mentioned or described in the various pages
hereof, nevertheless if directed by the Engineer the Contractor is to supply at his own
expense all apparatus and equipment of whatever kind necessary to carry out any test
mentioned in or required by the provisions of the various clauses in this specification and the
British Standard Specifications incorporated in this Specification.
The Engineer shall be the final arbitrator on which tests are necessary for the
proper execution of the works.