Marshall Mixing & Testing - Group C
Marshall Mixing & Testing - Group C
CIVE 3808
ENVIRONMENT,
GEOTECHNICAL &
HIGHWAY LABORATORY III
GROUP REPORT - HIGHWAY
LABORATORY
EXPERIMENT 8:
MARSHALL MIXING AND TESTING
1.0 Introduction 1
2.0 Objectives 2
4.0 Procedures 4
7.0 Graphs 8
8.0 Discussions 14
10.0 References 16
The aggregates blend that will be used for mixtures preparation must
fall within the specification requirements. Properties such as density
and bulk specific gravity of aggregates and bitumen used for each
mixture must be determined earlier before carrying out Marshall
Test. By using the Asphalt Institute Method, the Optimum Asphalt
Content are determined from the individual plots of bulk density,
voids in total mix and stability versus percent asphalt content.
The mix design determines the optimum bitumen content. There are
many methods available for mix design which varies in the size of
the test specimen, compaction and other test specifications. Marshall
Method of mix design is the most popular one. The Marshall
Stability and flow test provides the performance prediction measure
for the Marshall Mix design method.
1
Load is applied to the specimen till failure, and the maximum load is
designated as stability. During the loading, an attached dial gauge
measures the specimen’s plastic flow (deformation) due to the
loading. The amount of binder to be added to a bituminous mixture
cannot be too excessive or too little.
2.0 Objectives
The objectives for this Marshall Mixing and Testing Test is to
determine the optimal binder contents and the appropriate
aggregates combinations for the bituminous mixtures.
2
3.0 Apparatus and Equipment
Balance
Digital Calipers
Extrusion Jack
Frying Spatula
Flat Spatula
Gas Stove
Marshall Breaking Head
Marshall Compaction
Metal Trays
Oven
Ring Dynamometer Assembly
Specimen Molds Assembly
Scope
Thermometers
Water Bath
Water Tank
Wok
3
4.0 Procedures
and mixing carried out until all the aggregate are coated. The
mixing temperature shall be within 165°C-170°C.
5) The cleaned mould is heated in an oven to a temperature
between 94°C-149°C.
75 blows were given to the both top and bottom surfaces of the
cake.
4
10) The filter papers are removed from the top and bottom of
specimen is determined.
submerged weight.
15) After the specimen is been submerged for the required amount
breaking head.
5
5.0 Safety, Health and Precautions
We must make sure all the mixing and compaction process are done
at the required temperature
We must apply grease on the surface of whole inner mould so that
the asphaltic specimen would not stick on the mould
Assure aggregate and asphalt is well mixed. Make sure there is no
any filler stick on the wall of mixing blow
Make sure all the equipment that will be use the mix design was
always kept in the oven when it not uses
Try to control the temperature of asphalt and aggregate, so that in can
be maintained at its mixing temperature
Make sure the compaction effort occurs at best condition and similar
to what happened if use the machine. Do not rush to finish the
compaction; the compaction must be suitable periodic sequence
6
Bitumen Content (%) Density Stability (KN) Flow (mm) VTN (%) VFB (%)
7
7.0 Graphs
8
9
10
11
12
Value at Average
Marshall Properties % Bitumen Contents Optimum Bitumen Spec Limit
Contents
Density 6 2.257
13
8.0 Discussions
14
This resulting that the flow was failed in fulfilling the required
specification of 2 – 4mm. From the graph of void in total mix against
bitumen content, the VTM (%) obtained with the optimum bitumen
content was 7.5%. Thus, the VTM value was failed in accordance
with the required specification which exceeding the percentages
between 3–5%.
Thus, from all these 5 graphs, we can conclude that the values do not
meet the criteria provided is that there are some serious errors when
conducting the experiment. These errors might cause by the Marshall
cakes which are full of defects upon removal from the mould or any
misconducting of the experiment.
15
9.0 Conclusion and Recommendations
10.0 References
16
11.0 Pictures and Attachments
17
18
19