Term of Reference
Term of Reference
For
Consulting Services for Engineering and Environmental Study of
Kohalpur-Surkhet-Upper Karnali 400 kV Transmission Line and
Kohalpur-New Butwal 400 kV Transmission Line under Project
Preparatory Facility for Energy (PPFE)
1. Background and Definitions
1.1 This project includes study and detail design of (1) the 400 kV Double circuit New
Kohalpur New Butwal transmission line and 400 kV substations at New Butwal (the
design of New Kohalpur substation is covered by Nalsinggad Development Committee in
a separate consulting assignment) (2) the 132 kV Double circuit Chinchu (Surkhet)-
Subakuna (Surkhet) and 132 kV substation at Subakuna (Surkhet) (3) the 400 kV
Double circuit Upper Karnali substation Chinchu (Surkhet) transmission lines, and 400
kV substation at Upper Karnali (4) New Kohalpur-New Lumki-New Attaraiya 400 kV
Double circuit transmission lines, and associated 400 kV substation at New Lumki and
New Attariya.
1.2 Nepal is facing chronic power shortages. Currently, only about 70 percent of the
countrys households have access to grid electricity. The Government of Nepal has set a
target of providing electricity to all of the population in the nation by 2027 (90 percent
through the national grid and 10 percent from decentralized generation solutions). In
support of the Governments energy development goals, The Asian Development Bank
(ADB) has provided grant assistance under Project Preparatory Facility for Energy
(PPFE) which will support preparation of detail studies of New Butwal-New Kohalpur-
New Lumki New Attariya 400 kV Transmission Line and associated substations and
Chhichu (Surkhet) Upper Karnali 400 kV Double circuit transmission lines and
associated substations as well as 132 kV Chhinchu surkhet 132 kV Double Circuit
transmission line and substations. Nepal Electricity Authority (NEA) is the implementing
agency for this part of PPFE.
1.3 The term NEA, EA and the Employer have the same meaning and may be used
interchangeably in this document depending on the context.
1.4 Aimed at increasing transfer capacity of the grid and access to grid electricity, the PPFE
shall finance the detail studies of the following subprojects:
a) New Butwal - New Kohalpur & Surkhet-Upper Karnali transmission line project
comprising of following subprojects:
(i) the 400 kV Double circuit New Kohalpur New Butwal transmission line and
400 kV substation at New Butwal;
(ii) the 132 kV Double circuit Chinchu (Surkhet)- Subakuna (Surkhet) and 132 kV
substation at Subakuna (Surkhet)
(iii) the 400 kV Double circuit Upper Karnali substation Chinchu (Surkhet)
transmission lines, and 400 kV substation at Upper Karnali.
b) The 400 kV New Kohalpur - New Lumki - New Attariya transmission line with associated
400 kV substations at New Lumki and New Attariya.
1.5. All subprojects listed in 1.4 shall be collectively referred to hereafter in this document as
the Project.
1.6. Under ADBs Project Preparation Facility for Energy Grant, a project preparation
support consulting firm (PPS) will be engaged in preparation of :
(2) Profiling and tower spotting on PLS CADD of the transmission lines and verification
and demarcation of the tower spots in the site of actual construction;
(5) Review of existing 400 kV Transmission Line Tower design provided by NEA,
comment and redesign if necessary including special tower design.
(6) Complete Tower foundation design and all other associated designs of the
transmission lines;
(7) Detail Design of the Substations including protection system coordination and
substation automation;
(8) Environmental and Social Safeguard studies including IEE/EIA as applicable along
with EMP, IPP and RP of the transmission lines;
(9) Detail Tree cutting plan with marking in the tree and ROW details of the
transmission lines;
1.7. NEA seeks through this Expression of Interest (EoI) to engage a team of project
preparation consultants through a firm in accordance with ADBs Guidelines on the Use
of Consultants by Asian Development Bank and Its Borrowers to support in preparation
of the Project.
1.8. This document set forth terms of references (TOR) for the Services.
The following scope of work is proposed to achieve the objective of the project, which
shall include but not be limited to the tasks and assignments, activities outlined below:
4. Detailed Tasks
The PPSs detailed tasks are as follows:
(ii) Review all reports, drawings and plans prepared by or for NEA (if any)and
related to the proposed subproject;
(iv) Conduct field surveys. Prepare and conduct detail survey of the
transmission lines including route alignment, profiling, tower spotting and
demarcation in the site, optimization of tower locations, soil resistance
measurement, geo-technical investigation, determine substation location,
prepare the Right-of-Way plan along the transmission line route covering
land plots, title holders, land area to be acquired/ affected as per the NEA
prudent practice and submit report with incorporation of suggestions from
approving agencies. The transmission line route alignment plans and
profiles and tower spotting plans shall be prepared using PLS-CADD with
demarcation of tower spot in the site of actual construction. The detail
survey of the final route alignment shall be carried out by using state-of-
the-art survey techniques and instruments having error within the standard
acceptable limit. The three coordinates (latitude, longitude, elevation or
Northing, Easting and Elevation) of all tower positions shall be determined.
Further, major features (switch yard, substation, angle and all intermediate
points, river crossings, line crossings, houses/sheds/other structures, and
any major crossings) shall be determined with latest details/features up to
100 m on both sides of the recommended alignment.
(v) Carrying out sag-tension calculations using PLS-CADD software. Prepare
sag template in the scale of plan & profile drawings. Spot towers on the
prepared plan & profile drawings optimally and prepare sag curves using
PLS-CADD software. The sag curves shall be for both Hot and Cold
conditions with all other necessary details prescribed by international
standards.
(vi) Perform detail engineering and develop design of the transmission line
including but not limited to (a) development of design criteria, calculations,
drawings; (b) Design Manual for design of EHV transmission lines; (c)
Specifications for steel towers, conductor, shield wires, OPGW, dampers,
disc insulators, line hardware and all other line accessories etc; (d) review
of family of self-standing steel lattice tower designs provided by the client
and redesign if necessary including special towers design required if any (c)
Complete Tower foundation Design (e) Development of construction and
installation methods; and (f) other related activities to complete the intended
jobs and submit report with incorporation of suggestions from approving
agencies. This assignment inter-alia shall include but not limited to the
following:
- Based on loading zones, line route, ground profile & contours, terrain,
spans (ruling, basic and weight span values) and other relevant
parameters; review the design families of Towers and determine their
suitability, if necessary design special towers for the project, and
complete the tower foundation design.
- Carry out the prototype testing of the newly designed towers for
verification of the designs. (if necessary)
(vii) Perform detail engineering and design of the Substation as per relevant
IEEE, IEC standards including but not limited to a) develop design criteria
for AIS and GIS substations, calculations, drawings & technical
specifications of substations equipment (electrical, mechanical, protection
and communication equipment) and related accessories and propose
suitable AIS or GIS substations for each subproject under study (b) Design
of Gantry structures, Equipment structures, Structures foundations, Control
Building, Approach and Internal roads, Cable trench and associated civil
works. The structural designs shall be developed taking into consideration
the seismic factors applicable; (c) Design, drawing and calculation of
complete protection system including earthing system (d) Design and
drawings of Substation lay outs based on COMS principle, single line
diagrams, protection and control schematic diagrams, interlocking schemes
etc; (e) Design & drawings of SCADA, substation automation and
Communication system and all other related activities to complete the
intended jobs and submit report with incorporation of suggestions from
approving agencies.
(viii) Conduct Soil investigation for each substation, angle towers of the
transmission lines.
(ix) Prepare detail cost estimate of the project, viz; each subproject wise as
illustrated in clause 1.4. The PPS Consultant shall depict the major
assumptions forming the cost estimates in text including the major item wise
details of cost estimates. The PPS Consultant shall also provide following
information:
(xi) Prepare a workable and cost effective procurement, construction & execution
plan including schedule for the proposed subproject and a detail description
of the process and submit report with incorporation of suggestions from
NEA.
(xii) Prepare the contract package for procurement and Bidding documents for
each of the transmission lines & Substations contract package for the
subprojects along with the technical specifications, schedules and drawings
for bidding of the project on a turnkey basis and submit documents with
incorporation of suggestions from approving agencies until approved.
(xiii) Prepare Quality Assurance Plan for implementation during the construction.
(xiv) Following the Environment Act and Regulation of Nepal, prepare and conduct
EIA/IEE (as necessary), Tree cutting plan along the ROW and substations;
Forest clearance and submit report with incorporation of suggestions from
approving agencies. In addition, the PPS shall also prepare EMP, IPP, RP,
Social Impact Assessment as per ADBs requirement based on Safeguard
Policy Statement 2009 (SPS) with regard to environmental protection and
resettlement. Also, support Project in clarifying any queries from the
responsible authorities until it is approved.
The PPS shall perform a needs assessment and develop training programs for NEA
staff working on the Project as PPSs counterpart staff. The training program shall
include (a) Project preparation and formulation (b) Project management, project
planning, Expenditure planning and Budgeting (c) Preparation of Basic Design
according to International standards (d) Procurement and Contract Management of
turnkey projects with special focus on transmission lines and substations (e) Project
Management Professional (PMP) Certification Training (f) On the job training as
required.
The NEA counterpart staff will assist the consultant to the extent possible during all
phases of the project. All international experts of PPS are expected to work closely
with the NEA staff and shall ensure that the NEA staff persons achieve higher skill
levels as a result of their involvement.
5. Implementation Arrangement
5.1 The PPS will work closely with the office of New Butwal-New Kohalpur-Surkhet-
Upper Karnali 400 kV Transmission Line Project (the Project or Client) at Project
Management Directorate (PMD) of NEA and coordinate with Nalsinggad Hydropower
Development Board, NEA's specialized Departments, Local administration, Relevant
ministries & agencies, Consultant of Nalsinggad Hydropower Development Board,
Project Supervision Consultant (PSC) for this subproject as and when required. The
PPSs team leader will be the principal contact and will be expected to be readily
available at the Project office with a notice of seven days from the Project during the
assignment period. The PPS will be responsible for all aspects of performance of
services set forth in the TOR. The Client will be responsible for providing the existing
data and information and supporting arrangement for the necessary field
investigations.
5.2 Method Statements. Prior to commencing any section of the work, the PPS shall
submit method statement to the project in accordance with the requirement of the
Consulting Services with the allocated input of days from both national and
international experts and expected input from counterpart staff of NEA. When
requested by the Client, the PPS shall provide additional method statements related
to specific item of work.
5.3 Design Progress Meetings. The PPS shall hold periodic progress meetings with
the Client at least once a month. Additional meetings shall be scheduled as required
by the PPSs design. The intent of these meetings will be for the Client to provide
input and to discuss options for addressing the Client's comments. The PPS shall
fully cooperate with the Client in scheduling and attending such meetings as
requested by the Client. These meetings shall be held at PMD office in Kathmandu.
The Client will be responsible to prepare meeting minutes during each of these
meetings. Minutes will be distributed to participants for review and comment.
5.4 Monthly Progress Reports. The PPS shall furnish the Client with a written Monthly
Progress Report that summarizes all aspects of the completed month and
cumulative work progress. The objectives of the Monthly Progress Report are to:
(i) Provide a reliable and readily accessible summary record of the project activities
with daily activities performed by each individual at the site and progress of work
during the just completed month with verification of daily task in the site signed by
the Project's representative. (ii) Provide a detailed description of all work actually
completed to date and revision to the project schedule required, which shall reflect
changes in the critical path since the date of the last revision. (iii) Identify issues and
problems requiring action by the Client or PPS, including issues of conflicting
priorities. (iv)Provide a forecast of the work to be accomplished in the next month. (v)
Provide information to help substantiate PPSs pay request.
5.5 Submittal Protocol. No later than thirty (30) days after the Contract Date, the PPS
shall submit a submittal protocol for the Consulting Services. The submittal protocol
shall identify the submittal packages to be prepared by the PPS including but not
limited as specified in clause 10, including a detailed listing of the content, the
expected dates of the submittals, number of copies, and distribution of the submittals
by the PPS based on distribution information provided by the Client. The submittal
protocol shall include the time allowed for the Clients review, which at a minimum
shall be twenty (20) days. For large or complex submittals, the Client may require a
submittal review period longer and the PPS shall coordinate with the Client inclusion
of these review periods in the submittal protocol. The submittal protocol shall avoid
the simultaneous submittal of a large number of submittals for the concurrent Client
review.
5.6 PPSs Obligations. The PPS shall provide submittals for review consistent with the
submittal dates. The PPS acknowledges that the Clients review will often involve
input from, or consultation with, a number of individuals. Therefore, should submittal
dates to the Client be delayed, the PPS shall provide prompt notice to the Client of
the delay. In no case shall this notice be given less than ten (10) calendar days prior
to the scheduled submittal date for that submittal. The submittals shall identify any
proposed change to the requirements, or the design concept, project delivery
approach, or the project schedule provided in the consultants proposal,
accompanied by the rationale behind the proposed change. No changes shall be
implemented without Clients acceptance. Such acceptance shall not, however,
relieve the PPS of any of its obligations under the contract.
5.7 Form of Submittals. Each submittal shall be transmitted electronically and in hard
copy, unless otherwise required by other sections of the TOR, with a cover letter to
the Client (New Butwal- New Kohalpur-Surkhet-Upper Karnali 400 kV Transmission
Line) at the office of Project Management Directorate. Unless otherwise specified in
the contract, the PPS shall prepare up to eight (08) hard copies of each submittal for
distribution. The Client is responsible for distribution of submittals to reviewers.
Electronic submittals shall be in the original file format. The PPS is responsible for
the accuracy and completeness of the information submitted.
5.8 The PPS shall make submittals far enough in advance of subsequent activities to
allow time for reviews, consultations with other entities, for securing necessary
acceptance, for possible revisions and re-submittals. The Client intends to process
PPSs submittals as quickly as practical.
5.9 Clients Review. The Client will review submittals for consistency with the design
concept presented in the PPSs proposal. The primary purpose of the Clients review
is to satisfy itself that the submittals generally conform to the intent of the contract.
The Clients review shall not relieve the PPS of the sole risk and responsibility for all
defects, errors or omissions, or of sole responsibility for meeting all requirements of
the contract. The PPS shall not proceed with implementation of any work affected by
a submittal until review by the Client is complete and the submittal is returned with
review comments as below:
Not Reviewed: Indicates that the submittal is not called for by the contract
and that no action was taken by the Client. The PPS may
proceed.
5.10 The PPS is expected to commence the service by September 2017, and the duration of
the service will be Fifteen (15) months from September 2017 - November 2018.
5.1. It is estimated that in total 135 person-months of Services are required with 62 person
months from international experts and 73 person months by national experts. Details on
expertise and person month requirements are in Table 1. The international expertise
should be provided by a consulting firm specializing in designing and preparing the
construction of EHV transmission lines and substations in partnership with national firm(s)
and/or individual national consultants in Nepal.
6.1. All international experts indicated in Table 1 are considered as key experts. The main
responsibilities of each international experts are highlighted, but not limited to, as follows:
(i) Leading and managing the entire team including both international and
national experts and act as the teams point of contact with NEA and ADB.
(ii) Make necessary inputs and advice to the project team and to NEA on
transmission line and transmission substation technical matters.
(iii) Develop a full understanding of project requirements through discussion
with NEA.
(iv) Coordinate field surveys, necessary additional studies for the subproject to
ensure that the line and substations meet NEAs overall requirements of the
projects
(v) Coordinate to review all reports, drawings and plans prepared by or for
NEA and related to the proposed subproject until bid preparation.
(vi) Contribute to capacity building of NEA counterpart staff.
(vii) Prepare regular reports in accordance with ADB's requirements.
(viii) Prepare or lead the team to prepare all the reports as listed in the Reporting
Requirements in 10.
(ix) Handling contract administration matters related to the PPS contract.
(x) Support PMD/NEA in administration of the preparation of all turn-key
contracts for the Project.
(xi) Provide complete services or coordinate with appropriate expert or experts
to fulfill the outlined tasks on clause 4 "Detailed Task" in this TOR
(xii) Prepare project designs, documentation and bidding documents; including
and not limited to the technical specifications, performance specifications,
schedules and drawings; with assistance of other consultants of the
Transmission lines & Substations for the subprojects on a turnkey basis
and submit report with incorporation of the comments by ADB & NEA on
the draft bidding documents and finalize the draft bidding documents until
approved by ADB & NEA.
(xiii) Prepare Quality Assurance Plan for implementation during the
construction.
(xiv) Monitoring project progress against plan, report on progress, and propose
remedial measures as necessary.
(xv) Lead the consultant team to prepare detail cost estimate for subprojects
(xvi) Conduct other duties as reasonably requested by NEA-Project
Management Directorate.
(i) Provide inputs and advice to the project team and to NEA on transmission
line technical matters and bid document preparation.
(ii) Define transmission line design technical parameters, conductor
configurations, insulator and tower types, taking account of NEAs
requirements and Nepal-specific conditions including wind velocity, terrain
type and altitude.
(iii) With support from other key and non-key experts complete assignments as
demanded by this consulting works.
The Team Leader will lead the capacity building and be responsible for:
(i) Perform a training needs assessment for NEA staff and prepare a training
program with the assistance of the consultant team.
(ii) Contribute to capacity building of NEA counterpart staff.
f. SCADA/Communications Engineer
(i) Assess NEA's existing SCADA and communications systems and prepare
design concepts for interfacing with the transmission line and substations.
(ii) Contribute in the preparation of project designs, documentation, bidding
documents.
(iii) Perform other functions as may be assigned or delegated by Team Leader
from time to time during the time of assignment.
(iv) Contribute in preparation of the conceptual designs and layouts for the
substations, transmission line, tower foundations, substation equipment
foundations, SCADA, communications, protection etc.
(v) Conduct field visit and recommend SCADA/Communication system for the
transmission line and substation communication matters of the subprojects
with justification.
(vi) Contribute to capacity building of NEA counterpart staff.
(vii) Provide support to the Team Leader in completing SCADA/Communication
related assignments as demanded by this consulting works.
g. Protection Engineer
(i) Make necessary inputs and advice to the project team and to NEA on
transmission line and transmission substation protection system.
(ii) Assess NEA's existing protection systems and prepare design concepts for
protection of the transmission line and substations.
(iii) Contribute to capacity building of NEA counterpart staff.
(iv) Conduct field visit and recommend protection system for the subprojects with
justification.
(v) Study the system, determine the protection requirement for T/L and substation
and perform necessary calculation and suggest the Protection settings.
(vi) Perform other functions as may be assigned or delegated by Team Leader
from time to time during the time of assignment.
(viii) Provide support to the Team Leader in completing Protection related
assignments as demanded by this consulting works.
j. Geotechnical Engineer
(i) Perform field sampling and measurements to determine the site soil conditions
in conjunction with other team members.
(ii) Make necessary inputs and advice to the project teams and to NEA on
transmission line and transmission substation geotechnical matters.
(iii) Contribute to the preparation of project designs, documentation, bidding
documents.
(iv) Perform other functions as may be assigned or delegated by Team Leader from
time to time during the time of assignment.
(v) Conduct Soil investigation of substation, angle towers of the transmission lines
and submit report with incorporation of suggestions from approving agencies.
(vi) Provide support to the Team Leader in completing geotechnical related
assignments as demanded by this consulting works.
k. Procurement Expert
i) Contribute to the preparation of bidding documents in line with ADB standard
bidding documents.
ii) Perform other functions as may be assigned or delegated by Team Leader from
time to time during the time of assignment.
iii) Make necessary inputs and advice to the project teams and to NEA on
transmission line and transmission substation procurement related matters.
iv) Provide support to the Team Leader in completing procurement related
assignments as demanded by this consulting works.
l. Financial Expert
7.1. Although national consultants are classified as non-key in the proposal evaluation, they
play important role in the PPS team with local knowledge of dealing with social, technical
and geographical issues arising from the Project. Each national expert will perform the
same or similar duties as his/her counterpart in the international team in his/her
respective field. In addition, National Forest Conservation Expert shall work under the
consultant team to coordinate and execute clearance and permission of forest and
conservation area for tree cutting and Right of Way related issues of the subprojects.
8. Capacity Building
8.1. One of the basic objectives of the consulting services is the transfer of technology in this
field to the NEA's engineers. This will be achieved by involving the NEA engineers with
the PPS experts as much as possible in various activities of the project implementation
during field works as well as in the home office of the Consultant.
8.2. NEA's eight (8) engineers will visit the PPS's home office for one month each to gain
valuable experience and familiarity with the project and contract management issues. The
PPS shall arrange a training session in its home office for a total of eight (8) engineers.
The duration of the session shall be one month. The cost of such training including the
cost of travel, boarding, lodging and subsistence allowance in connection with the
Engineer's training on PPSs offices will be quoted under Provisional Sum. The training
shall be conducted in the in following disciplines:
(a) Project preparation and formulation
(b) Project management, project planning, Expenditure planning and budgeting
(c) Preparation of Basic Design according to International standards
(d) Procurement and Contract Management of turnkey projects with special focus
on transmission lines and substations
(e) Project Management Professional (PMP) Certification Training
8.3. The PPS shall provide hands on training on the latest version of internationally
recognized contract management of turnkey projects with special focus on transmission
lines and substations and Project Management Professional (PMP) Certification Training
from an institute accredited by Project Management Institute. PPS shall provide with its
proposal the details of proposed training.
9. Reporting requirements
9.1. The PPS shall prepare the various reports and maintain records documenting decisions
made at meetings, progress on project preparation, financial records and changes to
the contract plans. The reporting shall, in general, comprise of the following:
(i) Detail survey of the transmission lines with incorporation of suggestions from
approving agencies.
(ii) Report on revision of Tower Design of NEA and design of towers not covered by
the existing tower design of NEA and Report on the Foundation Design of the
transmission lines.
(iii) Transmission Line Tower Design Manual.
(iv) Report on Substation Design including design of gantry structure & their
foundations, equipment structure ant their foundation, equipment foundation,
Earthing design, Communication design, Protection design, Control Building &
cable trenches etc and all associated single line and schematic drawings with
incorporation of suggestions from approving agencies.
(v) Report on Soil investigation of substation, angle towers of the transmission lines
with incorporation of suggestions from NEA.
(vi) Bidding documents for each procurement package of the transmission lines &
Substations for the subprojects with incorporation of suggestions from NEA.
(vii) Report on recommendation of SCADA/Communication and protection system
for the subprojects
(viii) Report on EIA/IEE (as necessary); EMP, IPP, RP; Tree cutting plan with
numbering in the trees; ROW detail report of the transmission lines; Social Impact
Assessment; Forest clearance with incorporation of suggestions from approving
agencies.
(ix) Report on review of all reports, drawings and plans prepared by or for NEA and
related to the proposed subproject
(x) Report on line routing and tower spotting plans and survey information using PLS-
CADD with demarcation of tower spot in the field of actual construction.
(xi) Report on definition of transmission line and substation design technical
parameters, conductor configurations, insulator and tower types, taking account
of NEAs requirements and Nepal- specific conditions including wind velocity,
terrain type and altitude.
(xii) Report on detail cost estimate for subprojects
(xiii) Report on designs and layouts for the substations, transmission line, tower
foundations, substation equipment foundations, SCADA, communications,
protection etc.
(xiv) Report on technical specifications, performance specifications, schedules and
drawings for bidding of the project on a turnkey basis.
(xv) Report on Economic and Financial analysis of the Project/subprojects.
(xvi) Prepare Manual for checking drawings of towers and foundations.
(xvii) Other reports in accordance with the detailed task of PPS.
9.2. All documents and reports would be made available on hard copy as well as electronic
format. All reports will be in English language.
10.1. NEA Project Team: The office of New Butwal- New Kohalpur-Surkhet-Upper Karnali
400 kV Transmission Line Project, Project Management Directorate- NEA shall work in
close collaboration with the Consultant's team and be fully involved in all aspects of the
consulting services. Both NEA and Consultant's teams shall work together as one single
team in all matters related to the Project.
10.2. Project Preparation: NEA engineers and technicians will support in preparation
activities at different site locations of the subprojects and the Consultant shall report to
and work in tandem with the Project Management Directorate- NEA. NEA will provide in
total 9 and 6 man months of inputs of NEA electrical engineer and civil engineer
respectively to support the International Expert during project preparation.
10.3. Administrative support for PPS Team: If required by local regulations, NEA will
provide PPS with necessary support letters for obtaining visas and permits for its experts.
The cost and timing of obtaining the above is entirely the responsibility of the PPS.
10.4. Office Space, Office Equipment, Transportation and Accommodation: NEA will
provide office space, necessary furniture and office equipment (computers, fax,
telephone etc.) in Kathmandu. However, the PPS shall make his own arrangements for
transportation in Kathmandu and local transportation and accommodation for its
personnel in the project sites outside of Kathmandu. The PPS shall arrange itself any
other equipment required during execution of works. PPS shall be responsible for
international telephone bills, maintenance of office equipment and consumables
necessary for its own use.
a) Team Leader and Transmission Line & Substation Electrical Engineer shall have
preferably Masters Degree in Electrical Engineering/High Voltage Engineering and
preferably more than 15 years of consulting experience in transmission line projects
and substantial experiences in developing countries other than his/her own country.
The expert shall have previous team leader experience in detail design and project
preparation of 400 kV or above voltage level transmission line projects. Experience
shall cover 400 kV or higher voltage class transmission line detail design and bid
document preparation.
(ii) Review all reports, drawings and plans prepared by or for NEA and related
to the proposed subproject;
(iii) Determine and suggest the appropriate capacity of Transmission Line and
substations with needful calculations based on the transmission master plan
of NEA;
(iv) Walk over survey to propose three different alternative routes for each
Transmission line.
(v) Submission and approval of Report on walk over survey and review of all
reports, drawings and plans prepared by or for NEA and related to the
proposed subproject
Carrying out sag-tension calculations using PLS-CADD software. Prepare sag template in the
scale of plan & profile drawings. Spot towers on the prepared plan & profile drawings optimally
and prepare sag curves using PLS-CADD software. The sag curves shall be for both Hot and
Cold conditions with all other necessary details prescribed by international standards.
Submission and approval of Report on line routing and tower spotting plans and survey
information using PLS-CADD with demarcation of tower spot in the site of actual construction
with GPS coordinates.
Conduct Soil investigation including soil resistance measurement for each substation, angle
towers of the transmission lines to complete the specified scope of work
Submission and approval of Report on Soil investigation of each substation, angle towers of the
transmission lines with incorporation of suggestions from approving agencies.
Perform detail engineering and develop design of the transmission line including but not limited
to (a) development of design criteria, calculations, drawings; (b) Design Manual for design of
EHV transmission lines; (c) Specifications for steel towers, conductor, shield wires, OPGW,
dampers, disc insulators, line hardware and all other line accessories etc; (d) review of family of
self-standing steel lattice tower designs and redesign if necessary (e) Design of special towers
required if any (f) Complete Tower foundation Design (g) Development of construction and
installation methods; and (h) other related activities to complete the intended jobs and submit
report with incorporation of suggestions from approving agencies. This assignment inter-alia
shall include but not limited to the following:
- Based on loading zones, line route, ground profile & contours, terrain,
spans (ruling, basic and weight span values) and other relevant
parameters; review the design of Towers provided by clients and
determine their suitability for the project and design foundation, re-
design the Towers if required.
- Carry out the prototype testing of the towers for verification of the
designs. (if necessary)
Perform detail engineering and design of the Substation as per relevant IEEE, IEC standards
including but not limited to a) develop design criteria for AIS and GIS substations, calculations,
drawings & technical specifications of substations equipment (electrical, mechanical, protection
and communication equipment) and related accessories and propose suitable AIS or GIS
substations for each subproject under study (b) Design of Gantry structures, Equipment
structures, Structures foundations, Control Building, Approach and Internal roads, Cable trench
and associated civil works. The structural designs shall be developed taking into consideration
the seismic factors applicable; (c) Design, drawing and calculation of complete protection
system including earthing system (d) Design and drawings of Substation lay outs based on
COMS principle, single line diagrams, protection and control schematic diagrams, interlocking
schemes etc; (e) Design & drawings of SCADA, substation automation and Communication
system and all other related activities to complete the intended jobs and submit report with
incorporation of suggestions from approving agencies.
Submission and approval of Report on Substation Design technical parameters, taking account
of NEAs requirements, terrain type and altitude, design of gantry structure & their foundations,
equipment structure ant their foundation, equipment foundation, earthing design,
Communication design, Protection design, Control Building & cable trenches etc and all
associated single line and schematic drawings with incorporation of suggestions from approving
agencies.
Submission and approval of detail cost estimate of the project, viz; each subproject wise as
illustrated in clause 1.4. The PPS Consultant shall depict the major assumptions forming the cost
estimates in text including the major item wise details of cost estimates. The PPS Consultant shall
also provide following information:
- Reference price level of estimates
- Currency and Exchange rates and their referenced period
- Level of Contingencies
- Level of inventories of materials, spares etc,
- Scaling factors used for scaling up/down cost of any major
equipment/item
- Status of engineering and design on the basis of which the estimates
have been framed
- Rates and quantity of the items on the basis of value analysis.
- Insurance, Transportation, Custom Duty and Taxes etc
Submission and approval of the contract package for procurement and Bidding documents for
each of the transmission lines & Substations contract package for the subprojects along with the
technical specifications, schedules and drawings for bidding of the project on a turnkey basis and
submit documents with incorporation of suggestions from approving agencies until approved.
Submission and approval of a workable and cost effective procurement, construction & execution
plan including schedule for the proposed subproject, Quality Assurance Plan for implementation
during the construction and a detail description of the process and submit report with
incorporation of suggestions from NEA.
Following the Environment Act and Regulation of Nepal, prepare and conduct EIA/IEE (as
necessary), Tree cutting plan along the ROW and substations; Forest clearance and submit
report with incorporation of suggestions from approving agencies. In addition, the PPS shall also
prepare EMP, IPP, RP, Social Impact Assessment as per ADBs requirement based on
Safeguard Policy Statement 2009 (SPS) with regard to environmental protection and
resettlement. Also, support Project in clarifying any queries from the responsible authorities until
it is approved.
Submission and approval of EIA/IEE (as necessary); EMP, IPP, RP; Tree cutting plan; ROW
detail report of the transmission lines; Social Impact Assessment; Forest clearance with
incorporation of suggestions from approving agencies.
Other reports (if any) in accordance with the detailed task of PPS but not covered above.
Milestone 9: Retention for the validity of the works performed by the consultant - 5%
The 5% amount will be retained for the validation of the whole Designs and Demarcation works
produced by the Consultants where the Consultant may require to provide further justifications
and clarifications to the Concerned Contractor or Employer during the Construction phase of the
above project. The amount shall be retained for maximum 2 (two) years from the Completion of
PPS contract. However, the retained 5% amount may be released against the unconditional
Bank Guarantee.