Chapter Thirteen Design of Traffic Signals: 13-1 Interrupted Flow
Chapter Thirteen Design of Traffic Signals: 13-1 Interrupted Flow
Chapter Thirteen
Design of Traffic
Signals
13-1 Interrupted Flow
Interrupted flow is more complex than uninterrupted flow because of the
time dimension involved in allocating space to conflicting traffic streams.
On an interrupted flow facility, flow usually is dominated by points of fixed
operation, such as traffic signals and stop signs. These controls have
different impacts on overall flow.
1
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
13-2 Signal Control
The most significant source of fixed interruptions on an interrupted-flow
facility is the traffic signal. Traffic signals periodically halt flow in each
movement or set of movements. Movement on a given set of lanes is
possible only for a portion of the total time, because the signal prohibits
movement during some periods. Only the time during which the signal is
effectively green is available for movement. For example, if one set of lanes
at a signalized intersection receives a 30-s effective green time out of a 90-s
total cycle, only 30/90 or 1/3 of total time is available for movement on the
subject lanes.
Thus, only 20 minutes of each hour are available for flow on the lanes. If
the lanes can accommodate a maximum flow rate of 1,500 veh/h with the
signal green for a full hour, they could accommodate a total rate of flow of
only 500 veh/h, since only one-third of each hour is available as green.
Its headway will generally be less than that of the first vehicle. The third
and fourth vehicles follow a similar procedure, each achieving a slightly
lower headway than the preceding vehicle. After four vehicles, the effect of
the start-up reaction and acceleration has dissipated. Successive vehicles
then move past the stop line at a steady speed until the last vehicle in the
original queue has passed. The headway for these vehicles will be relatively
constant .this constant average headway, denoted as h, is achieved after four
vehicles. The headways for the first four vehicles are, on the average, greater
than h and are expressed as h + ti, where ti is the incremental headway for
the ith vehicle due to the start-up reaction and acceleration. As i increases
from 1 to 4, ti decreases. Figure (13.1) shows a conceptual plot of headways.
2
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
The saturation flow rate represents the number of vehicles per hour per
lane that can pass through a signalized intersection if the green signal was
3
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
available for the full hour, the flow of vehicles was never halted, and there
were no large headways.
The first four vehicles in the queue encounter headways longer than the
saturation headway, h. The increments, ti, are called start-up lost times. The
total startup lost time for the vehicles is the sum of the increments, computed
using Equation (13.2).
l1 = (13.2)
Where
l1 = total start-up lost time (s),
ti = lost time for ith vehicle in queue (s), and
N = last vehicle in queue.
Each stop of a stream of vehicles is another source of lost time. When
one stream of vehicles stops, safety requires some clearance time before a
conflicting stream of traffic is allowed to enter the intersection. This interval
when no vehicles use the intersection is called clearance lost time, l2.
The relationship between saturation flow rate and lost times is a critical
one. For any given lane or movement, vehicles use the intersection at the
saturation flow rate for a period equal to the available green time plus the
change interval minus the start-up and clearance lost times. Because lost
time is experienced with each start and stop of a movement, the total amount
of time lost over an hour is related to the signal timing. For instance, if a
signal has a 60-s cycle length, it will start and stop each movement 60 times
per hour, and the total lost time per movement will be 60(l1 + l2).
1. Isolated traffic signal control, in which the signal timing decisions are
based solely on the traffic demand in the approaches to that
intersection.
2. Coordinated traffic signal control, in which the signal timing decisions
are based with consideration also to other adjacent traffic signals to
4
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
which the intersection controller is connected in order to facilitate
passage of the signalized system.
5
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
Phase A
Phase B
Phase C
6
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
6. Yellow or amber interval: The first interval following the green
interval during which the yellow or amber signal indication is
displayed.
7. Controller: A device in a traffic signal installation that changes
the colors indicated by the signal lamps according to a fixed or
variable plan.
8. Intergreen interval: Is the total length in seconds of the yellow
and all-red signal indications . This time is provided for vehicles to
clear the intersection after the green interval.
Intergreen (4 sec)
7
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
13-6 Cycle Lengths of Fixed (Pretimed) Signals
Webster method has shown that for a wide range of practical conditions,
minimum intersection delay is obtained when the cycle length is obtained by
the equation :
(13.1)
Where:
Co=Optimum cycle length (sec.)
L= Total lost time per cycle (sec.)
Yi=Maximum value of the ratios of approach flows to saturation flows
for all traffic streams using phase i (qa/s)
n= Number of phases
qa=Flow on approach (actual flow rate) having the right of way during
phase i
s=Saturation flow on approach.
Dividing the number of vehicles that go through the intersection by the
saturation flow will give the effective green time , which is less than the sum
of the green and yellow times. This difference is considered lost time, since
it is not used by any other phase for the discharge of vehicles, it can be
expressed as:
li=Gi+ Ai gei (13.2)
Where:
li=Starting delay lost time for phase i
Gi= Actual green time for phase i (not including yellow time)
Ai= Yellow time for phase i (Amber)
gei = Effective green time for phase i
(13.3)
Where:
R= total all red time during the cycle.
8
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
Allocating of green times : In general , the total effective green time
available per cycle is given by:
Ge= C-L = C-( + All-R)
(13.4)
Where
C= Actual cycle length used (usually obtained by rounding off C o to
the nearest 5 sec),
Ge= Total effective green time per cycle.
To obtain minimum overall delay, the total effective green time should be
distributed among the different phases in proportion to their Y values to
obtain the effective green time for each phase.
gi= Ge
(13.5)
And the actual green time for each phase is obtained as:
Gi=gi + li A
(13.6)
G1=g1+l1-A
G2=g2+l2-A
No. of vehicle in queue = qa(Co-ge) (13.7)
Example (13.1): Figure below shows peak-hour volumes for a major intersection
on an freeway. Determine a suitable signal timing for the intersection
using the four-phase system shown below. Use a yellow interval of 3 sec.
and a saturation flow given. Use PHF=0.95 and li=3.5 sec.
9
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
Phase Lane group No. of Lane group Saturation yi y critical
lanes volume , q flow
Y Summation 0.729
sec
Ge= C-L = 100-14 = 86 sec
gi= Ge
Gi=gi + li A
GA=(0.264/0.729)*86+3.5-3=32 sec
GB=(0.183/0.729)*86+3.5-3= 22 sec
GC=(0.052/0.729)*86+3.5-3=7 sec
GD= (0.23/0.729)*86+3.5-3=27 sec
10
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
directly related to the control delay value. The criteria are listed in Table
(13-1).
11
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
(13.8)
12
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
A saturation flow rate for each lane group is computed according to
Equation(14.8) .The saturation flow rate is the flow in vehicles per hour that
can be accommodated by the lane group assuming that the green phase were
displayed 100 percent of the time (i.e., g/C = 1.0).
(13.9)
13
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
(13.10)
14
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
The ratio of flow rate to capacity (v/c), often called the volume to
capacity ratio, is given the symbol X in intersection analysis. It is typically
referred to as degree of saturation. For a given lane group i, Xi is computed
using Equation (13.11).
(13.11)
(13.12)
15
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
(13.13)
16
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
nonactuated lane groups in semiactuated control systems. The value of PF
may be determined using Equation(13.14).
(13.14)
The value of P may be measured in the field or estimated from the arrival
type. If
field measurements are carried out, P should be determined as the
proportion of vehicles in the cycle that arrive at the stop line or join the
queue (stationary or moving) while the green phase is displayed. The
approximate ranges of Rp are related to arrival type as shown in Table (13-
4), and default values are suggested for use in subsequent computations in
Table (13-5).
Table (13-4): Relationship between arrival type and platoon ratio (Rp)
17
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
(13.15)
18
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
of saturation of the lane group (X), the duration of the analysis period (T),
the capacity of the lane group (c), and the type of signal control, as reflected
by the control parameter (k). The equation assumes that there is no unmet
demand that causes initial queues at the start of the analysis period (T).
Finally, the incremental delay term is valid for all values of X, including
highly oversaturated lane groups.
(13.16)
19
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
aggregation is done by computing weighted averages, where the lane group
delays are weighted by the adjusted flows in the lane groups.
Thus, the delay for an approach is computed using Equation (13.17).
(13.17)
(13.18)
20
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
21
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
22
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
23
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
24
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
25
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
26
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
27
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
28
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
29
Traffic Engineering College of Engineering Kufa University
Third Year Civil department
Mooring & evening study
30