Guidelines For External Prestressing As Strengthening Technique For Concrete Structures PDF
Guidelines For External Prestressing As Strengthening Technique For Concrete Structures PDF
Guidelines For External Prestressing As Strengthening Technique For Concrete Structures PDF
The scarcity of technical documentation on methods for structural strengthening, combined with the
increasing importance of rehabilitation on the construction sector, justifies the work developed on
strengthening using external prestressing, herein presented in the format of guidelines. The selection of
this technique is due to its significant interest in situations where no other technique is adequate, e.g.
removal of columns, as well as to the fact of being probably the one with less information published.
Thus, this article aims at providing structural engineers with design guidelines, covering most relevant
aspects of conception, calculation and detailing, when adopting external prestressing as strengthening
technique.
1
(1) Concerning the structural strengthening of is defined, prestressing bars can also be used.
concrete elements, the use of the external The choice of the external prestressing profile
prestressing technique should be considered depends on the goals of the strengthening
when: operation and it should be performed
A. There is a need to change the according to the following instructions [3]:
structural system, such as in the case Situation A. (column removal) the
of the removal of a column, in which its profile must be polygonal with a
reaction will be replaced by a deviation deviation device in the region of the
force from the external prestressing removed column;
system (Fig. 1); Situation B. (deformation/cracking
correction) either a straight or a
polygonal profile may be used.
2
ducts, due to excessive stresses, the radius of existing structural element. If this is not
the external prestressing cables in the possible, due to geometrical limitations (lack of
deviation areas should be limited. When using space for the placement of the anchorage
smooth polyethylene ducts, the minimum value devices) or due to impositions of the profile
should be calculated using the following (need to maximize the eccentricity), one of the
expression [8]: following solutions should be adopted: (i)
increase the thickness of the element in the
( ) ( )( )
anchorage zone (Fig. 3a), (ii) use of reinforced
where fpk represents the characteristic tensile concrete blocks (Fig. 3b), or (iii) use of steel
strength of prestressing steel in MPa; and Ap elements (Fig. 3c).
represents the cross section area of the
2
prestressing cables in m .
( )
Table 1 - recommended maximum jacking stresses for 2.3 Materials and components
FRP straight tendons (adapted from [9])
(1) The external prestressing system consists
Type of fibre Allowable jacking of: prestressing tendons; anchorage devices;
stress external duct (frequent, but not mandatory);
*
Carbon 0,65fpu corrosion protection systems; and deviation
*
Aramid 0,50fpu devices (in the case of polygonal profiles).
*
Glass 0,45fpu
* Prestressing tendons
fpu represents the maximum tensile strength of
(1) The prestressing tendons are usually made
the prestressing material.
of high strength steel, although there are
The minimum radius adjacent to the trumpet in tendons made of FRP as well, usually carbon
the anchorage zone must comply with the fiber reinforced polymer (CFRP). Compared to
requirements present in source [10]. the high strength steel tendons, these provide
a higher resistance against corrosion and
(5) Whenever possible, the anchorage devices
fatigue. However, their cost is higher, their
should be positioned to lead the resultant of
resistance to UV radiation lower, they are
the forces to the center of mass of the pre-
3
much more difficult to anchor, and they present ducts is also possible. The diameter of the
a linear behavior up to failure. polyethylene duct can be calculated using the
following expression [10]:
(2) The high strength steel tendons must
comply with the requirements presented in the ( )
European standards [11], [12] and [13].
Regarding FRP, although there are different (2) Different corrosion protection systems are
commercial systems, European standards presented in [8]. External duct systems
have not been provided yet. Some of these injected with cement grout are most adequate
FRP commercial systems can be consulted at because, when compared to wax or grease
source [14]. injection, it reveals higher mechanical strength
and fire resistance, being also inexpensive and
Deviation and anchorage devices
easier to apply. In the external duct systems
(1) When adopting steel deviation devices,
filled with cement grout, the strands can be
these must be designed to provide the most
directly in contact with the cement grout or they
efficient profile to the prestressing cables. In
can be individually greased and plastic-
the contact areas with the ducts, the deviators
sheathed. The latter should be chosen if the
should comprise a curved tube made of
need to correct the tensioning force and/or to
smooth steel, larger than the external ducts, so
replace the tendons is foreseen.
that there is no interruption along its length
(Fig. 4). This way, the effectiveness of the 2.4 Preliminary design of the jacking force
corrosion protection system is assured. and the cross sectional area of the
Nevertheless, the use of other configurations is prestressing tendons
possible as well, as mentioned in [6]. (1) The preliminary design depends on the
strengthening purpose. The following
situations can arise:
1) Situation A (column removal) The
deviation force applied to the structure
Figure 4 Detail of the tendons duct in the deviation
zone (adapted from [15]) in the region of the removed column
must be equal to the axial force acting
(2) The anchorage devices of steel external
before in the latter, for the quasi-
prestressing cables used as strengthening
permanent combination of actions.
system are exactly the same as the ones used
2) Situation B (deformation/cracking
in current applications. Some examples of
correction) The deflection due to the
anchorages used for external prestressing with
quasi-permanent combination of
FRP tendons are given in [16].
actions added to the deflection
Ducts and materials used for protection against resulting from the equivalent external
corrosion of external steel tendons prestressing loads, must be lower than
(1) For external prestressing, smooth the maximum admissible deflection
polypropylene or polyethylene ducts are according to EC2 [17]. For a polygonal
advised. However, the use of smooth steel profile, as preliminary design criteria,
4
the load balancing criteria can be FRP tendons, which must be calculated
used. In this case, the deviation forces according to [9].
applied along the span should equal
(2) To calculate losses due to friction, the VSL
80 up to 90% of the quasi-permanent
European Technical Approval 06-0006 [10]
loads.
recommends the value of coefficient of friction,
(2) In the preliminary design of the jacking , as 0,05 for external cables comprised of
force, 10% of immediate and 5% of time individually greased and plastic-sheathed
dependent prestress losses may be strands. If the external tendons horizontal plan
considered. view is not straight (which is quite frequent in
external prestressing) it is necessary to take
(3) In the preliminary design of the cross
into consideration the sum of the angular
sectional area of the external prestressing
displacements in both horizontal and in vertical
tendon, the limit to the maximum stressing
plans. On the other hand, the losses due to
force must be taken into account, according to
friction may be neglected, if
section 5.10.2.1 from EC2 [17]. On the other
polytetrafluoroethylene is applied in the interior
hand, to better control the applied stresses,
of the tubes from the deviator that are in
and to preview the need to correct these, the
contact with the ducts of the prestressing
maximum stressing force should be limited to
tendons. Alternatively, the jacking force can be
50% of the characteristic tensile strength
applied simultaneously at both ends, which
defined in EC2 [17]. In this case, the time
require the existence of active anchorages
dependent losses can be estimated in nearly
1%, since, given the low stress level in the 2.6 Ultimate limit states
external cables, a reduced relaxation effect is Bending
expectable. The recommended maximum (1) The calculation of the ultimate moment
jacking stresses for straight FRP tendons resistance of an externally prestressed
should comply to the limits presented in table 1 element must consider the following aspects:
[9]. For deflected FRP tendons, the allowable (i) That the increase of force in tendons, from
force at jacking (P) should be limited taking the effective prestress to the force at ultimate
into account the radius in the deviation zones limit state, Fps, depends on the element's
(R) and the maximum allowable stresses for global deformation; and that (ii) the tendon
straight FRP tendons given in table 1, eccentricity loss must be accounted for at
according to the following expression: ultimate, if not taken measures for the limiting
of the second order effects.
( ) ( )
(2) In a conservative way, Fps can be
considered equal to 0, neglecting the increase
2.5 Losses of prestress
of strain in the external tendons, caused by the
(1) The losses of prestress in steel and FRP
deformation of the prestressed element, up to
Tendons can be calculated according to
failure. The EC2 [17] indicates that, in the
sections 5.10.5 and 5.10.6 from EC2 [17], with
absence of more rigorous calculation, Fps
the exception of losses due to relaxation in
may be considered equal to 100 MPa. For a
5
more rigorous calculation of Fps the
expression presented in [6] can be used.
Additional expressions can be consulted at where:
[18]. ( ) ( )
( ) ( )
( ) ( )
section 2 of the current chapter), then they each section, due to the external
stress in external prestressing tendons at the element length; the value of the
ultimate. Its accounting can be performed by moment, at each section of the element,
adjusting the effective depth of the external due to unitary load, applied to the element,
2.7 Serviceability limit states reinforcement steel due to dead loads, live
(1) The calculation of the long term deflection for the used combination of actions.
6
into consideration: (i) the design strength of the concrete interface, and are therefore less
compressive struts (according to section 6.5.2 effective.
from EC2 [17]); (ii) the design values for the
compressive stresses within the nodes
(according to section 6.5.4 from EC2 [17]);
(iii) the design strength of the transverse ties
(according to section 6.5.3 from EC2 [17]);
(iv) the concentrated resistance force for
partially loaded areas (according to section
6.5.3 from EC2 [17]); (v) the design shear
resistance at the concrete to concrete interface Figure 5- Example of the connection between the pre-
existing element and the reinforced concrete blocks
(according to section 6.2.5 from EC2 [17].
(adapted from [2])
Additionally, according to EC2 [17], in the
Fastening of steel elements to the concrete
verification of local effects, the value of
P,unfav.=1,2 should be used. (1) The steel elements that bear the
anchorages devices or that belong to the
(2) The calculation of the reinforcement to
deviators, are fastened to the concrete by
embed in concrete, so it can resist the tensile
means of anchors. The most common types of
stresses resulting from the action of
fastenings are shown in Figure 6. For external
prestressing, as well as its detailing, can be
prestressing, the most used types are the
carried out in accordance with what is stated in
threaded rods and the prestressing bars.
[21] and [22]. In order to guarantee the
When using threaded rods, its usual for them
cracking control in these areas, the
to go from side to side, but its also normal to
reinforcement ties should be calculated
use adhesive anchors. When considering
considering a maximum tension of 300 MPa
prestressing bars the fastening is always done
[17].
form side to side.
7
mobilized between the concrete surface and being of negative value in case of
the steel plates. traction and positive in case of
compression.
( ( ) )
between the steel plate and the aspects that must be understood for its proper
concrete surface, ranging between the use. These aspects relate to external
values of 0,3 and 0,5, depending on prestressing features, such as accounting for
the roughness of the steel plate and the second order effects and the correct
represents the axial force in elements, the setting of the minimum radius in
the deviation zones and limitation of the
the bar due to the forces which are
tendons free length, as well as traits related to
intended to transmit to the concrete,
8
the use of external prestressing in structural [4] Bruggling A. S. G. (1990), External
strengthening, such as the choice of the Prestressing a state of the art, External
tendons layout that best suit each situation Prestressing in Bridges, American Concrete
and the aspects concerning the preliminary Institute, 120: pp 61-81
design of solutions, and still features related to
[5] BD 58/94 (1995), The design of concrete
prestressing in general, to the interface
highway bridges and structures with external
between concretes cast at different times, to
unbounded prestressing, Design Manuals for
the fastening of steel elements to the concrete,
roads and bridges 1, section 3, part 9
amongst others. This paper is intended to
summarize the necessary information for the
[6] Preto P. (2014), Aplicao ed pr-
completion of all these aspects, with reference
esforo exterior como tcnica de reforo de
to relevant literature, as a complement of the
estruturas de beto, Tese de Mestrado,
information contained in it. However, the lack
Instituto Superior Tcnico
of technical documentation related to the use
of external prestressing for the strengthening [7] Tan K. H., Naaman A. E., Mansur M. A.,
of structures must be emphasized, since most Ng C. K. (1997), External Prestressing in
of the encountered documents only refer to the Structures, Final Report, July, Department of
use of external prestressing in new structures. Civil Engineering, National University of
Thus, given the strong growth in the Singapore
rehabilitation sector, it is important for scientific
research to move towards this field of [8] Neves S. M. P. (2012), Pr-esforo
[1] - Costa A., Reforo com pr-esforo [9] Dollan C. W., Hamilton R. H., bakies C.
exterior, Folhas de apoio s aulas de E.,Nanni A. (2001), Design recommendations
Reabilitao e Reforo de estruturas, Instituto for concrete structures prestressed with FRP
Superior Tcnico tendons, University of Wyoming, Pennsylvania
State University, University of Missouri-Rolla,
[2] Ng C. K. (2005), Flexural Strengthening
Final Report, FHWA contract, DTFH61-96-C-
of RC Beams via External Prestressing,
00019
University Malaysia Sarawak, Faculty of
Engineering [10] VSL International Ltd., European
Technical Approval No. ETA-06/0006 (2011)
[3] Almeida T. G. M. (2001), Reforo de
vigas de concreto armado por meio de cabos [11] - prEN10138-2. Prestressing steel Part
externos protendidos, Tese de Mestrado, 3: Wires. 2006
Escola de engenharia de So Carlos da
Universidade de So Paulo [12] prEN10138-3. Prestressing steel Part
3: Strand. 2006.
9
[13] prEN10138-4. Prestressing steel Part [23] Mendes M., Costa A. (2008),
4: Bars. 2006. Caracterizao da Ligao entre Betes de
idades diferentes, Encontro Nacional de
[14] Nordin H. (2006), Strengthening
Beto Estrutural 2008
structures with externally prestressed
tendons, Technical Report, Lulea University of [24] - Comite Euro-international du beton
Technology, Division of Structural Engineering (1990), CEB-FIP Model Code 1990, Design
Code
[15] VSL International Ltd., VSL construction
Systems, Brochure
10