Exam Questions
Exam Questions
Exam Questions
Question 1
6 out of 6 points
The question, What unique product does the customer expect from the project? is an example
of a(n) _____ constraint.
Selected Answer: scope
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 2
3 out of 3 points
A difference between operations and projects is that operations end when their objectives have
been reached, whereas projects do not.
Selected Answer: False
Answers: True
False
Question 3
3 out of 3 points
_____ is the application of knowledge, skills, tools, and techniques to project activities to meet
project requirements.
Selected Answer: project management
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 5
5 out of 5 points
Galaxy, a construction company, buys a particular brand of tiles manufactured by Tiles and
Floors, an eco-friendly tile manufacturing company. However, Tiles and Floors has declared
bankruptcy and closed down. At present, Galaxy is facing a crisis because there are no other
manufacturers in the market that supplies eco-friendly tiles. Which of the following constraints
is Galaxy currently facing?
Selected Answer:
Resources
Answers:
Resources
Time
Scope
Cost
Question 6
6 out of 6 points
Until the 1980s, project management primarily focused on providing _____ and resource data to
top management in the military, computer, and construction industries.
Selected Answer: schedule
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 7
5 out of 5 points
_____ refers to a problem-solving approach that requires defining the scope of a system,
dividing it into its components, and then identifying and evaluating its problems, opportunities,
constraints, and needs.
Selected Answer:
Systems analysis
Answers: Linear programming
Systems analysis
Response Systems analysis is a problem-solving approach that requires defining the
Feedback: scope of the system, dividing it into components, and then identifying and
evaluating its problems, opportunities, constraints, and needs.
Question 8
3 out of 3 points
the degree to which rules, policies, and direct supervision are used to oversee
employee behavior
Question 11
3 out of 3 points
Questions about how a team will track schedule performance is related to a projects scope.
Selected Answer: False
Answers: True
False
Question 12
3 out of 3 points
According to the symbolic frame, the most important aspect of any event in an organization is
not what actually happened, but what it means.
Selected Answer: True
Answers: True
False
Question 13
5 out of 5 points
Selected
Answer: In a strong matrix organizational structure, the project manager controls the
project budget and has moderate to high authority.
Answers: In a matrix organizational structure, employees are organized into departments
according to their skills, and there is little interaction between employees from
different departments.
The _____ frame of the organization is the one that is usually depicted in an organizational chart.
Selected Answer: structural
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 15
3 out of 11 points
Project managers and their teams must keep in mind the effects of any project on the interests
and needs of the entire system or organization instead of focusing on the immediate concerns
of the project.
Selected Answer: True
Answers: True
False
Question 17
5 out of 5 points
project manager
project team
Response Most projects have many interested parties or stakeholders, but someone
Feedback: must take the primary role of sponsorship. The project sponsor usually
provides the direction and funding for the project.
Question 18
6 out of 6 points
A(n) _____ is an overall model for thinking about things as sets of interacting components
working within an environment to fulfill some purpose.
Selected Answer: system philosophy
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 19
5 out of 5 points
A critical path:
Selected
Answer: determines the earliest completion date of a project.
Answers: is the shortest path through a network diagram.
A major element of good practice concerns _____ , which addresses the authority and control
for key IT activities in organizations, including IT infrastructure, IT use, and project
management.
Selected Answer: IT governance
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Contains goveranance
QUIZ 2
Question 1
3 out of 3 points
Decisions and actions taken in one knowledge area at a certain time rarely affect other
knowledge areas.
Selected Answer: False
Answers: True
False
Response Project management is an integrative endeavor; decisions and actions taken in
Feedback: one knowledge area at a certain time usually affect other knowledge areas.
Question 2
3 out of 3 points
An organizations information technology project selection process should guide the strategic
plan.
Selected Answer: False
Answers: True
False
Response Aligning IT projects with business strategy is consistently a top concern for
Feedback: CIOs. Most organizations face thousands of problems and opportunities for
improvement. Therefore, an organizations strategic plan should guide the IT
project selection process.
Question 3
3 out of 3 points
Project integration management must occur just within the context of a particular project.
Selected Answer: False
Answers: True
False
Response Project integration management includes interface management, which
Feedback: involves identifying and managing the points of interaction between various
elements of a project. The number of interfaces can increase exponentially as
the number of people involved in a project increases.
Question 4
3 out of 3 points
Monitoring and controlling processes overlap all of the other project management process
groups.
Selected Answer: True
Answers: True
False
Response Monitoring and controlling processes overlap all of the other project
Feedback: management process groups because changes can occur at any time.
Question 5
3 out of 3 points
The Rational Unified Process (RUP) framework is incompatible with the PMBOK process.
Selected Answer: False
Answers: True
False
Response According to RUP expert Bill Cottrell, RUP embodies industry-standard
Feedback management and technical methods and techniques to provide a software
: engineering process particularly suited to creating and maintaining component-
based software system solutions. Cottrell explained that you can tailor RUP to
include the PMBOK process groups because several customers asked for that
capability.
Question 6
3 out of 3 points
_____ is a planning process that is within the Project Scope Management knowledge area.
Selected Answer:
Creation of a WBS
Answers: Schedule development
Creation of a WBS
Quality planning
Response Creation of a WBS is a planning process falling under the Project Scope
Feedback: Management knowledge area.
Question 8
5 out of 5 points
The project cost management knowledge area maps to the _____ process group through the
activities of estimating costs and budget determination.
Selected Answer:
planning
Answers: initiating
planning
executing
Response The project cost management knowledge area maps to the planning process
Feedback: group through the activities of estimating costs and budget determination.
Question 9
5 out of 5 points
Identifying stakeholders
Response It is good practice to lay the groundwork for a project before it officially
Feedback: starts. Senior managers often perform several tasks, sometimes called pre-
initiation tasks which include the development of a business case for a project.
Question 10
5 out of 5 points
The _____ stage of information technology planning outlines business processes that are
central to achieving strategic goals and helps determine which ones could most benefit from
information technology.
Selected Answer:
business area analysis
resource allocation
IT strategy planning
Response The business area analysis outlines business processes that are central to
Feedback: achieving strategic goals and helps determine which processes could most
benefit from IT.
Question 12
5 out of 5 points
In the _____ stage of selecting information technology projects, organizations define project
scope, benefits, and constraints.
Selected Answer:
project planning
Answers:
project planning
resource allocation
IT strategy planning
A(n) _____ is a formal, documented process that describes when and how official project
documents may be modified, the people authorized to make modifications, and the paperwork
required for these changes.
Selected Answer:
change control system
Answers: WBS
project charter
performance report
Response A change control system is a formal, documented process that describes when
Feedback and how official project documents may be changed. It also describes the
: people authorized to make changes, the paperwork required for these changes,
and any automated or manual tracking systems the project will use
Question 14
6 out of 6 points
_____ analysis is a method of calculating the expected net monetary gain or loss from a project
by discounting all expected future cash inflows and outflows to the present point in time.
Selected Answer: Net Present Value
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 15
6 out of 6 points
The ideal outcome of the _____ process group is to complete a project successfully by delivering
the agreed-upon project scope within time, cost, and quality constraints.
Selected Answer: Monitoring and Controlling
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 16
6 out of 6 points
_____ are short descriptions written by customers of what they need a Scrum system to do for
them.
Selected Answer: User stories
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 17
6 out of 6 points
The _____ is a very important tool in project management because it provides the basis for
deciding how to do the work.
Selected Answer: Work Breakdown Structure (WBS)
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 18
6 out of 6 points
A(n) _____ is the approved project management plan plus approved changes.
Selected Answer: baseline
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Contains baseline
Question 19
6 out of 6 points
_____ include formal and informal plans, policies, procedures, guidelines, information systems,
financial systems, management systems, lessons learned, and historical information that can be
used to influence a projects success.
Selected Answer: Organizational process assets
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Organizational process
Exact Match
assets
Organizational process
Exact Match
assets (OPA)
Question 20
11 out of 11 points
List and briefly describe the six main processes involved in project integration management.
Selected
Answer:
Correct
Answer: 1. Developing the project charter involves working with stakeholders to create
the document that formally authorizes a projectthe charter.
2. Developing the project management plan involves coordinating all planning
efforts to create a consistent, coherent documentthe project management plan.
3. Directing and managing project execution involves carrying out the project
management plan by performing the activities included in it. The outputs of this
process are deliverables, work performance information, change requests, project
management plan updates, and project document updates.
4. Monitoring and controlling project work involves overseeing activities to
meet the performance objectives of the project. The outputs of this process are
change requests, project management plan updates, and project document updates.
5. Performing integrated change control involves identifying, evaluating, and
managing changes throughout the project life cycle. The outputs of this process
include change request status updates, project management plan updates, and
project document updates.
6. Closing the project or phase involves finalizing all activities to formally close
the project or phrase. Outputs of this process include final product, service, or
result transition and organizational process assets updates.
Response [None Given]
Feedback
:
QUIZ 3
Question 1
0 out of 5 points
In the _____approach for constructing a WBS, you use a similar projects WBS as a starting
point.
Selected Answer:
top-down
Answers: top-down
bottom-up
mind-mapping
analogy
Response A method for constructing a WBS is the analogy approach. In the analogy
Feedback: approach, you use a similar projects WBS as a starting point.
Question 2
3 out of 3 points
Project stakeholder management has only recently been identified as an entire knowledge area
by the Project Management Institute.
Selected Answer: True
Answers: True
False
Response Because stakeholder management is so important to project success, the
Feedback: Project Management Institute decided to create an entire knowledge area
devoted to it as part of the Fifth Edition of the PMBOK Guide in 2013.
Question 3
5 out of 5 points
_____ is a process for identifying and modeling business events, who initiated them, and how
the system should respond to them.
Selected Answer:
Use case modeling
Answers: Prototyping
JAD
RAD
Response Use case modeling is a process for identifying and modeling business events,
Feedback: who initiated them, and how the system should respond to them. It is an
effective tool for understanding requirements of information systems.
Question 4
5 out of 5 points
_____ involves reviewing the project charter, requirements documents, and organizational
process assets to create a scope statement, adding more information as requirements are
developed and change requests are approved.
Selected Answer:
Defining scope
Defining scope
Controlling scope
Validating scope
Response Defining scope involves reviewing the scope management plan, project charter,
Feedback: requirements documents, and organizational process assets to create a scope
statement, adding more information as requirements are developed and change
requests are approved.
Question 5
11 out of 11 points
What are some of the suggestions for improving the requirements process?
Selected
Answer:
1. Develop and follow a requirements management process that includes
procedures for initial requirements determination.
2. Employ techniques such as prototyping, use case modeling, and Joint
Application Design to understand user requirements thoroughly.
Prototyping involves developing a working replica of the system or some
aspect of the system.
3. Put all requirements in writing and keep them current and readily
available. Several tools are available to automate this function.
4. Create a requirements management database for documenting and
controlling requirements. Computer Aided Software Engineering (CASE)
tools or other technologies can assist in maintaining a repository for
project data.
5. Provide adequate testing to verify that the projects products perform
as expected. Conduct testing throughout the project life cycle.
6. Use a process for reviewing requested requirements changes from a
systems perspective.
Correct
Answer: 1. Develop and follow a requirements management process that includes
procedures for initial requirements determination.
3. Put all requirements in writing and keep them current and readily available.
Several tools are available to automate this function. For example, a type of
software called a requirements management tool aids in capturing and maintaining
requirements information, provides immediate access to the information, and
assists in establishing necessary relationships between requirements and
information created by other tools.
A(n) _____ is a tool used to group stakeholders based on their level of authority and their level
of concern for project outcomes.
Selected Answer: Stakeholder register
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 7
5 out of 5 points
The stakeholder register is the output of the _____ process of project stakeholder management.
Selected Answer:
executing
Answers: initiating
planning
executing
Response The stakeholder register is the output of the executing process of project
Feedback: stakeholder management.
Question 8
6 out of 6 points
In the _____ approach to creating a WBS, team members first identify as many specific tasks
related to the project as possible.
Selected Answer: Bottom-up
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
A work package represents one component of the product that the project aims to deliver.
Selected Answer: False
Answers: True
False
Response A work package is a task at the lowest level of the WBS. It represents the
Feedback: level of work that the project manager monitors and controls.
Question 10
5 out of 5 points
After identifying and analyzing stakeholders, the project manager and team should develop
a(n) ______ to help them effectively engage stakeholders and make sure that good decisions
are made throughout the life of the project.
Selected Answer:
stakeholder management plan
Answers:
stakeholder management plan
stakeholder register
issue log
power/interest grid
Response After identifying and analyzing stakeholders, the project manager and team
Feedback: should develop a stakeholder management plan to help them effectively engage
stakeholders and make sure that good decisions are made throughout the life of
the project.
Question 11
3 out of 3 points
Information from the project charter provides a basis for further defining the project scope.
Selected Answer: True
Answers: True
False
Response The charter describes the high-level scope, time, and cost goals for the project
Feedback: objectives and success criteria, a general approach to accomplishing the
projects goals, and the main roles and responsibilities of important project
stakeholders.
Question 12
6 out of 6 points
A(n) _____ is a technique for analyzing information to determine which stakeholders interests
to focus on and how to increase stakeholder support throughout the project.
Selected Answer: Stakeholder analysis
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 13
5 out of 5 points
Answers: variance
scope
deliverable
work package
Question 15
5 out of 5 points
The project team must take corrective action if stakeholders with high interest and high power
are categorized as _____.
Selected Answer:
resistant
Answers:
resistant
neutral
supportive
leading
Response The project team should take corrective action if stakeholders with high
Feedback: interest and high power are also categorized as resistant or unaware.
Question 16
3 out of 3 points
The scope management plan can be informal and broad or formal and detailed, based on the
needs of the project.
Selected Answer: True
Answers: True
False
Response The scope management plan is a subsidiary part of the project management
Feedback: plan. It can be informal and broad or formal and detailed, based on the needs
of the project.
Question 17
6 out of 6 points
The main outputs of scope definition are the _____ and project document updates.
Selected Answer: project scope statement
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Question 18
3 out of 3 points
A leading stakeholder is one who is aware of the project and is neither supportive nor resistant
to it.
Selected Answer: False
Answers: True
False
Response A leading stakeholder is one who is aware of the project and its potential
Feedback: impacts and actively engaged in helping it succeed
Question 20
6 out of 6 points
Quiz 4
Question 1
3 out of 3 points
After defining project activities, the next step in project time management is developing the
schedule.
Selected Answer: False
Answers: True
False
Response After defining project activities, the next step in project time management is
Feedback: sequencing them or determining their dependencies.
Question 2
3 out of 3 points
To define activities, the project team should start with reviewing the schedule management
plan, scope baseline, enterprise environmental factors, and organizational processes.
Selected Answer: True
Answers: True
False
Response Defining activities involves identifying the specific actions that will produce the
Feedback project deliverables in enough detail to determine resource and schedule
: estimates. The project team reviews the schedule management plan, scope
baseline, enterprise environmental factors, and organizational process assets to
begin defining activities.
Question 3
3 out of 3 points
Most WBSs include a section for project communications to ensure that reporting key
information is a project deliverable.
Selected Answer: True
Answers: True
False
Response Information about the content of essential project communications comes from
Feedback: the work breakdown structure (WBS). In fact, many WBSs include a section
for project communications to ensure that reporting key information is a project
deliverable.
Question 4
3 out of 3 points
A Tracking Gantt chart is based on the percentage of work completed for project tasks or the
actual start and finish dates.
Selected Answer: True
Answers: True
False
Response A Tracking Gantt chart is based on the percentage of work completed for
Feedback: project tasks or the actual start and finish dates. It allows the project manager
to monitor schedule progress on individual tasks and the whole project.
Question 5
3 out of 3 points
Good information technology project managers must have strong technical and communication
skills.
Selected Answer: True
Answers: True
False
Response Most IT professionals enter the field because of their technical skills. Most
Feedback: find, however, that communication skills are the key to advancing in their
careers, especially if they want to become good project managers.
Question 6
3 out of 3 points
_____ address where the project stands in terms of meeting scope, time, and cost goals.
Selected Answer:
Status reports
Status reports
Progress reports
Lessons-learned reports
Response Status reports describe where the project stands at a specific point in time.
Feedback: Status reports address where the project stands in terms of meeting scope,
time, and cost goals.
Question 10
5 out of 5 points
Using the formula for calculating the number of communication channels, how many channels
would five people require?
Selected Answer:
10
Answers: 9
10
11
14
Response The formula to determine the number of communication channels as the
Feedback: number of people involved in a project increases: number of communication
channels = n (n-1)/2. Two people will have one communication channel.
Question 11
5 out of 5 points
In project time management, the process of_____ primarily involves checking and managing
changes to the project schedule.
Selected Answer:
controlling the schedule
Answers: estimating activity durations
activity attribute
milestones list
Response Controlling the schedule involves controlling and managing changes to the
Feedback: project schedule. Outputs include work performance information, schedule
forecasts, change requests, project management plan updates, project
documents updates, and organizational process assets updates.
Question 13
0 out of 5 points
facial expression
spoken content
tone of voice
In project time management, the process of _____ involves deciding how many people,
equipment, and materials a project team should use to perform project activities.
Selected Answer: estimating activity resources
Correct Answer:
Evaluation Method Correct Answer
Question 15
6 out of 6 points
The main outputs of _____ include work performance measurements, organizational process
assets updates, and project document updates.
Question 16
6 out of 6 points
_____ is the number of workdays or work hours required to complete a task.
Selected Answer: Effort
Correct Answer:
Evaluation Method Correct Answer
Question 17
6 out of 6 points
Many experts agree that the greatest threat to the success of any project, especially information
technology projects, is a failure to _____.
Selected Answer: communicate
Correct Answer:
Evaluation Method Correct Answer
Question 18
6 out of 6 points
Question 19
6 out of 6 points
While trying to assess commitment of project stakeholders, a(n) _____ meeting or a Web
conference might be the most appropriate medium to use.
Selected Answer: face-to-face
Correct Answer:
Evaluation Method Correct Answer
Quiz 5
Question 1
3 out of 3 points
Validated changes and validated deliverables are the outputs of the quality assurance process.
Selected Answer: False
Answers: True
False
Response Controlling quality involves monitoring specific project results to ensure that
Feedback: they comply with the relevant quality standards while identifying ways to
improve overall quality. Validated changes and validated deliverables are the
outputs of the quality control process.
Question 2
3 out of 3 points
Integration testing involves testing of each individual component to ensure that it is as defect-
free as possible.
Selected Answer: False
Answers: True
False
Response Integration testing occurs between unit and system testing to test functionally
Feedback: grouped components. It ensures that a subset or subsets of the entire system
work together.
Question 3
3 out of 3 points
Products that are accepted by project stakeholders are considered to be validated deliverables.
Selected Answer: True
Answers: True
False
Response Acceptance decisions determine if the products or services produced as part of
Feedback: the project will be accepted or rejected. If they are accepted, they are
considered to be validated deliverables.
Question 4
3 out of 3 points
The lower the earned monetary value calculation for a project, the chances of project success is
higher.
Selected Answer: False
Answers: True
False
Response Expected monetary value (EMV) is the product of a risk event probability and
Feedback: the risk events monetary value. Because the EMV provides an estimate for the
total dollar value of a decision, you want to have a positive number; the higher
the EMV, the better.
Question 6
3 out of 3 points
Risk events refer to specific, certain events that may occur to the detriment or enhancement of
the project.
Selected Answer: False
Answers: True
False
Response Risk events refer to specific, uncertain events that may occur to the
Feedback: detriment or enhancement of the project.
Question 7
5 out of 5 points
Those who are _____ have a higher tolerance for risk, and their satisfaction increases when
more payoff is at stake.
Selected Answer:
risk-seeking
Answers:
risk-seeking
risk-averse
risk-neutral
risk-indifferent
Response Those who are risk-seeking have a higher tolerance for risk, and their
Feedback: satisfaction increases when more payoff is at stake. A risk-seeking person
prefers outcomes that are more uncertain and is often willing to pay a penalty
to take risks.
Question 8
5 out of 5 points
_____ are unplanned responses to risk events used when project teams do not have contingency
plans in place.
Selected Answer:
Workarounds
Answers:
Workarounds
Fallback plans
Contingency plans
Triggers
Response Workarounds are unplanned responses to risk events used when project
Feedback: teams do not have contingency plans in place.
Question 9
5 out of 5 points
_____ involves reducing the impact of a risk event by reducing the probability of its
occurrence.
Selected Answer:
Risk mitigation
Risk acceptance
Risk transference
Risk mitigation
Response Risk mitigation involves reducing the impact of a risk event by reducing the
Feedback: probability of its occurrence.
Question 10
5 out of 5 points
Process improvement plan, quality metrics, and quality checklists are the outputs of the _____
process of project quality management.
Selected Answer:
planning quality management
Response The main outputs of planning quality management are a quality management
Feedback: plan, a process improvement plan, quality metrics, quality checklists, and
project documents updates.
Question 11
5 out of 5 points
_____ is the cost of evaluating processes and their outputs to ensure that a project is error-free
or within an acceptable error range.
Selected Answer:
Appraisal cost
Appraisal cost
Response Appraisal cost is the cost of evaluating processes and their outputs to ensure
Feedback that a project is error-free or within an acceptable error range. Activities such as
: inspection and testing of products, maintenance of inspection and test
equipment, and processing and reporting inspection data all contribute to
appraisal costs of quality.
Question 12
5 out of 5 points
A(n) _____ is any instance where the product or service fails to meet customer requirements.
Selected Answer:
defect
Answers:
defect
yield
deliverable
variance
Response A defect is any instance in which the product or service fails to meet customer
Feedback: requirements. Because most products or services have multiple customer
requirements, there can be several opportunities to have a defect.
Question 13
5 out of 5 points
_____ help users to identify the vital few contributors that account for most quality problems in
a system.
Selected Answer:
Pareto charts
Pareto charts
Control charts
Response A Pareto chart is a histogram that can help you identify and prioritize problem
Feedback: areas. The variables described by the histogram are ordered by frequency of
occurrence. Pareto charts help you identify the vital few contributors that
account for most quality problems in a system.
Question 14
6 out of 6 points
Performing _____ involves monitoring specific project results to ensure that they comply with the
relevant quality standards while identifying ways to improve overall quality.
Selected Answer: Quality control
Correct Answer:
Evaluation Method Correct Answer
Question 15
6 out of 6 points
The _____ means taking responsibility for failures or not meeting quality expectations.
Selected Answer: Cost of nonconformance
Correct Answer:
Evaluation Method Correct Answer
Question 16
6 out of 6 points
_____ diagrams trace complaints about quality problems back to the responsible production
operations.
Selected Answer: Cause-and-effect
Correct Answer:
Evaluation Method Correct Answer
Question 17
6 out of 6 points
The term _____ is used to describe risks that the project team has identified and analyzed.
Selected Answer: known risks
Correct Answer:
Evaluation Method Correct Answer
Question 18
6 out of 6 points
_____ risks are risks that remain after all of the response strategies have been implemented.
Selected Answer: Residual
Correct Answer:
Evaluation Method Correct Answer
Question 19
6 out of 6 points
Question 20
Needs Grading
List and briefly describe four methods for identifying risks.
Selecte
d
Answer:
Brainstorming is a technique by which a group attempts to generate ideas or find a
solution for a specific problem by amassing ideas spontaneously and without
judgment. This approach can help the group create a comprehensive list of risks to
address later in the qualitative and quantitative risk analysis processes.