Assembly Line Design and Optimization Restructuring and Balancing of The Bus Pre-Assembly Line at MAN Nutzfahrzeuge AG Ankara Factory PDF
Assembly Line Design and Optimization Restructuring and Balancing of The Bus Pre-Assembly Line at MAN Nutzfahrzeuge AG Ankara Factory PDF
Assembly Line Design and Optimization Restructuring and Balancing of The Bus Pre-Assembly Line at MAN Nutzfahrzeuge AG Ankara Factory PDF
Restructuring and balancing of the bus pre-assembly line at MAN Nutzfahrzeuge AG Ankara factory
ARTUN TRENL
Department of Product and Production Development
Division of Production Systems
CHALMERS UNIVERSITY OF TECHNOLOGY
Gteborg, Sweden 2009
Assembly line design and optimization
Restructuring and balancing of the bus pre-assembly line at MAN Nutzfahrzeuge AG Ankara factory
ARTUN TRENL
Cover: Restructuring of stations for the single pre-assembly line at MAN Trkiye
ABSTRACT
MAN Trkiye A.. is one of the three bus production sites of MAN Nutzfahrzeuge AG with a
yearly production of about 2000 vehicles. Production of MAN and NEOPLAN branded vehicles
is handled at the factory with a total of 16 models and more than 200 variants.
The bus production system at MAN Trkiye is divided into five operational lines that are chassis
welding, paintshop, pre-assembly, assembly and finish. Production runs on a single line with 65
minutes of takt time with an exception in the pre-assembly line of two parallel lines of 19 stations
and 130 minutes of takt time. With this structure, the pre-assembly line acts as a factory within a
factory, bringing out its own problems of high operational and inventory costs. In order to
eliminate the complications of this structural difference, the company management aims to
construct a single assembly line by merging the pre-assembly and assembly lines at the same
building, which requires the current pre-assembly system to be switched to a single line of 65
minutes of takt time.
This project analyses the operations and balance losses at the current pre-assembly line, and
intends to create a framework for the restructuring process that will optimize resource utilization.
To conduct this study, the assembly line is observed and analyzed in order to evaluate the balance
losses and their reasons, and determine which operations are inappropriate for an assembly line.
Eliminating the most evident wastes and building up a simplified pre-assembly operations list, the
pre-assembly line is balanced for the desired number of stations in parallel with operator and line
layout planning tasks. Considering the difficulty of the task of balancing a line that assembles 16
different models, the most complex model of each bus type - city, intercity and coach- is selected
as base models.
The simplified operation list provides an improvement of vehicle operation time of about 30%.
The achieved results suggest that, in addition to according the whole production system with its
line flow properties, the new line structure makes it possible to reduce inventory costs by 40%,
operator demand by 17%, and idle time and takt overdue by about 80%. With a new line layout, it
is also possible to reduce total distance from the sub-assembly stations to main assemblies by
about 20%, which will improve material flow activities within the facility.
Keywords: Bus Assembly, Assembly Line Design, Assembly Line Balancing, Operator Planning,
Waste Reduction, Resource Utilization
This report is the result of the Masters Thesis project carried out at MAN Nutzfahrzeuge AG bus
factory in Turkey from February 2009 to July 2009 as part of the International Master of Science
programme in Automotive Engineering at Chalmers University of Technology, Sweden.
I would like to thank Bar Arpac for his belief in my aptitude and recommendation, and Yenal
Gndz for giving me the opportunity to do this project and the responsibility of such an
assignment. Without their support I would not be able to initiate and carry out this project.
Special thanks to Hseyin zsert for his ideas and consistent patience in giving answers to my
countless questions, Emrah Arslanta for helping me by-pass the bureaucracy within the company
while trying to get things done, Galip Bakpr for providing all required information about the
factory that is unreachable for the most, and the team leaders for helping me figure out the
dynamics at the shop floor by sharing their first hand experience.
I would also like to thank Bertil Gustafsson for accepting to be my examiner for this project and
sa Fasth for her help with bringing this report to a conclusion.
Artun Trenli
This chapter includes corporate presentation of the company and the background of the problem
that constitutes the motivation of the project. Furthermore, the scope, objectives and organization
of the project are also presented along with the brief outline of the report.
Holding 69% of the total turnover of the MAN Group, MAN Nutzfahrzeuge AG is the largest
company within the group and among the leading international suppliers of commercial vehicles.
The company includes MAN Trucks, MAN Buses, and NEOPLAN Buses. MAN Nutzfahrzeuge
AG has 15 different production sites worldwide that are distributed to 8 countries; Germany,
Austria, Poland, Turkey, India, Saudi Arabia, South Africa and Mexico.
Table 1.3 - Main buildings, work centers and performed operations at MAN Trkiye A..
Department Number of stations Building Type of work
Bus Chassis Assembly 29 U1 Chassis welding
Paintshop 14 U1 Anti-corrosive chemical application and painting
Bus Pre-assembly 19 (+19) U1 and G Assembly of infrastructural systems and glasses
Bus Assembly 27 U2 Assembly of seats and other interior&exterior accessories
Bus Finish 28 U3 Paint polish and final revisions
The steps of bus production at MAN Trkiye can be summarized as following. The production of
a bus starts at the bus chassis department. Welding of the beams and side plate covering
operations are held in this section. When the chassis of the bus is complete, the vehicle is taken to
the paintshop. In the paintshop, anti-corrosive chemicals are applied to the chassis, which is
followed by priming, cleaning of surfaces, and application of final paint. This is when the vehicle
is taken to the bus pre-assembly line. The operation of bus pre-assembly line can be simplified as
performing the infrastructural operations that are required to make a vehicle run. That is, a
vehicle that leaves the pre-assembly line is fully functional and can operate normally. Operations
such as wiring, assembly of brake systems, assembly of powertrain, floor and side covering, and
assembly of glasses are held at the pre-assembly line, which is partitioned into U1 and G
buildings. When a vehicle leaves this line, it is brought to U2 building, where all accessories of
the vehicle are installed. Finally, the vehicle is taken to the finish building U3 for final
inspections and paint polish operations.
The existing production system is established in 2004 as part of the development project
EVOLUTION 2004 and the production lines have been balanced for the contemporary models
of the time. However, the assembly lines havent been revised as new models are added to the
product range, which cumulatively increased the balance losses up to date.
The Work Preparation Group is aiming to rearrange the assembly lines to achieve a lean
production line that fulfills the requirements of the current product range. As the segment that
breaks the uniformity within the production system, restructuring of the pre-assembly line is the
most prominent prerequisite of the desired single production line. This requires a thorough
analysis of the current pre-assembly line operations and elimination of wastes in the whole
process. This work will form the basis for the companys planned future action of changing over
to joint-assembly by merging the pre-assembly and assembly operations in one building.
1.4 Objectives
Through analysis of operations at the pre-assembly line and processes at the corresponding
workstations at MAN Trkiye A.., the objectives of this study are,
1.5 Delimitations
The focus area of this study is only the two-line pre-assembly line that consists of 30 (15+15)
stations in U1 and 8 (4+4) stations in the glass assembly building. No other lines or stations in the
facility except these 38 stations are of concern of this study. Delays in internal logistics are
neglected and it is assumed that all parts are ready at the corresponding stations for assembly on
time. Task times will not be recalculated for all processes but for those that are not known, and
the existing task times will be regarded as the optimum duration for the given processes on the
line.
Tutor
sa Fasth, Ph.D. Candidate, Chalmers University of Technology
1.7 Disposition
This Masters thesis report consists of 9 chapters. Chapter 1 develops a general presentation of
MAN Trkiye A.. and explains the nature and organization of this thesis study. Chapter 2
provides the theoretical framework that this thesis study is built on. Chapter 3 describes the
project steps and applied methodology to carry out this study, and explains the course of the
performed work by presenting the details of the approach to the given problem. Chapter 4
projects the current state analysis of the production system. Chapter 5 analyzes the complications
with the current production system, suggests solutions to eliminate these problems and proposes
the future state mapping of the system. Chapter 6 evaluates the proposed system and investigates
the advantages it yields over the current system. Chapter 7 includes the discussion of results of
the study and generates methodology on how to implement and improve the proposed system.
Chapter 8 concludes the whole report and summarizes what is achieved throughout this study and
Chapter 9 shows the references that are used to complete this study.
This chapter contains definition of common terminology and concepts, and the theoretical
framework of this project.
2.1 Assembly
2.1.1 Common terminology and concepts
A product, according to Askin et al, ([2] p. 1) is any item that is designed, manufactured and
delivered with the intention of making a profit for the producer by enhancing the quality of life of
the customer. Most products are made up of various parts, where a part can be described as a
single unit of a product that are brought together with others to form the finished product.
Assembly, therefore, can be explained as the operation of bringing parts together, either manually
by operators or automatically by robots, to form a finished product. Fixing of more complex parts
that have more than one component before being assembled to the work-piece as a single unit is
called a sub-assembly. A work-piece is an unfinished product whose assembly is in progress.
Warehouses or suppliers
Parts or components Material flow
Sub-assembly stations
Sub-assembly
Assembly stations
Assembly
Figure 2.1 - Demonstration of work and material flow at a 5-station assembly line
8 CHALMERS, Product and Production Development, Masters Thesis 2009
Work station
A (work) station is a segment of the assembly line where a certain amount of the total assembly
work is performed. Each station on an assembly line is set up with all the materials, machines,
tools, jigs/fixtures, instructions and operators needed for the operation(s) assigned. A work-piece
does not return to the station it has already visited at an assembly line. (Baudin [3] p. 86, Scholl
[19] p. 4)
Operation (task)
The assembly process of a product consists of a sequenced set of actions that are applied to the
work-piece as it moves on the line. Each of these indivisible actions is called an operation.
Operator
Who performs an operation on an assembly line is an operator. Operators perform their tasks
either manually by using hand tools, or semi-manually by using automatic tools or task-specific
machines. Minimum number of operators required to complete all tasks on an assembly line is
calculated as,
Minimum number of assemblers= Total assembly time of the product/ Takt time
However, this is only a theoretical calculation and in most cases, due to some restrictions, this
calculation does not give reliable results. For instance,
this calculation gives the minimum number of operators required for the assembly of a
specific product. However, total assembly time of different products processed at the
same line can differ, which results in different assembler demands.
organization of the assembly line is an important factor while defining operator demand, i.e.,
assemblers do other time consuming work than assembly at the line such as material handling,
walking, picking etc. Therefore, assembly time data only is not enough to evaluate operator
demand. (Baudin [3] p. 50)
Material handling
Material handling can be explained as the extra work that a part is subjected to from the time it
becomes ready for assembly until it is assembled. This work includes transportation, storage and
sequencing of parts as well as rework on the parts to be assembled. In an ideal system, a part that
is ready for assembly should directly be transported to the site of assembly in order to eliminate
the extra cost that will emerge for storage and further transportation. Material handling does not
add any value to the finished product and is the greatest source of waste in a production system
that should be minimized.
The product process matrix proposed by Hayes and Wheelwright (1979) describes the dynamic
nature of product and process choices and represents the strategic choices available to firms in
both product and process dimensions. According to Schroeder ([20] p. 64), The diagonal of the
matrix represents a match between the product and process; a low-volume product with high
variety would be produced by a job shop, while a highly standardized product with high volume
would be produced by a continuous process. Any firm operating off the diagonal is likely to have
either the wrong product or the wrong process to remain competitive.
Regarding these aspects; standardized products, high volume production, stable product demands
and continuous supply of material is mandatory for successful installation of flow line systems.
(Scholl [19] p. 2)
Order initiation
Decision of production is customer-oriented; producers define what and how to produce
according to the demand of customers. Producers design production process with three major
strategies; Make-to-Stock (MTS), Make-to-Order (MTO) and Assemble-to-Order (ATO).
In the MTS system, producers specify a product range according to customer demands and the
finished products are stocked. The strategy behind this system is to stock the products that are
assumed to be demanded, and to supply these products immediately on demand. Forecasting,
inventory management and capacity planning play very important roles in this process. Although
Figure 2.3 - Comparison of MTS, MTO and ATO production processes (Schroeder [20] p. 59)
In the MTO system however, products are designed and produced according to customer
specifications. In this sense, MTO system provides higher flexibility for product customization,
but production costs are higher than the MTS system.
The ATO system is in a way a combination of the MTS and MTO systems. In the ATO process,
subassemblies that form the products are Made-to-Stock, and when customer order is received,
the product specifications are configured and final product is Made-to-Order. Modularity in
product design is therefore critical for this production process to be used. (Schroeder [20] p. 58-
59)
2.1.2 Time constraints
The following sections describe different time parameters that exist in a production system.
Operation time
Operation time is the time required to start and finish an operation at a station. (Scholl [19] p. 4)
Measurement of operation time studies are either made manually by stop-watch, or digitally by
image processing techniques. (Scholl [19] p. 5)
Cycle time
Starting from the moment a work-piece is delivered to a station, the required time for all
operations at that station to be completed on that work-piece is called cycle time. Cycle time at a
station is a function of the total operation time and number of operators at that station. (Scholl
[19] p. 5)
12 CHALMERS, Product and Production Development, Masters Thesis 2009
Takt time
Depending on the production plan shaped according to customer demands, number of products
that will leave a production system on a daily basis is a known data. Takt time can simply be
defined as the required time that must elapse between two consequent product completions,
which is also equal to the time for each work-piece on the line taken from its arrival to the current
station until its arrival to the next station. Takt time is a function of product volume and available
production time. (Ortiz [15] p. 48)
From the definition, takt time is the same for all stations on an assembly line, and it should not be
confused with cycle time. Takt time is the time for which a work-piece stays at a station; cycle
time is the time for which operations are completed while the work-piece is at the station.
Takt overdue
The case when all assigned operations at a station could not be completed within the takt time is
called takt overdue.
Idle time
Idle time (waiting time) defines the period in which no operations are held at a station after all
operations are completed and the work-piece stays idle until being moved to the next station.
Since cycle time differs for different stations of a line, idle time is also different for each station.
For individual stations it can be expressed as,
The sum of idle times for all stations of the line is called the balance delay time. (Scholl [19] p. 5)
Tolerance time
The required time for a work-piece to be delivered to the next station after it is processed at the
current station is called tolerance time. (Scholl [19] p. 5)
Throughput time
Throughput time is the total time for a work-piece to enter a production line and leave the line as
the finished product, which is equal to the total processing and waiting times of that production
system. (Scholl [19] p. 25)
Labor productivity
Labor productivity is the amount of output that an operator produces in unit time. This can be
formulated as,
Pa = Fv / Ia ,
where Fv and Ia represents the number of buses that leave the pre-assembly line in a given time
and number of operators at the pre-assembly line respectively. (Slack et al, [21] p. 50)
In bench assembly, the work-piece stays stationary on a bench; all required parts and equipment
for assembly are brought to the bench and assemblers move around the bench to perform the
assembly. (Schroeder [20])
Line assembly is an assembly method where work-pieces move through a sequence of stations for
assembly one piece at a time. (Schroeder [20]) An assembly line is the production system in
which assembly stations are organized in a serial layout and line assembly method is applied.
Figure 2.4 - A section of the bus pre-assembly line from stations D/E 09 to D/E 13
2.3 Flexibility
Schroeder ([20] p. 198) defines flexibility as the time it takes to change volume or product mix
by a certain percentage or amount. From this perspective, the supply chain and the physical
setup of the production system is the determining factor of the flexibility of the whole system.
Production process design has the most crucial effect on the flexibility of the production system.
Slack et al, [21] express this phenomena under the concept of series and parallel process
configurations (or short-fat versus long-thin) and use box analogy as an example shown below. In
the figure, three different arrangement options of the same system are discussed.
Desired output: 16
Number of lines: 4 (= 4 units/cycle)
Number of working hours: 8t
Cycle time: 2t
Desired output: 16
Number of lines: 2 (=2 units/cycle)
Number of working hours: 8t
Cycle time: t Desired output: 16
Number of lines: 1 (=1 unit/cycle)
Number of working hours: 8t
Cycle time: t/2
product mix and volume flexibility increases due to increased number of individual
production lines which may be specialized for different models or which can be closed for
capacity reduction,
the whole system becomes less vulnerable to problems since there are multiple individual
lines and any problems that occur will only affect the corresponding line instead of
affecting the whole line,
cycle times at stations increase since more operations are held due to reduced number of
stations at the line,
risk of making errors for operators increase due to the long cycle times at stations which
reduce attention,
logistics become a more critical issue since there are multiple individual lines,
station working environment becomes less motivating due to the increased number of
operators at the same station,
specialization for operators becomes less possible since the same operator may have to
make multiple operations in a longer cycle time.
Lean production can be defined as the application of lean fundamentals to all levels of a
production system in order to minimize production wastes. It denotes that a company or an
organization works at the most effective level and at a level suited to the purpose in combination
with a relentless pursuit of eliminating waste and all non value adding activities. (IVF [9] p.3).
Baudin [3] highlights the 7 wastes that exist in a production system as,
over-production
process
transportation
excess inventory
motion
waiting
rework
Processing becomes a waste when more work is done than what the customer demands. It is very
difficult to detect process wastes since it requires detailed knowledge of the assembly process.
Transportation is regarded as the movement of operators and stocks around the production
system without any purpose. Since moving does not add any value to the end product, it is a
waste that should be eliminated.
Inventory is a part of production systems, but when anything more than is required to perform the
job is stocked, it becomes a waste. Excess inventory causes extra carrying cost and damage, and
requires extra storage, containers, handling requirement and time.
Motion is not a work, it is thus non-value added. Therefore it causes time loss within the
production process. It is mainly caused by disorganized work sequence of layout and should be
minimized.
Waiting includes waiting for a machine to finish its process, a part or component to arrive from
an upstream activity, or an adhesive to dry. Waiting does not add value to the final product,
therefore it is non value added and should be minimized.
Rework is correcting a faulty operation, which means that additional time is spent for the same
operation twice and makes this operation a waste in the production system.
Value of operation = Value of product after operation - Value of the product before operation
A part of an operation that adds and does not add value to the product is therefore called value-
added and non-value-added operation respectively. To give an example, glass assembly operation
includes steps of unpacking the glasses, laying glasses on tables, sorting glasses in the order of
assembly, holding glasses, assembling glasses and cleaning surfaces. Among the steps of glass
assembly, only assembly of glasses and cleaning of surfaces add value to the final product, which
makes them the value-added steps of the glass assembly operation. The non-value-added rest is
capacity loss that must be eliminated. (Ortiz [15])
Among numerous sources on the subject, the most valid guide on this concept is introduced by
Muther et al, [13] who introduced a systematic approach to production system layout planning
that is organized under six steps. Called Simplified Systematic Layout Planning, this method
suggests,
1- identification of relationships between the elements of the production system and desired
closeness between them,
2- identification of physical space and resource requirements of the elements,
3- graphical expression of findings in step 1 and 2 by emphasizing the desired closeness with
different line weights, i.e. stronger relations are indicated with greater number of lines,
4- laying out the elements of the production system inside the real facility by considering their
specified relationship with each other and the physical structure of the facility itself,
5- creation of different layout proposals for different priorities, i.e. availability for new lines in
the future, lowest cost, etc. and make a selection,
6- detailed planning of the selected plan.
Production is a dynamic process with multiple dimensions, i.e., products, operations, operators,
material handling, production planning, machines, assembly line characteristics etc., and a
production system needs to adapt itself to changes that occur in any of these dimensions as
quickly as possible in order to minimize losses. From this perspective, anything fixed in the
production system is a potential source of loss for the entire system, which should be analyzed
and eliminated within the balancing process periodically.
Figure 2.7 - Demonstration of an unbalanced assembly line of 22 stations (cyclemax= 23.49 min)
Time
Figure 2.8 - Demonstration of a well-balanced assembly line of 22 stations (cyclemax= 3.44 min)
CHALMERS, Product and Production Development, Masters Thesis 2009 19
Idle times at stations are the primary indicators of balance losses at an assembly line. Idle time at
a station shows that there is excess capacity at that station, which is undesired. For a line
producing multiple types of products, variant losses are the main reason for station idle times.
Same operation may require different operation times for different product models, but when the
operator number is fixed at a station for the most complex model and when a less complex model
comes to the station, operators finish their work early and the be idle for the remaining time. As
number of variants produced at an assembly line increases, so do variant losses.
There are also other factors that cause losses that are not related to number of operators or
unequal distribution of operations to stations. These losses are primarily caused by other factors
of the production system and more difficult to determine. Among these factors, supply chain
related losses have the major effect. Supplying wrong parts or incomplete components to the
assembly stations causes operators to leave their stations for looking for those parts or do rework
when they receive them. Besides, the location and packaging of the supplied material seriously
affect the non value added work ratio of the operator at a station, i.e., walking to the parts,
unpacking the parts, sorting the parts, in some cases making the sub-assembly at the station etc.
These losses can be eliminated by improving the supply chain organization of the production
system.
Scholl [19] brings out the two objectives for balancing an assembly line as capacity oriented
goals and cost oriented goals, both of which are directly related to cycle time and number of
stations.
number of stations should be minimized for a given cycle time and cycle time should be
minimized for a given number of stations,
flow time and waiting time of pieces should be minimized,
sum and percentage of idle times over all stations should be minimized.
He also indicates investment and operating costs should be minimized, and identifies some of
these costs as,
Operations are classified as series and parallel, implying that series operations must be done one
after the other and parallel operations can be done at the same time without interfering each other.
After the precedence relation is determined, distribution of operations to stations and to operators
at stations is held according to the order and classification of operations. Figure 2.9 features an
example precedence diagram of 10 operations. Operation 2_1 is the predecessor of all the
following operations; after 2_1, 2_2 and 2_5 can start in parallel. 2_2, 2_3 and 2_4 are series
operations. Operation 4_4 can only be made after 4_1, 4_2 and 4_3 are completed.
The first and most critical limitation about performance of operators making manual assembly is
explained by Ortiz [15] as 85% rule, which simply suggests cycle time at a station not to exceed
85% of the takt time. According to Ortiz ([15] p. 49), Operators cannot work at optimum rate or
speed, 100% of their shift, or they will become less productive, create more defects, become
injured, and miss more days on the job. A realistic operator load of 85% allows for a smooth and
efficient flow of product, without jeopardizing quality, productivity, or health. The 85% loading is
not slow; it simply allows operators to work at a productive rate, which results in properly built,
quality products.
supplied materials should be ready to assemble and positioned at arms reach or behind the
operator which can be reached by simply turning behind
working environment should allow the operator to use both hands during operations
and work instructions should be clearly stated; assemblers should not spend time thinking
about how to make the assembly. (Ortiz [15] p. 82)
Different takt times require different job designs in terms of operator performance. (Baudin [3] p.
55) explains this as For instance, at very short takt times the work is too repetitive which threats
human endurance and causes repetitive stress injuries, while at very long takt times it is not
repetitive enough for the assembler to fall into a routine that he or she can follow without having
to think about it.. Operators run the risk of forgetting where they are and skipping a step by
mistake. Therefore, while assigning tasks, physical and mental capacity of operators should be
considered as well as the ergonomic requirements of the tasks.
2.6.3 Bottleneck
Schroeder ([18] p. 288-289) defines bottleneck as, a work center whose capacity is less than the
demand placed on it and less than the capacities of all other resources. A bottleneck resource
will constrain the capacity of the entire shop and an hour added to the bottleneck will add an
hour of capacity to the entire factory. An hour added to the non-bottleneck work center will not
help the schedule at all since the excess capacity exists there.
A bottleneck station determines the capacity of the whole production system; in a balanced
assembly line, if 5 minutes of work is added to the tasks of a station, all the following stations
will have to wait for 5 minutes for all assembled products. This shows that, in fact each operator
on the line is a bottleneck for the line and it is of crucial importance to eliminate the balance
losses for maximizing line capacity. (Baudin [3] p.173)
Number of joker workers at an assembly line is determined during balancing of the line regarding
the workload at the line. Instead of keeping a fixed number of operators at stations for complex
but rare models, in order to eliminate idle operators at the stations, fixing the least number of
operators to stations and providing the extra labor on demand by joker workers is a better option
in terms of station efficiency. On the other hand, it is not acceptable to have idle joker workers at
the facility when they are not needed at the main line. Therefore, the number of joker workers and
how to use them when they are not doing assembly work should be well-planned.
22 CHALMERS, Product and Production Development, Masters Thesis 2009
2.7 Sustainability
The term sustainability has been spelled for the first time in 1974 in the World Council of
Churches and highlights the importance of maintaining the living and non-living resources of our
planet. In 1987, Gro Harlem Brundtland, who was the Norwegian Prime Minister and the UN
World Commission on Environment and Development Chair of the time, published the report
Our Common Future, where the idea of sustainable development has been introduced for the
first time. This idea can be basically summarized as the development that meets the needs of the
present without compromising the ability of future generations to meet their own needs.
Sustainability can be maintained in the three main domains; economy, society and environment,
which are also known as the three pillars of sustainability. The relationship of these three pillars
is expressed by Porritt ([16] p.46) such that The economy is, in the first instance, a subsystem of
human society, which is itself, in the second instance, a subsystem of the totality of life on the
biosphere. And no subsystem can expand beyond the capacity of the total system of which it is a
part. According to Adams [1], however, these pillars have cooperative relationship with each
other unlike being subsystems of each other.
Figure 2.10 - Relation of three pillars of sustainability according to Porritt (left) and Adams (right)
The resources that are used for technological developments, industrialization and supporting the
needs of increasing population are not more than what is provided by the planet we are
occupying. Considering that the resources of the Earth are used above sustainable limits, in order
not to edge away from a livable world for both ourselves and the following generations, every
operation should be evaluated from the sustainability perspective. The main aspect of doing so
should be to use the energy and raw material sources in the most efficient and effective way.
The objectives of this project, which are to restructure and balance an existing assembly line,
requires a set of compulsory procedures to be followed in order to achieve reliable results. First of
all, it is crucial to have a complete list of operations of the assembly line and their times, because
this data is the basic reason for a line to exist, and evaluation of the balance of a line cannot be
made without this data. As the next step, it is important to evaluate the balance losses of the
existing line for determination of factors that cause these losses. Finally, after eliminating these
factors, the assembly line is structured according to desired specifications.
This first section of this chapter introduces the stages of the project and highlights the steps taken
at each stage. In the second section, the applied methodology to carry out this study is portrayed
in a detailed structure.
Introduction
data mining
time studies
observations
interviews
The theoretical basis and the application of these methods are described in the following sections.
3.1.1 Data mining
Data mining can be defined as collecting the information that will be used throughout the work to
be conducted. Quality of collected information, which is defined by McGilvray ([12] p. 12) as
The data of pre-assembly operations of vehicles of interest has been collected from the summary
sheets provided by the Work Preparation Group and different databases within the factory.
However, encountered unconformities between different sources indicated problems with
updating of the databases, which reduced the reliability of the collected data for a line balancing
procedure. Therefore, having the data from these sources as the guideline, three additional data
gathering techniques have been applied to complete and verify the information to be used
throughout this study.
Standard operation times for tasks held at the bus pre-assembly stations are provided by the Work
Preparation Group as Standard Operation Forms (SOF). An SOF is a company-specific data sheet
that includes detailed analysis of individual operations with their steps and times. For tasks that
do not have this information, time studies are made at the stations by using stopwatch and
applying the procedure given by Glassey [8], which is explained in the following section.
In order to keep the cycle times at stations 85% of the takt time as indicated by Ortiz [15], all
operation times are increased by 15% so that this distribution ratio would be included for each
operation during the balancing task.
3.1.3 Observations
Observations have been a supplementary method to double-check the data of operations lists that
was provided by the Work Preparation Group, and to make time studies for operations whose
times were not recorded/updated on the summary sheets.
Operations lists were completed by visiting the stations with the summary sheets of the
corresponding stations, and matching the assembly operations with the items listed on the
existing sheets. Any difference between the operations and lists were recorded and asked to the
team leaders for confirmation of the actual information.
3.1.4 Interviews
Interviews have been the greatest investigation tool for verification of the operations lists and
provided the critical ideas that affected the decisions taken throughout this study.
Bunting [5] indicates a range of interview question types that are determined according to the
information sought during the interview. The interviews made in this project aimed validating
data and figuring out if the theoretical assumptions could be applicable in the shop floor. From
this perspective, the questions that lead the interviews were either closed or probing open
questions.
Closed questions, which can be regarded as yes-no questions, were used during the initial
interviews held at the line with the operator team leaders while performing the verification of
operation lists. The purpose of those interviews was to check if there is an inconsistency with the
acquired operation lists from the management and the assembly operations at the stations.
The second set of interviews aimed to receive more detailed information from the team leaders
and assembly operators about operations, and to dig deeper in order to reveal as much about the
limitations as possible. Being the most experienced about the operations, each of the ten team
leaders were asked about indeterminate constraints that define precedence, and the operations
whose times were not possible to reduce by increasing number of operators. Besides, assembly
operators that were selected randomly at the line according to the complexity of the operations
they handled were asked about the steps of their work and if they had any suggestions for
improvement. Therefore, the prepared questions for these interviews were open, which allowed
them to tell as much about the operations as possible.
The most critical information required for this software to generate reliable results is the
precedence relation of operations. The software assigns operations to stations according to the
precedence of tasks. If this relation is defined incompletely or not correctly, violation of task
sequence during assignment of tasks to stations is inevitable. This problem becomes more serious
when dealing with the sequence of hundreds of operations, i.e., the number of bus pre-assembly
operations for the least complex bus model was 536. The precedence graph of first 99 operations
of A21 model is as shown in figure 3.2.
At the assembly line that is to be analyzed, the assembly of 16 different bus types and their
variants is handled. Even though similar processes are applied to all vehicle types, there are some
processes of different operation times for different vehicles, or some type-specific processes for
vehicles. Therefore it is of great importance to clarify and consider these differences while
maintaining the line balance.
The method applied to perform the balancing study at the bus pre-assembly line is stated below.
2. The operations applied at these stations are crosschecked with the process lists of the Work
Preparation Group and a complete process list of the pre-assembly line is prepared. This is
done in two steps.
The existing process list of the assembly line is divided according to their distribution to
stations. These lists are printed out and taken to the corresponding stations. The processes
applied at the stations are both visually observed and also checked by interviews with the
operators at the stations so that the missing / misaddressed / readdressed operations are
determined and updated on the list.
Factory database is used to enlist all materials that are addressed to the pre-assembly
stations for assembly. This database shows which item is addressed to which station in the
factory for all vehicle models. This list is used to check the assemblies at the pre-assembly
stations through the items that are addressed to these stations for assembly.
3. This updated list shows all processes that are applied at the pre-assembly stations. However,
there are operations that differ for different vehicle models (i.e., only coaches have WC
assembly or only CNG vehicles have CNG tank assembly) and also some similar operations
are completed in different durations for different models (i.e., task time of electrical systems
assembly of city buses is nearly half of that of coaches). Therefore a complete process list for
all three vehicle types of interest is prepared by using the updated process list.
4. Operation times and number of operators for all processes of each of the three vehicle types
are calculated. This is done by checking the existing operation time list and making time
studies for missing operations.
D / E 01 D E Toplam
YAPILAN LER
2 ARA ALMA
7 VAKS TAPASI
17 KAYAK TUTUCUSU
18
19
20
Yorumlar:
Comments
Figure 3.3 - Station operation list template prepared for and to be completed at D01
83.#0H10.0015 TAVAN PLAKALAMA ,TAVAN 88.73110.4101 TAVAN 900100 D01 TAVAN MONTAJI
YAN PARCASI ,PLASTIKTEN KAPLAMA
88.#05R0.0019 ON ISITICI AURORA Klimator 83.72010.6110 IZOLASYON 300100 D01 FRONTBOX IZOLASYONU
R134A Aurora
88.#05R0.0019 ON ISITICI AURORA Klimator 83.72010.8835 IZOLASYON 900100 D01 N ISITICI FRONTBOX
R134A Aurora MONTAJI IZOLASYONU
88.#05R0.0019 ON ISITICI AURORA Klimator 83.77915.0581 KAPATMA 200108 D01 N ISITICI FRONTBOX
R134A Aurora KAPATMA
88.#05R0.0019 ON ISITICI AURORA Klimator 88.77901.8012 ISITICI 900100 D01 N ISITICI FRONTBOX
R134A Aurora MONTAJI MONTAJI
88.#05R0.0019 ON ISITICI AURORA Klimator 88.77971.6092 KLIMA BORU 200100 D01 N ISITICI FRONTBOX
R134A Aurora MONTAJI MONTAJI
88.#3510.0041 ANTEN,RADYO ICIN ,D/E VE 83.73110.4567 ILAVE RESIM 900100 D01 ANTEN MONTAJI
GPS BAGLANTILI
Figure 3.5 - Station summary report for D01 from factory database
5. Analysis of the balance losses at the current line is made with this information.
For the next step of the work, which is to reorganize the production line and balance the
operations at the stations, further studies are made and added to the existing data, which is to be
used for running ProBalance.
6. In order to achieve a leaner assembly line, sources of wastes at the production process are
determined.
7. Operations at the stations are analyzed and improvement options such as removal of stations,
merging stations or cancelling processes by improving prior operations etc. are evaluated.
9. Clusters are created in ProBalance for related tasks and these clusters are sequenced
according to their precedence relationship. The purpose of this is to collect similar tasks
under the same clusters and making mapping the precedence of operations easier since total
number of tasks reaches a few hundreds.
The master precedence graph is mapped by applying the following procedure. Example figures
are used for demonstration purposes.
Precedence among tasks belonging to different groups is mapped and master diagram is
prepared.
10. A data sheet template for collecting the required data to run ProBalance is prepared. This
template is shown in figure 3.12.
11. In order to collect the required data for running ProBalance, a weekend workshop is
planned and arranged with the attendance of production engineers and 10 operator team
leaders of the pre-assembly line, and Work Preparation Group.
Notes
Page number
Date
Zone guide
participants are informed about the running procedure of line restructuring and balancing,
participants are informed about how line balancing will be done, and a short presentation
of ProBalance is made,
On the first day of workshop, all team leaders are provided with complete task lists, empty data
sheets printed on A3 size paper, and large vehicle code schemes. They are expected to write
down all tasks under their control, to put a cross for the equipment used to perform the
corresponding operation, indicate the task time and number of operators doing the task, indicate
which group (cluster) that operation belongs to and order of the preceding task. All tasks on the
complete list are given an individual number so that addressing of tasks are standard and less
confusing for later work.
critical
13. All collected data is sorted on Microsoft Excel and input to ProBalance.
This chapter contains the current state analysis of the bus pre-assembly line by focusing on
certain characteristics such as production process and operations, workload of operators,
current layout and balance of the line.
Each department is responsible from the segment of the production line where the processes
under their control are held and each of these sections is regarded as independent lines. That is,
there are 5 consequent lines in the factory that make up the bus production line. Chassis
assembly, paintshop and bus pre-assembly lines are located in building U1, and bus assembly and
bus finish lines are located in U2 and U3 respectively. All lines except the bus pre-assembly line
are single assembly lines. Bus pre-assembly line functions with two parallel lines D and E.
Working process inventory of the whole bus assembly line including buffers- is 225 units,
however, current number is 287 because of the pauses in production due to the global economic
situation. This difference is caused by the increased number of vehicles waiting at the buffers.
Among the 5 lines, bus pre-assembly line has the highest working process inventory with 38
buses.
Production is low-volume with about 2000 units per year. There is no automation throughout the
production process. Conveyance between stations is unpowered. All tasks -including moving the
vehicles to the next stations- are performed by human operators.
Product variance is high. There is no limitation for distribution of products and their variants to
lines; assembly of each bus model can be handled in both lines. City buses, intercity buses and
coaches of MAN and NEOPLAN brands, making 16 different bus models, are produced on the
same line. Every single vehicle is configured individually due to customer requests, which
increases the complexity of the assembly process. Task times vary for different bus models, i.e.,
roof wiring for A21 takes 180 minutes/operator while it takes 60 minutes/operator for P22.
There are no joker workers. Division of labor among operators is high, which makes replacement
for absent operators problematic.
Material flow within the factory is managed with the KANBAN system. Produced and
outsourced parts are collected in the warehouses and distributed to the stations by the internal
logistics unit just-in-time. No outsourced parts are directly delivered to the assembly location.
The main problem with the logistics is the missing parts, which results in the operator to leave
his/her station, walk to the warehouse and take the part himself/herself. Frequently, this causes
takt overdue, causing the operator to leave his station and complete his/her work in the next
station. For circumstances when the missing part is not in the warehouse, in order not to stop
production, the assembly continues with that part missing, causing a rework after it is received.
Manual material handling needs are high, having a dramatic effect on the efficiency of assembly
process, i.e., before assembling the glasses, two operators take out the randomly packed glasses
from the commissioning trolleys of the supplier onto the glass holding tables, after that they need
to sort these glasses in the order of assembly because glasses need to be assembled in a pre-
defined order, and only then they can take them and assemble.
Production process is built on assemble-to-order system; every bus is taken to the line after they
are configured individually by their customers and the payment is made. Production capacity of
the factory is planned for 8 vehicles per day. Daily working time is 520 minutes. Takt time is 65
minutes and throughput time is 15600 minutes for the whole line. Buffers are the primary reason
for this long throughput time. In the two line bus pre-assembly line only, this takt time is applied
as 130 minutes. The line delivers two vehicles in 130 minutes, one of which is directly delivered
to the bus assembly line of takt 65 minutes while the other vehicle is taken to the parking area for
waiting. In the next takt, while the operations in the pre-assembly line continue, this waiting
vehicle is delivered to the assembly line. Throughput time for the bus pre-assembly line is 2470
minutes.
The reason for the bus pre-assembly line to operate as two parallel lines is the time requirement
for operations that take longer time than the takt time. These processes are mainly indivisible, i.e.,
waiting for adhesives or isolation tools to dry, and due to the precedence relations of the
operations, it is not possible to start the following process while the previous is in progress, i.e.,
wiring cannot begin before piping is completed since both systems are installed to the same
sections of the vehicle that do not allow two operators work together.
Layout
The current layout of the pre-assembly line in U1 and the glass assembly buildings is as shown in
figure 4.1. A higher resolution layout can be found in appendix.
Station D/E 15 is the last pre-assembly station in the U1 building. Stations D/E 16-17-18 and 19
of the line are located in the glass assembly building, which is approximately 30 meters to the U1
building. From D/E 15 to D/E 16, again fork-lifts are used to pull the buses in between these
buildings. At D/E 19, bus pre-assembly operations are completed and the vehicles are started.
Buses are therefore driven to the Bus assembly line when the operations in the Bus pre-assembly
line are completed.
PAINTSHOP
Table 4.1 - Tasks held in the sub-assembly and assembly stations at the Bus pre-assembly line
Pre-assembly Sub-assembly
Definition Definition
Station Station
D / E 01 Roof cover assembly D50 Door handle preparation
D / E 02 Protective wax assembly D51 Roof air conditioner pipes preparation
D / E 03 Brake system preparation D52 Side plate preparation
D / E 04 Brake system assembly D53 Piston, mudguard support, light holders, mudflap preparation
D / E 05 Electrical system assembly D54 Lift and maintenance covers preparation
D / E 06 Roof filling and switch board assembly D56 Roof preparation
D / E 07 Axle assembly D57 Oil pipes and clutch pipes preaparation
D / E 08 Floor board adjustment D59 Heater pipes preparation
D / E 09 Floor board and engine assembly D60 Polyamide brake pipes preparation
D / E 10 Air conditioner compressor assembly D61 Isolation preparation
D / E 11 WC and roof isolation assembly D62 Brake valves preparation
D / E 12 Door handle - aspirator - air conditioner gas pipes assembly D63 Electrical systems preparation
D / E 13 Papering D65 Wheel preparation
D / E 14 Oil-cloth assembly D67 Axle preparation
D / E 15 Oil-cloth welding and baggage side profile assembly D70 Glass preparation
D / E 16 Glass assembly D71 Oil cloth preparation
D / E 17 Pedal assembly and air conditioner gas leak test D72 Engine preparation
D / E 18 Vehicle start - Quality control D73 Fuel tank and air conditioner compressor preparation
D / E 19 Rework D74 Radiator preparation
D75 Brake - steering hydraulic pipes preparation
D76 Steering wheel and pedal preparation
D77 Webasto preparation
D78 Piping preparation
D79 Baggage covers preparation
Work flow diagram of the bus pre-assembly line is as shown in figure 4.3.
Figure 4.5 - Material flow to the assembly stations from the sub-assembly stations
44 CHALMERS, Product and Production Development, Masters Thesis 2009
Number of operators
The number of assembly operators -excluding 10 team leaders and 30 sub-assembly station
operators- is 193. Team leaders are excluded because they do not make any assemblies on the
line. 48 of these 193 operators perform electrical system assemblies, 24 of which work at stations
D/E 05 and D/E 06. Other 24 of the 48 operators are assigned to station D/E 17, but according to
the precedence of their work, they work along the whole assembly line.
Total cost of one operator is calculated by the production management to be 16,09 /hour.
Piping
Wiring
Floor board assembly
Axle assembly
Engine assembly
Roof assemblies
Oil cloth assembly
Glass assembly
Floor board assembly can only be made after all piping and wiring is complete in the vehicle,
because after the floor board assembly, it is not possible to reach the pipe and wire assembly
points. Also, the vehicle has to be on four wheels instead of the donkeys and the engine has to be
assembled, because forces acting on the chassis are different in these two cases that result in
different bending characteristics and floor boards should be assembled in natural loading
conditions.
All infrastructural piping and electrical systems should be assembled before the axles and the
engine; later assembly of these parts is not possible due to space limitations.
Engine can only be assembled after the axles and with the vehicle on our wheels, because its
weight does not allow it to be assembled when vehicle is carried by another equipment such as a
lift due to safety issues. Not being able to assemble axle connection rods due to space limitations
is another reason for this precedence relation.
Glasses should be assembled after the oil-cloth due to working safety issues. Solvent-based
adhesives and other harmful gases that arise during fixing the oil cloth requires this operation to
Considering each group as a different layer, the order and precedence relation of assemblies is
shown in figure 4.7.
Station times
Total operation times and station times for A21, P22 and R13 models at the pre-assembly line is
shown in table 4.3. Colors indicate the stations with takt overdue for the corresponding vehicle
model.
Table 4.3 - Station times for A21, P22 and R13 models
Station D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 D18 D19 Total
Number of operators 4 1 8 4 8 10 6 2 10 3 3 3 2 5 5 6 14 1 2 97
Total operation time 505 105 890 935 1645 1529 397 400 1014 250 1156 361 130 940 508 640 1789 520 490 14204
A21
Station time 126 105 111 234 206 153 66 200 101 83 385 120 65 188 102 107 128 520 245 3245
Total operation time 596 110 840 775 794 1347 587 539 1124 520 1035 486 175 897 655 830 1954 520 490 14274
Operation time
P22
Station time 149 110 105 194 99 135 98 270 112 173 345 162 88 179 131 138 140 520 245 3393
Total operation time 647 110 1009 795 1285 1315 567 574 1090 330 875 522 175 677 290 700 1573 520 490 13544
R13
Station time 162 110 126 199 161 132 95 287 109 110 292 174 88 135 58 117 112 520 245 3230
Total operation time 583 108 913 835 1241 1397 517 504 1076 367 1022 456 160 838 484 723 1772 520 490 14007
Average
Station time 146 108 114 209 155 140 86 252 108 122 341 152 80 168 97 121 127 520 245 3289
Idle times and takt overdue at stations for A21, P22 and R13 models at the pre-assembly line is
shown in table 4.4. Colors indicate the maximum values for the corresponding vehicle models.
Table 4.4 - Idle times and takt overdue at stations for A21, P22 and R13 models
Station
Total
D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 D18 D19
Idle time 4 25 19 X X X 64 X 29 47 X 10 65 X 28 23 2 X X 315
A21
Idle time
Average
X 22 16 X X X 44 X 22 8 X X 50 X 33 9 3 X X 208
Takt overdue
16 X X 79 25 10 X 122 X X 211 22 X 38 X X X 390 115 1027
Takt time: 130
Time unit: minutes
Takt overdue is the common problem for all vehicle models with an average of 1027 minutes,
which usually results rework requirement for almost each bus that leave the pre-assembly line.
D18 is the most problematic station from this aspect with 390 minutes of overdue for all three
models.
This chapter includes analysis of stations at the bus pre-assembly line for determination of wastes
and solution proposals for elimination, and generation of the future state structure of the line.
Determining wastes at a production line is a time-taking and complicated procedure that requires
deep analysis of each operation in detail, which was not the target of and cannot be completed
within the time limits of this project. Thus, the focus has been set on the most significant
operations at each station that are not appropriate pre-assembly operations; non value added parts
of individual operations such as walking, processing or material handling are neglected.
5.1.1 Bottlenecks
Pre-assembly operations are infrastructural; assembled parts are complex and have many
components, and most of the assemblies are made along the whole vehicle, which increases
operation times. Precedence relation of the assembly elements is strict, not allowing other tasks to
be made at the same time. In addition to the general characteristics of the pre-assembly tasks,
high and changing product mix results in multiple and shifting bottlenecks to emerge on the bus
pre-assembly line.
The primary reason for the bus pre-assembly line to have multiple and shifting bottlenecks is the
fixed number of workers at stations combined with wide product range; different models require
different operation times for same tasks, but fixed number of workers cannot provide the required
flexibility at the line. Besides, strict specialization of the operators at stations does not allow on-
demand task assignments. Thus, depending on the vehicle models on the line, all pre-assembly
stations can become bottlenecks. This also results in the idle times to vary at stations typewise.
50 CHALMERS, Product and Production Development, Masters Thesis 2009
5.1.2 Wastes
Determination of wastes
High frequency of non value added operations is the main problem that is observed at the bus pre-
assembly line. Besides, task-specific station setups such as cabins or lifts on the pre-assembly
line do not allow task assignment to stations with such equipment due to ISIG, which increases
balance losses. In order to maintain a well-balanced assembly line, stations with high idle times
and operations that require additional labor and high material handling rates should be eliminated.
The operators should only grab and assemble their parts, not do any additional labor for the
assembly.
Station 1
Roof cover assembly: Raising and lowering of the vehicle for the roof covering operation does
not allow any other assemblies to be made at D/E 01 due to ISIG issues, causing balance loss on
the line. Besides, non value added work ratio is almost 20% of the whole operation; preparation
and assembly durations are 35 minutes/person and 165 minutes/person respectively, which
corresponds to a total work of 200 minutes/person.
The vehicles are taken to the bus pre-assembly line from Park 1 with roof open. With no roof
cover, buses are vulnerable to corrosion due to contact with rain and snow. Also, because cutting
operations that are held after the vehicle leaves the paint shop harms the surrounding painted
surfaces, there is a risk of corrosion at locations such as ventilation cover housing, roof side plate
and air conditioner gas pipe routes. It takes 15 minutes to re-paint these surfaces that are harmed
during operation. Also, for the cover gluing procedure to be correct, the glue has to be waited for
drying for 120 minutes. In the meantime no other assembly operations on the roof can be started.
Station 2
Anti-corrosive wax application: Waxing application is held at 3 different parts of the bus
assembly line; in the paint shop wax is applied inside the profile bars; in the pre-assembly line on
axles, under-pipe and front instrument panel areas; and at vehicle finish to whole underbody and
front instrument panel area of the vehicle. However, this operation is the most obvious bottleneck
operation on the bus pre-assembly line. It requires a ventilated cabin for application for a task of
90 min/person, and when waxing is in progress, no other task can be handled at that station.
In order to prevent the ground to get dirty during application, protective foils are used. The cost
of this material is 2000-2500/month. There are also additional cabin management costs of
maintenance, ventilation and cleaning. Besides, the sticky nature of and the dirt caused by the wet
wax cause motivational problems for the workers, i.e., it is a problem to select the operators who
will pull the vehicle to D/E 03 from D/E 02 because of the risk of getting waxed.
Applied wax does not dry for the next takt, which also affects quality of the tasks in the following
stations, i.e., while assembling a part, wet wax on the surfaces may be removed when an operator
touches the vehicle, affecting the visual quality of the product negatively. Because wet wax
shrinks after drying, errors occur in the assembly torque values of tubes and valves assembled at
D/E 03.
Station 6
Roof filling assembly: Roof filling assembly is filling of the gap between the pecolite roof cover
and the vehicle body by an isolation filling. Drying time for this material is about 240 minutes.
Long drying time does not allow following roof work to be held at the same station, causing the
need another lift in the following stations. Besides, during the assembly of heavy parts such as
CNG tubes or the air conditioner, this part is damaged, causing a rework.
Webasto assembly: Webasto is the preheater for the engine that helps the engine start at cold
weather conditions. It consists of multiple components that are put together at the assembly
station before assembly, taking 60 minutes/operator.
Station 8
Engine preparation: Before the engine assembly, some work such as the assembly of engine
holders to the engine block and engine to gearbox mechanical connection is made at this station.
This is an operation of 20 minutes/operator.
Floor board adjustment: Floor board adjustment operation is the cutting of the floor cover boards
according to the shapes of the chassis until they fit together inside the vehicle. It is a time
consuming process that cannot be regarded as an assembly operation; there is an adjustment
labour of 112 minutes per 1 workers for a single vehicle. Besides, thesawdust that arise during
this operation creates a dirty working environment at the line.
For intercity vehicles, primarily baggage compartment floor boards are adjusted. For city
vehicles, even though floor boards are received cut according to the technical drawings, work of
60-80 minutes/operator is required for adjustment. The primary reason for this problem is the
incorrect technical drawings of the floor boards that are provided to the suppliers.
Station 10
Air conditioner preparation: The top covers of air conditioners and CNG tubes are mounted on
the ground next to the vehicle before they are raised and assembled onto the vehicle. This is not a
suitable case since assembly line operators spend their operation time for preparation of the part.
Station 12
Papering: After the floor boards are assembled, in order to prepare the vehicle to oil cloth
upholstery assembly, the surface of the boards should be cleaned and perfected. This is done by
papering the inner surfaces of the vehicle. However, the dust that arises during this application
creates a cloudy environment at the pre-assembly line. Literally it becomes impossible for one
operator inside the vehicle to see the other working at the back of the vehicle. For this reason, no
other assemblies can be assigned to this station because of ISIG issues.
Station 16
Glass assembly: Glasses are delivered to the corresponding assembly stations D/E 16 with the
packaging received from the supplier. However, these glasses are randomly packed. Operators at
the stations first unpack these glasses and lay them on the glass holding tables. Secondly,
according to the assembly sequence specified, they order the glasses again. The assembly of
glasses start after this non value added, 30 minutes/operator time.
Solution proposals
Station 1
Roof cover assembly: The roof cover assembly can be made at the chassis assembly department
before the Paintshop. With the roof covered, direct contact of snow and rain water with the
vehicle will be prevented. Besides, since any possible damage given to the profile bars during
cutting will be followed by the painting procedure at the Paintshop, risk of corrosion will be
prevented. Vehicles will not be raised and waiting time for the glue will be eliminated, which will
result in assigning following roof tasks as well as other operations to station 1. In addition, flow
time of 15 minutes/vehicle will be gained because of the eliminated operation of re-painting.
Station 2
Anti-corrosive wax application: Application of the anti-corrosive wax at the Paintshop together
with the profile wax may be a solution to remove this task from the pre-assembly line. There are
many advantages of this action for the pre-assembly line, the most important of which is
removing the wax cabin from the line and gaining of 1 station. Removing the cabin will save
about 2500/month and the additional cabin maintenance costs.
There will not be any management costs for this transfer operation because there is already a
cabin for waxing at the Paintshop. This will also improve product quality since all pre-assembly
waxing operations will be made in a single cabin, and also visual quality will be improved. For
the following assemblies, because wax will be dry when vehicles enter the line, correct torque
values will be achieved in the mechanical assembly areas.
Station 3
Piping: The polyamide brake tubes and smaller connection tubes can be grouped and prepared as
a single system at a sub-assembly station before being taken into the vehicle so that only the
assembly operation can be held inside the vehicle by the operators.
Webasto assembly: Webasto can be assembled at a sub-assembly station and can be brought to
the station as one piece so that 60 minutes of gain can be maintained.
Station 8
Engine preparation: Engine preparation work can be made at the engine sub-assembly station
and the time spent for this task by the operators can be gained.
Floor board adjustment: Floor board adjustment operation should be removed from the bus pre-
assembly line by updating the drawings that are provided to the suppliers and increasing the
tolerance values on the drawings so that only the assembly of floor board is made on the
assembly line.
Station 10
Air conditioner preparation: This operation should be handled at a sub-assembly station and the
operators should only perform the assembly operation at the line.
Station 12
Papering: Since it is not possible to remove this operation from the line as long as oil cloth
assembly remains, a task specific vacuum system that is adapted to the papering equipment
should be designed and used at this station.
Stations 14-15
Oil cloth upholstery assembly: These cabins can be removed by using water-based adhesives, or
receiving the floor boards covered with oil cloth upholstery. The second option would also help
removal of the papering operation from the line.
Station 16
Glass assembly: In order to reduce material handling in this operation, glass supplier should be
informed about the sequence of glass assembly and asked to pack the parts in that order.
Restructuring of the bus pre-assembly line, however, has constraints that do not allow the
balancing and layout planning procedures to be followed independently. The primary constraints
that affect the course of the process are time and cost parameters that are defined by the
production management. That is, the operating pre-assembly line is expected to be replaced by a
new pre-assembly line preferably without stopping the production system with the lowest
possible amount of re-organization cost.
These constraints caused the balancing and layout planning procedures to diverge from the ideal
approach to the problem and to gain a more practical and case-oriented characteristic. The
determined strategy to design the new pre-assembly line turned out to be,
1. keeping the monumental resources that are time consuming and expensive to remove at
their existing locations so that transition time and reorganization costs are kept minimum,
2. evaluating alternative station layouts by considering the stationary equipment and trying
not to exceed the physical area on which the current pre-assembly line is located,
3. balancing the line by considering these stationary equipment at those positions and the
corresponding stations.
The greatest challenge with this strategy was to be forced to handle stationary resources together
with layout options and balancing work, which made it very complex to come up with reliable
solutions. Any change with the station layout changed the arrangement and thus the order of the
corresponding stations that overlap the stationary resources, which caused the distribution of
operations to be reviewed completely. Although ProBalance provided great flexibility with
modifying station data, since the software was not able to generate the optimum solution due to
the station constraints and the optimum balance required time consuming manual manipulation, it
became mandatory to set the station layout prior to balancing the line.
The method applied to balance the new system has been, after fixing which station has which
monumental constraint, letting ProBalance generate the initial line balance and to manually
manipulate the distribution of operations afterwards by considering the precedence relations.
Although an ideal approach to plan the layout of the pre-assembly and sub-assembly stations
suggests planning the whole system from scratch according to their relationships among with
other, it was not possible to do that due to constraints about time and costs.
By using the layout planning method suggested by Muther et al, [13] up to an extent, the layout
plan of the new pre-assembly line is generated. The main concerns while planning the layout has
been,
using the area of the previous line while planning station positions for the new line,
positioning the stations by considering the positions of monumental resources,
positioning the sub-assemblies as close to their main assembly stations as possible.
Figure 5.4 - Layout plan of the sub-assembly stations at the pre-assembly line
Figure 5.5 - Material flow from the sub-assembly stations to the main assembly stations
The main problem can be summarized as following. The assemblies that require these equipment
has to be made at the same physical location as before. Taking the Kumbruch lifts as an example,
when a different layout is proposed, the station number that these lifts correspond to changes, i.e.,
if it corresponds to station 10 in one plan, when the plan is changed, it may correspond to station
9. However, in order to run the balancing procedure, all station information has to be exact. That
is, the software distributes the operations among stations by taking station equipment into
account. Besides, since the balancing work required manual manipulation afterwards for every
case, it would be loss of time to repeat the procedure for every layout option. Considering that
there are 6 critical equipment that have to be considered, the situation becomes even more
complicated. Therefore, since the primary limitation was the layout, it was determined first.
Another issue has been determining the sub-assembly organization. Although the operations that
are held each sub-assembly are known, which assembly stations they would feed in the new line
were not known since the station setup was not yet determined. Therefore, having balanced the
line according to the assembly station layout, the layout of the sub-assemblies and material flow
from them is planned after the balancing operation.
The assembly and sub-assembly stations of the new pre-assembly line are shown in table 5.1.
The distribution of operators to stations and balance graphs of the two cases of minimum and
maximum number of operators are shown in table 5.9 and figures 5.7 and 5.8 respectively.
Table 5.2 - Distribution of operations to stations and operator demand for A21, P22, R13 models
A21 P22 R13
Station Number of Station Number of Station Number of
Station
time operators time operators time operators
D01 696 11 689 12 764 13
D02 415 8 414 8 426 8
D03 530 9 485 9 505 9
D04 940 16 811 15 840 14
D05 618 11 461 8 485 9
D06 828 13 645 11 659 13
D07 641 11 679 12 691 12
D08 290 5 287 5 295 5
D09 235 6 235 5 235 5
D10 181 4 240 4 241 4
D11 325 5 390 6 389 6
D12 536 9 727 13 688 12
D13 409 7 458 8 362 6
D14 110 2 120 2 120 2
D15 155 3 180 3 180 3
D16 430 7 513 9 380 7
D17 565 10 432 8 296 6
D18 871 15 858 15 741 13
D19 734 13 625 12 565 10
D20 330 6 325 6 320 6
D21 300 5 283 5 285 5
D22 80 2 120 2 120 2
Figure 5.8 - Balance of the line for the maximum required number of operators
Takt overdue 3 X X X X 4 X X X X 5 0 X X X 1 X X X X 0 X 13
Idle time 3 8 6 6 2 1 3 3 13 0 X 4 3 0 0 3 6 3 8 6 3 0 81
P22
Station time
Takt overdue X X X X X X X X X 0 5 X X 0 0 X X X X X X 0 5
Idle time 1 7 4 0 6 9 2 1 13 0 X 3 0 0 0 6 11 3 3 7 3 0 79
R13
Takt overdue X X X 0 X X X X X 0 5 X 0 0 0 X X X X X X 0 5
Average
Idle time 1 8 4 2 4 3 2 2 16 5 X 2 2 2 3 3 7 3 5 6 2 7 88
Takt overdue 1 X X X X 1 X X X X 5 X X X X 0 X X X X X X 8
Takt time: 65
Time unit: minutes
Table 5.4 - Idle times and takt overdue for minimum required number of operators at stations
Station
Total
D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 D18 D19 D20 D21 D22
Idle time X 8 1 X X X 2 2 13 15 X 0 X 5 8 X X X X 6 3 0 63
A21
Idle time X 8 6 2 2 1 X 3 13 0 X X X 0 0 X X X X 6 3 0 44
P22
Station time
Takt overdue 3 X X X X X 2 X X 0 18 21 16 0 0 13 12 6 3 X X 0 94
Idle time X 7 4 0 X 0 X 1 13 0 X X 0 0 0 6 11 3 3 7 3 0 58
R13
Takt overdue 9 X X 0 1 0 3 X X 0 18 16 0 0 0 X X X X X X 0 47
Average
Idle time X 8 4 1 1 X 1 2 13 5 X X X 2 3 2 4 1 1 6 3 0 55
Takt overdue 5 X X 2 6 5 2 X X X 14 12 8 X X 5 15 4 5 X X 0 84
Takt time: 65
Time unit: minutes
Table 5.5 - Idle times and takt overdue for maximum required number of operators at stations
Station
Total
D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 D18 D19 D20 D21 D22
Takt overdue X X X X X 4 X X X X X X X X X X X X X X 0 X 4
Takt overdue X X X X X X X X X 0 5 X X 0 0 X X X X X X 0 5
Takt overdue X X X X X X X X X 0 5 X X 0 0 X X X X X X 0 5
Average
Takt overdue X X X X X 1 X X X X 3 X X X X X X X X X X X 5
Takt time: 65
Time unit: minutes
This chapter evaluates the advantages of the proposed setup over the current system.
6.1.2 Efficiency
One of the most important objectives of this project was to eliminate the excess capacity at the
stations so that idle times and non-value-added work at the production system are minimized.
Considering that the same number of output is produced by a smaller number of operators in the
same duration, and the process times are reduced for the same products, it can be said that the
efficiency of the pre-assembly line increased as a result of this study. Besides, reduced idle times
at stations and new strategies developed for handling operations that cause takt overdue which is
the greatest waste in terms of efficiency- are other factors that improve the efficiency of the line.
Different from the previous system, operations causing takt overdue will not be completed by
rework. Instead, they will be completed by joker workers instantly at the corresponding station so
that wastes caused by over-processing will be eliminated. With the new line balance and operator
planning, the maximum balance delay time (total idle time) at the line can be reduced up to 80 %.
Also, the maximum total takt overdue can be reduced 90 % with the same method.
Table 6.2 - Comparison of idle times and takt overdue between current and new states
Totalidletime Totaltaktoverdue
A21 315 1091
Currentstate P22 168 1091
R13 246 1006
A21 63 110
Forminimumrequired
P22 44 94
numberofoperators
R13 58 47
NewState
A21 158 4
Formaximumrequired
P22 136 5
numberofoperators
R13 186 5
Timeunit:minutes
Unlike the current layout where most stations were positioned outside the U-shaped pre-assembly
line, the new plan suggests sub-assembly stations to be located right in the middle of the U-
shaped assembly line, reducing the distance between them and their main assembly stations
dramatically and improving material flow.
lining the ground to indicate assembly station areas for new stations D6 and D7,
removing station equipment from the emptied assembly line,
restructuring ground rails on which vehicle carrying fixtures move.
It can be said that avoiding radical solutions and preserving the current setup as much as possible
helped the reorganization cost to be kept at relatively low levels considering the scale of the
change. In contrast, elimination of one of the production lines will reduce air, electricity and
cleaning costs.
Table 6.3 - Comparison of distance from sub to main assembly stations for current and proposed
systems
Totaldistancebetweensubassemblyto
mainassemblystations
Current ~1065
New ~860
Change(%) ~20
Distanceunit:meters
Table 6.4 - Comparison of vehicle operation times for current and proposed systems
Processtimes
A21 P22 R13
Current 14204 14274 13544
New 10219 9977 9587
Change(%) 28 30 29
Timeunit:minutes
Table 6.5 - Comparison of number of operators for current and proposed systems
Numberofoperators
Current 193
minimum 160
New
maximum 189
On one hand, for eliminating idle times at stations, number of operators should be the minimum
of that is required at that station. On the other hand, this would cause takt overdue for more
complex assemblies, which can be solved by having the maximum number of operators required
at that station. In this sense, having the minimum number of operators fixed at stations is a better
approach in terms of efficiency of the line, because extra labor requirement can be handled by on-
demand operators such as joker workers, while idle losses are intolerable and complete loss of
capacity for the line.
29 operators, however, is considerably a great number for a line of 160 operators. Planning the
schedule of the joker workers is an important task since the cost of an idle joker worker is no
different from an idle assembly operator. Therefore, joker worker schedules should be planned
parallel to production so that there will be no problems with the line flow due to additional labor
demands. When the joker workers are not assigned to any operations at stations, they can take
part in Kaizen activities as well as doing rework.
Although the concept of using joker workers at the pre-assembly line is new, such organization
would be compatible with the structure of the company since continuous improvement
philosophy is a part of the company culture and is managed by an independent department, which
can organize and direct the joker worker activities together with the production management.
1. the properties of the two lines have to be the same with each other,
2. the physical area of the building that will host the merged line has to be large enough to
provide enough space for the assembly and sub-assembly stations as well as the logistics
activities.
With the proposed changes at the pre-assembly line, its structure became compatible with the rest
of the assembly lines in the whole production line. That is, the takt time of 130 minutes is
reduced to 65 minutes, and the parallel two-line production is switched to single line production,
which enables the pre-assembly and assembly lines to operate as a single line if merged. Also, the
physical area of the U1 building is enough to cover the pre-assembly and assembly lines and their
sub-assembly stations if the area occupied by the warehouses is emptied.
6.1.12 Competence
Cleveland et al., ([6] p.657) defines production competence as the preparedness, skill, or
capability that enables manufacturers to prosecute a product-market specific business strategy
and argue that the nine skills or capabilities of manufacturers are adaptive manufacturing, cost
effectiveness of labor, delivery performance, logistics, production economies of scale, process
technology, quality performance, throughput and lead time, and vertical integration.
The competition in the commercial vehicle market and the decreased demand due to ongoing
economic crisis forces the companies to reduce costs for maintaining their competitiveness. The
planned changes at MAN Trkiye is also aiming to improve the competence of the company in
the market by cutting production costs without changing productivity.
The proposed changes have affects on the reduction of costs that cannot be omitted. The primary
gain is achieved in the inventory costs by switching from two parallel lines to single line
production, which reduces the number of pre-assembly stations from 39 to 22. The reduction of
17 stations from the production line reduces the working process inventory of the pre-assembly
line more than 40%. The reduction in the station costs such as air, electricity, cleaning and
material costs is a plus to the inventory costs.
Besides the inventory costs, reduced number of operators at the pre-assembly line means a
reduction in the labor costs of about 17%. With the new takt time of 65 minutes, the learning time
of the operators at stations will decrease, which will improve the operating skills of operators and
reduce the quality flaws of the end-products.
This aim of this chapter is to approach the achievements of the conducted study from a critical
point of view. It presents the discussion of how the theory and applied methods affected the
generated results and whether these results fulfill the expectations of the company. The
prerequisites of taking the proposed system into service and recommendations on further
improvement of the project are also put forward.
Scholls capacity oriented and cost oriented goals for balancing an assembly line are adapted as
the major criteria that shaped the course of the project. Switching to single line assembly and
halving the takt time resulted in a significant reduction in inventory costs and flow time. For
reducing the wage costs, operator planning has been made by balancing the line for the most
standard configuration of products and handling the remaining work by joker workers, which
would minimize the required number of operators at the stations. This also helped the idle times
and takt overdue to be eliminated, helping the idle and incompletion costs to drop.
Product - Process Matrix has been the initial guide for comprehending the problems with the
existing system. It is observed that the production system at MAN Trkiye was off the diagonal
on the Product-Process Matrix, which indicated a wrong process decision for the product.
Besides, it was also noticed that the emphasized advantages of flow line systems were not
effective on the current system; throughput times were high and capacity utilization was low, in
process inventory was high, material handling needs were high due to the lack of mechanical
conveyance and required shop floor and storage space was high. For some parts of the assembly
line, it was also not possible to use less skilled operators since most operations required
specialization. Thinking about the reasons of this discrepancy and its reasons, it is finally
comprehended that the main reasons of this situation are the size and complex structure of the
products; buses are big and heavy, and they are made up of thousands of components that are
manually assembled. Low production volumes, high level of product variation and manual
processing requirements did not enable automation in the production process, which results in not
being able to take advantages of flow line assembly. Therefore, it is concluded that, since it is not
possible to change the product process pattern of the factory, necessary actions should be taken to
CHALMERS, Product and Production Development, Masters Thesis 2009 67
bring the position of system as close to the diagonal as possible. Switching to single line
assembly with a lower takt time had significant effects on reducing the in process inventory and
shop floor space needs at the assembly line as well as improving the operator learning time,
which enables less skilled operators to be used at the line. Other actions included improving
capacity utilization and reducing material handling needs at the pre-assembly line.
Calculation of number of operators required at the pre-assembly line has been completed in two
steps. In the first step, the theoretical calculation method is applied for figuring out the maximum
number of operators required for each vehicle model by simply dividing the total operation time
of each vehicle to the takt time. This number gave an idea about the number of operators needed
at each station for running the balancing operation at ProBalance. Having run the balancing
algorithm on the software and manually manipulating the addressing of operations to stations, the
distribution of operations to stations is determined, which is followed by the final operator
assignment to stations explained in Chapter 3.
Application of joker workers has been a new approach at the pre-assembly line, but it offered
considerable advantages in reducing capacity losses due to variation of products. However,
variant losses are not the only sources of idle times and takt overdue at stations; the KSW
operations with low frequency also caused the same results as the variants at the stations. In order
to eliminate the losses caused by KSWs, operations with frequencies lower than 50% are
Operator job design was another concept that was considered while improving operator
performance parameters. All operation times were increased by 15% and the line is balanced for
the operation times with this distribution ratio, which was stated to improve operator
productivity. Besides, in order to prevent two operators to work at the same region of the vehicle
simultaneously, all operations are labeled according to their corresponding vehicle regions, which
were taken as constraints during line balancing. In addition, for minimizing material handling
requirements at stations, the problematic deliveries are reported to the logistics department so that
actions like unpacking or sequencing of parts are made prior to their delivery to stations.
Acquiring a complete operations list and to verify the list by cross-checking with other references
has been the initial step of the project. The company uses a complex production management
system that controls whole operations by numbers instead of operations lists. Lists are prepared
by management groups to follow the operations at the line for their own use. Assuming the
frequent change of product features and thus operations, it would not be rational to accept the
existing list at the Work Preparation Group as the master list since it could be outdated. Cross-
checking, therefore, has taken more time than re-arranging the assembly line. Having achieved
the master list, the master precedence graph of operations is prepared by observations at the
stations and interviews.
Interviewing has been a very useful tool for gathering information during the project. The
operators and team leaders were quite cooperative and had numerous ideas that come with
experience. In order not to make it like an interrogation, questions were asked as if they were out
of curiosity and the subjects were allowed to tell whatever they wanted about the topic; the
sought information was highlighted as they explained.
Lean is a production culture that should be adopted and applied by all units within a company.
The objective of this project was not applying lean fundamentals to the production system; this
would be irrational and also there is a department whose specialization is applying lean to the
factory. Rather, lean has been a tool for determining significant wastes that should be focused on
and, if possible, eliminated throughout the balancing process.
Considering the 7 wastes in a lean production system, it has been much easier to identify the
problems at the pre-assembly line. Observation of long walks to the sub-assembly stations caused
the layout plan to be shaped in a way to reduce the distance between the sub-assembly and
assembly stations. Over-processing was another problem noticed at stations; operators used to
spend long times making sub-assemblies of parts or making adjustments on the assembled parts.
This is eliminated by re-addressing such operations to sub-assembly stations. Transportation of
materials at the pre-assembly line has been optimized by positioning the sub-assemblies as close
to the main assembly stations as possible. Elimination of waiting times and rework requirements
Simplified systematic approach has proved to be a reliable guide in the layout planning
procedure, but due to the limitations of the project it could only be applied up to an extent. The
main reasons for that method not to be able to shape the whole planning procedure are time and
cost limitations declared by the project managers; setting up the ideal line by replacing the
monumental station equipment required more reconstruction time and higher investment. Still,
determination of the positioning of sub-assembly stations with respect to the corresponding pre-
assembly stations is handled by applying this method, which resulted in a significant reduction of
transportation distance. The gain would be higher if the whole line could be rearranged.
The applied method can be regarded as a company-adopted theoretical method for assembly line
balancing. Although the theoretical approach to the given task is evident, it was not possible to
apply the theory to a functioning system directly; it was also compulsory to take advantage of the
own dynamics of that system and blend it within the ongoing restructuring process. Observing
that the existing operation culture would not easily adopt to a top-down decision, it became clear
to join the operators to the process via the team leaders. The target of this approach has been, as
the ones who literally do the operations, to integrate their ideas and experience while shaping the
new system. This has been done by the help of interviews and the workshops. On the other hand,
it would not be reasonable to totally rely on the information given by the operators since it would
reflect subjective opinion to protect their own interest. Therefore, to perform the given task, a
task-specific heuristic method is generated and integrated with the theoretical method.
Considering the nature of this study of maintaining the efficient usage of resources and reduction
of wastes, it can be said that this study has positive effects on economic sustainability. Overall,
the primary objective has been optimization of materials used in production, which leads to
reduction in used raw materials and wastes. In addition to the positive effect of resource
utilization on economic sustainability, closing of 16 stations has a significant reduction in the
usage of energy sources such as electricity and pneumatics as well as human resources, which can
be regarded as improvements in environmental and social pillars of sustainability.
7.2 Results
Throughout this study, the existing bus pre-assembly line at MAN Trkiye A.. is re-structured
by changing the production system from two-parallel lines to single line while halving the takt
time of 130 minutes and balancing the new line, with the primary constraints being minimum
transition cost and time.
At the beginning of this study no estimation has been made about the outcomes of the project; it
was known that there were inappropriate operations that should not be handled at an assembly
line and the line balance was not optimal, but no prediction was made about the gain that could be
achieved at the end of the project in terms of operation times or operator numbers at the line.
It can be said that the balancing procedure has been planned according to the demands of the
software; the course of the project is determined for gathering the information that is required to
run the software. It was a risky decision since any problem with the software would reset the
whole effort that was put into the work. However, the test runs with the software were promising,
which resulted in the work to be continued as planned. Although the final result was not the best
that could be achieved, the final lining is configured through manual manipulation on the
software.
A comparison between the current and the proposed system shows that the application of the
proposed system creates a more advantageous situation for the competence of the company with
its reduced costs and improved line efficiency. The proposed changes are feasible in terms of
reorganization costs and transition time, and the pay-off of the proposed line is higher. The
achieved results suggest that the objectives of the company with this project are obtained, and the
requirements of the project are fulfilled.
briefing the logistics department about the new organization of the assembly line and
about the assembly operations that will henceforth be handled at sub-assembly stations so
that material flow is reorganized,
verifying if the assumptions about breaking down operations to multiple stations or
conjoining operations of different assembly groups at the same stations are practically
applicable,
verification of the qualification matrices of operators at the line and making the new
operation assignment to operators regarding their skills.
There are also actions that should be taken to prepare the production site for the new assembly
line, which can be summarized as,
ProBalance is proven to be a very useful tool for organizing station and operation data at a
detailed level and maintaining assembly line balance with this information in a matter of seconds.
It provides great flexibility for modifying or re-addressing operations as well as operator planning
at stations. Integrating this or a similar tool for organizing assembly line setup can be of great
advantage for the company at the long run for visualizing the balance changes, planning future
actions like adding new products to the range or modification of operations at the pre-assembly
line, and analyzing the changes instantly. The only challenge with adapting this software to an
already running production system is that the software requires the operation data to be input in
every detail, which would take some time to analyze the operations and form the initial structure
of the production system in the software. However, once this is completed, no matter how
complex the assembly line is, any change on the assembly line can be demonstrated and planned
in a few minutes, reducing the time required to apply changes at the assembly line in a
conventional system.
The layout of the current pre-assembly line is a limiting factor on the performance of the line in
terms of material and line flow. Due to the limited area that is allocated to the pre-assembly line,
the layout of the line cannot be optimized for the requirements of the production system, which
also affects the balance of the line. If the pre-assembly and assembly lines are to be merged at U1
Moving the work-pieces to the next station at the pre-assembly line takes about 2-3 minutes, and
this operation cannot be started at all stations at the same time due to safety issues. That is, the
operators of the last station start pulling the bus from the previous, and when they are at about
half way, the operators of the previous station start pulling the previous bus to their station. At the
current line of 19 stations, completion of line flow takes up to 10 minutes. Besides the negative
effect of manual conveyance of buses on the motivation of the operators, with the new line of 22
stations and new takt time of 65 minutes, the conveyance time can become a serious problem.
Although the line is balanced for 60 minutes with 5 minutes of tolerance, this time may not be
sufficient for a complete line flow. Thus, a system for automating the conveyance at the line
should be designed to eliminate the risk of delay at the line caused by conveyance.
This study shows that an unbalanced assembly line may generate significant capacity loss in a
cumulative pattern, which requires a continuous waste elimination and balancing approach in
production. With conventional methods it is very difficult to handle such a task at an assembly
line with the number of operations reaching a few hundreds and frequently changing product
properties. From this perspective ProBalance is a very useful tool that can organize and
accelerate the process of continuous control and manipulation of an assembly line. Although it
requires a lot of time, attention and effort to integrate it to a running assembly system of high
complexity, it saves much more than what is invested in the following optimization activities.
The generated results throughout this study suggest that, with the desired single line structure of
22 stations and 65 minutes of takt time, in order to achieve maximum gain over the current
system in terms of reduced operational costs and resource utilization, the new pre-assembly line
should be organized such that,
operations that are concluded to be inappropriate for the pre-assembly line and re-
addressed to the sub-assembly stations should be removed from the pre-assembly line,
the line should be balanced for the minimum number of required operators at stations and
on-demand work force should be provided by joker operators,
sub-assembly stations should be relocated in order to meet the requirements of the new
line layout,
factory logistics should be informed about supplying the required parts in the desired
sequence.
Concurrent application of these changes at the existing pre-assembly line will result in,
In addition, with the new structure of the pre-assembly line, all segments of the bus production
line will acquire a uniform structure, which provides the groundwork of a possible integration of
these segments in the future.
[2] Askin, R. G., Goldberg, J. B. (2002) Design and Analysis of Lean Production Systems. John
Wiley & Sons, Inc., New York, ISBN 0-471-11593-2
[3] Baudin, M. (2002) Lean Assembly: The Nuts and Bolts of Making Assembly Operations Flow.
Productivity Press, New York, ISBN 1-56327-263-6
[4] Boothroyd, G., Dewhurst, P., Knight, W. (1994) Product Design for Manufacture and
Assembly. Marcel Dekker, Inc., New York, ISBN 0-8247-9176-2
[5] Bunting, S. (2005) The Interviewers Handbook: Successful Interviewing Techniques for the
Workplace. Kogan Page Limited, London, ISBN 9780749442934
[6] Cleveland, G., Schroeder, R.G., Anderson, J.C. (1989) A Theory of Production Competence.
Decision Sciences 20 (4), 655668.
[7] Dresner, S. (2002) The principles of Sustainability. Earthscan Publications Limited, London,
ISBN: 978-1-84407-706-9
[8] Glassey, W. C. (1966) The Theory and Practice of Time Study. Cox & Wyman Limited,
London
[9] IVF Industrial Research and Development Corporation (2004) Lean Production Presentation
as part of the MG2205 Operations Management Course, Royal Institute of Technology,
Stockholm
[10] Kolisch, R. (2001) Make-to-Order Assembly Management. Springer- Verlag, Berlin, ISBN
3-540-41098-8
[11] Lung, Y., Chanaron, J. J., Fujimoto, T., Raff, D. (1999) Coping with Variety: Flexible
Poductive Systems for Product Variety in the Auto Industry. Ashgate Publishing Company,
Vermont, ISBN 0-7546-1115-9
[12] McGilvray, D. (2008) Executing Data Quality Projects: Ten Steps to Quality Data and
Trusted Information. Morgan Kaufmann Publishers, San Francisco, ISBN 0-1237-4369-9
[13] Muther, R., Wheeler, J. D. (1994) Simplified Systematic Layout Planning. 3rd Edition,
Management and Industrial Research Publications, Georgia, ISBN 0-9336-8409-6
[15] Ortiz, C. A. (2006) Kaizen Assembly: Designing, Constructing and Managing a Lean
Assembly Line. Taylor and Francis Group, Boca Raton, ISBN 0-8493-7187-2
[16] Porritt, J. (2006). Capitalism as if the world mattered. Earthscan Publications Limited,
London, ISBN 9781844071937
[17] Render, B., Heizer, J. (1997) Principles of Operations Management with Tutorials. 2nd
Edition. Prentice-Hall, Inc., New Jersey, ISBN 0-13-840430-5
[18] Sawik, T. (1999) Production Planning and Scheduling in Flexible Assembly Systems.
Springer-Verlag, Berlin, ISBN 3-540-64998-0
[19] Scholl, A. (1999) Balancing and Sequencing of Assembly Lines. 2nd Edition, Physica-
Verlag, Heidelberg, ISBN 3-7908-1180-7
[20] Schroeder, R. G. (2007) Operations Management: Contemporary Concepts and Cases. 3rd
Edition, Mc Graw Hill/Irwin, Singapore, ISBN 007-125436-6
[21] Slack, N., Chambers, S., Jonhston, R. (2007) Operations Management. 5th Edition, Pearson
Education Limited, Essex, ISBN 978-0-273-70847-6
[22] Sule, D. R. (1994) Manufacturing Facilities: Location, Planning and Design. PWS
Publishing Company, Boston, ISBN 0-5349-3435-8
[24] Wagner, B., Enzler, S. (2006) Material Flow Management: Improving Cost Efficiency and
Environmental Performance. Physica-Verlag, Heidelberg, ISBN 3-7908-1591-8
[25] Womack, J. P., Jones, D. T. (2003) Lean Thinking: Banish Waste and Create Wealth in Your
Corporation. Simon & Schuster UK Ltd, London, ISBN 0-7432-3164-3