Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

ERODE - 638 104: Mg6088 Software Project Management Lecture Notes

Download as pdf or txt
Download as pdf or txt
You are on page 1of 53

ERODE 638 104

MG6088 SOFTWARE PROJECT MANAGEMENT LECTURE NOTES

Name of the Faculty : B.MANIVANNAN

Designation & Department : ASP& COMPUTER SCIENCE AND


ENGINEERING

Subject Code & Title : MG6088 & SOFTWARE PROJECT


MANAGEMENT

Year/Sem : IV/VIII
UNIT - I
Conventional Software Management: The waterfall model, conventional software Management performance.
Evolution of Software Economics: Software Economics, pragmatic software cost estimation
1. Conventional software management
Conventional software management practices are sound in theory, but practice is still tied to archaic (outdated)
technology and techniques.
Conventional software economics provides a benchmark of performance for conventional software manage-
ment principles.
The best thing about software is its flexibility: It can be programmed to do almost anything.
The worst thing about software is also its flexibility: The "almost anything" characteristic has made it difficult
to plan, monitors, and control software development.
Three important analyses of the state of the software engineering industry are
1. Software development is still highly unpredictable. Only about 10% of software projects are
delivered successfully within initial budget and schedule estimates.
2. Management discipline is more of a discriminator in success or failure than are technology advances.
3. The level of software scrap and rework is indicative of an immature process.
All three analyses reached the same general conclusion: The success rate for software projects is very low.
The three analyses provide a good introduction to the magnitude of the software problem and the current
norms for conventional software management performance.

1.1 THE WATERFALL MODEL


Most software engineering texts present the waterfall model as the source of the "conventional" software
process.
1.1.1 IN THEORY
It provides an insightful and concise summary of conventional software management
Three main primary points are
1. There are two essential steps common to the development of computer programs: analysis and
coding.
Waterfall Model part 1: The two basic steps to building a program.

Analysis Analysis and coding both involve creative work that


directly contributes to the usefulness of the end product.
Coding
2. In order to manage and control all of the intellectual freedom associated with software development,
one must introduce several other "overhead" steps, including system requirements definition,
software requirements definition, program design, and testing. These steps supplement the analysis
and coding steps. Below Figure illustrates the resulting project profile and the basic steps in
developing a large-scale program.
Requirement

Analysis

Design

Coding

Testing

Operation
3. The basic framework described in the waterfall model is risky and invites failure. The testing phase
that occurs at the end of the development cycle is the first event for which timing, storage,
input/output transfers, etc., are experienced as distinguished from analyzed. The resulting design
changes are likely to be so disruptive that the software requirements upon which the design is based
are likely violated. Either the requirements must be modified or a substantial design change is
warranted.

Five necessary improvements for waterfall model are:-

1. Program design comes first. Insert a preliminary program design phase between the software
requirements generation phase and the analysis phase. By this technique, the program designer
assures that the software will not fail because of storage, timing, and data flux (continuous
change). As analysis proceeds in the succeeding phase, the program designer must impose on the
analyst the storage, timing, and operational constraints in such a way that he senses the consequences.
If the total resources to be applied are insufficient or if the embryonic(in an early stage of
development) operational design is wrong, it will be recognized at this early stage and the iteration
with requirements and preliminary design can be redone before final design, coding, and test
commences. How is this program design procedure implemented?

The following steps are required:


Begin the design process with program designers, not analysts or programmers.
Design, define, and allocate the data processing modes even at the risk of being wrong. Allocate
processing functions, design the database, allocate execution time, define interfaces and processing
modes with the operating system, describe input and output processing, and define preliminary
operating procedures.
Write an overview document that is understandable, informative, and current so that every worker
on the project can gain an elemental understanding of the system.

2. Document the design. The amount of documentation required on most software programs is quite a lot,
certainly much more than most programmers, analysts, or program designers are willing to do if left to their
own devices. Why do we need so much documentation? (1) Each designer must communicate with interfacing
designers, managers, and possibly customers. (2) During early phases, the documentation is the design. (3) The
real monetary value of documentation is to support later modifications by a separate test team, a separate
maintenance team, and operations personnel who are not software literate.

3. Do it twice. If a computer program is being developed for the first time, arrange matters so that the version
finally delivered to the customer for operational deployment is actually the second version insofar as critical
design/operations are concerned. Note that this is simply the entire process done in miniature, to a time scale
that is relatively small with respect to the overall effort. In the first version, the team must have a special
broad competence where they can quickly sense trouble spots in the design, model them, model alternatives,
forget the straightforward aspects of the design that aren't worth studying at this early point, and, finally,
arrive at an error-free program.

4. Plan, control, and monitor testing. Without question, the biggest user of project resources-manpower,
computer time, and/or management judgment-is the test phase. This is the phase of greatest risk in terms of
cost and schedule. It occurs at the latest point in the schedule, when backup alternatives are least available, if
at all. The previous three recommendations were all aimed at uncovering and solving problems before
entering the test phase. However, even after doing these things, there is still a test phase and there are still
important things to be done, including: (1) employ a team of test specialists who were not responsible for the
original design; (2) employ visual inspections to spot the obvious errors like dropped minus signs, missing
factors of two, jumps to wrong addresses (do not use the computer to detect this kind of thing, it is too
expensive); (3) test every logic path; (4) employ the final checkout on the target computer.
5. Involve the customer. It is important to involve the customer in a formal way so that he has committed
himself at earlier points before final delivery. There are three points following requirements definition where
the insight, judgment, and commitment of the customer can bolster the development effort. These include a
"preliminary software review" following the preliminary program design step, a sequence of "critical software
design reviews" during program design, and a "final software acceptance review".

1.1.2 IN PRACTICE
Some software projects still practice the conventional software management approach.
It is useful to summarize the characteristics of the conventional process as it has typically been applied,
which is not necessarily as it was intended. Projects destined for trouble frequently exhibit the following
symptoms:

Protracted integration and late design breakage.


Late risk resolution.
Requirements-driven functional decomposition.
Adversarial (conflict or opposition) stakeholder relationships.
Focus on documents and review meetings.

Protracted Integration and Late Design Breakage


For a typical development project that used a waterfall model management process, Figure 1-2 illustrates
development progress versus time. Progress is defined as percent coded, that is, demonstrable in its target form.

The following sequence was common:

Early success via paper designs and thorough (often too thorough) briefings.
Commitment to code late in the life cycle.
Integration nightmares (unpleasant experience) due to unforeseen implementation issues and interface
ambiguities.
Heavy budget and schedule pressure to get the system working.
Late shoe-homing of no optimal fixes, with no time for redesign.
A very fragile, unmentionable product delivered late.
In the conventional model, the entire system was designed on paper, then implemented all at once, then
integrated. Table 1-1 provides a typical profile of cost expenditures across the spectrum of software activities.

Late risk resolution A serious issue associated with the waterfall lifecycle was the lack of early risk resolution.
Figure 1.3 illustrates a typical risk profile for conventional waterfall model projects. It includes four distinct
periods of risk exposure, where risk is defined as the probability of missing a cost, schedule, feature, or quality
goal. Early in the life cycle, as the requirements were being specified, the actual risk exposure was highly
unpredictable.

Requirements-Driven Functional Decomposition: This approach depends on specifying requirements com-


pletely and unambiguously before other development activities begin. It naively treats all requirements as
equally important, and depends on those requirements remaining constant over the software development life
cycle. These conditions rarely occur in the real world. Specification of requirements is a difficult and important
part of the software development process.
Another property of the conventional approach is that the requirements were typically specified in a
functional manner. Built into the classic waterfall process was the fundamental assumption that the software
itself was decomposed into functions; requirements were then allocated to the resulting components. This
decomposition was often very different from a decomposition based on object-oriented design and the use of
existing components. Figure 1-4 illustrates the result of requirements-driven approaches: a software structure
that is organized around the requirements specification structure.
Adversarial Stakeholder Relationships:
The conventional process tended to result in adversarial stakeholder relationships, in large part because of the
difficulties of requirements specification and the exchange of information solely through paper documents that
captured engineering information in ad hoc formats.

The following sequence of events was typical for most contractual software efforts:
1. The contractor prepared a draft contract-deliverable document that captured an intermediate artifact
and delivered it to the customer for approval.
2. The customer was expected to provide comments (typically within 15 to 30 days).
3. The contractor incorporated these comments and submitted (typically within 15 to 30 days) a final
version for approval.
This one-shot review process encouraged high levels of sensitivity on the part of customers and contractors.

Focus on Documents and Review Meetings:


The conventional process focused on producing various documents that attempted to describe the software
product, with insufficient focus on producing tangible increments of the products themselves. Contractors
were driven to produce literally tons of paper to meet milestones and demonstrate progress to stakeholders,
rather than spend their energy on tasks that would reduce risk and produce quality software. Typically,
presenters and the audience reviewed the simple things that they understood rather than the complex and
important issues. Most design reviews therefore resulted in low engineering value and high cost in terms of the
effort and schedule involved in their preparation and conduct. They presented merely a facade of progress.
Table 1-2 summarizes the results of a typical design review.
1.2 CONVENTIONAL SOFTWARE MANAGEMENT PERFORMANCE

Barry Boehm's "Industrial Software Metrics Top 10 List is a good, objective characterization of the state of
software development.
1. Finding and fixing a software problem after delivery costs 100 times more than finding and fixing the
problem in early design phases.
2. You can compress software development schedules 25% of nominal, but no more.
3. For every $1 you spend on development, you will spend $2 on maintenance.
4. Software development and maintenance costs are primarily a function of the number of source lines
of code.
5. Variations among people account for the biggest differences in software productivity.
6. The overall ratio of software to hardware costs is still growing. In 1955 it was 15:85; in 1985, 85:15.
7. Only about 15% of software development effort is devoted to programming.
8. Software systems and products typically cost 3 times as much per SLOC as individual software
programs. Software-system products (i.e., system of systems) cost 9 times as much.
9. Walkthroughs catch 60% of the errors
10. 80% of the contribution comes from 20% of the contributors.
2.1 SOFTWARE ECONOMICS
Most software cost models can be abstracted into a function of five basic parameters: size, process, personnel,
environment, and required quality.
1. The size of the end product (in human-generated components), which is typically quantified in terms
of the number of source instructions or the number of function points required to develop the
required functionality
2. The process used to produce the end product, in particular the ability of the process to avoid non-
value-adding activities (rework, bureaucratic delays, communications overhead)
3. The capabilities of software engineering personnel, and particularly their experience with the
computer science issues and the applications domain issues of the project
4. The environment, which is made up of the tools and techniques available to support efficient
software development and to automate the process
5. The required quality of the product, including its features, performance, reliability, and adaptability

The relationships among these parameters and the estimated cost can be written as follows:

Effort = (Personnel) (Environment) (Quality) ( Sizeprocess)

One important aspect of software economics (as represented within today's software cost models) is that
the relationship between effort and size exhibits a diseconomy of scale. The diseconomy of scale of software
development is a result of the process exponent being greater than 1.0. Contrary to most manufacturing
processes, the more software you build, the more expensive it is per unit item.
Figure 2-1 shows three generations of basic technology advancement in tools, components, and processes.
The required levels of quality and personnel are assumed to be constant. The ordinate of the graph refers to
software unit costs (pick your favorite: per SLOC, per function point, per component) realized by an
organization.
The three generations of software development are defined as follows:

1) Conventional: 1960s and 1970s, craftsmanship. Organizations used custom tools, custom processes,
and virtually all custom components built in primitive languages. Project performance was highly
predictable in that cost, schedule, and quality objectives were almost always underachieved.
2) Transition: 1980s and 1990s, software engineering. Organiz:1tions used more-repeatable processes and off-
the-shelf tools, and mostly (>70%) custom components built in higher level languages. Some of the
components (<30%) were available as commercial products, including the operating system, database
management system, networking, and graphical user interface.
3) Modern practices: 2000 and later, software production. This book's philosophy is rooted in the
use of managed and measured processes, integrated automation environments, and mostly
(70%) off-the-shelf components. Perhaps as few as 30% of the components need to be custom
built
Technologies for environment automation, size reduction, and process improvement are not independent of
one another. In each new era, the key is complementary growth in all technologies. For example, the process
advances could not be used successfully without new component technologies and increased tool automation.
Organizations are achieving better economies of scale in successive technology eras-with very large projects
(systems of systems), long-lived products, and lines of business comprising multiple similar projects. Figure 2-2
provides an overview of how a return on investment (ROI) profile can be achieved in subsequent efforts across
life cycles of various domains.
2.2 PRAGMATIC SOFTWARE COST ESTIMATION
One critical problem in software cost estimation is a lack of well-documented case studies of projects that used
an iterative development approach. Software industry has inconsistently defined metrics or atomic units of
measure, the data from actual projects are highly suspect in terms of consistency and comparability. It is hard
enough to collect a homogeneous set of project data within one organization; it is extremely difficult to homog-
enize data across different organizations with different processes, languages, domains, and so on.
There have been many debates among developers and vendors of software cost estimation models and tools.
Three topics of these debates are of particular interest here:

1. Which cost estimation model to use?


2. Whether to measure software size in source lines of code or function points.
3. What constitutes a good estimate?
There are several popular cost estimation models (such as COCOMO, CHECKPOINT, ESTIMACS,
KnowledgePlan, Price-S, ProQMS, SEER, SLIM, SOFTCOST, and SPQR/20), CO COMO is also one of the
most open and well-documented cost estimation models. The general accuracy of conventional cost models
(such as COCOMO) has been described as "within 20% of actuals, 70% of the time."
Most real-world use of cost models is bottom-up (substantiating a target cost) rather than top-down
(estimating the "should" cost). Figure 2-3 illustrates the predominant practice: The software project manager
defines the target cost of the software, and then manipulates the parameters and sizing until the target cost can
be justified. The rationale for the target cost maybe to win a proposal, to solicit customer funding, to attain
internal corporate funding, or to achieve some other goal.
The process described in Figure 2-3 is not all bad. In fact, it is absolutely necessary to analyze the cost risks and
understand the sensitivities and trade-offs objectively. It forces the software project manager to examine the
risks associated with achieving the target costs and to discuss this information with other stakeholders.
A good software cost estimate has the following attributes:
It is conceived and supported by the project manager, architecture team, development team, and test
team accountable for performing the work.
It is accepted by all stakeholders as ambitious but realizable.
It is based on a well-defined software cost model with a credible basis.
It is based on a database of relevant project experience that includes similar processes, similar
technologies, similar environments, similar quality requirements, and similar people.
It is defined in enough detail so that its key risk areas are understood and the probability of success is
objectively assessed.
Extrapolating from a good estimate, an ideal estimate would be derived from a mature cost model with an
experience base that reflects multiple similar projects done by the same team with the same mature processes
and tools.
UNIT II
Improving Software Economics: Reducing Software product size, improving software processes, improving
team effectiveness, improving automation, Achieving required quality, peer inspections.
The old way and the new: The principles of conventional software Engineering, principles of modern software
management, transitioning to an iterative process.

3. Improving Software Economics


Five basic parameters of the software cost model are
1.Reducing the size or complexity of what needs to be developed.
2. Improving the development process.
3. Using more-skilled personnel and better teams (not necessarily the same thing).
4. Using better environments (tools to automate the process).
5. Trading off or backing off on quality thresholds.
These parameters are given in priority order for most software domains. Table 3-1 lists some of the
technology developments, process improvement efforts, and management approaches targeted at
improving the economics of software development and integration.

3.1 REDUCING SOFTWARE PRODUCT SIZE


The most significant way to improve affordability and return on investment (ROI) is usually to produce a
product that achieves the design goals with the minimum amount of human-generated source material.
Component-based development is introduced as the general term for reducing the "source" language size to
achieve a software solution.
Reuse, object-oriented technology, automatic code production, and higher order programming languages are all
focused on achieving a given system with fewer lines of human-specified source directives (statements).
size reduction is the primary motivation behind improvements in higher order languages (such as C++, Ada 95,
Java, Visual Basic), automatic code generators (CASE tools, visual modeling tools, GUI builders), reuse of
commercial components (operating systems, windowing environments, database management systems,
middleware, networks), and object-oriented technologies (Unified Modeling Language, visual modeling tools,
architecture frameworks).
The reduction is defined in terms of human-generated source material. In general, when size-reducing
technologies are used, they reduce the number of human-generated source lines.

3.1.1 LANGUAGES
Universal function points (UFPs1) are useful estimators for language-independent, early life-cycle estimates.
The basic units of function points are external user inputs, external outputs, internal logical data groups,
external data interfaces, and external inquiries. SLOC metrics are useful estimators for software after a
candidate solution is formulated and an implementation language is known. Substantial data have been
documented relating SLOC to function points. Some of these results are shown in Table 3-2.
Languages expressiveness of some of todays popular languages
LANGUAGES SLOC per UFP
Assembly 320
C 128
FORTAN77 105
COBOL85 91
Ada83 71
C++ 56
Ada95 55
Java 55
Visual Basic 35
Table 3-2

3.1.2 OBJECT-ORIENTED METHODS AND VISUAL MODELING


Object-oriented technology is not germane to most of the software management topics discussed here, and
books on object-oriented technology abound. Object-oriented programming languages appear to benefit both
software productivity and software quality. The fundamental impact of object-oriented technology is in
reducing the overall size of what needs to be developed.
People like drawing pictures to explain something to others or to themselves. When they do it for software
system design, they call these pictures diagrams or diagrammatic models and the very notation for them a
modeling language.
These are interesting examples of the interrelationships among the dimensions of improving software eco-
nomics.

1. An object-oriented model of the problem and its solution encourages a common vocabulary between
the end users of a system and its developers, thus creating a shared understanding of the problem
being solved.
2. The use of continuous integration creates opportunities to recognize risk early and make incremental
corrections without destabilizing the entire development effort.
3. An object-oriented architecture provides a clear separation of concerns among disparate elements of a
system, creating firewalls that prevent a change in one part of the system from rending the fabric of
the entire architecture.

Booch also summarized five characteristics of a successful object-oriented project.

1
Function point metrics provide a standardized method for measuring the various functions of a software application.
The basic units of function points are external user inputs, external outputs, internal logical data groups, external data interfaces, and
external inquiries.
1. A ruthless focus on the development of a system that provides a well understood collection of essential
minimal characteristics.
2. The existence of a culture that is centered on results, encourages communication, and yet is not afraid
to fail.
3. The effective use of object-oriented modeling.
4. The existence of a strong architectural vision.
5. The application of a well-managed iterative and incremental development life cycle.

3.1.3 REUSE
Reusing existing components and building reusable components have been natural software engineering
activities since the earliest improvements in programming languages. With reuse in order to minimize
development costs while achieving all the other required attributes of performance, feature set, and quality. Try
to treat reuse as a mundane part of achieving a return on investment.
Most truly reusable components of value are transitioned to commercial products supported by
organizations with the following characteristics:

They have an economic motivation for continued support.


They take ownership of improving product quality, adding new features, and transitioning to new
technologies.
They have a sufficiently broad customer base to be profitable.
The cost of developing a reusable component is not trivial. Figure 3-1 examines the economic trade-offs. The
steep initial curve illustrates the economic obstacle to developing reusable components.
Reuse is an important discipline that has an impact on the efficiency of all workflows and the quality of most
artifacts.

3.1.4 COMMERCIAL COMPONENTS


A common approach being pursued today in many domains is to maximize integration of commercial
components and off-the-shelf products. While the use of commercial components is certainly desirable as a
means of reducing custom development, it has not proven to be straightforward in practice. Table 3-3 identifies
some of the advantages and disadvantages of using commercial components.
3.2 IMPROVING SOFTWARE PROCESSES
Process is an overloaded term. Three distinct process perspectives are.

Metaprocess: an organization's policies, procedures, and practices for pursuing a software-intensive


line of business. The focus of this process is on organizational economics, long-term strategies, and
software ROI.
Macroprocess: a project's policies, procedures, and practices for producing a complete software
product within certain cost, schedule, and quality constraints. The focus of the macro process is on
creating an adequate instance of the Meta process for a specific set of constraints.
Microprocess: a project team's policies, procedures, and practices for achieving an artifact of the
software process. The focus of the micro process is on achieving an intermediate product baseline
with adequate quality and adequate functionality as economically and rapidly as practical.
Although these three levels of process overlap somewhat, they have different objectives, audiences, metrics,
concerns, and time scales as shown in Table 3-4

In a perfect software engineering world with an immaculate problem description, an obvious solution space, a
development team of experienced geniuses, adequate resources, and stakeholders with common goals, we
could execute a software development process in one iteration with almost no scrap and rework. Because we
work in an imperfect world, however, we need to manage engineering activities so that scrap and rework
profiles do not have an impact on the win conditions of any stakeholder. This should be the underlying
premise for most process improvements.

3.3 IMPROVING TEAM EFFECTIVENESS


Teamwork is much more important than the sum of the individuals. With software teams, a project manager
needs to configure a balance of solid talent with highly skilled people in the leverage positions. Some maxims
of team management include the following:
A well-managed project can succeed with a nominal engineering team.
A mismanaged project will almost never succeed, even with an expert team of engineers.
A well-architected system can be built by a nominal team of software builders.
A poorly architected system will flounder even with an expert team of builders.

Boehm five staffing principles are


1. The principle of top talent: Use better and fewer people
2. The principle of job matching: Fit the tasks to the skills and motivation of the people available.
3. The principle of career progression: An organization does best in the long run by helping its people
to self-actualize.
4. The principle of team balance: Select people who will complement and harmonize with one another
5. The principle of phase-out: Keeping a misfit on the team doesn't benefit anyone

Software project managers need many leadership qualities in order to enhance team effectiveness. The
following are some crucial attributes of successful software project managers that deserve much more attention:

1. Hiring skills. Few decisions are as important as hiring decisions. Placing the right person in the right
job seems obvious but is surprisingly hard to achieve.
2. Customer-interface skill. Avoiding adversarial relationships among stakeholders is a prerequisite for
success.
Decision-making skill. The jillion books written about management have failed to provide a clear
definition of this attribute. We all know a good leader when we run into one, and decision-making
skill seems obvious despite its intangible definition.
Team-building skill. Teamwork requires that a manager establish trust, motivate progress, exploit
eccentric prima donnas, transition average people into top performers, eliminate misfits, and
consolidate diverse opinions into a team direction.
Selling skill. Successful project managers must sell all stakeholders (including themselves) on decisions
and priorities, sell candidates on job positions, sell changes to the status quo in the face of resistance, and
sell achievements against objectives. In practice, selling requires continuous negotiation, compromise,
and empathy

3.4 IMPROVING AUTOMATION THROUGH SOFTWARE ENVIRONMENTS


The tools and environment used in the software process generally have a linear effect on the productivity
of the process. Planning tools, requirements management tools, visual modeling tools, compilers, editors,
debuggers, quality assurance analysis tools, test tools, and user interfaces provide crucial automation support
for evolving the software engineering artifacts. Above all, configuration management environments provide the
foundation for executing and instrument the process. At first order, the isolated impact of tools and automation
generally allows improvements of 20% to 40% in effort. However, tools and environments must be viewed as
the primary delivery vehicle for process automation and improvement, so their impact can be much higher.
Automation of the design process provides payback in quality, the ability to estimate costs and
schedules, and overall productivity using a smaller team.
Round-trip engineering describe the key capability of environments that support iterative development. As we
have moved into maintaining different information repositories for the engineering artifacts, we need
automation support to ensure efficient and error-free transition of data from one artifact to another. Forward
engineering is the automation of one engineering artifact from another, more abstract representation. For
example, compilers and linkers have provided automated transition of source code into executable code.
Reverse engineering is the generation or modification of a more abstract representation from an existing artifact
(for example, creating a .visual design model from a source code representation).
Economic improvements associated with tools and environments. It is common for tool vendors to make rela-
tively accurate individual assessments of life-cycle activities to support claims about the potential economic
impact of their tools. For example, it is easy to find statements such as the following from companies in a
particular tool.
Requirements analysis and evolution activities consume 40% of life-cycle costs.
Software design activities have an impact on more than 50% of the resources.
Coding and unit testing activities consume about 50% of software development effort and schedule.
Test activities can consume as much as 50% of a project's resources.
Configuration control and change management are critical activities that can consume as much as
25% of resources on a large-scale project.
Documentation activities can consume more than 30% of project engineering resources.
Project management, business administration, and progress assessment can consume as much as 30%
of project budgets.

3.5 ACHIEVING REQUIRED QUALITY


Software best practices are derived from the development process and technologies. Table 3-5 summarizes
some dimensions of quality improvement.

Key practices that improve overall software quality include the following:
Focusing on driving requirements and critical use cases early in the life cycle, focusing on
requirements completeness and traceability late in the life cycle, and focusing throughout the life cycle
on a balance between requirements evolution, design evolution, and plan evolution
Using metrics and indicators to measure the progress and quality of an architecture as it evolves from
a high-level prototype into a fully compliant product
Providing integrated life-cycle environments that support early and continuous configuration control,
change management, rigorous design methods, document automation, and regression test automation
Using visual modeling and higher level languages that support architectural control, abstraction,
reliable programming, reuse, and self-documentation
Early and continuous insight into performance issues through demonstration-based evaluations
Conventional development processes stressed early sizing and timing estimates of computer program
resource utilization. However, the typical chronology of events in performance assessment was as follows

Project inception. The proposed design was asserted to be low risk with adequate performance
margin.
Initial design review. Optimistic assessments of adequate design margin were based mostly on paper
analysis or rough simulation of the critical threads. In most cases, the actual application algorithms
and database sizes were fairly well understood.
Mid-life-cycle design review. The assessments started whittling away at the margin, as early
benchmarks and initial tests began exposing the optimism inherent in earlier estimates.
Integration and test. Serious performance problems were uncovered, necessitating fundamental
changes in the architecture. The underlying infrastructure was usually the scapegoat, but the real
culprit was immature use of the infrastructure, immature architectural solutions, or poorly understood
early design trade-offs.

3.6 PEER INSPECTIONS: A PRAGMATIC VIEW


Peer inspections are frequently over hyped as the key aspect of a quality system. In my experience, peer reviews
are valuable as secondary mechanisms, but they are rarely significant contributors to quality compared with the
following primary quality mechanisms and indicators, which should be emphasized in the management process:

Transitioning engineering information from one artifact set to another, thereby assessing the consistency,
feasibility, understandability, and technology constraints inherent in the engineering artifacts
Major milestone demonstrations that force the artifacts to be assessed against tangible criteria in the
context of relevant use cases
Environment tools (compilers, debuggers, analyzers, automated test suites) that ensure representation
rigor, consistency, completeness, and change control
Life-cycle testing for detailed insight into critical trade-offs, acceptance criteria, and requirements
compliance
Change management metrics for objective insight into multiple-perspective change trends and
convergence or divergence from quality and progress goals
Inspections are also a good vehicle for holding authors accountable for quality products. All authors of
software and documentation should have their products scrutinized as a natural by-product of the process.
Therefore, the coverage of inspections should be across all authors rather than across all components.

4. THE OLD WAY AND THE NEW


4.1 THE PRINCIPLES OF CONVENTIONAL SOFTWARE ENGINEERING
1.Make quality #1. Quality must be quantified and mechanisms put into place to motivate its achievement
2.High-quality software is possible. Techniques that have been demonstrated to increase quality include
involving the customer, prototyping, simplifying design, conducting inspections, and hiring the best people
3.Give products to customers early. No matter how hard you try to learn users' needs during the requirements
phase, the most effective way to determine real needs is to give users a product and let them play with it
4.Determine the problem before writing the requirements. When faced with what they believe is a problem,
most engineers rush to offer a solution. Before you try to solve a problem, be sure to explore all the alternatives
and don't be blinded by the obvious solution
5.Evaluate design alternatives. After the requirements are agreed upon, you must examine a variety of
architectures and algorithms. You certainly do not want to use architecture" simply because it was used in the
requirements specification.
6.Use an appropriate process model. Each project must select a process that makes the most sense for that
project on the basis of corporate culture, willingness to take risks, application area, volatility of requirements, and
the extent to which requirements are well understood.
7.Use different languages for different phases. Our industry's eternal thirst for simple solutions to complex
problems has driven many to declare that the best development method is one that uses the same notation through-
out the life cycle.
8.Minimize intellectual distance. To minimize intellectual distance, the software's structure should be as close as
possible to the real-world structure
9.Put techniques before tools. An undisciplined software engineer with a tool becomes a dangerous,
undisciplined software engineer
10.Get it right before you make it faster. It is far easier to make a working program run faster than it is to make
a fast program work. Don't worry about optimization during initial coding
11.Inspect code. Inspecting the detailed design and code is a much better way to find errors than testing
12.Good management is more important than good technology. Good management motivates people to do
their best, but there are no universal "right" styles of management.
13.People are the key to success. Highly skilled people with appropriate experience, talent, and training are key.
14.Follow with care. Just because everybody is doing something does not make it right for you. It may be right,
but you must carefully assess its applicability to your environment.
15.Take responsibility. When a bridge collapses we ask, "What did the engineers do wrong?" Even when
software fails, we rarely ask this. The fact is that in any engineering discipline, the best methods can be used to
produce awful designs, and the most antiquated methods to produce elegant designs.
16.Understand the customer's priorities. It is possible the customer would tolerate 90% of the functionality
delivered late if they could have 10% of it on time.
17.The more they see, the more they need. The more functionality (or performance) you provide a user, the
more functionality (or performance) the user wants.
18. Plan to throw one away. One of the most important critical success factors is whether or not a product is
entirely new. Such brand-new applications, architectures, interfaces, or algorithms rarely work the first time.
19. Design for change. The architectures, components, and specification techniques you use must accommodate
change.
20. Design without documentation is not design. I have often heard software engineers say, "I have finished the
design. All that is left is the documentation. "
21. Use tools, but be realistic. Software tools make their users more efficient.
22. Avoid tricks. Many programmers love to create programs with tricks constructs that perform a function
correctly, but in an obscure way. Show the world how smart you are by avoiding tricky code
23. Encapsulate. Information-hiding is a simple, proven concept that results in software that is easier to test
and much easier to maintain.
24. Use coupling and cohesion. Coupling and cohesion are the best ways to measure software's inherent
maintainability and adaptability
25. Use the McCabe complexity measure. Although there are many metrics available to report the inherent
complexity of software, none is as intuitive and easy to use as Tom McCabe's
26.Don't test your own software. Software developers should never be the primary testers of their own
software.
27.Analyze causes for errors. It is far more cost-effective to reduce the effect of an error by preventing it than it
is to find and fix it. One way to do this is to analyze the causes of errors as they are detected
28.Realize that software's entropy increases. Any software system that undergoes continuous change will grow
in complexity and will become more and more disorganized
29.People and time are not interchangeable. Measuring a project solely by person-months makes little sense
30.Expect excellence. Your employees will do much better if you have high expectations for them.

4.2 THE PRINCIPLES OF MODERN SOFTWARE MANAGEMENT

Top 10 principles of modern software management are. (The first five, which are the main themes of my definition of an
iterative process, are summarized in Figure 4-1.)

Base the process on an architecture-first approach. This requires that a demonstrable balance be achieved
among the driving requirements, the architecturally significant design decisions, and the life-cycle plans
before the resources are committed for full-scale development.
Establish an iterative life-cycle process that confronts risk early. With today's sophisticated software
systems, it is not possible to define the entire problem, design the entire solution, build the software, and
then test the end product in sequence. Instead, an iterative process that refines the problem understanding,
an effective solution, and an effective plan over several iterations encourages a balanced treatment of all
stakeholder objectives. Major risks must be addressed early to increase predictability and avoid expensive
downstream scrap and rework.
Transition design methods to emphasize component-based development. Moving from a line-of-code
mentality to a component-based mentality is necessary to reduce the amount of human-generated source
code and custom development.

4. Establish a change management environment. The dynamics of iterative development,


including concurrent workflows by different teams working on shared artifacts, necessitates objectively
controlled baselines.
5. Enhance change freedom through tools that support round-trip engineering. Round-trip
engineering is the environment support necessary to automate and synchronize
engineering information in different formats(such as requirements specifications, design models,
source code, executable code, test cases).
6. Capture design artifacts in rigorous, model-based notation. A model based approach (such as UML)
supports the evolution of semantically rich graphical and textual design notations.
7. Instrument the process for objective quality control and progress assessment. Life-cycle assessment
of the progress and the quality of all intermediate products must be integrated into the process.
8. Use a demonstration-based approach to assess intermediate artifacts.
9. Plan intermediate releases in groups of usage scenarios with evolving levels of detail. It is
essential that the software management process drive toward early and continuous demonstrations
within the operational context of the system, namely its use cases.
10. Establish a configurable process that is economically scalable. No single process is suitable for
all software developments.

Table 4-1 maps top 10 risks of the conventional process to the key attributes and principles of a modern
process
4.3 TRANSITIONING TO AN ITERATIVE PROCESS

Modern software development processes have moved away from the conventional waterfall model, in which
each stage of the development process is dependent on completion of the previous stage.
The economic benefits inherent in transitioning from the conventional waterfall model to an iterative
development process are significant but difficult to quantify. As one benchmark of the expected economic
impact of process improvement, consider the process exponent parameters of the COCOMO II model.
(Appendix B provides more detail on the COCOMO model) This exponent can range from 1.01 (virtually no
diseconomy of scale) to 1.26 (significant diseconomy of scale). The parameters that govern the value of the
process exponent are application precedentedness, process flexibility, architecture risk resolution, team
cohesion, and software process maturity.
The following paragraphs map the process exponent parameters of CO COMO II to my top 10 principles of
a modern process.

Application precedentedness. Domain experience is a critical factor in understanding how to plan and
execute a software development project. For unprecedented systems, one of the key goals is to confront
risks and establish early precedents, even if they are incomplete or experimental. This is one of the primary
reasons that the software industry has moved to an iterative life-cycle process. Early iterations in the life
cycle establish precedents from which the product, the process, and the plans can be elaborated in evolving
levels of detail.
Process flexibility. Development of modern software is characterized by such a broad solution space and
so many interrelated concerns that there is a paramount need for continuous incorporation of changes.
These changes may be inherent in the problem understanding, the solution space, or the plans. Project
artifacts must be supported by efficient change management commensurate with project needs. A
configurable process that allows a common framework to be adapted across a range of projects is
necessary to achieve a software return on investment.
Architecture risk resolution. Architecture-first development is a crucial theme underlying a successful
iterative development process. A project team develops and stabilizes architecture before developing all the
components that make up the entire suite of applications components. An architecture-first and
component-based development approach forces the infrastructure, common mechanisms, and control
mechanisms to be elaborated early in the life cycle and drives all component make/buy decisions into the
architecture process.
Team cohesion. Successful teams are cohesive, and cohesive teams are successful. Successful teams and
cohesive teams share common objectives and priorities. Advances in technology (such as programming
languages, UML, and visual modeling) have enabled more rigorous and understandable notations for
communicating software engineering information, particularly in the requirements and design artifacts that
previously were ad hoc and based completely on paper exchange. These model-based formats have also
enabled the round-trip engineering support needed to establish change freedom sufficient for evolving
design representations.
Software process maturity. The Software Engineering Institute's Capability Maturity Model (CMM) is a
well-accepted benchmark for software process assessment. One of key themes is that truly mature
processes are enabled through an integrated environment that provides the appropriate level of automation
to instrument the process for objective quality control.

Important questions

Explain briefly Waterfall model. Also explain Conventional s/w management performance?
1.

2. Define Software Economics. Also explain Pragmatic s/w cost estimation?

3. Explain Important trends in improving Software economics?

4. Explain five staffing principal offered by Boehm. Also explain Peer Inspections?

5.. Explain principles of conventional software engineering?

Explain briefly principles of modern software management


6.
UNIT - III
Life cycle phases: Engineering and production stages, inception, Elaboration, construction, transition phases.
Artifacts of the process: The artifact sets, Management artifacts, Engineering artifacts, programmatic artifacts.
5. Life cycle phases
Characteristic of a successful software development process is the well-defined separation between "research
and development" activities and "production" activities. Most unsuccessful projects exhibit one of the following
characteristics:
An overemphasis on research and development
An overemphasis on production.
Successful modern projects-and even successful projects developed under the conventional process-tend to have
a very well-defined project milestone when there is a noticeable transition from a research attitude to a
production attitude. Earlier phases focus on achieving functionality. Later phases revolve around achieving a
product that can be shipped to a customer, with explicit attention to robustness, performance, and finish.
A modern software development process must be defined to support the following:
Evolution of the plans, requirements, and architecture, together with well defined synchronization
points
Risk management and objective measures of progress and quality
Evolution of system capabilities through demonstrations of increasing functionality

5.1 ENGINEERING AND PRODUCTION STAGES

To achieve economies of scale and higher returns on investment, we must move toward a software
manufacturing process driven by technological improvements in process automation and component-based
development. Two stages of the life cycle are:

1. The engineering stage, driven by less predictable but smaller teams doing design and synthesis
activities
2. The production stage, driven by more predictable but larger teams doing construction, test, and
deployment activities

The transition between engineering and production is a crucial event for the various stakeholders. The
production plan has been agreed upon, and there is a good enough understanding of the problem and the
solution that all stakeholders can make a firm commitment to go ahead with production.
Engineering stage is decomposed into two distinct phases, inception and elaboration, and the production stage
into construction and transition. These four phases of the life-cycle process are loosely mapped to the
conceptual framework of the spiral model as shown in Figure 5-1
5.2 INCEPTION PHASE
The overriding goal of the inception phase is to achieve concurrence among stakeholders on the life-cycle
objectives for the project.

PRIMARY OBJECTIVES
Establishing the project's software scope and boundary conditions, including an operational concept,
acceptance criteria, and a clear understanding of what is and is not intended to be in the product
Discriminating the critical use cases of the system and the primary scenarios of operation that will
drive the major design trade-offs
Demonstrating at least one candidate architecture against some of the primary scenanos
Estimating the cost and schedule for the entire project (including detailed estimates for the
elaboration phase)
Estimating potential risks (sources of unpredictability)

ESSENTIAL ACTMTIES
Formulating the scope of the project. The information repository should be sufficient to define the
problem space and derive the acceptance criteria for the end product.
Synthesizing the architecture. An information repository is created that is sufficient to demonstrate the
feasibility of at least one candidate architecture and an, initial baseline of make/buy decisions so that
the cost, schedule, and resource estimates can be derived.
Planning and preparing a business case. Alternatives for risk management, staffing, iteration plans,
and cost/schedule/profitability trade-offs are evaluated.
PRIMARY EVALUATION CRITERIA
Do all stakeholders concur on the scope definition and cost and schedule estimates?
Are requirements understood, as evidenced by the fidelity of the critical use cases?
Are the cost and schedule estimates, priorities, risks, and development processes credible?
Do the depth and breadth of an architecture prototype demonstrate the preceding criteria? (The
primary value of prototyping candidate architecture is to provide a vehicle for understanding the
scope and assessing the credibility of the development group in solving the particular technical
problem.)
Are actual resource expenditures versus planned expenditures acceptable

5.2 ELABORATION PHASE


At the end of this phase, the "engineering" is considered complete. The elaboration phase activities must ensure
that the architecture, requirements, and plans are stable enough, and the risks sufficiently mitigated, that the cost
and schedule for the completion of the development can be predicted within an acceptable range. During the
elaboration phase, an executable architecture prototype is built in one or more iterations, depending on the
scope, size, & risk.
PRIMARY OBJECTIVES
Baselining the architecture as rapidly as practical (establishing a configuration-managed snapshot in which
all changes are rationalized, tracked, and maintained)
Baselining the vision
Baselining a high-fidelity plan for the construction phase
Demonstrating that the baseline architecture will support the vision at a reasonable cost in a reasonable
time

ESSENTIAL ACTIVITIES
Elaborating the vision.
Elaborating the process and infrastructure.
Elaborating the architecture and selecting components.

PRIMARY EVALUATION CRITERIA


Is the vision stable?
Is the architecture stable?
Does the executable demonstration show that the major risk elements have been addressed and credibly
resolved?
Is the construction phase plan of sufficient fidelity, and is it backed up with a credible basis of estimate?
Do all stakeholders agree that the current vision can be met if the current plan is executed to develop the
complete system in the context of the current architecture?
Are actual resource expenditures versus planned expenditures acceptable?

5.4 CONSTRUCTION PHASE


During the construction phase, all remaining components and application features are integrated into the application, and
all features are thoroughly tested. Newly developed software is integrated where required. The construction phase represents a
production process, in which emphasis is placed on managing resources and controlling operations to optimize costs, schedules,
and quality.

PRIMARY OBJECTIVES
Minimizing development costs by optimizing resources and avoiding unnecessary scrap and rework
Achieving adequate quality as rapidly as practical
Achieving useful versions (alpha, beta, and other test releases) as rapidly as practical

ESSENTIAL ACTIVITIES
Resource management, control, and process optimization
Complete component development and testing against evaluation criteria
Assessment of product releases against acceptance criteria of the vision

PRIMARY EVALUATION CRITERIA


Is this product baseline mature enough to be deployed in the user community? (Existing defects are
not obstacles to achieving the purpose of the next release.)
Is this product baseline stable enough to be deployed in the user community? (Pending changes are
not obstacles to achieving the purpose of the next release.)
Are the stakeholders ready for transition to the user community?
Are actual resource expenditures versus planned expenditures acceptable?

5.5 TRANSITION PHASE


The transition phase is entered when a baseline is mature enough to be deployed in the end-user domain. This
typically requires that a usable subset of the system has been achieved with acceptable quality levels and user
documentation so that transition to the user will provide positive results. This phase could include any of the
following activities:

1. Beta testing to validate the new system against user expectations


2. Beta testing and parallel operation relative to a legacy system it is replacing
3. Conversion of operational databases
4. Training of users and maintainers
The transition phase concludes when the deployment baseline has achieved the complete vision.

PRIMARY OBJECTIVES
Achieving user self-supportability
Achieving stakeholder concurrence that deployment baselines are complete and consistent with the
evaluation criteria of the vision
Achieving final product baselines as rapidly and cost-effectively as practical

ESSENTIAL ACTIVITIES
Synchronization and integration of concurrent construction increments into consistent deployment
baselines
Deployment-specific engineering (cutover, commercial packaging and production, sales rollout kit
development, field personnel training)
Assessment of deployment baselines against the complete vision and acceptance criteria in the
requirements set

EVALUATION CRITERIA
Is the user satisfied?
Are actual resource expenditures versus planned expenditures acceptable?

6. Artifacts of the process

6.1 THE ARTIFACT SETS


To make the development of a complete software system manageable, distinct collections of information are
organized into artifact sets. Artifact represents cohesive information that typically is developed and reviewed as
a single entity.
Life-cycle software artifacts are organized into five distinct sets that are roughly partitioned by the
underlying language of the set: management (ad hoc textual formats), requirements (organized text and models
of the problem space), design (models of the solution space), implementation (human-readable programming
language and associated source files), and deployment (machine-process able languages and associated files).
The artifact sets are shown in Figure 6-1.

6.1.1 THE MANAGEMENT SET


The management set captures the artifacts associated with process planning and execution. These artifacts
use ad hoc notations, including text, graphics, or whatever representation is required to capture the
"contracts" among project personnel (project management, architects, developers, testers, marketers,
administrators), among stakeholders (funding authority, user, software project manager, organization
manager, regulatory agency), and between project personnel and stakeholders. Specific artifacts included
in this set are the work breakdown structure (activity breakdown and financial tracking mechanism), the
business case (cost, schedule, profit expectations), the release specifications (scope, plan, objectives for
release baselines), the software development plan (project process instance), the release descriptions
(results of release baselines), the status assessments (periodic snapshots of project progress), the software
change orders (descriptions of discrete baseline changes), the deployment documents (cutover plan,
training course, sales rollout kit), and the environment (hardware and software tools, process
automation, & documentation).
Management set artifacts are evaluated, assessed, and measured through a combination of the following:
Relevant stakeholder review
Analysis of changes between the current version of the artifact and previous versions
Major milestone demonstrations of the balance among all artifacts and, in particular, the accuracy of
the business case and vision artifacts

6.1.2 THE ENGINEERING SETS


The engineering sets consist of the requirements set, the design set, the implementation set, and the
deployment set.

Requirements Set
Requirements artifacts are evaluated, assessed, and measured through a combination of the following:

Analysis of consistency with the release specifications of the management set


Analysis of consistency between the vision and the requirements models
Mapping against the design, implementation, and deployment sets to evaluate the consistency and
completeness and the semantic balance between information in the different sets
Analysis of changes between the current version of requirements artifacts and previous versions
(scrap, rework, and defect elimination trends)
Subjective review of other dimensions of quality

Design Set
UML notation is used to engineer the design models for the solution. The design set contains varying levels
of abstraction that represent the components of the solution space (their identities, attributes, static
relationships, dynamic interactions). The design set is evaluated, assessed, and measured through a combination
of the following:
Analysis of the internal consistency and quality of the design model
Analysis of consistency with the requirements models
Translation into implementation and deployment sets and notations (for example, traceability, source
code generation, compilation, linking) to evaluate the consistency and completeness and the semantic
balance between information in the sets
Analysis of changes between the current version of the design model and previous versions (scrap,
rework, and defect elimination trends)
Subjective review of other dimensions of quality
Implementation set
The implementation set includes source code (programming language notations) that represents the tangible
implementations of components (their form, interface, and dependency relationships)
Implementation sets are human-readable formats that are evaluated, assessed, and measured through a
combination of the following:
Analysis of consistency with the design models
Translation into deployment set notations (for example, compilation and linking) to evaluate the
consistency and completeness among artifact sets
Assessment of component source or executable files against relevant evaluation criteria through
inspection, analysis, demonstration, or testing
Execution of stand-alone component test cases that automatically compare expected results with
actual results
Analysis of changes between the current version of the implementation set and previous versions
(scrap, rework, and defect elimination trends)
Subjective review of other dimensions of quality

Deployment Set
The deployment set includes user deliverables and machine language notations, executable software, and the
build scripts, installation scripts, and executable target specific data necessary to use the product in its target
environment.
Deployment sets are evaluated, assessed, and measured through a combination of the following:

Testing against the usage scenarios and quality attributes defined in the requirements set to evaluate
the consistency and completeness and the~ semantic balance between information in the two sets
Testing the partitioning, replication, and allocation strategies in mapping components of the
implementation set to physical resources of the deployment system (platform type, number, network
topology)
Testing against the defined usage scenarios in the user manual such as installation, user-oriented
dynamic reconfiguration, mainstream usage, and anomaly management
Analysis of changes between the current version of the deployment set and previous versions (defect
elimination trends, performance changes)
Subjective review of other dimensions of quality
Each artifact set is the predominant development focus of one phase of the life cycle; the other sets take on
check and balance roles. As illustrated in Figure 6-2, each phase has a predominant focus: Requirements are the
focus of the inception phase; design, the elaboration phase; implementation, the construction phase; and deploy-
ment, the transition phase. The management artifacts also evolve, but at a fairly constant level across the life
cycle.
Most of today's software development tools map closely to one of the five artifact sets.
1. Management: scheduling, workflow, defect tracking, change management,
documentation, spreadsheet, resource management, and presentation tools
2. Requirements: requirements management tools
3. Design: visual modeling tools
4. Implementation: compiler/debugger tools, code analysis tools, test coverage analysis tools, and test
management tools
5. Deployment: test coverage and test automation tools, network management tools, commercial components
(operating systems, GUIs, RDBMS, networks, middleware), and installation tools.

Implementation Set versus Deployment Set


The separation of the implementation set (source code) from the deployment set (executable code) is important
because there are very different concerns with each set. The structure of the information delivered to the user
(and typically the test organization) is very different from the structure of the source code information.
Engineering decisions that have an impact on the quality of the deployment set but are relatively
incomprehensible in the design and implementation sets include the following:
Dynamically reconfigurable parameters (buffer sizes, color palettes, number of servers, number of
simultaneous clients, data files, run-time parameters)
Effects of compiler/link optimizations (such as space optimization versus speed optimization)
Performance under certain allocation strategies (centralized versus distributed, primary and shadow
threads, dynamic load balancing, hot backup versus checkpoint/rollback)
Virtual machine constraints (file descriptors, garbage collection, heap size, maximum record size,
disk file rotations)
Process-level concurrency issues (deadlock and race conditions)
Platform-specific differences in performance or behavior

6.1.3 ARTIFACT EVOLUTION OVER THE LIFE CYCLE


Each state of development represents a certain amount of precision in the final system description. Early in
the life cycle, precision is low and the representation is generally high. Eventually, the precision of
representation is high and everything is specified in full detail. Each phase of development focuses on a
particular artifact set. At the end of each phase, the overall system state will have progressed on all sets, as
illustrated in Figure 6-3.

The inception phase focuses mainly on critical requirements usually with a secondary focus on an initial
deployment view. During the elaboration phase, there is much greater depth in requirements, much more
breadth in the design set, and further work on implementation and deployment issues. The main focus of the
construction phase is design and implementation. The main focus of the transition phase is on achieving
consistency and completeness of the deployment set in the context of the other sets.

6.1.4 TEST ARTIFACTS


The test artifacts must be developed concurrently with the product from inception through
deployment. Thus, testing is a full-life-cycle activity, not a late life-cycle activity.
The test artifacts are communicated, engineered, and developed within the same artifact sets as the
developed product.
The test artifacts are implemented in programmable and repeatable formats (as software programs).
The test artifacts are documented in the same way that the product is documented.
Developers of the test artifacts use the same tools, techniques, and training as the software engineers
developing the product.
Test artifact subsets are highly project-specific, the following example clarifies the relationship between test
artifacts and the other artifact sets. Consider a project to perform seismic data processing for the purpose of oil
exploration. This system has three fundamental subsystems: (1) a sensor subsystem that captures raw seismic
data in real time and delivers these data to (2) a technical operations subsystem that converts raw data into an
organized database and manages queries to this database from (3) a display subsystem that allows workstation
operators to examine seismic data in human-readable form. Such a system would result in the following test
artifacts:
Management set. The release specifications and release descriptions capture the objectives,
evaluation criteria, and results of an intermediate milestone. These artifacts are the test plans and test
results negotiated among internal project teams. The software change orders capture test results
(defects, testability changes, requirements ambiguities, enhancements) and the closure criteria
associated with making a discrete change to a baseline.
Requirements set. The system-level use cases capture the operational concept for the system and the
acceptance test case descriptions, including the expected behavior of the system and its quality
attributes. The entire requirement set is a test artifact because it is the basis of all assessment
activities across the life cycle.
Design set. A test model for nondeliverable components needed to test the product baselines is
captured in the design set. These components include such design set artifacts as a seismic event
simulation for creating realistic sensor data; a "virtual operator" that can support unattended, after-
hours test cases; specific instrumentation suites for early demonstration of resource usage; transaction
rates or response times; and use case test drivers and component stand-alone test drivers.
Implementation set. Self-documenting source code representations for test components and test
drivers provide the equivalent of test procedures and test scripts. These source files may also include
human-readable data files representing certain statically defined data sets that are explicit test source
files. Output files from test drivers provide the equivalent of test reports.
Deployment set. Executable versions of test components, test drivers, and data files are provided.

6.2 MANAGEMENT ARTIFACTS


The management set includes several artifacts that capture intermediate results and ancillary information
necessary to document the product/process legacy, maintain the product, improve the product, and
improve the process.
Business Case
The business case artifact provides all the information necessary to determine whether the project is worth
investing in. It details the expected revenue, expected cost, technical and management plans, and backup
data necessary to demonstrate the risks and realism of the plans. The main purpose is to transform the
vision into economic terms so that an organization can make an accurate ROI assessment. The financial
forecasts are evolutionary, updated with more accurate forecasts as the life cycle progresses. Figure 6-4
provides a default outline for a business case.
Software Development Plan
The software development plan (SDP) elaborates the process framework into a fully detailed plan. Two
indications of a useful SDP are periodic updating (it is not stagnant shelfware) and understanding and
acceptance by managers and practitioners alike. Figure 6-5 provides a default outline for a software
development plan.
Work Breakdown Structure
Work breakdown structure (WBS) is the vehicle for budgeting and collecting costs. To monitor and control a
project's financial performance, the software project man1ger must have insight into project costs and how they
are expended. The structure of cost accountability is a serious project planning constraint.

Software Change Order Database


Managing change is one of the fundamental primitives of an iterative development process. With greater
change freedom, a project can iterate more productively. This flexibility increases the content, quality, and
number of iterations that a project can achieve within a given schedule. Change freedom has been achieved in
practice through automation, and today's iterative development environments carry the burden of change
management. Organizational processes that depend on manual change management techniques have
encountered major inefficiencies.

Release Specifications
The scope, plan, and objective evaluation criteria for each baseline release are derived from the vision statement
as well as many other sources (make/buy analyses, risk management concerns, architectural considerations,
shots in the dark, implementation constraints, quality thresholds). These artifacts are intended to evolve along
with the process, achieving greater fidelity as the life cycle progresses and requirements understanding matures.
Figure 6-6 provides a default outline for a release specification
Release Descriptions
Release description documents describe the results of each release, including performance against each of the
evaluation criteria in the corresponding release specification. Release baselines should be accompanied by a
release description document that describes the evaluation criteria for that configuration baseline and provides
substantiation (through demonstration, testing, inspection, or analysis) that each criterion has been addressed in
an acceptable manner. Figure 6-7 provides a default outline for a release description.
Status Assessments
Status assessments provide periodic snapshots of project health and status, including the software project
manager's risk assessment, quality indicators, and management indicators. Typical status assessments should
include a review of resources, personnel staffing, financial data (cost and revenue), top 10 risks, technical
progress (metrics snapshots), major milestone plans and results, total project or product scope & action items

Environment
An important emphasis of a modern approach is to define the development and maintenance environment as a
first-class artifact of the process. A robust, integrated development environment must support automation of the
development process. This environment should include requirements management, visual modeling, document
automation, host and target programming tools, automated regression testing, and continuous and integrated
change management, and feature and defect tracking.

Deployment
A deployment document can take many forms. Depending on the project, it could include several document
subsets for transitioning the product into operational status. In big contractual efforts in which the system is
delivered to a separate maintenance organization, deployment artifacts may include computer system operations
manuals, software installation manuals, plans and procedures for cutover (from a legacy system), site surveys,
and so forth. For commercial software products, deployment artifacts may include marketing plans, sales rollout
kits, and training courses.
Management Artifact Sequences
In each phase of the life cycle, new artifacts are produced and previously developed artifacts are updated to
incorporate lessons learned and to capture further depth and breadth of the solution. Figure 6-8 identifies a
typical sequence of artifacts across the life-cycle phases.
6.3 ENGINEERING ARTIFACTS
Most of the engineering artifacts are captured in rigorous engineering notations such as UML, programming
languages, or executable machine codes. Three engineering artifacts are explicitly intended for more general
review, and they deserve further elaboration.

Vision Document
The vision document provides a complete vision for the software system under development and. supports the
contract between the funding authority and the development organization. A project vision is meant to be
changeable as understanding evolves of the requirements, architecture, plans, and technology. A good vision
document should change slowly. Figure 6-9 provides a default outline for a vision document.

Architecture Description

The architecture description provides an organized view of the software architecture under development. It is
extracted largely from the design model and includes views of the design, implementation, and deployment sets
sufficient to understand how the operational concept of the requirements set will be achieved. The breadth of
the architecture description will vary from project to project depending on many factors. Figure 6-10 provides a
default outline for an architecture description.
Software User Manual
The software user manual provides the user with the reference documentation necessary to support the delivered
software. Although content is highly variable across application domains, the user manual should include
installation procedures, usage procedures and guidance, operational constraints, and a user interface description,
at a minimum. For software products with a user interface, this manual should be developed early in the life
cycle because it is a necessary mechanism for communicating and stabilizing an important subset of
requirements. The user manual should be written by members of the test team, who are more likely to
understand the user's perspective than the development team.

6.4 PRAGMATIC ARTIFACTS


People want to review information but don't understand the language of the artifact. Many interested
reviewers of a particular artifact will resist having to learn the engineering language in which the artifact is
written. It is not uncommon to find people (such as veteran software managers, veteran quality assurance
specialists, or an auditing authority from a regulatory agency) who react as follows: "I'm not going to learn
UML, but I want to review the design of this software, so give me a separate description such as some
flowcharts and text that I can understand."
People want to review the information but don't have access to the tools. It is not very common for the
development organization to be fully tooled; it is extremely rare that the/other stakeholders have any capability
to review the engineering artifacts on-line. Consequently, organizations are forced to exchange paper
documents. Standardized formats (such as UML, spreadsheets, Visual Basic, C++, and Ada 95), visualization
tools, and the Web are rapidly making it economically feasible for all stakeholders to exchange information
electronically.
Human-readable engineering artifacts should use rigorous notations that are complete, consistent, and
used in a self-documenting manner. Properly spelled English words should be used for all identifiers and
descriptions. Acronyms and abbreviations should be used only where they are well accepted jargon in the
context of the component's usage. Readability should be emphasized and the use of proper English words
should be required in all engineering artifacts. This practice enables understandable representations, browse
able formats (paperless review), more-rigorous notations, and reduced error rates.
Useful documentation is self-defining: It is documentation that gets used.
Paper is tangible; electronic artifacts are too easy to change. On-line and Web-based artifacts can be
changed easily and are viewed with more skepticism because of their inherent volatility.

Unit III Important questions


1. Explain briefly two stages of the life cycle engineering and production.
2. Explain different phases of the life cycle process?
Explain the goal of Inception phase, Elaboration phase, Construction phase and
3.
Transition phase.
4. Explain the overview of the artifact set
Write a short note on
5.
(a) Management Artifacts (b) Engineering Artifacts (c) Pragmatic Artifacts
UNIT - V
Checkpoints of the process: Major mile stones, Minor Milestones, Periodic status assessments.
Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating,
Iteration planning process, Pragmatic planning.

9. Checkpoints of the process


Three types of joint management reviews are conducted throughout the process:

1. Major milestones. These system wide events are held at the end of each development phase. They
provide visibility to system wide issues, synchronize the management and engineering perspectives,
and verify that the aims of the phase have been achieved.
2. Minor milestones. These iteration-focused events are conducted to review the content of an iteration
in detail and to authorize continued work.
3. Status assessments. These periodic events provide management with frequent and regular insight
into the progress being made.

Each of the four phases-inception, elaboration, construction, and transition consists of one or more iterations
and concludes with a major milestone when a planned technical capability is produced in demonstrable form.
An iteration represents a cycle of activities for which there is a well-defined intermediate result-a minor
milestone-captured with two artifacts: a release specification (the evaluation criteria and plan) and a release
description (the results). Major milestones at the end of each phase use formal, stakeholder-approved evaluation
criteria and release descriptions; minor milestones use informal, development-team-controlled versions of these
artifacts.
Figure 9-1 illustrates a typical sequence of project checkpoints for a relatively large project.
9.1 MAJOR MILESTONES
The four major milestones occur at the transition points between life-cycle phases. They can be used in many
different process models, including the conventional waterfall model. Inan iterative model, the major milestones
are used to achieve concurrence among all stakeholders on the current state of the project. Different
stakeholders have very different concerns:

Customers: schedule and budget estimates, feasibility, risk assessment, requirements understanding,
progress, product line compatibility
Users: consistency with requirements and usage scenarios, potential for accommodating growth,
quality attributes
Architects and systems engineers: product line compatibility, requirements changes, trade-off
analyses, completeness and consistency, balance among risk, quality, and usability
Developers: sufficiency of requirements detail and usage scenario descriptions, . frameworks for
component selection or development, resolution of development risk, product line compatibility,
sufficiency of the development environment
Maintainers: sufficiency of product and documentation artifacts, understandability, interoperability
with existing systems, sufficiency of maintenance environment
Others: possibly many other perspectives by stakeholders such as regulatory agencies, independent
verification and validation contractors, venture capital investors, subcontractors, associate contractors,
and sales and marketing teams
Table 9-1 summarizes the balance of information across the major milestones.
Life-Cycle Objectives Milestone
The life-cycle objectives milestone occurs at the end of the inception phase. The goal is to present to all
stakeholders a recommendation on how to proceed with development, including a plan, estimated cost and
schedule, and expected benefits and cost savings. A successfully completed life-cycle objectives milestone will
result in authorization from all stakeholders to proceed with the elaboration phase.

Life-Cycle Architecture Milestone


The life-cycle architecture milestone occurs at the end of the elaboration phase. The primary goal is to
demonstrate an executable architecture to all stakeholders. The baseline architecture consists of both a human-
readable representation (the architecture document) and a configuration-controlled set of software components
captured in the engineering artifacts. A successfully completed life-cycle architecture milestone will result in
authorization from the stakeholders to proceed with the construction phase.

The technical data listed in Figure 9-2 should have been reviewed by the time of the lifecycle architecture
milestone. Figure 9-3 provides default agendas for this milestone.
Initial Operational Capability Milestone
The initial operational capability milestone occurs late in the construction phase. The goals are to assess the
readiness of the software to begin the transition into customer/user sites and to authorize the start of acceptance
testing. Acceptance testing can be done incrementally across multiple iterations or can be completed entirely
during the transition phase is not necessarily the completion of the construction phase.
Product Release Milestone
The product release milestone occurs at the end of the transition phase. The goal is to assess the completion of
the software and its transition to the support organization, if any. The results of acceptance testing are
reviewed, and all open issues are addressed. Software quality metrics are reviewed to determine whether
quality is sufficient for transition to the support organization.

9.2 MINOR MILESTONES


For most iterations, which have a one-month to six-month duration, only two minor milestones are needed: the
iteration readiness review and the iteration assessment review.
Iteration Readiness Review. This informal milestone is conducted at the start of each iteration to
review the detailed iteration plan and the evaluation criteria that have been allocated to this iteration .
Iteration Assessment Review. This informal milestone is conducted at the end of each iteration to
assess the degree to which the iteration achieved its objectives and satisfied its evaluation criteria, to
review iteration results, to review qualification test results (if part of the iteration), to determine the
amount of rework to be done, and to review the impact of the iteration results on the plan for
subsequent iterations.

The format and content of these minor milestones tend to be highly dependent on the project and the
organizational culture. Figure 9-4 identifies the various minor milestones to be considered when a project is
being planned.

9.3 PERIODIC STATUS ASSESSMENTS


Periodic status assessments are management reviews conducted at regular intervals (monthly, quarterly) to
address progress and quality indicators, ensure continuous attention to project dynamics, and maintain open
communications among all stakeholders.
Periodic status assessments serve as project snapshots. While the period may vary, the recurring event forces
the project history to be captured and documented. Status assessments provide the following:
A mechanism for openly addressing, communicating, and resolving management issues, technical
issues, and project risks
Objective data derived directly from on-going activities and evolving product configurations
A mechanism for disseminating process, progress, quality trends, practices, and experience
information to and from all stakeholders in an open forum
Periodic status assessments are crucial for focusing continuous attention on the evolving health of the
project and its dynamic priorities. They force the software project manager to collect and review the data
periodically, force outside peer review, and encourage dissemination of best practices to and from other
stakeholders.

The default content of periodic status assessments should include the topics identified in Table 9-2.
10. Iterative process planning
A good work breakdown structure and its synchronization with the process framework are critical factors in
software project success. Development of a work breakdown structure dependent on the project management
style, organizational culture, customer preference, financial constraints, and several other hard-to-define,
project-specific parameters.
A WBS is simply a hierarchy of elements that decomposes the project plan into the discrete work tasks. A
WBS provides the following information structure:
A delineation of all significant work
A clear task decomposition for assignment of responsibilities
A framework for scheduling, budgeting, and expenditure tracking
Many parameters can drive the decomposition of work into discrete tasks: product subsystems, components,
functions, organizational units, life-cycle phases, even geographies. Most systems have a first-level
decomposition by subsystem. Subsystems are then decomposed into their components, one of which is typically
the software.

10.1.1 CONVENTIONAL WBS ISSUES


Conventional work breakdown structures frequently suffer from three fundamental flaws.

1. They are prematurely structured around the product design.


2. They are prematurely decomposed, planned, and budgeted in either too much or too little detail.
3. They are project-specific, and cross-project comparisons are usually difficult or impossible.
Conventional work breakdown structures are prematurely structured around the product design.Figure 10-1
shows a typical conventional WBS that has been structured primarily around the subsystems of its product
architecture, then further decomposed into the components of each subsystem. A WBS is the architecture for
the financial plan.
Conventional work breakdown structures are prematurely decomposed, planned, and budgeted in either too
little or too much detail. Large software projects tend to be over planned and small projects tend to be under
planned. The basic problem with planning too much detail at the outset is that the detail does not evolve with
the level of fidelity in the plan.
Conventional work breakdown structures are project-specific, and cross-project comparisons are usually
difficult or impossible. With no standard WBS structure, it is extremely difficult to compare plans, financial
data, schedule data, organizational efficiencies, cost trends, productivity trends, or quality trends across
multiple projects.

Figure 10-1 Conventional work breakdown structure, following the product hierarchy

Management
System requirement and design
Subsystem 1
Component 11
Requirements
Design
Code
Test
Documentation
(similar structures for other components)
Component 1N
Requirements
Design
Code
Test
Documentation
(similar structures for other subsystems)
Subsystem M
Component M1
Requirements
Design
Code
Test
Documentation
(similar structures for other components)
ComponentMN
Requirements
Design
Code
Test
Documentation
Integration and test
Test planning
Test procedure preparation
Testing
Test reports
Other support areas
Configuration control
Quality assurance
System administration

10.1.2 EVOLUTIONARY WORK BREAKDOWN STRUCTURES


An evolutionary WBS should organize the planning elements around the process framework rather than the
product framework. The basic recommendation for the WBS is to organize the hierarchy as follows:

First-level WBS elements are the workflows (management, environment, requirements, design,
implementation, assessment, and deployment).
Second-level elements are defined for each phase of the life cycle (inception, elaboration,
construction, and transition).
Third-level elements are defined for the focus of activities that produce the artifacts of each phase.
A default WBS consistent with the process framework (phases, workflows, and artifacts) is shown in
Figure 10-2. This recommended structure provides one example of how the elements of the process
framework can be integrated into a plan. It provides a framework for estimating the costs and schedules of
each element, allocating them across a project organization, and tracking expenditures.
The structure shown is intended to be merely a starting point. It needs to be tailored to the specifics of a
project in many ways.
Scale. Larger projects will have more levels and substructures.
Organizational structure. Projects that include subcontractors or span multiple organizational entities
may introduce constraints that necessitate different WBS allocations.
Degree of custom development. Depending on the character of the project, there can be very different
emphases in the requirements, design, and implementation workflows.
Business context. Projects developing commercial products for delivery to a broad customer base
may require much more elaborate substructures for the deployment element.
Precedent experience. Very few projects start with a clean slate. Most of them are developed as new
generations of a legacy system (with a mature WBS) or in the context of existing organizational
standards (with preordained WBS expectations).
The WBS decomposes the character of the project and maps it to the life cycle, the budget, and the
personnel. Reviewing a WBS provides insight into the important attributes, priorities, and structure of the
project plan.
Another important attribute of a good WBS is that the planning fidelity inherent in each element is
commensurate with the current life-cycle phase and project state. Figure 10-3 illustrates this idea. One of the
primary reasons for organizing the default WBS the way I have is to allow for planning elements that range
from planning packages (rough budgets that are maintained as an estimate for future elaboration rather than
being decomposed into detail) through fully planned activity networks (with a well-defined budget and
continuous assessment of actual versus planned expenditures).

Figure 10-2 Default work breakdown structure


A Management
AA Inception phase management
AAA Business case development
AAB Elaboration phase release specifications
AAC Elaboration phase WBS specifications
AAD Software development plan
AAE Inception phase project control and status assessments
AB Elaboration phase management
ABA Construction phase release specifications
ABB Construction phase WBS baselining
ABC Elaboration phase project control and status assessments
AC Construction phase management
ACA Deployment phase planning
ACB Deployment phase WBS baselining
ACC Construction phase project control and status assessments
AD Transition phase management
ADA Next generation planning
ADB Transition phase project control and status assessments
B Environment
BA Inception phase environment specification
BB Elaboration phase environment baselining
BBA Development environment installation and administration
BBB Development environment integration and custom toolsmithing
BBC SCO database formulation
BC Construction phase environment maintenance
BCA Development environment installation and administration
BCB SCO database maintenance
BD Transition phase environment maintenance
BDA Development environment maintenance and administration
BDB SCO database maintenance
BDC Maintenance environment packaging and transition
C Requirements
CA Inception phase requirements development
CCA Vision specification
CAB Use case modeling
CB Elaboration phase requirements baselining
CBA Vision baselining
CBB Use case model baselining
CC Construction phase requirements maintenance
CD Transition phase requirements maintenance
D Design
DA Inception phase architecture prototyping
DB Elaboration phase architecture baselining
DBA Architecture design modeling
DBB Design demonstration planning and conduct
DBC Software architecture description
DC Construction phase design modeling
DCA Architecture design model maintenance
DCB Component design modeling
DD Transition phase design maintenance
E Implementation
EA Inception phase component prototyping
EB Elaboration phase component implementation
EBA Critical component coding demonstration integration
EC Construction phase component implementation
ECA Initial release(s) component coding and stand-alone testing
ECB Alpha release component coding and stand-alone testing
ECC Beta release component coding and stand-alone testing
ECD Component maintenance
F Assessment
FA Inception phase assessment
FB Elaboration phase assessment
FBA Test modeling
FBB Architecture test scenario implementation
FBC Demonstration assessment and release descriptions
FC Construction phase assessment
FCA Initial release assessment and release description
FCB Alpha release assessment and release description
FCC Beta release assessment and release description
FD Transition phase assessment
FDA Product release assessment and release description
G Deployment
GA Inception phase deployment planning
GB Elaboration phase deployment planning
GC Construction phase deployment
GCA User manual baselining
GD Transition phase deployment
GDA Product transition to user

Figure 10-3 Evolution of planning fidelity in the WBS over the life cycle

Inception Elaboration

WBS ElementFidelityWBS ElementFidelity


Management High Management High
Environment Moderate Environment High
Requirement High Requirement High
Design Moderate Design High
Implementation Low Implementation Moderate
Assessment Low Assessment Moderate
Deployment Low Deployment Low
WBS ElementFidelityWBS ElementFidelity
Management High Management High
EnvironmentHigh Environment High
RequirementsLowRequirements Low
Design Low DesignModerate
Implementation Moderate ImplementationHigh
AssessmentHigh AssessmentHigh
DeploymentHigh Deployment Moderate

Transition Construction

10.2 PLANNING GUIDELINES


Software projects span a broad range of application domains. It is valuable but risky to make specific planning
recommendations independent of project context. Project-independent planning advice is also risky. There is the
risk that the guidelines may pe adopted blindly without being adapted to specific project circumstances. Two
simple planning guidelines should be considered when a project plan is being initiated or assessed. The first
guideline, detailed in Table 10-1, prescribes a default allocation of costs among the first-level WBS elements.
The second guideline, detailed in Table 10-2, prescribes the allocation of effort and schedule across the lifecycle
phases.

10-1 Web budgeting defaults


First Level WBS Element Default Budget
Management 10%
Environment 10%
Requirement 10%
Design 15%
Implementation 25%
Assessment 25%
Deployment 5%
Total 100%

Table 10-2 Default distributions of effort and schedule by phase


Domain Inception Elaboration Construction Transition
Effort 5% 20% 65% 10%
Schedule 10% 30% 50% 10%

10.3 THE COST AND SCHEDULE ESTIMATING PROCESS


Project plans need to be derived from two perspectives. The first is a forward-looking, top-down approach. It
starts with an understanding of the general requirements and constraints, derives a macro-level budget and
schedule, then decomposes these elements into lower level budgets and intermediate milestones. From this
perspective, the following planning sequence would occur:

1. The software project manager (and others) develops a characterization of the overall size, process,
environment, people, and quality required for the project.
2. A macro-level estimate of the total effort and schedule is developed using a software cost estimation
model.
3. The software project manager partitions the estimate for the effort into a top-level WBS using
guidelines such as those in Table 10-1.
4. At this point, subproject managers are given the responsibility for decomposing each of the WBS
elements into lower levels using their top-level allocation, staffing profile, and major milestone dates
as constraints.

The second perspective is a backward-looking, bottom-up approach. We start with the end in mind, analyze the
micro-level budgets and schedules, then sum all these elements into the higher level budgets and intermediate
milestones. This approach tends to define and populate the WBS from the lowest levels upward. From this per-
spective, the following planning sequence would occur:
1. The lowest level WBS elements are elaborated into detailed tasks
2. Estimates are combined and integrated into higher level budgets and milestones.
3. Comparisons are made with the top-down budgets and schedule milestones.
Milestone scheduling or budget allocation through top-down estimating tends to exaggerate the project
management biases and usually results in an overly optimistic plan. Bottom-up estimates usually exaggerate the
performer biases and result in an overly pessimistic plan.
These two planning approaches should be used together, in balance, throughout the life cycle of the
project. During the engineering stage, the top-down perspective will dominate because there is usually not
enough depth of understanding nor stability in the detailed task sequences to perform credible bottom-up
planning. During the production stage, there should be enough precedent experience and planning fidelity that
the bottom-up planning perspective will dominate. Top-down approach should be well tuned to the project-
specific parameters, so it should be used more as a global assessment technique. Figure 10-4 illustrates this life-
cycle planning balance.

Figure 10-4 Planning balance throughout the life cycle

Bottom up task level planning based on metrics from


previous iterations

Top down project level planning based on microanalysis


from previous projects

Engineering Stage Production Stage


Inception Elaboration Construction Transition
Feasibility iteration Architecture iteration Usable iteration Product
Releases
Engineering stage planning Production stage planning
emphasis emphasis

Macro level task estimation for Micro level task estimation for
production stage artifacts production stage artifacts
Micro level task estimation for Macro level task estimation for
engineering artifacts maintenance of engineering artifacts
Stakeholder concurrence Stakeholder concurrence
Coarse grained variance analysis of Fine grained variance analysis of actual
actual vs planned expenditures vs planned expenditures
Tuning the top down project
independent planning guidelines into
project specific planning guidelines
WBS definition and elaboration

10.4 THE ITERATION PLANNING PROCESS


Planning is concerned with defining the actual sequence of intermediate results. An evolutionary build plan is
important because there are always adjustments in build content and schedule as early conjecture evolves into
well-understood project circumstances. Iteration is used to mean a complete synchronization across the project,
with a well-orchestrated global assessment of the entire project baseline.
Inception iterations. The early prototyping activities integrate the foundation components of a
candidate architecture and provide an executable framework for elaborating the critical use cases of
the system. This framework includes existing components, commercial components, and custom
prototypes sufficient to demonstrate a candidate architecture and sufficient requirements
understanding to establish a credible business case, vision, and software development plan.
Elaboration iterations. These iterations result in architecture, including a complete framework and
infrastructure for execution. Upon completion of the architecture iteration, a few critical use cases should
be demonstrable: (1) initializing the architecture, (2) injecting a scenario to drive the worst-case data
processing flow through the system (for example, the peak transaction throughput or peak load scenario),
and (3) injecting a scenario to drive the worst-case control flow through the system (for example,
orchestrating the fault-tolerance use cases).
Construction iterations. Most projects require at least two major construction iterations: an alpha release
and a beta release.
Transition iterations. Most projects use a single iteration to transition a beta release into the final product.
The general guideline is that most projects will use between four and nine iterations. The typical project would
have the following six-iteration profile:
One iteration in inception: an architecture prototype
Two iterations in elaboration: architecture prototype and architecture baseline
Two iterations in construction: alpha and beta releases
One iteration in transition: product release
A very large or unprecedented project with many stakeholders may require additional inception iteration and
two additional iterations in construction, for a total of nine iterations.

10.5 PRAGMATIC PLANNING


Even though good planning is more dynamic in an iterative process, doing it accurately is far easier. While
executing iteration N of any phase, the software project manager must be monitoring and controlling against a
plan that was initiated in iteration N - 1 and must be planning iteration N + 1. The art of good project
management is to make trade-offs in the current iteration plan and the next iteration plan based on objective
results in the current iteration and previous iterations. Aside from bad architectures and misunderstood
requirements, inadequate planning (and subsequent bad management) is one of the most common reasons for
project failures. Conversely, the success of every successful project can be attributed in part to good planning.
A project's plan is a definition of how the project requirements will be transformed into' a product within the
business constraints. It must be realistic, it must be current, it must be a team product, it must be understood by
the stakeholders, and it must be used. Plans are not just for managers. The more open and visible the planning
process and results, the more ownership there is among the team members who need to execute it. Bad, closely
held plans cause attrition. Good, open plans can shape cultures and encourage teamwork.

Unit Important Questions

1. Define Model-Based software architecture?


2. Explain various process workflows?
3. Define typical sequence of life cycle checkpoints?
4. Explain general status of plans, requirements and product across the major milestones.
5. Explain conventional and Evolutionary work break down structures?
6. Explain briefly planning balance throughout the life cycle?

You might also like