Is 14658
Is 14658
Is 14658
( Reaffirmed 2004 )
ICS 29.120.60
NATIONAL FOREWORD This Indian Standard which is identical with IEC 1633
( 1995 ) `High-voltage alternating current circuit-breakers -- Guide for short-
circuit and switching test procedures for metal-enclosed and dead tank circuit-
breakers' was adopted by the Bureau of Indian Standards on the
recommendations of the High Voltage Switchgear and Controlgear Sectional
Committee ( ET 08 ) and approval of the Electrotechnical Division Council. It
gives information on test circuits and procedures for type testing relevant to
short circuit making and breaking and switching perform-ante of metal-enclosed
and dead tank circuit breakers. The text of the IEC Standard has been approved
as suitable for publication as Indian Standard without deviations. In the adopted
standard, certain terminology and conventions are not identical to those used in
Indian Standards. Attention is specially drawn to the following: a) Wherever the
words `International Standard' appear referring to this standard, they should be
read as `Indian Standard'. b) Comma (,) has been used as a decimal marker
while in Indian Standards, the current practice is to use a point (.) as the decimal
marker. In this adopted standard, reference appears to certain International
Standards for which Indian Standards also exist. The corresponding Indian
Standards which are to be substituted in their place are listed below along with
their degree of equivalence for the editions indicated: International Standatd
Corresponding Indian Standard Degree of Equivalence Identical do
Only the English language text in the International Standard has been retained
while adopting it in this Indian Standard. For the purpose of deciding whether a
particular requirement of this standard is complied with, the final value, observed
or calculated, expressing the result of a test or analysis, shall be rounded off in
accordance with IS 2:1960 `Rules for rounding off numerical values ( revised)'.
The number of significant places retained in the rounded off value should be the
same as that of the specified value in this standard.
Indian Standard
The various test cases are evaluated and special test circuits are given, or
special precautions required to use test circuits developed for open-air
equipment. The test$ described can be made in principle in both direct and
synthetic circuits.
Normative references
High-voltage
alternating-current
1) The switching units are integrated parts of a given substation design. Thus,
the surrounding components of a substation have to be considered when
defining the test conditions. 2) Several breaking units of one pole, or even all
three poles, can be placed within a common enclosure. Various components of
switching units of the substation as well as other live and earthed parts, are in
close spatial neighborhood, due to the high dielectric strength of the insulating
medium. This may lead to strong interactions of different physical nature
between parts of switching units and their surroundings. It alsO results in a
relatively high capacitance and low inductance of tested and surrounding parts.
3.2
Suitable facilities might not be available in high-power test plants for the testing
of a complete circuit-breaker or a full pole, even in laboratories which make use
of synthetic test circuits. Hence the necessity exists to perform tests on parts of
a complete circuit-breaker. Depending on the alternatives, the interactions
between the tested object and the omitted parts should be analysed: between
circuit-breaker units and surrounding parts of the substation; between poles or
between poles and the enclosure; between different units or between units and
the enclosure.
3.3
General description
Interactions, which might influence the test results and cannot be taken into
account by unit testing or single-pole testing, will require full-pole or three-pole
testing, respectively.
2
IS 14658:1999 IEC 1633( 1995) 3.3.1 /nf/uence of the surrounding parts of a
substation
Integrated parts, for example bus-bar sections, feeding cables, bushings, voltage
transformers, and surge arresters, may influence the prospective stresses of the
test circuit.
The influence of these integrated parts of the system depends on the test
sequence. On the one hand, the large capacitance of surrounding elements
reduces the stress on the circuit-breaker in the case of SLF and terminal fault
ITRV, while, on the other hand, switching of capacitor banks may be more severe
when low impedance connections are used. 3.S.2 Interaction between poles,
interrupting units and enclosures
Various types of interactions of a different physical nature can arise between the
elements of the circuit-breaker considered. The most important are: mechanical;
electrostatic; electro-magn~tic; gas dynamical.
The intensity of these interactions will, in most cases, depend on the individual
design of the object under test. If a special interaction is eliminated in a given
design, -it is no longer necessary to adjust the tests to cover this interaction. In
that case, it is necessary to demonstrate that the interaction under consideration
has negligible influence on the test results, whitih could be made by model
cakulation, or experimental demonstration, using special measuring techniques.
The same demonstration could be applied for the judgement of the degree of
interaction which has to be represented in tests. [n addition,, consideration must
be given to the case of a switching device where the configuration is not
symmetrical in respect to the terminals. 3.3.2.1 Mechanical interaction
Subclause 6.102 .3.2.-2 of IEC 56 applies. The voltage distribution between units
of. multi-break circuit-breakers, as well as the electric field in the contact-gap, is
influenced by the high capacitances and especially by the presence of the
earthed enclosure and of other live parts. It may be different in various test
sequences and for different earlhi.ng conditions.
Induced currents and return currents in the enclosure may cause additional
effects, for instance a voftage drop between earthed parts affecting auxiliary or
protective equipment.
3.3.2.4
Hot, ionized and/or contaminated exhaust gases may influence the dielectric
strength between poles in a common enclosure, and between the pole(s) and the
enclosure. Similar effects may occur between the units of a pole with more than
one interrupting unit.
4 4.1
Tests for single pole In one enclosure Short-circuit making and breaking tests
The test circuits shall comply with figures 19a, 20a, 21a and 22a of [EC 56. Test
circuits 19b, 20b, 21 b and 22b of lEC 56 do not stress metal-enclosed and dead
tank circuitbreakers in earthed fault conditions correctly.
The conditions of 6.102 of IEC 56 shall be fulfilled. The -syn-thetic test circuits
shall comply with 4.2.1, 4.2.2 and clause 5 of IEC 427.
For single-phase testing purposes two situations have to be considered: a) single-
pole testing of three-pole circuit-breakers (see 4.1.1): b} unit testing (see 4.1.2).
4.1.1 Single-pole testing of a three-pole circuit-breaker
When test circuits 21a and 22a of IEC 56 are used, the full voltage has to be
applied to one terminal of the circuit-breaker, the other terminal and the
enclosure being earthed. The recovery voltage should preferably be a.c. The
conventional director synthetic circuits shall be used.
4
IS 14658:1999 IEC 1633(1995) 4.1.2 Unit testing
The synthetic circuit is shown in figure 1, both for current and for voltage
injection. It "consistsof: - a conventional synthetic test circuit that gives the
required portion of the total TRV between the terminals of the unit(s) under test
(UBOffi9ur82); - an additional test circuit (synthetic, d.c., or a.c. source) that
energizes enclosure, insulated from earth, with a suitable voltage (UE of figure
2). the
If it is not possible to apply the voltage stresses u~ and UE at the same time, a
multipart testing procedure can be used (see 6.102.1.3 of IEC 56). In the first
part, only the performance of the unit(s) under test is checked (the enclosure of
the circuit-breaker is earthed). In the second part, the insulation between the live
parts of the pole and the enclosure is checked. This can be done, for instance,
with all units breaking the short-circuit current, but at a reduced voltage
(dependent on the available current source) and applying voltage `between the
insulated enclosure and the earth. At the moment when the TRV peak is
produced, the instantaneous value of the applied voltage to the enclosure shall
be equal to the differences between the "reduced voltqge" and the total TRV
peak to be applied between the stressed terminal and the enclosure.
.5
IS 14658:1999 EC 1633( 1995) Test circuits without the use of a third bushing
exist. The required voltage across the unit under test is produced by shunting the
other units with large capacitors. The application of such circuits is not valid for
the interaction interval, and may only be used subject to circuits can be used for
basic a~reement between manufacturer and user. These short-circuit test
sequences, if the thermal behaviour of the circuit-breaker during interaction
intetval is verified separately (for example either by two-part testing, or by
performing short-line fault tests). Pay attention that during the basic short-circuit
test sequences, the arcing times are not considerably at variance with those
obtained during the thermal verification test.
NOTES
1 In the past, some unit testing has been carried out in a test circuit in which not
all unite break the short-circuit current. Such a test circuit may only be used for
cases with negligible interaction, due to gas circulation. This is, however, mostly
not the case and is also very difficult to prove.
In this circuit, a portion of the circuit-breaker has been short-circuited. ft is
assumed that this does not produce any mechanical, electrostatic, w
electromagnetic interaction, and special attention should be paid to the
interaction due to gas circulation. A synthetic test circuit is shown in figure 3,
both for current and voltage injection. The working principle of this circuit is the
same as that of the circuit in figure"1. The value and polarity of the voltage UE,
to be applied to the enclosure are such that the resulting voltage between the
energized terminal of the circuit-breaker and the enclosure is equal to the
required value of the full-pole test voltag~. In figure 4 an example relevant to a
half-pole testing shows the required voltages. 2 Insulation between live parts and
enclosures during making and breaking short-circuit currents for most circuit-
breakers can be proved by short-ciccuit test sequences nos. 4 and 5. Short-circuit
test sequences nos. 1,2 and 3 may be performed by conventional unit test
procedures. 3 To uncouple the control circuit of the circuit-breaker from the
energized enofosure, the fibre-optics transmission technique -can be applied
suooessfulfy; the power required to operate the closing and trip coils can be
provided by a turbine generator group driven by compressed air.
4.2
Shott-line
fault tests
Subclause 6.109 of IEC 56 and 4.2.1, 4.2.2, and 6.109 of IEC 427, when the
synthetic testing method is used, apply. Provided that the basic short-circuit test
duties have been carried out, no further attention need be paid to the insulation
between the live parts and the enclosure during short-line fault tests. 4.3
Switching of capacitive currents
The testing procedure shall be in agreement with 6.111 of IEC 56. For single-
phase laboratory tests,, according to 6.111.7 of iEC 56, only the dielectric stress
between terminals of the circuit-breaker is correctly reproduced. When the
dielectric stress between the terminals and the enclosure cannot be reproduced
correctly, additional tests shall be carried out.
6
IS 14658 :t999 IEC 1633(1995) Thus, laboratory tests for the verification of the
capacitive current switching shall be performed in accordance with the following
procedure. a) Performance of the switching test sequences in accordance with
6.111 of IEC 56. b) Performance of an additional dielectric test with the aim of
applying proper d.c. and/or power frequency dielectric stresses between the
terminals and the enclosure.
The need to apply power frequency voltage, or d.c. voltage, or both and their
values shall be determined. takino into account the conditions of the system and
the actual values of the source-side and-load-side voltages verified during the
switching tests given in a) above. Typical values of the source-side, load-side,
and recovery voltages during capacitive current switching are given in tables 1A
and B.
If the withstand to the power frequency voltage has to be checked, this voltage
shall be applied on the source-side terminal of the circuit-breaker, and shall be
maintained for 1 min. If the withstand to the d.c. voltage has to be checked, this
voltage shall be applied orkJhe load-side terminal of the circuit-breaker and
maintained for 0.3 s. When power frequency and d.c. voltage stresses have to be
verified, the voltages can be applied on the terminals in separate steps.
Souroa
2==+ `"ad
7
IS 14658:1999 IEC 1633(1995) Table 1A - Three-phase capacitive current
switching in actual service conditions: typlml values of the source-side, Ioad-side,
and recovery voltages
Unearthed capacitor
Lines
In all cases
Poles A and B dear at the first current zeros after the cfearance of pole C Poles A
and B do not cfear at the
C/earth C'/earth
u @151,5 u @/@g*5
U fl/G
u 6/6 2
u WIG
f,2 u.JF/JF 2,2 u p/fl
Clc'
C/earth
u @JT
U@#/@ u GIG
u 6/6
23
C'le&rth Clc'
u ~/@ u @T
u 4Z-IG
2111&/&C'.
u @/w
2
u F/+T
C = source side
loadside
NOTE - The indicated values for unearthed system apply if the source-side zero
sequence capacitance is negligible compared to that of the load side.
Lines
In all cases
C/earth C'/earth
1,4
u fl/G
u @/@ u 6/6
2
1,2
u d%6-
1,4 u WIG
1.4uc/4T
2,8 U @_/@
1,2u C]6
2,4 U @_/@
Clc'
C/C' = first pole to clear U = rated voltage
u @/@
Up[@
C = source side
8
IS 14658:1999 -IEC 1633(1995)
With the neutral of the supply earthed and in presence of single- or two-phase
earth faults, the voltages in the healthy phases can reach up to 1,4 U=. The
precise value depends on the zero sequence impedances. In that case, the
values of the voltages on source-side and load-side terminals to earth which
should be considered are: C/earth = C'/earth = 1,4 U@fi C/C' = 2,8 U
@/'~(recove~ voltage)
With the neutral of the supply -not earthed and in presence of single- or two-
phase earth faults, the voltages in the healthy phases can reach up to
approximately 1,7 U~ In that case, the values of the voltages on source-side and
load-side terminals to eaflh which should be considered are: C/earth = C'/earth =
1,7 U~lfi C/C' = 3,4 UJZK(recovery 4.3.1 Single-pole voftage)
Direct circuits or synthetic circuits shall be used. In some synthetic test circuits,
both voltages are combined at one terminal of the circuit-breaker, the other
terminal being earthed. This condition is more severe for the insulation to earth
and may effect the severity of the test across the circuit-breaker. To compensate
for this eff6ct, a bias voltage stress to the enclosure may be applied.
Possible solutions relevant to the current injection circuit and to the ciFcuit using
two power frequency sources are illustrated in figures 5 and 6. 4.3.2 Unit testing
II is necessary to take into account local field distortion within the gap between
neighboring elements, such as enclosures. In some cases, depending on the
number of the units of the pole, the test circuits do not reproduce the requested
d.c. and a.c. recovery voltages between the live parts of the unit(s) under test
and the enclosure.
Unit testing is only acceptable if the field strength to earth at one terminal is
equal to the field strength to earth at full-pole testing. This condition can be met
by:
Out-of-phase
switching
4.4.1
Single-pole
The symmetrical synthetic circuit is formed by two voltage circuits having TRV of
opposite polarity and oscillating at equal or different frequencies (see figure 8).
The injection of the two circuits shall occur in a suitable sequence in order to
obtain the required voltage stresses both between the terminals and between, at
least, one of the terminals and the enclosure. The voltage circuits can be
according to the current injection or voltage injection method, or a combination
of the two. Afternatively, a conventional direct or synthetic circuit can be used
with one of the terminals of the circuit-breaker earthed and the enclosure
energized and insulated from earth. 4.4.2 Unit testing
To reproduce the correct voltage stress between the terminals and the enclosure,
the enclosure has to be insulated and energized using a voltage source as
described in 4.1.2.
10
IS 14658:1999 IEC 1633(1995) Unit testing with the enclosure and one terminal
of the circuit-breaker earthed is permissible, provided that the required voltage
stress between the terminals and the enclosure has already been checked during
the short-circuit tests. 5 5.1 5.1.1 Tests for three poles In one enclosure Terminal
fault tests Test procedure
b) Information about the required test circuits for test sequences 4 and 5 is given
in table 2. Table 2Information on test clrcults for test sequences 4 and 5 ,
Test duty 4
Test duty 5 Other poles First clearing pole Application of 4.2.1 or 4.2.2 of IEC 427
for at least two operations. The third operation can be tested with 4.2.3 Other
poles Application of 4.2.1 or 4.2.2 of IEC 427 at least to the operation with major
extendad foop and longest arcing time
:.P.C.F
Firstclearing pole
Application of synthetic circuits of 4.2.1 or 4.2.2 of IEC 427 at all operations
1,5
Application of 4.2.1 or 4.2.2 of fEC 427 for at feast two operations. The third
operation can be tested with 4.2.3
Application ,of4.2.1 or 4.2.2 of IEC 427 at least to the second cfearing pole at the
operation with the longest arcing time
Application of 4.2.1 or 4.2.2 of IEC 427 for at least two operations. The third
operation can be tested with 4.2.3
Application of 4.2.1 or 4.2.2 of IEC 427 at least to the second clearing pole at the
operation with major extended foop and longest arcing time
11
IS 14658:1999 IEC 1633(1995) c) Between the different poles and between poles
and the enclosure, the maximum stresses for TRV and RV are given in tables 3
and 4 (see also figures 9 and 10). These stresses may be tested by using
synthetic circuits of 4.2.3 of IEC 427. For test duty 5, reference should be made
to IEC 427, 6.106.5. The recovery voltage shall be a.c. Table 3Test duties 1, 2,3
and 4- First-poie-to-ciear Voitage vaiues during 3-phase interruption
TRV peak/TRV peak first pole % RV peak At the rnstance At the instance of first-
pole af second-pole clearance clearance a b c a-b b-c c-a duldt
factor: 1,5.
p"
Phases
oo
100
58
S8 I
115 "58
1
1 1,732 1,732
70 70
100
o
100 100
Between phases
58
1,732
Uc= TRV peak first pole = 1,5 .1,4 U ~,~ lpu. ul@-
Tabie 4-
factor: 1,3.
RV peak pu
dlddt
%
Phases
oo
100 o 100 100
0 98 / 98 89
I
77 I I 98 1
91
1 1 1 1,732 1,732
1,732
70 95 100
Between phases
Uc = TRV peak first pole = 1,3 .1,4 U ~/d~ lpu=u~l~ The first pole to clear is
located on phase c.
12
IS 14658:1999 IEC 1633( 1995) d) In accordance with the requirements of
6.105.1 of IEC 56, and with the aim to reduce to the minimum the time interval,
and also to avoid changing the connection of the high-voltage circuit to the
circuit-breaker between the tests of each test sequence, all the required arcing
times shall be applied on the same phase. e) All the above stresses preferably
should be applied in the same test. If this is impossible, a multi-part testing
procedure may be allowed.
5.1.2
Test circuits
Different circuits are now used with different features. In the following, some
circuits are described; for the validity of these circuits refer to 5.2.
5.2
Short-line
Subclauses 6.102.2 and 6.102.3 of IEG 56 apply. NOTE - The spaoial situation of
three-phase short-fine fault with magnetic interaction batwaan phases `is under
oonsidamtion.
13
IS 14658:1999 IEC 1633(1995) 5.3 Capacitive current switching tests
Table 5-
Earthed capacitor banks pu 1,0 1,0 2,0 S1.73 2,0 2,0 2,0 2,0 2,0 2,0 2,7t 2,0 A =
Source side
Lines
Unearthed systems
pu 1,0 1,2 2,2 S1,73 2,1 1,9 2,0 1,9 2,2 1,9 2,2 2,0 A'= Load side
pu 1,5 1,0 2,5 S1,73 2,37 S1,73 1,87 1,87 2,5 1,87 2,5 1,s7
A-earth A'earth A-A' -N-a' A'.& B'-c* A-B' A-C' B-A' B-C' C-A' C-B'
1,0 1,5 2,5 <1,73 2,37 <1,73 1,87 1,87 2,5 1.87 2,5 1,87
Poles Band C clear at the first current zeros after the clearance of pole A. The
voltage value for A-B, A-C and B-C are in all cases equal to U ~. The voltages B-
earth, B-earth, B-B and C-earth, C'-earth and C-C' are not incorporated in the
table, beoause their values are lower than those for pole A.
-5.4
Out-of-phase
switching
test
14
IS 14658:1999 IEC 1633(1995)
IJ
U*
I
--
Uh
-t-d
U*
1
4
Ch
1
%
*
Uh
Sa ,
St
\
--
lb - Typical injection circuit with voltage circuit in parallel with the unit(s) ueed aa
auxiliarybreaker
s* St
G= u, i= ih Lh Zh Ch
= voltage of the current circuit currant of the current circuit = injected current =
inductance of voltage circuit = equivalent surge impedance of voltage circuit =
capacitance of voltage circuit which, together with Lh, contrcls the major part of
the TRV
with interaction
due
15
IS 14658:1999 IEC 1633(1995)
UC-B
"o
t2
Time -
u~
voltage voltage
u~ /.
..
." UA
~b
U*
u,
~ = instant of injection of the voltage UB
UA
I
Time
Current
Current
llE
U8
= voltage applied to the contact gap of the unit(s) under test (resuftfng voltage
between the terminaf not earthed of the unit under teat and the enclosure; a
tinear distribution of the voltage between the unite is assumed)
"1 UA
= voltage of the current circuit = resulting voltage between the terminal of the
auxifiary unit(s) connected to the current cfrcuit and
me encfosure
Figure 2-
16
1S 14658:1999 IEC 1633(1995)
`h
3a - Typical injaction circuit with voltaga circuit in parallel with the unit(a) undar
teat L,
Uh
--
3b - Typical injection circuit with voltage circuit in parallel with the auxiliary
circuit-breaker Sa St G % i= `h = = = = = auxiliary circuit-breaker unit (s) of the
circuit-breaker under test source for supply of UE, applied to the enclosure
voltage of the current circuit current of the current circuit injected currant
inductance of voltage circuit equivalent surge impedance of voltage circuit
capacitance of voltage circuit which together with Lh controls the major part of
the TRV
Lh = Zh = Ch = Figure
3-
Synthetic test circuit for unit testing (circuit-breaker interaction due to gas
circulation)
with negligible
17
IS 14658:1999 IEC 1633(1995)
Voltage "c
-c
UC= UB-UE
Uc -B
`c -E
E1
I
L2
II
f
I
II1
II
I UB
I
1I
II
/////////////////////
//
r/
(IE . %3 = u= =
voltage applied tothe insulated enclosure voltage applied to the contact gap of
the unit(s) under test resulting voltage between the energized terminal of the
unit(s) under test and the enclosure Figure 4testing of a clrcult-breaker inthe test
of figure 3. Exarnpie of the required TRVS to be appiied between the terminais of
the unit(s) under test and between the iive parts and the insuiated enciosure
Half-pole
18
IS 14658:1999 IEC 1633(1995)
i
a) c LC sa iL St (~ ~ See detail iv
c"
II
Lv
`P
Ce
-----r-+ t-=-%1+
f+
U* Ail
Rw
L
ev
+-i
up
= test voitage
(IA = raeuiting voltage between the energized terminai of the circuit-breaker and
the enciosure Ue resuiting voitage between the earthad terminai of tha circuit-
breaker and the enciosure
ic `v i~
Sa = auxiiiary circuit-breakars
1
6=
1
iv
J
St
Breaking operation b)
iv
iL
`P
U*
Figure 5b - Qualitative
Figure 5-
of
IS 14658:1999 IEC 1633(1995)
"1 % up
`A
= voltage of the current circuit = voltage of the voltage circuit teat voltage .
=
test voltage resulting voltage batween the enarg~ed terminal of the circuit-
breaker and the enclosure resulting voltage between the earthed terminal of the
circuit-breaker and the enclosure current of the current circuit current of the
voltage circuit test current
UB
i= iv `L
==
Breaking operation
b)
iC*
iv
ii
`P
UA
UB
Figure 6-
Capacitive synthetic circuit using two power frequency with the enciosure of the
circuit-breaker energized
sources and
20
IS 14658:1999 IEC 1633(1995)
i=
LC
s=
a)
See detail
,"1L pf
UE I "1
Detail I c lv~ "A
..
d.c. voltage apptied to the insulated enclosure rasulting voltage between the
energized terminal of the unit(s) under test and the enclosure resulting voltage
between the earthed terminal of the unit(s) under test and the enclosure current
of the current source injected current test current
I
f
3
I
. `A . . .
UE
`c `v
`L s,
..
`c
= auxiliary circuit-breakers .
circuit-breaker under test
s,
Sreaking operation b) ` i= `P =
2U~-N.K.m n~
m = multiplying factor for the single phase capacitive current switching tests K N
n. = voltage distribution factor = number of units under tests (N=l ) total number
of units of a pole (n=2)
`P "A
o UE= UB o
NOTE - UE shall have the same polarity as the test voltage Up. Figure 7b -
Qualitative current and voltage wave shapes
Fiaure 7-
Capacitive synthetic current inlection circuit. Exampie of unit testin9 on. haif a
poie of a circuit-bre-aker with two units `per poie. Enciosure energized with a d.c.
voitage source
21
IS 14658:1999 IEC 1633(1995)
L, I
Sa 1 I
U*
Voltage circuit A
I.-L
"1 =
"A "e up 1= = = =
t' 6
.s,
L__J
`P
_l--
II
,,
I
vottage of the current circuit voltage applied to one terminal of the tircuit-
braaker under test voltage applied to the other terminal of the circuit-breaker
undar test test voltage current in the test circuit-breaker auxiliary circuit-breaker
Sa = s,
L,
=
=
te$t Circuit-braakar
inductances of current circuit
Figure 8-
switching tests
22
Is 14656:1999 IEC 1633(1995)
Figure 9-
23
IS
IEC
Figure 10-
24
IS 14658:1999 IEC 1633(1995)
TR
E
G2
o00I
I I L ZOH
1A I 1 L -----
+!3
s,
TRV1 I [ TRV1 I I TRV1 A
s,
HC G2 G= TR
==
TRVI = TRV2 = St s, = =
Z.
Figure
11-
Three-phase
transforfner
injection
circuit
25
IS 14658:1999 IEC 1633( 1995)
I I L ZOH 1+ I I I I
II
s,
Voltage circuit dupfhe ckcuit
`-:+
s, #
ItI
/' =
L----
-----
----
Wi!!zzPi t
-----------------d I
factor 1,3 is
HC
s, St ?)=
a,b b,c
= t-t Circuit-breaker
impedance in the neutral connection (when circuit 20a of IEC 56, first-pole.to-
dear Used) = = voltage injection circuit currant injection circuit
Figure 12-
Combined clrcqi~
1S 14658:1999 IEC 1633(1995)
II
----
-*
-----
b.
s,
ZOH lJ
I 1. -------------------------
s,
,"+ :
I
I
-----
Figuro 1Ss
voltage circuit
I -----, I I I I I
IAIIII
I -----~ I I I I I I
c I I I I 4h (b
HC G;=
L ----s,
Voltage circuit
L ----s,
I=
Figure 13b
HC St s, 4
Figure 13-
27
IS 14658:1999 IEC 1633(1995)
Voltage oircuits
I I `->--~
,-----,
s,
I
s,
I
IIII
t- -----
-----
-----
-----
-----
------
-----
-----
HC St s,
==
= `auxiliary circuit-breaker
Z.
= impedanoe in the neutral connection (when circuit 20a of IEC 56, first-pole-to-
clear `factor 1,3 is
used)
Figure 14-
Three-phase
duplicate circuit
28
Bureau of Indian
Standards
Copyright 131S has the copyright of all its publications. NOpart of these
publications maybe reproduced in any form without the prior permission in
writing of BIS. This does not preclude the free use, in the course of implementing
the standard, of necessary details, such as symbols and sizes, type or grade
designations. Enquiries relating-to copyright be addressed to the Director
(Publications), BIS.
Review of Indian Standards
Date of Issue
Text Affected
BUREAU
Headquarters:
OF
INDIAN
STANDARDS
Telegrams: Manaksanstha ( Common to all offices ) Telephone 3237617
{ 3233841 3378499, 3378626, { 3378561 3378662 603843 { 602025
2350216,2350442 { 2351519,2352315 8329295,8327858 { 8327891,8327892
Manak Bhavan, 9 Bahadur Shah Zafar Marg, New Delhi 110002 Telephones :
3230131, 3239402, 3233375 Regional Offices: Central : Manak Bhavan, 9
Bahadur Shah Zafar Marg NEW DELHI 110002 Eastern : 1/14 C. I. T. Scheme VII
M, V. I. P. Road, Maniktola CALCUTTA 700054 Northern : SCO 335-336, Sector 34-
A, CHANDIGARH 160022 Southern : C. I. T Campus, IV Cross Road, CHENNAI
600113 Western : Manaka:aya, E9 MIDC, Marol, Andheri (East) MUMBAI 400093