I introduce myself A.PALANISAMY as, an Electrical Engineering Graduate having more than 30
years experience in the field of Electrical & HVAC equipments Construction, Installation,
Testing and Commissioning, HSE / PTW system (Electrical Isolation Authority / safety
Officer) and Production & Maintenance Equipments in Power Plant, OIL & GAS Plant. I
have experience in QA/QC activities of Electrical Equipments and ICAPS / IMIS / EDMS/ IDWH Documentations
maintaining & up-dating in OIL & GAS, POWER Plant & Marine field sectors.

I worked as Senior Engineer (Electrical) in AGIP KCO company at KAZAKHSTAN EP Project from Nov-2007 to
Jan-2012. Agip KCO co. is responsible for the execution and development of the giant Kashagan field in the North
Caspian Sea.

I worked (short term) as Senior Electrical Engineer in JGC (Japan Gas Corporation) at Nigeria BRT site (EAP-3
project at BRT site in NGL project).

I worked as Senior Commissioning Engineer in HVAC department at SHOAIBA POWER PLANT stage-II phase-1
(3X390MW) in Kingdom of Saudi Arabia.

I have worked as Electrical Engineer in ENELPOWER co. for RLPC (RasLaffan Power Company Power plant
project of 750 MW with 220KV sub-station) at QATAR.

I worked as Electrical Engineer in HYUNDAI Engineering & construction co, for Pre-com, Commissioning activities
Monitoring & / Work permit coordinator (HSE Electrical Isolation Authority) at IRAN for SOUTH PARS GAS
DEVELOPMENT Phase 4 & 5(A 1 Project) at IRAN, [Main client is ENI IRAN B.V].
Further I worked as Electrical Engineer in HYUNDAI Engineering & construction Co at IRAN for SOUTH PARS
GAS FIELD DEVELOPMENT Phase 2 & 3 (STAS project) at IRAN (main client is TOTAL FINA ELF co.) for Pre-
com, commissioning activities Monitoring for Electrical works.

Then I worked as PROJECT ENGINEER in INNOX POWER ENGINEERING, SINGAPORE, JAYA MARINE
GENERAL CONTRACTOR PTE LTD SINGAPORE, and AZEN MANUFACTURING PTE LTD SINGAPORE under
EMPLOYMENT PASS for 2.5 years.

I have 18 years experience in INDIA in Government sector undertaking Transport corporation & other.

I have got APPRECIATION REFERENCE LETTERS from my previous Project Managers (Billion Dollar projects of
South Pars Gas field Developments phase 2&3, 4&5 projects in IRAN and SBM project in Singapore).
Indebted with good communication skills, aptitude and specialized in Pre-com, Commissioning, start-up & Maintenance
of Electrical Equipments in Oil, Gas and Power plant projects. I would like to seek employment with your organization
for a job which offers good growth potential and perks commensurable with experience and qualifications. With proven
track record, I am sure to live up to your expectations.

This is a quest for a long-term career and not a short-term arrangement. I attach a brief resume of my career (to date) for
your reference and consideration. Hope to get a favorable response.

With Best regards,


Yours sincerely
A. palanisamy.
Present contact address:
C-2 Ragamaliga Apartment, Adyar, Chennai, India.
contact number at India :+91-9894720908
at Muscat (OMAN): +968-24478479
E. mail : apsamy57@gmail.com OR apsamy57@yahoo.com
CURRICULUM VITAE
GENERAL

1.1 Full name : ALAGARSAMY PALANISAMY


1.2 Date of birth & Age : 20-March-1957 (56 years)

1.3 Adress (Permanent) : E-13, Nethaji 5 th cross street, Thirunagar, Madurai, Tamilnadu, India.

Present contact address : A.Palanisamy, C-2 Ragamaliga Apartment,


No 2 Jeevarathinam nagar Adyar, Chennai - 600020

contact number : +91-9894720908 (India) OR +968-24478479 (OMAN)

1.4 E.mail Address : apsamy57@gmail.com OR apsamy57@yahoo.com

1.5 Passport no. : Z 2005240 (Valid up to 07-June-2019)

QUALIFICATION

sl no Exam passed Year Board / University Div. (%)


Madurai kamaraj University
Bachelor of Engineering (Electrical
2.1 1990 ( Thiagarajar college of 64%
&Electronics )
Engg.Madurai)
2.2 Diploma in Electrical Engineering 1979 Tamilnadu Polytechnic, Madurai 69%

ADDITIONAL QUALIFICATION.

MS WORD, EXCELL, AUTOCAD, ORACLE, D2K &


3.1 Computer knowledge 1998
OFFICE 2000
Competency certificate for Electrical
3.2 1979 Issued by Government of Tamilnadu INDIA
Supervisor
National certificate of Examination in
3.3 1982 Issued by National Productivity council Delhi
Supervision
3.4 Supervisory Examination certificate 1990 Issued by Institute of Road Transport, Madras

WORKING EXPERIENCE : 12 YEARS in ABROAD & 18 YEARS in INDIA.


Sl
no Name of company Position Period Type of company/ project.
Agip KCO Atyrau, Senior Lead 4 years 2
4.1 Oil & Gas Production Experimental Project
Kazakhstan Engineer months
Japan Gas Senior
4.2 corporation Ltd, Electrical 7 Months NGL Project in BRT site at Nigeria
Nigeria site Engineer
INTOP International Sen. Commg
4.3 3 months Shoaiba Power Plant at Saudi Arabia.
co, Abudhabi. Engineer
ENELPOWER co, Electrical
4.4 6 months Power Plant (RLPC Project)
Qatar site Engineer
HYUNDAI
Electrical A-1 project (Gas Plant with captive Power Plant) IRAN
4.5 Engineering & 1 year
Engineer site.
construction co.
HYUNDAI
Electrical STAS project (Gas Plant with captive Power Plant)
4.6 Engineering & 1.1 year
Engineer IRAN site.
construction co.
INNOX power
Project Marine Electrical contract works. (keppel, Fels,
4.7 Engineering 5 months
Engineer Sembawang, Jurong), SINGAPORE.
SINGAPORE
JAYA Marine general
Project
4.8 contractor, 8 months Marine Electrical contract works. SINGAPORE.
Engineer
SINGAPORE
AZEN
Electrical AXIAL fan (industrial,Marine use) Manufacturing
4.9 Manufacturing 1 year
Engineer company, SINGAPORE.
SINGAPORE
Pandiyan Roadways Assistant Transport service & Vehicle Maintenance.(Electrical
4.10 14 Years
Corporation, Madurai Engineer utilities)
Rasi Engineering Electrical
4.11 2.5 years Industrial Electrical contractor.
works Trichirappalli Engineer
Tamilnadu Electricity
4.12 Tech.Asst 1 year Electricity Generation & Distribution System
Board. Chennai

The following skill of Experience are Gathered in Power, Oil & Gas development projects.

* Experience in Construction, Pre-com, Commissioning & start-up procedures review in Power and Oil & Gas plant.
* PTW system (PTW coordinator / Electrical isolation authority) implementations
* Experience in the installation and Testing of electrical systems for onshore oil and gas facilities.
* Ability to read electrical drawings, SLD, block diagrams, schematics, termination drawings.
* Understanding of a complete management system.
* Familiar with, and experience in the application of, relevant codes and standards.
* Ability to interpret and apply the requirements of technical specifications and test acceptance criteria.
* Familiar with the implementation of inspection and test plans.
* Experienced in punch listing and rectifications.
* Perform electrical equipment inspections on (Ex) certified equipment.
* Perform Electrical equipments Operation & maintenance planning, scheduling and monitoring.
* Witness electrical tests and agree acceptance.
* Certified for inspection / test of hazardous area equipment.
* Ability to work unsupervised and be self motivated.

(4.0) Worked as SENIOR ENGINEER {ELECTRICAL} (from Nov-2007 to Jan-2012) in Agip KCO Kazakhstan
North Caspian Operating Company.
Agip KCO is the Operator of the North Caspian Sea Production Sharing Agreement (PSA) on behalf of a
consortium of oil companies: Eni (Operator), KazMunayGas, ExxonMobil, Shell, Total, ConocoPhillips and
INPEX. They are developing 11 blocks in the Kazakhstan sector of the Caspian Sea where the giant field of
Kashagan has been discovered.
My Prime Responsibilities & Duties are:

* Define maintenance system boundaries on project documentation, and assign into a functional asset
hierarchy.
* Maintenance analysis of platform equipment and systems.
* Equipment data retrieval and recording in various registers and computer systems.
* Analysis of maintenance work content and development of work order documentation.
* Performance of maintenance work order and task list scheduling and alignment.
* Provision of instruction to maintenance analyst and technical assistants and other team members as required.
* Performance of data and procedural quality checks.
* Review of equipment data sources and support of optimum transfer to the Maintenance Management system.
* Progress and reporting of allocated tasks and input into the weekly report.
* Providing maintenance input to modifications
* Taking accountability for overall maintenance planning
* Ensuring compliance with safety case maintenance requirements

(4.1) Worked as LEAD ELECTRICAL ENGINEER in JGC (Japan Gas Corporation) for NGL project at Nigeria
BRT site from April-07 to Oct-07.
Following are my responsibilities.
(a) To Lead & monitoring of electrical construction activities, inspection based on Technical specifications of the
project.
(b) To Review & modify pre-com, commissioning procedures submitted by contractors.
(c) Testing & commissioning of 4.5MW/6.6KV Gas Turbine Generator with 6.6KV/400V substation switchgears &
MCCs with relevant NGL Gas processing equipments like MV/LV motors control panels with lighting system.
(c) LOTO system (Lag Out Tag Out) for Isolation activities with PTW system implementation.

(4.2) I Worked as Senior Commissioning Engineer in HVAC system at Shoaiba Power Plant in Kingdom of Saudi Arabia
through INTOP INTERNATIONAL CO, ABUDHABI for short term (3 months from May-06 To July-06).
Responsible for independent commissioning of HVAC Package units (PMX540 / 240 type) with necessary auxiliary
equipments in all Electrical Control buildings (sub-stations) of this Power plant.
Preparing As-built drawings and Commissioning documentations like TOP (Turnover Package) & ITPL (Inspection
& Test Plan) preparations & progress updating.

(4.3) I Worked as Electrical Engineer in ENELPOWER CO. [American Engineering Services is the Main client of
this RLPC Project] for 750MW Power Plant with 220KV GIS sub-station at QATAR.
The following Engineering jobs are my Responsibility of this project as short term of 6 month (Jul05 to Dec05).
As-built Drawings preparation with site Modifications based on commissioning and after modifications based on
site conditions (modifications are done with AutoCAD) for 750 MW Power Plant having 4X110MW Gas
turbine Generators (GE9171 model Gas turbines) & 2X180MW Steam Turbine Generators (including 4
heat recovery steam generators (HRSG) with supplementary firing) and 210MW & 450MVA Power
Transformer in 220KV GIS Double-Bus sub-station.
Punch list of jobs are arrange to clear with additionally required items are prepared for approval by the
client and implemented with necessary modifications of relevant documents.

(4.3) I worked as ELECTRICAL ENGINEER in HYUNDAI ENGINEERING & CONSTRUCTION CO. at IRAN
for SOUTH PARS PHASE 4&5 ON-SHORE FACILITIES PROJECT (GAS PLANT with
CAPTIVE POWER PLANT of 4 x 40MW) with the following responsible works (ENI IRAN B.V is main client).
From Jan-2004 to Dec-2004.

The following are my Main Activities in this Project.

Documentation ICAPS (Integrated Commissioning & Planning System) Dossiers preparations and updating of
Pre-com & commissioning activities in ICAPS with updating the progress and monitoring, and Punch list
follow-up.
Pre-commissioning & Commissioning of 160 MW POWER PLANT having Gas / Diesel Turbine Generator
(4x40MW) with 12 SUB-STATIONS of 6K.V panel Board and 400V Switch Board (33KV/6KV switchboards in
main substation & 6KV/400V switchboards in all other substations). With pre-commissioning & commissioning of
HVAC Equipments in all sub-stations & admin building.
Familiar to adopt HSE Procedure, for General & Electrical protection of safety procedure during Testing,
commissioning & maintenance works with co-ordination of Commissioning section & Client with preparation of
necessary work permits.
In charge of Isolation Authority for All Electrical HV &LV Equipments in Power plant & Gas plant activities.
Worked as PTW controller with Isolation authority by adopting HSE/PTW procedure & safety procedures.
Arranging client Inspection / Energisation with necessary document preparation and supporting details.
As-commissioned drawings, related to (Power plant & Gas plant) Electrical activities of this project up-dating & co-
ordination to Field Engineering for implementation.
I have got APPRECIATION REFERENCE LETTERS from my Project commissioning Manager for the jobs
performed.

(4.4) WORKED AS ELECTRICAL ENGINEER in HYUNDAI ENGINEERING & CONSTRUCTION CO. at IRAN.
For SOUTH PARS PHASE 2&3 ON-SHORE FACILITIES PROJECT(GAS PLANT & CAPTIVE
POWER PLANT of 4x30MW & 1x20MW) TOTAL FINA ELF is the main client. From August 2001 to
September 2002.

Pre-commissioning & Commissioning of 140 MW POWER PLANT having Gas / Diesel Turbine
Generator & Steam Turbine Generator (4x30MW & 1x20MW) with 7 in-door SUB-STATIONS of 6K.V panel Board
and 400V Switch Board (33KV/6KV switchboards in main substation & 6KV/400V switchboards in all other substations).
With following Major equipments.
Generator : LEROY & SOMER / BRUSH / JEUMOUNT - 11 KV / 30MW & 6KV / 2MW.
Transformer: FRANSTRANSFO 11KV/33KV, 33KV/6KV & 6KV/400V. UPTO 50MVA
Protection Relays & panels: ALSTOM, ABB, SPIE.
With pre-commissioning & commissioning of HVAC Equipments in all sub-stations & admin building.
Familiar to adopt HSE Procedure, General & Electrical protection of safety procedure during Testing,
commissioning & maintenance works with co-ordination of Commissioning section in Client side with preparation
of necessary work permits.
Co-ordination of Pre-commissioning, Commissioning of All plant equipment motors & Electrical Equipments of
Generators, Transformers, Circuit breakers & MCCs.
Documentation for Integrated commissioning & planning (ICAPS) Dossiers preparations for client inspections,
and updating with up-to date progress monitoring. With Punch list follow-up.
As-commissioned drawings, related to (Power plant & Gas plant) Electrical activities of this project up-dating & co-
ordination to Field Engineering for implementation
Work permit procedure (Hot & Cold works) adopting for HSE safety procedures to Electrical Isolation for
HV & LV equipments in Hazardous & non-Hazardous areas.
I have got APPRECIATION REFERENCE LETTERS from my Project Commissioning Manager for the
jobs performed.

(4.5) WORKED AS PROJECT ENGINEER IN INNOX POWER ENGINEERING (S) PTE. LTD.,
SINGAPORE From May 99 TO October99.

The following projects responsible are handled for the production, which includes organizing, directing
and co- ordination.

1. GALAXY-III PROJECT (OFFSHORE RIG SHIP) at KEPPEL FELS, E&I installation including fixing of panel,
distribution board, cable wiring testing and commissioning, Quality control inspection combined with clients and
preparation of necessary documentation.
2. For SBM PROJECT KUITO FIELD PHASE-1 (PROSTER-II) FPSO (Floating production storage offloading) at
SEMBAWANG SHIPYARD Module 2&3, E&I installation including fixing of panel, distribution board, cable wiring
with testing and commissioning and QC inspection with documents.
3. For SBM PROJECT, (ESPADARTE FIELD FPSO-IV) at UDL SHIPYARD (Erected at Keppel Shipyard) Module
1&2 E&I work monitoring and compiled with ABS (American Bureau of Shipping). Specification executed with sub-
con of BOND INSTRUMENTATIONS (like installation, testing and commissioning) including documentations
maintaining also.
4. Implementation of HSE safety precautions in Hazardous & construction Areas during commissioning &
Testing of Equipments.
5. I have got APPRECIATION REFERENCE LETTERS from my Project commissioning Manager for the jobs
performed with SBM client.

(4.6) WORKED AS PROJECT ENGINEER IN JAYA MARINE GENERAL CONTRACTORS PTE. LTD.
SINGAPORE, From August98 To May99.

In KEPPEL, KEPPEL FELS, KEPPEL SING MARINE, SHEMBAWANG & JURONG SHIP YARDS Power
wiring & Lighting wiring with cable and conduits for VESSELS & DECKS including fixing of panel boards &
Distribution boards.
QA / QC inspection with client and related documents preparations as per IS specifications.
HSE Electrical safety procedure Implementations during construction, Inspection, Testing & commissioning of
installed Equipments.

WORKED AS ELECTRICAL ENGINEER IN M/S AZEN MNUFACTURING PTE. LTD.,


SINGAPORE From June97 To July98. (Under Employment Pass).

1. Preparation of design as per customer requirements.


2. Preparation of materials procurements for all types of fans
3. Executing the works to the subordinates.
(4) Assembling of all types of industrial fans with co-ordination to customer.
(5) Quality assurance & Quality control.
Verification of approved drawings as per customer requirements.
In process of all items as per the drawings and customer requirements
* Assembling is carried out as per the drawings
* Testing: (a) impeller balancing test (b) Electrical Load Test (c) Efficiency test
1. Axial fans trouble shooting & servicing at KEPPEL FELS, GLIDE DOOR and SINGAPORE
AIRLINES ENGINEERING Companies.
(7). Utilities and machines maintenance & servicing related to electrical works.

(4.8) WORKED AS ASSISTANT ENGINEER IN PANDIAN ROADWAYS CORPORATION LTD, MADURAI,


INDIA (14 YEARS).

From 16-06-83 to 31-05-97 worked as Assistant Engineer (electrical). In-charge of all the electrical works related to the
corporation, for H.T. power supply, installation, execution, operation and maintenance of 11KV/415V,2 pole structures
with 500KVA Transformer. 1000A.panel board with Interlocking arrangements and 110KVA, 62.5KVA alternators
operation and maintenance with trouble shooting. Operation and maintenance of Sub-switch board, Distribution boards
with MCBs and UG cable wiring repairs and maintenance works executed in 2 different HT services at different places.
Operation and maintenance of machines related to vehicle maintenance, vehicle production and tyre re-trading works.
Construction, Design, Estimation and Costing of Electrical installations, Power and Lighting wiring using with UG/PVC
cable wiring to administrative office buildings, vehicle maintenance yard, vehicle parking yard and service connection
works related to electricity board with necessary liaison works, for all 20 branches of the corporation.
All types of electrical works tender call-for with technical scrutinizing and preparation of note approval to all electrical
works related to our corporation including of 20 branches. Maintenance scheduling of electrical machines likes well
pumps of centrifugal type jet flow type, air compressors, battery charges welding transformers and wiring repairs and
maintenance of all overhead lines and UG cables wiring.

(4.9) SERVED AS ELECTRICAL ENGINEER IN RASI ENGINEERING WORKS,


MADRAS (2 YEARS & 6 MONTHS)

From 15-01-81 to 10-06-83 worked as Electrical Engineer in Rasi Engineering works, design, estimation and installation
of electrical panel boards, designing of industrial and official building wiring execution, preparation of estimation &
costing and supervision.

(4.10) ONE YEAR APPRENTICE TRAINING IN TNEB. (Tamil nadu Electricity board)
From 26-12-79 to 25-12-80 training has undergone in TNEB distribution of Electrical power, from power transformer,
overhead transmission line. Estimation and costing of residential, industrial service connection materials. Substation
equipments layout design, installation and maintenance like power transformer oil circuit breakers, circuit breakers and
bus bars incoming and out going feeders maintenance. Hydro generation Generator, turbine & panel board routine
maintenance schedule preparation and execution. Thermal generation boilers, steam turbine and alternator routine
maintenance checkup and follow up.