Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Bill of Materials and Cost Estimates Description QTY Unit Unit Cost Total Cost Site Works PHP 17,854.77

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

BILL OF MATERIALS AND COST ESTIMATES

DESCRIPTION QTY UNIT UNIT COST TOTAL COST


Php
SITE WORKS 17,854.77
47.652 cu.
Excavation 0 m. 200.00 9530.41
41.621 cu.
Backfill 8 m. 200.00 8324.36

Php
FORM WORKS 52,750.53
Marine Plywood (1/4" x 4' x
8') 55 pcs. 415.00 22,825.00
2" x 2" x 10' Lumber (490 1631.8 bd.
pcs.) 5 ft. 33.00 26,925.53
Assorted CWN (4" - 3" - 2"
kgs.
- 1") 50 60.00 3,000.00

Php
SCAFFOLDING 58,646.76
2" x 2" x 10' Good Lumber (Melina)
bd.
Column (808 pcs.) 2692.8 ft. 33.00 44,431.20
679.73 bd.
Beam (204 pcs.) 1 ft. 33.00 11,215.56
Assorted CWN (4" - 3" - 2"
kgs.
- 1") 50 60.00 3,000.00

Php
MASONRY 191,146.01
Wall
5" CHB 2450 pcs. 9.00 22,050.00
4" CHB 1025 pcs. 8.00 8,200.00
Portland Cement 271 bags 240.00 65,040.00
16.096 cu.
Sand (S-1) 96 m. 240.00 3,863.27
Septic Tank
4" CHB 147 pcs. 8.00 1,176.00
Portland Cement 16 bags 240.00 3,840.00
cu.
Sand (S-1) 1.2384 m. 240.00 297.22
cu.
Gravel (G-1) 0.5018 m. 360.00 180.65
Concrete
Portland Cement 292 bags 240.00 70,080.00
cu.
Sand (S-1) 16.17 m. 240.00 3,880.80
cu.
Gravel (G-1) 32.34 m. 360.00 11,642.40
Catch Basin
Portland Cement 3 bags 240.00 720.00
cu.
Sand (S-1) 0.183 m. 240.00 43.92
cu.
Gravel (G-1) 0.366 m. 360.00 131.76

Php
Tile Works & Finishes 25,294.31
Wall Finish
Portland Cement 5 bags 240.00 1,200.00
cu.
Sand (S-1) 0.3574 m. 110.00 39.31
60 x 60 Ceramic Tiles 203 pcs. 50.00 10,150.00
Bathroom Finish
Glazed Tile (.30m x .
pcs.
30m) 247 30.00 7,410.00
Unglazed Tile (.30m x .
pcs. 30.00
30m) 67 2010.00
Cement Mortar 9 bags 230.00 2,070.00
Tile Grout 5 bags 65.00 325.00
Tile Adhesive 11 bags 190.00 2,090.00

PAINT Php
LUMPSUM 65,000.00
Flat Latex (Boysen) 8 pails 1920.00 15,360.00
Flat Wall Enamel (Boysen) 2 pails 2120.00 4,240.00
Roller Tray (Hippo) 5 pcs. 35.00 175.00
Roller Brush (Omega) 40 ft 50.00 2,000.00
#80 Sand Paper (3M) 60 ft 50.00 3,000.00
Paint Thinner (Puree) 5 gal. 285.00 1,425.00
1" Masking Tape (Armak) 10 pcs. 35.00 350.00
Bathroom
Neutralizer 4 liters 425.00 1,700.00
Primer 8 liters 750.00 6,000.00
Top Coat 7 liters 790.00 5,530.00

Php
REINFORCING BARS 72,283.71
Slab
10mm RSB @ 6m 67 pcs. 118.00 7,906.00
Tie Wires 8.98 kgs. 60.00 538.80
Column Footing
16mm RSB @ 6m 32 pcs. 301.00 9,632.00
Tie Wires 3.057 kgs. 60.00 183.42
Column
16mm RSB @ 6m 53 pcs. 301.00 15,953.00
10mm RSB @ 6m 52 pcs. 118.00 6,136.00
Tie Wires 10.87 kgs. 60.00 652.20
Wall Footing
10mm RSB @ 6m 12 pcs. 118.00 1,416.00
Tie Wires 2.768 kgs. 60.00 166.08
Beams
16mm RSB @ 6m 25 pcs. 301.00 7,525.00
@ 7.5m 14 pcs. 375.00 5,250.00
@ 9m 6 pcs. 446.00 2,676.00
10mm RSB @ 6m 63 pcs. 118.00 7,434.00
Tie Wires 34 kgs. 60.00 2,040.00
Septic Tank
12mm RSB @ 6m 6 pcs. 169.00 1,014.00
10mm RSB @ 6m 20 pcs. 118.00 2,360.00
Tie Wires 1.5843 kgs. 60.00 95.06
Catch Basin
10mm RSB @ 6m 11 pcs. 118.00 1,298.00
Tie Wires 0.1358 kgs. 60.00 8.15

Php
ROOF FRAMING
46,100.00
1.2mm x 2" x 3" C-Purlins 35 pcs. 430.00 15,050.00
1/2" x 2" Angle Bar @ 6m 16 pcs. 660.00 10,560.00
@
1 pc. 800.00 800.00
7.5m
1/4" x 2" Angle Bar @ 6m 11 pcs. 500.00 5,500.00
@
1 pc. 620.00 620.00
7.5m
1/2" x 1-1/2" Angle Bar @
14 pcs. 490.00 6,860.00
6m
3/16" x 2" x 6m Flat bar 10 pcs. 290.00 2,900.00
12mm Sag Rod 6 pcs. 260.00 1,560.00
16mm Std. Turnbuckles 12 pcs. 80.00 960.00
Welding Rod 6 kgs. 65.00 390.00
Cut-off Disc 5 pcs. 180.00 900.00

Php
ROOFING SHEET
29,585.00
Panel
Rib Span 1220 44 pcs. 250.00 11,000.00
Bended Accesories
SP Gutter 10 pcs. 450.00 4,500.00
SP Ridge & Hiproll 8 pcs. 285.00 2,280.00
Plain GI Sheet 6 pcs. 400.00 2,400.00
Plain GI Fascia Flashings 9 pcs. 285.00 2,565.00
Hardware Accesories
Tekscrew 2500 pcs. 2.00 5,000.00
Blind Rivets 1500 pcs. 0.50 750.00
Touch Up Paint 1 can 250.00 250.00
Silicon Sealant 7 tubes 120.00 840.00

Php
DOORS
48,500.00
0.6m x 2.1m Panel Door 4 sets 4500.00 18,000.00
0.8m x 2.1m Panel Door 3 sets 6500.00 19,500.00
0.7m x 2.1m PVC Panel
2 sets 3500.00 7,000.00
Door
1m x 2.1m PVC Panel Door 1 set 4000.00 4,000.00

Php
WINDOWS
60,684.00
2.4m x 1.2m sliding
3 sets 8203.00 24,609.00
window
1.8m x 1.2m sliding
3 sets 6403.00 19,209.00
window
2.4m x 1.2m sliding with
1 set 9366.00 9,366.00
casement
.90m x .60m sliding
3 sets 2500.00 7,500.00
window

Php
PLUMBING WORKS
44,173.25
Sewer line (4" PVC pipe)
Sanitary Line @ 6m 3 pcs 605.00 1,815.00
Drainage @ 6m 4 pcs 605.00 2,420.00
CO 3 pcs 108.00 324.00
45 bend 2 pcs 100.00 200.00
90 bend 3 pcs 128.00 384.00
P-trap 2 pcs 318.00 636.00
Wye 2 pcs 205.00 410.00
Coupling 10 pcs 80.00 800.00
Water line (1/2" GI pipe)
Water Line @ 6m 4 pcs 345.00 1,380.00
Tee 2 pcs 16.00 32.00
90 bend 5 pcs 16.00 80.00
Coupling 10 pcs 12.00 120.00
HCG (wc, lav, faucet, soap
1 sets 25000.00 25,000.00
holder)
Shower head 2 pcs 385.00 770.00
Kitchen sink 1 pc 5500.00 5,500.00
Shower Valve 2 pcs 625.00 1,250.00
Bathroom Faucet 2 pcs 175.00 350.00
Outside Faucet 1 pc 175.00 175.00
Floor Drain 4 pcs 35.00 140.00
Hose Bibb 1 pc 344.75 344.75
Gate Valve 2 pcs 384.75 769.50
Angle Valve 4 pcs 248.75 995.00
Hose Bibb 1 pc 278.00 278.00

ELECTRICAL WORKS Php


LUMPSUM 50,000.00
3.5 mm wire 195 m 14.00 2730.00
5.5 mm wire 65 m 21.00 1365.00
20mm PVC conduit 39 pcs 75.00 2925.00
Panel Board 1 pc 700.00 700.00
Circuit Breaker 15A 6 pcs 200.00 1200.00
Circuit Breaker 20A 4 pcs 200.00 800.00
Circuit Breaker 30A 5 pcs 200.00 1000.00
Circuit Breaker 40A 1 pc 225.00 225.00
Circuit Breaker 100A 1 pc 440.00 440.00
Single Pole Switch 9 pcs 70.00 630.00
Two Gang Switch 1 pc 105.00 105.00
Three Gang Switch 7 pcs 140.00 980.00
Weatherproof Duplex
2 pcs 250.00 500.00
Outlet
Special Outlet 5 pcs 184.75 923.75
Electrical Tape 5 pcs 35.00 175.00
1 KWH meter 1 pc 1600.00 1600.00
Duplex Convenience Outlet 14 pcs 105.00 1470.00
Circular Lamp @ 100 VA 9 pcs 780.00 7020.00
Pin Light @ 50 VA 29 pcs 150.00 4350.00

TOTAL MATERIAL Php


COST 762,018.34

INDIRECT COST
JOBSITE DURATIO
COST UNIT AMOUNT
OVERHEAD N
20000.00
Warehouse 20,000.00 1 project
Power
12000.00
Consumption 3,000.00 4 months
20000.00
Fuel 5,000.00 4 months
Temporary Water
15000.00
Connection 15,000.00 1 project
10000.00
Representation 10,000.00 1 project
10000.00
Small Tools 10,000.00 1 project
SUPERVISION

Project Engineer 20,000.00 4 months 80000.00

Foreman 15,000.00 4 months 60000.00


Warehouse/
Checker 12,000.00 4 months 48000.00

TOTAL INDIRECT Php


COST 275,000.00

LABOR UNIT COST


TOTAL LABOR
Description Unit Worker Labor Cost COST
4 Carpenter 250.00 Php
LAYOUT
1 Foreman 350.00 868.14

Php
EXCAVATION 7 Laborer 250.00 5,956.51

7 Laborer 250.00 Php


BACKFILL
1 Foreman 350.00 6,243.27

CONCRETING
1 Mason 350.00
Php
FOOTING 6 Laborer 250.00
5,235.40
1 Foreman 350.00

1 Mason 350.00
Php
SLAB 6 Laborer 250.00
4,987.31
1 Foreman 350.00

1 Mason 350.00
Php
COLUMN 6 Laborer 250.00
3,574.98
1 Foreman 350.00

1 Mason 350.00
Php
BEAM 6 Laborer 250.00
3,187.13
1 Foreman 350.00

1 Foreman 350.00
FORMWORKS & Php
2 Carpenter 250.00
SCAFFOLDING 20,540.52
5 Laborer 250.00

3 Welder 350.00
CONCRETE Php
6 Laborer 250.00
REBARS 8,082.26
1 Foreman 350.00

CONCRETE 2 Mason 350.00


Php
HOLLOW BLOCKS 6 Laborer 250.00
17,494.26
(CHB) 1 Foreman 350.00

ROOFING 1 Welder 350.00 Php


5 Laborer 250.00 6,486.06
1 Foreman 350.00

2 Mason 350.00
Php
PLASTERING 6 Laborer 250.00
29,161.88
1 Foreman 350.00

2 Mason 350.00 Php


TILEWORKS
6 Laborer 250.00 14,002.94

2 Mason 350.00
Php
FLOOR FINISHES 8 Laborer 250.00
6,045.60
1 Foreman 350.00

6 Carpenter 350.00
Php
CEILING 2 Laborer 250.00
6,045.60
1 Foreman 350.00

Php
PAINTING 10,000.00
Php
PLUMBING 10,000.00
Php
ELECTRICAL 10,000.00

Php
TOTAL LABOR COST
167,911.86

You might also like