Reduction Barriers
Reduction Barriers
Reduction Barriers
Prepared By:
Mercados Energy Markets India Private Ltd.
Under
India: Coal Fired Generation Rehabilitation Project
(November 2013)
Study Report
Prepared By:
Under
Submitted to:
Disclaimer
Table of Contents
Executive Summary
Chapter 1 - Introduction...................................................................................21
List of Tables
Table ES: Potential Risks involved in R&M Process along with Key Strategies
to Handle Risks and Surprises 15
Table 7: Deviation of operating heat rate with the design heat rate
for NTPC stations 50
Table 15: Time gap between studies and Execution of Work 140
Table 20: Power plant parameters Pre and Post R&M 194
Table 30: Reduction Norm for thermal power plant under PAT
Scheme 265
List of Figures
Figure 1: Energy and Peak Deficit in India 23
Figure 14: Technical Results achieved during the Trial Run 202
Figure 16: Profile of operating fleet of coal fired power plants in India 251
Figure 17: Vintage of the operating fleet of coal fired power plants in
India 252
Figure 21: Capacity wise break up for state sector coal based units
identified for R&M/LE during 12th Plan 256
Figure 23: Capacity wise break up for state sector coal based units
identified for R&M/LE during 13th Plan 257
Figure 25: Capacity wise break up for central sector coal based units
identified for R&M/LE during 12th Plan 258
Figure 27: Capacity wise break up for central sector coal based units
identified for R&M/LE during 13th Plan 259
List of Boxes
Box 1: Benefits of undertaking R&M of old thermal power plants 23
Box 15: Lack of Penalty Clause for Delay in Completion of Work 103
Box 16: Need for Quality Control and Quality Assurance 105
Box 20: Delay in capital overhaul post R&M of the unit 111
Box 21: Adequate skills to undertake O&M, post R&M of the plant 111
List of Abbreviations
Central Electricity
ABB Asea Brown Boveri CEA
Authority
Condensate Extraction
AHP Ash Handling Plant CEP
Pump
Central Electricity
AOH Actual Operating Hour CERC
Regulatory Commission
Certified Emission
AOP Auxiliary Oil Pump CERs
Reductions
Asia-Pacific Economic
APEC CHP Coal Handling Plant
Cooperation
Bureau of Energy
BEE CO Carbon Monoxide
Efficiency
Chhattisgarh Power
Bihar State Electricity
BSEB CSPGCL Generation Company
Board
Limited
Control and
C&I DCS Digital Control System
Instrumentation
Designated Operational
CA Condition Assessment DOE
Entity
Energy Efficient
EE R&M Renovation & GWh GigaWatt hour
Modernization
Energy Efficiency
EESL GCC Gross Coal Consumption
Services Limited
Engineering Procurement
EPC HFO Heavy Furnace Oil
and Construction
Energy Sector
Haryana Power Generation
ESMAP Management Assistance HPGCL
Company Limited
Program
EU Emission Trading
EU-ETS ID Induced Draft
Scheme
Interest During
FD Forced Draft IDC
Construction
National Energy
LE Life Extension NETL
Technology Laboratory
Lease, Rehabilitate,
LROT NPV Net Present Value
Operate and Transfer
Memorandum Of
MOU O&M Operation & Maintenance
Understanding
Maharashtra State
MSEB P. A. Fan Primary Air Fan
Electricity Board
Performance Evaluation
PET SUBC Sub Critical
Test
Power Finance
PFC SUPERC Super Critical
Corporation
Perusahaan Listrik
PLN TOP Turbine Oil Pump
Negara (Indonesia)
Quality Assurance
QAC TWh Terawatt hour
Consultants
Uninterrupted Power
RMU Removal Unit UPS
Supply
Executive Summary
With this background the objective of the study was to identify key risks and
surprises faced in planning and implementation of R&M of thermal power
projects, and develop guidelines to mitigate such risks and technical surprises.
To achieve the above objectives, a case study based approach was adopted
wherein select plants were identified across the country by the CEA for
undertaking a detailed assessment of the experience of these plants in executing
R&M works. Visits were undertaken to all these plants and discussions were held
with concerned officials dealing with R&M including plant/unit level engineers,
operation and maintenance department and commercial department to
understand their experience in planning, tendering, procurement, executing R&M
program and O&M of the units subsequent to R&M. Study of these units also
enabled the project team to understand the type of technical surprises faced by
the utilities, the root causes, impact on the project. The team investigated the
existing mechanism adopted by utilities to handle such surprises. The team also
undertook extensive stakeholder consultation to understand perspectives of
various stakeholders. The stakeholder group included the State Generating
Stations, Central and State Electricity Regulatory Commissions, Equipment
Suppliers, Design Consultants, Implementation Support Consultants, Sector
Experts, Funding Agencies and the CEA. The study team also evaluated
international experiences from Czech Republic, Poland, Turkey, Romania,
Indonesia and South Africa, and visited Poland and Czech Republic to obtain the
relevant experiences from personnel involved in R&M of projects in these
countries.
Basis the analysis and consultations a detailed set of guidelines for managing
technical surprises was evolved. The process of finalisation of the guidelines
involved intense consultation with the members of the Task Force, constituted
by the CEA for Promotion of Energy Efficiency R&M in Thermal Power Stations in
India under the Chairmanship of Member (Thermal), CEA.
The final outcomes of the study are a comprehensive report that includes two
detailed guidelines, namely the Guidelines for Risk Identification and Mitigation
in R&M Projects in Thermal Power Stations in India and Guidelines for Early
The key risks identified in the study, categorized according to different stages
of the R&M life cycle along with appropriate strategies to handle the same are
indicated in the table below.
Table ES: Potential Risks involved in R&M Process along with Key Strategies to
Handle Risks and Surprises
S. Category of Strategies to handle risks
Stages Risk
No Risk and surprises
Lack of long
Establishment of rationale for
term
R&M project at the state level
generation plan
2 Management Risk taking into account all the
and awareness
alternative competing options.
of available
(Risk Avoidance)
market options
Identification
Need for Experience Sharing
and Dissemination (Risk
Mitigation)
Lack of
Need to Develop Market for
confidence and
R&M in the Country by
3 Market Risk uncertainty
communicating the overall
with regard to
market size and addressing
R&M projects
concerns of various
stakeholders (Risk
Avoidance)
Comprehensive Identification
and Assessment of Options
Weak analytical
including computation of
framework for
6 Management Risk financial returns, payback
selection of
period, shutdown time required
R&M options
and conformance to the set
objectives.(Risk Avoidance)
Appropriate
Practice of obtaining in-principle
Commission not
approval from the Appropriate
7 Regulatory Risk apprised of the
Commission should be
R&M project
encouraged.(Risk Avoidance)
plan
Increased proliferation of
innovative financing approaches
/models like LROT and JVs
coupled with creation of
Utility unable to awareness about benefits of
10 Funding Risk
mobilise funds R&M through pilot studies to be
taken up. Standard bid
document to include terms and
conditions for the above
models. (Risk Mitigation)
Implementation
To avoid conflict of interest, a
contract
single entity should generally
awarded to
be avoided to assume both the
14 Management Risk vendor involved
role of design consultant as well
in carrying out
as the supplier. (Risk
technical
Avoidance)
studies
Preventive Measures
Robust studies; Strong
internal data reporting &
alerts; Good O&M practices
including during interim
stage; Dedicated R&M team;
Minimizing the time gap b/w
studies & execution and Site
Execution inspection by vendors
Occurrence of
Measure to Manage
16 Technical Risk technical
Surprises- Defining a
surprises
technical surprise plan
upfront; Creation of dispute
resolution mechanism with
clear decision making
authority; Provision of
Unit/rate contractors;
Supplier strategy to deal
with surprises and Creation
of Contingency fund
Availability of key
components should be
ensured before the start of
the project and should be in
Mismatch (or accordance with the pre-
delay) in supply defined plan finalized before
of critical the commencement of
18 Market Risk work.(Risk Mitigation)
equipment and
the shutdown Provision of Penalties for
period delay in completion of work.
(Risk Sharing/Transfer)
Sequential delivery of
materials to the R&M site
(Risk Mitigation)
Failure Of The
Plant To
Achieve
Environmental
Socio-environment impact
Standards And
Socio- assessment to be conducted
Plant Is
20 Environmental and recommendations to be
Perceived To
Risk implemented in a time bound
Have Negative
manner (Risk Mitigation)
Social/Environ
mental Impact
On Near-By
Villages
Preparation and
implementation of O&M
Sustainability of action plan by preparing
R&M gains O&M manuals including
22 Closure Operational Risk affected by preventive, capital and
weak O&M breakdown maintenance
practices procedure / guidelines for
units undergoing R&M. This
should be adopted through a
Rectification/replacement of
components to meet
guaranteed parameters at
Post R&M
no extra financial cost to
23 Technical Risk guarantees not
utility. (Risk Mitigation)
achieved
Levy of Liquidated Damages
for shortfall in performance.
(Risk Mitigation)
Involvement of Regulator
should be ensured from the
Non-approval of
inception of the project with
24 Regulatory Risk costs incurred
regular updates about the
during R&M
progress of the project. (Risk
Avoidance)
The above provide essential guidance for the generating companies, who
must evaluate and analyse the potential technical surprises and risks in
necessary detail for implementing R&M projects and formulate appropriate
strategies in line with those suggested in the guidelines to minimize such risks
and surprises.
In addition to the above, the study also provides an estimate of the overall
GHG reduction potential of EE R&M during the 12th and 13th Five Year Plan. In
order to estimate the CO2 emission reduction, potential various scenarios
(Conservative, Intermediate and Optimistic) has been built in. These scenarios
were developed considering the fact that different utilities may select different
options for R&M depending upon the cost involved, timeframe for shutdown and
their priorities.
On the basis of assessment it is seen that the current operating average net
SHR of coal based thermal power plants assessed for R&M/LE in the 12th Plan is
around 2962 kcal/kWh which translates into an efficiency of around 29.03%. If
all the plants post R&M operate on their design efficiencies, the average net SHR
can be improved to 2,551 kcal/kWh i.e. around 33.7%. This has an important
consequence for the coal requirements in the country. At a time when the
country is increasingly dependent on expensive coal imports that are affecting
the balance of payments and the competitiveness of the country, the R&M
Chapter - 1
Introduction
1.1. Concept of R&M and Life Extension Programme for Coal Fired
Thermal Power Stations
a) Generic defects
b) Design deficiencies /modifications
c) Avoidance of inefficient operation
d) Non-availability of spares because of obsolescence of
equipment/components.
e) Poor quality of coal
f) Major replacements of equipment arising due to unforeseen failures
and /or generation sustenance not covered under regular O&M
g) Stringent environmental regulation
h) Safety requirements etc.
The expenditure on such works which are O&M in nature is to be met from
O&M charges recovered through tariff for sale of electricity as notified by the
regulatory commission(s). O&M ought to be attended on a regular basis lest the
condition of the unit should deteriorate to such an extent resulting in major
breakdowns requiring huge expenditure.
800 -15
%
-11.10
-9.90 -10.10
700 -8.50 -8.50 -8.70 -10
600
777
831
747
788
998
739
666
691
862
937
857
911
-5
500
2007-08 2008-09 2009-10 2010-11 2011-12 2012-13
Peak Deficit
-28
140
-21
Billion Units
110 -16.60
%
-11.90 -12.70 -14
-9.80 -10.60
80 -9.00
109
110
119
122
130
135
104
110
116
123
-7
91
97
50
2007-08 2008-09 2009-10 2010-11 2011-12 2012-13
With the high cost of new installations, poor financial health of the utilities
and emerging fuel constraints it has become essential to maximize generation
from the existing power stations by restoring their rated capacity and also
improve the efficiency of the power stations through R&M/LE. It is one of the
most cost effective options to achieve additional generation from existing old
units within a short gestation period. The benefits of undertaking R&M of old
plants are presented in the box below.
a) New plants are relatively expensive than the cost associated with
R&M of plants, wherein the old plants can be renovated and
modernized at lower costs along with the extension of their life.
R&M is thus a low hanging fruit that can be harnessed to bring in additional
capacity in the country. Also, considering the extent of shortages and severity of
challenges faced by the country, all modes of supply augmentation need to be
pursued simultaneously including R&M of old thermal power plants.
As per the National Perspective Plan of CEA, under 12th Plan, LE works have
been identified on 70 thermal units of total capacity 12,066 MW and R&M works
have been identified on 65 units (17,301 MW) during the 12th Plan.
Considering that the old generation capacities are likely to remain in use
(wherever possible) even after replacement capacities have been commissioned,
R&M needs to be accorded adequate focus and priority. Over the last decade,
the electricity supply industry has witnessed several changes that have
significant implications for R&M in the country. These changes need to be
understood in the context of the current legal, policy and regulatory framework,
which has been elaborated in the following sub-section.
benefit from debt financing from the Power Finance Corporation (PFC)
at an interest rate subsidy of 3-4 per cent. Consequently, the guidelines
were revised in 2009 by the MoP for R&M/LE works for power
generating stations.
1
New Regulations are under development which are likely to further incentivize R&M
(ii) The parts of a boiler when it completes a life of twenty five years
are to be tested as per table 2 for assessment of the remnant life
of such parts. If results are acceptable as per the standards laid
down by the Central Boilers Board, a certificate shall be issued
by the Chief Inspector of Boilers for extending the life of the
boiler for a further period of ten years or such less period as
recommended by the Remnant Life Assessment Organisation.
This assessment of remnant life shall be carried out thereafter
every five years by the organisations working in the field of
boilers and remnant life and extension thereof after such
organisation is approved by the Central Boilers Board. Such
organisation shall work in close coordination with the office of the
Chief Inspector of Boilers in the field of remnant life assessment
and extension. The working pressure of such boilers may be
reduced on the recommendations of such approved organisation.
The plan identifies eight core national missions running through 2017
which represents multi-pronged, long term and integrated strategies for
achieving key goals in the context of climate change.
8th 198
(LEP) (4)
9th 152
(LEP) (25)
10th 25
(LEP) (11)
11th 129
(LEP) (53)
Source: Quarterly Review Report- Renovation, Modernisation and Life Extension of Thermal Power
Stations (January March; 2012), CEA
The momentum for undertaking R&M works continued till the 9th Plan but
considerable slippages were observed thereon in the subsequent plan periods.
Equipment capacity constraints, contractual delays, reluctance to shutdown units
in light of chronic power shortages in the respective states, financial constraints
etc. were some of the reasons for such slippages. Although the performance of
the programme improved during the 11th Plan, achievement had only been 56%
and 61.4% of the planned number of units and capacity respectively. Planned
capacity viz-a-viz the achievement of R&M and LE works during 10th and 11th
Plan is presented below.
10,000 15,000
MW
MW
10,000
5,000
18,965
14,855
10,413
14,270
7,318
1,291
2,460
5,000
985
- -
LE R&M LE R&M
Planned Achieved
Source: National Electricity Plan and Quarterly Review Report- Renovation, Modernisation and Life
Extension of Thermal Power Stations, (January March; 2012), CEA
Table 2: Emerging Power Sector Market Scenario and Implications for R&M
Before
Characteristics
enactment Current
/ Market Implications for R&M
of the Scenario
Changes
EA2003
a) As a result of emergence of
power markets, alternate
procurement avenues are now
available to the state utilities
to prevent outages when
Presence of plants undergo R&M
Power Markets Absent Present b) Increased focus on efficiency
and Competition improvement owing to
competitive procurement of
power and possibility of
extension of the framework to
state generating companies in
the near future
Before
Characteristics
enactment Current
/ Market Implications for R&M
of the Scenario
Changes
EA2003
Before
Characteristics
enactment Current
/ Market Implications for R&M
of the Scenario
Changes
EA2003
All of the above trends indicate positive changes for R&M market in the
country. However, the above changes have to be accompanied by introduction
of measures that are aimed at addressing the inherent policy, technical,
commercial, and regulatory barriers faced by the stakeholders involved in the
R&M process. These barriers once removed can alter the risk profile of the R&M
projects making them an attractive proposition for all stakeholders in the sector.
interventions at CEA.
b) Study on reduction of barriers to R&M interventions in thermal power
stations in India.
c) Study on developing markets for implementation of R&M in thermal
power stations in India.
d) Review of experience from Pilot R&M interventions in thermal power
stations in India.
Accordingly, CEA has engaged M/S Mercados Energy Markets India Pvt. Ltd.
(AF-Mercados EMI) on April 02, 2012, for undertaking study on Reduction of
barriers to R&M interventions in thermal power stations in India.
risks.
c) On the basis of this study and interaction with Suppliers and Design
Consultants, the Consultant shall develop Guidelines for Early
Identification of Potential Surprises in R&M Projects and Ways of
Addressing Them.
Chapter - 2
Approach and Methodology
This chapter presents the Approach and Methodology (A&M) adopted by the
team for undertaking different tasks of the study.
Review of R&M in
Global Context
India
Review Past
Experience
3. Review of R&M in Global Context Task 1
and Task 2
4. Stakeholder and Expert Consultation
2
It may be noted that for Task 1 (Guidelines for Risk Identification and Mitigation in R&M Projects
in Thermal Power Stations in India) and Task 2 (Guidelines for Early Identification of Potential
Technical Surprises in R&M Projects and Ways of Addressing Them) similar A&M was adopted.
Figure 4: List of units to be considered for review of R&M/LE works as per the
Terms of Reference
Note: PSPCL- Punjab State Power Corporation Limited, HPGCL- Haryana Power Generation Corporation
Limited, GSECL- Gujarat State Electricity Corporation Limited, MSPGCL- Maharashtra State Power
Generation Company Limited, UPRVUNL- Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited, BSEB-
Bihar State Electricity Board, WBPDCL- West Bengal Power Development Corporation Limited,
CSPGCL- Chhattisgarh State Power Generation Company Limited, MPPGCL- Madhya Pradesh Power
Generating Company Limited
Visits were undertaken to all these plants and discussions were held with
concerned officials dealing with R&M including plant/unit level engineers,
operation and maintenance department and commercial department to
understand their experience in planning, tendering, procurement, executing R&M
program and O&M of the units subsequent to R&M.
The units visited provided adequate depth to the analysis carried out
in the study as these units differed in terms of coverage, current
performance, implementation model, mode of funding etc. These factors
are explained below:
This enabled the project team to understand the type of risks and technical
surprises faced by the utilities, its root causes, its impact on the project, bearer
of the risk and way of managing the risks and technical surprises. The table
below highlights in brief the unique attributes of the identified plants.
3
Mode of funding has influence on the level of preparedness and system introduced for robust
R&M implementation. While a few funding entities have enforced mandatory lending covenant to
be adopted by the utility during the course of design and implementation of R&M in their plants,
other entities have not followed such stringent lending criteria.
Further, study of these units also enabled the project team to understand the
type of technical surprises faced by the utilities, its root causes, its impact on
the project and the way of handling such surprises by the respective utilities.
In addition to the visit to these plants, the project team also participated in
the CEAs R&M Planning and Progress Review Meeting with the State and Central
Generation Utilities wherein the utilities highlighted the progress of their ongoing
R&M schemes and the key issues and concerns being faced in implementing
R&M projects.
The above review enabled the team to capture diverse experience being
offered by various countries which collectively can be synthesized to offer useful
lessons for risk identification and mitigation for R&M of thermal power plants in
India. The lessons learned from these experiences are suitably incorporated in
the Guidelines for Risk Identification and Mitigation in R&M Projects in Thermal
Power Stations in India and also in the Guidelines for Early Identification of
Potential Technical Surprises in R&M Projects and Ways of Addressing Them.
Table below provides a list of entities consulted during the visits made to
various states across the country.
Limited
bb) Central Power Research Institute
cc) Black & Veatch Consulting Private Limited
dd) L&T-Sargent & Lundy Limited
ee) EM Services India Private Limited
ff) Stock Redler India Private Limited
gg) Tecpro Systems Limited
hh) Techfab System Private Limited
ii) Assam Power Generation Corporation Limited
jj) Andhra Pradesh Power Generation Corporation
The Table below provide the list of task force members consulted in various
stages of the report.
Table 5: List of Task Force Members
S. No Organisation Name
Consultation
during R&M in India Lessons for
b) Selection of Countries India
(keeping in mind relevance
for India) for Detailed
Review of R&M Process
c) Site Visits to select
international plants Site Visits to select
d) Expert & Stakeholder international plants
Consultation
a) Context of R&M in the country including key drivers and priorities for
R&M.
b) Process adopted for design and implementation of R&M in the
country, including the roles and responsibilities of the entities
involved.
c) Measures considered for R&M including design of packages, award
and execution process.
d) Outcomes of the R&M process, and concerns and barriers faced in
R&M.
e) Identification of good practices and lessons for India.
The countries selected for the review included Czech Republic, Poland,
Turkey, Romania, Indonesia and South Africa. These case studies were prepared
on the basis of literature review and visits in some of the countries. The list of
references used for preparation of case studies/review is provided at the end of
the report.
Countries and power plants selected for R&M process review are presented in
Figure below.
Figure 6: Selected countries and power plants for Review of R&M experience
3
S. No Country Name of the Plant 2
4
Suralaya Power Station (Unit 1 & 2),
1 Indonesia 5
2x400 MW
Tusimice II (4x200 MW)
2 Czech Republic
Prunerov II (5x200 MW)
3 Poland Belchatow (12x370/380 MW) 1
4 Romania Turceni (7x330 MW)
Afsin Elbistan A (3x340 MW & 1x335
5 Turkey 6
MW)
6 South Africa Arnot (6x350 MW)
The following criteria were adopted for selection of the above countries:
a) Geographical Coverage
In order to ensure adequate geographical coverage of the worldwide
R&M experience, countries from different continents (European, Asian
and African continents) were reviewed. Further, experiences of both
developed and developing countries were reviewed.
b) Electricity scenario
Electricity scenario of respective countries was considered while
selecting countries for review. This included review of countries which
are surplus in electricity, as well as those that face electricity
shortages. Further, consideration was also given to countries using coal
as a primary/dominant source for production of electricity.
d) Implementation Model
Includes models such as (i) OEM initiated; or (ii) Competitive Bidding
(National/International)
e) Mode of Funding
Includes (i) Own sources of funds; (ii) Grants; (iii) Soft Loans by
Multi-lateral donor agencies
f) Specific Issues
Includes specific experience witnessed by a particular plant different
from the normal/routine.
Table below highlights in brief the unique attributes of the identified plants
reviewed as part of this report.
6. Afsin Elbistan i. Project was funded by the World Bank and by the
A Thermal owner of the plant i.e. Electricity Generation A..
Power Plant (EUAS), the state owned utility company.
(3*340+ ii. Due to perceived high risk by suppliers, strategy for
1*335 MW), bidding revised due to non-participation of vendors.
Turkey
iii. R&M works could not be implemented due to
concerns of the bidders with regard to perceived
risks of not being able to achieve the functional
guarantees. Also, unrelated investigations by the
Government into the procurement actions by EUAS
led to the cancellation of the project.
In Czech Republic visits were undertaken to Tusimice II Power Plant (4* 200
MW) and Prunerov II Power Plant (5*210 MW). During the site visits discussions
were held with concerned officials dealing with R&M at the utility level, at the
plant level and also with the EPC contractor i.e. Skoda Praha Invest to
understand their experience in planning, tendering, procurement and executing
R&M program of different units. Interaction with other sector experts was also
undertaken.
overall GHG reduction potential of EE R&M. AF-Mercados EMI in its report titled
Developing Markets for Implementation of R&M Schemes in Thermal Power
Stations in India has assessed the overall market potential for R&M during the
12th and 13th Five Year Plan4. To estimate the GHG potential, these identified
coal based units for both state and central sector have been considered
(Annexure 3). In addition to the above identified potential, there are certain
plants on which R&M/LE works are on-going i.e. the plants that have slipped
from 11th to 12th Plan and these plants have also been considered while
estimating the GHG potential. Based on the unit level performance data for the
identified units under the 12th and 13th Plan, GHG emissions for each of the units
has been estimated in pre and post R&M/LE scenario which is then aggregated
to estimate the overall GHG emission reduction potential of R&M in the country.
Analysis made in this section is based on the performance data for past three
years i.e. 2008-09, 2009-10 and 2010-11 and certain assumptions.
Absolute CO2 emissions (MT CO2) at the unit level = Specific CO2 emissions for
a unit (t CO2/MWh) * Net
Generation (MU) of the
unit
Mt Million Tonne; tCO2 tonne of CO2; ml millilitre; gCO2 gram of CO2; kcal kilocalorie
Wherein,
i. Fuel Emission Factor for different fuels are being provided in the CEA
publication titled CO2 Baseline Database for Indian Power Sector,
Version 8.0, January 2013. Fuel Emission Factor for coal and lignite
is considered as 90.6 g CO2/MJ and 100.5 g CO2/MJ respectively.
Specific emission for oil is being considered as 2.89 g CO2/ml.
ii. Net Station Heat Rate for each of the state sector unit is calculated
based on the average of gross station heat rate and the auxiliary
4
The report is available on the CEA website.
consumption for past three years. In case of NTPC units, year wise
data on Gross SHR is not available. However, CEA in its publication
titled Recommendations on Operation Norms for Thermal Power
Stations for Tariff Period beginning 1.4.2009 has worked out the
deviation of operating heat rate with the design heat rate for various
NTPC plants for different years. This is presented below:
Table 7: Deviation of operating heat rate with the design heat rate for NTPC
stations
Weighted Avg.
Design Heat 2002- 2003- 2004- 2005- 2006-
Average
Rate 03 04 05 06 07
(kcal/kWh)
iii. Net Generation for each of the unit is calculated based on the rated
capacity of the unit, average of PLF and auxiliary consumption for
past three years.
iv. Specific oil consumption for coal based and lignite based units is
considered as 2 ml/kWh and 3 ml/kWh respectively.
From the unit level CO2 emissions estimated above, total Baseline CO2
emissions are estimated for the R&M/LE for the 12th and 13th Plan. This is
estimated as follows:
Overall CO2 emissions (Mt CO2) for the R&M/LE in the 12th and 13th Plan =
Absolute CO2 emissions (Mt CO2) at the unit level.
R&M
Koradi a b
6 210 3264 2350 2395 under
TPS
process
R&M
Bandel
5 210 2874 2456b 2424 under
TPS
process
Panipat
2 110 3950 N.A. N.A. 3511
TPS
Bathinda
2 110 3030 N.A. 2482 3005
TPS
a
Notes: Figure is for 2009-2010; b Figure is based on the option selected in DPR; c
Achieved as per PG Test; N.A.: Not available
Source: Detailed Project Report for Koradi TPS (Unit 6) and Bandel TPS (Unit 5); Data
collected during site visit to Korba TPS, Panipat TPS and Bathinda TPS; CAG
Audit Report No.4 (Commercial) for the year ended 31 March 2010 for GSECL;
CEA study titled Mapping of 85 pulverized coal fired thermal power generating
units in different states, by Evonik Energy Services India, under Indo-German
Energy Program
5
Refer Standard Menu of Options for Energy Efficiency focused Rehabilitation and Life Extension of
210 MW and above units in TPS in India under Chapter Lessons for India based on review of
international best practices in R&M
These scenarios are developed considering the fact that different utilities may
select different options for R&M depending upon the cost involved, timeframe for
shutdown and their priorities.
For instance, if the plant design net station heat rate is say 2600 kcal/kWh
and the operating net station heat rate is 3366 kcal/kWh, according to this
scenario, net station heat rate for the calculation purposes would be considered
as 2983 kcal/kWh.
design value.
200/ 210 MW
ii. In cases where average operating heat rate is less than that of
design as mentioned above, average operating heat rate is
considered. In cases where average operating auxiliary consumption
is less than that of design value, average operating auxiliary
consumption is considered.
iii. Specific oil consumption for coal based and lignite based units post
R&M/LE scenario is being considered same as 2 ml/kWh and 3
ml/kWh respectively.
Based on the above steps total GHG emission reduction potential for the
plants has been estimated under various scenarios.
There are various barriers that may constrain the utilities in monetizing the
GHG emission reduction including the evolving market situations. The different
barriers along with overall strategies to overcome each of the barriers have also
been detailed out in this section.
Chapter - 3
R&M Process Cycle
In order to identify the risks and surprises experienced during R&M projects
and to design strategies to mitigate risk and technical surprises, it is essential to
first understand various sub-steps of the entire R&M process, the activities that
are undertaken at each step and the stakeholders involved during various stages
of the R&M process cycle. Figure 7 maps out the overall R&M process and
stakeholders involved during each of the identified stage.
The diagnosis at this stage is based on available plant records and design
data. No inspections and/or testing of material, plant or equipment is involved at
this stage. Timely identification and diagnosis of problems is of critical
importance and form the foundation for successful R&M of the plant in the
future. This obviates the need for a comprehensive R&M in one go (except for
BTG) and ensures that necessary up-gradation is carried out during the course
of plant operation and annual/capital overhaul and maintenance.
a) Plant retirement
b) Maintain and operate for extended time and retire subsequently
c) Capital Overhaul and refurbishment
d) R&M and Life Extension (LE)
e) R&M, LE and Up-rating
Several options can be worked out for involvement of private players in the
R&M process. Some options often discussed include: (i) Lease, rehabilitate,
operate and transfer; (ii) Joint venture between the private player and
public/private utilities.
Based on the technical studies and the option selected for R&M, the scope of
R&M Project is prepared. The aim here is generally to define scope in as precise
terms as possible however often changes and surprises occur when the plant is
actually opened up for implementing the R&M. The utility often is faced with the
issue of level of detailing that is required at the planning stage itself vs. the time
and resources that are available to be committed for achieving marginal
improvement in the scope assessment exercise.
Before the tenderization process begins, utility should also submit the details
of the assessment to the Appropriate Commission and seek its approval (often
in-principle approval, with the formal approval obtained post the R&M is
executed and actual amount incurred on the same is submitted).
Planning stage covers the entire bid process management i.e. issue of
tender(s), pre bid meetings, evaluation of technical and commercial bids,
selection of suitable bidder, negotiation of contracts and award of R&M contracts
to vendors/suppliers/OEMs.
In India, in certain cases, the bidding stage is omitted. In such cases, the
R&M process is directly initiated through the OEM and awarded for
implementation.
Identification of plant units Selection of agencies / consultants for Preparation of bid documents Arrival of Equipments Post R&M Performance
technical studies/implementation support Technical and Commercial Guarantee Tests
Monitor and maintain /quality assurance Plan for Shutdown of Plants
record of key plant unit Issue of tenders and evaluation of Plant Performance Analysis
parameters Plant Assessment bids Start of execution of R&M
RLA Studies Work Follow-up Activities to meet
Complete Plant Assessment Selection of Bidders deficiencies
Energy Audit
Understanding prevailing O&M Negotiation of R&M Contracts Post R&M- Training and O&M
Practice of Plant
Operators Experience Award of R&M Contract
Past History of Plant
Procurement Plan Sequence of
Evaluation of Alternatives procurement and follow up with
vendors
Preparation of Scope of Work
29
Design Consultant/Implementation Support Consultant
Generating Company
Regulator Regulator
Indicative timeframe suggested by CEA in the National Perspective Plan for Renovation, Modernisation and Life Extension of Thermal Power Stations
(Upto 2016-17) for implementing LE&U schemes:
Chapter - 4
Risk Identification and Mitigation Framework
This chapter describes the key risk faced in implementing R&M mapped
across different stages of the R&M life cycle and the framework for
management of such risks.
Over the R&M life cycle, there could be various types of risk affecting the
effective implementation of R&M project. These include:
indirectly affected by the risk event. This helps in design of approaches that
enable development of a balanced projects with specific risks allocated to the
entities that are best placed to manage them.
6
Risk Avoidance can also be defined as Preventive Risk Management. The concept is similar to
Preventive Maintenance in a thermal power plant that involves care and servicing by the plant
personnel for the purpose of maintaining equipment and facilities in satisfactory operating
condition by providing for systematic inspection, detection, and correction of incipient failures
either before they occur or before they develop into major defects.
Chapter - 5
Risk Management Guidelines
This chapter describes the risks identified across different stages of R&M
and the strategies to deal with the identified risk (refer Table 10).
S. Category of
Stage Risk
No Risk
Inadequate technical
5 Technical Risk
assessment/studies
S. Category of
Stage Risk
No Risk
Risk
Closure
Non-approval of costs incurred during
24 Regulatory Risk
R&M
The following section details out each of the above risk as per the R&M
process cycle along with the risk bearer, impact and strategy to manage the
risk.
A. Risk Description
This risk arises due to delay in timely decision for R&M works. Ideally
decision to undertake comprehensive R&M should be based on the diagnosis of
the early warning symptoms. This includes diagnosis of the reasons for
deterioration in plant performance parameters such as Plant Availability,
Station Heat Rate (SHR), Auxiliary Consumption etc. and the ageing analysis of
the unit and critical equipments i.e. the number of remaining years left before
the plant completes its economic/designed life of operation.
Thus, the operational performance of the plant must be regularly monitored and
considered as a key parameter for undertaking decisions related to R&M of the plant.
The early warning symptoms should be identified and acted upon.
In several cases the decision to undertake R&M is taken when either the
plant is already shutdown or the performance of the unit has significantly
deteriorated or the plant has outlived its economic/useful life.
D. Bearer of Risk
Utility/Plant Owner is the direct bearer of this risk. However, this also
impacts the consumer in the state as it disrupts the quantum of power to be
supplied to the discom which then has to resort to purchase of costly power
from the short-term market.
Based on the above, this risk can be completely avoided or its impact can
be significantly minimized. Some of the critical actions involve:
For this, input from O&M department is critical and recording of routine
data such as material properties, geometries, crack sizing, hardness,
operational parameters etc. during operation, annual/ capital maintenance, will
be useful for undertaking technical studies/R&M in future.
5.1.2. Lack of Long Term Generation Plan and Awareness of Available Market
Options (Management Risk)
A. Risk Description
Key priorities of the state in the context of energy sector are: (i) to provide
adequate and affordable power to the consumers; (ii) be energy secure and
environmentally benign; and (iii) ensure financially sustainable utilities. The
states and the power utilities in the country must have long-term plan
(Optimal Generation Plan) for achieving the above mentioned goals. The
decisions related to R&M must be a consequence of this long-term plan.
The risk arises when decisions related to R&M are taken up in isolation
without considering other available options.
a) Lack of power sector vision at the state level and vision at the
utility level
b) Conventional focus on augmentation of new supply as a means to
meet the increasing power demand
c) Lack of awareness of possible market options
This trend has been observed in several states reviewed as part of this
study. Hence, the frequency of occurrence of this risk is high. The risk impacts
the plant and utility performance gradually, hence severity is moderate.
D. Bearer of Risk
Utility/plant owner is the direct bearer of the risk. However, non-
performance also impacts the consumers in terms of higher tariff (if pass
through under the regulatory mechanism).
The final decision of R&M should also be considered in consultation with the
Discoms, wherein the refurbished plant should fit with the Discoms long-term
power procurement plan and merit order schedule.
A. Risk Description
Due to limited experience sharing and success stories in India, a number of
generating companies are uncertain about the outcomes of the R&M. Hence,
appreciation of benefits associated with R&M is limited.
This leads to a risk wherein the utility may not consider R&M as an option,
even though it makes economic sense.
Under performance was due to high vibration of turbine and excessive boiler tube
leakages which led to delay in stabilisation of operation of Unit I of Ukai TPS
(which was subsequently addressed by BHEL). Although, the performance
Uncertain outcomes have created apprehensions about viability of R&M among the
utilities.
The severity of the above risk depends on case to case basis, however may
range from low to moderate. The frequency of the above risk is moderate to
high.
D. Bearer of Risk
This risk impacts the entire R&M market including potential generating
companies, equipment suppliers, design consultants etc.
Example: Korba (East) Thermal Power Station- Unit 1 to 4 (4x50 MW) and
Unit 5& 6(2x120 MW)
In case of the above plants, the achievement post R&M viz-a-viz the contracted
parameters has been encouraging. This is tabulated below:-
As Per Contract
Agreement
Pre- Post-
Achieved as Per PG Test Results
Rehab Rehab
Rated
1 40 MW 50 MW 50MW 50MW 50MW 50MW
Capacity(MW)
TG Heat Rate
2 2714 2319 2186.12 2257.4 2253 2188.1
kcal/kWh
Boiler
3 83% 87.50% 89.03% 88.39% 88.97% 90.30%
Efficiency
Station Heat
4 3270 2650 2455.54 2553.85 2532.31 2423.145
Rate kcal/kWh
3 86.3(+/- 85.75(+/-
Boiler Efficiency 89.40% 88.13%
1%) 1%)
Pilot demonstrations in Bandel TPS Unit-5 (210 MW) and Koradi Unit 6 (210
MW) have already been initiated through the support of the World Bank. It is
expected that the experience from these pilots would help in better design and
implementation of R&M programs in future.
CEA has already initiated the above study with support from the World
Bank. The result of these will be available during 2013-2014.
5.2.1. Delay in Obtaining Unit Shut down for Undertaking Technical Studies
(Institutional Risk)
A. Risk Description
Robust baseline assessment through technical studies is the foundation for
the success of R&M project. In order to carry out comprehensive assessment of
the remnant life and condition of the plant, various standardised tests are
required to be performed (destructive and non-destructive) involving a
shutdown of approx. 2 to 3 months.
This risk arises if the utility is unable to obtain requisite approvals from the
relevant authorities (State Government or Regulatory Commission) for
shutdown of the plant for carrying out such studies.
The likelihood of the occurrence of this risk is low to high depending upon
the number of units requiring simultaneous shutdown. It may not be difficult to
obtain requisite approval for one unit but in case more units are scheduled for
such shutdown, obtaining requisite approvals/permissions may be difficult.
D. Bearer of Risk
Generating company is the direct bearer of this risk.
iii. Further, efforts should be made to plan such studies during off-
peak demand months when the stress on the generating
systems is low. This however, should be considered in view of
the market conditions. As in certain cases it is noticed that when
i. As per clause 6.2 (ix) of the MoP Guidelines for R&Min National
Perspective Plan for Renovation and Modernisation and Life
Extension of Thermal Power Stations (upto 2016-17), the
utilities may approach the Government for additional allocation
of power to the extent possible from unallocated quota of
central sector power stations during the period of shut down of
units for comprehensive life extension works.
A. Risk Description
Technical assessment is the most important and a resource intensive
activity in terms of time and manpower. It involves performance testing,
destructive and non-destructive evaluation of equipment, to diagnose the key
concern areas in the power plant. This risk arises on account of the following:
b) Due to lack of past operating and performance data with the utility,
it may difficult to identify improvement areas for certain
components in the unit/machine as every component cannot be
tested.
Based on the limited assessment scope of work was prepared for both
the units.
D. Bearer of Risk
The above risk impacts all the parties involved in the R&M activity including
generating company, supplier(s) and the Implementation Support Consultant
(if applicable).
Balance of
Boiler Turbine/Generator
Plants/Auxiliaries
In this regard CEA has prepared standard documents for carrying out
RLA/CA/EA studies which may be used by the utilities.
A. Risk Description
Post the technical studies have been undertaken, the decision to
repair/improvement/replace/retrofit or combination of these measures (or
7
In certain cases, wherein the assessment of O&M practices has revealed serious gaps, funding
agencies have insisted on development of an O&M improvement action plan that is accepted by
the Board of Directors by the generating company, and proposed for implementation as soon as
the R&M is completed.
This risk arises if the utility is not able to identify and/or evaluate different
options and select the best possible option depending upon the conditions of
the plant, financial constraints, etc.
D. Bearer of Risk
The ultimate bearer of this risk would be consumers as the suboptimal
decision would lead have relatively high cost viz-a-viz benefit resulting in high
consumer tariffs.
A detailed cost benefit analysis by estimating the net present value (NPV),
rate of return (IRR), payback period and cost-benefit ratio, should be
undertaken by the utility for different options. Analysis should also include the
impact on key parameters such as life, PLF, heat rate, efficiency etc. Further,
the robustness of the selected option should be tested through scenarios such
as time and cost over-run, shortfall in capacity, change in shut-down, heat rate
or a combination of adverse factors. The justification of the R&M project needs
It must be noted that there is no benchmark cost for R&M. The actual cost
depends on a variety of factors including:
Hence, net financial returns should be the determining factor rather than
capital expenditure incurred on R&M. Independent specialized entities could be
considered for undertaking such assessments.
Example: Unit 6 of Koradi Thermal Power Station (KTPS) (210 MW), Maharashtra State Power Generation Corporation Limited
(MSPGCL)
Table below indicates the options considered for R&M by MSPGCL for KTPS Unit 6. Based on the assessment Option D was selected.
Description/
A B C D E F G
Option
One to one
Option B,
replacement Option B plus
along with life
for life replacement
extension,
extension of of complete
aims for Option B plus
the plant for turbine with complete Insitu
restoration LP retrofit for
up to 20 new reaction replacement replacement
for design Increase in Option D plus
years with type turbine of the main of the main
capacity and Plant Capacity Generator
the present for increase in plant with plant with
restoration of up to 215 MW modification
Scope operating Plant Capacity new plant of new plant of
the design and to achieve
capacity up to 215 250 MW 250 MW
Unit Heat rate Improvement 220 MW
without MW, and capacity at capacity at
with Boiler in Unit Heat capacity
modification Improvement adjacent same
modification Rate beyond
for existing in Unit Heat location location.
for existing design Heat
coal quality, Rate beyond
coal quality
with design Heat
and Turbine
improvement Rate
refurbishment
in heat rate
Unit
Capacity 196 210 215 215 220 250 250
(MW)
Unit Heat
Rate
(kCal/kWh) 2476 2400 2370 2350 2350 2350 2350
PG Test
value
Project
Capital cost 309 403 456 486 536 984 849
Rs. Cr.
Cost per MW
1.57 1.92 2.12 2.26 2.43 3.93 3.39
(Rs. Cr/MW)
Cost of
Generation 2.27 2.27 2.23 2.21 2.24 2.59 2.36
(Rs/kWh)
FIRR % at
minimum
11.74 11.65 12.86 13.2 12.39 7.82 8.28
cost of
Generation
Pay Back
4.5 4.6 4.6 4.6 4.6 6.6 6.7
period
Shut down
period 5 6 6 6 6 4 18
months
Thus, various options for R&M should be comprehensively identified and evaluated, and best option be selected.
A. Risk Description
R&M project involves capital investment and hence regulatory approval for
such investment is essential to enable the generating company to recover the
amount through tariffs. It is thus, essential that the appropriate regulatory
commission is apprised well in advance about the plan for undertaking the
R&M. In addition, the plan should be in accordance with the regulations
notified by the Commission from time to time.
The risk arises when the Appropriate Commission is not apprised about the
R&M project.
D. Bearer of Risk
Utility is the bearer of the risk.
In accordance with the above, the generating company must provide all
required information to the regulator for obtaining such approval.
A. Risk Description
The risk arises due to the limited skills and expertise of the generating
company to plan and implement R&M. In addition, absence of dedicated
cell/department at the company level also contributes to the risk.
D. Bearer of Risk
Besides the utility, vendors also bear this risk as they would not be able to
perform their work effectively.
A. Risk Description
This risk arises if the scope of work is broad and does not clearly define the
role and responsibility of different stakeholders including the works to be
performed by each party.
Such clauses although included in the contract, in reality are not acceptable
to the vendors. It is also difficult for the utilities to make vendors adhere to
such clauses. Further, scope is kept broad or are prepared in manner to favour
a particular supplier in cases where in there exists a potential conflict of
interest i.e. same organisation or consultant is involved in the entire process of
undertaking the technical studies, preparation of scope and its ultimate
execution.
Contractual delays also impact the bottom line of the vendor and
opportunity cost for the utility. The likelihood of the occurrence of this risk is
high and severity differs from moderate to high.
D. Bearer of Risk
Both utility and vendor are the bearers of this risk.
A. Risk Description
This risk arises when the utility is unable to arrange adequate funding for
undertaking R&M of the project or faces constraints in raising funds for the
project.
Unit 4 and Unit 5 of BTPS (2x50 MW) were first identified by the CEA
for R&M works in 1989 and 1991 respectively. However, due to lack
of sufficient funds R&M works could not be taken up at that stage.
In addition to the above, most of the utilities are unable to justify the
benefits envisaged from R&M to the potential financiers. This occurs on
account of three factors: (i) lack of robust analysis of various possible options;
(ii) lack of confidence of financiers on R&M due to limited success stories in the
country; and (iii) overwhelming focus of financiers on new capacity addition
(until recently).
D. Bearer of Risk
Utility is the direct bearer of this risk. This also impacts the suppliers as
they may not receive timely payments for their works.
In the long run, this risk has repercussions on the entire R&M market.
company:-
In this option, a new company would be formed as a joint venture
(JV) of the state power utility/ State Government and selected
private/public collaborator. The JV Company would then undertake
the R&M/ LE works and also own, operate and maintain the power
station. The private collaborator could also be an equipment
supplier. Each partner shall hold minimum 26% equity in the JV
Company. For e.g. BSEB undertook the R&M of its Muzzaffurpur
Plant (Unit 1 and 2 (2x110)) by forming a new company, KBUNL,
as a Joint Venture (JV) of the State Power Utility (BSEB)/ State
Government (Government of Bihar) and public power utility
(NTPC).
The Indian power market particularly the new thermal capacity addition is
facing unprecedented challenges on account of acute shortage in domestic
coal, slow production of coal from the captive coal blocks and huge
dependence on imported coal. All of the above coupled with inflexible
contractual structure for pass through of variation in the coal prices is resulting
in slow down of the new capacity addition. Thus, there is likely to be a very
strong focus on increasing the efficiency of the existing generation fleet of the
country. R&M market is likely to gain momentum in the near future, with
financiers also preferring to finance projects that demonstrate visible
improvement in the performance in short time.
A. Risk description
This risk arises when the utility adopts the bidding process for selection of
vendors and receives a poor response to its bid(s).
The likelihood of occurrence of this risk was high in the past but with more
utilities resorting to competitive bidding framework as opposed to only OEM
based model, situation is now gradually changing. With the increase in the
participation of international players in the Indian R&M market, the likelihood
of this risk is expected to be low. The severity of risk is moderate.
D. Bearer of Risk
Utility is the direct bearer of this risk. This also impacts the potential
vendors who are discouraged from entering into the R&M market.
In case of Koradi Unit 6 (210 MW), participation of the vendors have been
encouraging. The process has been supported by the World Bank with robust
assessment and analysis of options. A participatory process has been undertaken
for finalization of specifications. Also, two stage bidding process has been involved
to address concerns of all the potential vendors.
All of the above have enable to create a balanced risk profile of the project
resulting in higher vendor participation. In case of BTG around 8-10 companies
purchased the tender and around 4 companies finally submitted the bids. In case
of Electrical package around 5 companies purchased the tender and around 2
companies finally submitted the bids. Similarly, large number of BoP vendors
purchased and participated in the bid for BoP works.
Source: Interactions of AF Mercados EMI with the officials of the KTPS, Mahagenco
In case of BTG package only one out of the four bidders qualified after the first
stage bid opening. Based on the discussions with the bidders, further refinements
in technical design and performance requirements were made and a decision was
undertaken to re-bid on a single stage basis. The single stage bids attracted two
bids.
Source: Interactions of AF Mercados EMI with the officials of the Bandel TPS, WBPDCL
A. Risk Description
This risk arises if the price discovered through competitive process or
through nomination basis is significantly higher in comparison to that
envisaged during the Planning Stage.
D. Bearer of Risk
This risk is borne by the Utility and Vendor.
d) Utility may also decide for rebidding (although it has its own risks)
the project with suitable modifications i.e. changes in qualification
criteria to increase participation, change in the selected R&M
option etc. However, efforts should be made for suitable
negotiations with the lowest bidder before resorting to such option.
Accordingly, KTPS published a global tender for Unit-1&2 R&M and LE Works in
January 2005.BHEL and NASL submitted the bids. Price bids were opened in
September2005 wherein the total cost of the project was Rs 492 Crores (Rs.
2.05 Crores per MW) with a payback period of 18 years and Life extension of 15
years.
Accordingly, the plans to undertake R&M for Unit 1 & 2 of KTPS were
abandoned.
A. Risk Description
This risk arises if the utility consumes significant time in awarding the
contract or has to rebid any of its contract or packages. There are examples
wherein this risk has originated from the vendor side as well as from the
utilitys side.
Source: CAG Report Audit Report and interaction of AF Mercados EMI with officials of
MPPGCL
Source: HPGCL Petition for Approval of Tariff for the year FY 2012-13
Source: CAG Report Audit Report (Commercial) for the year ended 31 March 2009
D. Bearer of risk
This risk is borne by both the Utility and the Vendor.
ii. Pre-bid meetings and two stage bidding process can be adopted
by the utility to address concerns of the suppliers and
incorporating their suggestions to improve specifications.
A. Risk Description
This risk arises if the same entity is involved in formulation of technical
specifications/scope of work and execution of R&M project.
Directly initiating the process with the OEM is considered safe, convenient
and saves time and effort of the utility.
D. Bearer of Risk
The utility is the direct bearer of this risk.
A. Risk Description
This risk arises if there is significant delay in undertaking decisions to
resolve issues faced during the execution of the work. This could be related to
the possible surprises upon the opening of machines which may require
contract modifications; difference in the interpretation of scope and
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 95
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
D. Bearer of Risk
This risk affects all the parties involved in the R&M implementation
including the utility, supplier and the implementation support consultant.
Alongside, empowered team of both the utility and the suppliers should be
nominated to ensure timely resolution of disputes and issues, as and when
they arise. In a number of successful examples of large projects being
implemented, a key governing philosophy of the host entity has been that
Success of the contractor/supplier is success of the projects. Hence, a
collaborative atmosphere needs to be created wherein both the utility and the
supplier work as partners.
A. Risk Description
A thermal power plant undergoing R&M, despite undertaking
comprehensive prior plant assessment might face unforeseen events once the
unit is shut down and opened up for R&M. Such unforeseen events are called
Technical Surprises. As the units are very old or nearing the useful life of
operation, such technical surprises are quite common. The utility due to such
surprises is faced with unexpected change or unforeseen additions in the scope
of work leading to cost and time overruns. In order to address this risk it is
suggested that CEA guidelines for Early Identification of Potential Technical
Surprises in R&M Projects and Ways of Addressing Them may be referred.
Table below presents the time gap between the completion of RLA study and
execution of work.
Ukai TPS, Unit 2 (120 MW), GSECL April 2003 August 2008
Barauni TPS, Unit 6 (110 MW), BSEB May 2006 November 2009
Bandel TPS, Unit 5 (210 MW), WBPDCL January 2005 February 2012
Source: CEA and interaction of AF- Mercados EMI with various utilities
In addition to the above, the finances of the utility are directly impacted in
absence of any strategy to deal with such surprises.
The frequency of occurrence and severity of this risk is high.
D. Bearer of Risk
Both Utility and Vendor are affected by this risk.
Further, this should also include the unit rates for equipment/parts and
total financial implications of the same. In this regard CEA has
prepared standard documents for Detailed Project Report which may
be considered by the utilities.
Turbine Side Valves: As per R&M contract, all valves were to be refurbished by the
contractor. However, requirement of spares for refurbishment of valves was
unknown during the contracting stage. When the valves were opened by contractor
8
The first aim in all earnest should be to minimize the occurrence of technical surprises.
An associated issue was that most of the valves were obsolete and now not being
manufactured by the contractor or their sub-vendors. Hence, replacement was the
only option.
Site accessibility and space constraint are important factors for delay of R&M works
in Obra, which were not considered before the start of the project. Due to space
constraints crane cannot move between the units and therefore R&M works for Unit
10 & 11 were taken together. ESP of unit 11 had to be dismantled so that the crane
could move and work on Unit 10 can be undertaken. This was not envisaged at the
assessment stage.
Thus comprehensive assessment and planning before the execution of R&M works is
necessary to avoid technical surprises.
Example 3: Additional Scope of Work in Ukai TPS (Unit 1 and 2), GSECL
In case of Ukai TPS additional work over and above R&M work was identified such as
(i) Rewinding & Recaging of HT motors, (ii) Supply of IP Inlet Gland Box &
Accessories, (iii) Supply of spares for ESP fields 1&2 of Unit 2 etc. Since these works
were considered essential for future performance of the plant and there was no
provision for addition/alteration of R&M, separate purchase orders were placed by
the company.
A. Risk Description
This risk arises due to occurrence of disputes including contractual disputes
that affect the execution of work.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 100
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
D. Bearer of Risk
Both Utility and Vendor are affected by this risk.
5.4.4. Mismatch (or delay) in Supply of Critical Equipment and the Shutdown
Period (Market Risk)
A. Risk Description
Various sub-activities within the R&M have to be planned and timed
according to the available shutdown period. Accordingly, the schedule of
supply of critical equipment has to be synchronized with the shutdown period
to ensure completion of work in the minimum possible time. This risk arises
when there is delay in supply of key components and equipments by the
supplier and delivery schedule of the equipments is not in sync with the
shutdown period of the plant.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 101
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Source: CAG Audit Report and Interactions of AF Mercados EMI with the officials of the
HPGCL
Source: CAG Audit Report and Interactions of AF Mercados EMI team with the officials of
UPRVUNL.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 102
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
D. Bearer of Risk
Both Utility and Vendor are affected by this risk.
The delay on the part of I.L, Kota in completing the work of unit No.1 &2 as
per the schedule (October 2008) resulted in potential loss of generation to
the utility for the delayed months (work completed in January 2009).
Further, due to absence of the penalty clause in the agreement no penalty
could be imposed on I.L., Kota such delays.
9
A review of supply contracts of various plants indicates that such penalties are generally
included in the contract, however in some cases omissions have also been observed.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 103
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
A. Risk Description
The process of quality control involves setting up the specification of
equipment and service upfront and ensuring that the delivered material/service
is in compliance with the stated targets. This is often performed through
random inspections and test.
D. Bearer of risk
Utility is the direct bearer of this risk.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 104
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Example 2: Case of Koradi TPS (Unit 6), Maharashtra and Bandel TPS
(Unit 5), West Bengal
The R&M project plan for the above plants indicates the following:
Independent Implementation Support and Quality Assurance Consultants,
working in collaboration with the concerned power generation utility, would be
appointed for monitoring implementation progress as well as quality. These
consultants would act as owners engineers for the power generation utility
and validate all design details, material supplies and works executions. The
consultants would also support decision making process to handle surprises
during the course of R&M implementation
Thus, the process of having independent QAC has been considered and
ensured as part of the implementation process.
Source: Interactions of AF Mercados EMI with the Utility Officials and Review of
documents collected during the site visits
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 105
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
A. Risk Description
Thermal power plants lead to gaseous emissions containing carbon dioxide,
oxides of sulphur and nitrogen, and solid particulate matter (ash). Besides, the
waste water discharges contains the pollutants. These power plants, thus
results in air, water, noise pollution and land degradation.
The risk arises if the units undergoing R&M are not able to achieve the
target emission standards even if efficiency gains are achieved. Further, the
risk also arises if rehabilitation work is perceived to have adverse
environmental and social impact on the habitants in the project vicinity.
D. Bearer of Risk
Both generating company and supplier are direct bearers of the risk.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 106
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 107
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
5.4.7. Delay in Provisioning of Unit Shut down for Executing R&M Works
(Institutional Risk)
A. Risk Description
This risk arises if the utility is unable to schedule timely shutdown for
executing R&M either due to grid conditions or delay in obtaining timely
approvals from the relevant authorities (State Government or Regulatory
Commission) for shutdown of the plant.
Box 18: Delay in obtaining shutdown for R&M works during execution
While the material for boiler was supplied by the vendor, delay in providing
shutdown for the unit led to deterioration of the new equipment which further
delayed the execution of R&M.
The likelihood of the occurrence of this risk is low to high depending upon
the number of units requiring simultaneous shutdown. It may not be difficult to
obtain requisite approval for one unit but in case multiple units are scheduled
for such shutdown, obtaining requisite approvals/permissions may be difficult.
Severity of risk varies from low to high depending upon the delay in
obtaining the approvals for shutdown.
D. Bearer of Risk
Both generating company and supplier are the bearers of the risk.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 108
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
A. Risk Description
O&M practises being followed by state owned generation companies in India
are weak. Most of the state owned generating companies do not adhere to the
schedule of annual maintenance and periodic capital overhaul of the plant
leading to deterioration in the condition and performance of the plant. Most of
the DPRs (pre-R&M study) reviewed by team corroborate the above fact.
Another reason which could affect the sustainability of R&M gain is the non-
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 109
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
This risk arises when the performance gain become difficult to sustain due
to weak O&M practices and poor support services by the vendor after R&M has
been completed.
Box 19: Weak O&M practices of various State Generation Companies in India
Most of the utilities do not adhere to the Maintenance Schedule and periodic Capital
Maintenance Schedule.
BSEB - Annual Maintenance has not been undertaken at regular intervals. For
Barauni TPS Unit 6 the first and last capital maintenance was done during October
1988- November 1989 and for unit 7 during July 1992-May 1993 respectively.
In most of the states the shutdown of the units for planned maintenance depends
upon the power availability situation of the state and thus, annual maintenance of
majority of units is delayed in many states.
Poor O&M practices impacts the long term performance of plant and leads
to its continual deterioration.
Source: CAG Audit Reports and Interaction of AF Mercados EMI with officials of various
utilities
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 110
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
The likelihood of the occurrence and severity of this risk is high leading to
suboptimal utilisation of R&M investment.
D. Bearer of Risk
Generating company is the direct bearer of the risk.
Box 21: Adequate skills to undertake O&M, post R&M of the plant
During interactions with various officials both at the utility headquarters and
the plant level, it was observed that most of the utilities lack adequate skills
and expertise in operation and maintenance of plant. The schedules are not
followed, there are no documented processes, and limited up-gradation has
happened over the years. In certain cases, this has resulted in degradation of
plant performance post R&M. Thus, it is important to ensure that O&M
practices are strengthened and a robust plan is developed upfront and
followed.
Source: Interaction of AF Mercados EMI with officials of various utilities
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 111
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Box 22: Experience of Engaging Specialised Company for O&M of Coal based
Power Plant in India
As per the agreement signed between the parties, Steag would be responsible for
smooth and reliable operations and maintenance for 4x600 MW Coal based Power
Plant at Jharsuguda. Further, as per the contract Steag would also bring in its
proprietary plant management system and latest fault prediction systems which
would ensure that the downtime for maintenance is reduced to a minimum. Health,
Safety and Environmental systems would also be given high priority. Thus, the
contract not only enables the company to ensure better O&M practices but also
enables access to the state of the art technologies, systems and processes.
DESEIN is currently handling total Operation & Maintenance of many plants in India
& Abroad. This includes :
10
http://www.business-standard.com/india/news/vedantaevonik-ink-rs-14000-crore-
omdeal/392724/, last accessed on 12th September 2012
http://steag.in/pdf/STEAG%20Energy%20Services%20(India)%20Pvt.%20Ltd.%20%20%20Pro
file.pdf, last accessed on 12th September 2012
http://www.desein.com/Services/om-services.php, last accessed on 12th September 2012
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 112
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Example: Korba East Thermal Power Station, CSPGCL: Unit 1 to 4(4x50 MW)
and Unit 5 and 6 (2x120 MW)
Table below presents the post refurbishment performance of units in O&M guarantee
period.
Source: Interaction of AF Mercados EMI with officials of CSPGCL and data collected during the
visits
A. Risk Description
Performance guarantee test are conducted to test the performance of the
plant viz-a-viz the guaranteed parameter, within a specified period of time
after commissioning of the plant. A review of contract indicates that in most
cases the following guaranteed parameters have been adopted: (i) plant
availability; (ii) ESP outlet emission level; (iii) boiler efficiency; (iv) turbine
heat rate, and (v) rated capacity.
This risk arises if the performance test fails and the requisite performance
guarantees are not achieved or if the performance guarantee test is not
conducted or delayed incessantly.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 113
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
D. Bearer of Risk
Both generating company and supplier are the bearers of this risk.
While the impact of this risk is seen towards the end of the R&M exercise a
number of actions indicated in the previous sub-sections also contribute
towards non-achievement of the guaranteed parameters. Hence, preventive
actions as indicated earlier in this chapter are critical to avoid such situations.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 114
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
including assistance of the CEA, however still the PG test remain pending.
Pre R&M
Post R&M
Note: Unit has been up-rated from 110 MW to 117.8 MW w.e.f. 07.04.200 and unit
was under shutdown for R&M from Sept. 2007 to Oct 2008
A. Risk Description
The capital cost incurred during the R&M is considered as part of the overall
regulatory asset base of the utility wherein the regulator admits the cost based
on prudence check and approves a tariff to be charged from the consumer for
recovery of such costs. This risk arises if the regulator does not approve the
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 115
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
D. Bearer of Risk
Generating company is the direct bearer of the risk.
A. Risk Description
Post evaluation of R&M works is essential to understand the
impact/effectiveness of the program. Such evaluations though largely missing
would not only facilitate stakeholder feedback towards the scheme, but also
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 116
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
This risk arises if the generating company does not undertake ex-post
evaluation of the R&M works and fails to incorporate the experience or unable
to improve upon the execution of R&M works for its ongoing units. Also, this
leads to lack of institutional memory when the staff involved in R&M moves
out.
The likelihood of occurrence of this risk is high. Severity of this risk is low
and it would also impact future R&M projects of the company.
D. Bearer of risk
Generating company is the direct bearer of the risk.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 117
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Chapter 6
Risk Heat Matrix and Management Plan
This chapter presents the risk heat matrix and the risk management plan
emerging from the assessment in the preceding chapter.
- Tier 4: presents risks which have low severity with low likelihood of
occurrence. These risks are of least importance for the project and
do not have material impact on the project.
Figure below presents the risk heat matrix for a typical R&M project.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 118
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
20 9
Reactive approach to identification of plant for R&M 2
1 8
High
5
12 4 B Technical Risk Occurrence of technical surprises 7
19
17 15
25 Post R&M guarantees not achieved 8
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 119
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Table below summaries the key risk, the category of risk, the bearer, frequency, severity and the strategies proposed to deal with
such risk.
IDENTIFICATION STAGE
Lack of long
Utility/Plant The rationale for R&M of a project should be
term
Owner is the established at the state level taking into account all
Management generation plan
2 High Moderate direct bearer. the alternative competing options. The decision
Risk and awareness
Also, impacts should involve multiple stakeholders including the
of available
the consumers. Discoms (Risk Avoidance)
market options
Lack of Moderate to Depends on case Entire R&M A. Need for Experience Sharing and Dissemination
3 Market Risk
confidence and high. to case basis, market (Risk Mitigation)
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 120
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
ASSESSMENT STAGE
Inadequate Impacts all the Comprehensive Studies for the unit planned for
Technical technical parties R&M should be mandatory. The scope of the study
5 High High including should cover both the Main Plant Equipment as well
Risk assessment/stu
dies generating as the Balance of Plant. The assessment should
company, cover review of O&M processes as well. Proxy
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 121
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Appropriate
Commission Practice of obtaining in-principle approval from the
Regulatory
7 not apprised of Moderate Moderate Utility Appropriate Commission should be
Risk
the R&M encouraged.(Risk Avoidance)
project plan
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 122
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 123
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
PLANNING STAGE
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 124
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Avoidance)
Implementatio
n contract
awarded to To avoid conflict of interest, a single entity should
Management vendor generally be avoided to assume both the role of
14 High Moderate Utility
Risk involved in design consultant as well as the supplier. (Risk
carrying out Avoidance)
technical
studies
EXECUTION STAGE
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 125
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
acceptance)
Weak dispute
resolution Creation of Dispute Resolution Committee at the
Contractual mechanism Utility and start of project to address disputes between the
17 Moderate High
Risk constraining Vendor Utility and the Contractor in a timely manner (Risk
the execution Mitigation)
of work
Weak
Approval of detailed quality plans and Engaging
Operational Supervision,
19 Moderate Moderate Utility Quality Control and Quality Assurance Consultants
Risk Quality Control
by the Utility. (Risk Mitigation)
And Assurance
20 Socio- Failure to High Moderate Generating A. Renovation of ESP system of the power
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 126
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
CLOSURE STAGE
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 127
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
A holistic assessment of the risks has been made (in the earlier chapter) by identifying risks occurring in different stages of R&M cycle i.e. in
identification, assessment, planning, execution and closure stage and by understanding the impact of the risk, its frequency of occurrence, its
severity and the bearer of the risk.
It is essential that the identified risks in these guidelines are evaluated by each generating company before implementing R&M
projects and appropriate strategies are formulated in line with these suggested in these guidelines to manage the
identified/evaluated risks.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 128
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Chapter - 7
Framework for Early Identification and Addressal of
Technical Surprises
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 129
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 130
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Chapter - 8
Identification of Technical Surprises along with its Root
Cause and Impact
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 131
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Superheater and There may be cracks in the seat and spindle of the
8 Reheater Safety safety valves which may be overlooked during the
Valves studies
11
This problem is non-existent when one to one replacement of the entire economizer is taken
up.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 132
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 133
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 134
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 135
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Civil Work
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 136
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Electrical System
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 137
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
- Vacuum Pump
- Low Pressure
Heaters
- Deaerator
- Gland Steam
Coolers
- Pressure Reducing
and De-
superheating
System (PRDS)
12
No major technical surprises were observed for these equipments/components during the
visits to select power plants, interactions and consultation held with the officials of the
generation utilities and sector experts.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 138
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
for any third party invited for R&M of the unit). Lack of overhauling
records with the utility is another related aspect. Due to the lack of
such records suppliers are unable to comprehensively understand
the exact condition of various equipments i.e. components that
were replaced during the operating life of the plant, replacement
time and history and remaining useful life of such equipments.
c) Inadequate Assessment
RLA and other tests are conducted for main plant and equipments
only whereas in case of rest of areas like Balance of Plant (BoP) the
scope is generally derived, without any actual condition assessment
for BoP items. Lack of planning/assessment of BoP was found to be
the one of the most common issues faced by the utilities. Lack of
well chalked out path for cranes to reach the sites, space
constraints etc. are some of the important issues generally
overlooked during the planning stages.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 139
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Table below presents the time gap between the completion of RLA study and
execution of work.
Ukai TPS, Unit 2 (120 MW), GSECL April 2003 August 2008
Source: CEA Quarterly Review Reports on R&M and LE of Thermal Power Stations and
interaction of AF- Mercados EMI with various utilities
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 140
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
g) Technological Obsolescence
Refurbishment of old equipment or spares may not be possible due to
technological obsolescence. This is true especially in case of old units
of 110/120 MW units wherein the manufacturers have stopped
manufacturing the spares (especially electrical) due to technological
obsolescence.
Also in most cases, the strategy to deal with such surprises is not
planned leading to distress for utilities.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 141
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
b) Cost Escalation
Any additional work discovered in the form of surprise has a cost
associated with it. This could be both direct as well as indirect.
Direct costs include the cost of additional work and increase in IDC
cost of the utility. Indirect cost include the loss in potential
generation and hence revenue of the utility due to additional time
required to address these surprises. Lack of ownership/active
participation by the utility in acknowledging such additional work
and deciding an acceptable course of action are key issues faced
during implementing R&M. Both suppliers and utility are bearers of
this risk. While the loss of supplier is limited to the cost of
addressing the surprise, utility suffers/bears a large proportion of
the cost in form of both direct as well as significant indirect cost
caused due to loss in potential generation. Moreover utility might
also face regulatory risk wherein recovery of these costs may not be
allowed by the state electricity regulatory commission while
determining generation tariffs.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 142
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
d) Quality Deviation
Technical surprise may also impact the quality of R&M works and
non-achievement of overall R&M benefits. One of the most
concurring technical surprises seen is non-availability of spares or
incompatibility of older system with the new system envisaged in
R&M project. Due to such surprises, the expected outcome of the
scope cannot be met and the utility has to look for other
alternatives which affect the quality of the system. This situation
arises due to improper assessment of the relationship and
interaction between different components/equipments in a thermal
plant. Further, to minimise the delays/shutdown period certain non-
priority items are not given due importance during the R&M process
which may affect the overall quality of work.
e) Contractual Dispute
Disagreement between supplier and utility regarding additional
scope on account of technical surprise and incomplete interfacing
between components and instruments may lead to contractual
dispute causing delay or slow execution of the work. This dispute
also arises from the fact that in most of the contracts, scope of work
is vague and to safeguard its interest utilities generally include
clauses such as:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 143
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Chapter - 9
Strategies for Early Identification of Technical
Surprises and Ways of Addressing Them
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 144
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
(OEMs).
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 145
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Based on the technical studies, efforts should be made to define the scope
as clear as possible along with the roles and responsibilities of each of the
stakeholder. This includes clarity in the scope with regard to the following:-
Further, this should also include the unit rates for equipment/parts and
total financial implications of the same. In this regard CEA has prepared
standard documents for Detailed Project Report which may be used by the
utilities.
13
The first aim in all earnest should be to minimize the occurrence of technical surprises.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 146
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
In this regard CEA has prepared standard bid documents which may be
used by the utilities.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 147
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Further, such pre-approved budget also reduces regulatory risk of the utility
at the closure stage.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 148
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
9.3.1. Minimizing time gap between assessment and award of contract and
preparation of interim O&M action plan by the utilities (Preventive)
One of the major reasons for occurrence of technical surprises is the time
gap between the assessment and the actual execution of the project. After
undertaking assessment of the plant and preparation of DPR, utility has to
undergo several approval procedures including approval from its own Board of
Directors, State Government (due to the requirement of equity capital),
regulatory commission etc. which may lead to significant lapse in time. Weak
contracting capabilities of the utilities may further add to the time delay.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 149
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 150
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Communication Objective of
Medium Frequency Participants
Type Communication
along with the
suppliers
R&M Cell-
Plant Level
officials,
Discussion over
implementatio
Technical the technical Face to
Weekly n support
Meetings issues / surprises Face
consultants
for the project.
along with the
senior officials
of suppliers
R&M plant cell
Report the status
to
of the project
Headquarter
Project Status including activities,
Email Weekly (HQ) Cell and
Reports progress, costs
subsequently
and issues, key
to higher
action points.
authorities
Report on the
status of the Board of
Monthly/Quarte
project to Face to Monthly/Quar Directors
rly Project
management. Face terly 3.4.
Status Meetings
Approval/decision R&M HQ Cell
on key issues
9.5.2. Ex-Post evaluation of surprises and lessons learnt for future R&M
projects (Managing Surprises)
Ex-post evaluation of surprises encountered during execution of R&M works
and the actions undertaken is essential to understand the impact/effectiveness
of the entire plan. Generating company must undertake ex-post evaluation of
the R&M works and should document its experiences. This is important
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 151
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 152
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Table 17: Areas of potential surprises in various components of plant system along with examples and key strategies to address
them
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 153
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 154
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 155
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
14
This problem is non-existent when one to one replacement of the entire economizer is taken up.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 156
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 157
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 158
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 159
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 160
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
15
Central Pollution Control Board (CPCB)Standards for Particulate Matter Emissions for Thermal Power Station are as follows-
Generation capacity 210 MW or more- 150 milligrams per normal cubic metre
Generation capacity less than 210 MW- 350 milligrams per normal cubic metre
However, it is advised that the utility should also check the standards of their respective state pollution control boards.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 161
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 162
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 163
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 164
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 165
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 166
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 167
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 168
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 169
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 170
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 171
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 172
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 173
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 174
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 175
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 176
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Chapter - 10
Global R&M Experience: Case Studies from
selected countries
Note: Numbers
Source: in parentheses
IEA, 2012, Technologyrepresents
Roadmap,theHigh-Efficiency,
ratio of total coal resources-to-reserves
Low-Emissions, for Power
Coal-Fired each
region
Generation
Coal reserves in gigatonnes (Ct)
Therefore, Coal is Worlds most widely used fossil fuel for electricity
generation. In 2010, coal accounted for more than 40% of total electricity
generation in the World, (Refer Figure below) followed by natural gas and hydro.
Power generation from fossil fuel accounts for majority of CO2 emissions. In
2009, generation of electricity and heat contributed to 41% of the World CO2
emissions from fuel combustion primarily due to its heavy dependence on coal.
Despite increasing environmental concerns, coal is expected to remain one of
the major fuels for power generation in the foreseeable future driven by the
increasing demand from developing countries to improve electricity access in
their respective countries. Given the current and expected dominance of coal in
the World energy mix, improvement in the efficiency of coal based generation is
of immense importance.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 177
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Hydro
16%
Coal/Peat
40%
Nuclear
13%
Natural Gas
22%
Oil
5%
Notes: Other includes geothermal, solar, wind, bio-fuels and waste, and heat.
Total electricity generated in 2010 is 21 431 TWh. This excludes pumped storage .
Figure 11: World CO2 emissions from fuel combustion by sector in 2009
Other
10%
Electricity and
Transport Heat
23% 41%
Residential
6%
Industry
20%
The average efficiency of coal-fired power generation units in the major coal
using countries varies enormously. Efficiencies from fossil fuel based power
plants for some of the countries are shown below. In 2008, the energy
efficiencies for coal-fired power generation ranged from 31% in India to 41% in
France.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 178
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
40.00%
Australia
China
35.00% France
Germany
India
30.00% Japan
Korea
UK + Ireland
25.00% United States
20.00%
1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
Although review of literature indicates that R&M is one of the cost effective
options to improve the efficiency of thermal power plants, the drivers for
undertaking R&M differ across countries. The decision for undergoing R&M
depends upon a number of macro and micro level factors such as national level
policies, environmental regulations, resource availability, cost effectiveness of
competing fuels for power generation, need for increasing the availability and
reliability of power plant etc. For e.g., in EU member countries, climate change
policy and compliance to environmental standards acts as a major driver for
improving efficiency of thermal power plants. In South Africa, power
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 179
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Given the above background, this chapter presents the international R&M
experience of selected thermal power plants in different countries. The case
studies have been developed keeping in view the following research questions
(consistent with the scope of work and identified risks as part of Task 1 and Task
2 of this assignment):
Based on these experiences, lessons have been drawn for India for the
successful implementation of R&M in the country and measures required to
mitigate risks and technical surprises faced during the entire R&M process.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 180
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 181
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
iv. Two thirds of the installed coal plants are older than
30 years presenting an opportunity for Poland's old
power plants to be replaced by newer and significantly
more efficient power stations.
5. Turkey ii. Turkey produces both hard coal and lignite. However,
it has significant reserves of lignite as compared to
hard coal. It produces all the lignite it uses while it
imports about 90 per cent of the hard coal it
consumes. Further, it is expected that volumes of
imported coal may rise in the future with the increase
of coal's importance for electricity generation.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 182
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 183
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
10.2. Case Study of Suralaya Power Station Unit 1 And 2 (2x400 Mw),
Indonesia
1. Plant Details
Suralaya Thermal Power Plant is one of the largest coal fired thermal power
station in Indonesia with a total generating capacity of 4025 MW. The plant
comprises 8 units of different capacities commissioned between 1983 and 2011.
Units 1 to 4 are of 400 MW each, Units 5 to 7 are rated at 600 MW each and
Unit 8 is rated at 625 MW.
The plant was constructed in 4 stages with Units 1 and 2 being placed into
service in 1983 and 1984. Units 3 and 4 were commissioned in 1989. Units 5 to
7 were placed into service in 1997. The last stage, consisting of Unit 8, was
placed into service in 2011.
Unit 1 and 2 have been operated for baseload power since commissioning.
Having exceeding their design life, rehabilitation and up gradation works were
carried out on the ageing boilers for Unit 1 and 2. The boilers for Units 1 and 2
are 400 MW pulverised coal fired radiant tower types and were originally
supplied by Babcock & Wilcox Power Generation Group Inc. and Japan's
Marubeni Corporation back in the early 1980s. The first unit outage began in
October 2010 and successfully passed all of its performance guarantees in July,
2011. The second unit outage began in July 2011 and successfully completed its
performance tests in February 2012.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 184
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
a) Risk Assessment
Risk assessment on Unit 1 and 2 boilers was undertaken to
determine the probability of occurrence of a perilous event. Based
on known history, statistical data, judgment by experts, and an
evaluation of the consequences and repair or replacement costs of
the equipment, PLN/PT Indonesia assessed the potential risks.
b) Condition assessment
In order to assess the condition of the boiler and auxiliary
equipments following steps were undertaken:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 185
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
4. Project Execution
This project was carried out in partnership with Japan's Marubeni Corporation
and Babcock & Wilcox Power Generation Group Inc. (B&W) of the US and was
funded by the Japan Bank for International Co-operation.
d) Burner upgrade
Existing burners were replaced with low NOx burners complete with
igniters and flame scanners, which resulted in NOx emissions
reduction of 56% for both units combined.
Based on the above interventions the comparison of pre and post overall
project benefits are provided in Table below:
*NOTE: The values for (metric tons/yr) are for both units combined and are based on a boiler
capacity factor of 0.85 and the post-retrofit (increased) boiler output for both the Pre-
Retrofit and Post-Retrofit values.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 186
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
The project was successful and met all the initial overall objectives, which
were to extend the life of the units, reducing the emissions and restoring unit
efficiency subsequently leading to reduction in fuel consumption.
5. Summary
In summary, the following points need to be highlighted:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 187
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
10.3. Case Study of Tusimice II (ETU II) Power Plant (4x200 MW),
Czech Republic
In the period from 2007 to 2012, Tuimice Power Plant II underwent complex
restoration works to ensure its future operation in line with the current European
standards and planned operation life of the plant after rehabilitation corresponds
to the remaining life of the adjacent Libou mine.
2. Objective of R&M
There were several objectives for undertaking R&M. At the country level, the
decision for R&M was driven by energy security, compliance to EU environmental
regulations etc.
At the plant level, the decision for renewal of plant was based on the
availability of sufficient coal and quality of the available coal. The following two
considerations were assessed:
Since, the remaining life of Libou coal mine was only 25 years, Option 2 was
selected.
Further, assessment of the mine indicated that the coal available from
the mine for future utilization would be of markedly low quality and
hence power plant needs to be adapted to the lower fuel efficiency and
higher content of sulphur in future.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 188
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Civil surveys were also undertaken to inspect both the conditions for laying
foundation of the new structures and as-built state of the existing structures.
These surveys resulted in the decision on preservation or repair of the original
structures in order to allow the extension of the operational life of the plant.
On the basis of technical and economic study, a business plan was prepared
which provided the targets of the reconstruction of the power plant and main
principles of the technical solution.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 189
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
4. Project Execution
The project was executed through EPC contractor Skoda Praha Invest, Group
Company of CEZ. The contract for the preparation of the design was signed in
May 2005. The geological survey and inspection of the condition of buildings,
structures and process equipment at the power plant was carried out in order to
determine the possibility of their use for another 25 years.
After the successful completion of this stage, the EPC contract for the Power
Plant was signed in April 2006. The work related to the specifications started
immediately, along with the supplier selection procedure. The sub vendors for
the project were selected by Skoda Praha Invest on tender basis. Packaging was
done in a way that it ensures competition among different vendors leading to
competitive prices and at the same time the number of vendors to be managed
was limited. Around 10 major vendors were selected for the work related to
Machine, Turbine, Boiler House, I&C, Chemical Water treatment etc.
b) The first stage of the execution started in June 2007 with the
shutdown of Unit 3 and 4. The Unit 3 and 4 were commissioned in
February 2009 and April 2009 respectively. The trial run of these
units was completed in November 2009 and Protocol of the
Provisional Acceptance (PAC) was signed in September 2010.
d) It was observed that first phase of R&M was delayed by one year but
the second Phase of R&M was delayed by only one month. The
experience gained and lessons learnt in undertaking R&M works
during the first phase was duly incorporated while executing R&M
works of second phase.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 190
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
a) Construction Work
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 191
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
4.4. In order to resolve the technical surprises a joint committee was formed
by EPC contractor and CEZ
a) Boiler
Boilers were installed by Vitkovice Power Engineering and were
designed in a manner that can reach high effectiveness even while
burning fuel with a decreased quality in the future, while fulfilling
emission requirements.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 192
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
c) Machine Room
Modern three-stage turbines, each with a 200 MW power output,
were mounted on the slightly adjusted turbine foundations in the
original machine room. The turbines installed are of the action
blading, condensing type with steam reheating and eight non-
regulated steam outlets for heating of the condensate, feeding
water, and exchanger station heating water and feed water pump
drive. The turbine is being supplied by Skoda and generator is
being supplied by Siemens.
e) Water handling
Removal of hydraulic de-slagging and integration of waste water in
the power plant process
g) Construction
Some of the major civil parts of the work included repair of the
boiler steel structure, exchange of the machine hall roof shell,
adjustment of the turbo set foundation, repair of the internal and
external surface of the cooling towers etc. Construction of
completely new buildings also formed part of the work (such as
FGD buildings, water treatment, new piping and cable bridges and
slag silos).
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 193
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 194
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
R&M. Results of the warranty tests showed that the renewed power plant
equipment met all required technological and ecological parameters as
highlighted above. The EPC contractor met all the conditions and the
requirements stipulated in the contract. Emissions post R&M works were less
than the emission limits provided by EU standards.
Source: AF-Mercados EMI interactions with the utility and the EPC Player
5. Summary
In summary, the following points need to be highlighted:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 195
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
bidding.
f) Execution of R&M works on the plant was divided into phases.
g) The funding for the project was garnered from the internal resources
of the utility
h) Occurrence of technical surprises was observed during the
implementation of R&M works and were resolved through formation
of joint committee between EPC contractor and the utility
i) The project was successful and met all the conditions and the
requirements stipulated in the contract.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 196
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
10.4. Case Study of Prunerov II (EPR II) Power Plant (5x210 MW),
Czech Republic
1. Plant Details
The Prunerov TPP is owned by CEZ, the largest generating company of Czech
Republic. It consists of 5 units of 210 MW each, which was first taken into
operation in 1981 1982. In 1996, all units were retrofitted with limestone
based wet scrubbers to ensure proper SO2 emission control. In addition to the
production of electricity, also district heating is supplied to the neighbouring
urban agglomerations. Currently, R&M works are on-going on unit number 3-5.
R&M works are proposed for Unit 3-5 only. Unit number 1 and 2 are in
operation and are proposed to be retired after the R&M works for Unit 3-5 are
completed. Unit 1 is proposed to be closed in 2016 and Unit 2 in 2018. Time
schedule for R&M of Unit 3-5 is Sept 2012-2014.
2. Objective of R&M
The objective for undertaking R&M works include:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 197
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
The three refurbished blocks of EPR II will have an increased unit capacity of
250 MW.
4. Project Execution
In order to build upon the experience of R&M works of Tusimice and to
handle technical surprises, the learning of the project has been incorporated in
the preparatory work of EPR II.
This project is also executed under EPC mode and Skoda Praha Invest is
selected as the EPC contractor. In order to utilise the past R&M experience,
suppliers of key components are being retained.
Also, same project manager involved in R&M works of Tusimice power plant
has been involved for the R&M works of EPR II from the utility side.
The implementation of the project has started and timeline for R&M works
has been Sept 2012-2014. In order to effectively manage the project Skoda
Praha Invest organises working meetings with the relevant officials on a daily
basis. Further one official meeting per 14 days is also organised besides
providing the summary of work to the utility every week.
5. Summary
In summary, the following points need to be highlighted:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 198
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
1. Plant Details
PGE Elektrownia Belchatow, in the Lodz province of Poland, approximately
170 km south west of Warsaw, is the largest power plant in Poland and the
largest lignite-fired power station in Europe. It consists of 12 x 370/380 MW
(originally 360 MW) lignite fired reheat units commissioned between 1982 and
1988 (initially 4320 MW installed capacity, now 4450 MW, following the various
modernisation activities completed to date). The plant accounts for 20% of the
electricity produced in Poland. Upon completion of a new 858 MW supercritical
unit, currently under construction, and completion of modernisation programmes
on ten of the existing units, the installed capacity will be around 5500 MW. The
Belchatow power plant was originally developed by the state-owned power
utility, but as a result of the privatisation process, it is now owned and operated
by PGE (Polska Grupa Energetyczna).
All units are in operation and R&M works are expected to be carried out
initially on 10 of its units. It was decided to operate Unit 1 and 2 till the time
R&M works are completed on other units and the new unit is being
commissioned. Unit 3, 4, 5, 6 are renovated as on date. R&M works on Unit 7
and 8 is expected to be completed in 2013. Based on the R&M experience,
generating company has decided to even undertake R&M on Unit 2 as well.
Therefore, in total 11 units are subjected to R&M works and are expected to be
refurbished by 2016. Although R&M works on Unit 7 and 8 are on-going,
contracts for unit 9-12 have been signed and awarded wherein the R&M work
will commence after the completion of R&M works on unit 7 and 8. Although
R&M works are undertaken on several units, details are provided with regard to
Unit 6 as it has one of the most recent experiences.
2. Objective of R&M
The objective of R&M for Unit 6 was to extend the plants life, increase output
and availability of the plant, enhance the environmental performance etc. The
key objectives are detailed out below:-
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 199
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
the load range, and operating load range extended from 60-100%
MCR to 40-100% MCR plus compliance with grid code
requirements.
Effective utilisation of the coal mine was also one of the key drivers for R&M
works of the power plant as the generating company is also the owner of the
mine.
Based on the studies, PGE Elektrownia Belchatow initially aimed for a live
steam temperature of 547C, a reheat steam temperature of 568C and live
steam pressure of 170.2 bar, with the existing feedwater temperature, 255C,
for units 3 and 4.
Unit 3 was the first unit which underwent R&M. It acted as a pilot project
wherein the execution process and the results of R&M were tested.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 200
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
4. Project Execution
Indicative cost of R&M works for Unit 3, 4, 5, 6 were in the range of 200-220
Million Euros for each of the unit. However, there was decrease in the cost of
R&M works for subsequent units i.e. for Unit 7-12 due to the experience gained
from the R&M works on the earlier units. Indicative cost of R&M works for Unit
7-12 are in the range of 180 Million Euros/unit.
Packaging strategy for each of the units differed. Initially, R&M works (in
case of Unit 3) were divided into large number of packages but due to
coordination issues among different vendors and inability of the utility to
manage large suppliers, works were later divided into lesser number of
packages as illustrated below:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 201
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
a) Absolute guarantees
b) Penalized guarantees
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 202
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Celsius
v. Water injection to reheated steam - 20 t/h
vi. Combustible part in volatile ash - 3%
vii. Availability - 90%-92.5%
5. Summary
In summary, the following points need to be highlighted:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 203
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
10.6. Case Study of Turceni Thermal Power Plant (7x330 MW), Romania
1. Plant details
Romania has a diversified and balanced energy mix. Hydropower dominates
the energy mix with a share of ~36% followed by Coal with 33% and Nuclear
with 19% share.
b) A2 Program
Reconditioning of units 3 and 7, in cooperation with ABB, Babcock,
Hannemann, Flender, Taprogge, Hartmann Braun (Germany), Voith
(Austria), Alsthom (France) financed by EIB loan and own financial
resources. It has led to increased time availability and an increased
average output.
c) A3 Program
Rehabilitation of units 4 and 5, in cooperation with ABB Kraftwerke
and Deutsche Babcock. Unit 4 was commissioned in 2004; Unit 5 was
commissioned in 2006. It was financed via a KfW loan and own
financial resources. It has led to increased time availability, average
output, reduced fuel and internal electricity consumption.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 204
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
2. Objective of R&M
The objectives for undertaking R&M were as follows:
4. Project Execution
The following interventions were undertaken for the rehabilitation of Turceni
TPP Unit no.5:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 205
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
5. Summary
In summary, the following points need to be highlighted:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 206
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
1. Plant details
Afsin Elbistan A, a conventional thermal power plant utilizing low quality
lignite, was established by TEK in 1984-1987 and has 1355 MW of capacity. It
has four units and is of great importance in Turkey. The plant, owned by EAS,
the state owned Electricity Company. The plant was designed to burn low quality
lignite with high moisture easily without using supplementary fuel. The system
developed for such lignite is to first dry the lignite to increase its calorific value.
This TPP was designed for an annual electricity production of 8,800 GWh.
However, with the decrease in capacity and reliability of the plant due to
wear and tear of equipments and some unscheduled shutdowns. The average
efficiency decreased below the design efficiency. The R&M of this project was
planned as part of The World Banks support under the proposed Electricity
Generation Rehabilitation and Restructuring Project of Turkey.
2. Objective of R&M
Objectives envisaged for undertaking R&M were:
a) Technical
b) Economic
i. Increasing the capacity and efficiency
ii. Increasing the amount of electrical energy produced
iii. Help the generator decrease its losses
iv. Increasing operation period
v. Increasing the Availability and Reliability
c) Environmental
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 207
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
a) Plant output of each unit will be increased from about 260 MW net
to 300 MW net;
b) Capacity factor will be increased from 40% or below to 75%; and
c) Net plant efficiency will be increased from 27% to 31% (30.6%
with the FGD).
The detailed scope for rehabilitation was prepared based on the feasibility
study and broadly it included R&M of the boiler and firing system, the
electrostatic precipitators (ESPs), the main cooling water and condensate water
system (covered under the Balance of Plant Mechanical), control and
instrumentation, and ash and coal handling. The scope of rehabilitation work is
summarized below:
a) Boiler
Detailed inspection and repair work of the boiler waterwall,
superheater, reheater and economizer tubes, headers and other
pressure parts. Installation of new boiler cleaning system and soot
blowing system to improve the boiler efficiency as well as preventing
slugging which causes tube failures.
b) Steam Turbine
Overhauling of high pressure (HP), intermediate pressure (IP) and low
pressure (LP) inner casing and blades and replacement of the same in
selected units in order to achieve efficiency improvements and
increase in plant output. It also included replacement of turbine
governors for better frequency control.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 208
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
e) Precipitator
This included addition of a compartment to the main boiler flue gas
and the bruden vapour Electrostatic Precipitators (ESPs) to achieve the
required particulate emission level (100 mg/Nm3). This was necessary
to comply with the Turkish environmental regulations for Afsin (150
mg/Nm3) and the Bank's environmental guidelines for rehabilitated
existing plants.
h) Civil Works
This included repair/replacement of the reinforced concrete, steel
structure for the boiler, turbine and balance of plant. It also included
exterior and interior painting, earthquake safety (additional walls)
repair of damaged clear covers, and exposed reinforcement, protective
coatings and new foundations for concrete structure
Initially two stage bidding process was adopted. Two bidders applied at
the first stage with qualified bids, and were initially not found fully responsive.
Clarificatory meeting were held with the bidders, on the basis of which the
bidders were considered qualified, and were invited to the second stage.
The main concern of the bidders were perceived risks of not being able to
achieve the functional guarantees of a large scope rehabilitation works (1,300
MW), and the associated financing challenge.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 209
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Further, one of the bidders stated that they would not be able to qualify for
the rehabilitation of all four units of the plant, and thus requested that four units
of the plant be rehabilitated in two stages of two units each, EUAS did not agree
with this request, but allowed the bidder to strengthen their consortium.
However, despite all these adjustments, neither of the two bidders bid at the
second stage of the bidding process for the rehabilitation works.
The Government and the Bank agreed that under the environment of the on-
going investigation, EUAS may not be in a position to implement such a large
and complex project. Therefore, instead of re-starting a third procurement
attempt, it would be more prudent to cancel the project.
4. Summary
In summary, the following points need to be highlighted:
a) The R&M of this project was planned as part of the World Banks
support under the proposed Electricity Generation Rehabilitation
and Restructuring Project of Turkey.
b) Detailed studies were undertaken by the utility to assess the
condition of the plant, preparation of scope of work etc.
c) Higher perceived risks by the vendors led to their limited/non-
participation in the bidding process.
d) Vendors were to be selected based on competitive bidding.
e) R&M works on all the four units were envisaged to be
implemented at the same time which also acted as one of the
reasons for non-participation of vendors due to increase in
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 210
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
perceived risks
f) R&M works were not implemented on the plant due to start of an
unrelated investigation by the government related to procurement
actions of EUAS.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 211
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
10.8. Case Study of Arnot Power Station (6x350 MW), South Africa
1. Plant Details
ARNOT thermal power station is a coal fired power station located in
Mpumalanga, South Africa, is a coal-fired power plant operated by Eskom, a
South African utility. The plant initially comprised of 6 units of 350 MW each and
was commissioned between 1971 (unit 1) and 1975 (unit 6). Completion of 30
years of its useful lifetime/design life combined with the increasing demand for
electricity in the country, sustained running of the plant required
replacement/retrofit of most of the parts. Alstom was selected to retrofit and up-
rate the six units of Arnot power station.
2. Objectives
The objective of Rehabilitation works were to retrofit major plant components
in the most cost effective manner such that each unit would produce a
continuous gross electrical output of 400 MW and there is extension in the life of
the plant by another 20 years.
4. Project Execution
The scope of the project carried out by Alstom included the complete retrofit
for the high pressure and intermediate pressure steam turbines, a capacity
upgrade of the low pressure steam turbine and the replacement and upgrade of
associated turbine side pumps and auxiliaries.
In addition, Alstom carried out major upgrading works to the boiler plant.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 212
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
b) Boiler Plant
The following description outlines the equipment upgraded or
replaced as part of the project to upgrade the boiler plant from a
continuous output of 365 MW to 400 MW.
i. Furnace
The existing furnace size was adequate for the 400 MW upgrade
and the furnace plan and heat release rating were within
allowable maximums for the normally supplied coals.
iii. PA Fans
New Primary air fans were installed.
v. Economiser
Two additional rows of extended economizer surface were added
to the existing configuration. The economizer profile was similar
to that previously installed and the support structure was
suitable for the additional surface with only minor modifications.
R&M was performed during routine major outages of the six units over
a three-year period. In each case, the outage length was 13 weeks,
principally the significant amount of work required on the boiler.
For each of Arnots six steam generating units, the output was
upgraded from 350MWe to 400MWe. Results of the performance tests
carried out by Eskom on two units had been extremely encouraging.
Power output under calibrated steady state test conditions has been
measured as 406.2 MWe for Unit 3 (against a target of 400) and 409.0
MWe for Unit 2. Informally, substantially higher outputs have been
observed under high load conditions.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 213
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
The first unit was completed by December 2007 and the last unit by
December 2010.
b) Technical surprises
Alstom was the Original Equipment Manufacturer (OEM) for the
major equipment at Arnot Power Station. Copies of the original
design documentation still existed and had been used for the initial
feasibility study. However, to minimize occurrence of technical
surprises, access to records of Eskom were made and interactions
were held with the plant level officials with long experience at the
plant, which revealed some items previously unknown to either
party, particularly from the plants construction phase. Minor
surprises still occurred when the equipment was opened up
for retrofit. These surprises or variations were recorded in a formal
system so that lessons may be may be applied in future, both on
other units on the same project and on similar plant elsewhere.
5. Summary
In summary, the following points need to be highlighted:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 214
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 215
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Based on the review undertaken in previous chapters, this section presents the comparative analysis of R&M experience in
different countries.
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
The plant was Objectives: Objectives: The plant was The plant was
Objectives:
selected for R&M selected on the selected for R&M as
Restoring Extend the The plant was
as it is the basis: Extension of it is the largest TPP
production useful life of selected on
largest TPP in plant life in Romania with a
portfolio for the the units The plant had the basis that
Indonesia with a total capacity of
next 25 to 30 exceeded its Removal of it had
total capacity of Improving the 2310 MW.
years indexed to useful lifetime operational completed its
Selection of 4025 MW and the life of the environmental and contributes problems useful Objectives:
Unit/Plant plays a critical mine. performance around 20%of lifetime/desig
for R&M role in meeting of the plant Reduction To maintain its
the total n life of 30
1. along with the electricity Improving the and to comply of current position of
electricity years
objectives demand. environmental with the maintenanc being a net exporter
produced in
of carrying performance of European e work Objectives: of electricity
Objectives: Poland
out R&M the plant emission Technologic To increase Reduction of CO2 and
Reduction in CO2 standards. Objectives:
To comply with al the unit SO2 emissions in
and NOx the emission Extension of improveme capacity order to follow the
Efficiency
emissions standards Unit life nts environmental
Improvement Extension of
Upgrade the prescribed by and reduce (especially regulations.
Thermal plant life
capacity of unit 1 the European consumption in electrical
optimisation to To increase the
and 2 from 400 legislation. of primary components
increase operational and
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 216
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
S. South
Parameters Indonesia Czech Republic Poland Turkey Romania
No. Africa
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
Automated
start-up,
shutdown and
operation of the
unit throughout
the load range,
and operating
load range
2. Advanced Convection pass Boilers used Partial Turbine island R&M of the Turbine Plant: Boiler full
technologic pressure part were designed in replacement modernisation boiler and The major replacement of
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 217
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
S. South
Parameters Indonesia Czech Republic Poland Turkey Romania
No. Africa
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
al options replacement a manner that of the turbine include HP and firing retrofit pressurized water
for EE R&M could reach high IP turbine system, the required to circuit.
Safety valve Installation of
such as effectiveness retrofits, electrostatic the turbine
replacement new Turbine HP case
turbine up- even while turbine precipitators plant was the
electrostatic and rotor
gradation, Air heater burning low auxiliaries, (ESPs), the complete
precipitators replacement
efficient refurbishment quality fuel in extraction pipe main replacement
for dust
and the future, while work, generator cooling of the high Generator system
Burner upgrade removal
environmen fulfilling emission retrofit, new water and pressure (HP) modernisation
t friendly Pulverizer rebuild requirements. Installation of feed-water heat condensate and
Coal firing system
furnace- and upgrade new wet exchangers, water intermediate
Reconstruction has been re-
boilers, coal scrubbers for electro- system pressure (IP)
of Flue gas designed,
utilization SO2 removal hydraulic (covered turbine inner
Desulphurization
etc control system under the cylinders. A digital command
units Complete
and, I&C Balance of system has been
replacement Milling Plant:
Machine Room: equipment. Plant implemented
of the modifications
Modern three- Mechanical),
automatic Boiler undertaken Conveyor belts
stage turbines, control and
control modernisation with regard to modernisation
each with a 200 instrumenta
system for the includes the mill
MW power tion, and ESP modernisation
entire facility pressure parts, classifier and
output, were ash and coal
firing system, gearbox. 10.6.
mounted in the Partial handling.
flue gas and air
original machine replacement PA Fans: New
ducts, ID and
room. and Primary air
FD fan retrofit
modernisation fans were
In case of Coal and I&C
of electrical installed.
handling the equipment.
equipment
original Burner
Air pre-heater
equipment was Introduction Nozzles: New
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 218
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
S. South
Parameters Indonesia Czech Republic Poland Turkey Romania
No. Africa
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 219
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
S. South
Parameters Indonesia Czech Republic Poland Turkey Romania
No. Africa
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 220
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
S. South
Parameters Indonesia Czech Republic Poland Turkey Romania
No. Africa
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 221
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
S. South
Parameters Indonesia Czech Republic Poland Turkey Romania
No. Africa
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
works related to
turbine
generator, ESP,
certain BOP
works etc. and
Babcock would be
undertook Boiler
works.
The EPC
contractor International
The EPC Skoda Praha Competitive
contractor Skoda was selected bidding
Praha was on nomination Process was
selected on basis as it is a used to
Procuremen group Suppliers for Competitive
nomination basis select
t Process company. different units bidding
as it is a group vendors.
for While the Sub were selected Process was
5. Not Available company. While However, Not Available
Selection of vendors were based on adopted to
the Sub vendors the bidding
Consultant/ selected competitive select the
were selected process was
Contractor through a bidding process. vendor
through a cancelled
competitive competitive and R&M
bidding process bidding works were
by Skoda Praha. process. not
However, some undertaken.
of the key
vendors
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 222
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
S. South
Parameters Indonesia Czech Republic Poland Turkey Romania
No. Africa
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
involved in
R&M works of
Tusimice
project were
retained.
The source of
The source of
financing for
financing for
IFI Funding undertaking
Funding was undertaking R&M IFI funding
Funding of (funded by Japan R&M works Financed via a KfW
through the works included (funded by
6. R&M Bank for included Not Available loan and own financial
internal sources of internal The World
Projects International internal resources
the utility resources and Bank)
Cooperation) resources and
balance sheet
balance sheet
financing
financing
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 223
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
S. South
Parameters Indonesia Czech Republic Poland Turkey Romania
No. Africa
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
Option 2: In case
of modernization
life of 25 years can
be obtained
Since, the
remaining life of
Libou coal mine
was only 25 years,
Option 2 was
selected.
Implement R&M was The project R&M works are In total 11 units R&M was Phased approach was
R&M works
8. ation of implemented in a implementation ongoing. Time are subjected to performed undertaken for
were not
R&M phased manner. was divided into schedule for R&M works. during routine refurbishment of
implemented
Projects Phased outages for two stages. The R&M of Unit 3- major outages different units of the
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 224
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
S. South
Parameters Indonesia Czech Republic Poland Turkey Romania
No. Africa
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
including unit 1 and unit 2. first stage of the 5 is Sept 2012- The current . of the six units Turceni TPP. Unit 4 was
shut down The first unit execution started 2014. modernisation over a three- commissioned in 2004;
time outage began in in June 2007 with programme year period. In Unit 5 was
October 2010 and the shutdown of underway at the each case, the commissioned in 2006.
successfully Unit 3 and 4. The Belchatow plant outage length
passed all of its Unit 3 and 4 were was started was 13 weeks.
performance commissioned in during 2007 and
The first unit
guarantees in July, February 2009 is expected to be
was completed
2011. The second and April 2009 refurbished by
by December
unit outage began respectively. The 2016.
2007 and the
in July 2011 and trial run of these
last unit by
successfully units was
December
completed its completed in
2010.
performance tests November 2009.
in February 2012.
The second stage
of the execution
started in
November 2009
with the
shutdown of Unit
1 and 2. The trial
run of Unit 2 was
completed in
October 2011.
The trial run of
Unit 1 was
completed in April
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 225
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
S. South
Parameters Indonesia Czech Republic Poland Turkey Romania
No. Africa
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
2012.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 226
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
S. South
Parameters Indonesia Czech Republic Poland Turkey Romania
No. Africa
Afsin
Suralaya Power
Prunerov II Belchatow Elbistan A
Plant Station Tusimice II Arnot Turceni
Name (5x200 (12x370/380 (3x340 MW
(Units 1 & 2) (4x200 MW) (6x350 MW) (7x330 MW)
MW) MW) & 1x335
2x400 MW
MW)
R&M was
successful as it
R&M was R&M works met all the
successful as it Warranty period not pre-
met all the pre- is three years and implemented. determined
determined one warranty One of the objectives.
objectives. The engineer is main Suitable
guarantee period present at the concerns of equipment
Measures R&M was of 24 months for site for any the bidders warranties
In line with
for successful as it process assistance during were were R&M was successful as
that of
10. Guaranteed met all the pre- equipment and 60 the warranty perceived negotiated for it met all the pre-
Tusimice II
Performanc determined months for the period. risks of not the scope of determined objectives.
project.
e post R&M objectives civil structures being able to hardware and
start after the Stipulation of achieve the services being
signature of the Absolute and functional provided by
Protocol of the penalised guarantees of Alstom
Provisional guarantees in the a large scope together with
Acceptance contract. rehabilitation adequate non-
(PAC). works. conformance
resolution and
remedy.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 227
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Chapter - 11
Lessons for India based on review of International
Best Practices in R&M
Second part presents the measures that can be used to mitigate the risks
and handle technical surprises in the thermal power stations in India. Third part
presents the standard menu of options/ advance technological options for
energy efficiency focused rehabilitation and life extension of 210 MW and above
units in thermal power stations in India.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 228
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 229
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
g) Technical feasibility
Before taking up R&M works undertaking technical feasibility
studies are pre-requisites. From the international experience it is
observed that such studies are being carried out before undertaking
R&M works based on which a detailed scope of work is prepared. In
the Indian context, it is observed that at times utility does not
undertake comprehensive studies or undertake proxy assessments
leading to weak or unrepresentative scope of work and sub-optimal
outputs. Therefore, it is suggested that technical feasibility of
different R&M options must be undertaken by the utilities before
undertaking such works.
h) Efficiency Improvement
Efficiency improvement is a key objective and outcome for
implementation of R&M works. To effectively implement R&M
projects it is important to mitigate different risks and technical
surprises that may occur during the implementation of R&M
projects. Various measures that are required to be undertaken to
address such risks is explained in detail in next section.
i) Environmental safeguards
Meeting environmental standards has been one of the key
objectives for undertaking R&M works in the international scenario.
R&M works are carried out keeping in view not only the existing
standards but compliance to possible future stringent standards
that may come into effect in future. Some of the interventions
undertaken in this regard included installation of new electrostatic
precipitators for dust removal, installation of new wet scrubbers for
removal of SO2, Redesigning of combustion system to reduce NOx
emissions etc. Therefore, it is important for successful
implementation of R&M works and operation of plant thereafter
environmental considerations/safeguards or interventions need to
be built in while planning R&M works.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 230
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 231
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Appropriate
Commission not This risk was not observed in the selected
Regulatory
7 apprised of the international case studies undertaken as
Risk
R&M project part of the study.
plan
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 232
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 233
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 234
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Mismatch (or
delay) in supply
This risk was not observed in the selected
of critical
18 Market Risk international case studies undertaken as
equipment and
part of the study.
the shutdown
period
Delay in
Obtaining shutdown has not been
provisioning of Institutional
21 observed as a concern in the international
obtaining unit Risk
scenario.
shut down for
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 235
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Sustainability of
R&M gains This risk was not observed in the selected
Operational
22 affected by international case studies undertaken as
Risk
weak O&M part of the study.
practices
applications/options exist for different components of the power plant that can
be implemented to improve the overall efficiency of the plant. Based on the
review of international experiences, this section brings out the
possible/indicative/achievable improvement in the efficiency or station heat rate
of the unit in post R&M scenario.
Boiler Island
Turbine Island
Refurbishment/Overhaul of Turbine
Replacement of turbine blades
Reduction of steam leakages
Optimization or Repair of Condensers
Refurbishment of Boiler Feed Pump
Refurbishment of Feed Water Heaters
Others
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 237
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 238
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Retrofit improvements:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 239
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Table 25: Summary of the technological options along with the efficiency
potential identified in S&L report for different power plant
components
Air Heater and Duct Leakage Control 0.03 - 0.13 0.03 - 0.13
Turbine Island
Replacement of centrifugal ID fans with axial fans 0.03 - 0.16% 0.03 - 0.16
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 240
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
O&M training
Computerized maintenance and management Included in combustion
O&M systems and Reliability centered maintenance and steam cycle gains.
Efficient operation
Distributed control systems realized over the long
term.
Combined Total 3.5
Based on the above standard menu of options for energy efficiency focused
rehabilitation and life extension for different power plant components is
presented in brief below:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 241
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Table 27: Standard menu of options for energy efficiency focused rehabilitation and life extension for different power plant
components based on international review
Potential
Technological Options Description Efficiency Reference
Improvement (%)
Boiler Island
Pulverizer:
Low Speed:
- Ball and Tube Mil
Medium Speed:
Improvements in pulverisers and
- Ring and Ball Mill
feeder design allows better grinding
- Vertical Spindle
of coal which leads to:
Roller Mill
Improvement in combustion due
Pulverizers and Feeder - Bowl Mill
to better fineness of coal Up to 0.3 APEC
Upgrade High Speed:
Reduces the amount of coal
- Hammer Mill required to be burnt in boiler as
- Attrition Mill carbon content in the bottom ash
Coal - Beater Wheel Mill and in fly ash reduces.
Handling
Plant Feeder:
Volumetric Feeders
Gravimetric Feeders
Coal Dryers
- Rotary Dryers
- Pneumatic Dryers
Coal Drying process reduces the
- Fluid-bed dryers
Upgrade Coal Drying moisture content in coal and
with spouted bed 0.1 to 1.7 NETL
Process improves combustion efficiency of
- Vibratory fluid-bed
the boiler
dryers
- Shaft Dryers
- Mill type Dryers
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 242
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Potential
Technological Options Description Efficiency Reference
Improvement (%)
Bottom Ash
Handling
- Water impounded
Bottom Ash hopper
with hydro jet
pump or ash slurry
pumps
- Dry type Bottom Dry Ash Handling System doesnt
Ash hopper with require water in the bottom ash
removal process. It provides several
submerged scraper
conveyor benefits such as improvement in
boiler efficiency, reduced thermal
- De-watering Bin
energy losses as the air is heated by
System
Ash the heat of bottom ash. Further, as
Installation of dry ash - Pressure Pneumatic
Handling the land availability is very difficult it Upto 0.1 NETL
extraction system Conveying System
Plant is going to be the latest
- Dense Phase
environmental norms.
Pneumatic
Conveying system
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 243
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Potential
Technological Options Description Efficiency Reference
Improvement (%)
- Fly ash Storage
Silos
- Feeder ejector
system
- Dry mechanical
conveyors
Advanced Low NOx
Combustion System
- Low NOx Burners
- Overfire Air (OFA)
System
Improvement in combustion control
Improved Combustion Combustion enables proper air and coal flow NETL
0.15 to 0.84
system control/optimise Optimisation DCS leading to better heat transfer and SKM
and Software for improvement in boiler efficiency
- Fireball Centering
- O2 distribution
Boiler
balancing
- Combustion
balancing
Soot Blowers
- Long Retractable Installation of additional/intelligent
Soot Blowers soot blowers (ISB) helps in keeping
Soot blower
- Wall Blowers the boiler pressure parts surface S&L
optimisation/Installation of 0.09 to 0.65
clean improves furnace performance NETL
new/intelligent soot blowers Intelligent Soot
by better heat transfer and increases
Blowers
the longevity of tubes.
Sonic Soot Blowers
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 244
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Potential
Technological Options Description Efficiency Reference
Improvement (%)
Excess of air in flue gas means that
there is more air than required for
combustion. If controlled and tuned, APEC
Low Excess Air Operation 0.2 to 1.22
low excess air reduces heat loss from SKM
flue gas exiting the boiler and
improves the efficiency.
Recuperative Type
- Cast Iron Air
Preheater
- Plate Air Preheaters
- Tubular Air
Air Pre- Replacement/Upgrade Air Preheater Replacement or up-gradation S&L
0.03 to 1.5
heater Pre-heater improves the efficiency due to better NETL
Regenerative Type heat transfer from the flue gas.
- Ljunstorm
- Bi-sector Extra heat surface also allows more
- Tri-sector heat to be extracted leading to
- Rothemuhle maintain/lower flue gas temperature
Boiler Tubes
Provides better heat pickup area and
Extended Surface increases the boiler efficiency.
Replacement/Upgrade - Stud Fins
Economiser 0.16 to 0.32 S&L
Economiser - Longitudinal Fins
- Helical Fins
- Rectangular Fins
-Baffles
Improvement in FD Fan Axial Fan Replacement of centrifugal fans with 0.03 to 0.16
FD Fan S&L
efficiency axial fans and replacement of (without VFD)
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 245
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Potential
Technological Options Description Efficiency Reference
Improvement (%)
Centrifugal Fan dampers with Variable Frequency
- Airfoil Drives (VFD) maximises efficiency 0.03 to 0.48
- Backward Inclined and minimises operating costs by (with VFD)
- Curved Backward lowering the Auxiliary power
Improvement in ID Fan Inclined consumption.
ID Fan
efficiency - Flat Backward
Inclined
- Radial Tip
- Forward Curved
Blades
Turbine Island
Technological advancement in
Refurbishment/Overhaul computation in fluid dynamics has S&L
Reaction Type allowed the manufacturers design 0.32 to 2.6
of Turbine NETL
Turbine higher efficient turbines. In any case,
whether the utilities decide to
Impulse Type replace the entire turbine or
Replacement of turbine Turbine refurbish turbine with better blades, APEC
0.5 to 0.98
Turbine blades the utility stands benefited from the NETL
enhanced performance.
Steam leakages in turbine means
that the steam gets wasted without
doing any useful work in the turbine.
Reduction of steam leakages 0.84 to 1.1 Aus NETL
Reduction in leakages like in main
gland can greatly enhance the
performance of the turbine output.
Optimisation or Repair of Offline/Online From thermodynamics point of view, S&L
Condenser 0.09 to 2.4
Condensers Condenser Cleaning the steam condensed in condenser NETL
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 246
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Potential
Technological Options Description Efficiency Reference
Improvement (%)
System should occur at lowest feasible
vacuum temperature. However with
time, due to degradation and fouling
of condenser, installation of either
offline or online condenser cleaning
can greatly reduce the back pressure
which results in significant reduction
in heat rate.
BFP consumes significant amount of
auxiliary power and thus
refurbishment of Boiler Feed Pump
Boiler Feed
Refurbishment of Boiler Feed Pump can significantly increase the 0.08 to 0.16 S&L
Pump (BFP)
reliability and availability of the unit.
In addition to this turbine driven
BFPs are also being used.
Feed water heaters primarily preheat
the boiler feed water and improves
steam cycle efficiency by using heat
Feed Water from low / high pressure steam from NETL
Refurbishment of Feed Water Heaters 0.2 to 1.97
Heaters the turbine. Refurbishment or SKM
addition of feed water heaters can
significantly increase the feed water
temperature
Others
Computer simulation model with real
time measurement of plant
Control Installation of new integrated Neural Network with
performance from data input from 0.16 to 2 S&L - NETL
System Distributed Control System (DCS)
DCS can help in optimising boiler
performances by predicting and
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 247
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Potential
Technological Options Description Efficiency Reference
Improvement (%)
adapting to the different load
requirement at different time of the
day. The optimisation Neural
Network model can be also be
extended to efficient use of FGD,
superheat and reheat temperature.
Variable Frequency Drives provide
many advantages over varying
pressure/temperature with fixed
speed drives:
Increase in life of motors due to
soft start
Increases the life of pumps and
Variable
fans by reducing the stress and
Frequency
Installation of Variable Frequency Drives wear 0.06 to 1.97 S&L - SKM
Drives
Ensures high degree of accuracy
(VFD)
due to accurate speed control
and quick response
Increases reliability and
availability of drives as it
eliminates any sudden voltage
dip and ensures smooth control
over motors, pumps and fans.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 248
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Chapter - 12
Estimation of the Potential Reduction in GHG Emissions
on account of Implementation of Energy Efficient R&M
Table 28: Source of Production for different types of Greenhouse Gases (GHG)
Greenhouse
Source of production
Gas
Primarily the emission is through burning of fossil fuels (oil, natural
gas, and coal), solid waste, and trees and wood products. Further,
Carbon-dioxide
deforestation and soil degradation leads to increase in carbon-
dioxide, whereas forestation reduces it.
Methane is emitted during the production and transport of coal,
natural gas, and oil. The emission also occurs due to livestock
Methane
breeding, agricultural practices and from the anaerobic decay of
organic waste in municipal solid waste landfills.
Nitrous and Main emissions are from combustion of fossil fuels and solid waste
Sulphur oxide and also from agricultural and industrial activities.
Source: http://www.epa.gov/climatechange/ghgemissions/gases.html
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 249
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
In 2009, generation of electricity accounted for more than 50% of the total
CO2 emissions from fuel combustion in India primarily due to its heavy
dependence on coal.
Figure 15: Indias CO2 emissions from fuel combustion by sector in 2009
Others
Transport
10%
9%
Residential
5%
Electricity
and Heat
54%
Industry
22%
Further, average efficiency of coal fired power plants in India is lower than
the world average. Worldwide coal-fired power plant efficiency averaged around
35.1% in 2007 (IEA, and CIAB 2010).
a) Technology
Efficiency to a great extent is dependent upon the technology adopted for power
generation. In India most of the past installed capacity is sub critical technology
16
Report of The Working Group on Power for Twelfth Plan (2012-17), Ministry of Power,
Government of India, January 2012
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 250
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Figure 16: Profile of operating fleet of coal fired power plants in India
Recent advancement in super critical and ultra supercritical technology has led
to higher performance levels by the coal fired power plants. Although, as of now
the majority of the new power plants are sub critical, there has been increasing
emphasis on the super critical technology and large numbers of recent units
(under construction) are super critical units. In addition, according to the
12thPlan Working Group Report on Power, 38% of the overall 12thPlan capacity
addition target is based on supercritical technology. Further, it is expected that
13thPlan may stipulate all new coal fired plants constructed to be at least on
supercritical technology.
b) Vintage
Lower levels of performance can be expected from plants of older design,
although upgrades can improve even the oldest plants. For example, in case of
turbine, efficiency decreases with the increase in the years of operation and in
the initial years of operation this deterioration in efficiency may be relatively
faster. Deterioration may be equivalent of 0.25% of heat rate per year of
operation between overhauls and up to 2% in the first two years alone.
However, with routine maintenance some of the deterioration can be restored.
Plant performance can also be restored during major overhauls (IEA, 2010).
In India, more than 40% of the total operating coal fired power plant fleet is
older than 20 years.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 251
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Figure 17: Vintage of the operating fleet of coal fired power plants in India
Younger
Older than than 10
20 years
42% 38%
Between
10-20 years
20%
Figure 18: Share of coal fired generation units in terms of capacity in India
Larger than
300 MW
29%
Lower than
300 MW
71%
d) Coal Quality
Indian coal is predominantly from the open cast mines and has high ash and
high moisture content, which results in the lower plant efficiency. The typical ash
content in Indian domestic coal is in the range of 30% to 45% as compared to
15-20% in most of the developed countries.
Over the years, the coal quality is degrading due to increasing ash content and
due to high moisture content. The new coal mines identified are also producing
inferior quality coal. Over the years, the calorific value of Indian coal has
reduced from 5900 kcal/kg in 1960s to 3500 kcal/kg in the present scenario.
This is one of the major reasons for low operating efficiency of coal fired power
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 252
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
plants in the country. Poor quality of coal also leads to higher wear and tear in
combustion chambers/mills etc. and leads to lower plant efficiency. In FY 2011,
the generation loss due to poor coal quality was estimated to be around 5.9
Billion Units17.
It can be observed from above that the current efficiency of coal based power
plants in India is well below the state of art and it is important to improve the
overall efficiency of power plants by improving existing plants through
Renovation and Modernisation (R&M) or by installing new systems based on
advanced technologies. Improving the efficiency of coal based generation plants
offers several benefits in terms of reduced consumption of coal, meeting energy
shortages, increased access of electricity and savings in balance of payment
through reduction in importation of coal. Further, as electricity accounts for
majority of emissions, improvement in the efficiency of the coal based
generation becomes the key policy target for reducing the GHG emissions of the
country.
With the above background, the next section presents GHG emission reduction
potential of EE R&M of thermal power stations in India under various scenarios.
17
Central Electricity Authority, Operation Performance of Generating Stations in the Country
During the Year 2011-12, April, 2012
18
The report is available in the CEA website.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 253
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
presented below provides the sector-wise breakup of the R&M/LE potential in the
12thand 13th plan as assessed in the report.
The current operating average net SHR of coal based thermal power plants
assessed for R&M/LE in the 12th Plan is around 2962 kcal/kWh which translates
into an efficiency of around 29.03%. If all the plants post R&M operate on their
design efficiencies, the average net SHR can be improved to 2,551 kcal/kWh i.e.
around 33.7%. The CO2 emission reduction potential ranges from 6%-13%
depending upon the level of average efficiency achieved post R&M/LE in the 12th
Plan. In absolute terms CO2 emission reduction potential ranges from 14.91 Mt
CO2 to 29.81 Mt CO2 across different scenarios with respect to the Baseline.
19
This also includes slipped units (Both State and Central) from 11thPlan. Units which have
completed R&M/LE during the FY- 2012-13 have not been considered while estimating GHG
reduction potential.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 254
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Figure 19: CO2 emission reduction potential of coal based power plants
targeted for R&M/LE in India in the 12th Plan
220.48 MtCo2
9%
1044 gCo2/kWh
Similarly, CO2 emission reduction potential ranges from 6%-12% in the 13th
Plan with absolute terms CO2 emission reduction potential ranging from 6.31 Mt
CO2 to 12.61 Mt CO2 across different scenarios with respect to the Baseline. The
result is summarized in the figure below:
Figure 20: CO2 emission reduction potential of coal based power plants
targeted for R&M/LE in India in the 13th Plan
98.70 MtCo2
9%
1062 gCo2/kWh
95.55 MtCo2 12%
1028 gCo2/kWh
92.40 MtCo2
994 gCo2/kWh
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 255
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
The CO2 emission reduction potential ranges from 8%-15% depending upon the
level of average efficiency achieved post R&M/LE in the 12th Plan. In absolute
terms CO2 emission reduction potential ranges from 8.96 Mt CO2 to 17.93 Mt
CO2 across different scenarios with respect to the Baseline.
Figure 21: Capacity wise break up for state sector coal based units identified
for R&M/LE during the 12th Plan
100 MW 1
Capacity (MW)
110 MW 13
200 MW 8
210 MW 63
500 MW 4
0 10 20 30 40 50 60 70
Number of units
Figure 22: CO2 emission reduction potential through R&M/LE of coal based
power plants in the state sector of India during the 12th Plan
115.00 1065.86
1021.78
110.00 1050.00
gCO2/unit
977.71
Mt CO2
105.00
100.00 900.00
117.40
108.44
103.95
99.47
95.00
90.00 750.00
Baseline Conservative Intermediate Optimistic
Scenario Scenario Scenario
Scenarios Mt CO2
g CO2/unit
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 256
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Further, CO2 emission reduction potential ranges from 6%-12% depending upon
the level of average efficiency achieved post R&M/LE in the 13th Plan. In absolute
terms CO2 emission reduction potential ranges from 3.70 Mt CO2 to 7.41 Mt CO2
across different scenarios with respect to the Baseline.
Figure 23: Capacity wise break up for state sector coal based units identified
for R&M/LE during the 13th Plan
Capacity (MW)
250 MW 3
210 MW 34
500 MW 2
0 5 10 15 20 25 30 35 40
Number of Units
Figure 24: CO2 emission reduction potential through R&M/LE of coal based
power plants in the state sector of India during the 13th Plan
65.00 1300.00
1104.93
1038.26
gCO2/unit
60.00 1004.93 1100.00
Mt CO2
971.59
55.00 900.00
57.68
61.38
55.82
53.97
50.00 700.00
Baseline Conservative Intermediate Optimistic
Scenario Scenario Scenario
Scenarios Mt CO2
g CO2/unit
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 257
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
identified for R&M/LE in the 12th Plan is around 2847 kcal/kWh which translates
into an efficiency of around 30%. If all the plants post R&M operate on their
design efficiencies, the average net SHR can be improved to 2535 kcal/kWh i.e.
efficiency of around 34%.
The CO2 emission reduction potential ranges from 5%-10% depending upon the
level of average efficiency achieved post R&M/LE in the 12th Plan. In absolute
terms CO2 emission reduction potential ranges from 5.93 Mt CO2 to 11.87 Mt
CO2 across different scenarios with respect to the Baseline.
Figure 25: Capacity wise break up for central sector coal based units identified
for R&M/LE during the 12th Plan
Capacity (MW)
200 MW 13
210 MW 25
500 MW 17
0 5 10 15 20 25 30
Number of Units
Figure 26: CO2 emission reduction potential through R&M/LE of coal based
power plants in the central sector of India during the 12th Plan
110.00 900.00
117.98
112.05
109.08
106.11
105.00 800.00
100.00 700.00
Baseline Conservative Intermediate Optimistic
Scenario Scenario Scenario
Scenarios
Mt CO2
g CO2/unit
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 258
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
The CO2 emission reduction potential ranges from 6%-12% depending upon the
level of average efficiency achieved post R&M/LE in the 13th Plan. In absolute
terms CO2 emission reduction potential ranges from 2.6 Mt CO2 to 5.20 Mt CO2
across different scenarios with respect to the Baseline.
Figure 27: Capacity wise break up for central sector coal based units identified
for R&M/LE during the 13th Plan
250 MW 1
Capacity (MW)
200 MW 1
210 MW 13
500 MW 5
0 2 4 6 8 10 12 14
Number of units
Figure 28: CO2 emission reduction potential through R&M/LE of coal based
power plants in the central sector of India during the 13th Plan
1166.71
46.00 1200.00
1097.09
44.00 1062.28
1027.47
42.00 1050.00
Mt CO2
gCO2/unit
40.00
38.00 900.00
39.73
43.63
41.03
38.43
36.00
34.00 750.00
Baseline Conservative Intermediate Optimistic
Scenario Scenario Scenario
Scenarios Mt CO2
g CO2/unit
Source: AF-Mercados EMI analysis
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 259
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Chapter 13
Possible Framework for Monetizing the GHG
Emission Reduction
This chapter presents the global carbon market mechanism and different
monetising framework for R&M in India. This chapter also presents the barriers
in monetizing GHG reductions from R&M measures and the related strategies to
overcome the barriers.
Voluntary Market
Compliance Market
(governed by standards)
CDM JI
Australia
Europe Japan New Zealand
NSW GHG Abatement US
EU - ETS Japanese ETS NZ ETS
Scheme
California
RGGI WCI
ETS
Source: AF-Mercados EMI Compilation from United Nations Framework Convention on Climate
Change (UNFCCC) and various reports
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 260
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
1. Global Mechanism
Kyoto Protocol20
The Kyoto Protocol was signed in 1997, at the 3rd Conference of the Parties
(COP 3) to the Framework Convention on Climate Change in Kyoto, Japan. This
treaty provided for legally binding national caps on GHG emissions on developed
countries, known as Annex 1 countries that ratified the protocol.
The emission reductions from CDM and JI projects can be procured by Annex 1
countries to meet their Kyoto commitments.
2. Regional Market
In addition to Kyoto Protocol there are other numerous emission trading
schemes established at the regional and national level. Some of these are
explained in brief below:
20
The Clean Development Mechanism, An Assessment of Progress, United Nations Development
Programme, November 2006
21
In the recent CDM Conference of Parties (COP) at Doha, the parties have agreed to extend the
CDM mechanism for the second commitment period, which runs from 1 January 2013 to 31
December 2020. The CERs generated through the CDM projects will remain tradable in the second
commitment period as well.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 261
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
c) USA
i. Regional Greenhouse Gas Initiative (RGGI)24
Regional Greenhouse Gas Initiative (RGGI) is the first market-
based regulatory program in the United States to reduce GHG
emissions. RGGI is a cooperative effort among the states of
Connecticut, Delaware, Maine, Maryland, Massachusetts, New
Hampshire, New York, Rhode Island, and Vermont. Together, these
states have capped and will reduce CO2 emissions from the power
sector by 10 per cent by 2018. States sell nearly all emission
allowances through auctions and invest proceeds in consumer
benefits: energy efficiency, renewable energy, and other clean
energy technologies.
22
http://www.greenhousegas.nsw.gov.au/
23
http://ec.europa.eu/clima/policies/ets/index_en.htm
24
http://www.rggi.org/
25
http://www.westernclimateinitiative.org/
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 262
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Out of all these mechanisms, VCS is most commonly and widely used GHG
program in the global voluntary carbon market.
26
http://www.cleanenergyfuture.gov.au/why-we-need-to-act/what-others-are-doing/united-
states-of-america/
27
PAT Perform, Achieve and Trade, Ministry of Power, Government of India, July 2012
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 263
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
The figure below illustrates the phase-wise scheme of Perform, Achieve and
Trade (PAT).
Implementation
Target Setting Verification Trading
& Monitoring
Target Setting Phase In this phase, energy intensive companies, also known
as Designated Consumers (DCs) were identified which will fall under the PAT
Scheme. The Specific Energy Consumption (SEC) reduction targets have been
notified to DCs in March 2012.
Trading Phase Trading and allotment of ESCerts will take place during April
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 264
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
2015 March 2016. Companies which have over achieved their targets would
entail them to issue ESCerts and companies with under achieved targets will
need to purchase ESCerts to fill the gap between targets and achievements.
Failure to do so will attract market based penalties. The penalties would be
based on the price of ESCerts and the quantum under achieved targets.
Saving Achieved
Targets SEC
Compliance
Achieved Purchased
SEC ESCerts
Source: PAT Perform, Achieve and Trade, Ministry of Power, Government of India, July 2012
The PAT Scheme covers eight industry sectors (Thermal Power Plants,
Fertilizers, Iron & Steel, Cement, Pulp & Paper, Aluminium, Chlor-alkali and,
Textiles) based on the intensity or quantity of energy consumed.
With regard to thermal power plants, in first PAT cycle 144 designated
consumers from various states have been identified for which the target have
already been notified. Thermal Power Plant sector has been categorized on the
basis of their fuel input i.e. gas, oil and coal/lignite based plants where there are
107 units under Coal/lignite, 33 and 4 under gas and diesel respectively. The
total reported energy consumption of these designated consumers is about 104
million ton of oil equivalent. By the end of the first PAT cycle, the energy savings
of 3.211 million ton of oil equivalent /year is expected to be achieved, which is
around 48% of total national energy saving targets assessed under PAT. The
target reduction for thermal plants has been based on the deviation of average
net heat rate (2007-2010). The table below illustrates the reduction norm for
the thermal plants:
Table 30: Reduction Norm for thermal power plant under PAT Scheme
Deviation in net SHR from Reduction target (%) as percentage of
designed net SHR deviation in net heat rate
Upto 5% 10%
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 265
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
The BEE notification document of July 2012 provides the specific reduction
targets for individual units.
These thermal plants can improve the efficiencies of their plants through EE
R&M in order to comply with the PAT target and can become eligible for ESCerts,
which can be traded at market determined prices.
Project Implementation
Monitoring and and Operation
Operation of CDM /
VCS Project
Evaluation of
technology options
of CDM Project
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 266
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
a) Identification Stage
During this stage of R&M the plant operators regularly monitor the key plant unit
parameters covering at least the following aspects to identify symptoms that
may necessitate R&M of power plants: (a) Plant Availability, (b) Plant Load
Factor, (c) Auxiliary Consumption, (d) Emission Factors, (e) Level of Outages, (f)
Life of the plant etc., (g) Frequency of annual overhaul; (h) frequency of capital
overhaul etc. The diagnosis at this stage is based on available plant records and
design data. Timely identification and diagnosis of problems is of critical
importance and form the foundation for successful R&M of the plant in the
future.
Similarly, this stage also forms foundation for developing project under the CDM.
In order to initiate CDM project, it is important to establish a credible baseline
for the project. Past unit wise data on parameters such as fuel consumption,
electricity generation, plant load factor etc. for at least five years prior to
implementation of R&M is generally required for developing the R&M project
under the CDM.
b) Assessment Stage
During the assessment stage detailed technical evaluation of the plant is
undertaken through conducting various studies such as Residual Life
Assessment, Condition Assessment studies, Energy Audit etc. The technical
evaluation of the plant is followed by the economic evaluation of the plant to
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 267
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
decide on the most optimal option for undertaking R&M of the project. This is
followed by preparation of Detailed Project Report and preparation of the scope
of R&M Project for the selected option.
c) Planning Stage
Once the scope of the project is finalised, the utility develops the design
specification and proposal package and determines the procurement/bidding
strategy. Planning stage covers the entire bid process management i.e. issue of
tender(s), pre bid meetings, evaluation of technical and commercial bids,
selection of suitable bidder, negotiation of contracts and award of R&M contracts
to vendors/suppliers/OEMs.
The CDM process in this stage starts after the issuance of purchase order to the
suppliers in accordance with the scope of work formulated in the previous stage.
Within 180 days of issuance of the purchase order utility is required to submit a
Prior Consideration Form to UNFCCC. The purpose of this form is to submit the
notification of the commencement of the project activity and the intention to
seek CDM status.
After the submission of this form, utility is required to prepare the Project
Design Document (PDD). The PDD contains a detailed description and
specification of the proposed CDM project, including information about the
project, baseline scenario and quantification methodology, monitoring plan,
stakeholder comments, and environmental impacts. An essential component of
the PDD is the determination of the project baseline against which emission
reductions are measured. The project proponent/utility must also make the case
that the projects emission reductions are in addition to reductions that would
have otherwise occurred. In order to determine the baseline scenario, UNFCCC
approved methodologies may be used or a new methodology may be developed
by the project proponent (for which approval from CDM EB will be required). In
case of Energy Efficient R&M measures there are few existing approved
methodologies to estimate GHG reduction through R&M measures such as AM
0061, AM 0062 etc. A detailed discussion on the existing approved
methodologies is undertaken in the next sub-section of the report.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 268
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
d) Execution Stage
This stage covers the entire R&M project implementation stage which begins
with the receipt of equipments to the site and planning of shutdown of unit. This
stage involves the Validation and Registration of CDM project.
After the preparation of PDD, utility is required to appoint a Designated
Operational Entity (DOE), approved by the UNFCCC, for independent
validation/evaluation of the project. DOE evaluates the PDD and also make the
document public for stakeholder consultation/comments on the PDD.
This stage also involves approval of the project from the host country and the
confirmation that the project activity assists the host country in achieving
sustainable development. In case of India, this approval is required from the
National CDM Authority (NCDMA). NCDMA evaluates the project in the light of
sustainable development objectives of the country and also assess the
probability of successful implementation of CDM projects.29
After the successful project validation, the revised PDD along with host country
approval and other details is submitted for the review of CDM Executive Board
(EB) by the DOE. The CDM EB is the ultimate point of contact for CDM Project
Participants for the registration of projects and the issuance of CERs.30
CDM EB evaluates the PDD, validation report and provides its observation on the
same. These documents are also made public for receiving the comments on the
same.
The CDM EB may, based on its evaluation approve the project for registration,
request a project review, or reject the proposed project.
28
A designated operational entity (DOE) is an independent auditor accredited by
the CDM Executive Board (CDM EB) to validate project proposals or verify whether implemented
projects have achieved planned greenhouse gas emission reductions. Source:
http://cdm.unfccc.int/DOE/index.html
List of DOEs: http://cdm.unfccc.int/DOE/list/index.html
Sectoral scopes related to approved methodologies and DOEs (as on 27 Dec 2012):
http://cdm.unfccc.int/DOE/scopes.html
29
http://www.cdmindia.in/constitution.php
30
http://cdm.unfccc.int/EB/index.html
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 269
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
e) Closure Stage
After the R&M work is completed, it is very essential to evaluate whether the
goals and objectives of the R&M project was achieved or not. For this post-R&M
Performance Guarantee Test is conducted. Further, Operation and Maintenance
Training is imparted to engineers for efficient operation of the unit that has
undergone R&M.
After the completion of R&M works, monitoring of the CDM project is initiated.
This includes collection of the required data to quantify the actual emission
reduction achieved by the project. The actual monitoring of the project must be
in line with that specified in PDD.
The monitoring of the project is followed by the validation stage wherein DOE
will verify the emission reduction as proposed by the monitoring report. In order
to avoid conflict of interest it is important that a new DOE be appointed for
verification. The time period for undertaking Verification process and issuance of
CERs can be annually/monthly depending upon the volume of emission reduction
or the time frame specified in the PDD.
It must be noted that adoption of proper O&M practises post R&M is crucial as
deterioration in the performance of the plant would reduce the quantity of CERs
to be issued to the utility.
CDM Consultant
Generating Company
DOE
DNA
CDM EB
Regulator
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 270
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Issuance of CERs is followed by the trading of CERs and sharing of the CDM
benefits with the consumers, in line with that specified by the State Electricity
Regulatory Commission/Central Electricity Regulatory Commission (CERC). As
per CERC, Tariff Regulations 2009 2014, Regulation 36, the proceeds from
carbon credit from approved CDM project shall be shared in the following
manner:
For trading the CERs; the utility may opt for two methods. They may
approach CDM consultants directly or they can trade in the exchange. In case,
the utility opts for CDM consultant, the consultants can provide the following
services:
31
Additionality is the requirement that the greenhouse gas emissions after implementation of a
CDM project activity are lower than those that would have occurred in the most plausible
alternative scenario to the implementation of the CDM project activity. The alternative scenario
may be the business-as-usual case (that is, the continuation of current emission levels in the
absence of the CDM project activity), or it may be some other scenario which involves a gradual
lowering of emissions intensity.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 271
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
In this approach, the utility with the help of CDM consultants can directly
come into negotiations with the buyer and trade carbon credits. Alternatively,
the utility can sell carbon credit in the exchange. In India, the Multi Commodity
Exchange (MCX) entered into an alliance with the Chicago Climate Exchange in
2005 to introduce future carbon credit trading in India. There are certain
benefits in trading carbon credit in the exchanges which are given below:
32
ERPA is an agreement between the buyer and seller where the responsibilities, rights and
obligations to manage project risks is recorded. It also defines the commercial terms of the project
including price, volume and delivery schedule of emission reductions
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 272
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
The selection of particular methodology will depend upon the site specific
conditions and type of technological interventions undertaken during R&M of the
plant.
CDM projects can be classified into large scale project and small scale project
depending on the scale of the projects. If utility is planning to undertake small
R&M works and the expected benefit is low, then the project can be developed
under small scale methodology. Further, small scale projects can be applied with
simplified modalities and procedures. For small scale project, the following
criteria must be fulfilled:
The eligible existing methodology under small scale project is given below:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 273
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Efficient auxiliary
AM0044: Energy efficiency improvement in boiler
technologies
Baseline case: Continuation of the current situation; i.e. use of the existing
fossil-fuel-fired energy generation equipment with lower efficiency.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 274
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Baseline Parameter to be
Applicability condition Project Scenario
case monitored
Baseline case: Use of fossil fuel in a boiler with a low efficiency to supply steam
to a steam system.
Project scenario: Use of less fossil fuel in a boiler as less steam is required for
the steam system due to improved efficiency. Improvement in the boiler
operation leads to reduction in coal consumption for same output. Reduction in
coal consumption means less GHG emission.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 275
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Baseline case: Use of fossil fuel in a boiler to supply steam to a process with
high steam consumption.
Project scenario: Use of less fossil fuel in a boiler as less steam is required for
the process with a higher efficiency. This methodology majorly covers efficiency
improvement on the boiler. Improvement in the boiler operation leads to
reduction in coal consumption for same output.
Applicability Project
Baseline case Parameter to be monitored
condition Scenario
1. Production output
2. Corresponding steam
consumption
A project Use of fossil fuel Use of less fossil
activities that in a boiler to fuel in a boiler 3. Boiler efficiency
optimize the supply steam to as less steam is 4. Steam enthalpy
use of steam in a process with required for the
a production high steam process with a 5. Additional electricity /
steam / fuel consumption
process consumption higher efficiency
for the project activity
6. Fuel consumption analysis
and calorific values
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 276
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Boiler(s)
1. The boilers that are with lower The efficiency of 1. Total thermal output
rehabilitated under the efficiency boiler(s) of each boiler in the
project should have will project.
is improved
some remaining lifetime continue to through their 2. Amount of fossil fuel
2. The installed capacity of operate at rehabilitation consumed; net
each boiler shall be multiple resulting in a calorific value of
determined using a locations, reduction of fossil fuel, emission
performance test in thereby fossil fuel factor of fossil fuel,
accordance with well- consuming consumption oxidation factor of
recognized international high and related CO2 fossil fuel in each
standards. amounts of emissions boiler in the project.
fossil fuel
Baseline case: Continuation of the current situation; i.e. use of the existing
boilers without fossil fuel switch, replacement of retrofit of the boilers.
Applicability Parameter to be
Baseline case Project Scenario
condition monitored
1. Quantity of fuel
1. Completely Continuation of the Complete
used in the
replace one or current situation; replacement of
boilers;
more boilers i.e. use of the boilers, and/or
with some existing boilers retrofitting of an 2. Quantity of steam
remaining without fossil fuel existing steam produced;
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 277
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Applicability Parameter to be
Baseline case Project Scenario
condition monitored
3. Implement
optional switch
in fossil fuel.
Project Parameter to be
Applicability condition Baseline case
Scenario monitored
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 278
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Project Parameter to be
Applicability condition Baseline case
Scenario monitored
this increase is limited to the project, and fired power 3. Calorific value
15% of the former design undertaking plant. As a and emission
power generation business as usual result, less factor of the
capacity of the whole maintenance. fossil fuel is fuel used in the
plant consumed to project power
generate plant
3. The existing power plant
electricity.
has an operation history 4. Electricity
of at least 10 years and supplied to the
data on fuel consumption grid by the
and electricity generation project power
for the most recent five plant.
years prior to the
implementation of the
project are available
Baseline case: Continuation of the current practise; i.e. the turbine continues
to operate without retrofit.
Project scenario: Retrofitting of steam turbines and gas turbines with
components of improved design to increase the energy efficiency in an existing
fossil fuel power plant.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 279
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Project Parameter to be
Applicability condition Baseline case
Scenario monitored
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 280
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Project Parameter to be
Applicability condition Baseline case
Scenario monitored
3. An official agreement is
required between the
generating facility and
the recipient facility of
energy generated by
project, in case they
are different entities
Under the methodology AM0061, two case studies33 are available wherein
both the projects are registered.
Similarly, under the methodology AM0062, three case studies are available,
wherein two projects are registered and the other one has been rejected.
Further, at present, no projects related to thermal power plant has been
registered in case of other large scale methodologies mentioned above.
It must be noted that none of the Indian R&M projects have attempted to
claim CDM benefits for R&M measures in coal based thermal power plant except
Budge Budge Generating Station, CESC Limited and that too under small scale
methodology. Further, even internationally the exposure of energy efficiency
projects especially related to in R&M of thermal power plants to CDM has been
limited. Nevertheless, successful registration of few of the cases presented
below highlights that possibility for availing CDM benefits do exist.
33
The number of case studies is provided as on 9th July 2013 and the number of projects may
vary with time.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 281
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Table 33: Case Study on Budge Budge Generating Station (BBGS), CESC Limited
http://cdm.unfccc.int/Projects/DB/DNV-CUK1151074102.67/view
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 282
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
natural gas.
Following R&M measures were considered in the scope of CDM:
Table 35: Case Study on Shandong Shiheng Power Plant Energy Efficiency
Improvement Project
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 283
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Reference http://cdm.unfccc.int/Projects/DB/BVQI1343203714.92/view
Emission The emission reductions projected are 72,484 metric tonnes CO2
Reduction equivalent per annum.
Table 36: Case Study on Energy efficiency improvements of Mae Moh Power
Plant through retrofitting turbines in Thailand
Reference http://cdm.unfccc.int/Projects/DB/TUEV-
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 284
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
RHEIN1355199535.37/view
Emission The total emission reductions are 3,94,878 metric tonnes CO2
Reduction equivalent per annum for four years..
Table 37: Case Study on #2 Steam Turbine Retrofit Project of Tianjin Guohua
Panshan Power Plant Co., Ltd
Status of
Registered
project
Reference http://cdm.unfccc.int/Projects/DB/JCI1316688124.05/view
Emission
The estimated emission reduction from the project is 92,463 tCO2e.
Reduction
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 285
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Figure 34: Demand and Supply Imbalance and Declining Prices of CERs
Source: Climate Change, Carbon Markets and the CDM: A Call to Action Report of the High-Level
Panel on the CDM Policy Dialogue, 2012
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 286
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
The above has happened due to market distortions that have crept in
the last few years. However, this has resulted in emergence of several
regional and country based mechanisms that are likely to be available
to promote efficiency improvement.
13.10. Strategies for Monetising GHG Reductions from the R&M measures
The carbon price over the recent years have declined significantly, the
agreements by the Parties to the Kyoto Protocol for the second commitment
period of emission reductions from 2013 2020 is expected to provide the
requisite impetus to the carbon market.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 287
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
other regional or country based mechanisms that may come up in the future.
Therefore, it is important to devise strategies to overcome the challenges faced
by the utilities in monetizing carbon emissions. These are detailed below:
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 288
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
As of now 144 plants have been included under the PAT mechanism and
range of efficiency to be achieved has also been specified. The target provided
as of now is not very stringent and the plants can achieve some of these targets
either by improving their O&M of the plant or by undertaking small R&M works.
Since O&M practises at the plant site especially in the state sector is weak,
significant efficiency can be gained by just improving the O&M. The plants which
have good O&M practices and are already operating at higher efficiency levels
may have to undertake small R&M works to achieve the target.
However it must be noted that plants which achieve higher efficiency vis--
vis the targets will become eligible for ESCerts which can be traded in the
market leading to monetisation of the efficiency gained.
Also going forward, at the end of first PAT cycle, targets are expected to be
further strengthened and achieving targets through undertaking R&M works
would remain the only viable options for the utility.
Indecisiveness from the utilities to undertake R&M works will not only lead to
financial loss to the utilities in the form of penalty paid for non-achievement of
targets but also leads to opportunity loss in terms of benefits that could have
been accrued in case of overachievement of targets.
Thus, these actions of the utilities would enable the country to move towards
low carbon footprints in line with its sustainable development priorities.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 289
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Chapter - 14
Conclusion
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 290
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Climate Change Talks, 2012, it is expected that in the medium to long term
developing R&M/LE projects under such mechanisms would provide an attractive
option to monetize GHG emission reductions. Further, the market trend recently
has also moved towards regional and country level mechanisms to support
efficiency improvement. Plants that have been identified in the PAT scheme can
improve upon the efficiencies of their plants through R&M beyond the target
levels and can become eligible for ESCerts, which can be traded at market
determined prices.
The role of R&M in bridging the demand supply gap through generation
optimisation is well recognised in the Indian context. This is increasingly
becoming more important in view of the shortage of fuel experienced in recent
times and the necessity to optimally utilize this scarce resource. An approach
that balances the risks of various parties involved is much desired.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 291
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Annexure 1
1. Background
1.1 Renovation & Modernisation (R&M) including Life Extension (LE) of
existing old power plants is one of the most cost effective options to
achieve additional generation from these plants in a short gestation
period.
1.2 The importance of R&M was recognised by the Government of India way
back in 1984 when Phase-I R&M Programme for 34 thermal power
stations in the country was launched by the CEA as a Centrally sponsored
scheme. Since then R&M option has been effectively utilised over the
various plan periods. As per the National Perspective Plan of CEA, under
12th Plan, LE works have been identified on 70 thermal units of total
capacity 12,066 MW and R&M works have been identified on 65 units
(17,301 MW) during the 12th Plan.
1.3 Planning and implementing R&M projects is often witnessed by occurrence
of adverse events that can derail the objectives of the project. Identifying
and mitigating project risks are crucial steps in managing successful R&M
projects. Thus, a well structured and documented Risk Management at
each stage of the process is of utmost importance. Mitigation of the
identified risks can significantly alter the risk profile of the R&M projects
making them an attractive proposition for all stakeholders in the sector.
1.4 With the above background, the objective of the guidelines is to provide
direction to the utilities in identifying and addressing the key risks faced in
design and implementation of R&M in the country.
- Generic defects
- Design deficiencies /modifications
- Avoidance of inefficient operation
- Non-availability of spares because of obsolescence of
equipment/components.
- Poor quality of coal
- Major replacements of equipment arising due to unforeseen
failures and /or generation sustenance not covered under
regular O&M
- Stringent environmental regulation
- Safety requirements etc.
2.2 R&M Programme With Life Extension (LE) & Uprating
The equipment subjected to fatigue stresses and creep due to high
temperatures such as turbine rotor and casings, HP piping, boiler headers,
boiler drum, main steam piping and valves, feed discharge lines etc. are
designed for a given fatigue life of about 25-30 years of operation.
However, many equipment/components might become prematurely weak
metallurgically due to various operational stresses like frequent
temperature and pressure excursions, full load tripping, frequent start and
stops etc. and accordingly there is need to check the remaining life of
these components after 20 years of life or 1,60,000 hours of operation
lest it may result into serious failures. A systematic study called the
Residual Life Assessment (RLA) involving non-destructive and destructive
tests help reveal the remaining life of various critical components of plants
and equipment to enable introducing measures to extend the life of the
plant by a further period of about 15-20 years. A RLA study may be
carried out earlier, say after 15 years or 1, 00,000 hrs. of operation if the
plant condition so necessitates and as stipulated in IBR 391 A.
The LE programme is a major event in the thermal power stations
history, as it envisages extension of life over a considerable period of time
beyond its designed life. At this time it is a good practice to examine
whether a plant requires a viable modernization which has not been
carried out earlier so that during the extended life the plant operates
efficiently and delivers the rated or higher capacity with improved heat
rate. Adoption of improved and proven technology can play an important
role in plant upgraded output & higher efficiency. There are cost effective
options to up-rate the machines for higher output and improved
efficiencies thus making it economically viable to integrate life extension
programme with uprating.
2.3 Works Not Relating to R&M / LE
In general, works usually done under routine maintenance and annual or
capital maintenance do not fall under the purview of R&M Programme.
The repetitive nature of activities having the frequency once in five year
or less is covered under O&M. The following works should not be included
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 293
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 294
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
technical studies and tests. This includes the following:- (a) Residual Life
Assessment (b) Complete Condition Assessment (c) Performance
Evaluation Test (d) Energy Audit (e) Past History of Plant (including
maintenance schedules, overhauls and assessment of O&M practices). The
technical evaluation of the plant is followed by the economic evaluation of
the plant to decide on the most optimal option. This includes (a) Plant
retirement (b) Maintain and operate for extended time and retire
subsequently (c) Capital Overhaul and refurbishment (d) R&M and Life
Extension (e) R&M, LE and Up-rating. Detailed Project Report prepared for
assessment of above options also includes a detailed technical and
economic analysis of the identified option. This also includes assessment
of the sources of fund and the phasing required for execution of R&M
option. Based on the technical studies and the option selected for R&M,
the scope of R&M Project is prepared. Before the tenderization process
begins, utility is expected to submit the details of the assessment to the
Appropriate Commission and seek its in-principle approval.
4.3 Planning Stage
Once the scope of the project is finalised, the utility develops the design
specification and proposal package and determines the
procurement/bidding strategy. Planning stage covers the entire bid
process management i.e. issue of tender(s), pre bid meetings, evaluation
of technical and commercial bids, selection of suitable bidder, negotiation
of contracts and award of R&M contracts to vendors/suppliers/OEMs.
4.4 Execution Stage
This stage covers the entire R&M project implementation stage which
begins with the receipt of equipments to the site and planning of
shutdown of unit. This stage includes effective monitoring of work, timely
decision making on bottlenecks faced, ensuring the quality of work,
inspection of material and smooth implementation of work.
Implementation support consultant hired by the utility plays a key role in
managing all the activities covered under this stage through a structured
process.
4.5 Closure Stage
After the R&M work is completed, it is very essential to evaluate whether
the goals and objectives of the R&M project were achieved or not. For this
post-R&M Performance Guarantee Test is conducted. Further, O&M
training is imparted to engineers for efficient operation of the unit that
has undergone R&M.
4.6 The indicative timeframe suggested by CEA in the National Perspective
Plan for Renovation, Modernisation and Life Extension of Thermal Power
Stations(Upto 2016-17) may be adopted for implementing LE&U schemes:
i. Appointment of consultant by utilities - 3 months
ii. RLA / Energy Audit - 6 months
iii. Freezing the scope of work/activities
for LE&U - 3 to 4 month
iv. Preparation of DPR - 6 to 8 months
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 295
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 296
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 297
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
market etc. This should form the basis of the decision i.e. whether to: (i)
Retire; (ii) Maintain and Operate for few years and eventually retire; (iii)
Capital Overhauling and Refurbishment; (iv) R&M and Life Extension; and
(v) R&M, LE and Uprating.
The final decision of R&M should also be considered in consultation with
the Discoms, wherein the refurbished plant should fit with the Discoms
long-term power procurement plan and merit order schedule.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 298
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 300
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
ii. Due to lack of past operating and performance data with the
utility, it may difficult to identify improvement areas for certain
components in the unit/machine as every component cannot be
tested.
iii. Utilities may also not be keen to undertake detailed assessment
as they generally underestimate the importance of data or in
interest of time these studies may be omitted.
iv. Scope of work prepared for carrying out technical studies may
be weakly defined especially for critical plant components
operating in creep and fatigue range. Further, deliverables
based on such technical studies are not defined appropriately by
the utilities
v. In case of multiple units, it is sometime assumed that since both
units are operating under same condition, assessment of any
one of the units would suffice the purpose. This is often done to
save time and cost during the initial stages
c) Impact of Risk
The impact of this risk is reflected in the form of surprises or additional
scope of work at the project execution stage leading to increase in cost
and time of the project.
d) Strategy to Manage the Risk
Comprehensive Studies for the unit planned for R&M should be
mandatory. The scope of the study should cover both the Main
Plant Equipment as well as the Balance of Plant. (Risk Avoidance)
A comprehensive R&M assessment should aim to undertake the following
for each unit being considered for R&M or LE: (i) Data Gathering; (ii) Plant
Walk-down; (iii) Energy Audit; (iv) Pre-R&M Performance Testing; (v)
Residual Life Assessment; (vi) Steam Path Audit; (v) Stress Analysis of
Critical Piping; (vi) Potentially Non-destructive and Destructive
Evaluation; and (vii) Review of O&M Practices.
Additionally, diagnostic studies should also review the procedures, training
system and other similar aspects.
Further, in order, to minimize the impact of this risk it is advisable to
undertake comprehensive R&M assessment for each unit planned for R&M,
and review both the main plant equipment and the BoPs. Also, it is
suggested that project financiers should consider submission of the
reports/results of such studies as a pre-requisite for funding the project.
In this regard CEA has prepared standard documents for carrying out
RLA/CA/EA studies which may be used by the utilities.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 301
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
options and select the best possible option depending upon the conditions
of the plant, financial constraints, etc.
b) Root Cause Analysis
The root causes of the above behaviour are:
i. Poorly defined objectives for undertaking R&M
ii. Focus only on the technical criteria, with limited focus on
financial and economic returns
iii. Limited project appraisal skills
c) Impact of Risk
The above risk leads to selection of sub-optimal option that may result in
unmet objectives and outcomes, and/or higher time and cost.
d) Strategy to Manage the Risk
Comprehensive Identification and Assessment of Options including
computation of financial returns, payback period, shutdown time
required and conformance to the set objectives (Risk Avoidance)
A detailed cost benefit analysis by estimating the net present value (NPV),
rate of return (IRR), payback period and cost-benefit ratio, should be
undertaken by the utility for different options. Analysis should also include
the impact on key parameters such as life, PLF, heat rate, efficiency etc.
Further, the robustness of the selected option should be tested through
scenarios such as time and cost over-run, shortfall in capacity, change in
shut-down, heat rate or a combination of adverse factors. The justification
of the R&M project needs to be established clearly demonstrating that the
R&M project is competitive against all feasible power generation supply
options.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 302
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 303
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 304
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 305
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 306
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 307
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 308
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 309
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 310
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 311
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 312
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 313
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
dispute, hearing of the dispute and the final decision) of the DRC should
be specified in the tender document itself. Any dispute which cannot be
amicably settled between the parties can be referred to the DRC.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 314
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 315
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
documented quality plans are being adhered to. Consultants would also
certify quality of materials and works before the payments are made as
per contractual milestones. The QAC would also be responsible for the
inspection of material quality at the workshop/facility of supplier.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 316
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
5.4.7. Delay in Provisioning of Unit Shut down for Executing R&M works
(Institutional Risk)
a) Risk Description
This risk arises if the utility is unable to schedule timely shutdown for
executing R&M either due to grid conditions or delay in obtaining timely
approvals from the relevant authorities (State Government or Regulatory
Commission) for shutdown of the plant.
b) Root Cause Analysis
Significant energy and peak deficit scenario in most of the states coupled
with lack of planning for procurement of power from other sources inhibits
shutdown of state owned units for executing R&M works.
c) Impact of Risk
The above risk leads to the following:
i. Contractual disputes and delay in execution of work.
ii. Change in baseline parameters due to time gap between the
studies and actual execution.
iii. Deterioration in the material quality already supplied by the
vendor
iv. Deterioration in condition of plant and occurrence of technical
surprises
d) Strategy to Manage the Risk
i. Advance Planning for Scheduling of Shutdown for
Execution of Works (Risk Avoidance)
Shutdown for executing R&M works must be planned well in
advance and distribution utilities must be informed
accordingly.
ii. Additional Allocation of Power to States from
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 317
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 318
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
The above risk leads to the gradual deterioration of the condition and
performance of the plant and hence the gains expected from undertaking
R&M may not be achieved over a longer period of time.
d) Strategy to Manage the Risk
i. Preparation and implementation of O&M action plan on
priority basis and engaging specialized agency for O&M
of the plant, post R&M. (Risk Mitigation)
- O&M practices of the plant should be reviewed at the start
of the project and based on the assessment a long term
O&M action plan like preparation of O&M manuals including
preventive, capital and breakdown maintenance procedure
/ guidelines should be formulated. Further, the plan so
formulated should be approved at the highest authority and
credible actions should be taken to implement the plan on
priority.
- Contractor should revise the existing O&M manual as per
the new system/unit requirements.
- Adequate training should be provided by the contractor
before handing over the plant to the utility.
- The list of mandatory spares along with its unit prices
should be included in the total price of the R&M contract.
This mitigates the financial risk related to procurement of
mandatory spares post R&M of the project.
- Generating company can also outsource O&M of the plant;
post R&M to a specialized agency. There are models
available for participation of private players in O&M.
- Generating company can also include O&M supervision in
the contract of executing agency.
ii. After sale services to be made an integral part of the
contract (Risk Mitigation)
After sale services provided by the vendors should be
considered as an important element during the bidding stage
and support services for some specific period of time (say one
to two years) should be incorporated in the contract.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 319
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 320
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
the project with regular updates about the progress of the project.
(Risk Avoidance)
The need for apprising the regulator about the R&M plan is important as
the recovery of the cost incurred towards R&M is approved by the
Regulator. This involves:
i. Obtaining in-principle approval from the Regulator
ii. Updating the regulator on progress and achievement of critical
milestones
iii. Updating the regulator in case of abnormal or unexpected
changes leading to cost and time overruns
iv. Sharing of information about the outcomes, performance
achieved vis--vis the guaranteed parameters with the
regulator
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 321
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 322
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Annexure 2
Guidelines for Early Identification of Potential Technical
Surprises in R&M Projects and Ways of Addressing Them
1. Background
1.1 Renovation & Modernisation (R&M) including Life Extension (LE) of
existing old power plants is one of the most cost effective options to
achieve additional generation from these plants in a short gestation
period.
1.2 The importance of R&M was recognised by the Government of India way
back in 1984 when Phase-I R&M Programme for 34 thermal power
stations in the country was launched by the CEA as a Centrally sponsored
scheme. Since then R&M option has been effectively utilised over the
various plan periods. As per the National Perspective Plan of CEA, under
12th Plan, LE works have been identified on 70 thermal units of total
capacity 12,066 MW and R&M works have been identified on 65 units
(17,301 MW) during the 12th Plan.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 323
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
regular O&M
- Stringent environmental regulation
- Safety requirements etc.
2.2 R&M Programme With Life Extension (LE) & Uprating
The equipment subjected to fatigue stresses and creep due to high
temperatures such as turbine rotor and casings, HP piping, boiler headers,
boiler drum, main steam piping and valves, feed discharge lines etc. are
designed for a given fatigue life of about 25-30 years of operation.
However, many equipment/components might become prematurely weak
metallurgically due to various operational stresses like frequent
temperature and pressure excursions, full load tripping, frequent start and
stops etc. and accordingly there is need to check the remaining life of
these components after 20 years of life or 1,60,000 hours of operation
lest it may result into serious failures. A systematic study called the
Residual Life Assessment (RLA) study involving non-destructive and
destructive tests help reveal the remaining life of various critical
components of plants and equipment to enable introducing measures to
extend the life of the plant by a further period of about 15-20 years. A
RLA study may be carried out earlier, say after 15 years or 1, 00,000 hrs
of operation if the plant condition so necessitates and as stipulated in IBR
391 A.
The LE programme is a major event in the thermal power stations
history, as it envisages extension of life over a considerable period of time
beyond its designed life. At this time it is a good practice to examine
whether a plant requires a viable modernization which has not been
carried out earlier so that during the extended life the plant operates
efficiently and delivers the rated or higher capacity with improved heat
rate. Adoption of improved and proven technology can play an important
role in plant upgraded output & higher efficiency. There are cost effective
options to up-rate the machines for higher output and improved
efficiencies thus making it economically viable to integrate life extension
programme with uprating.
2.3 Works Not Relating to R&M / LE
In general, works usually done under routine maintenance and annual or
capital maintenance do not fall under the purview of R&M Programme.
The repetitive nature of activities having the frequency once in five year
or less is covered under O&M. The following works should not be included
as a part of R&M / LE programme:
- Infrastructural development work such as township, welfare
measures etc., general civil works within the plant such as
boundary wall, roads, drainages etc. However, technological
structure works required for equipments / structure based on
RLA done as per design criteria (such as turbine deck,
foundation etc.) shall be part of LE.
- Procurement of spare equipments.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 324
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 325
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
R&M of the units: (a) Plant Availability, (b) Plant Load Factor, (c) Auxiliary
Consumption, (d) Emission Factors, (e) Level of Outages, (f) Life of the
plant etc., (g) Frequency of annual overhaul; (h) Frequency of capital
overhaul etc. The diagnosis at this stage is based on available plant
records and design data. No inspections and/or testing of material, plant
or equipment is involved at this stage.
5.2 Assessment Stage
During this stage systematic evaluation of the plant is undertaken through
technical studies and tests. This includes the following:- (a) Residual Life
Assessment (b) Complete Condition Assessment (c) Performance
Evaluation Test (d) Energy Audit (e) Past History of Plant (including
maintenance schedules, overhauls and assessment of O&M practices). The
technical evaluation of the plant is followed by the economic evaluation of
the plant to decide on the most optimal option. This includes (a) Plant
retirement (b) Maintain and operate for extended time and retire
subsequently (c) Capital Overhaul and refurbishment (d) R&M and Life
Extension (e) R&M, LE and Up-rating. Detailed Project Report prepared for
assessment of above options also includes a detailed technical and
economic analysis of the identified option. This also includes assessment
of the sources of fund and the phasing required for execution of R&M
option. Based on the technical studies and the option selected for R&M,
the scope of R&M Project is prepared. Before the tenderization process
begins, utility is expected to submit the details of the assessment to the
Appropriate Commission and seek its in-principle approval.
5.3 Planning Stage
Once the scope of the project is finalised, the utility develops the design
specification and proposal package and determines the
procurement/bidding strategy. Planning stage covers the entire bid
process management i.e. issue of tender(s), pre bid meetings, evaluation
of technical and commercial bids, selection of suitable bidder, negotiation
of contracts and award of R&M contracts to vendors/suppliers/OEMs.
5.4 Execution Stage
This stage covers the entire R&M project implementation stage which
begins with the receipt of equipments to the site and planning of
shutdown of unit. This stage includes effective monitoring of work, timely
decision making on bottlenecks faced, ensuring the quality of work,
inspection of material and smooth implementation of work.
Implementation support consultant hired by the utility plays a key role in
managing all the activities covered under this stage through a structured
process.
5.5 Closure Stage
After the R&M work is completed, it is very essential to evaluate whether
the goals and objectives of the R&M project were achieved or not. For this
post-R&M Performance Guarantee Test is conducted. Further, O&M
training is imparted to engineers for efficient operation of the unit that
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 326
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 327
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
34
This problem is non-existent when one to one replacement of the entire economizer is taken up.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 328
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 329
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 330
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 331
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Civil Work
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 332
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Electrical System
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 333
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 334
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 335
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 336
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 337
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 338
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
CEA has prepared standard documents for carrying out RLA/CA/EA studies
which may be used by the utilities.
9.4.2 Creation of technical surprise plan (Managing Surprises)
A well-defined technical surprise plan should be prepared for effectively
handling technical surprises, as and when they occur35. The design
consultant involved in undertaking comprehensive assessment, DPR and
subsequent scope of work should also prepare a technical surprise plan.
This should be prepared in consultation with the plant level officials
involved in operation, repair and maintenance of the plant to understand
the potential surprises as they have the experience of the actual condition
of the plant. This includes a list of possible surprises, ensuring availability
of spare parts to minimize delays, addressing upfront the likely
contractual aspects of additional supplies and works etc. Further, this
should also include the unit rates for equipment/parts and total financial
implications of the same. In this regard CEA has prepared standard
documents for Detailed Project Report (DPR) which may be used by the
utilities.
9.4.3 Creation of Dispute Resolution Mechanism (Managing Surprises)
Due to the occurrence of technical surprise there may be disagreement
between the utility and vendor on certain aspects which may translate
into disputes and affect overall execution of work. Therefore, in order to
resolve disputes between the contractor, sub-contractor and utility, it is
important to create a Dispute Resolution Mechanism. Under this
mechanism a Dispute Resolution Committee (DRC) should be formed at
the start of the project with fair participation from both utility and
contractor. In this regard, CEA has prepared standard bid documents
which may be used by the utilities.
9.4.4 Creation of dedicated R&M Cell and Engaging Specialised
Consultants (Preventive)
In order to effectively deliver a successful R&M project, the following steps
are required:
i. Creation of dedicated R&M cell by the utility at the
headquarter and at the plant
In order to effectively deliver on the R&M project it is important
to create a separate R&M cell with adequate and dedicated
manpower for the project. This team should involve plant level
officials dealing with the different departments like Boiler,
Turbine, Electrical, C&I, CHP, Milling system and AHP etc.
Further, officials having prior R&M experience should also be
included in the team.
To ensure timely decisions and approvals within the organization
it is important that a dedicated R&M cell should also be formed
35
The first aim in all earnest should be to minimize the occurrence of technical surprises.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 339
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 340
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 341
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 342
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Annexure 3
List of R&M/LE Plants for Estimating GHG Reduction
Potential
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 343
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 344
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 345
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 346
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 347
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 348
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 349
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 350
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
References
1. National Perspective Plan for Renovation, Modernization and Life Extension of
Thermal Power stations (up to 2016-2017), Central Electricity Authority,
December 2009.
9. Presentation on India Power Sector Case for Plant Life Extension with
Energy Efficient R&M, Mr. Sarajit Sen, Managing Director, Power Service,
Doosan Power Service India Pvt. Ltd., Conference on Renovation &
Modernization of Power Plants: New Delhi, October, 2011.
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 351
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
October 2008.
14. Report on Renovation and Modernization of Power Plants in India- USD 6.5
Billion Opportunity, Infraline Energy, April 2012
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 352
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
September 2009.
26. Costs and Effectiveness of Upgrading and Refurbishing Older Coal-Fired Power
Plants in Developing APEC Economies, APEC Energy Working Group, Expert
Group on Clean Fossil Energy (APEC study), June 2005.
27. IEA 2012( a), Key World Energy Statistics, International Energy Agency, 2012
28. IEA 2012(b), CCS RETROFIT - Analysis of the Globally Installed Coal-Fired
Power Plant Fleet, International Energy Agency, 2012
29. IEA 2011, CO2 Emissions from Fuel Combustion, International Energy Agency,
2011
30. ECOFYS 2011, International Comparison of Fossil Power Efficiency and CO2
Intensity, Study by ECOFYS for Mitsubishi Research Institute, Japan, 2011
31. Reducing CO2 Emissions by Improving the Efficiency of the Existing Coal-fired
Power Plant Fleet, National Energy Technology Laboratory, July 2008
33. www.romelectro.ro/romelectro/en/...thermal/a1-a3-turceni-rovinari
35. Joint Implementation Project Design Document Form Version 01; Turceni
Energy Efficiency Project; Document Version Number 4; 17 January 2007
36. http://www.eturceni.ro/date_gen.htm
37. http://www.eturceni.ro/desulfurare.htm
38. http://en.wikipedia.org/wiki/prun%c3%a9%c5%99ov_power_station
39. http://www.cez.cz/edee/content/file/investori/equity-investors-august-
2008.pdf
40. http://www.vitkovicepower.cz/default/file/download/id/12966/inline/1
41. http://www.mzp.cz/c1257458002f0dc7/cz/news_tz_100318_dnv/$file/100317
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 353
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
%20final%20report%20%203rd%20party%20assessment%20dnv.pdf
42. http://www.ispe.ro/en/references/casestudies/energy_power_generation/10_t
urceni_tpp_rehabilitation_4x5.html
43. Belchatw - Retrofitting the EUs Largest Power Plant Site; 2012
44. 858 MW supercritical extension for Belchatow: Poland's largest and most
efcient lignite-red plant; October 2007
48. Complex Renewal of the Tusimice II Power Plant (4*200 MW); Skoda Praha
Invest
50. www.babcock.com/library/pdf/br-1885.pdf
51. www.slthermal.com/pdf/suralaya,%20indonesia.pdf
52. http://www.thefreelibrary.com/b%26w+subsidiary+awarded+contract+to+up
grade+boilers+at+indonesia+power...-a0192354813
53. http://www.powerengineeringint.com/articles/print/volume-20/issue-
10/features/turn-something-old-into-something-new.html
57. Project appraisal document on a proposed loan in the amount of eur 280
million (USD 336 million equivalent) to ELEKTHK WTIM (EUAS) with the
guarantee of the republic of turkey for the report no: 35747-tu electricity
generation rehabilitation and restructuring project; May 5,2006
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 354
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
59. http://wwwwds.worldbank.org/external/default/wdscontentserver/wdsp/ib/20
06/02/06/000160016_20060206153650/rendered/pdf/35162.pdf
60. An Alstom Integrated boiler and Turbine Retrofit Project to increase unit
output and efficiency; Alstom Annual Conference 2007
62. http://www.alstom.com/south-africa/projects/arnot/
63. Coal-Fired Power Plant Heat Rate Reductions, Sargent & Lundy LLC study,
January 2009
66. Retrofitting of Coal-Fired Power Plants for CO2 Emission Reductions, MIT
Energy Initiative Symposium, March 2009
67. http://www.eia.gov/countries/analysisbriefs/indonesia/indonesia.pdf
68. http://energyindonesia.com/03dge/0120720%20electricity%20development%
20in%20indonesia.pdf
70. Energy Policies of IEA countries, The Czech Republic, 2010 Review
71. Yearly report on the operation of the Czech Electricity Grid for 2011, Energy
Regulatory Office
73. http://bankwatch.org/our-work/projects/coal-fired-power-plants-poland
74. http://www.marketinfo.dk/index.php/markets/romania/energy-sector-romania
75. http://www.kpmg.com/ro/en/issuesandinsights/articlespublications/factsheets
/audit/documents/romanian_energy_market_factsheet_en_.pdf
77. http://wwwwds.worldbank.org/external/default/wdscontentserver/wdsp/ib/20
06/05/15/000160016_20060515185428/rendered/index/e1307.txt
78. http://www.eia.gov/countries/analysisbriefs/turkey/turkey.pdf
79. http://www.eskom.co.za/content/gx_0001genplantmixrev13.pdf
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 355
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
80. http://cigrasp.pik-potsdam.de/countries/833900607/energy_profile
81. http://www.eia.gov/countries/cab.cfm?fips=sf
82. http://www.info.gov.za/otherdocs/2008/nationalresponse_sa_electricity1.pdf
84. PAT - Perform, Achieve and Trade, Ministry of Power, Government of India,
July 2012
85. The Future Context of the CDM, Vivid Economics, July 2012
87. State and Trends of the Carbon Market, Carbon Finance at the World Bank,
May 2012
91. Cleaner Power in India Clean Coal Technology Roadmap, December 2007
92. National Action Plan on Climate Change, Government of India, June 2008
93. http://cdm.unfccc.int/projects/db/dnv-cuk1324273859.59/view
94. http://cdm.unfccc.int/projects/validation/db/1gi6f47dwy1k8rzl0br7x4li3s7df1/
view.html
95. http://cdm.unfccc.int/projects/db/jqa1302517640.25/view
96. http://cdm.unfccc.int/projects/db/jci1316688124.05/view
97. IEA and CIAB 2010, Power Generation from Coal Measuring and Reporting
Efficiency Performance and CO2 Emissions, IEA and Coal Industry Advisory
Board 2010
99. Recommendations on Operation Norms for Thermal Power Stations for Tariff
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 356
CENTRAL ELECTRICITY AUTHORITY AF MERCADOS EMI
100. CO2 Baseline Database for Indian Power Sector, CEA, 2012
101. CEA study titled Mapping of 85 pulverized coal fired thermal power
generating units in different states, Evonik Energy Services India, under
Indo-German Energy Program
102. CEA Published Performance Review of Thermal Power Stations for 2008-09,
2009-10 and 2010-11
103. Tariff Orders for different years by various State Electricity Regulatory
Commission
104. Tariff Petitions for different years by various State Generating Companies
106. CEA 2009, National Perspective Plan for Renovation, Modernization and Life
Extension of Thermal Power stations (up to 2016-2017), Central Electricity
Authority, December 2009
107. Climate Change, Carbon Markets and the CDM: A Call To Action Report of the
High-Level Panel on the CDM Policy Dialogue, 2012
Report on Reduction of Barriers to R&M Interventions in Thermal Power Stations in India 357