Distillation
Distillation
Trouble-free design of
refinery fractionators
A review of factors most frequently the cause of distillation towers falling short
of design objectives. Analysis of case histories provides guidelines for identifying
potential troublespots in the most important fractionators
Henry Z Kister
Fluor Corporation
A
two-phase survey was recently refinery fractionators,
completed by Fluor of all the case and these form the
histories related to malfunctions in basis for the current
refinery towers that have been document- analysis.
ed over the last 50 years. Altogether, 400 As with other Fluor
case histories were found in the literature. surveys, certain
The first phase identified the most com- ground rules were
mon root causes of problems in refinery applied to limit the
fractionators (towers), but did not exam- scope. Only specific
ine the troublespots in each specific ser- incidents were
vice. This phase yielded general included. For exam-
guidelines for trouble-free design, but did ple, a statement such
not address issues related to each specific as “leakage from
fractionator. chimney trays in
In the second phase, case histories of refinery vacuum tow-
tower malfunctions are analysed specifi- ers can be reduced by
cally for each of the major refinery frac- seal-welding” does
tionators. Each case history teaches a not constitute a case Figure 1 Uplifted packing in wash section of a vacuum tower
lesson. Together, these lessons are the best history. On the other
tool for understanding the potential trou- hand, a statement such as “one vacuum It clearly shows that the vacuum tower is
blespots in each service, and for drawing tower experienced severe chimney tray by far the most troublesome refinery ser-
guidelines for trouble-free design of each leakage at low-rate operation. Seal weld- vice, which is where the survey begins.
service. ing tray sections reduced leakage to
I have previously described the Fluor acceptable levels” does. Vacuum tower malfunctions
survey methodology in Distillation Opera- Also, incidents of corrosion and foul- The 86 case histories reported for the vac-
tion (McGraw-Hill, New York,1990). All ing were included only if a feature unique uum tower is almost double the number
the case histories used as a basis for the to the column design, operation, or con- reported for the atmospheric crude tower,
survey were extracted from the published trol contributed to their occurrence. For which is the next most troublesome refin-
literature. There were 900 total cases, of instance, an incident where the wrong ery tower. When a vacuum tower per-
which 400 were for refinery towers. In corrosion inhibitor or antifoulant was forms poorly, valuable distillate is lost to
about one quarter of these, the specific applied does not qualify as a case history the resid, and poor distillate quality poi-
service was not stated or the service was in this survey. A case where fouling was sons FCC catalyst. The wash section of
one that did not have enough cases caused by insufficient liquid flow, maldis- the fractionator is the most critical sec-
reported on to permit detailed analysis. tribution, or poor process control, does. tion and also one where most of the mal-
This left about 300 cases for the main Finally, optimisation case studies
(where capacity was raised or pressure Top causes of vacuum tower
Fractionator malfunctions drop lowered by replacing trays by pack- malfunctions
ings) are outside of the scope of the sur-
Number of vey. The objective of the current survey is No. Description Cases
cases to identify the issues that make towers fall
1 Damage 27
1. Vacuum towers 86 short of achieving these design capacities.
2 Coking 21
2. Atmospheric crude fractionators 45 There is some overlap in the tabulation
3 Intermediate draws 17
3. Debutanisers 37 of cases for each fractionator. For 4 Misleading measurements 10
4. FCC main fractionators 33 instance, a coked chimney tray case study 5 Plugging 9
5. Deethanisers 23 will be listed once under “coking” and – Installation mishaps 9
6. Depropanisers, C3/C4 splitters 22 another time under “intermediate draws”. – Abnormal operation (startup,
7. Alky main fractionators/isostrippers 17 This means that adding the individual shutdown, commissioning) 9
8. Coker main fractionators 15 malfunctions may yield a number greater 8 Maldistribution 6
9. Naphtha splitters 11
than the number of malfunctions report- – Weeping 6
10. Deisobutanisers 8
ed for the service. Table 1 lists the main 10 Condenser 4
11. Amine towers 8
fractionators surveyed and the concise
Table 1 number of cases reported for each service. Table 2
109
P T Q AUTUMN 2003
w w w. e p t q . c o m
MASS TRANSFER: DISTILLATION
Table 3 Figure 3 Coking of fouling resistant grid in the wash section of a vacuum tower
110
P T Q AUTUMN 2003
MASS TRANSFER: DISTILLATION
111
P T Q AUTUMN 2003
MASS TRANSFER: DISTILLATION
112
P T Q AUTUMN 2003
MASS TRANSFER: DISTILLATION
113
P T Q AUTUMN 2003
MASS TRANSFER: DISTILLATION
tion, and pressure control. Plugging and There is a distinct link between the or pan causing liquid to bypass a once-
coking can be alleviated by providing ade- feeds and reboiler draw arrangements. through thermosiphon reboiler (two
quate on-line wash facilities near the top Both constitute “points of transition”, ie, cases); a reboiler tube leak and slug flow at
of the fractionator, by using plugging- where a stream enters or leaves the tower. the reboiler outlet pipe.
resistant trays there, and by preferring These points of transition are some of the Slightly behind, with six case histories, is
shed decks or disk and donut trays to grid major troublespots in a tower. The lesson tower flooding by excess base level. Two of
in the wash section. Shed decks and disk for debutanisers is that all points of transi- these resulted from the type of reboiler
and donut trays are far less sensitive to tion need to be critically examined for problems previously discussed. False level
vapour or liquid maldistribution than potential bottlenecks, both at the design indica tions led to two others, and frothing
grid, and therefore far less prone to cok- (or debottleneck) and when trouble- or foaming at the tower base led to the
ing during upsets. shooting. remaining two. Clearly, the lessons learned
Startups and shutdowns are major are that troubleshooting and trouble-free
issues in FCC main fractionators, and a Deethaniser malfunctions debottlenecks of C3/C4 splitters should focus
good design of these needs to hazop what The strippers and absorbers are included in on the reboiler piping and the bottom
can go wrong and take preventive mea- the deethaniser malfunctions. Topping the sump.
sures. Intermediate draws and liquid dis- list (Table 9) with six case histories are Similar to debutanisers, depropanisers
tributors are the weakest links in the reboiler draw and return arrangements. and C3/C4 splitters have experienced a high
internals design, and need to be designed Three of the six cases report excessive pres- number of vapour cloud releases, mostly
and inspected carefully, not just left to sure drop in the process inlet or outlet due to line rupture (three cases), but also
others. Finally, pressure controls as well as pipes of a kettle reboiler. The high-pressure due to poor blinding or plugging/freeze ups
liquid flow control to the wash section drop either caused the tower base liquid of valves. Some major blasts resulted. The
are major considerations in these frac- level to rise above the reboiler return inlet, vapour cloud lessons described under
tionators. or back liquid up on the chimney tray feed- debutanisers extend to depropanisers and
ing the reboiler to the top of the chimneys. C3/C4 splitters.
Debutaniser malfunctions Insufficient heat during coke drum
Due to similar functions, stabilisers and switchover was reported in two cases, one Other fractionators
depentenisers have been lumped together of them due to weeping from the draw tray For other refinery fractionators, the num-
with debutanisers. Over 70% of the cases, to a once-through thermosiphon reboiler. ber of case studies reported was less than
however, were contributed by debutanis- Four case histories were reported of base 20, a sample too small for a detailed anal-
ers. level exceeding the reboiler return. Two of ysis. Nonetheless, some observations are
Table 8 shows that the most common these were due to high-pressure drop in significant and require more detail, includ-
malfunctions experienced in debutanisers the kettle piping (those previously men- ing coker main fractionators, alky unit
are widely different from those experi- tioned), the other two due to absence of or main fractionators/isostrippers, naphtha
enced in the vacuum, crude and FCC frac- to poor level indication. As with debu- splitters, deisobutanisers and amine
tionators. Topping the list with 10 case tanisers, control issues are also important absorbers/regenerators.
histories is controls, an item that showed in deethanisers, and account for four case A total of 15 malfunction case histories
low down (if at all) on the main fraction- histories. Also, with four case histories, of coker fractionators have been report-
ator malfunctions list. Of the 10 cases, five component accumulation in deethanisers ed. Of the 15, seven described fouling by
reported difficulties with pressure and con- is a problem. coking or carryover of coke, while five
denser controls. In all five, a total con- Either ethane or water or both accumu- others described damage due to water-
denser was used with partial flooding of late and can lead to cycling, capacity bot- induced pressure surges. There is no
the condenser. In two of the five, the prob- tlenecks, and in the case of water, also doubt that coking and water-induced
lem was induced by presence of non-con- corrosion. Finally, choking of side draws pressure surges are the major issues with
densables. Composition control or the with entrained gas bubbles has been a these fractionators.
assembly of a control system contributed problem in four case histories. A total of 17 malfunctions have been
the other control case histories. The lessons learned from this documen- reported for alky unit main
Vapour cloud release and installation tation are that the points of transition in fractionators/isostrippers. Of these, four
mishaps share the second spot in Table 8. deethanisers (the side draws as well as the described plugging, mostly by scale or cor-
Three of the five case histories of vapour region below the bottom tray, including rosion products; three described explo-
clouds ended in explosions, and one more the reboiler draw and return lines) require sions, either due to vapour cloud release or
in a fire. Some of these were accompanied thorough design, review, and inspection, due to HF carryover in the hydrocarbons
by injuries and heavy damage. Line frac- and must not just be left to others. Preven- and a violent reaction in a caustic bed
ture (two incidents), poor blinding (two tion of component accumulation and care- downstream; and three others described
incidents), and freeze-ups in leaking ful review of the control systems are also accumulation of either ethane or water in
valves (two incidents) were some of the prime considerations that make the differ- the overhead system.
contributing factors. Hazops of debutanis- ence between a troublesome and trouble- A total of 11 naphtha splitter malfunc-
ers should consider some of the lessons free deethaniser. tions have been reported. Four of these
learned from previous vapour cloud reported plugging, mainly by scale and cor-
releases to positively eliminate further Splitter malfunctions rosion products; three reported reboiler
accidents. Malfunctions in C3/C4 splitters also include issues; two were a result of poor installa-
With four case histories, poor feed depropanisers other than those in alky tion; and two reported control problems.
arrangements closely follow, leading to a units, which are uniquely different (Table Control problems with other refinery
capacity bottleneck or an efficiency loss in 10). Similar to deethanisers, reboiler draw fractionators have also been reported. For
the feed region. Also with four case histories and return arrangements lead the list with example, of the eight total deisobutaniser
are reboiler draw arrangements, including seven reported cases. Again, the main prob- malfunctions that have been reported, six
vapour entrainment choking the reboiler lems have been excess pressure drop in involved control problems. Five of these
draw lines and liquid leaking from a trapout inlet and outlet lines of a reboiler causing were temperature control issues that can
tray to a once-through thermosiphon base liquid level to exceed the reboiler be particularly troublesome with narrow-
reboiler, thus “starving” the reboiler. return inlet (two cases); leaking draw tray boiling mixtures.
114
P T Q AUTUMN 2003
MASS TRANSFER: DISTILLATION
115
P T Q AUTUIMN 2003