Mil STD 785b
Mil STD 785b
Mil STD 785b
com
MIL-STD-?85B
15 Septaber 1980
SUPERSEDING
MIL-STD-?85A
28 March 1969
MILITARY STANDARD
RELIABILIfl PROGRAM
FOR
MIL-STD-785B
5 September ~980
DEPARTMENT OF DEFENSE
Washington, D. C. 20301
MIL-STD-785B
MIL-STD-785B
15 September 1$180
FOREWORD
Many of the tasks solicit facts and recommendations from the contractors
on the need for, and scope of, the work to be done rather than requirinq that a
specific task be done in a specific way. The selected tasks can be tailored :0
meet specific and peculiar program needs.
Although no: all encompassing, the guidance and ratiamale pra~ided ir~
Appendix A is intended to serve as an aid in selectinq and scopinq the tasks
and requirements.
iii
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 September 1980
CONTENTS
f=aawah
1. SCOPE.. . . . . . . . . . . c
1
1.1 Purpose. . . , . . s c 1
1.2 Applicability . . . . . . . . c c 9 . 1
1.3 Method of reference . . . . . . . 1
2. REFERENCED DOCUMENTS . . . . . 9 9 1
4. GENERAL REQUIREMENTS o . . . . . 4
TASK DESCRIPTIONS . . c . . * . ~ o , 6
5.
100-1 - 100-2
Downloaded from http://www.everyspec.com
?41L-STD-785B
15 September 1980
200-1 - 200-2
300-1 - 300-2
APPENDIX A
m 1
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 September 1980
30 DEFINITIONS A-1
vi
. w w *
- ,..
m t m m ---
Downloaded from http://www.everyspec.com
MIL-STD-785B
IS Septmber 1980
TABLES
vii
Downloaded from http://www.everyspec.com
MIL-STD-785R
Is September ~9U()
1. SCOPE
2. REFERENCED DOCUMENTS
STANDARDS
MILITARY
1
Downloaded from http://www.everyspec.com
HIL-STD-785B
15 September 1980
PUBLICATIONS
MILITARY HANDBOOK
b.
P41L-STL735P
15 September1980
The
maintenance manpower (e.g., !4ean-Time-Between-WintenanceActions(NTEMA)).
other system reliability Parameters shall employ clearlv defined subsets of all
item life units and all failures.
I I ANU 2.urrLALna 1 1
Downloaded from http://www.everyspec.com
MILSTD-785B
15 Sept-ber 1980
4. GENERAL REQUIREMENTS
4
Downloaded from http://www.everyspec.com
M~L.$TD.795~
15 Seotember 1980
.
phases of the systeca/subsystem/equipment
acquisition.
5
Downloaded from http://www.everyspec.com
MIL-STD-785B
1S September1980
.
5. TASK DESCRIPTIONS
5.1 The task descriptions following are divided into three ueneral sections:
Section 100, Program Surveillance and Control; Secticm 200, Design and
Evaluation;and Section300, Developmentand Production Tcstinu.
Custodians: PreoarinfgActiVltv:
Army - CR Air Force - 11
Navy - As
Air Force - 11 Project RELI-0008
Review Activities:
Army - AR, AV, AT, ME, MI, SC, TE
lia~ - EC, OS, SA, SH, YD, TD, MC, CC
Air Force - 10, 13, 17, 18, 19, 26, ?5
Downloaded from http://www.everyspec.com
!UL-STD-795F
TASK SECTION 100
15 September 1980
100-1
I 9
Downloaded from http://www.everyspec.com
..
MIL-STD-785B
TASK SECTION 100
15 September 1980
. . . . .
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 September wao
CASK101
101.2.1 A reliabilityprogram plan shall be prepared and shall include, but not
be limited to, the following:
TASK 101
15 September ?980
101-1
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 September 1980
TASK 101
75 September :983
101-2
Downloaded from http://www.everyspec.com
MIL-sTD-T85E
15 September 1980
TASK 102
102,1 ~ The purpose of task 102 Is to provide the prtie contractor d~d
PA with appropriate surveillance and management control of
Subcontractors/suppliersreliability programs so that timely managment action
can be t~ken as the need arises and program progress is ascertained. -
102,2.1 The contractor shall insure that system elements obt~ined from
s~ppllers will meet reliability requirements. This effwt sh~ll app2J tc C?E
items obtained from any supplier whether in the first or any subsequent tier,
or whether the item is obtained by an Intra-company order fran .Anyelement of
the contractors Organization. All subcontracts shall include provisions fcr
review and evaluation of the suppliers reliability efforts by the Pr~e
contractor, and by the procuring activity at their discretion.
102.2.2 The contractor shall assure, and advise the PA, that his
subcontractors and suppliers reliability efforts are consistent ti.thGverall
svsta requirements, And that provisions we made for surveillance of their
reliability activities, Tne contractor sh~l, 4s ~ppropri~te:
TASK 102
: September IGt!j
Downloaded from http://www.everyspec.com
?41L-STD-785B
15 September 1989
production and deployment of the hardware. This support may include failure
analyses and corrective action for fa~ures occurringIn the tots use
environment, if specified under 102.2 herein.
TASK102
15 September 1980
102-2
-...._ . .._. .
I .- - -.-,
m
Downloaded from http://www.everyspec.com
MIL.STD-785B
15 September 1980
TASK 103
PROGRAM REVIEUS
103.2.2 The reviews shall identify and discuss all pertinentaspects of the
reliabilityprogram such as the following,when applicable:
(a) Reliabilitymodeling
(b) Reliabilityapportionment
(c) ReliabQlty predictions
(d) F14ECA
(e) Reliabilitycontont of specification
(f) Design guidelinecriteria
(g) Other tasks as identified.
(3) Partsprogramprogress
(4) Reliabilitycritical items program.
b. .
.
TASK 103
15 September 1980
703-1
==-=--=--..--=
Downloaded from http://www.everyspec.com
MIL-STI)-785B
15 September 1980
(6) PHECA
c. At QAauJlsv pr~ .
(1) Discussion of those items reviewed at PDRs and CDRS
~~ ~
(~) Reliabilityanalyses status, prlmarlly prediction
e.
TASK 103 .
15 September 1980
193-2
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 September 1980
e. Delivery identification
of any data itaa required.
103-3
Downloaded from http://www.everyspec.com
MIL-STD-?85B
15 Septaaber 1980
TASK 103
;5 September ?98CI
Downloaded from http://www.everyspec.com
MIL-STD-785B
IS Sepember 1980
TASK 104
104.2.3 The closed 100p gyst~ g~l ticl~e ~ovigiong to a99We that
effective corrective actions are taken on a timely basis by a follow-up audit
that reviews all open fal.lurereports, fafiure analyses, and corrective action
suspense dates, and the reporting of delinquencies to management. The failxe
cause for eaeh failure shall be clearly stated.
104.2.5 The contractor~s closed loop failure reporting syst~ data shall be
transcribed to Gover~ent forms only if specifically required by the procwing
activity.
TASK 10U
15 September 1980
104-1
Downloaded from http://www.everyspec.com
PUL-STD-785B
15 September Ig80
TASK l13h
15 September 1?80
?04-2
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 September 1~80
TASK 105
105.3
TASK ?05
15 September ?980
105-:
. . .
Downloaded from http://www.everyspec.com
MIL-sTD-785B
15 September Ig80
TASK 105
15 September 198~
105-2
!41L-STD-T85B
15 September 1980
TASK 201
RELIABILITY MODELING
201,3
a. Imposition of tasks 202 and 203 as requisite tasks in the FSED phase,
TASK 201
15 September 198G
201-1
. . ..
Downloaded from http://www.everyspec.com
..
tlxL-sTD-785B
15 Septaober 1980
201-2
Downloaded from http://www.everyspec.com
y&L-sTD-785E
d September ?98?
TASK 202
RELIABILITY ALLOCATIONS
a. Imposlt$on of tasks 201 and 203 as requisite tasks in the FSED phase.
TASK 202
15 September !S80
Downloaded from http://www.everyspec.com
MIL-sTD-785B
15 %ptanber 1980
.
TASK 202
15 September 1980
202-2
!IIIL-STD-T85B
15 September 1980
TASK 203
RELIABILITY PREDICTIONS
203.Z!.l.l Failure rates other than those established at contract award may De
used only upon approval of the pMCWiW activitY*
203.2.1.3 When the individual part operating conditions are defined, the
prediction procedure in section 2 of MIL-HDBK-217, or PA approved alternative,
shall be umed.
203.2.1.4 If the part type and quantity 1s the only Infoneation available, the
prediction procedure of section 3 of MIL-HDBK-217, or PA approved alternative,
shall be wad.
203.2.2 predictions for electronic equipment shall be made using one of the
two methods contained in MXL-HDBK-217, or alternatives approved or provided by
the PA. Predictions for mechanical, electrical, and electro-mechanical
equlpnnt shall be made wirg either contractor data w alternatives, both of
which shall require PA approval.
TASK 203
15 Sept=ber 1980
203-1
Downloaded from http://www.everyspec.com
IUL-STD-785B
IS Septauber 1980
203.3
.
203,3.1 Details to be specified In tho SOW shall Include the fallowing, as
applicable:
a. Imposition of WSka 201 and 202 as requisite taske in the FSED phase.
TASK 203
15 Sept-ber 1980
203-2 .
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 September 1980
TASK 204
204*2 ~
TASK 204
15 September :980
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 Sept-ber 1980
TASK 204
15 Saptember ?980
204-2
MIL-STD-785B
15 September 1980
TASK 205
205.3
TASK 205
15 September 198c
205-1
Downloaded from http://www.everyspec.com
HIL-STD-785B
15 Septanber1980
.-
IAX 205
15 September 1980
205-2
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 September 1980
TASK 206
206.2 ~
206.2.1 Parts/circuits tolerance analyses shall be conducted on critical
circuitry as defined in the ccmtract, These analyses shall verify that, given
reasonable combinations of within-specification characteristics and parts
tolerance buildup, the circuitry being analyzed will perform within
specification performance. In making these analyses the contractor shall
examine the effect of cwlponent parasitic parameters, input signal and power
tolerances, and impedance tolerances on electrical parameters, both ;:n::rcdu~~
nodes (c-ponent interconnections) and at input and output points.
of the stated factors may not be significant to all circuits, only the critical
factors for that circuit shall be considered.
206.3
TASK 206
15 September 198o
206-1
--- . . . .
Downloaded from http://www.everyspec.com
HIL-sTD-785B
IS Sept-ber 1980
TASK 206
15 September198o
206-2
Downloaded from http://www.everyspec.com
MXL-STD-785B
15 September 1980
TASK 207
PARTS PROGRAM
207.1 UREQSL The purpose of task 207 Is to control the selection and use
of standaml and nonstandard partst
207.3
Contractor/supplier
participationh the GIDEP programper
MIL-s%-1556.
TASK 207
15 September 198C
207-1
--===-.
_._=__
_~a==_.~=====._=_._._=_.~._.
-====-=.=--e .--. .
_____~>_ ~ -_-_-=_=-G.._-= . . .
. . . ..
Downloaded from http://www.everyspec.com
PIIL-STD-785B
15 September 1980
TASK 207
15 September 1980
207-2
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 September 1980
TASK 208
208.1 ~ The purpose of task 208 la to ldentlfy and control those items
which require special attention because of complexity, application of
advanced state-of-the-art techniques, and the tipact of potential failure on
safety, readiness, mission success, and demand for maintenanceiloglstics
support.
208.3
TASK 208
15 September1980
208-1
--
HIL-STD-785B
15 Sept-bar 1980
state-of-the-art techniques.
(10) The it- does not have sufficient history of its own, or
similarityot other Itas having danonstrated high reliability, to provide
confldmoe In its rellabUty,
TASK 208
15 September 1980
208-2
Downloaded from http://www.everyspec.com
MIL-sTD-7851?
15 September 1980
TASK 209
20g.2 ~
209.2,1 Procedures shall be established, maintained, and implemented to
detenalne by test and analysis, or estimation, the effects OF storage,
handlhg, paakag~ng, transportation? mtinte~ance~ and ~wated exwa~e to
functional testing on the design and reliability of the hardware. The results
of this effort shall include items such as:
The reaulta of this effort shall be used to support long term failure rate
predictions, design trade-offs, definition of allowable test exposures, retest
after storage decisions, packaging, handling, or storage requirements, and
refurbishment plans.
209.3
TASK 209
IS Sept-ber 1980
209-1
Downloaded from http://www.everyspec.com
HIL-STD-785B
15 Septaber 1980
TASK 209
15 September 1980
209-2
Downloaded from http://www.everyspec.com
MIL-STD-785B
TASK SECTION 300
15 September 1980
300-1
.
Downloaded from http://www.everyspec.com
MIL-STD-785B
TASK SECTION 300
15 September 1980
300-2
.
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 September 1980
TASK 301
301.2.4 The results of ESS testing during development shall be analyzed and
wed as the basis for the ESS procedures to be speclfled for production.
301.3
TASK 301
IS September 1980
301-1
. __=_. .
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 Septaaber 1980
TASK 301
15 September 1980
301-2
Downloaded from http://www.everyspec.com
MIL-STD-785B
15 September 1980
TASK 302
302~2 ~
302.2.2 A TAAF test plan shall be prepared and shall include the following,
subject to PA approval prior to initiation of testing:
TASK 302
15 September 1g80
302-1
Downloaded from http://www.everyspec.com
MUATD-785B
15 Sept~ber 1980
J. FRACX3
302.2.3 As specified by the procuring activity, the TAAF test plan shall be
submitted to the procuring act%vlty far its review and approvd.a This plan, as
approved, shall be incorporated into the contract and shall beoome the basis
for contractual canplianmc
TASK 302
15 Sept~ber 1980
302-2
.-.
Downloaded from http://www.everyspec.com
MIL-STD-785B
IS September 1980
TASK 303
303.2 ~
c. Test durat$on and the appropriate test plan and test environments,
The test placiand test environments (if llfeimission profties are not specified
by the PA) shall be derived from MIL-STD-781. If It is deemed that alternative
procedures are more appropriate, prior PA approval shall be requested with
sufficient selection rationale to permit procuring activity evaluation.
303.2.3 DetaUed test procedures shall be prepared for the tests that =e
Included in the RQT plan.
303.2.4 As specified by the procuring activity, the RQT plan and test
procedures shall be submitted to the procuring activity for its review and
approval. These documents, as approved, shall be Incorporated into the
contract and shall become the basis for contractual compliance.
303,3
TASK 303
15 September ,9c3
Downloaded from http://www.everyspec.com
?41L-STD-785B
15 Septauber 1980
TASK 303
?5 September ;980
Downloaded from http://www.everyspec.com
MXL-STD-765B
15 September 1980
TASK 304
304.2 ~
c. Test duration, test frequency, and the appropriate test plan and test
environments. The test plan and test environments (if mission profiles are not
specified by the PA) shall be derived from MILATD-781. If it is deemed that
alternative procedures are more appropriate, prior PA approval shail be
requested with sufficient selection rationale to permit procuring actlv~ty
evaluation.
304.2.3 DecaiLed test procedures shaAi be prepared for Che tests that are
included in the PRAT pl~ or the equipment specification.
304.2.4 As spec$fied by the procuring activity, the PRAT plan amd ~rocedurea
shall be submitted to the procuring activity for its review and approval.
These aocuments, as approved by the procuring acClvity, shall be incorporated
tito the contract and shall become the basis for contractual compliance.
TASK 304
15 SepCember 138G
304-1
Downloaded from http://www.everyspec.com
PJIILSTD-785B
IS September 1980
TASK 304
15 Septe@ber 1980
304-2
Downloaded from http://www.everyspec.com
MIL-STD-785P
APPENDIX A
15 September 1980
APPENDIX A
10. GENERAL
10.1 ,%@D@ This appendix providesrationale and guidance for the selection
of tasks to fit the needs of any reliabilityprogram, and identifiesapplicable
data items for Implementationof reouirti tasks.
10,3 ~ The user of this appendix may include the Departmentof Defense
procuringactivity, Government in-houseactivity, and prime contractor,or
subcontractor,who wishes to impose reliabilitytasks uoon his supolier~s).
20. REFERENCEDDOCUMENTS
30. DEFINITIONS
Reference llIL-STD-785
basic.
A-1
----.
-----,=---
--
Downloaded from http://www.everyspec.com
MIL-STD-785B
APPENDIX A
15 September 1980
40.1.2 Once appropriate tasks have been selected, the tasks themselves can be
tailored as outlined in the Details To Be Specified By The PA. It is al~o
important to coordinate task requirements with other enqinerinq suoDort grouDs,
such as Logistics Support, System Safety, et cetera, to eliminate duplication
of tasks and to be aware of any additional information of value to reliability
which these other groups can provide. Finally, the ti!uinqand depth required
for ach task, as well as action to be taken based on task outcome, are largely
dependent on individual experience and program requirements. For these
reasons, hard and fast rules are not stated.
A-2
Downloaded from http://www.everyspec.com
7ABLE A-x.
I PRCGRAM PHASE I
TASK TITLE ASK
TPt CONCEPT VALID I FSE: I PROC I
TOLERANCE ANALYSIS I
1 I
207 PARTS PROGRAN ENG s ,
208 RELIABILITY
CRITICAL
KTMS m s(l)
209 EFFECTS OF FUNCTIONAL TESTING, EM NA ~(l)
STORAGE, NANDLING, PACKACING,
TRANSPORTATION, AND MAINTENANCE
304 PROMJCTIOM
RELIABILITY
ACCEPTANCE ACC NA NA
ACCEf?ANC& TEST (PRAT) PROGRM
JAauxtE
NA - NOT APPLICABLE
A-3
Downloaded from http://www.everyspec.com
HIL-STD-785B
APPENDIX A .
15 September 1980
50.1
50.1.1
A-4
Downloaded from http://www.everyspec.com
!lIL-sTD-785B
APPENDIX A
15 September 1980
dvisable at this time. The apportionment and the estimate procedures should
be repeated until reasonable apportioned values are obtaln~d. The
apportionment should be frozen orior to the contractors awarclinqsubcontracts
which have firm reliability requirements.
50.1.1.2.2 Reasons for the disparity between the apportioned and the
estimated valuds of the reliability critical items should be investigated.
Discussions of these reasons and tentative wavs to attain the acmortioned
values, (ea., relaxed performance requirements, either more or less deslun
redundancy, additional environmental protection), should be held with
appropriate project personnel. The object of the investizatlons and
discussions is viable recommendation(s) for action to overcome the
deficiencies. A significant benefit which can be eained from this process is a
consensus on, and a wide awareness of, the soeciflc equipment which is
considered reliability critical. When systems or equipment Derformartce
requirements create a wide and irreconcilabledisparltv between aooortion~d and
stimated values of required reliability, the procurinu authority shall
challenge the perfommnce requirements. Elimination of less essential
equipment functions can reduce equipment complexity and siqnlficantlv enhance
reliability.
A-s
._
.=__
___
_._. =.__.___.
___ _
Downloaded from http://www.everyspec.com
MIL-sTI)-785B
APPEND_-XA
1S September 1980
50.1.2
A-6
Downloaded from http://www.everyspec.com
50.1.2.3 W* r~ (F~ r)
Early elimination of failure causes 1s a major contributor to
reliability growth and attaininu acceptable field reliability. The sooner
failure causes can be identified, the easier It is to implement effective
corrective action. As the desiun, documentation and Dr?li!ninarvhardware
mature, corrective action can still be identified, but its ifuDlementation
A-7
Downloaded from http://www.everyspec.com
?HL-STD-785B
APPENDIX A
15 September 1980
50.1.2.4 ~ F th =au~slt~onof
expensive, complex, or critical systems or equipment it may be necessary and
desirable to formalize FRACAS proceedings to the extent of having them
controlled by a FRB.
50.1.2.4.1 The addition of this task to a reliability program will orovide the
procurinq activity with further assurance of tight control of reporting,
analysis, and corrective actions taken on Identified failures. It should be
noted, however, that in some instances the application of this task may
duplicate QA tasks under ?41L-O-9858and may not be cost effective or in the
best interests of the overall proqram. l%erefore, a survey should be made bv
the procuring activity to determine the need for application of this task.
A-8
Downloaded from http://www.everyspec.com
IIIL-STD-785B
APPENDIX A
15 September 1980
50.1,3 ~
50.1.3.1.4 When all the necessary planning for a reliability procramhas been
ccomplished, it should be clocum?ntedas a reliability procraa!plan (task 101).
A reliability program plan is normally submitted as part of the contractors
response to the procuring activitys request for proposals. After mutual
agreement has bean reached and procuring activl.tyapproval has been granted,
the reliability program plan must be made a part of the contract. Since ?tie
plan is a contractual tool used to evaluate the contractors Feliabilitv
program, it should be kept current, subject to procuring acti71ty approval.
A-O
Downloaded from http://www.everyspec.com
!41L-STD-785B
APPENDIX A
1S September 1980
50.1.3.2.1 While almost all tasks described in this standard can be Derformed
at varying levels of detail during any acquisition DhaSe, it is incumbent uDon
the procuring activity reliability monitor to ensure that only essential tasks
are specified, to avoid wasting resources. The procuring activity and the
contractor should critically appraise what has, or what will have been
achieved, at given milestones. For example, as the transition between FSED and
PROD approaches, judgments reqardina reliability tasks duri~ pr~uction must
be made. In some instances, only some kind of minimal testing will be
required, while in other instances, a substantial number of FSED tasks will
need to be continued, along with some testinq. yet other cases may call for a
reliability gromh proqram or perhaps a Dhase-uniouc task such as PRAT. (The
FSED-PROD transition point was chosen for illustrative purposes. Similar
reasoning applies whenever program change mints occur or are anticipated.) lt
is not the purpose of this paragraph to match a set of tasks ulth everv
conceivable set of program circumstances. Rather, its puroose is to emphasize
that the reliability monitor must assess and project accomplishments, determine
what still needs to be accomplished to achieve reliability requirements, and
then tailor a program to meet those requirements.
Downloaded from http://www.everyspec.com
?JIIL-sTD-795e
APPENDIX A
15 %$DtWIIbt2r
19fi0
50.2 00
50.2.1 ~
A-1
_=_._._.._._
..=
_._=
.--A_...m - ___ _ -= = - _ _ -.
-. ._=_= _.=_= _.=_=__=._____._<e. .-._<~__==___-=G~=
Downloaded from http://www.everyspec.com
MIL-STD-785B
APPENDIX A
15 September 1980
50.2.2.1.1 The basic information for the reliabUlt~ model 1s derived from tne
functional (schematic) block diagrams. The diagrams depict functional
relationships of subsystems and ccmocnents available to Drovicle the reauired
performance. The reliability model reorients the diagrams into a
series-parallel network shoulng reliability relationships amonq the various
subsystems and components. (The authenticity of the functional relationships
depicted by the diagrams should be checked by a failure modes, ffects, and
criticality analysis.)
50.2.2.1.3 The model should be continually expanded to the detail level for
which planning, mission, and system definition are firm. The expansion need
not be to the same level for all functions until desiqn definition is comDlete.
In the interim, more detail should be added to the model as it becomes
available so that evaluations may proceed aoace with program decisions.
50.2.2.1.4 Together with duty cycle and mission duration information, the
model is used to develop mathematical expressions or computer proqrams which,
with appropriate failure rate and probability of success data, can provide
A-12
Downloaded from http://www.everyspec.com
MIL-STD-785B
APPENDIX A
15 Seotember 1980
50.2.2.2.4 After the lower level reliability requirements are defined, thev
should be levied on the responsible equipment en~ineers (contractor and
subcontractor) for all hardware levels. Without sneclfic reliabiiltv
requirements which must be desiqned to or achieved, reliability becomes a vauue
and undefined general objective for which nobody is responsible. From another
perspective, program progress can be measured by valuating defined reliabil~tv
requirements at a given milestone/ti!neperiod with what has actuallv been
accomplished.
MIL-STD-785B
APPENDIX A
15 September 1980
requirements.
50.2.2.3 ~
A-14
Downloaded from http://www.everyspec.com
50.2.2.3.3.1 Eauioment
level predictions usin~ part failure rates: (1) provide a basis for
Identifying design, part selection/annlicationand environmental oroblem
areas, (2) provide early indicationof capability to meet the reliabiiitvtest
requirement, and (3) are essential inDuts to svstern/subsystemlevel
predictions(50.2.2.3.3).
A-l?
Downloaded from http://www.everyspec.com
MIL-STl)-785B
APPENDIX A
15 Sept&iiber1980
50.2.3 ~
50.2.3.1 (F=) (~?o Q)L
A F14ECA1s a powerful tool to optimize the perfom8ance/llfe cyole cost tradeoff
between mission reliability and basic reliability at the blaok box/component or
major subsystan level, where these tradeoffs are most appropriately analyzed
and evaluated. Potential design weahesses are identified through the use of
engineering schematics and mission rules to systematically identify the likely
modes of failure, the possible e~fects of @ach failure (which may be different
for each life{misalon proftie phase), and the crltluality of eaoh effect on
safety, readiness, mission wcoess, d~d for maintenanoeilogistlcs support,
or some other outcome of significance. A reliability criticality number may be
assigned to each failure mode, usually based on failure effect, severity, and
probability of occurrence. These numbers are sometimes used to estabUsh
corrective action priorities, but beoause of the subjective judgment required
to establish them, they should be usd only as indicators of relative
priorities. FM.ECAcan also be uoed to confirm that now fa$lure modes have net
been introduced in transforming schematics into production drawings.
50.2.3.1.1 The lnltial FMECAcan be done early In the CONCEPT phase, and
becauae only limlted design deftiAtton may be avafiable, only the more obvious
failure modes may be identified. It till, houevcr, identify many of the single
failure points, sow of tilah oan be eliminated by a Sch-tic re~rW~ent
As greater mission and design definitions are developed in VALID and FSED
phases, the analysis can be expanded to successively more detall~ levels and
ult~tely, if requtied, to the part level. Additionally, for non4etectable
failures, the analysls should be carried further to determine the effect of a
Woond failure (e.g., double-point failure). Where non4etectable failures
cannot be eliminated, soh.duled maintenance procedures may have to be modified
to mlnlmlze their probability of occurrence. Non-duteutable failures (e.g.,
check VdV4JS, wel.ght-on-uheelssultches, et cetera) are often overlooked by
analysis and the F?4ECAshould be carried out far enough to consider the overall
effect on the total syst~. Ulth regard to one-shot systems, it may be
Partlcuhrly desirable to analyze manufacturing documentation such as circuit
board layouts, wire routings and connector keying to determine if new fallxe
modes have been introduced that ~re not in circuit schematics.
A-16
Downloaded from http://www.everyspec.com
MIL4TD-785B
APPENDIX A
15 September 1980
50.2.3.1.4 Becauae of the many and varied skills required to determine failtme
modes, effects, corrective action, etc., the FMECA requires inputs from many
diaciplineg. For this reason, it is relatively unimportant which engineering
grouP is 80i90t@d to make the and.ytis. What i9 important is the critical
examination of the results by all disciplines which could have useful knowledge
that oan be brought to bear on the analysis. The analys~s is most effective
when made as the design progreme~, i.e. , it is a working toOlo It 13
therefore more cost effective to review the analysia prior to formal
publication and at scheduled Program Reviews!.
A-17
Downloaded from http://www.everyspec.com
HIL4TD-785Ei
APPENDIX A
15 September 1980
50.2.3,3 Becau9e of
within-specificationpart tole;ance buildup, an output frcm a circuit,
subassembly, or equipment may be outside spec values and therefore
unacceptable. In such cases, fault isolation will not identify any part as
fatied or input as unacceptable. To preclude the existence of this condition,
a pUts/CUctita tolerance analysis la conducted. This analysis examines, at
component titerconnectlons and Input and output points, the effects of
partsicircuits electrical.tolerances and parasitic parameters over the range of
specified operatl.ngtemperatures. This analysis has proven coat effective h
identifying equipment perfomaancelreliabilityproblem areas so they oan be
corrected prior to production.
50.2.4.1 . A
system which can tolerate failures and still successfully complete a mission
has a higher MCSP than one which must abort-following a failure. System,
subsystem, or equipment designs which have this attribute are somet~s tailed
failure tolerant, Statements which establish the specifics of such tolerance
are called failure tolerance criteria.
A-18
Downloaded from http://www.everyspec.com
bA~L-sT~-755p
A?PENDIX A
15 Sebtember 19eo
50.2.4.1.1 These criteria provide standards for design compliance, and snaoe
~ub~ystem architecture. They are usually found in several elates in weaDon
system and subsystem speciricatlons. Tvpicai of such criteria is the following:
nA single failure in any ~ub~y~teqj shall not Cauge or reauirea TliSSiOn abort,
and durina an abort the single malfunction or failure of a subsvstem or
component shall not cause loss of the crew. Criteria such as these in~luence
the design and operation of almost all subsystems, and therefore an oraanized
approach is required to meet them. The compliance attained by this ~DWrOaCh
will use a minimum of added redundancy and comlexity. It must be realize~
that failure tolerant design techniques U!3uallyincrease comDlexitv and totai
number of Darts: reduce basic reliability (~~F), maintenance-re~at@d
reliability (MTBMA), and louistics-related reli.ablity(YTBR~; and thus usJa:l/
increase both acquisition cost and cost of ownership.
50.2.4.1.2 Compliance with the mission success criteria can best be determined
by examining functional diaurams, systems schematics, and software
specifications and documentation in the liaht of mission rules and
requirements. Particular attention should be paid to providina uowe~ from
different sources (where feasible) to redundant or alternative means of
accomplishing a function. Eesides different oower sources, conslderati~n
should also be given to the use of different conneetorslwtrinc Dins, a?vsical
separation/orientation,and different software for redundant equipments. b~r~
generally, careful scrutiny is required to identify and avoid arranze~ents
which can invalidate the functional redundancy provided.
50.2.~.2.l Parts and components are the basic items comnrlsine hi~+er level
assemblies, which in turn ultimately constitute the system, where the svstem
may be a radio, a space satellite, or a nuclear submarine. Significant
contributions toward system optimization can be realized by applying attention
and resources to parts application, selection, and control startinq arlv ir
VALID phase and continulnq throughout the life of the system,
50.2.4.2.2 The decisisns as te the deuth and extent of the aarts ar~zram
designed for a particular item acquisition should be made based on
considerations of factors such as: fni33ioncriticality, Dar:3 es~ent:ali:v :2
successful mission completion and reduced frequency of maintenance),
maintenance concept, production quantity, oarts availability, aacuntfdegre? z:
A-19
Downloaded from http://www.everyspec.com
MIL-STD-785B
APPENDIX A
15 September 1980
b. Parta standardization
A-20
Downloaded from http://www.everyspec.com
MIL-STD-7859
APPENDIX A
15 Seoternber198c
50.2.U.2.7 Parts proqram activities are interrelated with all other analyses
described in this document, and with analyses performed by other disciplines
such as safety, qu~ity enqineerinq, maintairiability,survivzibiiitvand
vulnerability. Any of these analyses can indicate the need for different parts:
upqraded or uniaue, in some cases, to meet system requirements; standard or
readily available parts, in other cases, to minimize system life cvcle costs
and ensure suooortability.
A-21
Downloaded from http://www.everyspec.com
HIL-STD-785B
APPENDIX A
15 September 1980
A-22
Downloaded from http://www.everyspec.com
MIL-STD-785B
WPENDIX A
15 September 1980
50.3
50.3.1 ~
A-23
Downloaded from http://www.everyspec.com
PUL-STD-785B
APPENDIX A
15 September 1980
A-24
Downloaded from http://www.everyspec.com
MIL-STD-785B
APPENDIX A
15 September 1980
50.3.1,4.2 Reliability values measured during ESS and the early portion of
RDGT cannot be expeoted to correlate with reliability values in service.
Reliability values measured dur~ng the final portion of RDGT, and both ROT And
PRAT, must be correlated with reliability values in service, by optimum test
redlsm and clear traeeabilty between test and field measurements. Al1
relevant test data must be used to project operational reliability for
e~t~te~ of operational ePfeotiveness (readiness and mission success) and
ownership cost (maintenancemanpowr costs and logistic support cost). Only
chargeable test results shall be used to detexmine contractual compliance with
qwntltatiwe reliability req~ements.
A-25
Downloaded from http://www.everyspec.com
MIL-STD-785B
APPENDIX A
15 September 1980
test plan for ROT or PRAT shall be based on the amount of confidence gained
(the degree that confidence Lntervals are reduced) by each additional increment
of testing. For example, a test that stops at the first failure leaves a wide
range of uncertainty; testing to the fifth or sixth failure dramatically
reduces that mcertainty; but testing beyond the eighth or ninth failure buys
very lzttle in terms of increased confidence or reduced risk. Finally,
speclf:ed oonfidenoe levels, discrimination ratios, and decision risks shall be
subject to tradeoffs with total test time and uost, to inulude impact cost of
program schedule delay,
50.3.1.6.1 Probability ratio sequential test (PRST) plans are only intended to
cietexminecompllanae (accept or rejeot) on ths bas~ ef predetermined deoision
risks. They are not intended b provide esthatos of demonstrated rellablllty,
and they leave no decisions to the PA once they have been specified. PRST
Plans contain significant uncertainties in regard to actual test time.
Therefore, if program cost and mhedule are based on the expected decision
Pointw, rather than the ha.xinnm allowable test ttiem, specification of a PRST
will build in potentiti cost and schedule overruns that the PA cannot control.
in general, PRST plans may be used for PRAT, if only a simple aaccept or
reJect* dec$slon is desired and if schedule uncertainty is not a major concern,
but they should not be used for RQT.
50.3.1.6.2 Fixed-length t~st plans should-be specif$ed when actual test time
must be subject to PA control, and when something more than a simple accept or
reject decision i3 desired, For example, the PA may wish to specify a
ftied-length test, assess the data as it becomes available, and make an early
accept decision on the basis of measured test results to date. (Reject
decisions based on real-t- data assessment are not rec~nded, because they
may require changes in the contract. ) Fixed-length test plans may also provide
a basis for strwturing inaentive fees. For example, the contract may state
that ba8e price uIH be paid for those items having a demonstrated reliability
(~int estimate) within a spoclfied range; that an $ncentlve fee will be P&d
for reliability above that range; that penalty or remedy till be required for
reliability below that range, and that Items having demonstrated reMabilLty
below a minimm acceptable (obgemed) v~ue will not be purchased by the
government. These provisions may also apply to production lots,
A-26
Downloaded from http://www.everyspec.com
MILATD-785B
APPENDIX A
15 September 1980
141L-STD-785B
APPENDIX A
15 September 1980
the PA should specify a minim= test time per Item, a falJure-~ee interval,
and a maximum test time per item (after which that Item wfil be considered too
worn out by the test to be a deliverable item). The contractor must not be
penalized for the nmbar of failures discovered during ES, but must be
required to correct every faUur*, and to prevent recurrence of fafiures
through u8e of more rel$able parts and the reduction of workmanship errors
d~l.ng the manufacturing process.
5od3.2cl,2 ESS must not be confised with PRAT. ESS employs less expensive
test facilities, and is recommended for 100% sampling. PllATrequires a more
reallstio simulation of the life profile, and more expens3ve test facilities,
and therefore Is not recommended for 100S sampling. ESS must be conducted by
the oontraotor, ~fie PRAT must be independent of the contractor if at all
possible. Uhere the statlztlcal test plans for RQT or PRAT are based on the
exponential distribution (constant fatlure rate), MS is a prerequisite for RQT
and PRAT, because those test plans assume that early failres have been
eliminated,
50.3.2,2 RDCT is a
phnned, pre-quaUfioation, test-analyze-and-fixprocasa, in which equipments
are tested mder actual, simulated, or accelerated envknments to disclose
design deficiencies and defects. Thh test~rg Is Intended M provide a basis
for early Inuarporation of uorrmtivo autioos, and verification of their
effectivenosa, thereby praotlng reliabflty growth. Howovor:
TESTING DOES NOT IMPROVE RELIABILITY. ONLY CORRECTIVE ACTIONS THAT PREVENT THE
RECURRENCE OF FAILURES IN IWE OPERATIONAL XWIMTORY ACTUALLY XMPROVE
RELIABILITY,
A-28
Downloaded from http://www.everyspec.com
MILSTD-785B
APPENDIX A
15 September 1980
50*3*3 ~
TESTING TEN ITEMS FOR TEN HOURS EACH IS NOT EQUIVALENT TO TESTING ONE ITEM FOR
ONE HUNDRED HOURS, REGARDLESS W ANY STATISTICAL ASSUMPTIONS TO THE CONTRARY.
A-29
Downloaded from http://www.everyspec.com
WLaTD-?85B
APPENDIX A
15 Septanber 1980
statement of precisely who will conduct this test on behalf of the government
(50.3.1*7)* The requirements and submittal schedulefor these document must be
in the CDRL.
50.3.3.2 PRAT is
intended to simulate in-service evaluation of the delivered it- or production
lot. It must be operationally realistic, and may be required to provide
estimates of demonstrated reliability. The statistical test plan must
predefine criteria of c-plhnce (naccept-) which llmit the probability that
the item tested, and the lot It represents, may have a true reliability less
than the minimum acooptable reliability, and these criteria must be tailored
for cost and soheduleefficiency. PRAT may be reqtied to provide a basis for
positive and negative financial feedback to the contractor, in lieu of an
in-aervioe warranty (50.3.1.6). Because it must sim-ulatethe item life profile
and operational envlroment, PRAT may ~equlre rather expensive test facilitie~;
therefore, all-equipment PRAT (100% sampling) is not recommended. Because it
must provide a basis for doterminlng oentractural ccxpliance, and because it
applles to the items aotually delivared to qaratlmal forces, PRAT must be
independent of the supplier $f at all possible (50.3.1.7). Finally, even
though sapling freqwncy should be reduced after a production run is well
established, the protection that PRAT provides for the government (md the
!mtivat$on it provides for the contractors quality control program) should not
be dixarded by cauplete waiver of the PRAT requirement.
A-30
m
1
Downloaded from http://www.everyspec.com
MXL-STE-785B
APPENDIX A
15 September 1980
60,1 The following is a l$st of data Item descriptions associated with the
reliability tasks specified herein:
60.2 The following tasks have DIDs associated with them related to imposition
of t41L-STD-781C:
302,
303, DI-R-7033 Plan, Reliability Test
304
303,
304 DI-R-7035 Procedures, ReliabilityTest and Demonstration
NOTES: (1) Only data items specified h the CDRL are deliverable. Therefore,
thoso data requirements identified j.nthe Reliability Program Plan mu9t a190
appear in the CDRL,
(2) The PA should mvlew all DIDs and assure through tailor~, that
the preparation Instructions in the DID are compatible with task requirements
as specified in the SOW.
A-3?
-.. .
. .
Downloaded from http://www.everyspec.com
ASD/ENESS
Wrxght-Patterson AFB, O 45433
Downloaded from http://www.everyspec.com