Chapter 5
Chapter 5
Chapter 5
Typical methods:
Pollution prevention
Waste minimization
Wastewater treatment at source
2- Preliminary treatment
Objective of Treatment:
1. To remove or reduce size of large solids to protect
equipment.
2. To remove immiscible liquid such as oil and grease
3. To reduce fluctuations in flow and concentration
4. To adjust pH
5. To remove other constituents such as heavy metals
Typical methods:
Treated wastewater (receiving waters)
Solids (land application , landfills)
Preliminary
treatment
Introduction
Head works: refers to the unit operations that are placed at
the upstream end of the wastewater treatment plant
(WWTP). These include the pumping station, flow
measurement, and a group of unit operations (preliminary
treatment).
Typically WWTPs are designed so that flow through the plant
is by gravity. The wastewater frequently is carried to the
WWTP by gravity.
Flow measurement is an essential component of the
operation management of the WWTP.
Design Considerations for Pump Station
Pumping station is the location where pumps are installed.
There may be only one pump, or several pumps.
The pumps may be connected in parallel or in series.
In parallel connection, the discharges of all the pumps are
combined into one. Thus, pumps connected in parallel
increases the discharge from the pumping station.
Pumps connected in series increase the total head output
from a pumping station by adding the heads of all pumps.
Although the total head output is increased, the total output
discharge from the whole assembly is just the same input to
the first pump.
Section and plan views of a sewage pumping station
Fig. 5.2 Plan and section of pumping station showing parallel connections
(a)
(b)
Fig. 5.4 Performance curve of centrifugal pump
Table 5.1
Flow Measurement
The two most common flow measuring devices used for
wastewater are the Parshall flume and the magnetic flow
meter.
Parshall flume
5.1
5.2
Where,
v = velocity, m/s
n = coefficient of roughness, unit less
R = hydraulic radius, m
= cross-sectional area of flow, m2
Wetted perimeter, m
Example 5.1:
Design the channel for the bar rack for a towns W.W.T.P.
Assume the following:
Average flow rate at design capacity = 37,000 m3/d
Peak factor = 2.8
Approach velocity at average flow rate 0.4 m/s.
Approach velocity at peak hour flow rate at design capacity
0.9 m/s.
Slope of channel is 0.0001 m/m.
Width of channel is equal to Parshall flume inlet (1.6 m).
Two channels will be provided for redundancy, but one
channel must handle the flow for the peak hydraulic flow rate.
Freeboard = 0.6 m.
Bar rack Design.
5.3
The approximate number of bars is:
5.4
5.5
Example 5.2
Estimate the head losses for a bar rack for Towns W.W.T.P
shown in example 5.1 with clean bar rack and with partial
blockage of the screen. Use the following assumptions:
1. Mechanically cleaned bar rack.
2. Bar width = 15 mm.
3. Bar spacing = 20 mm.
4. Angle from vertical = 300
5. Differential head loss for activation of the cleaning rakes is
150 mm.
6. Maximum flow area blockage to initiate continuous
operation is 50%.
Bar Rack Design.
5.6
5.6
Example 5.3
Design a screen for the W.W.T.P of the town, if the following
data are given:
Population equivalent (PE) = 10000 capita
Water usage (q) =225 L/capita.day
Flow through velocity at the peak flow = 0.57 m/s
The depth of the water at the maximum flow = 0.8 m
The dimensions of the screenings trough (hopper) are:
Length = 1.15 m
Width = 0.5 m
Depth = 0.3 m
Note: use the design criteria of the Malaysian guidelines for
the developers, volume IV, 1998. Slide 18
Grit Chambers
5.8
Aerated grit chambers
5.9