WR WQ Pub Design Criteria Ch12
WR WQ Pub Design Criteria Ch12
WR WQ Pub Design Criteria Ch12
12.1.1 Definition
12.1.2 Total Systems Approach To Design
12.1.3 Recycle Streams
12.1.4 Multiple Units
12.1.5 Sludge Pumps
12.1.6 Sludge Piping
12.3 Thickening
12.3.1 General
12.3.2 Gravity Thickeners
12.3.3 Flotation Thickeners
12.3.4 Centrifugal Thickeners
12.3.5 Other Thickeners
12.4 Conditioning
12.4.1 General
12.4.2 Chemical
12.5 Digestion
12.6 Composting
12.7.1 General
12.7.2 Sludge Drying Beds
12.7.3 Mechanical Dewatering
12.1 General
12.1.1 Definition
Sludge is a broad term used to describe the various aqueous suspensions of solids
encountered during treatment of sewage. The nature and concentration of the
solids control the processing characteristics of the sludge. Grit screenings and
scum are not normally considered as sludge and therefore are not discussed in this
section.
Multiple units and/or storage facilities should be provided so that individual units
may be taken out of service without unduly interrupting plant operation.
12.1.5.1 Capacity
12.1.5.3 Type
12.1.6.3 Cleaning
Provision should be made for draining and flushing suction and discharge
lines. Where sludge pumps are available, piping should be such that
suction lines can be backflushed with pump discharge or rodded.
Glass-lined or equivalent pipe should be considered for raw sludge piping
and scum lines.
The sludge production rates listed in the literature have often been shown to be
underestimated. The sludge production rates (SPR) listed below in Table 12-1
have been determined from various studies and provide a more realistic basis for
designing solids handling facilities. These values shall be used for design unless
other acceptable data is submitted.
Table 12-1
Sludge Production Rates
(lb sludge)
Type of Treatment SPR ( lb BOD removed)
12.3.1 General
12.3.1.1 Capacity
12.3.1.2 Septicity
Tank depth shall be sufficient so that solids will be retained for a period
of time needed to thicken the sludge to the required concentration and to
provide storage for fluctuations in solids loading rates.
The thickener should be operated to avoid denitrification. At least two
feet of freeboard shall be provided above the maximum water level.
The engineer shall provide the design basis and calculations for the solids
and surface loading rates and the support calculations upon request.
Thickener solids loading rates vary with the type of sludge. Some typical
solids loading rates are given below in Table 12-2. These values shall be
used for design unless other acceptable data are submitted. For loading
rates of other type sludges, refer to Table 5.2 of the EPA Process Design
Manual-Sludge Treatment and Disposal.
Table 12-2
Solids Loading Rate
Primary 20-30
Activated sludge 5-6
Trickling filter 8-10
Primary and activated combined 6-10
Primary and trickling filter combined 10-12
Surface loading rates of 400 gallons per day per square foot (gpd/sq ft) or
less will normally result in septic conditions. To prevent septic conditions,
surface overflow rates should be maintained between 500 and 800 gpd/sq
ft. For very thin mixtures or WAS only, hydraulic loading rates of
100-200 gpd/sq ft are appropriate. An oxygen-rich water source, such as
secondary effluent, shall be available as a supplemental flow to the
thickener to achieve the necessary overflow rates.
Bottom slopes shall be sufficient to keep the sludge moving toward the
center well with the aid of a rake. Generally, the slope should be greater
than conventional clarifiers. A floor slope of 2-3 inches per foot is
recommended.
The engineer shall provide the design basis for sizing the units and for the
support calculation. Design sizing should be based on rational
calculations, including: total pounds of waste sludge anticipated, design
solids and hydraulic loading of the unit, operating cycle in hours per day
per week, removal efficiency, and quantity and type of chemical aids
required. Flotation thickeners are normally sized by solids surface
loadings.
Typical design loadings range from 1.0 to 2.5 pounds per hour per square
foot. (See Table 12-3, for typical solids loading rates to produce a
minimum 4% solids concentration.)
Waste activated
sludge (WAS)
Air 0.42 up to 2.0
Oxygen 0.6 - 0.8 up to 2.2
Primary + trickling
filter 0.83 - 1.25 up to 2.5
12.3.4.1 Pretreatment
Solid bowl decanter centrifuges require grit removal in the feed stream
and are a potentially high maintenance item.
The engineer shall provide the design basis for loading rates and support
calculations. Both hydraulic and solids loading rate limitations should be
addressed.
12.4 Conditioning
12.4.1 General
12.4.2 Chemical
12.5 Digestion
12.5.1.1 General
(iii) toxics (volatile acids, heavy metals, light metal cations, oxygen,
sulfides, and ammonia)
b. Multiple Units
c. Depth
(i) Slope
The tank bottom shall slope to drain toward the withdrawal pipe. A slope
of between 1 inch per foot and 3 inches per foot is recommended.
At least two access manholes should be provided in the top of the tank, in
addition to the gas dome. One opening should be large enough to permit
the insertion of mechanical equipment to remove scum, grit, and sand. A
separate side wall manhole should be provided at ground level.
(iii) Safety
Multiple sludge inlets and draw-offs and multiple recirculation suction and
discharge points should be provided to facilitate flexible operation and
effective mixing of the digester contents, unless adequate mixing facilities
are provided within the digester. One inlet should discharge above the
liquid level and be located at approximately the center of the tank to assist
in scum breakup. Raw sludge inlet points should be located to minimize
short-circuiting to the supernatant drawoff.
a. General
Where the composition of the sewage has been established, tank capacity
should be computed from the volume and character of sludge to be
digested. The total digestion tank capacity should be determined by
rational calculations based upon factors such as volume of sludge added,
its percent solids and character, volatile solids loading, temperature to be
maintained in the digesters, and the degree or extent of mixing to be
obtained. These detailed calculations shall be submitted to justify the
basis of design.
Where composition of the sewage has not been established, the minimum
combined digestion tank capacity outlined below shall be provided. Such
requirements assume that the raw sludge is derived from ordinary
domestic wastewater, a digestion temperature is maintained in the range of
85 to 100 F, there is 40 to 50 percent volatile matter in the digested
sludge, and that the digested sludge will be removed frequently from the
process.
For heated digestion systems providing for intimate and effective mixing
of the digester designed for a constant feed loading rate of 150 to 400
pounds 1,000 cubic feet of volume per day in the active digesting unit.
The design average detention time in completely mixed systems shall have
sufficient mixing capacity to provide for complete digester turnover every
30 minutes.
Where solids data are not available, the following unit capacities shown in
Table 12-4 for conventional, heated tanks shall be used for plants treating
domestic sewage.
The capacities should be increased by allowing for the suspended solids
population equivalent of any industrial wastes in the sewage. The
capacities stated apply where digested sludge is dewatered on sand drying
beds and may be reduced if the sludge is dewatered mechanically or
otherwise frequently withdrawn.
Table 12-4
Cubic Feet Per Capita
Moderately Completely
Mixed Mixed
Type of Plant Systems Systems
Primary 2 to 3 1.3
Primary and
Trickling Filter 4 to 5 2.7 to 3.3
Primary and
Activated Sludge 4 to 6 2.7 to 4
For small installations (population 5,000 or less) the larger values should
be used.
a. General
All portions of the gas system, including the space above the tank liquor,
storage facilities, and piping shall be so designed that under all normal
operating conditions, including sludge withdrawal, the gas will be
maintained under positive pressure. All enclosed areas where any gas
leakage might occur shall be adequately ventilated.
b. Safety Equipment
e. Waste Gas
Waste gas burners shall be readily accessible and should be located at least
50 feet away from any plant structure, if placed near ground level, or may
be located on the roof of the control building if sufficiently removed from
the tank. Waste gas burners shall not be located on top of the digester.
The waste gas burner should be sized and designed to ensure complete
combustion to eliminate odors.
g. Metering
Gas meters with bypasses should be provided to meter total gas production
and utilization.
12.5.1.5 Heating
a. Insulation
Digestion tanks should be constructed above the water table and should be
suitably insulated to minimize heat loss.
b. Heating Facilities
Hot water coils for heating digestion tanks should be at least 2 inches in
diameter and the coils, support brackets, and all fastenings should be of
corrosion-resistant material. The use of dissimilar metals should be
avoided to minimize galvanic action. The high point in the coils should be
vented to avoid air lock.
c. Heating Capacity
(iii) Thermometers
a. Piping Size
b. Withdrawal Arrangements
(iv) Sampling
Problems such as shock organic loads, pH, and high ammonia levels
associated with digester supernatant shall be addressed in the plant
design. Recycle streams should be bled continuously back to the
treatment process.
The size and number of aerobic sludge digestion tank or tanks should be
determined by rational calculations based upon such factors as volume
of sludge added, its percent solids and character, the degree of volatile
solids reduction required and the size of installation with appropriate
allowance for sludge and supernatant storage.
The volatile solids loading shall be in the range of 0.1 to 0.2 pound of
volatile solids per cubic foot per day.
c. Dissolved Oxygen
d. Mixing Energy
12.6 Composting
12.7.1 General
Drainage from drying beds and centrate or filtrate from dewatering units should
be returned to the sewage treatment process at appropriate points preceding the
secondary process. The return flows shall be returned downstream of the influent
sample and/or flow measuring point and a means shall be provided to sample
return flows. These organic loads must be considered in plant design.
12.7.2.1 Area
Drying bed design should be based on square feet per capita or pounds
of sludge solids per square foot per year.
Table 12-5 presents the range of values that should be used, these values
are for drying anaerobically digested sludges. Additional area is required
for wetter sludges such as those resulting from aerobic digestion;
therefore, use the higher number of the required range.
*The design engineer should rely on his experience and the plant location.
a. Gravel
b. Sand
The top course shall consist of at least nine inches of sand with a
uniformity coefficient of less than 3.5. For trickling filter sludge, the
effective size of the sand shall be between 0.8 to 3.0 millimeter. For
waste activated sludge, the effective size of the sand shall be between
0.5 to 0.8 millimeter. For combinations, use the lower size range.
c. Underdrains
Paved surface beds may be used if supporting data to justify such usage
are acceptable to the Department. The use of paved beds for aerobically
digested sludge is generally not recommended.
12.7.2.4 Walls
Not less than two beds should be provided and they should be arranged to
facilitate sludge removal. Concrete truck tracks should be provided for all
The sludge pipe to the beds should terminate at least 12 inches above the
surface and be arranged so that it will drain. Concrete splash plates shall
be provided at sludge discharge points.
The methods used to dewater sludge may include use of one or more of
the following devices:
c. Filter presses
g. Reliability
i. Space requirements
12.7.3.3 Storage
Refer to Chapter 9, Ponds and Aerated Lagoons, for the requirements of sludge
storage lagoons.
The ultimate disposal of sludge through various methods (i.e., landfilling, land
application) is subject to the regulations and/or guidelines of the Tennessee
Division of Water Pollution Control (DWPC). Approval by DWPC is required
prior to initiation of the selected disposal alternative.