Final Report Kevin Watte
Final Report Kevin Watte
Final Report Kevin Watte
K.A.A. Watt
R.D. de Herder
Cover photo:
Side-by-side berthing arrangement between FSRU and LNG carrier in West Java. This FSRU project is Indonesias
first LNG regasification terminal and represents the worlds first FSRU project in Asia.
K.A.A. Watt
Final report
Graduation Committee
Chairman Prof. Ir. Tiedo Vellinga
Supervisor TU Delft Ass. Prof. Dr. Ir. Jarit de Gijt
Supervisor TU Delft Dr. Ir. Arie Romeijn
Supervisor Royal HaskoningDHV Ir. Dirk Jan Peters
Supervisor Seaway Heavy Lifting Engineering B.V. Ir. Vladimir Thumann
Daily supervisor
Supervisor Royal HaskoningDHV Ir. Priscilla Veldhuizen
II
MSc Thesis
III
K.A.A. Watt
Preface
This report presents the results of a study into the feasibility of standardization of a mono-pile mooring facility
for FSRUs on exposed locations. The graduation project was carried out at Royal HaskoningDHV in cooperation
with Delft University of Technology. This project was performed to obtain the Masters degree in Hydraulic
Engineering at Delft University of Technology.
I would also like to thank the committee members for the time and energy they dedicated to my work.
On a personal note, I would like to express my gratitude to my parents for their confidence and financial
support during all those years.
Kevin Watt,
IV
MSc Thesis
Abstract
As the LNG market continues to grow internationally, Floating Storage and Regasification Units (FSRUs) have
become an increasingly important component as governments and private companies strive for faster, cheaper
and more flexible means of re-gasifying.
In order to have a FSRU mooring system which is equally fast deliverable, standardization is considered. In this
study standardization of the civil structures is investigated for a jetty-type mooring system on exposed
locations, more specifically standardization of the breasting dolphins. The considered dolphins consist of a
simple steel mono-pile which transfers the mooring loads to the sub-soil and a pile-head which connects the
fender to the mono-pile.
It was concluded that standardization of the mono-piles is only possible to a certain extent, namely in a
conceptual design phase. In this report a standardized work approach is presented regarding the design of the
mono-piles. Additionally, multiple pile designs are conceived for varying conditions. In an early design stage,
when very little information is available, already some insight can be gained regarding the dimensions and the
costs of these piles.
In this thesis, also, the pile-head concept is presented which is most suitable for standardization purposes. This
is achieved by a Fiber Reinforce Polymers (FRP)-composite, floating structure with a slide-bearing sliding
system. The application of composite has some major advantages as it is fatigue resistant, low maintenance,
light weighted and corrosion resistant. The form of the pile-head is also optimized for its application so that the
fender loads are transferred in the most efficient manner to the mono-pile, while the slide-bearing allows
smooth sliding along the piles shaft.
Next to standardization of the civil structures, the loading conditions are investigated. Since the FSRU is
permanently moored at exposed locations, this issue cannot be treated with normal mooring of traveling ship,
but must be calculated with the aid of numerical software where the relation between the environmental
conditions and the load conditions is critical. The application of such software, however, is considered time-
consuming for early design stages. An assessment tool is therefore conceived that calculates the design fender
loads in a quick and analytical manner. This report shows that this assessment tool can generate rather
accurate results, but that its application is limited.
Keywords
Floating Storage and Regasification Unit, LNG, jetty-type mooring system, dolphins, standardization, permanent
mooring
V
K.A.A. Watt
Contents
Preface ................................................................................................................................................................... IV
Abstract ................................................................................................................................................................... V
1 Introduction.................................................................................................................................................... 1
2 Research description ...................................................................................................................................... 3
2.1 Scope ..................................................................................................................................................... 3
2.2 Problem definition ................................................................................................................................. 5
2.2.1 Standardization ................................................................................................................................. 5
2.2.2 Load conditions ................................................................................................................................. 5
2.3 Research objective................................................................................................................................. 5
2.4 Outline of the thesis .............................................................................................................................. 6
3 Methodology .................................................................................................................................................. 7
3.1 Part 1: Determination of the design loads ............................................................................................. 7
3.2 Part 2: Standardization of the mono-piles............................................................................................. 7
3.3 Part 3: Standardization of the pile-head................................................................................................ 7
4 Analysis Part 1: Design loads .......................................................................................................................... 8
4.1 Introduction ........................................................................................................................................... 8
4.2 Design conditions .................................................................................................................................. 8
4.2.1 Storm conditions ............................................................................................................................... 8
4.2.2 Short waves ....................................................................................................................................... 8
4.2.3 Beam-on and beam-quartering wave/wind directions ..................................................................... 9
4.2.4 Fender Loads ..................................................................................................................................... 9
4.2.5 Foam filled floating fenders .............................................................................................................. 9
4.2.6 Ballasted condition .......................................................................................................................... 10
4.2.7 FSRU-only mooring configuration ................................................................................................... 10
4.3 Assessment tool ................................................................................................................................... 11
4.3.1 Fender loads due to wave-action .................................................................................................... 11
4.3.2 Fender loads due winds and currents ............................................................................................. 11
4.3.3 Design fender loads ......................................................................................................................... 13
4.4 Results ................................................................................................................................................. 13
5 Analysis Part 2: Mono-pile............................................................................................................................ 15
5.1 Introduction ......................................................................................................................................... 15
5.2 Design conditions ................................................................................................................................ 15
5.2.1 Requirements and assumptions ...................................................................................................... 15
VI
MSc Thesis
VII
K.A.A. Watt
VIII
MSc Thesis
1 Introduction
Natural gas is used as a major source of energy. However, many cities and industries that need that energy are
located far from the gas fields. Since transportation of natural gas may not always be feasible through
pipelines, Liquefied Natural Gas (LNG) is created which can then be transported safely and economically by sea.
LNG is thus natural gas, predominantly methane, which has been converted to a liquid state for ease of storage
and transport. The liquefaction process consists of condensing the natural gas into a liquid by cooling it to
approximately -162C, significantly reducing the volume to 1/600 of its original value making it very efficient
and thus economically valuable.
The global gas demand has known a significant growth the last couple of years and will be expected to grow
even more in the future. The International Energy Agency (IEA) sees natural gas being one of the most
important energy sources in the future as it forecasts that the natural gas growth rate will be more than twice
the expected growth rate of oil. The growth of the global LNG energy demand, however, is expected to be
even stronger. To illustrate this rapid growth the projected growth is given in Table 2 [18].
Exploration and First deposits of natural gas are detected and pumped to the surface from onshore or
extraction offshore wells through pipelines to the liquefaction plant.
Storage and At the liquefaction plant, all impurities are removed from the gas, prior to cooling.
liquefaction process Cooling of the natural gas, as mentioned above, will reduce its volume considerable
making transport efficient and economically valuable.
LNG transportation The LNG is loaded onto double-hulled ships specially designed to prevent hull leaks
and ruptures in the event of accidents. Those ships are knows as LNG carriers (LNGC).
Once the ship arrives at the receiving port, the LNG is offloaded and pumped into
storage tanks.
1
K.A.A. Watt
Storage and LNG is stored in storage tanks at just above atmospheric pressure at a temperature of
regasification -162C. Regasification is used to convert the LNG back into its natural gaseous state by
process gradually warming the gas back up to a temperature of over 0C. Finally, the gas
enters the domestic pipeline distribution system and is ultimately delivered to the
end-user.
The scope of this thesis will focus on the final link of the LNG supply chain, the LNG receiving (import) terminals
as highlighted in Figure 1.
Conventional LNG import terminals are land based, situated within ports or as stand-alone facilities. Every
terminal would be constructed in combination with a quay or jetty structure to support the mooring of LNG
carriers, storage tanks for the LNG and special equipment for the regasification process. Due to the hazardous
nature of gas, the construction of such conventional LNG import terminals encountered growing public
resistance to terminals located close to populated areas as an unacceptable high risk to public safety was
perceived. Consequently, this was in direct conflict with the ambitions of Gas enterprises which are preferably
situated close to the market, in proximity of residential areas. New sorts of import terminal were therefore
required. This has led to multiple new solutions for importing gas from which offshore terminals, in particular
Floating Storage and Regasification Units (FSRUs), would be able to provide a solution capable of meeting the
expectations of both the Gas enterprises and the local communities.
A FSRU is an LNG import terminal located offshore. It is a specially designed floating vessel which provides LNG
receiving, storage and regasification services. As a hull, a FSRU consist of a LNG carrier (LNGC) converted by
attaching a regasification infrastructure. The FSRU is typically 300 meters long and does normally not have a
complete propulsion system. There are applications in which rapid disconnection and relocation is required, in
these cases propulsion will be part of the FSRU. The main advantages of a FSRU compared to conventional land
based terminals are listed below [32], [33]; it must be noted that these are valid for the general case; further
information regarding these topics are not treated within this thesis.
Low initial costs For the construction of the FSRUs less initial CAPEX is needed due to the fact that the
storage tanks are already "built in" to the converted LNG carrier, which are the most
expensive terminal components. FSRUs are therefore a more cost-effective way to
meet small scale LNG demand or to access new emerging markets
Speed of delivery A shorter start-up and construction time makes rapid access to high value gas markets
possible. Also there is less risk of delays related to land acquisitions.
Flexibility The FSRU can be relocated, moored offshore or near shore. Due to its flexibility the
FSRU is an obvious choice in areas where economic growth is uncertain or where
there is an element of political or economic instability.
Lower resistance Since a FSRU is situated offshore, there is less resistance of local communities.
As the LNG market continues to grow internationally, FSRUs have become an increasingly important
component, in particular to smaller and growing economies worldwide. FSRU operations are predicted to
double in the next two years as governments and private companies continue to take advantage of a faster,
cheaper and more flexible means of re-gasifying LNG [27]. In order to have a FSRU mooring system which is
equally fast deliverable, standardization is required. The purpose of this study is thus saving costs and schedule
of the civil structures for moorings by investigating the feasibility of standardization. Additionally, the focus
shall lie on standardization of a jetty-type system where the mooring of the FSRU is carried out through a
combination of both breasting and mooring dolphins.
2
MSc Thesis
2 Research description
In this chapter first the scope of the research is described (2.1). Subsequently the problem definition is treated
(2.2) from which the research objectives (2.3) will follow. Lastly, an outline of the report will be given (2.4).
2.1 Scope
In order to prevent the FSRU from floating away and allow safe LNG transfer, an appropriate mooring system is
indispensable. Vessels station keeping can be divided into two functions:
Heading control
Position control
Depending on the operations, one or both functions are required. In this study the focus shall lie on a jetty-type
mooring system which is a combination of the abovementioned functions.
The considered jetty-type mooring system consists of four mooring dolphins and four breasting dolphins
illustrated in Figure 2. The mooring dolphins are required to withstand lateral forces on the moored vessel,
when the vessel is pushed away from the mooring system. From the bow and the stern breasting lines are
connected to the mooring dolphins restricting these lateral motions. The breasting dolphins are required to
withstand the longitudinal forces on the moored vessel; spring lines are connecting the vessel to the
breasting dolphin in order to achieve this. Additionally, the breasting dolphins are required to withstand the
lean-on forces caused by the vessel being pushed towards the fenders. These fenders have as main function
to absorb energy caused by the moving vessels, preventing damage to the structure and vessel. The fenders are
located between FSRU and breasting dolphins and between the FSRU and LNGC.
Fenders
LNGC
FSRU
Figure 2 Jetty-type mooring system; side-by-side mooring configuration between FSRU and LNGC
This considered mooring system is meant for exposed locations. The FSRU is permanently fastened to the
mooring system and shall only be relocated under extreme events. Quick Release Hooks are therefore
applied which enables quick and easy release of the mooring lines.
3
K.A.A. Watt
For the transfer of LNG, an incoming LNGC will berth along the FSRU in a side-by-side configuration, offloading
the cargo by means of hydraulic arms. Once the LNG is re-gasified, the gas will be transferred to a transfer
platform by means of jumpers (flexible hoses). Subsequently, from the platform, the gas will be transferred
via a riser to a fixed seafloor-pipeline to the main land. A more detailed explanation regarding the FSRU-
vessel and its operations is included in Appendix I.
This study focusses on dolphins which are constructed from mono-piles. These are large diameter, tubular,
steel elements, generally driven into the soil. The load exerted by the moving vessels on the mooring system
will be transferred by means of bending deflection to the sub-soil.
Even more specifically, the emphasis of this study will be on the breasting dolphins. Two main elements are to
be distinct:
The mono-pile itself which transfers the mooring forces to the sub-soil,
The pile-head which connects the fender to the mono-pile
4
MSc Thesis
2.2.1 Standardization
As LNG makes great strides in the global energy demand, FSRUs become increasingly applied. Their flexibility,
low CAPEX and fast deliverance makes them, in many cases, the preferred type in comparison to the
conventional land-based terminal. In order to prevent counteracting these advantages, the required FSRU
mooring system shall be equally cheap and fast deliverable. In order to achieve these means, standardization is
considered.
The purpose of this study is therefore to investigate standardization of the civil structures of a mono-pile
mooring facility for permanently moored FSRUs, in particular standardization of the breasting dolphins. The
focus shall lie on the design of the mono-pile and the pile-head.
The relation between the environmental conditions and the load conditions is thus one of the critical issues for
the design of the flexible mono-pile dolphins. These design loads are normally determined based on the
outcome of a so-called dynamic mooring analysis (DMA). DMAs are simulated by means of numerical software
packages and are used to determine the response of a moored ship to its environment. However, the
simulation of DMAs is a complex and time-consuming procedure. In order to prevent using this type of
software in early design stages, a standardized method is required that quickly estimates the mooring loads.
The first part concerns the loads acting on the breasting dolphins. As mentioned in the problem definition,
currently numerical software is used to calculate mooring loads. The application of such software in an early
design stage, however, is considered rather inefficient. A standardized assessment tool has therefore to be
designed with which an estimate of the design loads can be obtained in an analytical manner. The relationship
between the environmental conditions and the loads due to ship motion are therefore critical. These shall be
rationalized covering a large range of wind, current and wave conditions.
Part 2 focusses on standardization of the mono-pile dolphins. A feasibility study shall be performed by
analyzing whether standardization is possible without largely over-dimensioning the piles. The effect of the
loads and geotechnical parameters on the pile design shall be investigated. Since the mooring facility is to be
designed for exposed locations, also fatigue loading needs to be taken into account. The fatigue life of the
mono-piles shall therefore be assessed
5
K.A.A. Watt
In the final part, Part 3, special attention is given to the pile-head; a standardized concept shall be designed. For
this study multiple materials, forms and properties of the pile-head are to be considered. Different variants
shall be conceived and compared by means of an evaluation-study. The variant which will be the best fit for
standardization purposes shall subsequently be elaborated; both a structural analysis as a fatigue assessment
shall be performed.
Chapter 3: Methodology
In the methodology the general work approach of the three different Parts is described.
This chapter concerns the analysis of Part 1. The design conditions on which the assessment tool is based are
drafted. Subsequently, a description of the assessment tool including its application is elaborated. Lastly, its
accuracy is tested by comparing the obtained results to actual DMA-results from several reference projects.
Chapter 5 regards the analysis of Part 2; the design of the mono-piles. As standardization is only possible within
certain limits, first the design conditions and requirements are defined. Thereafter the modeling procedure and
design verifications of the mono-piles are clarified. The influence of the input parameters on the pile design is
included in the results. Based upon these results, conclusions regarding standardization will be drawn.
The analysis of Part 3, the pile-head, is included in Chapter 6. Here again, first design conditions are
established. Afterwards a brief introduction and specific material properties of FRP-composites will be given.
Subsequently, the modelling procedure and performed design verifications are mentioned. The results of the
global structural analysis will follow. It must be noted that the structural optimization process is not very much
discussed; only the final design is presented.
Discussion of results consists of a quick recapitulation of the obtained results mentioned in the previous
chapters. Additionally, these results will be further enlightened and rationalized.
Based on the obtained results conclusions will be presented. Lastly, some recommendations for further
research are given.
6
MSc Thesis
3 Methodology
In this chapter the methodology of the different parts is briefly described. These will be further elaborated in
Chapters 4, 5 and 6 for respectively Part 1, 2 and 3.
The laterally loaded pile calculations are performed with LPile v6.0 software. This software models the pile as
an elastic beam on a foundation of uncoupled non-linear springs, representing the soil, the so-called p-y curves.
The ULS design verifications for the steel mono-piles include yield stresses and local buckling. The fatigue life is
checked based on a cumulative damage factor which is calculated by means of Miners Law.
In order to see to what extend standardization of the mono-piles is possible; the influence of the load on the
pile design is investigated. Also the effect of the subsoil is taken into account by considering two extreme soil
profiles: a stiff sand profile and a soft clay profile. Since standardization will inevitably lead to some over-
dimensioning, this is also investigated. The analysis of Part 2 is treated in Chapter 5.
The structural analysis of this concept is performed with Finite Element-software package SCIA Engineer
which was used to perform a global elastic analysis. The final design is obtained through an optimization
process, constantly adjusting the size and material properties of the different elements. Finally, the design is
checked on its fatigue life based on Miners law and the most critical joint connection is analyzed. The complete
analysis including the final design is presented in Chapter 6 Analysis Part 3.
7
K.A.A. Watt
4.1 Introduction
The main goal of Part 1 is to design an assessment tool that, in a conceptual design phase, gives a quick
estimate of the design loads, thus avoiding having to use DMA software.
With the aid of this assessment tool, for a given set of environmental conditions, the critical loads on the
breasting dolphins can be calculated in an analytical manner. Nevertheless, such tool is only designed within
defined limits and is therefore only valid for a certain range of wind, wave and current conditions. The range of
environmental conditions and additional assumptions are treated in section (4.2) Design conditions. The
assessment tool is described in section (4.3) and its calculated accuracy is included in section (4.4). Discussion
of the obtained results is treated in Chapter 7.
For this study only relatively short waves are considered (see Figure 4, each dot is represents one DMA run).
For swell environments or near-shore locations where un-bounded long waves may occur, this assessment tool
is not applicable.
This method was conceived for waves with a maximum significant wave height of 2 meters. For larger wave
heights this method still need validation.
8
MSc Thesis
Two types of mooring loads are exerted on breasting dolphins: the fender loads and the spring-line loads.
When the fender loads are maximal, however, the spring lines are slack, their load zero and are therefore
neglected.
Due to their wave-shaped force-deflection curve, however, the Cone/Cell fenders are very sensitive to fatigue
damage and are therefore not applicable for moorings on exposed locations. The Foam filled floating-types,
which have a much flatter force-deflection curve, fatigue is already much less of an issue. These are therefore
the only type of fenders which can be applied for the considered mooring facility.
9
K.A.A. Watt
Figure 7 Picture of a Foam filled floating fender and its corresponding force-deflection curve
10
MSc Thesis
In the following section only the method is described which gives the most accurate results. It consists of
relating wave heights to fender deflections. The other method consists of normalizing a force-displacement
curve. A detailed explanation of the latter is included in Appendix V.
A longitudinal force component (FX) corresponding to the surge motion of the ship.
A lateral force component (FY) corresponding to the sway motion of the ship.
A yaw moment component (MXY) corresponding to the yaw motion of the ship.
11
K.A.A. Watt
Figure 9 Drag force components. Blue arrow represents incoming metocean conditions
For the calculation of the fender load, however, only the lateral force and yaw moment are of interest. The
total fender force due to respectively winds and currents can be calculated by means of the following equation:
1 1
= 2 / 1000 [] = 2 / 1000 []
2 2
Where:
Cyw and Cyc dependent on: the angle of attack and the type of vessel. These coefficients have been empirically
determined based upon data from physical tests and are illustrated in the OCIMF Guidelines [30].
Alpha is a coefficient which takes the distribution of Fy and Mxy into account for varying incoming directions.
This coefficient is obtained through observed DMA-data and can be extracted from Figure 10. E.g. if the winds
and currents would come from beam-on direction (270), the yaw moment would be practically zero and the
load will be evenly distributed over the four fenders. Hence a factor of, approximately, 0.25 is found.
For storm conditions, the 1-hourly mean wind velocity is multiplied with a gust factor of 1.37 which is in
accordance to the British standard [4].
Figure 10 Coefficient Alpha - incoming direction (according to the Cartesian convention [34])
12
MSc Thesis
= + +
An example of how the application tool should be applied is included in Appendix IV.
4.4 Results
The accuracy of the conceived assessment tool is checked based on the outcome of DMA runs. The DMA runs
considered have been taken from the reference projects; Golar and Aqaba.
Fender
The fenders applied within these runs are represented by a maximum fender reaction force (Freaction). Their
force-deflection curves are illustrated in Figure 11. A distinction is made between stiff- and soft fender cases:
The stiff case includes a +15% manufacturing tolerance on the reaction force.
The soft case includes a -15% manufacturing tolerance and a -15% multiple cycle reduction on the
reaction force.
Environmental conditions
In order to test the accuracy of the assessment tool for somewhat extreme conditions, different types of
combinations are considered. The storm conditions represent mild storms. The wave conditions represent
runs which have been made with relatively large wave heights and the wind conditions with relatively large
wind velocities. The tsunami conditions represent runs made with large current velocities.
DMA Results
The outcome of DMA runs consist of a varying fender load over time. The maximum occurring peak load in
these runs is described by MAX Ffender. However, since DMA runs in time domain, the maxima are influenced
by the length of the runs. The longer the runs, the more likely a larger maximum is found. The Most Probable
Maximum (MPM)-method is therefore introduced and is a realization obtained through the distribution of
13
K.A.A. Watt
these maxima. This MPM Ffender is applied as a design value and will therefore be used as comparison for the
outcomes of the assessment tool.
Calculated Results
The results were calculated following the procedure discussed in the previous section. The accuracy of these
calculated values, compared to the MPM-values, is represented by an error margin.
14
MSc Thesis
5.1 Introduction
Part 2 consists of standardization of the mono-piles. The design of these piles is very much depend on the local
conditions; constitution of the soil, environmental weather conditions and the local water depth. The relations
between these variables are studied in order to see to what extent standardization is possible. Once again, this
can only be achieved within defined limits. These are described in the Design Conditions (5.2).
The design procedure of the mono-piles is treated in the section Design procedure (5.3). This consists of
determining the dimensions of the mono-pile based on an ULS load case and checking the fatigue damage in
the FLS. For the fatigue calculations a case study is used to see whether it may be a decisive factor in the pile
design. The results of this analysis are mentioned in section (5.4) and will be further discussed in Chapter 7.
3
= = 9.23
The typical period of an FSRU at berth is obtained from previous RHDHV projects and is equal to 6
second (0.17Hz). The natural frequency of the structure is thus much higher than the excitation
frequency. Extensive calculations regarding the dynamic effects are therefore left out of
consideration.
Environmental loads acting on the pile are ignored as they are small compared to the mooring loads.
Torsion due to friction between fender and dolphin is included in the design calculations. The friction
force is assumed to be 50% of the fender load.
15
K.A.A. Watt
5.2.4 Loadings
Furthermore, as the structure is loaded cyclically by the fender due to the constantly moving FSRU vessel at the
berth; consequently the mono-piles need to be checked with respect to fatigue. The variable loads which are
used for the fatigue assessment are obtained through the case study, Golar-project. These loads were
calculated with the aid of Dynamic Mooring Analyses and are included in Appendix XI.
16
MSc Thesis
Since sustained hard driving may be expected for installation of the piles in the abovementioned soil layer, the
minimum wall thickness is in accordance to the API RP-2A-LRFD and should not be less than:
= 6.35 + /100
5.2.6 Standards
The main design considerations are according to the DNV standards. However, for some particular calculations
other standards were applied as they were considered more appropriate:
Serviceability Limit State (SLS) and Accidental Limit State (ALS) are left out of consideration as no conditions
have been defined with respect to pile deformation and undesired events.
The load and material factors applied to the considered limit states are included in Table 5 and are in
correspondence to DNV-OS-C101. For ULS two combinations have been considered: one for structural steel
checks (Steel) and the other for the geotechnical stability (Soil).
Regarding the geotechnical stability of the piles, a factor 1.20 will be applied for effective stress analysis
1 2
(drained conditions ) and factor 1.30 will be applied for total stress analysis (undrained conditions ):
tan
tan =
1.20
1
Drained conditions occur when there is no change in pore water pressure due to external loading. In drained
conditions, the pore water can drain out of the soil easily, causing volumetric strains in the soil. [3]
2
Undrained conditions occur when the pore water is unable to drain out of the soil. In an undrained
condition, the rate of loading is much quicker than the rate at which the pore water is able to drain out of the
soil. [3]
17
K.A.A. Watt
,
, =
1.30
18
MSc Thesis
It has to be noted that the determination of the p-y curves are based on results of lateral load tests of piles
with a diameter of 0.15m to 0.60m. The application of these curves on larger diameter piles is found to be a
conservative approach. However, no other method was found in the literature regarding this matter. The p-y
curves are therefore still applied for geotechnical modelling.
19
K.A.A. Watt
Normal stresses
The normal stresses in the structure are due to the self-weight of the pile-shaft and the pile-head. This stress
increases along the pile as the volume of the pile-shaft (and thus the self-weight) becomes larger towards the
mud line.
Bending stress
The bending stresses occur due to two types of bending moments. The first one is due to the operational loads
acting in lateral direction. The second is due to the displacement of the top pile, whereby the self-weight exerts
a vertical load in an eccentric manner. The general formula for the bending stress reads:
It must be noted that the bending stress due to the lateral acting load is much larger than the bending moment
due to self-weight. At the level of the largest occurring bending moments, the self-weight only contributes for
2% of the total moment.
Shear stress
The shear stresses are due to the lateral acting force. The maximum shear stress for a hollow cylinder is
calculated as follows:
4 (3 3 )
= =
3( ) (4 4 )
20
MSc Thesis
Torsional stress
Since a friction coefficient of 0.5 is assumed, a torsional moment within the cross-section needs to be taken
into account. This torsional moment is equal to the friction forces times the outer radius of the pile. The
general formula for torsional stress reads:
= =
(4 4 )
2
In case of combined membrane stresses and shear stresses the equivalent Von Mises stress shall be used:
, = 2 + 3 2
Where d represents the meridional stresses due to bending moments and normal forces and d the shear
stresses due to shear forces and torsional moments.
In the cross-sectional check, bending stresses and shear stresses are not combined, as they are concentrated in
a different location in the cross-section. The equivalent Von Mises stress is therefore calculated for two
locations in the cross-section:
where bending stresses are maximal and shear stresses are zero:
= +
where shear stresses are maximal and bending stresses are zero:
= +
21
K.A.A. Watt
The design equivalent Von Mises stress will be the governing value of the abovementioned combinations.
Where is a buckling reduction factor, dependent on the relative slenderness of the shell structure. The
calculation method for local buckling is included in Appendix VII. The partial factor is based on the DNV-OS-
C101.
22
MSc Thesis
Fatigue loading may result during the operational phase due to vessel motions and during the installation
phase due to pile-driving. Depending on the soil conditions, pile driving may be of influence on the pile design.
In this report, however, only the fatigue loads during the operational phase are taken into account. The effect
of the environmental loads on the fatigue life of the dolphin piles had been assessed in a previous study of
RHDHV and proven to be negligible compared to the operational loads.
In contrast to ULS calculations, the design stresses for the fatigue assessment ( nominal) are not based on
maximum occurring loads, but on alternating loads (F) which are the difference between a maximum- and
minimum value during a certain time segment (typ) as is depicted in Figure 14. Critical is the number of times a
certain alternating load occurs.
Figure 14 Example of a time series and time segment needed for fatigue assessment
The fatigue life will be checked based on data from the Golar- case study, which is an FSRU mooring system
located offshore approximately 15km north of Jakarta in the Java Sea. However, since ULS loads and FLS loads
are highly correlated it would be unreasonable to check the fatigue life of a pile which has been designed for
different ULS loading conditions as the one from the case study. For this reason, only a fatigue assessment is
performed on the mono-pile which was designed on the same ULS design load of approximately 5000kN.
For each wave height and incoming direction (16 in total), the number of force fluctuations is described. Below
shows an example of the obtained input for the fatigue assessment. The total input is included in Appendix XI.
As the DMA models a duration of 6 hours, hence the result is the number of cycles within 6 hours. Based on the
probability of occurrence of the considered environmental conditions the total number of cycles during the
design life time of the structure (20 years) is calculated:
= 24 365 20 %
6
23
K.A.A. Watt
The SCF is dependent on the type of weld and pile geometry. Since piles are considered without thickness
transition, the SCFs are calculated according to the following equation:
In above formula t is the plate thickness, D the diameter and m is the maximum allowable misalignment
which is equal to 0.1*t and reaches a maximum value of 4mm.
= ( )
In which N is the allowable number of cycles and S the stress range. The values of the parameters for the S-N
curve C1 in seawater with cathodic protection are included in Table 7:
24
MSc Thesis
= = 1
=1
The actual number of cycles (nc) of a certain alternating stress range is divided by the allowable number of
cycles (Nc) for that same range. This is done for all occurring stress ranges. The sum of this is referred to as the
cumulative damage number and shall not be larger than 1. A design fatigue factor (DFF) of 10 is applied to
obtain an overall safety on the calculated fatigue.
A design fatigue factor (DFF) of 10 is normally applied for all the parts of the structure which cannot be
inspected during its service life. For the parts that can be expected a lower DFF is allowed. However it is safe to
apply a DFF to all sections.
25
K.A.A. Watt
5.4 Results
For each combination of fender load and soil profile a pile design is made characterized by its dimensions:
diameter (D), wall thickness (t) and length (L). For each combination two pile designs are possible; one with an
optimized diameter, the other with an optimized wall thickness. For a few combinations, however, the designs
were outside the chosen D/t range (65 < D/t < 85), those are marked with a no.
In the following graphs the influence of the parameters are illustrated. The green dots represent the stiff sand
profile; the blue dots the soft clay profile. The lines represent an approximated upper- and lower bound.
In Figure 20 the design loads are plotted against the material costs. Those material costs only comprise the
costs of steel. Installation costs due to hoisting and pile driving are not taken into account.
Table 8 Pile designs for varying design loads and soil profiles; L is the total length of the pile, D is the outer diameter and
t the wall thickness
26
MSc Thesis
Figure 17 Design load / Pile diameter; green: stiff soil, blue: soft soil
Figure 18 Design load / Wall thickness; green: stiff soil, blue: soft soil
27
K.A.A. Watt
Figure 19 Design load / Pile length; green: stiff soil, blue: soft soil
Figure 20 Design load / Material costs; green: stiff soil, blue: soft soil
28
MSc Thesis
As can be observed from the graphs, for both soil profiles, the pile diameter and wall thickness increases in a
rather similar fashion. Those dimensions, moreover, do not differ that much between the two soil cases. The
difference in pile length, however, is considerable. For the stiff profile the length increases from 40m to 47.5m,
whereas the length for the soft profile increases from 55m to 80m. Due to this large difference, a generalized
pile design cannot be achieved without large over-dimensioning.
Additional limits are therefore introduced. As well as distinction in soil profiles, also a distinction in
environmental condition is made. Three classes are distinguished; mild, moderate and harsh. The mild
environmental conditions result in design fender loads ranging between 3000kN and 5000kN, moderate
conditions between 5000kN and 7000kN and harsh conditions between 7000kN and 9000kN.
For each combination of environmental condition and soil profile, a standardized pile design has been defined.
These are based on the upper limit.
Environmental condition
Soil profile Dimensions
Mild Moderate Harsh
t [mm] 45 50 55
Stiff sand
D [mm] 3300 3800 4100
profile
L [m] 42.5 45 47.5
t [mm] 50 55 60
Soft clay
D [mm] 3400 3900 4300
profile
L [m] 65 70 80
Table 9 Standardized pile dimensions for different combinations of environmental- and geotechnical conditions
29
K.A.A. Watt
Over-dimensioning
In order to gain an insight in the significance of over-dimensioning of these standardized piles, the excess of
steel has been calculated. The over-dimensioning costs increase as the difference between the actual load and
the load on which the standardized pile is designed increases. Such is depicted in Figure 21; green for the stiff
soil profile, blue for the soft soil profile. It must be noted that the costs of over-dimensioning only cover the
material costs of steel.
Figure 21 Over-design in case of standardization [USD]; green: stiff soil profile, blue: soft soil profile
From Figure 21 can be seen that the over-dimensioning costs of the standardized designs are much larger for
the softer soil than for the stiffer soil. These can reach up to 0.38 million USD for the worst case. If compared
with the total costs of an FSRU-project, which amounts roughly 25 million USD (based on the Golar-project),
these may still be considered small (only 1.5% of the total costs). The averaged range of the over-dimensioning
costs per soil profile is listed in Table 10.
For large scale FSRU-projects, as considered in this thesis, the over-dimensioning costs of the mono-pile
breasting dolphins are relatively small. The standardized design discussed in this section can therefore be
beneficial for early design stages, where, with little information a good insight can be gained in the dimensions
and costs of the dolphins.
30
MSc Thesis
Rescaling
Since the FSRU import terminal will always be located as close as possible to the shore, the variation in water
depth is considered small. If, however, larger water depths are to be expected, the standardized pile designs
presented in Table 9 should be rescaled to an appropriate design. In Appendix IX, the rescaling of the piles has
been investigated for a water depth increased by 10 meters (26m total).
In Table 11 rescaling parameters are presented which should be added to the dimensions of the standardized
piles in order to increase their size and satisfy their structural stability for a water depth of 26 meters. These
rescaling parameters are valid for both soil cases.
Rescaling parameters
Dimensions
for 26m water depth
Thickness + 5 mm
Diameter + 400 mm
Length + 12.5 m
Table 11 Increased pile dimensions for an a water depth of 26m
Since ULS-loads and FLS-loads are highly correlated, the fatigue assessment is only performed for the mono-
pile which had been designed on the same ULS conditions as the one from the case study, namely: soft soil
profile and design load of 5000kN. The considered pile dimensions are: 65m x 3.4m x 0.050m (L x D x t).
The results of the assessment are listed below. Respectively: the Stress Concentration Factor, Load Transfer
Function and cumulative damage number are:
SCF LTF DD
1.21 0.086 7.83E-02
31
K.A.A. Watt
6.1 Introduction
This chapter concerns the third and final part of this study, the design of a standardized pile-head. The design
procedure started off by conceiving multiple variants very different one from another. The properties of those
variants were then evaluated and compared by means of a so-called multi criteria analysis (MCA). From this
MCA-evaluation, the pile-head most favorable for standardization purposes is subsequently elaborated.
The variant study is presented in Section (6.2). The requirements and boundary conditions used for the design
of the pile-head are mentioned in the Design Conditions (6.3). Subsequently more information regarding the
applied material and its mechanical properties are described in Material properties (6.4), while the design
procedure and verifications are treated in the section Design procedure (6.5). The structure was modelled in
Finite Element-software SCIA Engineer, where the final design was obtained through an optimization process,
constantly adjusting the size and material properties of the different elements. The fatigue life is assessed
based on the same case study as the mono-piles. The final design is treated in the section (6.6). Discussion of
these results will be included in Chapter 7.
6.2.1 Material
There are several materials which could be applied for the construction of the pile head. The most common
ones are steel and concrete, but also composites becomes more and more practice in hydraulic structures.
Regarding sustainability, wood may be an interesting choice.
6.2.1.1 Steel
Steel is the most applied material in offshore and hydraulic engineering due to its high strength to weight ratio
and the possibility of welding the connection of different elements for an improved stress distribution. A large
disadvantage of the application of steel in wet environments is corrosion which leads to deterioration of the
materials properties. The most vulnerable part is located in the splash zone which is intermittently exposed to
air and immersed in the sea. Different methods are possible with respect to mitigation and control of corrosion
such as coatings, cathodic protections or even design with a corrosion allowance.
6.2.1.2 Concrete
Concrete is very much applied for its high compressive strength. In combination with reinforcement steel (for
tensile stresses) it has really good overall properties and is therefore also often applied in hydraulic
engineering. However, applying concrete in a wet environment also has its limitation:
A large concrete cover must be applied for the protection of the reinforcement steel in seawater.
Poring and hardening of concrete at offshore locations may be problematic. This issue can be partially
resolved by applying prefabricated elements.
6.2.1.3 Wood
A wooden pile-head would be a very eco-friendly solution. With respect to durability, only several types of
hardwood would be suitable for a construction in a salty environment. Their composition should also be able to
32
MSc Thesis
withstand fungus and marine borers. However due to the large expected loads, the strength and mechanical
properties are assumed to be insufficient for the design of the pile-head. For this reason wood will not be
further discussed in this study. [29]
6.2.1.4 Composite
The application of composites in marine environments is not yet common practice. However, the use of this
material may offer significant advantages such as corrosion resistance, fatigue resistance, very high structural
damping and low maintenance. Furthermore its low density makes composite an interesting choice for a
floating pile-head concept. The main disadvantages include high initial costs and the disability to deform
plastically (compared to steel). [20] [31]
6.2.2 Concepts
Multiple concepts have been conceived for the pile-head. A distinction is made between fixed and floating
ones. When considering fixed structures, the fender panel may reach very large heights for locations with high
tidal variations. The fender itself must then be loose enough to follow the rising and falling of the tide. For a
floating pile-head, the height of the fender panel can be reduced significantly. Since the pile-head itself is
floating, the fender can be attached in a fixed manner (see Figure 22). The buoyancy can either be achieved by
the fender support structure or the fender panel.
Figure 22 Foam filled floating fender. Left: floating position, Right: fixed position
33
K.A.A. Watt
Mono-pile
Figure 23 Steel fender panel connected with steel horizontal support plates to the mono-pile
The whole structure can be prefabricated and welded in a single operation onto the mono-pile.
Ring stiffeners are probably necessary on the locations where the fender support structure is
connected to the mono-pile.
Diagonal trusses required in order to cope with the weight of the fender panel.
All connections can be welded for an improved stress distribution
Concrete cap
Floating fender
Easy access for maintenance vessels and simple connection of secondary structures such as bollards,
ladders, mooring pads, etc.
Fatigue resistant.
Good quality concrete is required preventing corrosion of the reinforcement steel.
For locations where large tidal differences must be overcome, very large amounts of concrete
necessary.
Its large top mass results in a low natural frequency of the whole system which can be within range of
environmental loadings.
34
MSc Thesis
Composite cube
The whole structure can be prefabricated and slid in one operation onto the mono-pile.
Easy access for maintenance vessels and simple connection of secondary structures
The whole structure can be prefabricated and slid onto the mono-pile
Its rectangular shape can reflect waves which could lead to resonance effects.
Fixed fender
The tubular elements provide improved characteristics against environmental conditions such as drag,
inertia and friction.
The bottom tubes must be relatively large to provide the pile-head with enough buoyancy.
The whole structure can be prefabricated and slid onto the mono-pile. Since it is made out of steel,
relatively large hoisting capacity is required.
All connections can be welded for an improved stress distribution
35
K.A.A. Watt
Fixed fender
The fender panel must be large enough to provide the pile-head with enough buoyancy.
Due to the eccentricity of the center of buoyancy, additional loads can be expected in the pile-head.
The whole structure can be prefabricated and slid onto the mono-pile.
The floating fender panel must be reinforced by inner compartments whichll acts as vertical stiffeners
increasing its flexural rigidity.
Steel sleeve-element
Fixed fender
Figure 28 Floating concrete fender panel with vertical steel support plates
The size of the floating concrete fender panel must be considerably larger than the one of concept 5.
Good quality concrete is required preventing corrosion of the reinforcement steel.
The support structure will be subjected to lateral flexion due to its non-parallel orientation compared
to the exerted load.
The whole structure can be prefabricated and slid onto the mono-pile. However, due to its very large
weight, troublesome hoisting operations are inevitable.
36
MSc Thesis
6.2.4.1 Criteria
The robustness of the structure concerns the ability to withstand large impacts and
Robustness
weather it is susceptible for collapse and deformations.
Durability is the capability of withstanding wear and tear, aging and decay over time. This
Durability criterion takes into account whether or not the structure is designed for the full lifespan,
or if some elements must be replaced during the service life.
Maintenance regards the ease of replacing certain elements and if the maintenance
Maintenance
works can be done in-situ. This criterion also concerns corrosion resistance.
This takes into account the extent to which the structure is resistant to fatigue due to
Fatigue
cyclic loading. This criterion mainly concerns the connections since those are the critical
resistance
elements.
Constructability regards the fabrication of the elements, the ease of assembly, and the
Constructability complexity of the connections. This criterion takes into account whether the structure can
be prefabricated or must be constructed in-situ.
37
K.A.A. Watt
For the installation the weight of the structure is important. Installation mainly regards
Installation the installation equipment; whether or not cranes with high hoisting capacity are
required.
The costs in this MCA only mentions the initial material costs depending on the applied
Costs
material.
This criterion depends on the accessibility of the pile-head for inspection and
Accessibility
maintenance works.
Sustainability takes into account the environmental impact; such as CO2 emissions, use of
Sustainability
chemicals, etc.
Weighting Factor
Constructability
Sustainability
Maintenance
Accessibility
Reparability
Robustness
Installation
Durability
Transport
Fatigue
Costs
Robustness X 1 2 2 1 2 2 2 2 2 2 Total
18.0 16.4
Durability 1 X 2 2 1 2 2 2 1 2 2 17.0 15.5
Maintenance 0 0 X 1 1 1 1 0 1 1 0 6.0 5.5
Reparability 0 0 1 X 0 1 1 1 1 1 0 6.0 5.5
Fatigue 1 1 1 2 X 2 2 2 2 2 2 17.0 15.5
Constructability 0 0 1 1 0 X 2 2 1 2 1 10.0 9.1
Installation 0 0 1 1 0 0 X 1 1 1 1 6.0 5.5
Transport 0 0 2 1 0 0 1 X 0 1 0 5.0 4.5
Costs 0 1 1 1 0 1 1 2 X 2 1 10.0 9.1
Accessibility 0 0 1 1 0 0 1 1 0 X 0 4.0 3.6
Sustainability 0 0 2 2 0 1 1 2 1 2 X 11.0 10.0
Total 110.0 100.0
Table 15 Weighing factors applied for the MCA
38
MSc Thesis
The most favorable pile-head concept is concept 5; floating composite fender panel with horizontal support
plates and a slide-bearing sliding system. The design is further elaborated in the following sections.
39
K.A.A. Watt
6.3.2 Material
The pile-head will be designed with FRP-composite as was concluded from the MCA. The main pros and cons
are listed below [15]. More information regarding the applied composite is further elaborated in Section (6.4).
Pro Con
Good in-plane mechanical properties Brittle
High fatigue and environmental resistance High initial costs
Adjustable mechanical properties Low to moderate application temperature (-20/+80 C)
Lightweight Low fire resistance (sometimes with unhealthy gases)
Low maintenance Lack of design practice
High material damping
Table 17 General pros and cons of FRP composite
6.3.3 Loadings
40
MSc Thesis
Compression Deflection Reaction Force Diameter Flat length Flat height Pressure
[%] [m] [kN] [m] [m] [m] [kN/m]
0.0% 0.00 0 3.30 4.20 0.00 0
2.0% 0.07 237 3.23 4.23 0.10 560
5.0% 0.17 591 3.14 4.28 0.26 532
10.0% 0.33 1184 2.97 4.35 0.52 523
20.0% 0.66 2367 2.64 4.50 1.04 506
30.0% 0.99 3551 2.31 4.65 1.56 490
36.8% 1.21 4356 2.09 4.75 1.91 480
49.2% 1.62 5823 1.68 4.94 2.55 462
55.0% 1.82 6510 1.49 5.03 2.85 455
60.0% 1.98 7101 1.32 5.10 3.11 448
At the interface between the fender and the composite panel a friction coefficient of 0.4 is adopted. A
horizontal- and vertical friction force is therefore taken into account working parallel to the fender panels
surface.
Inside the sleeve-element a low friction material is added such as PTFE (polytetrafluoroethylene) or UHMWPE
(Ultra High Molecular Weight Polyethylene). For the interface between the mono-pile and the sleeve element a
friction coefficient of 0.1 is used which works along the pile-shaft, according the GUR product-catalogue [24].
Furthermore, as the structure is loaded cyclically by the fender due to the constantly moving FSRU vessel at the
berth; consequently the structure needs to be checked with respect to fatigue.
The dimensions of the fender panel are according to Trelleborg Marine Systems [41] and are depicted in Figure
29:
41
K.A.A. Watt
The length of the panel is taken as the length of the fender including a 1m clearance at each side for fastening
of the chains:
= + 2 1 = 8.5
The width of the fender panel must be taken large enough in order provide the whole system with sufficient
buoyancy.
The sleeve element must fit tightly around the mono-pile, preventing it from moving and deform which would
lead to undesired secondary forces. The inner diameter must therefore be a little bit larger than the outer
diameter of the mono-pile of 4.5m.
6.3.7 Standards
Load factors according to DNV-OS-C101 [12].
Structural design of composite structures according to CUR 096 [7].
Fatigue of composite according to GL Wind Energy.
The Serviceability Limit State (SLS) is left out of consideration as no limit is defined regarding deformations of
the structure during daily conditions.
The Accidental Limit State (ALS) mostly concerns undesired accidental events. This Limit State is taken into
consideration by testing the structure on loads which are exerted in an eccentric manner onto the fender
panel. This may occur for example by failing of one of the fender chains. This limit state is included in one of
the ULS load cases as will be clarified later on.
42
MSc Thesis
The loads will be modified applying a load factor in accordance to the DNV standard. The structural design of
the composite and its corresponding material- and conversion factor is in accordance to the CUR 96 [7].
Material and conversion factors will be clarified in section Material properties.
6.3.9.2 Kolibri
Kolibri was used to calculate and analyze the mechanical properties of different laminates based on the
laminate theory. With this software stiffness matrices were generated which were necessary in order to define
certain orthotropic material properties within SCIA Engineer. More information regarding the stiffness matrices
will be given in the section (6.4) Design procedure.
43
K.A.A. Watt
Resin systems have limited mechanical properties, but it is when combined with reinforcing fibers that
exceptional properties can be obtained. The resin then spreads the load applied to composite between each of
the individual fibers and also protects it from damage. Since FRPs combine a resin system with reinforcement
fibers, the properties of the resulting composite material will be a combination of both material properties.
The properties of a ply are thus very much dependent on the alignment and orientation of the fibers within the
ply. In order to have good mechanical properties in all directions, most laminates are built up by stacking plies
of fibers of different directions onto each other (see Figure 31).
44
MSc Thesis
For laminates which need extra flexural stiffness, a sandwich structure can be applied. Such a sandwich
structure consists of two skins, which are built op by stacks of plies, and a core material in the middle. By
inserting a core into the laminate is a way of increasing its thickness without drastically increasing its weight. In
effect the core acts like the web in an I-beam.
Monolithic laminate; a single skin laminate consisting of stacks of reinforced plies only
Sandwich laminate; two skins separated by a core in the middle.
6.4.2.1 Fibers
Three main fiber types are distinct: glass-, aramid and carbon fibers. The carbon fibers have a very low density
and a greater stiffness compared to glass fiber. Regarding the impact strength, aramid is the advantageous
choice. However, both aramid and carbon are far more expensive than glass fibers (up to a factor 4-8 higher).
Since no extremely good mechanical properties are required for the design of the pile head, the costs are the
decisive factor in the fiber choice. Glass fiber will therefore be applied.
6.4.2.2 Resin
For resin, three main types are distinct: polyester, vinyl and epoxy. The density, Youngs modulus and tensile
strength of the different resin do not differ much. Regarding the maximum elongation, epoxy (8.0%) is more
advantageous than polyester (2.5%) and vinyl (6.0%).
But also for the resins choice, the costs outweigh the mechanical properties. Because polyester is the most
economical resin it is also the preferred choice.
From preliminary designs could be concluded that certain elements of the support structure are subjected to
very large shear forces. In order to increase the shear capacity, very high density foam is therefore applied,
type PMI foam 200s. Further design characteristics are listed in Table 20 [5].
Where; Xk is the characteristic value of a certain materials properties; m is the material factor and c the
conversion factor.
The skin material is quasi-isotropic and consists of 50% resin and 50% fiber from which 25% is orientated in
each direction: 0/ +45 / -45 / 90.
45
K.A.A. Watt
The strength of the skin material in each direction (for tension, compression and shear) is based on a single
strain criterion. This strain criterion is according the CUR 96 and amounts 1.2%. The characteristic values of
both skin material and core material are listed below:
= ,1 2
With:
m1: takes into account uncertainties in the material properties and is equal to 1.35
m2: takes into account uncertainties in the manufacturing process. For vacuum- and pressure injection a
partial factor of 1.2 applied.
With:
cv: conversion factor for moisture effects. For a FRP structure which is constantly exposed to humid
conditions, as is the case in this study, a partial factor of 1.3 is applied.
ck: conversion factor for creep. Since the structure is subjected to short impact loads this partial factor is
set as 1.0.
Table 21 indicates which partial conversion factors need to be applied for the different Limit States and is in
accordance to the CUR 96. The conversion factor for fatigue and creep only needs to be applied for stiffness
issues which are required for ULS design checks.
46
MSc Thesis
47
K.A.A. Watt
6.5.1 Material
This laminate stiffness matrix is used to express resultant forces (N) and resultant moments (M) in terms of
mid-plain strains () and mid-plain curvatures (). The matrix consists of thee sub-matrices: an extensional
stiffness matrix [A], a bending stiffness matrix [D] and an extension-bending coupling matrix [B].
When a composite is built up in an asymmetric manner, coupling may occur between normal forces and
bending moments described by matrix B. However also other coupling effects may arise, all shown in Figure 33.
48
MSc Thesis
Nevertheless, for this study both the skin material as the core material are chosen isotropic, which means that
the laminate is symmetric and the mechanical properties are similar in x- and y-direction. The coupling effects
can therefore be neglected and the terms showed in Figure 33 are equal to zero.
Regarding the design check of the sandwich plate, those cannot be achieved by modelling the Von Mises
equivalent stresses as is the case for the monolithic laminates. For sandwich panels the unity check must be
performed by comparing the local strain to the maximum strain criterion of 1.2%. The local strain variation in
the laminate can be calculated with the equation showed below, where z is the level within the laminate and
the other parameters are calculated through the ABD matrix.
0
[ ] = [ 0 ] + [ ]
0
6.5.2 Load
6.5.2.1 Modelling
The impact load is induced by the FSRU being pushed into the fender which is then transferred as a fender
reaction force onto the structure. This reaction force is referred to as the primary load and consists of:
The load (in x-direction) which is due to the direct impact of the vessel onto the fender.
Horizontal- (y-direction) and vertical friction loads (z-direction) at the interface between fender and
fender panel.
Since the vertical friction load is much larger than the buoyancy force, the structure has the tendency to move
up and down during impacts. This leads to a secondary friction forces along the piles shaft, at the interface
between steel and the low friction material (yet to be defined), see left Figure 34.
49
K.A.A. Watt
The vertical friction component is taken differently for ULS and FLS. For the ULS case, the horizontal impact
force is so large that the pile-head will not be able to slide in vertical direction. The maximum friction force is
thus taken as 0.4*Ffender (friction coefficient between fender and panel). For the FLS case the impact loads are
considerably less during which the pile-head will still be able to slide along the mono-pile. For this limit state
the maximum friction force is taken as 0.1* Ffender (friction coefficient between mono-pile and sleeve element).
The upward buoyancy force is a factor 17 smaller than the vertical friction load and is therefore neglected in
the model.
Also the chain loads are left out of consideration as they do not contribute to the general stability of the
system. In a more detailed phase however, the connection between the fender chains and fender panel must
be looked into.
Additionally, for every case, the fenders footprint is positioned at the bottom of the panel as this leads to the
most critical loads within the structure.
In the following section, the direct fender reaction force (in x-direction) is referred to as FF. The vertical- and
horizontal friction components are respectively described by FVER (z-direction) and FHOR (y-direction).
50
MSc Thesis
For the ULS 1 load case the fender is located centrally on the panel. Additionally, both friction coefficients are
taken as 0.4.
FF = ULS*7101 kN
FVER = 0.4*FF
FHOR = 0.4* FF
FVER = 0.4* FF
For this load case the horizontal friction load is not taken into account. It was already considered very
unfavorable having the load in an eccentric position. Besides, the probability of failure of the fender chains is
considered very small.
FF = ULS*7101 kN
FVER = 0.4* FF
FHOR = 0
FVER = 0.4* FF
For the FLS load case the fender is located centrally on the panel. The vertical friction coefficient is taken as 0.1
and the horizontal coefficient as 0.4.
FF = FLS*7101 kN
FVER = 0.1* FF
FHOR = 0.4* FF
FVER = 0.4* FF
FHOR = 0.4* FF
51
K.A.A. Watt
This Goodman diagram can be used to calculate the permissible load cycle numbers N and is in accordance to
GL [21];
, + |, | |2 , , , + |, ||
=( )
2 ( /1 ) ,
m: slope parameter of the S-N curve (m = 9 for laminates with polyester resin)
52
MSc Thesis
M: material factors
The fatigue life of the structure is checked based on a cumulative damage D D which is calculated by means of
Miners Law:
1 2
= = + + + 1
1 2
=1
The actual number of cycles (nc) of a certain stress range is divided by the allowable number of cycles (N c) for
that same stress range. This is done for all occurring stress ranges. The sum of this is referred to as the
cumulative damage number and shall not be larger than 1.
For the fatigue assessment, again, the Golar-project is used as a case study.
Regarding the pre-tensioned mooring lines, 16 are used for fastening of the FSRU; 12 breasting lines and 4
spring lines. In order to calculate the net resulting lateral force pushing the vessel towards the fenders, only the
breasting lines are taken into account. As the spring lines are mainly meant for longitudinal stability of the
moored ship their contribution to the lateral force is considered negligible.
The breasting lines applied in the Golar project consist of a standard ISO-2408, 8-strand steel rope with a steel
wire diameter of 56mm combined with a nylon tail with a diameter of 129.4mm and a Minimum Breaking Load
(MBL) of 3335kN. The pre-tensioning force is 3% of the MBL, leading to a force of 100kN in each line. The
resulting lateral force is obviously also depending on the fairleads positions.
53
K.A.A. Watt
The total lateral pre-tensioning force has then to be distributed over four fenders. Subsequently, the mean
force per fender (FF = 292.31kN) is inserted in SCIA Engineer in order to calculate the critical mean stresses for
the different elements of the pile-head. Since this pre-tensioning can be seen as a static force, the horizontal-
and vertical fender friction components are set equal to zero (FH = 0, FV = 0).
It must be noted that this approach is not fully correct for the elements consisting of sandwich laminates.
However, it already gives good estimation of the fatigue stresses and therefore the fatigue damage.
The alternating fatigue loads are time-varying impact loads. When modelling those within SCIA, the friction
components are taken into account (FH = 0.4*FF, FV = 0.1*FF).
54
MSc Thesis
The sleeve-element is a cylindrical bearing which is constructed of 40mm thick monolithic laminate with on the
inside a fabric of low friction material for smooth sliding operations.
The horizontal plates transfer the loads from fender panel in a circumferential manner to mono-pile. Those
elements contain high axial- and flexural rigidity in order to cope with respectively large normal forces and
bending moments. The horizontal plates consist of sandwich laminates with two outer skins of 20mm and a
foam core of 300mm.
The side plates increases the stiffness of the horizontal plates extremities. They prevent large deformations
and transfer horizontal loads directly into the membrane of the sleeve-element. The side plates are monolithic
laminates with a height of 400mm and thickness of 30mm.
The front plates increase the stiffness of the horizontal plates at the connection with the fender panel and
improve the load distribution within these horizontal plates. The front plates are monolithic laminates of
400mm high and 40mm thick.
The front panel is the element on which the fender is compressed. It consists of a sandwich laminate with two
outer skins of 10mm and a core of 250mm
The rear panel provides the back facing of the whole fender panel. This element distributes the fender loads
over the three horizontal plates. It has similar dimensions as the front panel.
The inner walls connects front- and rear panel. Also they function as vertical stiffeners for the front panel
increasing its flexural stiffness. The inner walls are 2m wide, 5.3m high and are built up as 30mm thick
monolithic laminates.
The top and bottom plates have as main function to keep the fender panel watertight as they do not really
contribute to load transfer. Those plates are 2m wide, 8.5m long and are 30mm thick monolithic laminates.
55
K.A.A. Watt
56
MSc Thesis
6.6.2 Dimensions
57
K.A.A. Watt
Because the loads are acting on the lower side of the fender panel, the lower horizontal plate takes up the
largest forces and is thus governing over the other two. Only the results of this plate are therefore illustrated.
58
MSc Thesis
The shear forces within these elements are induced by the vertical friction force. This shear component has to
be taken by the core, which has a maximum shear capacity of:
59
K.A.A. Watt
The largest shear forces are located in the middle of the horizontal plates, at the shortest distance between
fender panel and mono-pile. As is illustrated in Figure 47, the critical shear force (marked in orange and yellow)
is approximately 600kN/m (U.C. = 0.93). However at the intersection with the inner walls higher peak values
are modelled (until 730kN/m). Nevertheless, those peak values act on such small areas they are considered not
normative for the design.
The critical stresses are found at two locations: where the horizontal plates have a tendency to deform and at
the corners on the fender panels side. The signs plus and minus indicate respectively the upper and lower side
of the plate.
60
MSc Thesis
61
K.A.A. Watt
The most critical location is situated at the connection with the front plates, at the level of the load. On that
location the corresponding critical loads are:
The shear capacity of this element is determined by the thickness of the core and is equal to:
62
MSc Thesis
The shear forces in the rear panel are induced by the horizontal fender load. The maximum values are at the
intersection with the horizontal plates, those amount approximately 520kN/m (U.C. = 0.97). However, some
extreme peak values are modelled (until vX = 589.28kN/m). These values can be explained by the fact that SCIA
doesnt model the front plates as separate structures, but as a local thickening of the rear-panel. Also, since
those values act on such a small area, they are considered negligible for the design.
63
K.A.A. Watt
The most critical loads are located at the level where the fender is compressed.
The maxima strains, which are calculated through the ABD-matrix, are checked according the strain criterion of
1.2%.
64
MSc Thesis
The shear forces in the front panel are induced by the horizontal fender load, which result in a maximum shear
force within the structure of 268.96kN/m (U.C. = 0.5) and therefore fulfilling the shear requirement.
Figure 59 Left: sigE-, Right: sigE+, plots of the top- & bottom plate
65
K.A.A. Watt
The contribution of this element to load transfer, compared to the inner walls, is very small. The occurring
stresses are therefore insignificant.
6.6.4 Buoyancy
Since a floating structure is chosen, buoyancy is a critical issue in the design. The fender panel must be large
enough to provide the whole structure with enough floating capacity. In this section this issue is checked.
SUPPORT STRUCTURE
Sleeve element Monolithic (30mm) 1.499 0 2772
Horizontal plates Sandwich (340mm) 1.386 10.393 3343
Side plates Monolithic (30mm) 0.260 0 480
Front plates Monolithic (40mm) 0.408 0 755
FENDER PANEL
Rear panel Sandwich (270mm) 0.901 11.263 2512
Inner walls Monolithic (30mm) 3.498 0 6471
Upper and lower plates Monolithic (30mm) 1.020 0 1887
Front panel Sandwich (270mm) 0.901 11.2625 2512
Total weight [kg] 20732
Buoyancy surface [m] 16
Draught [m] 1.26
Table 33 Buoyancy calculations
=
( )
Where:
As can be seen from Table 33, the structure has a draught of 1.26m and the floating capacity is thus sufficient.
If a larger draught is required, extra ballast can be added.
66
MSc Thesis
6.6.6 Joints
In general structurally joining composite sections can be achieved in three different manners: mechanically,
adhesively and a combination of both [25].
For mechanical joints, fasteners are applied such as rivets or bolts. The main advantage of such type of joints is
its well-known behavior to stresses and failure mechanisms. Additionally, mechanical joint can reach high
stress capacities. On the other hand, they are very fatigue sensitive as they lead to concentrated stresses and
thus to initiation of cracks.
Bonded (adhesive) connections do have a high fatigue- and impact resistance as they have a uniform stress
distribution. Their overall capacity, however, is lower than that of a mechanical connection. Also quality control
is more difficult and costly.
For combined joints, both mechanical fasteners and adhesive are used. The fatigue stresses can be resisted by
the adhesive while high peak stresses, leading to failure of the adhesive, can be taken over by the fasteners to
secure the structural integrity.
Critical connection
For this study only the most critical joint will be investigated. For the conceived pile-head this regards the
connection between the sleeve member and the horizontal plates. This connection, which connects a flat
element to a curved element, is not only geometrically problematic but it is also subjected to high
concentrated loads during large impacts. These high concentrated loads make the use of an adhesive-only not
possible as its capacity is insufficient without applying a large overlap joint [8].
Next to very large impact loads, fatigue loads are of great importance which makes the use of solely
mechanical joints not possible. Furthermore, placements of fasteners within the sleeve-element will hinder the
sliding capabilities of the pile-head. For this latter reason the application of a combined joint is also not
possible. [20]
The only method which can be applied is thus connecting both elements during the construction process. This
can be achieved by extending the fibers out of the sleeve-element as is illustrated in Figure 60. Subsequently
those are connected within the horizontal plates creating a stiff connection. Supplementary reinforcement
67
K.A.A. Watt
fibers may be added increasing the strength of the connection and preventing it from becoming a weak spot in
the structure. Detailed calculations regarding this issue are however out of the scope of this thesis
Additional fiber-reinforcement
Decreased mono-pile
diameter
Conical transition
Mono-pile
68
MSc Thesis
7 Discussion of results
In this chapter the results of the previous chapters are summarized and discussed.
7.1 Part 1
In part 1 a method is presented for the estimation of the design loads on the mooring system. The underlying
idea behind this method is the separation of the environmental components. The loads on the structure due to
wave-action are obtained through a wave height-fender deflection relationship. The loads due to winds and
currents are calculated as quasi-static drag forces.
The results of Part 1 are summarized in Table 35. The accuracy of the assessment tool was tested by comparing
the outcome of the calculated results to the MPM-results for varying conditions.
From the abovementioned table is concluded that the assessment tool can generate rather accurate results.
However, some important aspects should be enlightened.
The first one being that stiff fender cases always leads to larger fender loads than softer cases. Relating wave
height to fender deflection thus not totally eliminates the influence of the applied fender.
Another interesting aspect is that, in general, the fender loads are slightly overestimated, except for the Golar
tsunami case where relatively small values were generated. For larger current velocities the corresponding
forces are thus largely underestimated.
The fender loads calculated for larger wave heights are slightly larger than the ones resulting from the DMA
runs, thus the positive error margin. This may be explained by the lack of DMA-data for such larger wave
heights. The trend line drawn through these data points is therefore not as accurate as for smaller wave
heights.
7.2 Part 2
For Part 2 standardization of the mono-piles was researched. This is done by investigating the influence of the
soil and of the load on the pile design. From the obtained results, the conclusion is drawn that a generalized
pile design is not possible since the dimensions (diameter, thickness and length) differ too much. The limits are
consequently redefined.
A strict distinction between stiff- and a soft soil profiles is established, where in reality soil profiles could be a
combination soft soil layers and stiff soil layers. In addition a distinction is made between different classes of
environmental conditions; mild, moderate and harsh. For each of the abovementioned combinations a
standardized pile design is made as is shown in Table 36. Subsequently, for each class, the over-dimensioning
costs were calculated.
69
K.A.A. Watt
Environmental condition
Soil profile Dimensions
Mild Moderate Harsh
t [mm] 45 50 55
Stiff sand
D [mm] 3300 3800 4100
profile
L [m] 42.5 45 47.5
t [mm] 50 55 60
Soft clay
D [mm] 3400 3900 4300
profile
L [m] 65 70 80
Table 36 Standardized pile designs for varying conditions
The over dimensioning costs for stiff soil profiles vary between 0 and 0.15 million USD, while those for soft soil
profiles vary between 0 and 0.35 million USD. This can be explained by the fact that the variation in pile length
is much larger for the softer soils.
If the FSRU import terminal must be designed for water depths larger than 16m, the standardized pile designs
have to be rescaled. This can be achieved by means of the rescaling parameters mentioned in Table 38 which
are valid for an increased water depth-case of 26m.
Rescaling parameters
Dimensions
for 26m water depth
Thickness + 5 mm
Diameter + 400 mm
Length + 12.5 m
Table 38 Rescaling parameters for 26m water depth
The fatigue life of the mono-pile dolphins is assessed by means of a case-study. The calculated cumulative
damage factor is far below one (0.0782 << 1); fatigue damage is therefore proven insignificant for the Java Sea
without considering pile-driving.
7.3 Part 3
The designed floating pile-head is constructed of two main elements: the fender panel and the support
structure. The fender panel consists of an empty box-element which provides floatation capacity for the whole
structure and a continuous facing for the compressed fender. The support structure consists of horizontal plate
elements, which transfer the loads to the mono-pile, and a sleeve element which slides along the pile shaft.
The pile-head was designed with FRP composite of which two types of laminates were applied: monolithic
laminates consisting of a single skin and sandwich laminates which are constructed of two skins separated by a
70
MSc Thesis
core in the middle. This latter construction was primarily used for the structural elements which were
subjected to large shear forces and bending moments.
The application of FRP composite resulted in a very light weighted construction, only 21 tons. This mostly
improves floating issues as the structure reaches a draught of only 1.26m. This lightweight is also favorable for
installation operations as low hoisting capacity is required compared to a conventional fixed, steel pile-head.
Fatigue is considered to be insignificant. The fatigue damage was calculated for multiple elements of the pile-
head as is listed in Table 39. The cumulative damage numbers (DD) are far below 1, proving once more the high
fatigue resistance of composite structures.
The geometrical boundary of the sliding-element, which is the outer diameter of the applied mono-pile, can be
overcome by constructing a conical transition. A certain pile-head can therefore be applied for a large range of
different pile sizes, enhancing its standardization capabilities.
In the following table a feedback-loop is made, re-evaluating the designed pile-head on the criteria selected for
the MCA.
The structure is designed such that the loads are transferred in an efficient and
Robustness Pro well-distributed manner to the mono-pile. Additionally composite has good
impact properties.
The application of composite leads to good capabilities of withstanding wear and
Durability Pro tear. Creep-effects may play a role; however, the permanent pre-tensioning load
is very small and this effect therefore negligible.
The application of composite results in a structure which require low maintenance
Maintenance Pro
works. Corrosion is not an issue.
The ease to repair broken components may be troublesome, but thats not
Reparability Neutral
different for other pile-head structures.
Fatigue
Pro The structure has very high fatigue resistance and high material damping.
resistance
Constructability is an issue. Problematic are: the connection between the sleeve-
Constructability Con element and the horizontal support plates, and the attachment of the low friction
material within the sleeve-element.
The low self-weight of the structure facilitates hoisting and installation of the pile-
Installation Pro
head onto the mono-pile.
71
K.A.A. Watt
FRP composite has high initial costs. However, since the pile-head is floating, the
amount of material required can significantly be reduced for locations with large
Costs Neutral
tidal variations. Furthermore, since the pile-head has good durability properties, it
may be re-used for other projects (if still in good condition).
Accessibility of the pile-head for inspection and maintenance works is more
Accessibility Con
difficult for floating pile-heads than for fixed ones
FRP composite has generally a high carbon footprint [9]. Additionally, during fires
Sustainability Con
chemical gasses may be released.
72
MSc Thesis
8.1 Part 1
Part 1 describes a standardized method to visualize the analysis results of the fender loads due to FSRU
motions. From the results can be concluded that a standardized assessment tool is possible within certain
limits.
However, in order to fully validate such tool, still more DMA-data is required, especially for larger waves (HS >
1.5m).
The current assessment tool has some restrictions as it is designed for very limited environmental conditions. It
would therefore be interesting to investigate expansion possibilities by applying the same design procedure for
other type of environmental conditions and see if a similar level of accuracy can be obtained. Interesting
environmental conditions to analyze would be, e.g., swell waves or different types of wind loadings.
As was concluded from the results, the fender force due to larger current velocities (2 m/s) is severely
underestimated. Additional DMA-runs should be performed and new parameters should be introduced in order
to obtain more accurate results. Perhaps find a factor, similar to the gust factor of wind, by which the current
velocity can be multiplied.
8.2 Part 2
The main idea behind standardization is to save costs and schedule of the civil structures of a jetty-type
mooring system on exposed locations. Part 2 concluded that standardization of the mono-piles can only be
achieved to a certain extent, namely in a conceptual design phase.
In this report a standardized work approach is presented. The same starting points and design procedure can
be followed in order to reduce the start-up time of the project.
The results discussed in Part 2 can be used in order to get a first indication of pile dimensions. With very little
information (soil type and loading) a quick estimate of the design can be made. The over-dimensioning costs of
these standardized designs are calculated to be relatively small compared to the total costs of an FSRU-project
and therefore considered very acceptable in an early design stage.
More detailed standardization designs can be possible for very site-specific locations, where the geotechnical-
and environmental conditions do not differ much. For these limited locations, still, multiple FSRU-projects
would be necessary in order to make standardization of its mooring facility feasible. A thorough LNG-market-
study is therefore recommended, determining the areas where many FSRU-projects are to be expected before
looking into standardization of the civil structures.
For locations with bad soil conditions standardization could be combined with soil improvement, by removing
poor soil and replacing it with dense sand. The variation in pile length, due to varying load conditions, would
significantly be reduced. An economic feasibility study is recommended comparing the costs of soil
improvement to the costs of excess steel.
The fatigue damage of the mono-piles is calculated to be insignificant for the case-study. This calculated value,
however, is not so small that fatigue can be neglected for all cases; for a mooring system on exposed locations
73
K.A.A. Watt
a fatigue assessment should always be performed. Nevertheless there are some aspects that can be taken into
account in order to significantly reduce this fatigue damage;
For moorings on exposed locations only foam filled floating fenders should be applied with nearly flat
force-deflection curve. The application of other types of fenders will result in a considerable increase
of fatigue damage.
The misalignment between two consecutive pile-sections has to be reduced as much as possible.
Well executed butt welds should be applied which should be grinded flush.
For locations where many storms are expected, a threshold can be introduced above which the FSRU
should be temporarily relocated.
8.3 Part 3
In Part 3 the pile-head concept is presented which is the most suitable for standardization purposes, namely
a FRP composite, floating structure with a slide-bearing sliding system.
The application of composite in exposed marine environment has some major advantages. Its fatigue
resistance and high material damping are much desired properties since the exerted load is of cyclic nature. Its
lightweight enhances buoyancy and facilitates installation, while its low maintenance and corrosion resistant
properties results in a very durable material.
The form of the pile-head is optimized for its application. The slide-bearing system contains at the inner side a
fabric of low friction material which allows smooth sliding along the mono-pile. The horizontal support plates
transfer the loads in an efficient manner to the mono-pile, while the fender panel provides a continuous facing
for the fender and enough buoyancy for the system.
In this study general stability of the structure was looked at, however still some technical details must be
further investigated:
The slide bearing-system requires more detailing, in particular the interface between the low friction
material and the steel-mono-pile.
Accumulation of water will occur on the top of the horizontal plates. A drainage system must
therefore be designed.
The contact between the pile-head and the FSRU-vessel must be investigated. A scale model could
give a good insight in whether or not the system (pile-head + vessel) will behave as expected.
The connection of the fender chains to the fender panel must be designed.
The corners of the structural elements can be smoothened improving the load distribution and
reducing the magnitude of local peak-loads.
Next to technical details it is also advisable to perform a thorough economic feasibility study and compare it to
conventional fixed solutions. Not only direct costs should be taken into account, such as material-,
construction-, and maintenance costs. But also durability and environmental effects need to be included.
74
MSc Thesis
9 References
[1] API, American Petroleum Institute (2010). API-2A-LRFD, Recommended practice for planning,
designing and constructing fixed offshore platforms Load and Resistance Factor Design.
[2] Arnout de Pee (2005). Operability of a floating LNG terminal; the influence of operating limits for the
approach, transfer and departure cycle on the weather downtime.
[3] Bangladesh University of Engineering and Technology (2002). Lecture: Undrained and drained shear
strength. URL: http://teacher.buet.ac.bd/sid/download/CE341/lecture11_4on1.pdf
[4] BSI, British Standard Institute (1989). BS 6349 - 6:1989, Code of practice for marine structures, Part 6:
design of inshore moorings and floating structures.
[5] Clarke JL. (1996). Structural Design of Polymer Composites, EUROCOMP Design Code and Handbook.
[6] CEE, Center for Energy Economics (2006), Offshore LNG receiving terminal.
[7] CUR-96, Civieltechnisch Centrum Uitvoering Research en Regelgeving, Aanbeveling 96 (2003).
Vezelversterkte kunststoffen in civiele draagconstructies.
[8] Dat Duthinh (2000). Connection of Fiber-Reinforced Polymers (FRP) Structural Members: A Review of
the State of the Art.
[9] Delft University of Technology, Trude Maas, Jarit de Gijt, David Dudok van Heel. Comparison of quay
wall designs in concrete, steel, wood and composites with regard to CO2-emisison and the Life Cycle
Analysis
[10] Delft University of Technology (2011). Manual Hydraulic Structures, CT3330.
[11] Deshpande (2012), The design of sandwich panels with foam cores, Cambridge University.
[12] DNV, Det Norske Veritas (2008). DNV-OS-C101, Design of offshore steel structures, general (LRFD
method).
[13] DNV, Det Norske Veritas (2010). DNV-RP-C203, Fatigue design of offshore steel structures.
[14] DNV, Det Norske Veritas (2010). DNV-RP-C205, Environmental conditions and environmental loads,
October 2010
[15] Dr. Ann Schumacher (2010). Lecture: Design of FRP-Profiles and All-FRP-Structures.
[16] Eindhoven University of Technology, ABD-matrix:
URL: http://www.mate.nl/~piet/edu/dos/pdf/linlam.pdf
[17] EN, European Standard (2007). EN 1996-1-6, Euro code 3, Design of steel structures, Part: 1-6 Strength
and Stability of Shell Structure, February 2007.
[18] Ernst & Young (2013), Global LNG - Will new demand and new supply mean new pricing?
[19] FenderTeam. Product catalogue
[20] Fiberline (2003). Fiberline Design Manual. URL: www.fiberline.dk
[21] GL, Germanischer Lloyd (2005). Rules and Guidelines IV, GL Wind Energy.
[22] Golar. Golar LNG catalogue, Floating Storage and Regasification Unit FSRU
[23] Gurit. Guide to Composite. URL: http://wwwgurit.com/
[24] Howard E. Boyer. Atlas of Fatigue Curves
[25] J.C. Moen (2014). Feasibility Study on Heavy-Traffic FRP Bascule Bridges, Delft University of
Technology.
nd
[26] John W. Gaythwaite. Design of Marine Facilities for the Berthing, Mooring and Repair of Vessels, 2
Edition
[27] LNG Floating Storage Regasification Unit International Conference (2014). URL: http://fsru.informa-
mea.com/
75
K.A.A. Watt
[28] NEN, Dutch Standards Insitute (2012). NEN-EN 1993-1-9+C2:2012, Eurocode 3, Design of steel
structures, Part: 1-9 Fatigue.
[29] Novascotia. Wood utilization and Technology; Physical and Mechanical properties wood. URL:
http://novascotia.ca/
rd
[30] OCIMF, Oil Companies International Marine Forum. Mooring Equipment Guidelines, 3 Edition
[31] Refitech. Carbon components. URL: http://www.refitech.nl/
th
[32] Royal Haskoning (2011). Presentation Golar FSRU West Java Mooring Facilities, 6 of October 2011.
th
[33] Royal HaskoningDHV (2012). Aqaba LNG Terminal, Design Basis Report infrastructure, 7 of
November 2012.
st
[34] Royal HaskoningDHV (2012). Aqaba LNG Terminal, Preliminary Dynamic Mooring analysis, 31 of
January 2012.
[35] Royal HaskoningDHV (2012). Golar Floating LNG Terminal West Java; Basis of a detailed design of the
th
FSRU Mooring arrangement and gas transfer platform, 13 of April 2012.
[36] Royal HaskoningDHV (2012). Golar Floating LNG Terminal West Java; Design report breasting dolphins,
th
13 of April 2012.
[37] Royal HaskoningDHV (2012). Golar Floating LNG Terminal West Java; Dolphin head design report
th
breasting dolphin, 13 of April 2012.
th
[38] Royal HaskoningDHV (2012). Golar Floating LNG Terminal West Java; Dynamic Mooring Analysis, 13
of April 2012.
[39] SHELL. Liquefied Natural Gas. URL: http://www.shell.com/
[40] Ticona. GUR - product brochure, Ultra High Molecular Weight Polyethylene (PE-UHMW)
[41] Trelleborg Marine Systems. Catalogue, Safe berthing and Mooring
[42] Unitrove. Natural gas and LNG density calculator. URL: http://www.Unitrove.com/
[43] Vincent Calard (2011). Formulas and equations for the classical laminate theory.
URL: http://www.aac-research.at/downloads/Formula-collection-for-laminates.pdf
[44] OTEO Conference (2012). An overview of SBM mooring systems.
76
MSc Thesis
10 List of Symbols
Assessment tool
Geotechnical modelling
D Pile diameter m
t Wall thickness m
L Pile length m
V Shear stress due to shear force MPa
Vd Shear force kN
R Outer radius m
r Inner radius m
Izz Moment of inertia m
Sz First moment of area m
M Bending stress due to bending moment MPa
Md Bending moment kNm
W Section modulus m
N Normal stress due to normal force MPa
Nd Normal force kN
77
K.A.A. Watt
A Cross-sectional area m
T Torsional stress due to torsional moment MPa
Td Torsional moment kNm
Ip Polar moment of inertia m
d Meridional stresses MPa
d Shear stresses MPa
vm,d Von Mises equivalent yield strength MPa
fyd Design yield strength MPa
Rd Design buckling strength MPa
Buckling reduction factor -
Fatigue analysis
Factors
M Material factor -
C Conversion factor -
78
MSc Thesis
11 List of Abbreviations
ALS Accidental Limit State
API American Petroleum Institute
BD Breasting Dolphin
BS British Standards
CAPEX Capital Expenditure
CBM Conventional Buoy Mooring System
CD Chart Datum
CUR Civieltechnisch Centrum Uitvoering Research en Regelgeving
DFF Design Fatigue Factor
DMA Dynamic Mooring Analysis
DNV Det Norske Veritas
EN European Standard
FLS Fatigue Limit State
FSRU Floating Storage and Regasification Unit
FRP Fiber Reinforced Polymers
GL Germanischer Lloyd
IEA International Energy Agency
LNG Liquefied Natural Gas
LNGC LNG Carrier
LTF Load Transfer Function
MBL Minimum Breaking Load
MCA Multi Criteria Analysis
MD Mooring Dolphin
MPM Most Probable Maximum
NEN Dutch Standards Institute
OCIMF Oil Companies International Marine Forum
PTFE Polytetrafluoroethylene (= Teflon)
RAO Response Amplitude Operators
RP Return Period
SCF Stress Concentration Factor
SLS Serviceability Limit State
SPM Single Point Mooring Systems
UHMWPE Ultra High Molecular Weight Polyethylene
ULS Ultimate Limit State
USD United States Dollar
79
K.A.A. Watt
12 List of Figures
Figure 1 The LNG supply chain ................................................................................................................................ 1
Figure 2 Jetty-type mooring system; side-by-side mooring configuration between FSRU and LNGC ..................... 3
Figure 3 Schematic representation of a mono-pile breasting dolphin. * Not scaled............................................... 4
Figure 4 Wave height/wave period correlation used in the DMA's ......................................................................... 9
Figure 5 Direction according to the Cartesian convention [34] ............................................................................... 9
Figure 6 Picture of a Cell fender and its corresponding force-deflection curve ..................................................... 10
Figure 7 Picture of a Foam filled floating fender and its corresponding force-deflection curve ........................... 10
Figure 8 Wave height / fender deflection .............................................................................................................. 11
Figure 9 Drag force components. Blue arrow represents incoming metocean conditions .................................... 12
Figure 10 Coefficient Alpha - incoming direction (according to the Cartesian convention [34]) ........................... 12
Figure 11 Fender curves applied in the reference projects .................................................................................... 13
Figure 12 Schematic representation of the p-y method ........................................................................................ 19
Figure 13 Illustration of working bending stresses and shear stresses ................................................................. 22
Figure 14 Example of a time series and time segment needed for fatigue assessment ........................................ 23
Figure 15 Section through weld............................................................................................................................. 24
Figure 16 Transverse butt weld, welded from both sides. .................................................................................... 24
Figure 17 Design load / Pile diameter; green: stiff soil, blue: soft soil .................................................................. 27
Figure 18 Design load / Wall thickness; green: stiff soil, blue: soft soil ................................................................. 27
Figure 19 Design load / Pile length; green: stiff soil, blue: soft soil ....................................................................... 28
Figure 20 Design load / Material costs; green: stiff soil, blue: soft soil ................................................................. 28
Figure 21 Over-design in case of standardization [USD]; green: stiff soil profile, blue: soft soil profile ................ 30
Figure 22 Foam filled floating fender. Left: floating position, Right: fixed position .............................................. 33
Figure 23 Steel fender panel connected with steel horizontal support plates to the mono-pile ........................... 34
Figure 24 Fixed concrete cap on top of the mono-pile .......................................................................................... 34
Figure 25 Floating composite cube ....................................................................................................................... 35
Figure 26 Floating steel tubular support structure ................................................................................................ 35
Figure 27 Floating composite fender panel with horizontal support plates .......................................................... 36
Figure 28 Floating concrete fender panel with vertical steel support plates ........................................................ 36
Figure 29 Mounting area foam filled floating fender [41] .................................................................................... 42
Figure 30 Material properties FRP Composite [23] ............................................................................................... 44
Figure 31 Left: Stacking sequences, Right: Sandwich panel loading [23] .............................................................. 44
Figure 32 ABD-matrix [43] ..................................................................................................................................... 48
Figure 33 Coupling effects [16] ............................................................................................................................. 49
Figure 34 Schematization of the modelled pile-head within SCIA Engineer .......................................................... 50
Figure 35 Position of the modelled load for ULS 1- load case ............................................................................... 51
Figure 36 Position of the modelled load for ULS 2- load case ............................................................................... 51
Figure 37 Position of the modelled load for FLS- load case ................................................................................... 51
Figure 38 Time series of varying fender load ........................................................................................................ 52
Figure 39 Goodman diagram [21] ......................................................................................................................... 52
Figure 40 Mooring lay-out, Golar-project in the Java Sea *Dimensions in meters ............................................... 53
Figure 41 Front view final design pile-head .......................................................................................................... 56
Figure 42 Rear view final design pile-head............................................................................................................ 56
Figure 43 Top- and Side view of the pile-head including dimensions .................................................................... 57
Figure 44 Left: Nx, Right: Ny, plots of the horizontal plates .................................................................................. 58
80
MSc Thesis
Figure 45 Left: Nxy, Right: Mxy, plots of the horizontal plates ............................................................................. 58
Figure 46 Left: Mx, Right: My, plots of the horizontal plates ................................................................................ 59
Figure 47 Left: Vx, Right: Vy, plots of the horizontal plates .................................................................................. 59
Figure 48 Left: sigE-, Right: sigE+, plots of the side plates .................................................................................... 60
Figure 49 Left: sigE-, Right: sigE+, plots of the front plates................................................................................... 60
Figure 50 Left: Nx, Right: Ny, plots of the rear panel ............................................................................................ 61
Figure 51 Left: Nxy, Right: Mxy, plots of the rear panel ........................................................................................ 61
Figure 52 Left: Mx, Right: My, plots of the rear panel .......................................................................................... 62
Figure 53 Left: Vx, Right: Vy, plots of the rear panel ............................................................................................. 62
Figure 54 Left: Nx, Right: Ny, plots of the front panel ........................................................................................... 63
Figure 55 Left: Nxy, Right: Mxy, plots of the front panel ...................................................................................... 63
Figure 56 Left: Mx, Right: My, plots of the front panel ......................................................................................... 64
Figure 57 Left: Vx, Right: Vy, plots of the front panel ........................................................................................... 64
Figure 58 Left: sigE-, Right: sigE+, plots of the inner walls .................................................................................... 65
Figure 59 Left: sigE-, Right: sigE+, plots of the top- & bottom plate ..................................................................... 65
Figure 60 Fabrication procedure of the critical joint ............................................................................................. 68
Figure 61 Conical transition .................................................................................................................................. 68
Figure 62 Regasification unit on the FSRU ............................................................................................................ 86
Figure 63 LNG storage tank systems ..................................................................................................................... 87
Figure 64 Picture of a Tower Yoke Mooring System .............................................................................................. 88
Figure 65 Picture of a Conventional Buoy Mooring system .................................................................................. 88
Figure 66 Picture of a Single Point Mooring System ............................................................................................. 89
Figure 67 Picture of a Turrets Mooring System ..................................................................................................... 89
Figure 68 FSRU mooring arrangement - Golar project .......................................................................................... 92
Figure 69 FSRU mooring arrangement Aqaba project ....................................................................................... 95
Figure 70 Fender curves applied for the comparison ............................................................................................ 99
Figure 71 Maximum fender force [kN] per incoming direction, Golar project, Foam fender .............................. 101
Figure 72 Hs / fender deflection .......................................................................................................................... 103
Figure 73 Fender curve for the Ocean Guard-type with a maximum reaction force of 5967 kN ........................ 103
Figure 74 Coefficient alpha / incoming direction ................................................................................................ 104
Figure 75 Schematic representation of systems with different rigidities ............................................................ 106
Figure 76 Results of the method for determination of design fender loads ........................................................ 108
Figure 77 Characteristic shapes of p-y curves for soft clay below water table: cyclic loading (Matlock) ........... 110
Figure 78 Relation between pile diameter (d) and correction factor (c) ............................................................. 110
Figure 79 Characteristic shapes of p-y curves for stiff clay below water table: cyclic loading (Reese et al) ....... 111
Figure 80 Values of constants As (static loading) and Ac (cyclic loading) ........................................................... 112
Figure 81 Left: values C1, C2, C3; Right: Initial modulus of subgrade reaction ................................................... 113
Figure 82 Soft clay profile - Design load / Pile diameter; light blue: 16m water depth, dark blue: 26m water
depth ................................................................................................................................................................... 120
Figure 83 Soft clay profile - Design load / Wall thickness; light blue: 16m water depth, dark blue: 26m water
depth ................................................................................................................................................................... 120
Figure 84 Soft clay profile - Design load / Pile length; light blue: 16m water depth, dark blue: 26m water depth
............................................................................................................................................................................ 121
Figure 85 Stiff sand profile - Design load / Pile diameter; light green: 16m water depth, dark green: 26m water
depth ................................................................................................................................................................... 122
Figure 86 Stiff sand profile - Design load / Wall thickness; light green: 16m water depth, dark green: 26m water
depth ................................................................................................................................................................... 122
81
K.A.A. Watt
Figure 87 Stiff sand profile - Design load / Pile length; light green: 16m water depth, dark green: 26m water
depth ................................................................................................................................................................... 123
Figure 88 S-N curve; steel vs. composite ............................................................................................................. 127
82
MSc Thesis
13 List of Tables
Table 1 Density of Natural gas and LNG [42] .......................................................................................................... 1
Table 2 Global demand of Natural Gas and LNG .................................................................................................... 1
Table 3 Error margins of the calculated results ..................................................................................................... 14
Table 4 Geometrical parameters for the soft- and stiff soil case .......................................................................... 16
Table 5 Applied load- and material factors for the calculations of the mono-piles .............................................. 17
Table 6 Distribution of number of cycles for alternating loads ............................................................................. 23
Table 7 Parameters S-N curve C1 in seawater with cathodic protection .............................................................. 25
Table 8 Pile designs for varying design loads and soil profiles; L is the total length of the pile, D is the outer
diameter and t the wall thickness ...................................................................................................................... 26
Table 9 Standardized pile dimensions for different combinations of environmental- and geotechnical conditions
.............................................................................................................................................................................. 29
Table 10 Over-dimensioning costs compared to the total costs per mono-pile .................................................... 30
Table 11 Increased pile dimensions for an a water depth of 26m ........................................................................ 31
Table 12 Results of the fatigue calculations of the mono-pile .............................................................................. 31
Table 13 Sliding directions and load distribution of a slide bearing ...................................................................... 37
Table 14 Criteria applied for the MCA ................................................................................................................... 38
Table 15 Weighing factors applied for the MCA ................................................................................................... 38
Table 16 Results of the MCA ................................................................................................................................. 39
Table 17 General pros and cons of FRP composite................................................................................................ 40
Table 18 Fender characteristics, Ocean Guard-type 3.3 x 6.5 ............................................................................... 41
Table 19 Applied factors for the calculations of the pile-head .............................................................................. 43
Table 20 Mechanical properties skin- and core material ...................................................................................... 46
Table 21 Conversion factors for the different Limit States .................................................................................... 47
Table 22 Resulting lateral pre-tensioning force .................................................................................................... 54
Table 23 Critical loads horizontal plates ............................................................................................................... 59
Table 24 Maximum strains horizontal plates ........................................................................................................ 59
Table 25 Critical stresses, side plates .................................................................................................................... 60
Table 26 Critical stresses, front plates................................................................................................................... 61
Table 27 Critical loads, rear panel ......................................................................................................................... 62
Table 28 Maximum strains rear panel .................................................................................................................. 62
Table 29 Critical loads, front panel ....................................................................................................................... 64
Table 30 Maximum strains front panel ................................................................................................................. 64
Table 31 Critical stresses, inner walls .................................................................................................................... 65
Table 32 Critical stresses, top & bottom plates ..................................................................................................... 66
Table 33 Buoyancy calculations ............................................................................................................................ 66
Table 34 Results fatigue assessment pile-head ..................................................................................................... 67
Table 35 Error margins, assessment tool .............................................................................................................. 69
Table 36 Standardized pile designs for varying conditions ................................................................................... 70
Table 37 Over-dimensioning costs compared to the total costs ........................................................................... 70
Table 38 Rescaling parameters for 26m water depth ........................................................................................... 70
Table 39 Fatigue results, pile-head ....................................................................................................................... 71
Table 40 Re-evaluation of the pile-head on the MCA criteria ............................................................................... 72
Table 41 Input- and output parameters a DMA .................................................................................................... 90
Table 42 Dimensions 125.000m3 spherical LNGC ................................................................................................. 92
83
K.A.A. Watt
84
MSc Thesis
14.1 Introduction
In this Appendix first a closer look is taken in the FSRU operations (14.1), namely the offloading process, the
storage of LNG and finally the regasification process and delivery of the LNG. Then the main components of the
FSRU will be described (14.2) and finally the main components of the FSRU mooring system will be dealt with
(14.3).
After the LNGC arrives at the FSRUs location, it will be positioned parallel to the FSRU aligning the manifolds of
both vessels. With the assistance from tugs the LNGC is maneuvered alongside the FSRU for the offloading of
the cargo in a so-called side-by-side mooring configuration. After berthing a combination of transverse mooring
lines and spring lines will be used to limit horizontal relative motions.
After the LNGC is securely moored, the offloading of the LNG can begin by means of loading arms. After the
offloading operations 5 to 10% of the cargo will be kept onboard. This is referred to as the heel and this is
required for tank cooling during the return voyage.
On completion of offloading, the loading arms are disconnected and the LNGC can be un-berthed. Tugs will
then secure the LNGC while the mooring lines and spring lines are released. Thereafter the LNGC will be pulled
away by tugs until sufficient distance is reached in order to sail away safely.
Operation with two LNG arms will ensure a loading time of 16 hours. Berthing, loading and un-berthing will
take approximately 24 hours. [22]
The storage tanks of the FSRU not only serve as immediate storage of LNG when a carrier is offloading, but also
works as a buffer in case the supply and demand of LNG fails. The storage capacity of the FSRU must therefore
3
be sufficient in order to supply natural gas for base load operations in a continuous matter and supply for
some peak demand events. Furthermore enough storage capacity is required to compensate delays in
4
shipments and limit demurrage .
14.3 The regasification process and the delivery of LNG from FSRU to land
When the consumer demands the gas, the LNG has to processed back into its gaseous state and transported by
pipeline to its desired location.
3
Base load operations = natural gas supply that must always be delivered on a daily basis [6]
4
Demurrage = detention or delay of a tanker due to loading or unloading [6]
85
K.A.A. Watt
LNG is sent from the tanks to the regasification unit situated forward, see Figure 62. The regasification unit
essentially comprises booster pumps and steam heated vaporizers. The booster pumps will increase the
pressure, before the high pressure LNG is vaporized after which the gas is sent to the subsea pipeline via
jumpers and flexible risers. [22]
Regasification Unit
When considering FSRUs which have been converted from LNGC four LNG tank systems can be distinct; two
self-supporting tank systems and two membrane tank systems.
Membrane tanks, unlike self-supporting tanks, are embedded in the ship structure utilizing the hull shape more
efficiently and thus having less space between the storage tanks for the LNG and the ballast tanks. As a result
membrane tank systems are cheaper than self-supporting tank systems. The two membrane types are the GTT
Mark III and the GTT No.9
On the other hand, self-supporting tank systems are far more robust and have greater resistance to sloshing
forces. Membrane types may break due to sloshing impact, therefore destroying the ships hull. The self-
supporting tank systems are thus the preferred type where rough environmental conditions are a significant
factor. The two self-supporting types are the Moss (spherical) and the IHI-SPB (prismatic). The storage tank
systems are depicted in Figure 63. The membrane type systems have the same shape and are therefore
illustrated as one.
86
MSc Thesis
Regasification system
Sea water pumps which are used to pump seawater to the vaporizers
Vaporizers warm up the LNG so that it can be transformed back to its natural gaseous state.
Booster pumps pump the LNG under high pressure into the vaporizers
Boil of Gas (BOG) compressors, compresses gas that boils off (resulting in vaporization of the LNG).
This compressed boil-off gas is typically added to the natural gas send-out. It may also be re-liquefied
and returned to the LNG storage tanks.
Loading arms
Loading arms are used to transfer the LNG from the LNGC to the FSRU. Standard loading arms are placed on
5
one side of the FSRU and allow side-by-side transfer of LNG and vapor return . The loading arms will be quite
similar to the type that is used on onshore terminals however modified to account for relative motions
between LNGC and FSRU [22].
Ballasting tanks
By using ballasting tanks the freeboard is kept constant which improves the mooring integrity and limits the
operating range necessary for the loading arms. Also the ballasting tanks may improve the general stability of
the FSRU when it is not loaded with LNG.
5
Vapor return = transfer of boil-off-gas back to the LNGC while it is being unloaded. The boil-off-gas fills the
void being created in the ship's tanks thereby preventing tank collapse and the introduction of oxygen into the
system.
87
K.A.A. Watt
88
MSc Thesis
89
K.A.A. Watt
16.1 Introduction
In this appendix first some general background information is given regarding the Dynamic Mooring Analyses
(16.2). Subsequently the parameters of the reference projects will be mentioned: Golar (16.3) and Aqaba
(16.4). Finally some drawn conclusions from the DMA-analysis will be presented (16.5).
The output of a DMA run is: a time series of the vessels motions in the 6 Degrees Of Freedom (6-DOF) and of
the mooring forces for that particular run. For the mooring system considered in this study, the output mooring
forces are: 4 fender forces and 20 mooring line forces. The maximum motions and maximum mooring forces
are subsequently calculated by processing the DMA output.
Input Output
Environmental conditions Time series ship motions:
Current: velocity, direction surge, sway, heave, roll, pitch, yaw
Wind: velocity, direction Time series mooring forces:
Waves: Height, period, direction mooring line forces, fender forces
Spectral shapes
Additional input
Mooring configuration: FSRU-only, side-by-
side
Ship: type, dimensions, condition
Lines: diameter, material allocation
Fenders: type, size position
Water depth
Pile-stiffness
Table 41 Input- and output parameters a DMA
90
MSc Thesis
Initial runs
As a first step the varying environmental conditions from all directions are considered in the so-called initial
DMA runs. From the results of these runs, the critical runs can be defined which contain the maximum
mooring loads as well as the maximum vessel motions. Those critical runs are than considered in more detail
by looking at the Most Probable Maximum (MPM).
Since DMA runs in time domain, the maxima of a run are influenced by the length of the run. The longer the
run, the more likely a larger maximum is found. The MPM method is therefore introduced. A certain critical
case will be simulated various times with different random seeds in order to arrive at a distribution of the
maxima. Subsequently the mean and standard deviation of the distribution can be established. The Most
Probable Maximum of that distribution can then be derived at the peak of the probability density function.
As indicated previously, the critical cases for mooring loads (breast line, spring line and fender loads) are
considered in more detail in order to determine the Most Probable Maximum of the loads. The MPM line and
fenders loads are used to determine the maximum loads on the breasting and mooring dolphins. Those
maximum forces are determined as follows:
The maximum mooring dolphin (MD) load is determined by adding the MPM loads of the breast lines
which are attached to one single mooring dolphin.
, =
The maximum breasting dolphin (BD) load is determined by combining the MPM fender load with the
fender friction and the spring line load. The fender load and spring line load are taken from the same
run but act perpendicular to each other.
2
, =
2
+ ( + )
91
K.A.A. Watt
The mooring loads and vessel motion are assessed with the aid of numerical simulation, DMA.
The mooring arrangement of the FSRU, including the dolphin/bollard locations is illustrated below. The bow of
the vessel is directed towards the north.
The bollard level of the breasting dolphins (BD) is CD+7.0m and the bollard level of the mooring dolphin (MD) is
CD+4.0m. The total number of mooring lines of the FSRU is 20:
92
MSc Thesis
93
K.A.A. Watt
Waves
RP = 1 yr RP = 10 yr RP = 100 yr
Direction Hs [m] Tm [sec] Hs [m] Tm [sec] Hs [m] Tm [sec]
0 1,6 6,2 1,7 6,6 1,8 7,1
30 1,5 6 1,6 6,4 1,7 6,8
45 1,5 6 1,5 6,3 1,6 6,6
60 1,4 5,6 1,4 5,9 1,5 6,1
90 1,2 4,8 1,3 5 1,4 5
120 1 3,8 1,2 4 1,3 4
135 0,9 3,2 1,1 3,5 1,2 3,6
150 0,8 3 1 3,2 1,1 3,3
180 0,7 2,6 0,8 2,8 0,9 2,9
210 0,8 3 1 3,1 1,1 3,2
225 0,9 3,2 1,1 3,3 1,2 3,4
240 1 3,7 1,2 3,9 1,3 4
270 1,3 4,9 1,4 5 1,5 5,1
300 1,5 5,5 1,6 5,8 1,6 6,2
315 1,6 5,9 1,7 6,2 1,7 6,8
330 1,6 6 1,7 6,3 1,7 6,9
Wind
RP = 1 yr RP = 10 yr RP = 100 yr
Direction Storm [m/s] Squall [m/s] Storm [m/s] Squall [m/s] Storm [m/s] Squall [m/s]
0 13 21 14 27 16 33
30 11,7 21 13,3 27 14,7 33
45 11 21 13 27 14 33
60 11,7 20,7 13,3 26,7 14,7 32,3
90 13 20 14 26 16 31
120 13 19,3 14 25,3 16 30,3
135 13 19 14 25 16 30
150 12,7 19,3 13,7 25,3 15,7 30,3
180 12 20 13 26 15 31
210 13,3 20,7 15 26,7 16,3 32,3
225 14 21 16 27 17 33
240 14,3 21 16,7 27 18 33
270 15 21 18 27 20 33
300 15 20,3 16,7 26,3 18,7 31,7
315 15 20 16 26 18 31
330 14,3 20,3 15,3 26,3 17,3 31,7
94
MSc Thesis
The FSRU is a 170,000m3 converted LNGC. Further specifications are listed below.
The mooring arrangement of the FSRU, including the dolphin/bollard locations is illustrated below. The bow of
the vessel is directed towards the NNE (-25N)
95
K.A.A. Watt
For this case the recommendations of the OCIMF guidelines have been adopted. A current of 0.5m/s with an
approximate direction of 10 and 170 with respect to the ships center line has been taken into account
Waves
RP = 1 yr RP = 2 yr RP = 5 yr RP = 10 yr
Direction Hs [m] Tp [sec] Hs [m] Tp [sec] Hs [m] Tp [sec] Hs [m] Tp [sec]
S 0,9 5,9 1 6,1 1,1 6,4 1,2 6,6
SSW 1,3 6 1,5 6,4 1,7 6,6 1,8 6,9
SW 1,4 5,5 1,6 5,9 1,8 6,3 2 6,5
WSW 1,2 4,9 1,4 5 1,7 5,4 1,8 5,5
W 1,1 4,2 1,2 4,3 1,4 4,5 1,6 4,6
WNW 0,9 3,7 0,9 3,8 1 3,9 1,1 4
NW 0,8 3,6 0,8 3,7 0,9 3,8 0,9 3,8
NNW 0,7 3,6 0,7 3,6 0,8 3,7 0,8 3,8
N 0,5 3,2 0,5 3,3 0,6 3,5 0,6 3,5
96
MSc Thesis
RP = 20 yr RP = 50 yr RP = 100 yr
Hs [m] Tp [sec] Hs [m] Tp [sec] Hs [m] Tp [sec]
1,3 6,9 1,4 7,1 1,5 7,3
2 7,1 2,1 7,4 2,3 7,6
2,1 6,7 2,4 7 2,5 7,1
2 5,8 2,2 6 2,4 6,2
1,7 4,8 1,9 5 2 5
1,2 4,1 1,2 4,2 1,3 4,2
0,9 3,8 1 3,9 1 3,9
0,8 3,8 0,9 3,8 0,9 3,9
0,7 3,6 0,7 3,8 0,7 3,8
Wind
Direction RP = 1 yr RP = 2 yr RP = 5 yr RP = 10 yr RP = 20 yr RP = 50 yr RP = 100 yr
S 13,3 14,5 16 17 18 19,3 20,2
SSW 14,5 15,8 17,5 18,7 19,8 21,2 22,2
SW 13,4 14,9 16,7 17,9 19,2 20,8 21,9
WSW 12,9 14,4 16,3 17,7 19,1 20,8 22
W 13,7 15,1 16,9 18,2 19,5 21,1 22,3
WNW 12,6 13,5 14,6 15,4 16,2 17,1 17,8
NW 12,2 12,7 13,3 13,8 14,2 14,8 15,1
NNW 11,5 12 12,7 13,2 13,7 14,3 14,8
N 9,4 10,1 11 11,6 12,3 13,1 13,8
NNE 5,9 7,2 8,8 10,1 11,3 13 14,2
NE 6 6,5 7,2 9 10,8 13,1 14,8
ENE 5,1 5,7 6,5 7,1 7,7 8,5 9,1
E 6,7 7,1 7,5 7,8 8,1 8,4 8,7
ESE 7,8 8,2 8,7 9,1 9,5 9,9 10,3
SE 7 7,6 8,4 8,9 9,5 10,3 10,9
SSE 8,5 9,2 10,1 10,7 11,2 11,9 12,4
97
K.A.A. Watt
98
MSc Thesis
The maximum fender forces (MAX Fd1) are direct output of the DMAs. The resultant fender force (RES Fd1) is
calculated by subtracting the contribution of wind and currents to MAX Fd1. RES Fd1 represents the fender
force due to wave action only. The corresponding fender deflections are calculated by means of the Force-
Deflection curves. For this study only the environmental conditions coming from portside direction (330 - 210
) are considered, since those lead to the maximum fender forces.
99
K.A.A. Watt
Fender Fender
Input parameters Foam fender Cell fender
force deflection
Wind/ RES MAX RES RES RES Margin RES
Run Wave Wave Wind Current Current MAX RES Fd1 Margin
Wave u1 Fd1 Fd1 u1 Fd1 of u1
Name height period speed direction velocity Fd1 [kN] [kN] of Error
Direction [m] [kN] [kN] [m] [kN] Error [m]
Run
0010B
330 1.1 3.4 16.3 330 0.7 849 562 0.21 726 445 0.18 117 21% 0.03 14%
Run
0011B
315 1.2 3.6 17 315 0.8 1523 942 0.35 1260 692 0.32 251 27% 0.03 8%
Run
0012B
300 1.3 4.2 18 300 0.9 2035 1176 0.43 1842 982 0.44 193 16% -0.01 1%
Run
0013B
270 1.5 5.3 20 270 1.1 3333 2393 0.88 2751 1825 0.86 567 24% 0.02 2%
Run
0014B
240 1.6 6.5 18.7 240 1 1755 1239 0.46 1781 1239 0.56 0 0% -0.10 22%
Run
0015B
225 1.7 7.1 18 225 0.9 1462 1083 0.40 1328 949 0.41 134 12% -0.01 3%
Run
0016B
210 1.7 7.2 17.3 210 0.9 842 628 0.23 770 554 0.24 75 12% 0.00 2%
Run
0030B
330 1.1 3.4 16.3 90 0.9 296 320 0.12 319 334 0.16 -14 4% -0.04 34%
Run
0031B
315 1.2 3.6 17 90 0.9 525 365 0.13 820 630 0.28 -266 73% -0.15 109%
Run
0032B
300 1.3 4.2 18 90 0.9 888 540 0.20 1274 877 0.40 -337 62% -0.20 99%
Run
0033B
270 1.5 5.3 20 90 0.9 2161 1734 0.64 2281 1820 0.80 -86 5% -0.16 24%
Run
0034B
240 1.6 6.5 18.7 90 0.9 1246 1015 0.37 1498 1248 0.57 -232 23% -0.19 51%
Run
0035B
225 1.7 7.1 18 90 0.9 1075 950 0.35 1070 944 0.49 6 1% -0.13 38%
Run
0036B
210 1.7 7.2 17.3 90 0.9 514 536 0.20 633 652 0.25 -116 22% -0.05 28%
Run
0050B
330 1.1 3.4 16.3 270 1.1 1255 691 0.26 992 427 0.19 263 38% 0.07 26%
Run
0051B
315 1.2 3.6 17 270 1.1 1723 943 0.35 1447 656 0.30 287 30% 0.05 14%
Run
0052B
300 1.3 4.2 18 270 1.1 2112 1140 0.42 1922 924 0.42 216 19% 0.01 1%
Run
0053B
270 1.5 5.3 20 270 1.1 3333 2393 0.88 2751 1825 0.86 567 24% 0.02 2%
Run
0054B
240 1.6 6.5 18.7 270 1.1 1930 1313 0.48 1883 1239 0.52 74 6% -0.04 8%
Run
0055B
225 1.7 7.1 18 270 1.1 1640 1109 0.41 1581 1041 0.39 68 6% 0.02 5%
Run
0056B
210 1.7 7.2 17.3 270 1.1 1145 732 0.27 1011 618 0.25 114 16% 0.02 8%
The conclusion which can be drawn from this study is that; comparing the fender forces is much less accurate
then comparing the fender deflections. This can be explained by the fact that the fenders have a different
Force-Deflection relationship as can be seen from the graph. In this case the Cell fender is more advantageous
as it is much more flexible and may allow larger movements of the vessel for similar fender reaction forces. This
can also be seen from the DMA results; for similar environmental conditions the Foam fender lead to much
larger fender forces than the Cell fender.
From this study can be assumed that the motions of the vessel are not significantly restrained by the choice of
the fender. The vessel will move due to certain environmental conditions. Those movements are only very little
restrained/influenced by the type of fender. It is therefore recommended to analyze the lateral movements of
the ship and link them afterwards to a fender force based on a certain fender type (through the Force-
Deflection curves).
100
MSc Thesis
Based on DMA result can be concluded that; squall conditions always lead to larger fender forces than storm
conditions. Even if for the storm conditions somewhat larger waves are applied within the DMAs. When
considering wind and wave conditions coming beam-on the maximum fender force due to squall may be up to
40% higher than for storm conditions. This can also be seen in Figure 71.
The following graph shows the fender force per incoming wind/wave direction, for both storm and squall
conditions. The directions are according the reference system described in the introduction.
Figure 71 Maximum fender force [kN] per incoming direction, Golar project, Foam fender
101
K.A.A. Watt
It starts off with the definition of the input variables; environmental conditions, vessel dimensions and fender
characteristics.
102
MSc Thesis
For the calculation of the fender force due to wave action, the fender deflection should be determined. This is
achieved by translating a design wave height to a fender deflection by means of the graph illustrated in Figure
72.
Figure 73 Fender curve for the Ocean Guard-type with a maximum reaction force of 5967 kN
The winds were assumed quasi-static. Their corresponding fender force can calculated with the following
equation:
1 1 282
= 2 /1000 = 0.27 1.165 1.28 (1.37 18)2 15.4 = 532
2 2 1000
103
K.A.A. Watt
A gust factor of 1.37 is applied. The Cw coefficient is described in the OCIMF guidelines, where the alpha-
coefficient is obtained through Figure 74 and is dependent on the incoming direction of winds according to the
Cartesian convention.
1 1 282
= 2 = 0.27 0.653 1025 (1)2 9.6 = 245
2 1000 2 1000
The total fender force is then a simple summation of the three terms:
Subsequently, the calculated value shall be multiplied with a load factor in order to have the design load.
104
MSc Thesis
18.1 Introduction
In this appendix another method is presented for the visualization of the design fender loads. It must be noted
that this method is not yet optimized and still need some research before generating reliable results. The
underlying idea behind this method is described in Section (18.2). The current results and conclusions are
presented in Section (18.3).
18.2 Method
For this method, as well as for the one presented in the main report, the three environmental components are
separated: wind, wave and current. This is considered a safe assumption as foam filled floating fenders are
applied with a, nearly, linear force-deflection curve. The calculation of the fender loads due to winds and
currents is performed in the same manner as for the method presented in the main report (Section 4.3.2). The
fender forces due to wave action are obtained through a dimensionless fender force fender deflection
relationship. Such relationship is normally described by the fender curves and represents the stiffness of the
system.
The dimensionless fender force is determined by dividing the actual fender force (F) by the maximum fender
force if the vessel was fully fixed to a system of infinite stiffness (F*).
E.g. if the FSRU would be attached directly to a caisson (without the resonance effects of the waves
being reflected against the wall). The mooring system would be infinitely stiff and there would be little
to no energy dissipation. The load would therefore be maximal and the displacement zero. (see Figure
75 top)
The dimensionless fender deflection is determined by dividing the actual fender deflection (u) by the largest
possible motion if the vessel was completely free in its movements (u*), thus attached to a system of zero
stiffness.
E.g. if the FSRU would be attached to very loose anchor lines. The vessel would be completely
unrestrained in its movements and therefore the displacement would be maximal while and the force
zero. (see Figure 75 bottom)
The stiffness of the mooring system considered in this study, which is a fender combined with a flexible mono-
pile, must be situated somewhere in between the two abovementioned extremes (see Figure 75 middle). By
analyzing where the position of the considered mooring system is in the dimensionless graph, an insight can be
gained into the stiffness of this system.
105
K.A.A. Watt
Calculation of F*
The maximum force on the structure if the vessel would be completely fixed, F*, is calculated by means of
wave force transfer functions which can be found in the so-called hydrodynamic files (HYD-files) of a vessel.
Those files describe the hydrodynamics of an object, in this case the LNG carriers. A HYD-file contains the
results of diffraction calculations: added masses, potential damping, and first and second order wave force
transfer functions.
By means of the wave force transfer function the force can be calculated resulting from an incoming wave. The
force amplitude response (FAMP) which follows from the wave transfer functions depends on: wave period, -
direction and the motion of the vessel being considered. Each of the 6 Degrees of Freedom (6 DOF) has its own
corresponding transfer function.
The first order wave transfer functions are the direct response to an incoming wave. The second order wave
transfer function regards secondary drift forces. Those occur due to the fact that the waves at one side of the
vessel are larger than the transmitted waves at the other side of the vessel (partly damped), which leads to a
net force in the same direction as the wave field. For the results presented in the following section, F* was only
calculated as a result of the first order wave force transfer functions. For accurate results the secondary drift
forces should be taken into account.
= /
106
MSc Thesis
= +
= [ ] Force Amplitude response for sway
= [ ] Force Amplitude response for yaw
Calculation of u*
This maximum displacement (in Y-direction according to the Cartesian convention, Figure 5) of the vessel when
being completely free to move, u*, is calculated by means of so-called RAOs (Response Amplitude Operators).
RAOs are transfer functions used to determine the effect that a sea state will have upon the motion of a ship
through the water. RAOs are computed in tandem with the generation of a hydrodynamic database (HYD-
files). The RAOs can be found for the 6 DOF. Furthermore, they are dependent on wave period and direction.
In must be noted that, also in these calculations only the oscillatory component of the waves are taken into
account. The drift component is neglected.
=
= ()
[] =
= +
= [ ] Response Amplitude Operator for sway
= [ ] Response Amplitude Operator for yaw
[] Yaw angle
The motions of a vessel as a result to a certain sea state are described by an amplitude and a phase angle:
: () = sin()
: () = sin( + )
: () = sin( + )
For the calculations made in this section, the phase angles are neglected. The assumption is made that the
maxima of the motions (and forces), for sway and yaw, will occur simultaneously. This is an overestimation.
107
K.A.A. Watt
As can be observed, the results are clustered which indicate that this method may generate reliable results.
The horizontal axis, however, is not rightly scaled; both axes should range between 0 and 1. This can mainly be
explained by the fact that the second order drift component is not yet implemented in the method. The vertical
axis does show good results; the processed DMA data is ranging between 0.05 and 0.15, already giving some
indication on the stiffness of the system.
108
MSc Thesis
19.1 Introduction
Different p-y curves applied for the lateral bearing capacity of the piles are described in this Appendix. Since
the loads are of cyclic nature, the modified p-y curves are used. These curves are implemented within the
program LPile v6.0 with which the laterally loaded pile calculations are made. In (19.2) the p-y curves for soft
clay are discusses, in (19.3) the p-y curves for stiff clay and in (19.4) the p-y curves for sand.
The ultimate soil resistance for soft clays depends on the depth below the surface and can be calculated using
the smaller of the values calculated by the following equations:
= 3 + +
= 9
J: dimensionless empirical constant with values ranging between from 0.25 to 0.5
XR: depth below soil surface to bottom reduced resistance zone [mm]. For a condition of constant
strength with depth, the two above equations are solved simultaneously to give:
6
=
+
With the ultimate soil resistance determined, the deflection y50, at one-half of the ultimate soil resistance will
be determined by:
50 = 2.5 50 []
The p-y curve for soft clay is given in Figure 77. The first branch of the curve (0 < y < 3y50) is given by:
1
3
= 0.5 ( )
50
109
K.A.A. Watt
The other branches are linear. For y/y50 >3 two lines can be distinguished, namely one line (for depth: X > X R)
where the flow around failure governs and one (for depth: X < XR) where wedge failure occurs.
Figure 77 Characteristic shapes of p-y curves for soft clay below water table: cyclic loading (Matlock)
It has to be noted that the determination of the p-y curves for soft sand are based on results of lateral load
tests of piles with a diameter of 0.15m to 0.60m. In a study of Stevens and Audibert it was concluded that the
adaptation theory on larger diameter piles (up to 1.50m) will overestimate the deflection and maximum
moment of the piles. So a correction factor of the yc value is suggested, according to the following relation:
= 2.5 0.5 []
= 45 0.5 []
As LPile uses the original theory of Matlock without compensation of large diameter piles a correction factor
will be used defined as follows:
45 0.5 45
= =
2.5 2.5 0.5
The correction factor will be applied on the y-values in the LPile program for the correction of the p-y curves for
soft clay. The correction factor (c) for different pile diameters (D) is illustrated in Figure 78.
Figure 78 Relation between pile diameter (d) and correction factor (c)
110
MSc Thesis
= 2 + + 2.83
= 11
XN: depth below soil surface to bottom reduced resistance zone [mm]. For a condition of constant
strength with depth, the two above equations are solved simultaneously to give:
6
=
+
The p-y curve for stiff clay below the water table is illustrated in Figure 79.
Figure 79 Characteristic shapes of p-y curves for stiff clay below water table: cyclic loading (Reese et al)
111
K.A.A. Watt
For stiff clay the appropriate value of Ac (cyclic loading) has to be chosen from Figure 80, with on the vertical
axis the non dimensional depth following from the depth X divided by the pile diameter.
The ultimate bearing capacity for sand depends on the depth below the surface and can be calculated using the
smaller of the values calculated by the following equations:
= (1 + 2 )
= 3
112
MSc Thesis
Figure 81 Left: values C1, C2, C3; Right: Initial modulus of subgrade reaction
= tanh ( )
k: initial modulus of subgrade reaction [kN/m] determined from Figure 81 as a function of angle of
internal friction
H: depth [m]
113
K.A.A. Watt
20.1 Introduction
Three different approaches were considered regarding local buckling of shell structures: the DNV standard, the
European Standard and the API. The method presented by DNV, however, was too vague and therefore
considered not applicable. In the following section both the European-method (20.2) as the API-method (20.3)
is presented. It must be noted that the European- approach is at all times governing.
,
, = =
1 1
The buckling reduction factor X should be determined as a function of the relative slenderness of the shell
from:
= 1
0
0
= 1( ) 0 <
0
=
2
Where:
: interaction exponent.
The values from the plastic limit relative slenderness should be determined from:
=
1
114
MSc Thesis
The relative shell slenderness parameters for different stress components should be determined from:
=
,
The length of the shell segment is characterized in terms of the dimensionless length parameter :
The elastic meridional buckling stress, using a value of Cx depending on the length of the cylinder, should be
obtained from:
, = 0.605
0.62
=
1 + 1.91( )1.44
1
=
The fabrication quality parameter Q should be taken from Table 54 for the specified fabrication tolerance
quality class. For this case Q is taken as 25.
0 = 0.20 ; = 0.60 ; = 1.0
For long cylinders (which are defined by: > 0.5 ; = ) the meridional squash limit slenderness
115
K.A.A. Watt
,
0 = 0.20 + 0.10 ( )
xE,M: component of xEd that derives from tubular global bending (peak value of the circumferentially
varying component)
Cylinders need not to be checked against meridional shell buckling if they satisfy:
0.03
20.2.1 API
In the API standards a nominal inelastic buckling strength F xc is determined which the design stress shall not
exceed:
= / 60
0.25
= (1.64 0.23 ( ) ) / > 60
116
MSc Thesis
The calculations are only shown for the first 16 meters of the pile, extending from CD+6.0m until approximately
CD-10.0m. The load acts at a level of CD+2.5m. Additional parameters are listed below.
Input parameters
Material properties
3
Density Steel 78.5 kN/m
ES 210000 MPa
X60 (f,yield) 448 Mpa
Factors
gm,yield 1.15 -
gm,e.g 1.3 -
Loads
Design Load 8000 kN
Weight Pile head 1500 kN
Output parameters
Length 47.5 m
D 3.8 m
t 0.055 m
R,outer 1.900 m
R,inner 1.873 m
117
INPUT STEEL STRESSES VON MISES YIELD STRENGTH BUCKLING STRENGTH
Level Md Vd Uhor OD t A W Section Nd Td ,M (Md) ,M (Uhor) ,N ,V ,T ,max ,max ,vm1 ,vm2 ,vmd f,yd U.C. EN1993-1- API U.C.
[m] [kNm] [kN] [m] [mm] [m] [m^2] [m^3] Weight [kN] [kN] [kNm] [MPa] [MPa] [MPa] [MPa] [MPa] [MPa] [MPa] [MPa] [MPa] [MPa] [Mpa] [-] [MPa] [MPa] [-]
6.0 0 0 0.801 3.8 0.055 0.647 0.597 1500.0 1500.0 7600.0 0.00 0.00 2.32 0.00 12.45 2.3 12.5 21.7 21.7 21.7 389.6 0.06 351.67 380.56 0.06 ok
5.5 0 0 0.789 3.8 0.055 0.647 0.597 31.4 1531.4 7600.0 0.00 0.03 2.37 0.00 12.45 2.4 12.5 21.7 21.7 21.7 389.6 0.06 351.67 380.56 0.06 ok
5.1 0 0 0.776 3.8 0.055 0.647 0.597 31.4 1562.7 7600.0 0.00 0.06 2.42 0.00 12.45 2.5 12.5 21.7 21.7 21.7 389.6 0.06 351.67 380.56 0.06 ok
4.6 0 0 0.764 3.8 0.055 0.647 0.597 31.4 1594.1 7600.0 0.00 0.10 2.46 0.00 12.45 2.6 12.5 21.7 21.7 21.7 389.6 0.06 351.67 380.56 0.06 ok
4.1 0 0 0.751 3.8 0.055 0.647 0.597 31.4 1625.5 7600.0 0.00 0.13 2.51 0.00 12.45 2.6 12.5 21.7 21.7 21.7 389.6 0.06 351.67 380.56 0.06 ok
3.6 0 0 0.739 3.8 0.055 0.647 0.597 31.4 1656.8 7600.0 0.00 0.16 2.56 0.00 12.45 2.7 12.5 21.7 21.7 21.7 389.6 0.06 351.67 380.56 0.06 ok
3.2 0 0 0.726 3.8 0.055 0.647 0.597 31.4 1688.2 7600.0 0.00 0.20 2.61 0.00 12.45 2.8 12.5 21.7 21.7 21.7 389.6 0.06 351.67 380.56 0.06 ok
2.7 0 1250 0.714 3.8 0.055 0.647 0.597 31.4 1719.6 7600.0 0.00 0.24 2.66 7.67 12.45 2.9 20.1 21.8 35.0 35.0 389.6 0.09 351.67 380.56 0.10 ok
2.2 1188 4400 0.702 3.8 0.055 0.647 0.597 31.4 1750.9 7600.0 1.99 0.27 2.71 27.00 12.45 5.0 39.5 22.1 68.4 68.4 389.6 0.18 351.67 380.56 0.19 ok
1.7 4180 7150 0.689 3.8 0.055 0.647 0.597 31.4 1782.3 7600.0 7.00 0.31 2.75 43.87 12.45 10.1 56.3 23.8 97.6 97.6 389.6 0.25 351.67 380.56 0.28 ok
1.3 7980 8000 0.677 3.8 0.055 0.647 0.597 31.4 1813.7 7600.0 13.36 0.35 2.80 49.09 12.45 16.5 61.5 27.2 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
0.8 11780 8000 0.664 3.8 0.055 0.647 0.597 31.4 1845.0 7600.0 19.73 0.38 2.85 49.09 12.45 23.0 61.5 31.5 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
0.3 15580 8000 0.652 3.8 0.055 0.647 0.597 31.4 1876.4 7600.0 26.09 0.42 2.90 49.09 12.45 29.4 61.5 36.5 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-0.2 19380 8000 0.639 3.8 0.055 0.647 0.597 31.4 1907.8 7600.0 32.45 0.46 2.95 49.09 12.45 35.9 61.5 41.8 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-0.7 23180 8000 0.627 3.8 0.055 0.647 0.597 31.4 1939.1 7600.0 38.81 0.50 3.00 49.09 12.45 42.3 61.5 47.5 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-1.1 26980 8000 0.614 3.8 0.055 0.647 0.597 31.4 1970.5 7600.0 45.18 0.54 3.05 49.09 12.45 48.8 61.5 53.3 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-1.6 30780 8000 0.602 3.8 0.055 0.647 0.597 31.4 2001.9 7600.0 51.54 0.58 3.09 49.09 12.45 55.2 61.5 59.3 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-2.1 34580 8000 0.590 3.8 0.055 0.647 0.597 31.4 2033.2 7600.0 57.90 0.63 3.14 49.09 12.45 61.7 61.5 65.3 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-2.6 38380 8000 0.577 3.8 0.055 0.647 0.597 31.4 2064.6 7600.0 64.27 0.67 3.19 49.09 12.45 68.1 61.5 71.5 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-3.0 42180 8000 0.565 3.8 0.055 0.647 0.597 31.4 2096.0 7600.0 70.63 0.71 3.24 49.09 12.45 74.6 61.5 77.6 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-3.5 45980 8000 0.553 3.8 0.055 0.647 0.597 31.4 2127.3 7600.0 76.99 0.75 3.29 49.09 12.45 81.0 61.5 83.9 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-4.0 49780 8000 0.541 3.8 0.055 0.647 0.597 31.4 2158.7 7600.0 83.36 0.80 3.34 49.09 12.45 87.5 61.5 90.1 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-4.5 53580 8000 0.529 3.8 0.055 0.647 0.597 31.4 2190.1 7600.0 89.72 0.84 3.38 49.09 12.45 93.9 61.5 96.4 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-4.9 57380 8000 0.517 3.8 0.055 0.647 0.597 31.4 2221.4 7600.0 96.08 0.89 3.43 49.09 12.45 100.4 61.5 102.7 106.6 106.6 389.6 0.27 351.67 380.56 0.30 ok
-5.4 61180 8000 0.505 3.8 0.055 0.647 0.597 31.4 2252.8 7600.0 102.45 0.93 3.48 49.09 12.45 106.9 61.5 109.0 106.7 109.0 389.6 0.28 351.67 380.56 0.31 ok
-5.9 64980 8000 0.493 3.8 0.055 0.647 0.597 31.4 2284.2 7600.0 108.81 0.98 3.53 49.09 12.45 113.3 61.5 115.4 106.7 115.4 389.6 0.30 351.67 380.56 0.33 ok
-6.4 68780 8000 0.481 3.8 0.055 0.647 0.597 31.4 2315.5 7600.0 115.17 1.02 3.58 49.09 12.45 119.8 61.5 121.7 106.7 121.7 389.6 0.31 351.67 380.56 0.35 ok
-6.8 72580 8000 0.469 3.8 0.055 0.647 0.597 31.4 2346.9 7600.0 121.53 1.07 3.63 49.09 12.45 126.2 61.5 128.1 106.7 128.1 389.6 0.33 351.67 380.56 0.36 ok
-7.3 76380 8000 0.457 3.8 0.055 0.647 0.597 31.4 2378.3 7600.0 127.90 1.12 3.68 49.09 12.45 132.7 61.5 134.4 106.7 134.4 389.6 0.35 351.67 380.56 0.38 ok
-7.8 80180 8000 0.445 3.8 0.055 0.647 0.597 31.4 2409.6 7600.0 134.26 1.17 3.72 49.09 12.45 139.1 61.5 140.8 106.7 140.8 389.6 0.36 351.67 380.56 0.40 ok
-8.3 83980 8000 0.434 3.8 0.055 0.647 0.597 31.4 2441.0 7600.0 140.62 1.21 3.77 49.09 12.45 145.6 61.5 147.2 106.7 147.2 389.6 0.38 351.67 380.56 0.42 ok
-8.7 87780 8000 0.422 3.8 0.055 0.647 0.597 31.4 2472.4 7600.0 146.99 1.26 3.82 49.09 12.45 152.1 61.5 153.6 106.7 153.6 389.6 0.39 351.67 380.56 0.44 ok
-9.2 91580 8000 0.411 3.8 0.055 0.647 0.597 31.4 2503.7 7600.0 153.35 1.31 3.87 49.09 12.45 158.5 61.5 160.0 106.7 160.0 389.6 0.41 351.67 380.56 0.45 ok
-9.7 95380 8000 0.399 3.8 0.055 0.647 0.597 31.4 2535.1 7600.0 159.71 1.36 3.92 49.09 12.45 165.0 61.5 166.4 106.7 166.4 389.6 0.43 351.67 380.56 0.47 ok
-10.2 99180 8000 0.388 3.8 0.055 0.647 0.597 31.4 2566.5 7600.0 166.08 1.41 3.97 49.09 12.45 171.4 61.5 172.8 106.7 172.8 389.6 0.44 351.67 380.56 0.49 ok
Level [m]
10.0
-50.0
-40.0
-30.0
-20.0
-10.0
0.0
0.0
sigma,vmd
200.0
f,yd
Stress [MPa]
400.0
f,bucd
K.A.A. Watt
118
MSc Thesis
A distinction was made between two extreme soil profiles: a soft clay profile and a stiff sand profile. In
Section (22.2) the pile designs are presented for the soft clay profile, in Section (22.3) for the stiff sand profile.
Drawn conclusions regarding this matter are mentioned in Section (22.4).
For each combination of fender load and soil profile a pile design is made characterized by its dimensions:
diameter (D), wall thickness (t) and length (L). For each combination two pile designs are possible; one with an
optimized diameter, the other with an optimized wall thickness. For a few combinations, however, the designs
were outside the chosen D/t range (65 < D/t < 85) and considered unsuitable.
Table 55 Soft clay profile - Pile designs for varying design loads and water depths
119
K.A.A. Watt
Figure 82 Soft clay profile - Design load / Pile diameter; light blue: 16m water depth, dark blue: 26m water depth
Figure 83 Soft clay profile - Design load / Wall thickness; light blue: 16m water depth, dark blue: 26m water depth
120
MSc Thesis
Figure 84 Soft clay profile - Design load / Pile length; light blue: 16m water depth, dark blue: 26m water depth
Table 56 Stiff sand profile - Pile designs for varying design loads and water depths
121
K.A.A. Watt
Figure 85 Stiff sand profile - Design load / Pile diameter; light green: 16m water depth, dark green: 26m water depth
Figure 86 Stiff sand profile - Design load / Wall thickness; light green: 16m water depth, dark green: 26m water depth
122
MSc Thesis
Figure 87 Stiff sand profile - Design load / Pile length; light green: 16m water depth, dark green: 26m water depth
22.4 Conclusions
In the graphs showed above can be observed how the pile diameters, wall thicknesses and pile lengths increase
for increasing water depth (from 16m to 26m).
Pile diameter
For both soil profiles the same phenomena has been observed. The difference in diameter, between the two
water depth cases, increases for increasing load. The difference in pile diameter increases:
Wall thickness
For a 10m increase of the water depth, the wall thicknesses of the piles increase with 5mm for both soil
profiles.
Pile length
For the stiff sand profile; the length of the piles increases with 12.5m. For the soft clay profile, the difference in
pile length is 12.5m for small loads and decreases linearly to 10m for larger loads.
123
K.A.A. Watt
The standardized pile designs presented in Section (5.4.1) can quite easily be rescaled in the following manner:
Environmental condition
Soil profile Dimensions
Mild Moderate Harsh
t [mm] 45 +5 50 + 5 55 + 5
Stiff sand
D [mm] 3300 + 400 3800 + 400 4100 + 500
profile
L [m] 42.5 + 12.5 45 + 12.5 47.5 + 12.5
t [mm] 50 + 5 55 + 5 60 + 5
Soft clay
D [mm] 3400 + 300 3900 + 400 4300 + 400
profile
L [m] 65 + 12.5 70 + 12.5 80 + 10
Table 57 Rescaling of the standardized pile designs for a 10m increased water depth
The change in pile dimension is nearly similar for all six cases listed above. Since the standardized pile designs
are meant for a conceptual design stage, it is concluded acceptable to define generalized rescaling parameters.
124
MSc Thesis
As can be seen some of the shear strength (V) unity checks are below 1 (marked in red). Those are shear forces
resulting from an incorrect modelling of the connection between the rear fender panel and the front plates of
the support structure. Furthermore those shear forces act on very small surfaces and are therefore considered
negligible for the design.
125
K.A.A. Watt
SIDE PLATES FRONT PLATES INNER WALLS BOTTOM- & TOP PLATES
Parameters ULS 1 ULS 2 ULS 1 ULS 2 ULS 1 ULS 2 ULS 1 ULS 2
Value U.C. Value U.C. Value U.C. Value U.C. Value U.C. Value U.C. Value U.C. Value U.C.
sigE-
24.30 0.28 60.10 0.68 37.10 0.42 34.70 0.39 76.90 0.87 73.50 0.84 40.30 0.46 13.10 0.15
[MPa]
sigE+
28.90 0.33 71.40 0.81 36.70 0.42 31.70 0.36 69.20 0.79 76.80 0.87 31.70 0.36 18.00 0.20
[MPa]
126
MSc Thesis
The alternating loads are described by Delta F. These are translated to alternating stresses by means a linear
load-stress relation, described by so-called load transfer functions (LTFs). E.g., a Delta F of 10 represents the
load variations 0-10kN / 10-20kN/ 20-30kN / 30-40kN. The corresponding stress variations are described as s1 /
s2 / s3 /s4. For the fatigue calculations of the mono-piles, these are then multiplied with a Stress Concentration
Factor (SCF) to obtain the hot-spot stresses (s,hot).
The actual number of cycles for each alternating stress range is represented by n, while the allowable
number of cycles is abbreviated with N. The final cumulative damage number is the summation of all the
damage factors (Dd) which can be found in the last column of the table.
In section (24.3) the S-N curve for steel and composite are plotted in one figure in order to illustrate their
difference.
In section (24.4) the fatigue calculations of a mono-pile are showed. The considered mono-pile is designed for
stiff soil conditions and an ULS design load of 5000kN.
In section (24.5) the fatigue calculations of the critical pile-head element are illustrated, namely the front- and
side plates.
As can be seen, composite is much more fatigue resistant for smaller alternative stresses, up to 3MPa.
127
K.A.A. Watt
128
s1 s2 s3 s4 p s,hot1 s,hot2 s,hot3 s,hot4
Hs = 0.5 Delta F n1 n2 n3 n4 SCF N1 N2 N3 N4 (n/N)1 (n/N)2 (n/N)3 (n/N)4 Dd
[MPa] [MPa] [MPa] [MPa] % [MPa] [MPa] [MPa] [MPa]
MSc Thesis
North 5 0.340 0.680 1.020 1.360 0.13 1800 6.9E+04 0.0E+00 0.0E+00 0.0E+00 1.21 0.41 0.82 1.23 1.65 8.4E+17 3.9E+16 5.1E+15 8.3E+14 8.2E-14 0.0E+00 0.0E+00 0.0E+00 8.2E-13
NNE 5 0.340 0.680 1.020 1.360 0.14 1641 159 6.6E+04 6.4E+03 0.0E+00 0.0E+00 1.21 0.41 0.82 1.23 1.65 8.4E+17 3.9E+16 5.1E+15 8.3E+14 7.9E-14 1.6E-13 0.0E+00 0.0E+00 2.4E-12
NE 10 0.680 1.360 2.040 2.720 0.43 1260 529 11 1.6E+05 6.7E+04 1.4E+03 0.0E+00 1.21 0.82 1.65 2.47 3.29 3.9E+16 8.3E+14 9.2E+13 3.8E+13 4.0E-12 8.0E-11 1.5E-11 0.0E+00 9.9E-10
ENE 10 0.680 1.360 2.040 2.720 2.28 913 822 65 6.1E+05 5.5E+05 4.3E+04 0.0E+00 1.21 0.82 1.65 2.47 3.29 3.9E+16 8.3E+14 9.2E+13 3.8E+13 1.5E-11 6.6E-10 4.7E-10 0.0E+00 1.1E-08
East 75 5.100 10.200 15.300 20.400 5.63 1140 625 35 1.9E+06 1.0E+06 5.8E+04 0.0E+00 1.21 6.17 12.34 18.51 24.68 9.3E+11 5.1E+10 6.2E+09 9.2E+08 2.0E-06 2.0E-05 9.3E-06 0.0E+00 3.2E-04
ESE 25 1.700 3.400 5.100 6.800 5.22 1306 493 1 2.0E+06 7.5E+05 1.5E+03 0.0E+00 1.21 2.06 4.11 6.17 8.23 4.0E+14 8.4E+12 9.3E+11 3.9E+11 4.9E-09 9.0E-08 1.6E-09 0.0E+00 9.6E-07
SE 10 0.680 1.360 2.040 2.720 2.77 1053 706 41 8.5E+05 5.7E+05 3.3E+04 0.0E+00 1.21 0.82 1.65 2.47 3.29 3.9E+16 8.3E+14 9.2E+13 3.8E+13 2.2E-11 6.9E-10 3.6E-10 0.0E+00 1.1E-08
SSE 5 0.340 0.680 1.020 1.360 0.38 1730 70 1.9E+05 7.8E+03 0.0E+00 0.0E+00 1.21 0.41 0.82 1.23 1.65 8.4E+17 3.9E+16 5.1E+15 8.3E+14 2.3E-13 2.0E-13 0.0E+00 0.0E+00 4.3E-12
South 5 0.340 0.680 1.020 1.360 0.08 1800 4.3E+04 0.0E+00 0.0E+00 0.0E+00 1.21 0.41 0.82 1.23 1.65 8.4E+17 3.9E+16 5.1E+15 8.3E+14 5.1E-14 0.0E+00 0.0E+00 0.0E+00 5.1E-13
SSW 5 0.340 0.680 1.020 1.360 0.08 1800 4.3E+04 0.0E+00 0.0E+00 0.0E+00 1.21 0.41 0.82 1.23 1.65 8.4E+17 3.9E+16 5.1E+15 8.3E+14 5.1E-14 0.0E+00 0.0E+00 0.0E+00 5.1E-13
SW 10 0.680 1.360 2.040 2.720 0.37 1333 458 9 1.4E+05 4.9E+04 9.6E+02 0.0E+00 1.21 0.82 1.65 2.47 3.29 3.9E+16 8.3E+14 9.2E+13 3.8E+13 3.6E-12 5.9E-11 1.0E-11 0.0E+00 7.3E-10
WSW 15 1.020 2.040 3.060 4.080 1.11 776 916 108 2.5E+05 3.0E+05 3.5E+04 0.0E+00 1.21 1.23 2.47 3.70 4.94 5.1E+15 9.2E+13 1.1E+13 5.0E+12 4.9E-11 3.2E-09 3.1E-09 0.0E+00 6.3E-08
West 75 5.100 10.200 15.300 20.400 2.25 1500 299 1 9.9E+05 2.0E+05 6.6E+02 0.0E+00 1.21 6.17 12.34 18.51 24.68 9.3E+11 5.1E+10 6.2E+09 9.2E+08 1.1E-06 3.9E-06 1.1E-07 0.0E+00 5.0E-05
WNW 10 0.680 1.360 2.040 2.720 2.57 1066 711 23 8.0E+05 5.3E+05 1.7E+04 0.0E+00 1.21 0.82 1.65 2.47 3.29 3.9E+16 8.3E+14 9.2E+13 3.8E+13 2.0E-11 6.4E-10 1.9E-10 0.0E+00 8.5E-09
NW 10 0.680 1.360 2.040 2.720 1.51 1637 163 7.2E+05 7.2E+04 0.0E+00 0.0E+00 1.21 0.82 1.65 2.47 3.29 3.9E+16 8.3E+14 9.2E+13 3.8E+13 1.8E-11 8.6E-11 0.0E+00 0.0E+00 1.0E-09
NNW 5 0.340 0.680 1.020 1.360 0.39 1775 25 2.0E+05 2.9E+03 0.0E+00 0.0E+00 1.21 0.41 0.82 1.23 1.65 8.4E+17 3.9E+16 5.1E+15 8.3E+14 2.4E-13 7.3E-14 0.0E+00 0.0E+00 3.1E-12
s1 s2 s3 s4 p s,hot1 s,hot2 s,hot3 s,hot4
Hs = 0.7 Delta F n1 n2 n3 n4 SCF N1 N2 N3 N4 (n/N)1 (n/N)2 (n/N)3 (n/N)4 Dd
[MPa] [MPa] [MPa] [MPa] % [MPa] [MPa] [MPa] [MPa]
North 5 0.340 0.680 1.020 1.360 0.09 1800 4.7E+04 0.0E+00 0.0E+00 0.0E+00 1.21 0.41 0.82 1.23 1.65 8.4E+17 3.9E+16 5.1E+15 8.3E+14 5.6E-14 0.0E+00 0.0E+00 0.0E+00 5.6E-13
NNE 10 0.680 1.360 2.040 2.720 0.03 1246 538 16 1.2E+04 5.1E+03 1.5E+02 0.0E+00 1.21 0.82 1.65 2.47 3.29 3.9E+16 8.3E+14 9.2E+13 3.8E+13 3.0E-13 6.2E-12 1.7E-12 0.0E+00 8.1E-11
NE 25 1.700 3.400 5.100 6.800 0.21 1304 482 14 8.1E+04 3.0E+04 8.7E+02 0.0E+00 1.21 2.06 4.11 6.17 8.23 4.0E+14 8.4E+12 9.3E+11 3.9E+11 2.0E-10 3.6E-09 9.3E-10 0.0E+00 4.7E-08
ENE 25 1.700 3.400 5.100 6.800 1.74 834 888 75 3 4.2E+05 4.5E+05 3.8E+04 1.5E+03 1.21 2.06 4.11 6.17 8.23 4.0E+14 8.4E+12 9.3E+11 3.9E+11 1.1E-09 5.4E-08 4.1E-08 3.9E-09 1.0E-06
East 100 6.800 13.600 20.400 27.200 3.80 361 868 501 70 4.0E+05 9.6E+05 5.6E+05 7.8E+04 1.21 8.23 16.46 24.68 32.91 3.9E+11 8.3E+09 9.2E+08 3.8E+08 1.0E-06 1.2E-04 6.0E-04 2.0E-04 9.2E-03
ESE 25 1.700 3.400 5.100 6.800 2.09 391 988 371 50 2.4E+05 6.0E+05 2.3E+05 3.0E+04 1.21 2.06 4.11 6.17 8.23 4.0E+14 8.4E+12 9.3E+11 3.9E+11 5.9E-10 7.2E-08 2.4E-07 7.7E-08 3.9E-06
SE 25 1.700 3.400 5.100 6.800 0.42 1145 638 17 1.4E+05 7.7E+04 2.1E+03 0.0E+00 1.21 2.06 4.11 6.17 8.23 4.0E+14 8.4E+12 9.3E+11 3.9E+11 3.4E-10 9.2E-09 2.2E-09 0.0E+00 1.2E-07
SSE 10 0.680 1.360 2.040 2.720 0.03 1668 131 1 1.6E+04 1.2E+03 9.5E+00 0.0E+00 1.21 0.82 1.65 2.47 3.29 3.9E+16 8.3E+14 9.2E+13 3.8E+13 4.0E-13 1.5E-12 1.0E-13 0.0E+00 2.0E-11
South 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SW 25 1.700 3.400 5.100 6.800 0.05 1206 580 14 1.7E+04 8.3E+03 2.0E+02 0.0E+00 1.21 2.06 4.11 6.17 8.23 4.0E+14 8.4E+12 9.3E+11 3.9E+11 4.3E-11 9.9E-10 2.1E-10 0.0E+00 1.2E-08
WSW 25 1.700 3.400 5.100 6.800 0.42 389 1018 357 36 4.8E+04 1.3E+05 4.4E+04 4.5E+03 1.21 2.06 4.11 6.17 8.23 4.0E+14 8.4E+12 9.3E+11 3.9E+11 1.2E-10 1.5E-08 4.8E-08 1.1E-08 7.4E-07
West 125 8.500 17.000 25.500 34.000 1.21 838 847 113 2 3.0E+05 3.0E+05 4.0E+04 7.0E+02 1.21 10.29 20.57 30.86 41.14 8.5E+10 4.0E+09 5.2E+08 8.4E+07 3.5E-06 7.4E-05 7.7E-05 8.4E-06 1.6E-03
WNW 25 1.700 3.400 5.100 6.800 1.92 1292 502 6 7.3E+05 2.8E+05 3.4E+03 0.0E+00 1.21 2.06 4.11 6.17 8.23 4.0E+14 8.4E+12 9.3E+11 3.9E+11 1.8E-09 3.4E-08 3.6E-09 0.0E+00 3.9E-07
NW 15 1.020 2.040 3.060 4.080 1.28 943 797 59 1 3.5E+05 3.0E+05 2.2E+04 3.7E+02 1.21 1.23 2.47 3.70 4.94 5.1E+15 9.2E+13 1.1E+13 5.0E+12 6.9E-11 3.2E-09 1.9E-09 7.5E-11 5.3E-08
NNW 10 0.680 1.360 2.040 2.720 0.28 1489 310 1 1.2E+05 2.5E+04 8.1E+01 0.0E+00 1.21 0.82 1.65 2.47 3.29 3.9E+16 8.3E+14 9.2E+13 3.8E+13 3.1E-12 3.0E-11 8.8E-13 0.0E+00 3.4E-10
24.4 Fatigue mono-pile: soft soil profile, Fd = 5000kN
129
s1 s2 s3 s4 p s,hot1 s,hot2 s,hot3 s,hot4
Hs = 1.1 Delta F n1 n2 n3 n4 SCF N1 N2 N3 N4 (n/N)1 (n/N)2 (n/N)3 (n/N)4 Dd
[MPa] [MPa] [MPa] [MPa] % [MPa] [MPa] [MPa] [MPa]
North 5 0.340 0.680 1.020 1.360 0.02 1789 11 8.5E+03 5.2E+01 0.0E+00 0.0E+00 1.21 0.41 0.82 1.23 1.65 8.4E+17 3.9E+16 5.1E+15 8.3E+14 1.0E-14 1.3E-15 0.0E+00 0.0E+00 1.1E-13
NNE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
NE 50 3.400 6.800 10.200 13.600 0.01 877 835 82 6 2.1E+03 2.0E+03 2.0E+02 1.4E+01 1.21 4.11 8.23 12.34 16.46 8.4E+12 3.9E+11 5.1E+10 8.3E+09 2.5E-10 5.0E-09 3.8E-09 1.7E-09 1.1E-07
ENE 100 6.800 13.600 20.400 27.200 0.10 521 843 410 26 1.5E+04 2.4E+04 1.2E+04 7.4E+02 1.21 8.23 16.46 24.68 32.91 3.9E+11 8.3E+09 9.2E+08 3.8E+08 3.8E-08 2.9E-06 1.3E-05 1.9E-06 1.8E-04
East 250 17.000 34.000 51.000 68.000 0.08 729 980 89 2 1.7E+04 2.3E+04 2.1E+03 4.8E+01 1.21 20.57 41.14 61.71 82.28 4.0E+09 8.4E+07 9.3E+06 3.9E+06 4.3E-06 2.8E-04 2.3E-04 1.2E-05 5.2E-03
ESE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
South 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
WSW 75 5.100 10.200 15.300 20.400 0.01 533 968 274 25 1.3E+03 2.3E+03 6.5E+02 5.9E+01 1.21 6.17 12.34 18.51 24.68 9.3E+11 5.1E+10 6.2E+09 9.2E+08 1.4E-09 4.5E-08 1.1E-07 6.5E-08 2.2E-06
West 300 20.400 40.800 61.200 81.600 0.07 564 904 312 20 1.1E+04 1.7E+04 5.9E+03 3.8E+02 1.21 24.68 49.37 74.05 98.74 9.2E+08 5.0E+07 6.1E+06 9.6E+05 1.2E-05 3.4E-04 9.8E-04 4.0E-04 1.7E-02
WNW 100 6.800 13.600 20.400 27.200 0.30 1115 670 15 9.8E+04 5.9E+04 1.3E+03 0.0E+00 1.21 8.23 16.46 24.68 32.91 3.9E+11 8.3E+09 9.2E+08 3.8E+08 2.5E-07 7.1E-06 1.4E-06 0.0E+00 8.8E-05
NW 50 3.400 6.800 10.200 13.600 0.57 1167 610 23 1.9E+05 1.0E+05 3.8E+03 0.0E+00 1.21 4.11 8.23 12.34 16.46 8.4E+12 3.9E+11 5.1E+10 8.3E+09 2.3E-08 2.6E-07 7.5E-08 0.0E+00 3.6E-06
NNW 25 1.700 3.400 5.100 6.800 0.24 1070 684 45 1 7.4E+04 4.7E+04 3.1E+03 6.9E+01 1.21 2.06 4.11 6.17 8.23 4.0E+14 8.4E+12 9.3E+11 3.9E+11 1.8E-10 5.6E-09 3.3E-09 1.8E-10 9.3E-08
s1 s2 s3 s4 p s,hot1 s,hot2 s,hot3 s,hot4
Hs = 1.3 Delta F n1 n2 n3 n4 SCF N1 N2 N3 N4 (n/N)1 (n/N)2 (n/N)3 (n/N)4 Dd
[MPa] [MPa] [MPa] [MPa] % [MPa] [MPa] [MPa] [MPa]
North 5 0.340 0.680 1.020 1.360 0.01 1601 198 1 3.8E+03 4.7E+02 2.4E+00 0.0E+00 1.21 0.41 0.82 1.23 1.65 8.4E+17 3.9E+16 5.1E+15 8.3E+14 4.5E-15 1.2E-14 4.7E-16 0.0E+00 1.7E-13
NNE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
NE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
ENE 150 10.200 20.400 30.600 40.800 0.02 509 913 356 22 3.6E+03 6.5E+03 2.5E+03 1.6E+02 1.21 12.34 24.68 37.03 49.37 5.1E+10 9.2E+08 1.1E+08 5.0E+07 7.1E-08 7.1E-06 2.2E-05 3.1E-06 3.3E-04
East 350 23.800 47.600 71.400 95.200 0.01 1071 672 55 2 2.5E+03 1.6E+03 1.3E+02 4.8E+00 1.21 28.80 57.60 86.39 115.19 6.5E+08 1.6E+07 2.9E+06 8.2E+05 3.9E-06 1.0E-04 4.6E-05 5.8E-06 1.6E-03
ESE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
South 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
WSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
West 500 34.000 68.000 102.000 136.000 0.01 567 940 283 10 1.3E+03 2.2E+03 6.7E+02 2.4E+01 1.21 41.14 82.28 123.42 164.56 8.4E+07 3.9E+06 7.5E+05 4.1E+05 1.6E-05 5.7E-04 9.0E-04 5.8E-05 1.5E-02
WNW 150 10.200 20.400 30.600 40.800 0.08 753 898 148 1 1.8E+04 2.1E+04 3.5E+03 2.4E+01 1.21 12.34 24.68 37.03 49.37 5.1E+10 9.2E+08 1.1E+08 5.0E+07 3.5E-07 2.3E-05 3.1E-05 4.8E-07 5.5E-04
NW 50 3.400 6.800 10.200 13.600 0.29 601 928 246 25 5.0E+04 7.7E+04 2.0E+04 2.1E+03 1.21 4.11 8.23 12.34 16.46 8.4E+12 3.9E+11 5.1E+10 8.3E+09 6.0E-09 2.0E-07 4.0E-07 2.5E-07 8.6E-06
NNW 50 3.400 6.800 10.200 13.600 0.11 1508 291 1 4.7E+04 9.0E+03 3.1E+01 0.0E+00 1.21 4.11 8.23 12.34 16.46 8.4E+12 3.9E+11 5.1E+10 8.3E+09 5.6E-09 2.3E-08 6.1E-10 0.0E+00 2.9E-07
s1 s2 s3 s4 p s,hot1 s,hot2 s,hot3 s,hot4
Hs = 1.5 Delta F n1 n2 n3 n4 SCF N1 N2 N3 N4 (n/N)1 (n/N)2 (n/N)3 (n/N)4 Dd
[MPa] [MPa] [MPa] [MPa] % [MPa] [MPa] [MPa] [MPa]
North 5 0.340 0.680 1.020 1.360 0.02 1264 524 12 6.0E+03 2.5E+03 5.7E+01 0.0E+00 1.21 0.41 0.82 1.23 1.65 8.4E+17 3.9E+16 5.1E+15 8.3E+14 7.2E-15 6.3E-14 1.1E-14 0.0E+00 8.2E-13
NNE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
NE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
ENE 0 0.000 0.000 0.000 0.000 0.02 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
East 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
ESE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
South 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
WSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
West 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 1.21 0.00 0.00 0.00 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
WNW 250 17.000 34.000 51.000 68.000 0.02 728 910 158 4 5.2E+03 6.5E+03 1.1E+03 2.9E+01 1.21 20.57 41.14 61.71 82.28 4.0E+09 8.4E+07 9.3E+06 3.9E+06 1.3E-06 7.7E-05 1.2E-04 7.2E-06 2.1E-03
NW 100 6.800 13.600 20.400 27.200 0.08 1155 618 27 2.7E+04 1.5E+04 6.4E+02 0.0E+00 1.21 8.23 16.46 24.68 32.91 3.9E+11 8.3E+09 9.2E+08 3.8E+08 7.0E-08 1.8E-06 7.0E-07 0.0E+00 2.5E-05
NNW 50 3.400 6.800 10.200 13.600 0.08 1103 671 26 2.6E+04 1.6E+04 6.2E+02 0.0E+00 1.21 4.11 8.23 12.34 16.46 8.4E+12 3.9E+11 5.1E+10 8.3E+09 3.1E-09 4.1E-08 1.2E-08 0.0E+00 5.6E-07
K.A.A. Watt
130
s1 s2 s3 s4 p
Hs = 0.5 Delta F n1 n2 n3 n4 N1 N2 N3 N4 (n/N)1 (n/N)2 (n/N)3 (n/N)4 Dd
[MPa] [MPa] [MPa] [MPa] %
North 5 0.044 0.087 0.131 0.174 0.13 1800 6.9E+04 0.0E+00 0.0E+00 0.0E+00 1.1E+30 2.1E+27 5.4E+25 4.1E+24 6.5E-26 0.0E+00 0.0E+00 0.0E+00 6.5E-26
MSc Thesis
NNE 5 0.044 0.087 0.131 0.174 0.14 1641 159 6.6E+04 6.4E+03 0.0E+00 0.0E+00 1.1E+30 2.1E+27 5.4E+25 4.1E+24 6.2E-26 3.1E-24 0.0E+00 0.0E+00 3.2E-24
NE 10 0.087 0.174 0.261 0.348 0.43 1260 529 11 1.6E+05 6.7E+04 1.4E+03 0.0E+00 2.1E+27 4.1E+24 1.1E+23 7.9E+21 7.7E-23 1.6E-20 1.3E-20 0.0E+00 3.0E-20
ENE 10 0.087 0.174 0.261 0.348 2.28 913 822 65 6.1E+05 5.5E+05 4.3E+04 0.0E+00 2.1E+27 4.1E+24 1.1E+23 7.9E+21 2.9E-22 1.4E-19 4.1E-19 0.0E+00 5.5E-19
East 75 0.653 1.305 1.958 2.610 5.63 1140 625 35 1.9E+06 1.0E+06 5.8E+04 0.0E+00 2.8E+19 5.4E+16 1.4E+15 1.1E+14 6.8E-14 1.9E-11 4.1E-11 0.0E+00 6.0E-11
ESE 25 0.218 0.435 0.653 0.870 5.22 1306 493 1 2.0E+06 7.5E+05 1.5E+03 0.0E+00 5.4E+23 1.1E+21 2.8E+19 2.1E+18 3.7E-18 7.1E-16 5.5E-17 0.0E+00 7.7E-16
SE 10 0.087 0.174 0.261 0.348 2.77 1053 706 41 8.5E+05 5.7E+05 3.3E+04 0.0E+00 2.1E+27 4.1E+24 1.1E+23 7.9E+21 4.1E-22 1.4E-19 3.1E-19 0.0E+00 4.6E-19
SSE 5 0.044 0.087 0.131 0.174 0.38 1730 70 1.9E+05 7.8E+03 0.0E+00 0.0E+00 1.1E+30 2.1E+27 5.4E+25 4.1E+24 1.8E-25 3.8E-24 0.0E+00 0.0E+00 4.0E-24
South 5 0.044 0.087 0.131 0.174 0.08 1800 4.3E+04 0.0E+00 0.0E+00 0.0E+00 1.1E+30 2.1E+27 5.4E+25 4.1E+24 4.0E-26 0.0E+00 0.0E+00 0.0E+00 4.0E-26
SSW 5 0.044 0.087 0.131 0.174 0.08 1800 4.3E+04 0.0E+00 0.0E+00 0.0E+00 1.1E+30 2.1E+27 5.4E+25 4.1E+24 4.0E-26 0.0E+00 0.0E+00 0.0E+00 4.0E-26
SW 10 0.087 0.174 0.261 0.348 0.37 1333 458 9 1.4E+05 4.9E+04 9.6E+02 0.0E+00 2.1E+27 4.1E+24 1.1E+23 7.9E+21 6.9E-23 1.2E-20 9.1E-21 0.0E+00 2.1E-20
WSW 15 0.131 0.261 0.392 0.522 1.11 776 916 108 2.5E+05 3.0E+05 3.5E+04 0.0E+00 5.4E+25 1.1E+23 2.7E+21 2.1E+20 4.7E-21 2.8E-18 1.3E-17 0.0E+00 1.6E-17
West 75 0.653 1.305 1.958 2.610 2.25 1500 299 1 9.9E+05 2.0E+05 6.6E+02 0.0E+00 2.8E+19 5.4E+16 1.4E+15 1.1E+14 3.6E-14 3.6E-12 4.7E-13 0.0E+00 4.1E-12
WNW 10 0.087 0.174 0.261 0.348 2.57 1066 711 23 8.0E+05 5.3E+05 1.7E+04 0.0E+00 2.1E+27 4.1E+24 1.1E+23 7.9E+21 3.9E-22 1.3E-19 1.6E-19 0.0E+00 3.0E-19
NW 10 0.087 0.174 0.261 0.348 1.51 1637 163 7.2E+05 7.2E+04 0.0E+00 0.0E+00 2.1E+27 4.1E+24 1.1E+23 7.9E+21 3.5E-22 1.8E-20 0.0E+00 0.0E+00 1.8E-20
NNW 5 0.044 0.087 0.131 0.174 0.39 1775 25 2.0E+05 2.9E+03 0.0E+00 0.0E+00 1.1E+30 2.1E+27 5.4E+25 4.1E+24 1.9E-25 1.4E-24 0.0E+00 0.0E+00 1.6E-24
s1 s2 s3 s4 p
Hs = 0.7 Delta F n1 n2 n3 n4 N1 N2 N3 N4 (n/N)1 (n/N)2 (n/N)3 (n/N)4 Dd
[MPa] [MPa] [MPa] [MPa] %
North 5 0.044 0.087 0.131 0.174 0.09 1800 4.7E+04 0.0E+00 0.0E+00 0.0E+00 1.1E+30 2.1E+27 5.4E+25 4.1E+24 4.4E-26 0.0E+00 0.0E+00 0.0E+00 4.4E-26
NNE 10 0.087 0.174 0.261 0.348 0.03 1246 538 16 1.2E+04 5.1E+03 1.5E+02 0.0E+00 2.1E+27 4.1E+24 1.1E+23 7.9E+21 5.7E-24 1.3E-21 1.4E-21 0.0E+00 2.7E-21
NE 25 0.218 0.435 0.653 0.870 0.21 1304 482 14 8.1E+04 3.0E+04 8.7E+02 0.0E+00 5.4E+23 1.1E+21 2.8E+19 2.1E+18 1.5E-19 2.8E-17 3.1E-17 0.0E+00 6.0E-17
ENE 25 0.218 0.435 0.653 0.870 1.74 834 888 75 3 4.2E+05 4.5E+05 3.8E+04 1.5E+03 5.4E+23 1.1E+21 2.8E+19 2.1E+18 7.8E-19 4.3E-16 1.4E-15 7.4E-16 2.5E-15
East 100 0.870 1.740 2.610 3.480 3.80 361 868 501 70 4.0E+05 9.6E+05 5.6E+05 7.8E+04 2.1E+18 4.1E+15 1.1E+14 7.9E+12 1.9E-13 2.4E-10 5.3E-09 9.8E-09 1.5E-08
ESE 25 0.218 0.435 0.653 0.870 2.09 391 988 371 50 2.4E+05 6.0E+05 2.3E+05 3.0E+04 5.4E+23 1.1E+21 2.8E+19 2.1E+18 4.4E-19 5.7E-16 8.2E-15 1.5E-14 2.3E-14
SE 25 0.218 0.435 0.653 0.870 0.42 1145 638 17 1.4E+05 7.7E+04 2.1E+03 0.0E+00 5.4E+23 1.1E+21 2.8E+19 2.1E+18 2.6E-19 7.3E-17 7.5E-17 0.0E+00 1.5E-16
SSE 10 0.087 0.174 0.261 0.348 0.03 1668 131 1 1.6E+04 1.2E+03 9.5E+00 0.0E+00 2.1E+27 4.1E+24 1.1E+23 7.9E+21 7.7E-24 3.1E-22 9.0E-23 0.0E+00 4.1E-22
24.5 Fatigue pile-head: front-/ side plates
South 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SW 25 0.218 0.435 0.653 0.870 0.05 1206 580 14 1.7E+04 8.3E+03 2.0E+02 0.0E+00 5.4E+23 1.1E+21 2.8E+19 2.1E+18 3.2E-20 7.8E-18 7.2E-18 0.0E+00 1.5E-17
WSW 25 0.218 0.435 0.653 0.870 0.42 389 1018 357 36 4.8E+04 1.3E+05 4.4E+04 4.5E+03 5.4E+23 1.1E+21 2.8E+19 2.1E+18 8.9E-20 1.2E-16 1.6E-15 2.1E-15 3.9E-15
West 125 1.088 2.175 3.263 4.350 1.21 838 847 113 2 3.0E+05 3.0E+05 4.0E+04 7.0E+02 2.8E+17 5.4E+14 1.4E+13 1.1E+12 1.1E-12 5.5E-10 2.8E-09 6.6E-10 4.0E-09
WNW 25 0.218 0.435 0.653 0.870 1.92 1292 502 6 7.3E+05 2.8E+05 3.4E+03 0.0E+00 5.4E+23 1.1E+21 2.8E+19 2.1E+18 1.3E-18 2.7E-16 1.2E-16 0.0E+00 3.9E-16
NW 15 0.131 0.261 0.392 0.522 1.28 943 797 59 1 3.5E+05 3.0E+05 2.2E+04 3.7E+02 5.4E+25 1.1E+23 2.7E+21 2.1E+20 6.5E-21 2.8E-18 8.0E-18 1.8E-18 1.3E-17
NNW 10 0.087 0.174 0.261 0.348 0.28 1489 310 1 1.2E+05 2.5E+04 8.1E+01 0.0E+00 2.1E+27 4.1E+24 1.1E+23 7.9E+21 5.8E-23 6.2E-21 7.7E-22 0.0E+00 7.0E-21
s1 s2 s3 s4 p
Hs = 0.9 Delta F n1 n2 n3 n4 N1 N2 N3 N4 (n/N)1 (n/N)2 (n/N)3 (n/N)4 Dd
[MPa] [MPa] [MPa] [MPa] %
North 5 0.044 0.087 0.131 0.174 0.05 1800 2.6E+04 0.0E+00 0.0E+00 0.0E+00 1.1E+30 2.1E+27 5.4E+25 4.1E+24 2.4E-26 0.0E+00 0.0E+00 0.0E+00 2.4E-26
NNE 25 0.218 0.435 0.653 0.870 0.01 1458 340 2 3.5E+03 8.1E+02 4.8E+00 0.0E+00 5.4E+23 1.1E+21 2.8E+19 2.1E+18 6.4E-21 7.6E-19 1.7E-19 0.0E+00 9.4E-19
NE 50 0.435 0.870 1.305 1.740 0.05 1397 395 8 2.0E+04 5.6E+03 1.1E+02 0.0E+00 1.1E+21 2.1E+18 5.4E+16 4.1E+15 1.9E-17 2.7E-15 2.1E-15 0.0E+00 4.9E-15
ENE 75 0.653 1.305 1.958 2.610 0.56 1103 676 21 1.8E+05 1.1E+05 3.4E+03 0.0E+00 2.8E+19 5.4E+16 1.4E+15 1.1E+14 6.6E-15 2.1E-12 2.5E-12 0.0E+00 4.5E-12
East 150 1.305 2.610 3.915 5.220 0.83 239 1066 484 11 5.8E+04 2.6E+05 1.2E+05 2.7E+03 5.4E+16 1.1E+14 2.7E+12 2.1E+11 1.1E-12 2.5E-09 4.3E-08 1.3E-08 5.8E-08
ESE 50 0.435 0.870 1.305 1.740 0.14 616 1005 174 5 2.5E+04 4.1E+04 7.0E+03 2.0E+02 1.1E+21 2.1E+18 5.4E+16 4.1E+15 2.3E-17 2.0E-14 1.3E-13 5.0E-14 2.0E-13
SE 50 0.435 0.870 1.305 1.740 0.02 1320 474 6 9.4E+03 3.4E+03 4.3E+01 0.0E+00 1.1E+21 2.1E+18 5.4E+16 4.1E+15 8.9E-18 1.6E-15 7.9E-16 0.0E+00 2.4E-15
SSE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
South 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
WSW 75 0.653 1.305 1.958 2.610 0.10 1259 536 5 3.6E+04 1.5E+04 1.4E+02 0.0E+00 2.8E+19 5.4E+16 1.4E+15 1.1E+14 1.3E-15 2.8E-13 1.0E-13 0.0E+00 3.9E-13
West 200 1.740 3.480 5.220 6.960 0.34 600 921 253 26 6.0E+04 9.2E+04 2.5E+04 2.6E+03 4.1E+15 7.9E+12 2.1E+11 1.5E+10 1.5E-11 1.2E-08 1.2E-07 1.7E-07 3.0E-07
WNW 50 0.435 0.870 1.305 1.740 0.89 1207 581 12 3.1E+05 1.5E+05 3.1E+03 0.0E+00 1.1E+21 2.1E+18 5.4E+16 4.1E+15 2.9E-16 7.3E-14 5.8E-14 0.0E+00 1.3E-13
NW 25 0.218 0.435 0.653 0.870 0.74 784 886 123 7 1.7E+05 1.9E+05 2.7E+04 1.5E+03 5.4E+23 1.1E+21 2.8E+19 2.1E+18 3.1E-19 1.8E-16 9.6E-16 7.3E-16 1.9E-15
NNW 15 0.131 0.261 0.392 0.522 0.24 1073 678 48 1 7.4E+04 4.7E+04 3.3E+03 6.9E+01 5.4E+25 1.1E+23 2.7E+21 2.1E+20 1.4E-21 4.4E-19 1.2E-18 3.4E-19 2.0E-18
131
s1 s2 s3 s4 p
Hs = 1.1 Delta F n1 n2 n3 n4 N1 N2 N3 N4 (n/N)1 (n/N)2 (n/N)3 (n/N)4 Dd
[MPa] [MPa] [MPa] [MPa] %
North 5 0.044 0.087 0.131 0.174 0.02 1789 11 8.5E+03 5.2E+01 0.0E+00 0.0E+00 1.1E+30 2.1E+27 5.4E+25 4.1E+24 8.0E-27 2.5E-26 0.0E+00 0.0E+00 3.3E-26
NNE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
NE 50 0.435 0.870 1.305 1.740 0.01 877 835 82 6 2.1E+03 2.0E+03 2.0E+02 1.4E+01 1.1E+21 2.1E+18 5.4E+16 4.1E+15 2.0E-18 9.6E-16 3.6E-15 3.5E-15 8.1E-15
ENE 100 0.870 1.740 2.610 3.480 0.10 521 843 410 26 1.5E+04 2.4E+04 1.2E+04 7.4E+02 2.1E+18 4.1E+15 1.1E+14 7.9E+12 7.2E-15 5.9E-12 1.1E-10 9.4E-11 2.1E-10
East 250 2.175 4.350 6.525 8.700 0.08 729 980 89 2 1.7E+04 2.3E+04 2.1E+03 4.8E+01 5.4E+14 1.1E+12 2.8E+10 2.1E+09 3.2E-11 2.2E-08 7.7E-08 2.3E-08 1.2E-07
ESE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
South 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
WSW 75 0.653 1.305 1.958 2.610 0.01 533 968 274 25 1.3E+03 2.3E+03 6.5E+02 5.9E+01 2.8E+19 5.4E+16 1.4E+15 1.1E+14 4.6E-17 4.3E-14 4.6E-13 5.6E-13 1.1E-12
West 300 2.610 5.220 7.830 10.440 0.07 564 904 312 20 1.1E+04 1.7E+04 5.9E+03 3.8E+02 1.1E+14 2.1E+11 5.4E+09 4.0E+08 1.0E-10 8.4E-08 1.1E-06 9.5E-07 2.1E-06
WNW 100 0.870 1.740 2.610 3.480 0.30 1115 670 15 9.8E+04 5.9E+04 1.3E+03 0.0E+00 2.1E+18 4.1E+15 1.1E+14 7.9E+12 4.7E-14 1.5E-11 1.3E-11 0.0E+00 2.7E-11
NW 50 0.435 0.870 1.305 1.740 0.57 1167 610 23 1.9E+05 1.0E+05 3.8E+03 0.0E+00 1.1E+21 2.1E+18 5.4E+16 4.1E+15 1.8E-16 4.9E-14 7.1E-14 0.0E+00 1.2E-13
NNW 25 0.218 0.435 0.653 0.870 0.24 1070 684 45 1 7.4E+04 4.7E+04 3.1E+03 6.9E+01 5.4E+23 1.1E+21 2.8E+19 2.1E+18 1.4E-19 4.4E-17 1.1E-16 3.3E-17 1.9E-16
s1 s2 s3 s4 p
Hs = 1.3 Delta F n1 n2 n3 n4 N1 N2 N3 N4 (n/N)1 (n/N)2 (n/N)3 (n/N)4 Dd
[MPa] [MPa] [MPa] [MPa] %
North 5 0.044 0.087 0.131 0.174 0.01 1601 198 1 3.8E+03 4.7E+02 2.4E+00 0.0E+00 1.1E+30 2.1E+27 5.4E+25 4.1E+24 3.6E-27 2.3E-25 4.4E-26 0.0E+00 2.7E-25
NNE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
NE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
ENE 150 1.305 2.610 3.915 5.220 0.02 509 913 356 22 3.6E+03 6.5E+03 2.5E+03 1.6E+02 5.4E+16 1.1E+14 2.7E+12 2.1E+11 6.7E-14 6.2E-11 9.3E-10 7.6E-10 1.8E-09
East 350 3.045 6.090 9.135 12.180 0.01 1071 672 55 2 2.5E+03 1.6E+03 1.3E+02 4.8E+00 2.6E+13 5.1E+10 1.3E+09 1.0E+08 9.7E-11 3.1E-08 9.8E-08 4.7E-08 1.8E-07
ESE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
South 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
WSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
West 500 4.350 8.700 13.050 17.400 0.01 567 940 283 10 1.3E+03 2.2E+03 6.7E+02 2.4E+01 1.1E+12 2.1E+09 5.4E+07 4.1E+06 1.3E-09 1.1E-06 1.2E-05 5.9E-06 1.9E-05
WNW 150 1.305 2.610 3.915 5.220 0.08 753 898 148 1 1.8E+04 2.1E+04 3.5E+03 2.4E+01 5.4E+16 1.1E+14 2.7E+12 2.1E+11 3.3E-13 2.0E-10 1.3E-09 1.2E-10 1.6E-09
NW 50 0.435 0.870 1.305 1.740 0.29 601 928 246 25 5.0E+04 7.7E+04 2.0E+04 2.1E+03 1.1E+21 2.1E+18 5.4E+16 4.1E+15 4.7E-17 3.7E-14 3.8E-13 5.1E-13 9.3E-13
NNW 50 0.435 0.870 1.305 1.740 0.11 1508 291 1 4.7E+04 9.0E+03 3.1E+01 0.0E+00 1.1E+21 2.1E+18 5.4E+16 4.1E+15 4.4E-17 4.3E-15 5.7E-16 0.0E+00 5.0E-15
s1 s2 s3 s4 p
Hs = 1.5 Delta F n1 n2 n3 n4 N1 N2 N3 N4 (n/N)1 (n/N)2 (n/N)3 (n/N)4 Dd
[MPa] [MPa] [MPa] [MPa] %
North 5 0.044 0.087 0.131 0.174 0.02 1264 524 12 6.0E+03 2.5E+03 5.7E+01 0.0E+00 1.1E+30 2.1E+27 5.4E+25 4.1E+24 5.7E-27 1.2E-24 1.1E-24 0.0E+00 2.3E-24
NNE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
NE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
ENE 0 0.000 0.000 0.000 0.000 0.02 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
East 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
ESE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSE 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
South 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
SW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
WSW 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
West 0 0.000 0.000 0.000 0.000 0.00 0.0E+00 0.0E+00 0.0E+00 0.0E+00 2.1E+63 4.1E+60 1.1E+59 7.9E+57 0.0E+00 0.0E+00 0.0E+00 0.0E+00 0.0E+00
WNW 250 2.175 4.350 6.525 8.700 0.02 728 910 158 4 5.2E+03 6.5E+03 1.1E+03 2.9E+01 5.4E+14 1.1E+12 2.8E+10 2.1E+09 9.6E-12 6.1E-09 4.1E-08 1.4E-08 6.1E-08
NW 100 0.870 1.740 2.610 3.480 0.08 1155 618 27 2.7E+04 1.5E+04 6.4E+02 0.0E+00 2.1E+18 4.1E+15 1.1E+14 7.9E+12 1.3E-14 3.6E-12 6.1E-12 0.0E+00 9.7E-12
NNW 50 0.435 0.870 1.305 1.740 0.08 1103 671 26 2.6E+04 1.6E+04 6.2E+02 0.0E+00 1.1E+21 2.1E+18 5.4E+16 4.1E+15 2.5E-17 7.7E-15 1.1E-14 0.0E+00 1.9E-14
K.A.A. Watt
132
MSc Thesis
133