G011653135 PDF
G011653135 PDF
G011653135 PDF
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 11, Issue 6 Ver. V (Nov- Dec. 2014), PP 31-35
www.iosrjournals.org
Abstract: Failure in reinforced concrete elements (Partial or complete collapse) may due to lack in design or
in certainties of detailing or due to poor construction, or poor concreting and insufficient curing, or due to poor
building materials, such as cement, aggregates and reinforcing steel.
Failure in reinforced concrete structures may also due to the movement of foundations or due to excessive
vibrations in the neibour-hoods.
During the last 10 years (1998-2014) failure in reinforced concrete buildings in Khartoum district has been
predominant.
The research contained in this paper is a result of a series of scientific case studies regarding failure or at least
deficiency in some building complexes in Khartoum district carried by the author during his professional
practice through his consultant firm named (Thiga for Engineering Consultants and Experimentation) located
in Khartoum.
Many buildings (having number of stories range between 7-13 storey) has been studied according to scheduled
investigations.
It has been found that the major reasons of these failure are duo to poor concreting, slab excessive deflection,
excessive cracks in beams, foundation settlement, insufficient design, low thickness of slab, and other reasons.
I. Introduction:
Cracks may be caused by the external applied load on the structure just like flexural crack, shear crack,
other cracks are also occurring independently, for example cracking of restrained members due to concrete
shrinkage. Or temperature change, surface cracking of fresh concrete in plastic stage, and surface cracking of
new concrete near reinforcing bar. However, the major cracks in concrete structures may be due to lack in
design or details, bad instruction.
Settlement in foundation or due to the time factor (1). A typical study in Egypt showed percentage
comparisons of these factors as shown in Fig. 1 (2).
- Partial collapse of foundation, which is common among older stone foundation. Mortar has deteriorated and
stones have fallen into the basement area. The loss of structural foundation support has caused cracking of
drywall in the building interior. This is a form of deterioration.
- Cracks in wallboard due to settling.
- Cracks formed instantaneously as a result of a natural gas leakage fueled explosion in the building.
- Cracks in block wall about halfway up the wall. This is an indicator of soil and! or water pressure causing
inward deflection of the wall and impending failure. In this case, water drainage toward the foundation had
caused an excessive hydraulic load. Lock of maintenance of gutter drainage and grade near the wall has
increased hydraulic loading against the wall over time. (see Fig. 2 for the differenftypes of cracks in
buildings).
Taking fig.. (a & b) under consideration, Welch and Janjua (4) proposed that the crack spacing S is given by:
www.iosrjournals.org 32 | Page
Failure cracks in reinforced concrete structures in Khartoum District
Where h is the concrete cover measured to the bar centre and db is diameter; the same authors proposed the
following formula for the maximum crack width;
The CEB- FIP model code (5) proposed the following formula for the crack spacing:
Where a is the spacing of the reinforcing bars and pr is the ratio of steel bar to effective surrounding area of
concrete in tension.
Gergely and Lutz (6) has proposed that
Where h is the minimum cover to the centre of the bar and A is the concrete tension area surrounding
each bar.
ACI (7) proposed the following formula for the maximum crack width in fully cracked tensile
members.
(5)
Or
(6)
Where = ratio of distance between neutral axis and tension face to distance between neutral axis and centroid
of reinforcing steel 1.2 in beams.
fs = actual tensile strength of concrete in psi dc = distance from centre of bar to extreme tension fiber in (in.)
A = area of concrete symmetric with reinforcing steel divided by the number of bars (in2).
www.iosrjournals.org 33 | Page
Failure cracks in reinforced concrete structures in Khartoum District
2.
Riadh KRT 7 Flat - Raft
3.
Riadh KRT 6 Flat - Raft
www.iosrjournals.org 34 | Page
Failure cracks in reinforced concrete structures in Khartoum District
IV. Conclusions:
From the case study in this research, the following conclusions can be drawn:
1) The main cracks in reinforced concrete buildings are due mainly to lack in construction process.
2) Soil testing is very important before the design process of the reinforced concrete building.
3) The flat slab may be one of the main causes of failure in reinforced concrete structures due to the punching
shear developed at the column face.
4) Insufficient design and poor detailing may lead to failure in reinforced concrete structures.
5) In design the ability requirements like the expansion joints, the reinforced concrete cores, and the shear
walls should be taken under consideration.
References:
[1]. Future Engineering Group Design of high rise building to resist wind and seismic loads in Arabic, walid printing press, Egypt
1994, 480 pp.
[2]. Abu Almagd. .et..al Cracks in Reinforced Concrete Structures and its Repair, Egyptian Universities Printing Press, Cairo,
2007.
[3]. Concrete manual, 8th edition, U.S. Bureau of Reclamation, Denver, 1975, 627 pp.
[4]. Janjun, M.A and Welch, G.B Magnitude and Distribution of concrete cracks in Reinforced concrete Flexural Members, UNICJV.
Report No. R 78, Univ. of NSW, Kensington, 1972.
[5]. CEB-FIP Model Code for Concrete Structures, C&CA, London, 1979.
[6]. Gergely P., and Lutz, L.A Maximum crack width in reinforced concrete flexural member, ACT publications, sp-20, Detroit, 87-1
17 pp. 1968.
[7]. 7. ACI 224 2R 92, Cracking of Concrete Members in Direct Tensiontt, re-approved 1997.
[8]. Finite Element Analysis of Reinforced Concrete, American Society of Civil Engineers, New York, 1982, 545 pp.
[9]. Morell, P. Design of Reinforced Concrete Elements, Granda,U.K,1984.
www.iosrjournals.org 35 | Page