Pump Station Design Manual
Pump Station Design Manual
Pump Station Design Manual
STATION SIZING
SPREADSHEET
1.0 DESCRIPTION
This spreadsheet was developed as a tool to perform the preliminary sizing of storm sewer pump
station and to complement the analysis performed by much advanced software which don’t have
the flexibility of quickly varying the input data. This spreadsheet could be used first to pre-size and
calibrate a pump station and then use the results for further analysis without having the burden of
performing countless trial and error analysis.
The analysis performed by this spreadsheet is a level pool flood routing of a pump station system
given its watershed area, the rainfall depth and duration, the unit hydrograph and peaking factor.
In addition the user can choose different storm hydrograph generating procedure. The pump
station is defined by its geometry, pumps capacities, “on” and “off” setting, and the storage
available in the storm sewer network.
This spreadsheet generates watershed inflow hydrograph output, outflow hydrograph output,
stage duration graph, and displays also the number of times a pump will turn “on” and “off”, as
well as the amount of working hours.
Areas
Areas are entered as “Acres” or “Hectares”.
SCS CN
CN (curve number) depends on the type of land cover.
Time of Concentration
The time of concentration is entered in minutes.
Hydrologic Method
Three different hydrologic analysis method can be used.
SCS – Santa Barbara Method
SCS – Design Storm
SCS – Flood Hydrograph
Rainfall Depth
Rainfall depth for the selected storm is entered in inches or millimeters.
Routing Time
This is the duration of the storm in hours.
Peaking Factor
The SCS peaking factor, and the length of the receding leg of the hydrograph. This variable
is dependent on the hydrologic method selected.
Pumps Settings
The pumps “on” and “off” elevations are entered in feet or meter. The CUMULATIVE flow
for all the pumps are entered at each row. The unit is either cfs, or cubic meter per second.
Additional Storage
The storage within the drainage system is entered at each stage elevation. The unit is feet,
and cubic feet, or meter, and cubic meter.
Design Criteria:
Design storm to satisfy FDOT critical storms duration as per Chapter 14-86.
Minimum elevation of +3.70 for new pavement.
Drainage for low lying side streets will need to be accommodated.
Design:
Total tributary area A=36.81 acres
SCS weighted curve number CN = 96
Critical storm is FDOT 1 Hour hydrograph with rainfall depth of 3.60 inches
Maximum watershed runoff flow is 132.23 cfs at 54.25 hours
Trunk line length is 4,600 feet divided into a south and north reach.
The south reach controls the design with a length of 2,490 feet.
The south reach has 30 manholes risers, and 1 terminal manhole.
The north reach is 2,110 feet.
The north reach has 25 manholes risers, and 1 terminal manhole.
Minimum existing inlet elevation +2.20 NAVD
Step 1
Find pump station preliminary total flow estimated at 70% of the watershed flow.
Qtotal = 132.23 cfs x 70% of inflow = 92.56 cfs
A preliminary headloss – system curve analysis yields a pump station with three pumps
having a total capacity of 93.36 cfs. (refer to step 5)
Step 2
Find trunk line preliminary pipe diameter for a conveyance velocity of 3.0 ft/s to 3.5 ft/s
Diameter for 3.0 ft/s = (92.56 cfs x 4 / (3.0 ft/s x 3.14159))^.5 = 6.3 ft ( 6.0 feet = 72 inches)
Diameter for 3.5 ft/s = (92.56 cfs x 4 / (3.5 ft/s x 3.14159))^.5 = 5.8 ft ( 5.5 feet = 66 inches)
Step 3
Calculate head losses along trunk line
Crown elevation based on structure type = 3.70 NAVD – 3.67 = +0.03 NAVD
In order to expedite construction the City has decided to use spiral reinforced HDPE pipe. This pipe
will be placed under water and requires a soil overburden atop the pipe to prevent floatation. The
minimum crown elevation needed to prevent uplift is -1.00 NAVD.
Although the 66 inches pipe is sufficient, the 72 inches pipe will be used with crown placed at -1.00
NAVD, invert set at -7.00 NAVD. The benefit of using the 72 inches instead of the 66 inches will be
less head loss (lower HGL), longer filling time which will translate into longer cycling time between
pumps start.
The pumps used are “in tube” axial flow pump. This setting allows lower minimum
submergence depth. As a result the pump station needs not to be set very deep.
The spacing between pumps is also reduced.
Another requirement was to construct the station in a modular fashion. The modular
approach allowed the units to be pre-cast at the casting yard, and transported on
site for setting and installation.
Daugherty, Robert L., and Franzini, Joseph B.: “Fluid Mechanics with Engineering Applications,”
McGraw-Hill Book Co., New York, 1985.
Mc Cuen, Richard:”Hydrologic Analysis and Design”, Second Edition, Prentice Hall, New Jersey,
1998.
Reitz, and Jens:”Design of Urban Highway Drainage, the State of the Art”, FHWA-TS-79-225, Federal
Highway Administration, August 1979.
Shammas, Namir C.; “Mathematical Algorithms in Visual Basic for Scientists and Engineers,”
McGraw-Hill Book Co., New York, 1995.