Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Pump Station Design Manual

Download as pdf or txt
Download as pdf or txt
You are on page 1of 35

STORM SEWER PUMP

STATION SIZING
SPREADSHEET

Francis Mitchell, M.S., P.E.


F-MITCHELL@ATT.NET
STORM SEWER PUMP STATION SIZING SPREADSHEET
Abstract:
This spreadsheet is a tool to help the drainage engineer designs a storm sewer pump station by
performing a level pool analysis of the pumping system, and storage areas. The settings of the
pumps “on” and “off” points, flows, system storage, the storm hydrograph, rainfall depth, and
duration, are parameters that could be adjusted to optimize the size of a pump station.

This spreadsheet can be downloaded through the link below,


https://www.dropbox.com/sh/jf8vsmhhq013mdd/AACJfnUjpiiCieTCusBS0JxEa?dl=0

Francis Mitchell, M.S., P.E. PAGE 1


STORM SEWER PUMP STATION SIZING SPREADSHEET

Table of Contents Page


1.0 DESCRIPTION ................................................................................................................................ 3
2.0 INPUT DATA WORKSHEETS.......................................................................................................... 4
3.0 OUTPUT DATA WORKSHEETS ...................................................................................................... 8
4.0 CASE STUDY ................................................................................................................................ 16
5.0 AUTHOR ...................................................................................................................................... 33
6.0 REFERENCES ............................................................................................................................... 34

Francis Mitchell, M.S., P.E. PAGE 2


STORM SEWER PUMP STATION SIZING SPREADSHEET

1.0 DESCRIPTION
This spreadsheet was developed as a tool to perform the preliminary sizing of storm sewer pump
station and to complement the analysis performed by much advanced software which don’t have
the flexibility of quickly varying the input data. This spreadsheet could be used first to pre-size and
calibrate a pump station and then use the results for further analysis without having the burden of
performing countless trial and error analysis.

The analysis performed by this spreadsheet is a level pool flood routing of a pump station system
given its watershed area, the rainfall depth and duration, the unit hydrograph and peaking factor.
In addition the user can choose different storm hydrograph generating procedure. The pump
station is defined by its geometry, pumps capacities, “on” and “off” setting, and the storage
available in the storm sewer network.

This spreadsheet generates watershed inflow hydrograph output, outflow hydrograph output,
stage duration graph, and displays also the number of times a pump will turn “on” and “off”, as
well as the amount of working hours.

Francis Mitchell, M.S., P.E. PAGE 3


2.0 INPUT DATA WORKSHEETS

Francis Mitchell, M.S., P.E. PAGE 4


Design Unit
Design unit is either “Metric” or “English”.

Areas
Areas are entered as “Acres” or “Hectares”.

SCS CN
CN (curve number) depends on the type of land cover.

Time of Concentration
The time of concentration is entered in minutes.

Hydrologic Method
Three different hydrologic analysis method can be used.
 SCS – Santa Barbara Method
 SCS – Design Storm
 SCS – Flood Hydrograph

Rainfall Depth
Rainfall depth for the selected storm is entered in inches or millimeters.

Routing Time
This is the duration of the storm in hours.

Flood Routing Time Step


The time step increment for the routing analysis to be performed.

Print Display Time step


The time step for a result to be printed. This option is currently disabled.

Peaking Factor
The SCS peaking factor, and the length of the receding leg of the hydrograph. This variable
is dependent on the hydrologic method selected.

Francis Mitchell, M.S., P.E. PAGE 5


Francis Mitchell, M.S., P.E. PAGE 6
Top Elevation and Top Area
The pump station top elevation and top area are entered in feet, and square feet, or meter,
and square meter.

Critical Water Level


The stage at which the water level reached a critical value is entered in feet or meter. This
input data is only for graphical representation of the design constraint.

Starting Water Level


The starting water level is the level of the permanent pool of water inside the pump station.
This data is entered in feet or meter. The stage of the starting water level cannot be higher
than the lowest pump starting elevation.

Bottom Elevation and Bottom Area


The pump station bottom elevation and bottom area are entered in feet, and square feet,
or meter, and square meter.

Pumps Settings
The pumps “on” and “off” elevations are entered in feet or meter. The CUMULATIVE flow
for all the pumps are entered at each row. The unit is either cfs, or cubic meter per second.

Additional Storage
The storage within the drainage system is entered at each stage elevation. The unit is feet,
and cubic feet, or meter, and cubic meter.

Francis Mitchell, M.S., P.E. PAGE 7


3.0 OUTPUT DATA WORKSHEETS

Francis Mitchell, M.S., P.E. PAGE 8


Francis Mitchell, M.S., P.E. PAGE 9
Francis Mitchell, M.S., P.E. PAGE 10
Francis Mitchell, M.S., P.E. PAGE 11
Francis Mitchell, M.S., P.E. PAGE 12
Francis Mitchell, M.S., P.E. PAGE 13
Francis Mitchell, M.S., P.E. PAGE 14
Francis Mitchell, M.S., P.E. PAGE 15
4.0 CASE STUDY
Project:
The City of Miami Beach, and the Florida Department of Transportation District Six, have decided
to jointly fund the construction of a major storm sewer pump station facility to offer relief from
recurrent flooding events along Indian Creek Drive from 25th Street to 41st Street. These floodings
are mainly caused by the ever increasing high tides, and deficient gravity drainage systems that
were built in the 1940s.

Design Criteria:
 Design storm to satisfy FDOT critical storms duration as per Chapter 14-86.
 Minimum elevation of +3.70 for new pavement.
 Drainage for low lying side streets will need to be accommodated.

Design:
 Total tributary area A=36.81 acres
 SCS weighted curve number CN = 96
 Critical storm is FDOT 1 Hour hydrograph with rainfall depth of 3.60 inches
 Maximum watershed runoff flow is 132.23 cfs at 54.25 hours
 Trunk line length is 4,600 feet divided into a south and north reach.
 The south reach controls the design with a length of 2,490 feet.
 The south reach has 30 manholes risers, and 1 terminal manhole.
 The north reach is 2,110 feet.
 The north reach has 25 manholes risers, and 1 terminal manhole.
 Minimum existing inlet elevation +2.20 NAVD

Step 1
Find pump station preliminary total flow estimated at 70% of the watershed flow.
Qtotal = 132.23 cfs x 70% of inflow = 92.56 cfs
A preliminary headloss – system curve analysis yields a pump station with three pumps
having a total capacity of 93.36 cfs. (refer to step 5)

Step 2
Find trunk line preliminary pipe diameter for a conveyance velocity of 3.0 ft/s to 3.5 ft/s
Diameter for 3.0 ft/s = (92.56 cfs x 4 / (3.0 ft/s x 3.14159))^.5 = 6.3 ft ( 6.0 feet = 72 inches)
Diameter for 3.5 ft/s = (92.56 cfs x 4 / (3.5 ft/s x 3.14159))^.5 = 5.8 ft ( 5.5 feet = 66 inches)

Step 3
Calculate head losses along trunk line

Francis Mitchell, M.S., P.E. PAGE 16


Head losses for 66 inches pipe – south branch

Ref: Hydraulic Calculator Software from HYDTRENCH


Manhole risers losses = 30 x 0.15 x ((3.93)^2 / 64.4) = 1.08 feet
Terminal manhole loss = 1 x 0.5 x ((3.93)^2 / 64.4) = 0.12 foot
Manhole 90 deg. Bend to pump station = 1 x 0.7 x ((3.93)^2 / 64.4) = 0.17 foot
Pipe exit losses to pump station = 1 x 1.0 x ((3.93)^2 / 64.4) = 0.24 foot
Losses along length of south pipe = 2,490 feet x 0.0659 / 100 = 1.64 feet
-------------
Total Losses 3.25 feet

Minimum crown elevation of pipe for HGL to be below existing inlet


+2.20 NAVD – 3.25 feet (head losses) = -1.05 NAVD

Francis Mitchell, M.S., P.E. PAGE 17


Head losses for 66 inches pipe – south branch

Ref: Hydraulic Calculator Software from HYDTRENCH


Manhole risers losses = 30 x 0.15 x ((3.30)^2 / 64.4) = 0.76 foot
Terminal manhole loss = 1 x 0.5 x ((3.30)^2 / 64.4) = 0.08 foot
Manhole 90 deg. Bend to pump station = 1 x 0.7 x ((3.30)^2 / 64.4) = 0.12 foot
Pipe exit losses to pump station = 1 x 1.0 x ((3.30)^2 / 64.4) = 0.17 foot
Losses along length of south pipe = 2,490 feet x 0.0414 / 100 = 1.03 feet
-------------
Total Losses 2.16 feet

Minimum crown elevation of pipe for HGL to be below existing inlet


+2.20 NAVD – 2.16 feet (head losses) = +0.04 NAVD

Francis Mitchell, M.S., P.E. PAGE 18


Step 4
Find crown elevation based on concrete manhole structures placed along new pavement
Frame and cover height 9.0 inches
Brick leveling (2 layers) 8.0 inches
Concrete slab thickness 8.0 inches
Minimum wall height above opening 6.0 inches
Minimum spaces around pipe 6.0 inches
Pipe thickness 7.0 inches
---------------
Total Cover 44 inches (3.67 feet)

Crown elevation based on structure type = 3.70 NAVD – 3.67 = +0.03 NAVD
In order to expedite construction the City has decided to use spiral reinforced HDPE pipe. This pipe
will be placed under water and requires a soil overburden atop the pipe to prevent floatation. The
minimum crown elevation needed to prevent uplift is -1.00 NAVD.

Although the 66 inches pipe is sufficient, the 72 inches pipe will be used with crown placed at -1.00
NAVD, invert set at -7.00 NAVD. The benefit of using the 72 inches instead of the 66 inches will be
less head loss (lower HGL), longer filling time which will translate into longer cycling time between
pumps start.

Francis Mitchell, M.S., P.E. PAGE 19


Typical project pump station layout

Drawing Sketch Credit: Ribbeck Engineering Inc.

The pumps used are “in tube” axial flow pump. This setting allows lower minimum
submergence depth. As a result the pump station needs not to be set very deep.
The spacing between pumps is also reduced.

Another requirement was to construct the station in a modular fashion. The modular
approach allowed the units to be pre-cast at the casting yard, and transported on
site for setting and installation.

Francis Mitchell, M.S., P.E. PAGE 20


Step 5 – Head loss at low water level

Pump flow at low water level (maximum head) is 29.57 cfs

Francis Mitchell, M.S., P.E. PAGE 21


Head loss at high water level

Pump flow at high water level (minimum head) is 32.67 cfs


Average of pump flow for high and low water level is (32.67 cfs + 29.57 cfs)/2 = 31.12 cfs

Francis Mitchell, M.S., P.E. PAGE 22


Watershed input data

Francis Mitchell, M.S., P.E. PAGE 23


Pump station input data

Francis Mitchell, M.S., P.E. PAGE 24


Inflow Hydrograph

Francis Mitchell, M.S., P.E. PAGE 25


Outflow hydrograph

Francis Mitchell, M.S., P.E. PAGE 26


Inflow – outflow hydrograph

Francis Mitchell, M.S., P.E. PAGE 27


Stage duration

Francis Mitchell, M.S., P.E. PAGE 28


Cumulative inflow – outflow volume

Francis Mitchell, M.S., P.E. PAGE 29


Pumps running time

Francis Mitchell, M.S., P.E. PAGE 30


Pumps capacity and “on” “off” setting rating curve

Francis Mitchell, M.S., P.E. PAGE 31


System storage capacity rating curve

Francis Mitchell, M.S., P.E. PAGE 32


5.0 AUTHOR

This spreadsheet can be ordered from the following address.

Francis Mitchell, M.S., P.E.


f-mitchell@att.net
Phone: (305) 979-6387

Or by accessing the link below,


https://www.dropbox.com/sh/jf8vsmhhq013mdd/AACJfnUjpiiCieTCusBS0JxEa?dl=0

Francis Mitchell, M.S., P.E. PAGE 33


6.0 REFERENCES
Federal Highway Administration, Highway Stormwater Pump Station Design Manual,
HEC-24, 2000. Formerly Highway Storm Water Pumping Stations, Volumes 1 and 2,
FHWA-IP-82-17.

Daugherty, Robert L., and Franzini, Joseph B.: “Fluid Mechanics with Engineering Applications,”
McGraw-Hill Book Co., New York, 1985.

Mc Cuen, Richard:”Hydrologic Analysis and Design”, Second Edition, Prentice Hall, New Jersey,
1998.

Reitz, and Jens:”Design of Urban Highway Drainage, the State of the Art”, FHWA-TS-79-225, Federal
Highway Administration, August 1979.

Shammas, Namir C.; “Mathematical Algorithms in Visual Basic for Scientists and Engineers,”
McGraw-Hill Book Co., New York, 1995.

Soil Conservation Service:”National Engineering Handbook Section 4-Hydrology, (Part 1 of 2, 2 of


2), Engineering Division Soil Conservation Service, USDA, Washington, March 1985.

South Florida Water Management District:”Management and Storage of Surface Waters-Permit


Information Manual Volume IV”.Streeter, Victor L., and Wylie, Benjamin E.: “Fluid Mechanics,”
McGraw-Hill Book Co., New York, 1979.

Mitchell, Francis : “HYDTRENCH, Exfiltration Trench manual”, Miami, 1999.

Francis Mitchell, M.S., P.E. PAGE 34

You might also like