My Te - Der
My Te - Der
My Te - Der
SPECIFICATION
and
for
for
Client:
SECTION 1 3
Preliminary Matters 3
1.0 Introduction 3
1.1 PRELIMINARY PARTICULARS ETC. 5
1.2 GENERAL MATTERS 5
1.3 STATUTORY/GENERAL OBLIGATIONS 6
1.4 MANAGEMENT/ADMINISTRATION PROCEDURES 8
1.5 RESOURCES/TEMPORARY WORKS AND SERVICES 9
1.6 THE WORKS GENERALLY 11
1.7 CONTRACTUAL MATTERS 15
1.8 CONTINGENCY/ PROVISIONAL/ PRIME COST SUMS 15
1.9 APPROVED SUB-CONTRACTORS 16
1.10 PROVISIONAL DAYWORKS 16
1.11 WORKS UNDERTAKEN CONCURRENTLY BY OTHERS 16
1.12 LIAISON
1.13 PHASING OF WORKS 16
1.14 TEMPORARY SIGNAGE 16
1.15 SITE RULES 16
1.16 SECURITY CLEARANCE 17
APPENDIX 1 18
SECTION 2 20
HEALTH & SAFETY 20
PRE TENDER HEALTH & SAFETY PLAN 20
2.0 GENERAL REQUIREMENTS 20
2.2 Checking/Handling and Site Storage of Materials and Components Error! Bookmark not
defined.
2.3 Loading. Error! Bookmark not defined.
2.4 Working at Heights Error! Bookmark not defined.
2.5 Proximity to Public
2.6 Method Statements Error! Bookmark not defined.
2.7 Pre-Tender Health & Safety Plan
2.8 Client’s own Safety Representative Error! Bookmark not defined.
2.9 Health & Safety File Error! Bookmark not defined.
SECTION 3 23
Trade Preambles 23
3.01 MATERIALS 23
3.02 WORKMANSHIP
SECTION 4 27
SCHEDULE OF WORKS 27
SECTION 5 28
TENDER SUBMISSION
5.0 TENDER SUBMISSION
5.1 TENDER ACCEPTANCE
5.2 BASIS OF PRICES
5.3 AWARD CRITERIA (other than price)
5.4 PRICING SCHEDULE
SECTION 6
POINTS OF CONTACT
SECTION 7 31
CONTRACT TIMETABLE 31
7.0 CONTRACT TIMETABLE 31
REF IWM/VPS1292 IWMD LWH External redecoration.
REF IWM/VPS1292 IWMD LWH External redecoration.
SECTION 1
Preliminary Matters
1.0 Introduction
1.1.1 Employer
S J Rogers FRICS
Capital Projects manager
Imperial War Museum
Duxford CB22 4QR
The works comprise the redecoration of the external steel frame to the Land
Warfare Hall located on the south site at Duxford.
The site is located immediately to the east of the M11/A505 junction in South
Cambridgeshire.
Access into the site is from the A505 to the south side and via the staff
entrance/guardroom.
The following drawings form part of this specification and will become contract
documents.
The contractor shall limit his operations to the immediate area of the works.
REF IWM/VPS1292 IWMD LWH External redecoration.
The Contractor shall be deemed to have visited and inspected the site and to have
examined drawings (if any) and contract documents and to have adequately
acquainted himself with local conditions, accessibility of the works and site, the
nature of the ground and subsoil, supply of and conditions affecting labour, the
availability and supply of materials, water, electricity and telephones, all in relation to
the execution of the works as no claim on the ground of want of knowledge in such
respect will be entertained.
The term ‘Contractor’ used throughout this document relates to the Contractor who
is contracted to carry out and complete the works. The contractor shall be the
‘Principal Contractor’ under the CDM regulations.
The reference to Building Inspector means Building Control Officer, District Surveyor
or any other person with authority under statute to require compliance with any
regulation or byelaw.
The term ‘Provide’ means that the item(s) is to be supplied, delivered and fixed at
the expense of the builder.
The term ‘Day Work’ is applicable to the work of an unknown or unforeseen nature
that could not be specified and therefore estimated for during the preparation of the
schedule of works. Such work is usually paid for on a time and material basis with
the Contractor submitting evidence of hours of work and invoices for materials,
plant, etc.
Allow for complying with all enactments, regulations and working rules relating to
safety, health and welfare of work people.
These works are subject to the CDM Regulations 2015, but is considered not to be
notifiable.
Monday to Friday - 0730 - 1700. Weekend working will only be allowed with the
prior agreement of Employer. The contractor may extend working hours on
weekdays subject to approval of Employer.
1.3.4 Noise
Fit all compressors, percussion tools and vehicles with effective silencers of a type
recommended by manufacturers of the compressors, tools or vehicles.
Adequately protect, uphold, maintain and prevent damage to all services. Do not
interfere with their operation without consent of the service authorities or private
owners or the CA as appropriate.
Prevent damage to existing buildings, fences, gates, walls, roads, paved areas,
other of the site features, which are to remain in position during the execution of the
works.
The contractor shall be responsible for properly making good to the satisfaction of
the C.A. all areas disturbed during the execution of the works. Contractor is to plan
the works and in particular the maneuvering of plant and machinery so as to cause
minimal disturbance to adjacent areas.
The contractor is advised the roof of the LWH is finished with a single ply
membrane, laid over approx. 130mm PIR insulation board, and supported by a
troughed metal deck. The roof is designed to accommodate occasional pedestrian
REF IWM/VPS1292 IWMD LWH External redecoration.
1.4.1 Supervision
1.4.2 Insurances
Before starting work on site submit to the employer (through the CA) documentary
evidence and/or policies and receipts for all insurances which are required to be
taken out by the Contractor.
1.4.3 Programme
As soon as possible and prior to starting work on site, prepare, in an approved form,
a programme for the works that should make allowance for all:
Inform CA as least seven working days before proposed date for commencement of
the work on site.
1.4.5 Monitoring
REF IWM/VPS1292 IWMD LWH External redecoration.
Record progress on site and keep a copy of the programme on site. Update or re-
draft without delay if circumstances arise which affect the progress of the works with
copies of all revisions to CA.
Hold regular site meetings as necessary for the proper management and co-
ordination of the contract and as required by the CA. Meetings will normally be held
every four weeks. Attend all meetings and inform subcontractors and suppliers
when their presence is required. Notify all consultants. The CA will take the Chair
and minutes will be taken and distributed by the CA.
1.4.8 Measurements
Give reasonable notice to the CA before covering up work, which the CA requires to
be measured.
1.4.9 Covering Up
Give not less than one working days notice to the CA or Clerk of Works before
covering up.
1.5.1 Accommodation
Routes from fire escape staircases away from the building must not be obstructed at
any time.
1.5.2 Protection
Provide temporary fencing, hoardings, screens, vans, planked footways, guard rails,
gantries and the like as may be necessary for protecting the public and others, for
the proper execution of the works and for meeting the requirements of the Local or
other Authority.
The contractor will be required to fence the works to prevent unauthorized persons
entering into the working area. Plastic mesh fencing held by metal posts, to 1.2m
REF IWM/VPS1292 IWMD LWH External redecoration.
1.5.3 Scaffolding
The contractor must allow in his tender for providing a safe means of access for
operatives to all areas subject to works. In deciding what access equipment is
necessary, the contractor must fully appraise the works, undertake a risk
assessment and identify the most suitable method of operation.
Where the scaffold falls outside the scope of a ‘basic’ scaffold, the contractor must
supply to the CA detailed information to show compliance with the BSEN12811-1
standard. Further advice on what is required is contained in volume 2 of TG20-08.
As a minimum, this must include drawings showing the general scaffold
arrangement, a method statement describing the erection and dismantling
sequence, the permitted platform loadings, restrictions on use and
calculations to show compliance with the standard.
Where the scaffold is the subject of design the person responsible for the design
shall make an inspection and certify the scaffold is erected in accordance with the
design and drawings.
Erection, alteration and dismantling of all scaffolds must be under the direct
supervision of a competent person – an advanced scaffolder or design engineer
with the appropriate industry experience.
REF IWM/VPS1292 IWMD LWH External redecoration.
The contractor is referred to HSE guidance note for a list of scaffold structures that
need to be the subject of design.
For the avoidance of doubt, the means of access to any particular working
platform must be arranged so that it is outside of the working platforms and does not
obstruct or restrict their use. eg a ladder access tower, or platform steps. (The use
of trap doors within the platforms will not be permitted).
If ladders are proposed for access to scaffold platforms, these must not be used for
bringing materials or tools of any sort to the working platform. A separate
arrangement must be made for bringing material to the platform level – hoists etc.
1.5.4 Water
Water for the works is available on site free of charge. Contractor is to make
temporary arrangements for storing and distributing around the site.
1.5.5 Electricity
The contractor is to make his own arrangements for the supply of power he may
require.
GENERALLY
Where and to the extent the materials, products and workmanship are not fully
specified they are to be:
Handle, store, prepare and use, or fix each product in accordance with
manufacturers printed or written instructions/recommendations. Inform CA if these
conflict with any other specified requirement.
1.6.3 Workmanship
The works to be carried out by, or under the close supervision of, experienced
tradesmen, skilled in the particular type of work.
Make adequate provisions for services, including unobstructed routes and fixtures.
Wherever possible, ducts, chases and holes to be formed during construction rather
than cut.
PRODUCTS/MATERIALS GENERALLY
Unless otherwise specified. Ensure that the whole quantity of each product and
material required to complete the work is of consistent kind, size, quality and overall
appearance.
Handle, store and fix products with care to ensure that they are not damaged when
incorporated into the works.
ACCURACY/SETTING OUT
1.6.9 Accuracy
N/A
Adequately safeguard the site, products, materials, plant, the works and any existing
buildings affected by the works from damage and theft. Take all responsible
precautions to prevent unauthorized access to the site, the works and adjoining
property.
REF IWM/VPS1292 IWMD LWH External redecoration.
1.6.11 Stability
Accept responsibility for stability and structural integrity of the works during the
contract, and support as necessary. Prevent overloading/damage. Details of
design loads may be obtained from the CA.
Adequately protect the works from damage by inclement weather and use all
reasonable and approved building aids and methods to prevent or minimize delays
during cold or inclement weather.
1.6.13 Rubbish
Remove rubbish and debris as it accrues and keep the site and works clean and
tidy.
Control the drying and humidity of the works and the application of heat to prevent:
3. Excessive movement.
ALTERATIONS/EXTENSIONS/MAINTENANCE WORK
Means carry out local remedial work, including the following as appropriate and
necessary to leave the work sound and neat to approval:
1. Remove defective parts of existing finishes and components and around any
stated features.
2. Fill, dress down, piece in, patch, extending existing finishes, make minor
repairs and adjustments.
3. Refix or re-stick.
4. Redecorate.
SAMPLES/APPROVALS/TESTING/INSPECTION
REF IWM/VPS1292 IWMD LWH External redecoration.
Retain approved samples on site for comparison with the works. Remove samples
which are not part of the finished works when no longer required.
1.6.24 Approvals
Inspection of any other action by the CA must not be taken as approval of materials,
products or work unless the CA confirms in writing the express terms referring to:
1. Date of inspection.
FIXING/FASTENINGS/ADHESIVES/MORTAR
Use fixings and jointing methods and types and spacings of fastenings which are
suitable having regard to:
1.6.26 Cleaning
1.6.27 Certification
Not required.
The Form of Contract will be the JCT Agreement for Minor Works 2011 Edition,
together with amendments to date including the April 2015 ammendement
incorporating the CDM Regulations 2015.
The Contractor should include for all costs incurred in compliance with the Terms
and Conditions of the Contract.
The Specification and drawings (if any) will become contract documents.
The Contractor must include for all works shown on the drawings, whether referred
to in the Specification or not, and for all works which are not included in the
Specification, or on the drawings which could reasonably be expected to be
included in the works.
Appendix 1 at the end of these Preliminaries describes the contractual details that
will be included in the Contract Conditions.
Allow the contingency sum of £3000, for works of an unforeseen nature. Such sum
is only to be expended on the authority of the CA.
Not used.
Not used.
Not used.
Not used
Not used.
The works are located at roof level – and as such this provides separation of the
working area from the remainder of the site.
Any ladders for emergency egress must be tied, and enclosed with fencing fence at
the bottom with warning signs to keep people away. Such ladders will be required to
be taken down at the end of each working day. Any fencing/enclosure should be
arranged so that is does not obstruct pedestrian or staff access/egress from the
building.
Contractor is to provide appropriate warning signs and notices in order to warn the
public or site users.
The Museum operate specific rules for ‘Safe Working Conditions and Protection of
its Staff, Visitors and Collection’.
REF IWM/VPS1292 IWMD LWH External redecoration.
These will be made available as part of the contractor’s induction which the CA will
provide pre contract. The contractor will be required to sign the form included in the
booklet to confirm he has read the rules and will ensure all work is carried out in
accordance with same.
The C.A. will carry out a site induction for all contractors’ operatives on the morning
of the first day of starting on site.
All of the contractor’s staff will need to be security cleared prior to undertaking any
work on site. Security forms are available from the guardroom and must be
competed and returned at least 3 weeks prior to commencement.
The successful contractor if not on the museum’s approved supplier system, will be
required to complete a ‘New Suppliers Form (appendix 3) and return it to the C.A.
within 5 days of award of contract.
REF IWM/VPS1292 IWMD LWH External redecoration.
APPENDIX 1
Contract:
The form of contract will be the JCT Agreement for Minor Building Works 2011
together with any amendments to date.
ARTICLES OF AGREEMENT:
Recitals:
First. The work required is the external redecoration of steel roof structure, Land
Warfare Hall, Duxford.
Third. The contractor shall supply a fully priced copy of the specification to the
employer.
Fifth. This project is considered not to be notifiable under the CDM Regulations
2015.
Articles :
Article 5 The appointed contractor will be the Principal Contractor under the
CDM Regulations.
Contract Particulars:
4.8.1. 3 months
4.11 Deleted
SECTION 2
HEALTH & SAFETY
GENERAL REQUIREMENTS
The works that are the subject of this Specification are subject to the Construction
(Design & Management) Regulations 2015. Specifically Part 4 – General
Requirements for all construction sites. The principal contractor will be required to
comply with the relevant regulations contained in part 4.
The Contractor will be required to operate as the ’Principal contractor’ under those
regulations and co-ordinate and manage Health & Safety issues during construction
work, and, liaise with the Contract administrator during the course of these works.
Prior to commencement the contractor must ensure a construction phase health and
safety plan has been produced, and that adequate provision is made on site for
provision of welfare.
The Contractor will be responsible for ensuring that subcontractors employed by him
operate in a safe manner appropriate to the work they are employed to undertake.
Special attention is to be paid to the scaffold work, not only the design of same, but
also the erection and dismantling sequence and methodology.
The following aspects of the work are considered to represent a risk, either to the
person engaged in undertaking that work directly, or to other persons in the area of
the works. These are to be addressed in the Principal contractor’s Construction
Phase Plan.
The work will involve working in areas where public have access around, and into
buildings. Staff similarly will have access to and be in occupation of buildings during
the works.
Contractor is to organize works such that pedestrian access into and egress from
buildings is not obstructed.
REF IWM/VPS1292 IWMD LWH External redecoration.
The museum has 3 major airshows during the year, when the site is particularly
busy.
Contractor is to pay particular attention to how paint and associated materials are
handled and stored.
Manufacturer’s COSSH data sheets should be followed and available on site for
inspection by CA.
Some products are likely to be flammable - specific provisions for safe storage and
handling must be identified by Contractor.
The contractor is to detail the measures to be taken to ensure safe working access
and platforms.
The steel roof trusses make access and egress to the working area difficult.
Arrangements must be put in place to ensure safe egress from the roof in an
emergency.
The client will arrange for a temporary alarm sounder to be wired in to the fire alarm
to warn of a fire.
Emergency egress provision should be made such that the distance from any point
of working, to emergency egress ladder/platform is no more than 25m.
The contractor is advised the roof of the LWH is finished with a single ply
membrane, laid over approx. 130mm PIR insulation board, and supported by a
troughed metal deck. The roof is designed to accommodate occasional pedestrian
access for the purposes of maintenance only. Works must be undertaken in a
REF IWM/VPS1292 IWMD LWH External redecoration.
manner that does not cause damage to the roof coverings/ fabric of the building and
does not overload the roof.
The Contractor shall provide, with his tender, an outline Method Statement setting
out how the work is to be approached, organized and monitored in order to ensure
the works are undertaken both efficiently and safely.
Throughout the construction phase the principal contractor is to ensure the plan is
reviewed, and updated, or revised so that it continues to be sufficient to ensure
construction work is so far as is reasonably practicable carried out without risks to
health or safety.
The ‘Principal Designer’ for this project is The IWM, represented by S J Rogers
Capital Project Manager. The Principal contractor shall liaise and cooperate with the
Principal designer in preparing the plan and providing information for inclusion into
the Health and safety File.
The Principal Designer will prepare the Health and Safety file. The Principal
Contractor is to provide information on request to enable the file to be preapared.
Such information is likely to include, but not be limited to
.
REF IWM/VPS1292 IWMD LWH External redecoration.
SECTION 3
Trade Preambles
3.01 MATERIALS
The contractor is asked to supply a ‘extra over price with his tender for applying a
different weather coat as follows.
Interfine 979 – Application to achieve a wet film thickness of at least 100 micron to
achieve dry film thickness of 75 micron.
0.05 Primer
After suitable preparation of surfaces, apply Interplus 256 primer to a wet film
thickness of at least 156micron and dry film thickness 125 micron.
3.02 WORKMANSHIP
0.01 Generally
Obtain liquid materials in containers sized to suit the extent of the work and to
prevent deterioration of residual quantities in opened containers.
Work in a sequence that ensures the finished work is not spoilt by dust and debris
arising from subsequent preparation work. When planning the work consider the
need for cleaning, washing down, heating or drying equipment.
Ensure removal of defective, flaking, peeling and poorly adhering coatings back to a
firm coating or back to the original background.
Note – the preparation of surfaces will require considerable work as the existing
paints finishes are in poor condition.
Use portable power tools to clean welded or bolted joints any damaged areas to St3
ISO 8501-1:1998 (Swedish Standard SIS 05 5900/SSPC-SP3). Feather all loose
and cracked paints to a firm edge.
Apply Interthane Plus to any areas where the steel substrate, or rust is evident.
This will usually involve thoroughly stirring liquid paints so that all solids are fully and
evenly incorporated. Do not use thinners without the specific consent of the
CA.
Take particular care to observe manufacturer’ pot life, timing and queueing
directions when preparing two part coatings.
Wash, wipe or otherwise remove any dirt or contaminant. (Do not use a brush as
this move dust to another surface.)
(i) Temperature of the surface is too low eg. heavy metalwork, plastered
external walls etc.
0.09 Application
Lightly rub down between coats if necessary by fine wet and dry paper on fully
hardened surfacing.
0.10 Inspections
CA will make frequent site inspections to judge the preparation and quality of the
work.
The work will be inspected from time to time by a qualified coating inspector who will
check surface preparation and sample paint film thicknesses to establish the work is
compliant with the specification.
‘
0.11 Sampling and Testing
Contractor shall supply samples of paints for analysis at the CA’s request during the
course of the work. The samples may be taken from open tins, or from applied
work.
H3 IWMD External redecoration and repair
SECTION 4
SCHEDULE OF WORKS
Exposed steel eaves beam to the barrel vault at the west end
of the building.
Steel handrail over the Bailey bridge at the main entrance and
the steel guard railing each side of the entrance along the
path.
Page 28 of 34
H3 IWMD External redecoration and repair
SECTION 5
Tender Submission
The contractor will be required to comply with the following in order for their tender
to be considered.
If the contractor does not comply fully, then the tender may be rejected by the
Museum.
As part of the process the Contractor shall visit site to acquaint themselves with the
site, the extent of the work and the conditions under which it is to be carried out.
The contractor is to contact Mr. S Rogers at the Duxford site on 01223 497220 to
make arrangements.
FM Department
Imperial War Museum
Duxford airfield
Duxford
Cambs CB224QR
FAO Mr S Rogers.
Envelopes and/or packages should be plain and bear no reference to the tenderer's
name; franking machines that automatically print the company name should not be
used.
Tenders in envelopes that in any way may identify the tenderer will not be
considered.
Page 29 of 34
H3 IWMD External redecoration and repair
It is the responsibility of the tenderer to ensure that their tender is delivered no later
than the appointed date and time.
The Trustees do not undertake to consider tenders received after the appointed
date and time unless clear evidence of posting is available (i.e. a clear postmark
and/or certificate of posting).
Late tenders franked with the firm’s own franking machine will automatically be
rejected.
The Trustees do not bind themselves to accept the lowest or any tender and reserve
the right to accept a portion of any tender unless the tenderer expressly stipulates
otherwise on his tender. Tenders shall remain open to acceptance by the Trustees
for a period of 6 weeks from the date required for submission.
The Trustees will not accept liability for any expenses incurred in the preparation of
the tender.
All prices must be quoted on the basis of lump sum fixed price based on no re-
measurement, as indicated in the accompanying documents. Quantities given are
for guidance only and prices entered should exclude VAT.
The contractor shall as part of tender submission include the following information:
b) The names & contact details of two references where the company has
carried out similar work.
Page 30 of 34
H3 IWMD External redecoration and repair
The employer does not bind himself to accept the lowest or any tender; when
awarding the contract in addition to price the Employer will have regard to the
following.
h) Accuracy of submission.
Page 31 of 34
H3 IWMD External redecoration and repair
SECTION 6
CONTRACT TIMETABLE
The following schedule represents the proposed timetable for the appointment of a
consultant and commencement of the contract for the services in relation to various
external building projects as detailed within the tender documents on behalf of the
Trustees of the Imperial War Museum.
To be advised.
CT 2.2 Contract Start Date:
Page 32 of 34
H3 IWMD External redecoration and repair
I/We having read the following documents delivered to me/us in respect of the
above Contract:
£_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ (excluding VAT)
(_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ amount in words).
Alternatively for the enhanced specification for the use of Interthane 979 as
the weather coat , I/we Do hereby offer to execute and complete in
accordance with the Conditions of Contract the whole of the works as
described for the sum of: -
£_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ (excluding VAT)
(_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ amount in words).
Company Name:
___________________________________________________
Address:
___________________________________________________
__________________________________________________
_
__________________________________________________
_
Tel. No. _____________________
Fax. No. _____________________
Signature:
___________________________________________________
Print Name:
___________________________________________________
In the Capacity of:___________________________________________________
Page 33 of 34
H3 IWMD External redecoration and repair
(The above named person is duly authorised to sign tenders for and on behalf
of the Company)
Page 34 of 34