A Civ Spe 000 30002 1
A Civ Spe 000 30002 1
A Civ Spe 000 30002 1
Revision History
Revision Changes
Holds
Hold No. Location Description
Page 2 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
CONTENTS
1 INTRODUCTION 5
1.1 PURPOSE 5
1.2 PROJECT OVERVIEW 5
1.3 SCOPE 5
1.4 REGULATORY REQUIREMENTS 6
2 REFERENCES 6
2.1 RELATED ENGINEERING SPECIFICATIONS AND DOCUMENTS 6
2.2 ALGERIAN REGULATIONS 6
2.3 CODES 6
2.4 ORDER OF PRECEDENCE 7
2.5 UNITS 7
3 DEFINITIONS 8
3.1 DEFINITIONS OF MATERIALS 8
4 SURVEYS 10
5 SITE DATA 10
6 SITE CLEARANCE (STRIPPING AND GRUBBING) 10
7 GENERAL EXCAVATION 12
8 PROOF ROLLING AND RECONDITIONING 13
8.1 PROOF ROLLING SUBGRADE 13
8.2 RECONDITIONING THE SUBGRADE 14
9 STOCKPILING AND DISPOSAL OF MATERIALS 14
10 DRAINAGE AND DEWATERING 15
11 FILL MATERIALS 16
11.1 SUITABLE FILL (GENERAL) 16
11.2 FILL AROUND AND UNDER FOUNDATIONS 16
11.3 FILL AROUND AND UNDER BURIED CABLES 16
11.4 TUFF MATERIAL 17
12 PLACEMENT OF FILL 17
12.1 GENERAL 17
12.2 FILL MATERIAL 18
12.3 CRUSHED STONE MATERIAL 19
13 COMPACTION 19
13.1 GENERAL 19
13.2 FILL COMPACTION 20
13.3 DEGREE OF COMPACTION 20
14 SHORING AND SAFETY 21
Page 3 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
Page 4 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
1 INTRODUCTION
1.1 PURPOSE
The objective of this specification is to describe the minimum requirements for all
earthworks operations for the Ain Tsila Development.
1.3 SCOPE
The scope of this document is to specify the minimum requirements for quality of
materials and workmanship for all earthworks carried out throughout the Ain Tsila
Development for site preparation, cut and fill operations, berms and dikes, road works,
foundation construction, trenches and underground services including but not limited to:
• Rough grading of the site, including site clearance.
• Excavation and backfill
• Drains and service trenches
• Stockpiling and disposal of materials
• Shoring and protection
• Reconditioning of the subgrade
• Compaction and testing
Page 5 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
2 REFERENCES
2.3 CODES
Current editions of the industry standards including all mandatory addenda in effect at
the time of the order shall apply unless otherwise indicated.
2.3.1 British codes
BS 1377 Methods of test for soils for civil engineering purposes.
Parts 1 to 9
BS 5930+A2 Code of practice for site investigation
BS 6031 Code of practice for earthworks
BS 812 Testing aggregates. Parts 2, 103.2, 104, 109 to 114, 119, 121, 123 and 124
BS 8004 Code of practice for foundations
2.3.2 American codes
ASTM D421 Standard Practice for Dry Preparation of Soil Samples for Particle size
Analysis and Determination of Soil Constants
Page 6 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
In the event of conflict between the requirements of this specification and other
referenced documents, the CONTRACTOR shall request written clarification from
COMPANY. The order of precedence will normally be:
• Algerian Legislation.
• Algerian Regulatory Authorities Regulations.
• International codes and standards.
• COMPANY Philosophy documents.
• Project Specifications
2.5 UNITS
• Elevations : Metre (m).
• Dimensions : Millimetre (mm).
• Force : Kilo Newton (kN).
• Mass : Kilogramme (kg).
• Moment : Kilo Newton metre (kNm).
Page 7 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
3 DEFINITIONS
The terms and definitions as used within this document are listed below :
“CONTRACTOR” means the party, which carries out all or part of the design,
engineering, installation and commissioning, procurement
and construction applicable to this specification
“shall” or “must” indicates that the specified action is mandatory (i.e. must be
done by the specified action party)
“Goods” means the physical items delivered under the terms of the
purchase order or contract
Page 8 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
Page 9 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
3.1.8 Fill
The term ‘fill’ shall mean any materials which can be deposited formed and compacted
under a designed and controlled scheme of placement to achieve a specified quality of
ground.
3.1.9 Rock fill
"Rock fill" shall consist of hard, durable, inert material of size and shape suitable for
placement and compaction.
3.1.10 Silt
"Silt" shall mean non-clayey soils with individual particle size less than 0.06 mm.
3.1.11 Cemented soil
"Cemented soils" shall mean soils in which the grains or aggregates adhere firmly and
are bound together by a material which acts as a cementing agent, e.g., lime, silica and
aluminium hydrates.
3.1.12 Contaminated soil
The term "Contaminated soil" shall mean soil which contains extraneous material or
materials which have a deleterious effect on the engineering properties of the soil or
may create an environmental hazard.
4 SURVEYS
• The sub-contractor shall establish all lines and grades after starting from the
horizontal and vertical control lines furnished by the CONTRACTOR in
accordance with contract drawings.
• The location and description of existing survey monuments to be used for
horizontal and vertical control shall be shown on the topographical drawings.
Existing monuments shall not be removed unless the removal is approved in
advance by COMPANY.
• It is the CONTRACTOR’s responsibility for accuracy of survey work performed.
5 SITE DATA
The results of soil investigation carried out on various locations are described in the
Project documents and the following geotechnical reports:
• A-CIV-REP-000-30019 Geotechnical Survey Report for CPF and associated
facilities
• A-CIV-REP-000-30020 Geotechnical Survey Report for Pipelines and Remote
areas
Page 10 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
• The stripped material shall not be used as fill, unless approved by COMPANY,
and shall be removed from site and disposed of at locations to be agreed with
and approved by COMPANY. Disposal shall be in accordance with Algerian
regulations.
• Trees, shrubs and other landscape features specifically designated for
preservation shall be carefully protected from abuse, marring or damage during
construction operations. An exclusion zone shall be established around such
trees and haul, traffic routes, and material storage shall not be permitted within
a horizontal distance equivalent to 1.5 x H, where H = height of the tree (H=Min.
4 m). This measure will ensure protection against “pressure” damaging root
structures.
• In areas designated for clearing and grubbing, all stumps, roots etc shall be
removed to a depth of at least 900 mm below existing grade or below final grade
whichever is lower.
• All holes remaining after grubbing shall be backfilled as required with approved
material to re-establish the final grades.
• Where unsuitable material (such as organic soils or debris) extends below the
required elevations, the excavation shall be continued until suitable soil is
reached (as approved by COMPANY). After all unsuitable material is removed,
refill the excavation in layers to the required elevation with suitable fill material
and compact as stated in section 12.0 and 13.0.
• The CONTRACTOR shall inform COMPANY, in writing, concerning any existing
obstacles, including culverts, ditches, cables, pipes or foundations, which are
encountered during top soil stripping or excavation work. The CONTRACTOR
shall prepare a report which includes the location, description, dimensions,
elevation and any other data determining the exact extent of the underground
objects.
• The CONTRACTOR shall not commence demolition or removal of such
obstacles without receipt of COMPANYs written approval.
• In accordance with local regulations and the Environmental Plan for the Ain Tsila
Project the CONTRACTOR shall consider the recycling of demolition materials
for use as fill materials. CONTRACTOR shall seek approval of COMPANY prior
to use and shall demonstrate that the materials have suitable engineering
properties and will not have any adverse environmental impact if re-used.
• The CONTRACTOR shall adequately protect from damage any items or
features that require to be preserved.
• All demolition materials if not suitable for use as fill materials shall be removed
regularly from site as work progresses
• Before commencing any excavation work the CONTRACTOR shall inspect and
survey each job site, using detection tools if appropriate, to identify and locate
any existing cables or pipes. The CONTRACTOR shall take adequate
precautions to avoid damage or disturbance to existing cables and pipes
Page 11 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
7 GENERAL EXCAVATION
• Common excavation shall include removal and transportation of all material of
whatever nature that is encountered in the work to the fill or spoil areas.
• Excavation work shall be executed using modern, suitable and well maintained
equipment and workmanship shall comply with BS 6031.For selection of the
equipment the CONTRACTOR shall take into account, the type of soil, the
presence of existing constructions and environmental considerations.
• Selection of equipment and work sequence are the responsibility of the
CONTRACTOR unless specified otherwise by COMPANY. The
CONTRACTOR’s choice of equipment and work sequence shall be subject to
the approval of COMPANY.
• The CONTRACTOR shall provide and maintain all necessary shoring and
bracing to prevent excavation slips or collapse and damage to existing work
caused by settlement, lateral movement, undermining, wash outs or other
hazards.
• Personnel shall not enter or perform works in excavations unless the
excavations have been stepped, braced or otherwise stabilized to eliminate the
risk of collapse. Excavations shall be inspected at the start of each shift by a
competent person before any personnel are allowed to enter.
• The CONTRACTOR shall take all necessary measures to keep excavations free
of water.
• Excavation shall extend a sufficient distance from walls and footings faces to
provide safe working space for operations such as placing and removal of
formwork or for the installation of any utilities or other works or to provide access
for inspection.
• Where excavation is required for several closely spaced individual footings, the
whole area may be excavated.
Page 12 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
• After stripping, if the topsoil is below the design elevation (i.e. fill areas), 300mm
of soil shall be removed and replaced with suitable fill compacted to 95% MDD.
For areas, where loose/soft soil (like fech-fech) is found after removal of 300mm;
further cutting and backfilling shall be done.
• Excavation in an area shall not be made below the levels indicated on the design
drawings except where removal of unsuitable material is required by this
Specification. Material excavated below designated levels shall be replaced with
suitable fill.
• Where soft/loose (like fech-fech material), unstable or otherwise unsuitable
material is encountered at the bottom of a cut, excavation shall continue to a
suitable horizon approved by COMPANY. The cut shall then be refilled to the
required elevation with concrete or other approved compactable material.
• The bottoms of excavations for footings and foundations shall not be disturbed
or trimmed to final grade earlier than of twenty four hours before the concrete is
to be placed unless approved by COMPANY.
• The under-cutting of existing foundations shall not be carried unless approved
by COMPANY.
• Excavated material which is intended to be re-used as fill shall be stockpiled
safely at an adequate distance from the edge of excavations in accordance with
section 9 below.
• Pipe trench excavation should start at a low point, to enable the excavation to
be kept dry.
• The width of trenches shall be sufficient to provide adequate working space
between the outside of pipes, cables or other works and the face of any required
shoring or trench sheeting.
• Minimum widths of excavations and depth for cable trenches and duct banks
shall be indicated on the electrical and instrument drawings.
• Excavations should only be kept open as long as reasonably required for the
work.
• Excavated material shall be stored in designated stockpile areas on site.
Adequate support shall be provided where necessary to prevent slope failure of
earth or settlement of adjacent ground, structures or other works.
• All required safety and personnel protection measures (fall protection) shall be
provided in accordance with section 14 below.
Page 13 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
suitable fill, pavement base etc. Although proof rolling operations may achieve
additional compaction of the stable soils, it is primarily intended to locate
unstable areas.
• All subgrade areas shall be proof rolled and shall be completely covered by
compaction equipment (of min 10Ton) minimum 6-8 passes (minimum 3 to 4
passes in each direction) as required each way in perpendicular directions.
Equipment and passes required for proof rolling under restricted surfaces, refer
Appendix 1. The existing soil shall be compacted and proof rolled but no
compaction (in-situ density) test is required except below foundations.
• After any stripping/excavation, the existing soil shall be proof rolled. As per
section 4.3.6 (c) of Doc No-PIP CVS02100 (Revision May 2014), if proof-rolling
demonstrates (by visual observation) ruts between 1 and 2 inches (25 to 50mm)
deep after localized soft spots have been repaired, the top 6 inches (150mm) of
the overall area shall be scarified and re-compacted. For areas where ruts
exceed 2 inches deep, top 12 inches (300mm) shall be scarified and re-
compacted.
• If unsatisfactory conditions are observed the CONTRACTOR shall notify
COMPANY. The related earthwork operations shall not proceed until such
conditions are corrected.
Page 14 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
Page 15 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
11 FILL MATERIALS
Page 16 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
12 PLACEMENT OF FILL
12.1 GENERAL
12.1.1 Backfill to excavated areas shall be carried out as promptly as the work allows, but not
until completion of the following:
• Removal of concrete formwork, shoring and bracing
• Approval by COMPANY or its representative of any underground construction
work.
• Inspection by COMPANY or its representative of excavated area.
12.1.2 Prior to placement of fill, the area shall be cleared of topsoil, debris, waste and soil
containing organic material.
12.1.3 Before backfilling around newly installed foundations, all formwork shall be removed,
and the excavation cleared of debris and waste.
12.1.4 Fill shall not be placed against foundations for at least three days after placing concrete
and not before the concrete has been inspected and approval to backfill has been given
by COMPANY.
12.1.5 Where there is a shortage of suitable fill materials locally available, imported fill shall be
used, subject to the approval COMPANY.
12.1.6 Retaining walls shall not be backfilled for at least seven days after concreting and shall
be subject to obtaining satisfactory concrete cylinder strength results and the approval
of COMPANY.
12.1.7 Backfill shall be placed symmetrically to prevent eccentric loading on structures. It shall
be placed in horizontal layers not exceeding 250 mm loose thickness or as specified on
engineering drawings and shall have the correct moisture content for the required degree
of compaction. All layers shall be tested to ensure adequate compaction unless one of
the methods described in Appendix 1 is used in which case a reduced testing regime
may be agreed with COMPANY. Any reduction in testing shall be subject to satisfactory
test results being consistently achieved.
12.1.8 Backfilling shall be to the grades and levels shown on the engineering drawings.
12.1.9 Backfill around culverts and pipes shall be symmetrically placed to prevent side loading
and shall be compacted to provide firm support. Backfill shall be placed in horizontal
layers not exceeding 150 mm loose thickness to the tops of all piping, culverts and
Page 17 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
electrical cables. Above this level fill should be placed in layers not exceeding 200 mm
loose thickness.
12.1.10 When backfilling pipes and cable trenches, the following guidelines shall be adhered to
unless specific guidelines exist in the relevant electrical and piping specifications:
• Fill to cable trenches shall be as specified in section 11.3 placed below and
around the cables up a minimum level of 150 mm above the top cables. Above
that level the same material as specified for suitable fill can be used.
• Fill to buried piping shall be clean sand placed for a minimum depth of 100 mm
below and a minimum of 300 mm above and around buried piping. Above the
sand layer the same material as specified for suitable fill can be used.
• Pipe joints should be left exposed until the necessary tests have been
performed, and in the case of concrete pipes for at least twenty four hours after
joints have been made.
• Pipes, cables and protective coatings shall not be damaged during backfilling
operations.
• Fill shall not be placed around piping and cables until they have been inspected
and approval to fill has been given by COMPANY.
12.1.11 When subgrades are likely to sustain damage due to shrinkage cracks, they should be
kept moist until protected by sub-base, capping or surfacing material.
12.1.12 Areas which are improperly backfilled or where settlement occurs shall be re- excavated
to the original depth or a depth to be agreed with COMPANY. The top layer of subgrade
shall be scarified to a depth of 300 mm and re-compacted before commencing fill
operations. The CONTRACTOR shall refill as necessary and restore the surface to the
required grade and degree of compaction.
Fill material placed within 300mm of the finished paving shall not contain more than 20%
material passing through a 75 microns BS sieve.
12.1.13 Placement of backfilling in compressible areas - The geotechnical report shall identify
the areas where the earth at fill-in level is likely to settle under backfilling action. If any,
operations shall be carried out following a precise calendar and the settlement measured
and recorded. The CONTRACTOR shall submit to COMPANY approval a special
monitoring program. The fill-in shall be made to a level higher than the project level and
shall be completed as settlement occurs. Once the settlement is stable the fill-in shall be
completed to the planned project level. The methods used to speed up settlements must
be submitted to the COMPANY for approval.
Page 18 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
required to achieve the necessary degree of compaction for the material. However,
sections 12.1.7, 13.1.12 and 13.1.13 are still applicable.
13 COMPACTION
13.1 GENERAL
13.1.1 The CONTRACTOR shall be responsible for choosing the equipment to be used for
earthworks and compaction which shall be subject to the approval of COMPANY.
13.1.2 Compaction shall be carried out as method compaction or end-product compaction using
appropriate equipment for the type of fill and the site conditions. Method compaction
shall normally apply to general fill and large areas of fill. End product compaction shall
normally apply to fill under and around foundations and structures.
13.1.3 Power driven hand tampers shall be used to compact backfill adjacent to and between
structures, piping and duct banks. Vibrating plates shall be used for compaction of sand
fill in cable trenches.
13.1.4 Before commencing filling activities, the existing soil shall be compacted and proof rolled.
13.1.5 The degree of compaction of fill shall be measured against Modified Proctor values
obtained in the laboratory at optimum moisture content using accepted test methods
such as ASTM D 1557.
13.1.6 Unless otherwise specified on the design drawing, the compaction criteria given below
shall be used for compacting fill materials.
13.1.7 Each fill layer shall be tested by the CONTRACTOR unless agreed otherwise by
COMPANY. The CONTRACTOR shall receive approval of COMPANY representative
before starting the next layer.
13.1.8 Each layer of fill shall be compacted to at least the following percentages of the maximum
density obtained in the laboratory at optimum moisture content by the test specification
indicated:
• 95% of the maximum density test values for fills under and around foundations
and under floor slabs, paving and roads.
• 90% of the maximum density test values for fills in open areas (other than facility
areas).
Page 19 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
13.1.9 The water content of fill during compaction shall be within ±2% of the optimum moisture
content determined by laboratory test.
13.1.10 Care shall be taken to apply water uniformly to the soil to be compacted.
13.1.11 Compaction testing shall be carried out the frequency specified in section 15.4.
13.1.12 The acceptance of both granular and clayey fill layers greater than 250mm loose
thickness is dependent on the compaction criteria being verified by tests. The field
density of the compacted layer shall be measured on full thickness. Where results fall
outside the specification limits the layers are to be reduced to a maximum 200mm
thickness.
13.1.13 A guide to compaction methods is given in Appendix 1. The CONTRACTOR is not
obliged to adopt any of the method specifications described and in any case will remain
solely responsible for ensuring that the equipment and procedures that he does use will
achieve the required degree of compaction through the full thickness of the compacted
layer.
13.1.14 The location of, and the class of fill will be noted on the design drawings or as specified
in the other standards and specifications.
13.1.15 The type of compaction plant, minimum number of passes and maximum thickness of
compacted layer shall generally be in accordance with Appendix 1.
Page 20 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
13.3.2 Locations for 90% Maximum Dry Density (MDD) Compacted Fill or existing soil -
Unless noted otherwise on drawings the following areas shall be compacted to 90% of
MDD:
a. Tankage bund walls
b. Laydown and temporary facility
13.3.3 Bund for Vehicle Protection Lines
VPL bund shall be constructed with excavated soil from ditch and tamping of side slopes
shall be done after achieving bund height for stability.
13.3.4 If the existing soil in contact with the bottom of the foundations cannot be compacted to
the requirements of sections 13.3.1 and 13.3.2, it shall be removed to a 300 mm depth
and replaced by a suitable fill material. The compaction of the suitable material shall
meet the requirements of sections 13.3.1 and 13.3.2. Before backfilling, section 13.1.4
applies.
Page 21 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
15.1 GENERAL
The CONTRACTOR shall ensure the quality of the work in respect of both workmanship
and materials. Quality Control procedures shall include the submission of records on a
daily basis to COMPANY or as otherwise agreed.
The CONTRACTOR shall be responsible for sampling and testing of materials and the
preparation and submission of test reports.
The CONTRACTOR shall employ the services of an independent and licensed materials
testing laboratory for quality control of the material to be used for excavation and fill
operations. A testing program shall be agreed at the start of the contract for physical
and chemical tests. Test reports shall be submitted to COMPANY to prove compliance
with the specification.
15.1.1 Workmanship
The CONTRACTOR shall employ qualified personnel, fully experienced in the works to
be carried out. Drivers/operators for the following machines shall have the experience
for driving each particular machine as follows:
• bulldozers, backhoes, front loaders, graders – 5 years minimum
• trucks - 3 years minimum
• compactors – 1 year minimum
Page 22 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
15.4.1 Unless agreed otherwise by COMPANY compaction tests of the fill layers (each layer)
shall be carried out as follows:
• For bulk filling (site preparation):
For each layer one (1) field density test for every 500 m² of backfill or subgrade area
with a minimum of two tests per layer.
• For Foundations and Paving:
For each layer one (1) field density test for every 100 m² under foundations / for
each heavy equipment foundations (for example compressors, tall columns,
slug catchers, GTG, etc….).
For each layer one (1) field density test for every 200 m² under paving areas.
• For retaining wall backfill:
At least two (2) field density tests at locations and elevations directed by COMPANY.
• For other fill activities:
Take at least two (2) density tests at locations and elevations as directed by COMPANY
or its representative.
15.4.2 Soil moisture content shall be tested at the same frequency as density testing.
15.4.3 Additional field density and moisture content test shall be performed as follows:
• If, in the judgment of COMPANY, based on tests, the fill has been placed below
the specified density, the CONTRACTOR will be required to provide additional
compaction and testing.
• Testing shall normally be carried out using proprietary density gauges (e.g.
Troxler gauge) and the type of shall be subject to approval by COMPANY
• Alternatively testing of small areas may be carried out using, in-place field
density tests in accordance with BS 1377 part 9.
15.5 INSPECTION
15.5.1 COMPANY reserves the right of inspection by itself or its representative during all
phases of the works.
15.5.2 The CONTRACTOR shall keep a competent representative at the work location who
shall supervise and be fully authorized to act on behalf of the CONTRACTOR and to
receive such orders as may be given for proper continuation of the work.
15.6 APPROVAL
Prior to any backfilling operation COMPANY's approval shall be obtained for, but not
limited to, any of the following:
• Compaction of subgrade.
• Concrete work.
• Cable pulling.
• Buried piping installation
Page 23 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
Page 24 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
Page 25 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
Note:
D = Maximum depth of compacted layer (mm).
N = Minimum number of passes.
U = Unsuitable.
Definitions and Requirements Associated with Table
Page 26 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
a. The depth of compacted layer is the height by which the embankment is raised
by each successive compacted layer.
b. The number of passes is the number of times that each point on the surface of
the layer being compacted has been traversed by the item of compaction.
c. The compaction effort of each compactor is a function of the mass of the
machine and the compaction plant listed, in above table, in terms of their
masses. The mass per meter width of roll is the total mass on the roll divided by
the total roll width. Where a smooth-wheeled roller has more than one axle, the
machine shall be assessed on the basis of the axle giving the highest value of
mass per meter width.
d. A tamping roller is a machine with a roll or rolls from which "feet" project. The
projected end area or each "foot" shall exceed 0.01 m² and the sum of the area
of the feet shall exceed 15% of the area of the cylinder swept by the ends of the
feet. The requirements for tamping rollers apply to machines that have two rolls
in tandem.
If only one tamping roll traverses each point on the surface of the layer on any one pass
of the machine, the minimum number of passes shall be twice the number given in the
table.
e. For pneumatic-tired rollers, mass per wheel is the total mass of the roller divided
by the number of wheels.
In assessing the number of passes of pneumatic-tired rollers, the effective width shall
be the sum of the widths of the individual wheel tracks together with the sum of the
spacing between the wheel tracks, provided that each spacing does not exceed 230
mm. Where the spacing exceeds 230 mm, the effective width shall be the sum of the
widths of the individual wheel tracks only.
f. Vibrating rollers are self-propelled or towed smooth-wheeled rollers, having
means of applying mechanical vibration to one or more rolls.
• The requirements for vibrating rollers are based on the use of the lowest
gear on a self-propelled machine with mechanical transmission and a speed
of 1.5 - 2.5 km/h for a towed machine or a self-propelled machine with
hydrostatic transmission. If higher speeds are used, an increased number of
passes shall be provided in proportion of the increase in speed of travel.
• Where the mechanical vibration is applied to two rolls in tandem, the
minimum number of passes shall be half the number given in the table of
the appropriate mass per meter width of one vibrating roll. If one roll differs
in mass per meter width form the other, the number of passes shall be
calculated as for the roll with the smallest value. Alternatively, the machine
may be treated as having a single vibrating roll with a mass per meter width
equal to that of the roll with the higher value.
• Vibrating-type rollers operating without vibration will be classified as smooth-
wheeled rollers.
Page 27 of 28
Specification for Earthworks
Document No: A-CIV-SPE-000-30002
Revision 1
Page 28 of 28