Ain Tsila Development Main EPC Contract A-CNT-CON-000-00282
Ain Tsila Development Main EPC Contract A-CNT-CON-000-00282
Ain Tsila Development Main EPC Contract A-CNT-CON-000-00282
A-CNT-CON-000-00282
Sub-contractor Name:
SARPI
WELLHEADS & MANIFOLDS MEI
WORKS
Accepted without comment subject to
PIUL Approval Code/Name/Signature company approval and any company
Name: Shaju Thalody comment will be informed on receipt
Signature:
CODE DEFINITION
A Issued For Review & Comments 25/11/2020 S.BOUMEGOURA Z.KALKIL S. BRAHMI N.YEKHLEF
Revision History
Revision Changes
Holds
Hold No. Location Description
Page 2 of 12
SITE ITP FOR LOCAL PANELS AND INSTRUMENT
JUNCTION BOXES INSTALLATION
Document No: B-QAC-PLN-210-39270
Revision A
Contents
1 INTRODUCTION 4
2 PURPOSE 4
3 SCOPE OF DOCUMENT 4
4 DEFINITIONS/ABBREVIATIONS 4
5 REFERENCE DOCUMENTS 6
5.1 Project References 6
5.2 Project Specifications 6
5.3 International Standards 7
5.4 National Algerian legislation 7
6 LIST OF VERIFYING DOCUMENTS 8
7 INSPECTION AND TEST PLAN 9
8 APPENDICES 12
Page 3 of 12
SITE ITP FOR LOCAL PANELS AND INSTRUMENT
JUNCTION BOXES INSTALLATION
Document No: B-QAC-PLN-210-39270
Revision A
1. INTRODUCTION:
SARPI hereinafter referred as Subcontractor will execute the (Gathering Pipelines, Wellheads &
Manifolds MEI Works) Subcontract on behalf of PETROFAC referred hereafter as Contractor.
Whereas the Groupement ISARENE, hereinafter collectively referred to as “client” or
“COMPANY” have awarded Petrofac a Contract for EPCC of Ain Tsila Development (hereinafter
referred to as the “Contract” or “Main Contract”).
2. PURPOSE:
The purpose of this document is to describe in detail the practice that will be implemented by
SARPI to manage, verify and control overall Inspections for activities of installation of Local
Panels and Instrument Junction Boxes and materials conforms to the specified requirements of
the COMPANY specifications, documents and drawings on Ain Tsila Development Project.
3. SCOPE OF DOCUMENT:
The scope of this Inspection and Test Plan including the referenced ITRs applies to the execution
of Inspection and Test activities as per the Quality Control Procedure (QCP) for performing
installation of Local Panels and Instrument Junction Boxes by assigned qualified personnel
during the Project Construction/Inspection activities.
The Inspection will be carried out by the SARPI in their respective areas as per this procedure
under the guidance of the CONTRACTOR’s Construction and Quality Management team to
ensure that Quality requirements are fulfilled within the scope of this document.
In case of any conflict between Project specification, drawings and applicable code, Project
specifications shall take precedence over this ITP and applicable ITRs.
This ITP serves primarily as a plan and it shall not be used to obtain signatures. Acceptance
signatures shall be obtained on the referenced Inspection and Test Record, which shall form part
of generic records to be handed over to the Client. COMPANY signature is optional for Review
and Surveillance points.
The referenced Inspection and Test Records (ITRs) are controlled independently. Therefore, the
latest revision of these ITRs, at the time of initiation, shall be utilized.
ITR number suffixed with letter “X” are classified as in-process Site/Field Quality Records and will
not be part of the Turnover System Process where as ITR number suffixed with letter “A” are part
of the Turnover Process and Turnover Records.
When filling ITRs do not leave any blanks. If an item/activity is not applicable, denote as N/A.
Use of Blanco, Tipp-ex etc. on ITR is forbidden.
4. DEFINITIONS/ABBREVIATIONS:
Page 4 of 12
SITE ITP FOR LOCAL PANELS AND INSTRUMENT
JUNCTION BOXES INSTALLATION
Document No: B-QAC-PLN-210-39270
Revision A
Page 5 of 12
SITE ITP FOR LOCAL PANELS AND INSTRUMENT
JUNCTION BOXES INSTALLATION
Document No: B-QAC-PLN-210-39270
Revision A
5. REFERENCES:
Page 6 of 12
SITE ITP FOR LOCAL PANELS AND INSTRUMENT
JUNCTION BOXES INSTALLATION
Document No: B-QAC-PLN-210-39270
Revision A
Page 7 of 12
SITE ITP FOR LOCAL PANELS AND INSTRUMENT
JUNCTION BOXES INSTALLATION
Document No: B-QAC-PLN-210-39270
Revision A
Page 8 of 12
SITE ITP FOR LOCAL PANELS AND INSTRUMENT
JUNCTION BOXES INSTALLATION
Document No: B-QAC-PLN-210-39270
Revision A
Inspection Codes: SC: SARPI PEC: PIUL C: Company/Client (GIS) ARH: Algerian Hydrocarbons Regulations
R: Document/Report Review S: Surveillance RR: Random Review
H: Hold Point (Notification Required & Presence is Mandatory) W: Witness Point (Notification Required but Presence is not Mandatory)
Page 9 of 12
SITE ITP FOR LOCAL PANELS AND INSTRUMENT
JUNCTION BOXES INSTALLATION
Document No: B-QAC-PLN-210-39270
Revision A
Inspection Codes: SC: SARPI PEC: PIUL C: Company/Client (GIS) ARH: Algerian Hydrocarbons Regulations
R: Document/Report Review S: Surveillance RR: Random Review
H: Hold Point (Notification Required & Presence is Mandatory) W: Witness Point (Notification Required but Presence is not Mandatory)
a. Panel base frame /Junction Box
Instrument
frames are fabricated, installed and
installation details
fixed, bolted, levelled and aligned PEC Site
Installation of Equipment layout Complies with
b. Check stub ups are installed as per Supervisor
5.0 mounting frame and drawings installation details ITR-I-0401X H S S N/A
drawings SC Instrument
supports Manufacturer’s and layout drawings
c. Verify location and elevation as per QC Inspector
published data
drawing Project Spec.
Page 10 of 12
SITE ITP FOR LOCAL PANELS AND INSTRUMENT
JUNCTION BOXES INSTALLATION
Document No: B-QAC-PLN-210-39270
Revision A
Inspection Codes: SC: SARPI PEC: PIUL C: Company/Client (GIS) ARH: Algerian Hydrocarbons Regulations
R: Document/Report Review S: Surveillance RR: Random Review
H: Hold Point (Notification Required & Presence is Mandatory) W: Witness Point (Notification Required but Presence is not Mandatory)
a. Check as per manufacturer’s
published data
b. Verify cable size, type against
Instrument Complies with
Earthing of Local installation details PEC Site
Panels and Junction installation details installation details
c. Check all earthing connection to Supervisor
7.0 boxes, including doors Typical earthing and layout drawings ITR-I-0401X H S S N/A
earthing system correctly installed SC Instrument
and cables layout drawings Good bonding to QC Inspector
and is bonded to the specified Project Spec. earth network
network
d. Verify correct tightness
Page 11 of 12
SITE ITP FOR LOCAL PANELS AND INSTRUMENT
JUNCTION BOXES INSTALLATION
Document No: B-QAC-PLN-210-39270
Revision A
8. APPENDICES:
Page 12 of 12
INSPECTION & TEST RECORD-INSTRUMENTATION
ITR No: JI2045-I-0401X
I-0401X
Project No.: Record No:
Tag No:
Sub-System No:
Equip./Panel Description:
Make: Model No: Sl. No:
Area: Location:
Layout Drawing No:
General Arrangement Drawing No:
Typical Installation Drawing No:
Ex. Prot.Type: Gas Group: Temp. Class: IP Rating:
Certifying Authority: Certificate No:
Haz. Area Classification Drawing No: Haz. Area Class:
Name
Signature
Date
Page 1 of 2 Ref. ITP No. B-QAC-PLN-210-39270
INSPECTION & TEST RECORD-INSTRUMENTATION
ITR No: JI2045-I-0401X
I-0401X
Project No.: Record No:
Tag No:
Sub-System No:
2.14 Unused cable entries are blanked off with correct type of plugs.
2.17 Equipment is adequately protected against corrosion, weather, vibration and other adverse factors.
2.19 Where applicable, sealing of trunking, ducts, pipes, and /or conduit are satisfactory.
Enclosure lids are satisfactory with suitable gasket (where applicable) and fixing screws / bolts
2.20
tightened and IP rating is maintained, this includes correct IP washers.
Verify earth connections/bonding (including bonding of doors and cables) are in accordance with
2.21
standard drawing and record resistance to earth: ( Ω).
Remarks
Name
Signature
Date
Page 2 of 2 Ref. ITP No. B-QAC-PLN-210-39270