Hydarulics and Drainage Design
Hydarulics and Drainage Design
Hydarulics and Drainage Design
CHAPTER 203
NOTE: References to material in 2011 Design Manual have been highlighted in blue throughout
this document.
TABLE OF CONTENTS
Figure Title
HYDRAULICS AND
DRAINAGE DESIGN
203-1.0 INTRODUCTION
This Chapter describes aspects of highway drainage such as that for a culvert, bridge, stormwater
drainage, storage facility, pump station, or channel work. They should be accepted as the most
common uses and desirable course of action. There can be exceptions that deviate from the
policies shown. The Office of Hydraulics should be contacted for special considerations or
changes to a particular design.
The goal is a design that is the most cost-efficient while still satisfying the criterion described
below. In considering a cost-efficient drainage design, the initial cost should be considered, but
facility longevity and future maintenance costs and legal and environmental constraints should
be considered also.
203-2.0 CULVERT
203-2.01 Introduction
This Section provides design procedures for the hydraulic design of a highway culvert, which are
based on FHWA Hydraulic Design Series Number 5 (HDS #5) Hydraulic Design of Highway
Culverts. This Section also provides a summary of the design philosophy included in the
AASHTO Highway Drainage Guidelines, Chapter IV.
2. FHWA defines a culvert as a structure with a span length of less than a 20 ft along the
centerline of roadway between extreme ends of openings for multiple barrels. Figure
203-2A, Maximum Span Length for Culvert, provides schematics which define a culvert
based on span length for various structural configurations.
The culvert to be selected should best integrate hydraulic policy and economic and political
considerations. The selected culvert should be based on construction and maintenance costs, risk
of failure or property damage, roadside safety, land-use requirements, and satisfaction of the
applicable structural and hydraulic criteria. Culvert design should also consider the adjacent
channel. Considerations such as sumping, improved inlet, erosion at the inlet or outlet, are all an
integral part of culvert design.
The failure of, or damage to, a culvert or detention-basin outlet structure can be traced to
unchecked erosion. Erosive forces which are at work in the natural drainage network are often
exacerbated due to the construction of a highway or other urban development. Interception and
concentration of overland flow or constriction of a natural waterway inevitably results in an
increased erosion potential. To protect the culvert and adjacent areas, an energy dissipater can
be necessary.
1. Each culvert should be hydraulically designed. However, the minimum pipe size
specified in Figure 203-2B will sometimes control.
2. HY-8 and the HEC-RAS culvert modules are the only computer programs allowed for the
hydraulic analysis of a culvert. The FHWA HDS #5 Hydraulic Design of Highway
Culverts is also acceptable and available from the FHWA website.
3. HY-8 and the HEC-RAS culvert module have design limitations if the structure span
approaches 20 ft. Therefore, in designing a replacement culvert, where the existing
structure has a span of 20 ft or greater measured perpendicular to flow, only the HEC-
RAS bridge module should be used for hydraulic analysis. Both the existing and
proposed structures should be analyzed using the same module.
4. The Office of Hydraulics will review each culvert of diameter of 36 in. or greater. The
Office reserves the right to review all culverts.
5. The design-storm frequency selected should be consistent with the criteria described in
Figure 203-2C, Design-Storm Frequency for Bridge or Culvert.
6. Survey information should include topographic features, channel characteristics, high-
water information, existing-structure data, and other related site-specific information.
7. Culvert location in both plan and profile should approximate the alignment of the natural
channel to avoid sediment build-up in the barrel.
9. The detail of documentation for each culvert site should be commensurate with the risk
and importance of the structure. Design data and calculations should be assembled in an
orderly fashion and retained for future reference as provided for in this Chapter.
10. The culvert design should incorporate the environmental requirements of IDNR, IDEM,
USACE, and other applicable government agencies.
2. Length and Slope. The culvert length and slope should be chosen to approximate existing
topography and, as practical, the culvert invert should be aligned with the channel bottom
and the skew angle of the stream. The roadway clear-zone requirements and the
embankment geometry can dictate the culvert length. See Chapter 49.
4. Location in Profile. The culvert profile should approximate the natural stream profile.
Exceptions which require approval by the Office of Hydraulics can be considered as
follows:
a. Arrest stream degradation by utilizing a drop-end treatment or broken-back
culvert.
b. Improve hydraulic performance by utilizing a slope-tapered end treatment.
c. Avoid conflicts with other utilities that are difficult to relocate such as sanitary
sewers.
Allowable headwater is the depth of water that can be ponded at the upstream end of a culvert
during the design flood. AHW will be limited by one or more of the following.
1. New Alignment. The maximum backwater, or increase in headwater elevation over the
sum of TW depth plus inlet flowline elevation, should not exceed 0.14 ft. The maximum
backwater may be modified if the backwater dissipates to 0.14 ft or less at the right-of-
way-line or the channel is sufficiently deep to contain the increased elevation without
overtopping the banks. If backwater remains within the channel banks or right of way, it
is limited to a maximum of 1 ft.
4. Inlet Depression. An inlet depression should be limited to a depth of not more than half
of the rise of the structure. If the structure is required to be sumped, an inlet depression
should not be used without prior approval of the appropriate resource agencies.
See Figure 203-2C, Design-Storm Frequency for Bridge or Culvert, for guidance regarding
roadway-serviceability freeboard and design-storm frequency.
Riprap or an energy dissipator should be used to manage the design-outlet velocity. See Figure
203-2D.
The minimum velocity in the culvert barrel should result in a tractive force, τ = γdS, greater than
critical τ of the transported streambed material at a low-flow rate. A flow rate of 3 ft/s should be
used if the streambed-material size is not known.
Storage should not be considered. Because upstream storage is not typically controlled by
INDOT, it cannot be presumed to exist for the life of the structure.
203-2.02(08) Culvert Skew
The culvert skew should not exceed 45 deg as measured from a line perpendicular to the
roadway centerline, without the approval of the Office of Hydraulics.
203-2.02(09) Cover
Sumping consists of placing the structure-invert elevation and scour protection at a specified
depth below the waterway or stream flowline to satisfy the IDEM Water Quality Section 401
permit requirements. Sumping allows the natural movement of stream-bed material through the
structure. Sumping should be provided for each structure over Waters of the United States and
Waters of the State.
1. Three-Sided Structure. The sump depth should be 18 in. for a stream bed of sand, 12 in.
for a stream bed of other soil, or 3 in. for a stream bed of rock or till. The stream bed and
scour protection should be as shown on the INDOT Standard Drawings. A base slab
should be used only if the geotechnical report identifies flowline-area soil that will not
support riprap. No increase in structure size is required due to sumping. The sump area
will not require backfill as part of the contract work, but will be allowed to fill in
naturally over time.
2. Pipe or Box Structure. Such a structure should be sumped as shown on the INDOT
Standard Drawings and Figure 203-2E, Pipe- or Box-Structure Sump Requirement.
If the required sump exceeds 3 in., the structure diameter or rise may need to be increased by the
sump value. The structure’s design capacity should be checked to determine if such increase is
required. If a pipe end section or riprap is required, these should be sumped to the same depth as
the structure. The sump area of the structure and end section or riprap will not require backfill as
part of the contract work, but will be allowed to fill in naturally over time.
Scour-protection limits should be shown on the plans. Quantities for geotextile and riprap, or a
base slab intended for scour protection, should be determined and identified as such in the
Structure Data table for each applicable structure. Appropriate columns have been incorporated
into the Structure Data table.
The proposed structure span should be equal to or greater than the existing span unless prior
approval is given from the Office of Hydraulics. Each culvert with a diameter of 48 in. or
greater that is to be replaced will require a geotechnical report.
The culvert-sizing process is performed in accordance with a priority system. The design
priority system is as follows.
For a circular or deformed pipe, both corrugated and smooth alternates are required. The
smooth-interior hydraulic design will be based on a minimum Manning’s n value of 0.012. For
corrugated-pipe design, the Manning’s n value should be in accordance with accepted
engineering practice. See Figure 203-2F for typical values.
The two hydraulic designs for an individual structure will be based on identical pipe lengths and
invert elevations.
If separate hydraulic designs are performed for smooth and corrugated interior pipes, the
following situations are possible.
1. The required smooth-interior and corrugated-interior pipe sizes are identical. The
structure callout on the plans should include the required pipe size. No reference to an
interior designation is made.
2. The required smooth-interior and corrugated-interior pipe sizes are different. The
structure callout on the plans should indicate that the structure requires a smooth pipe of
one size or a corrugated pipe of another.
3. An acceptable pipe size can be determined for one interior designation but not the other.
If this occurs, the structure callout on the plans should indicate the required pipe size and
interior designation.
a. The structure barrel should be relatively straight, not significantly damaged, and
basically intact.
b. The backfill around the structure should be free from large voids.
c. There should be sufficient room to work from at least one end of the existing
structure.
2. Design Criteria. A structure may not increase backwater over existing conditions.
Exceptions to this will require justification and approval by the Office of Hydraulics.
1. Match Existing Pipe Size and Interior Designation. If practical, the pipe extension should
be the same size and material as the existing pipe. However, at this stage, it is necessary
only to identify the required interior designation for the extension.
4. Age and Condition. The remaining life expectancy of the existing structure should be
evaluated in comparison to the proposed extension.
If the extended structure satisfies the required design criteria, the structure-sizing process is
complete. If the extended structure does not satisfy the required design criteria, replacement of
the existing structure with a new structure should be reevaluated. If it is not practical to replace
the existing pipe because of construction method, traffic maintenance, or other constraints, the
Office of Hydraulics should be contacted for further instructions.
A Structure Data Table should be included in the plans for drainage structures requiring
modification. Details sheets should be provided where required.
An energy dissipator is used to protect the culvert and downstream channel from scour. The two
primary types of scour are local scour and channel degradation. Local scour is the result of high-
velocity flow at the culvert outlet and extends only a limited distance downstream. Channel
degradation can proceed in a fairly uniform manner over a long length or can be evident in one
or more abrupt drops, or headcuts, progressing upstream with each runoff event.
The culvert should be designed independent of the dissipator design, with the exception of an
internal dissipator, which may require an iterative solution. The culvert design should be
completed before the outlet protection is designed and should include computation of outlet
velocity. The downstream channel protection should be designed concurrently with the
dissipator design.
A culvert will likely require outlet protection. The class of riprap used for outlet protection
should be sized in accordance with Figure 203-2D. For a side ditch that does not carry a live
stream, sod can be used at the outlet. Seeding should be used if the design velocity is less than 2
ft/s.
For a structure that creates an outlet velocity greater than 13 ft/s, an energy dissipater will be
required unless either of the following conditions are satisfied. Otherwise Class II riprap should
be used.
1. The existing outlet velocity is already greater than 13 ft/s, there are no signs of scour at
the outlet, and the proposed outlet velocity does not increase over existing velocity.
2. The natural stream has an average velocity that is at least 70% of the proposed outlet
velocity.
203-2.03 Design Considerations
In addition to INDOT’s hydraulic policy, other design considerations that should be evaluated
are described below.
A culvert should be located and designed to present a minimum hazard to vehicular and
pedestrian traffic. Where necessary as directed, a means should be provided for personnel and
equipment access to facilitate maintenance.
See Chapter 202 for information on hydrology. A constant peak discharge is assumed for culvert
design and will yield a conservatively-sized structure where temporary storage is available but
not considered.
A larger waterway downstream should be checked to determine if its flood elevations can
backwater through the system and affect road serviceability. If this potential exists, a joint
stream probability analysis should be performed (see Figure 203-2G) to check the correct storm
events that should be analyzed for potential road overtopping. The joint stream probability
analysis is based on the peak discharges of both the design stream and the larger downstream
waterway occurring at different times. The analysis compares the streams at different storm
designs based on their difference in drainage area.
The culvert end-treatment type should be selected from the list shown below based on the given
considerations and the entrance loss coefficient, KE. See Figures 203-2H and 203-2 I for the
recommended values of KE. Roadside safety should be considered in the selection and design.
See Chapter 49 for a discussion of practices for the safety treatment of a drainage structure.
The following discusses the types of culvert end treatments and their advantages and
disadvantages.
5. Wingwall.
6. Apron.
a. Used to reduce scour from a high headwater depth or from approach velocity in
the channel.
b. Should extend at least one pipe diameter upstream.
c. Should not protrude above the normal streambed elevation.
d. May be constructed of riprap and an appropriate geotextile or concrete.
e. Should be set at the structure invert elevation.
7. Cutoff Wall.
a. Used to prevent piping along the culvert barrel and undermining at the culvert end.
b. Should be used for a culvert with headwalls.
c. Depth should be of minimum 20 in., or as shown in the INDOT Standard
Drawings or Standard Specifications.
After the structure size and cover have been determined, the required length should be
determined. The design length for a culvert structure should be rounded to the next higher 1 ft.
Pipe end sections, concrete anchors, or other means of anchoring should be considered for a
flexible culvert where a projecting end treatment or outlet is used.
The severity of buoyancy depends on the steepness of the culvert slope, depth of the potential
headwater which debris blockage can increase, flatness of the upstream fill slope, height of the
fill, large culvert skew, or mitered ends. For anchor details, see the INDOT Standard Drawings
and Standard Specifications.
Where a culvert serving as a relief opening has its outlet set above the normal stream flow line,
precautions should be made to prevent headcutting or erosion from undermining the culvert
outlet.
203-2.03(08) Erosion and Sediment Control
Temporary measures should be shown on the plans. For more information, see Chapter 37.
An improved end treatment is a flared culvert inlet with an enlarged face section and a
hydraulically-efficient throat section. An improved end treatment can have a depression, or fall,
incorporated into the end-treatment structure or located upstream of the end treatment. The
depression is used to exert more head on the throat section for a given headwater elevation.
Therefore, an improved end treatment improves culvert performance by providing a more-
efficient control section, which is the throat. An improved end treatment with a fall also
improves performance by increasing the head on the throat. For information concerning the
design of an improved end treatment, see HDS-5.
1. A culvert end which is projecting or mitered to the fill slope offers no outlet protection.
2. Headwalls provide embankment stability and erosion protection. They provide
protection from buoyancy and reduce damage to the culvert.
3. Commercial end sections add little cost to the culvert and may require less maintenance,
retard embankment erosion, and incur less damage from maintenance.
Wingwalls are used where the side slopes of the channel are unstable, where the culvert is
skewed to the normal channel flow, to redirect outlet velocity, or to retain fill.
In designing an energy dissipator, chosen alternatives should satisfy the topography, design
policies, and criteria. Alternatives should be analyzed for environmental impact, hydraulic
efficiency, and risk and cost. The selected dissipator should satisfy the selected structural and
hydraulic criteria. It should also be based on construction and maintenance costs, risk of failure
or property damage, traffic safety, environmental or aesthetic considerations, political or
nuisance considerations, and land-use requirements.
A riprap apron is the most commonly used form of energy dissipation and scour protection. It is
a riprap pad located at the outlet of the culvert. The minimum apron dimensions are shown in
Figure 203-2J, Riprap Apron. Site conditions can dictate a longer apron.
A riprap basin, also referred to as a designed scour hole, is the most common energy dissipator
where a riprap apron is not sufficient. It is acceptable for use where undermining of the culvert
outlet will not occur, the expected scour hole will not cause costly property damage, and there is
no nuisance effect. The design of a scour hole is described in Section 203-3.03(04). Other
dissipators should be considered if there is limited right of way.
An internal dissipator includes the tumbling-flow type and the increased-resistance type. This
should be used only for an inlet-control situation where the flow near the outlet of the culvert is
shallow enough. This should be used where the scour hole at the culvert outlet is unacceptable,
the right of way is limited, debris is not a problem, or moderate velocity reduction is required.
This Chapter does not address the design of an internal dissipator. See FHWA HEC-14 and
FHWA/OH-84/007 Internal Energy Dissipators if a design procedure is required.
Another type of external dissipator can be used where the riprap basin is not acceptable and a
moderate amount of debris is anticipated. This can include USBR Type VI Impact, CSU rigid
boundary, Contra Costa, hook, or hydraulic jump. This Chapter does not address the design of
this type of external dissipator. See HEC-14 if a design procedure is required.
A stilling basin is used where the riprap basin is not acceptable, and debris is anticipated. This
can include Saint Anthony Falls (SAF), USBR Type II, USBR Type III, or USBR Type IV. This
Chapter does not address the design of this type of stilling basin. See HEC-14 if a design
procedure is required.
This Chapter does not address the design of a drop structure. See HEC-14 if a design procedure
is required.
Traffic should be protected from an external energy dissipator by locating it outside the
appropriate clear-zone distance as described in Chapter 49.
203-2.04(01) General
An exact theoretical analysis of culvert flow is complex. First, the analysis of non-uniform flow
with regions of both gradually varying and rapidly varying flow should be performed. Then, the
flow-type changes should be determined as the flow-rate and tailwater elevations change.
Backwater and drawdown calculations, and energy and momentum balances, should be
completed. Results of hydraulic-model studies should be applied. It should be determined if
hydraulic jumps occur and if they are inside of or downstream of the culvert barrel. Calculations
can be simplified, based on the following.
1. Control Section. The control section is where there is a unique relationship between the
flow rate and the upstream water-surface elevation. Inlet control is governed by the inlet
geometry. Outlet control is governed by a combination of the culvert end-treatment
geometry, the barrel characteristics, and the tailwater elevation.
2. Minimum Performance. This is assumed by means of analyzing both inlet and outlet
control and using the highest headwater elevation. The culvert can operate more
efficiently at times with more flow for a given headwater level, but it will not operate at a
lower level of performance than calculated.
3. Culvert Sizing. The culvert-sizing process should satisfy the criteria as follows:
4. Computer Software. The HY8 software and the HEC-RAS Culvert Module are
acceptable design methods for structure sizing.
203-2.04(02) Headwater Factors
1. Headwater depth is measured from the flowline of the inlet-control section to the surface
of the upstream pool.
2. Inlet area is the cross-sectional area of the face of the culvert. The inlet-face area is the
same as the barrel area.
4. Inlet shape is the same as that of the culvert barrel. Shapes include rectangular, circular,
elliptical, and arch. The shape should be checked for an additional control section, if
different than the barrel.
3. The existing outlet depth may be used in lieu of the tailwater depth if the culvert outlet is
operating with a low tailwater depth or a free outfall.
4. The headwater elevation of a nearby downstream culvert should be used if it is above the
channel depth.
Since the riprap basin is the preferred energy dissipator where the riprap apron is not adequate,
design procedures are as follows. The riprap-basin design is based on laboratory data obtained
from full-scale prototypical installations. The features of the basin include the following:
When high tailwater conditions, TW/yo > 0.75, exist, the following characteristics apply. The
high-velocity core of water emerging from the culvert retains its jet-like character as it passes
through the basin. The scour hole is shallower and longer than that found in a low-tailwater
condition. Riprap may be required for the channel downstream of the rock-lined basin.
1. Determine Input Flow. yo or yE, Vo, Fr at the culvert outlet, and yE, the equivalent depth at
the brink = (A/2)0.5.
2. Check TW. Determine if TW/yo ≤ 0.75.
3. Determine d50.
a. Use Figure 203-2M, Riprap-Basin Scour Depth.
b. Select d50/yE. Satisfactory results will be obtained if 0.25 < d50/yE < 0.45.
c. Obtain hS/yE using Fr.
d. Check if 2 < hS/d50 < 4 and repeat until d50 is found to be within the range.
4. Size basin as shown in Figure 203-2K.
a. Determine length of the dissipating pool, LS = 10hS or 3Wo minimum.
b. Determine length of basin, LB = 15hS or 4Wo minimum.
c. Thickness of riprap:
(1) Approach, 3d50 or 1.5dmax
(2) Remainder, 2d50 or 1.5dmax
5. Determine VB.
a. Basin exit depth, yB = critical depth at basin exit.
b. Basin exit velocity, VB = Q/WByB.
c. Compare VB with the average normal flow velocity in the natural channel, Vd.
6. High-Tailwater Design.
a. Design a basin for low-tailwater conditions, Steps 1-5.
b. Compute equivalent circular diameter, DE, for brink area as follows:
2
DE
A yoWo
4
c. Estimate centerline velocity at a series of downstream cross sections using Figure
203-2N, Distribution of Centerline Velocity for Flow from Submerged Outlets.
d. Size riprap using Figure 203-2D.
7. Filter Placement. Geotextile should be placed under a riprap feature.
The dissipator geometry can be computed using the HY-8, Culvert Analysis Software, Energy
Dissipator module.
Perpendicular-span length is measured between the inside faces of the structure walls,
perpendicular to them. Structural-span length is measured between the inside faces of the
structure walls, along the roadway centerline.
The hydraulic-recommendations letter will indicate if a three-sided structure with a base slab is
an acceptable alternate to an oversize box structure. The designer should contact the Office of
Hydraulics for guidance as to whether the two structure types are interchangeable for the specific
site. A cost comparison should be used in making the final structure selection.
An oversize box culvert should be laid out so that the total structure length is a multiple of the
box-segment length for the given box size. It is not necessary to add a tolerance for the joints
between segments in determining the total structure length. The typically-available segment
weights and lengths are shown in Figure 203-2 O. For a 9-ft through 12-ft rise, at least one box-
structure supplier should be contacted for available weights and lengths.
203-2.05(03) Precast-Concrete Three-Sided Structure
1. Structure Sizing and Selection. The designer will choose either the flat-topped, arch-
topped, or true-arch structure section, show it on the plans and reference, by note, the
other sections. The designer will determine the hydraulic size for the alternate structures.
The hydraulic recommendations will include the Q100 elevation, the assumed flowline
elevation, the required perpendicular span, and the required waterway opening for all
structure sections. The designer will determine the rise of the structure for all structure
sections. The minimum desirable freeboard requirement will be 1 ft for a flat-topped or
an arch-topped structure, with the low-structure elevation determined at the structure
centerline for each section. The minimum desirable freeboard requirement will be 2 ft
for a true-arch structure. If the designer elects to use a freeboard of less than desirable,
the designer should obtain the concurrence of the Office of Hydraulics manager.
Figure 203-2P should be used as guidance for determining the acceptable alternates to
show on the plans.
The arch-topped structure will likely have a greater perpendicular-span requirement than
the flat-topped structure where it is used with less than 2 ft of freeboard. The arch-topped
structure will not be included as an alternate in the hydraulics recommendation letter if its
required perpendicular span exceeds that of the flat-topped alternate by more than 4 ft.
The true-arch structure will likely have a greater perpendicular-span requirement than the
flat-topped or arch-topped structure.
Where the required structural span exceeds 30 ft, the designer will also provide the
required waterway opening for a spill-through bridge. The designer will size an
appropriate bridge and perform an economic comparison between the bridge and the
three-sided structure options.
The dimensional designation shown in Figure 203-2Q for perpendicular span, and Figure
203-2R for rise, should be used for designating each required three-sided structure. The
plans should show the structure size in feet.
2. Segment Configuration and Skew. Skew should be rounded to the nearer most-practical
5 deg, although the nearer 1 deg is permissible where necessary.
It is not necessary for the designer to determine the exact number and length of segments.
The final structure length and segment configuration will be determined by the fabricator
and may deviate from that implied by the plans. However, a minimum horizontal
clearance of 6 ft must exist between the front face of guardrail and the outside face of the
structure headwall where the drainage-structure end is within the clear zone.
Square segments are more economical if the structure is skewed. Laying out the structure
with square segments will result in the greatest right-of-way requirement and thus allow
ample space for potential redesign by the contractor, if necessary, to another segment
configuration.
For a structure with a skew of 15 deg or less, structure segments may be laid out square
or skewed. Skewed segments are preferred for a structure of less than 80 ft length.
Square segments are preferred for a longer structure. However, skewed segments have a
greater structural span. A structure with a skew of greater than 15 deg requires additional
analysis as described in the AASHTO LRFD Bridge Design Specifications. Skewed
segments and the analysis both contribute to higher structure cost.
For a structure with a skew of greater than 15 deg, structure segments should be laid out
square. If hydraulic conditions dictate the use of a flat-topped structure only, the
segments may be laid out skewed if the structure is relatively short.
A number of flat-topped structures are built with skewed segments, i.e., segments shaped,
in plan view, like parallelograms. However, some INDOT structures have been
redesigned to use only square segments. Where a flat-topped structure is laid out with
ends parallel to the roadway, skewed segments are implied by the designer.
The preferred layout scheme for an arch-topped structure with a skew of greater than 15
deg should assume square segments with a sloping top of headwall to yield the shortest
possible wingwalls. Where an arch-topped structure is laid out with skewed ends,
therefore, headwalls parallel to the roadway, the skew will be developed within the end
segments by varying the lengths of the legs as measured along the centerline of the
structure. The maximum attainable skew is controlled by the difference between the full-
segment leg length as recommended by the arch-topped-structure fabricator and a
minimum leg length of 2 ft.
An alternate structure type with a _____-ft perpendicular span and a _____-ft rise
may be substituted for the structure shown on the Layout sheet.
Where a flat-topped structure is the only option permitted, the General Plan should
include a note as follows:
The elevations to be provided on the General Plan or other detail sheet are as follows:
a. Q100;
b. flow line, at both structure ends and the roadway centerline;
c. the low structure at the centerline of the structure;
d. the tops of headwalls; and
e. the tops of wingwalls.
The assumed elevations of the top of the footing and the base of the structure leg should
also be shown. For structure-layout purposes, a 2-ft footing thickness should be assumed
with the base of the structure leg seated 2 in. below the top-of-footing elevation. With
the bottom of the footing placed at the standard depth of 4 ft below the flowline
elevation, the base of the structure leg should therefore be shown as 2’-2” below the
flowline. An exception to the 4-ft depth will occur where the anticipated footing
thickness is known to exceed 2 ft, where the footing must extend to rock, or where poor
soil conditions dictate that the footing should be deeper.
The footing should be kept level if possible. If the stream grade prohibits a level footing,
the wingwall footings should be laid out to be constructed on the same plane as the
structure footings.
The structure length and the flare angle, and the length and height of wingwalls should be
shown. For a skewed structure, the wingwall geometrics should be determined for each
wing. The sideslope used to determine the wing length should be shown on the plans.
A structure should extend to a point where the headwall height can be kept to a
minimum, preferably 1 ft. All headwalls should have standard-length-post guardrail
protection unless the structure cover does not permit it. Where structure cover does not
permit a standard headwall and standard-length-post guardrail installation, another option
as shown on the INDOT Standard Drawings should be shown, with the selected low-
cover guardrail option. A minimum of 6 ft of clearance should exist horizontally
between the face of guardrail and the outside face of the structure headwall.
If the height of the structure legs exceeds 10 ft, pedestals should be shown in the structure
elevation view. For illustration purposes, the pedestals should be drawn at approximately
2-ft width, but the dimensions and details should not be shown. The pedestal height
should be included in the rise dimension specified in the pay-item name.
The design and details for footings or base slabs, wingwall footings, wingwalls, and
headwalls will be provided by the structure manufacturer once the working drawings are
submitted. The designer who prepared the contract plans will review the design
calculations and working drawings. For a federal-aid local-agency project, such
documents are reviewed and approved by the local agency or its design consultant.
Designed for HL-93 loading in accordance with AASHTO LRFD Bridge Design
Specifications, [current-edition year], and all subsequent interim specifications.
Quantities for the structure and wingwall footings should be included with those for the
structure and the wingwalls, respectively. Quantities for headwalls and foundation
excavation should also be included in those for the structure.
4. Foundations. The allowable soil bearing pressure should be shown on the plans. If the
footing is on piling, the nominal driving resistance should be shown.
Where a pile footing is required, the type and size of pile and the required pile spacing,
and which piles are to be battered, should be shown on the plans. The final design of the
pile cap will be performed by the fabricator, and the details will be shown on the working
drawings as is the practice for other footing types. If the geotechnical report recommends
that piling be used, the structure-type selection should be re-evaluated to consider a spill-
through bridge due to the added expense of pile footings.
The plans for a three-sided structure should include a sheet showing the soil boring logs for the
structure.
Wingwalls and headwalls are required without regard to structure type or size. Such wingwalls
and headwalls may be precast or cast in place.
1. a plan view showing the total length of the structure, skew angle, distance from roadway
centerline to each end of structure, and the flare angle of all wingwalls;
2. an elevation view of the end of the structure including wingwalls and headwall if
applicable. The perpendicular span and rise of the structure should be dimensioned. The
height of the headwall should be shown;
3. wingwalls labeled A through D with a table showing all dimensions and elevations for
each wingwall, and summarizing the wingwall areas required; and
4. the allowable soil bearing pressure. A table should be included on the plans listing the
soil parameters for wingwall design as follows:
These soil parameters will be provided in the geotechnical report for the structure. If the
geotechnical report is lacking this information, it should be requested from the Office of
Geotechnical Services.
If the distance between the top of the pavement and the top of the structure is less than 2 ft as
measured at the edge of travel lane, all reinforcement in a three-sided structure or an oversized
box structure should be coated. Coated reinforcement should be indicated in the Structure Data
Table’s structure-description name.
The standard footing depth of 4 ft below the flowline and the riprap protection shown on the
INDOT Standard Drawings will suffice for scour protection in a routine installation. Riprap and
geotextile used in the waterway should be shown on the plans in the plan view and labeled as
Scour Protection.
Figure 203-2 S should be used to determine the type of scour protection required for a three-sided
structure, or the channel. The riprap type and quantity should be shown on the plans. A note should
be placed on the plans, similar to the following:
Quantities of ___ tons of [Class 1] [Class 2] [revetment] riprap and _____ sys of geotextile
shall be placed as scour protection.
For a routine installation, the riprap and geotextile shown on the INDOT Standard Drawings will
suffice for scour protection on the stream banks adjacent to the wingwalls or projecting ends of
the structure. Quantities of riprap and geotextile used on the stream banks adjacent to the
wingwalls or projecting ends of the structure should be shown on the plans.
If an INDR Floodway Construction, IDEM Water Quality 401, or a U.S. Army Corps of Engineers
404 permit application is required, the required scour quantities of riprap or cast-in-place concrete
should be incorporated into the application. If one or more of these permits has already been
granted, the designer must provide the quantities information to the Environmental Services
Division’s Ecology and Permits Team. The Team leader will then apply for a permit amendment.
For a three-sided structure, if the allowable soil bearing pressure is less than 1000 lb/ft2, or where
the stream velocity exceeds 13 ft/s, a concrete base slab should be provided instead of a
conventional strip footing. Details of the base-slab method of scour protection are shown on the
INDOT Standard Drawings. If the allowable soil bearing pressure is not extremely low or where
the stream velocity does not exceed 13 ft/s, the cost effectiveness of providing a base slab versus
providing a strip footing with scour protection should be considered. The input of the district
Office of Construction should be requested at the preliminary field check if the costs appear to be
equal.
203-2.06(04) Backfilling
Where there is less than 2 ft of cover between the top of the structure and the top of the proposed
pavement structure, as measured at the edge of travel lane, the backfill should be structure
backfill type 5 to the top of the structure. The backfill above the top of the structure should be
structure backfill type 2.
Where there is 2 ft or more of cover between the top of the structure and top of the proposed
pavement structure, as measured at the edge of travel lane, all backfill should be structure
backfill type 2.
The minimum and maximum cover distances should be shown in the Structure Data Table. The
material used to backfill the structure should be also used to backfill the wingwalls.
The minimum cover distance between the top of the structure and the top of the pavement
section should be equal to the pavement-section thickness. If the minimum cover distance is less
than the pavement-section thickness, the Planning Division’s Office of Pavement Engineering
should be consulted for the minimum pavement thickness to be used above the structure.
For a three-sided structure, the structure and wingwall backfill limits should be shown on the
plans. The backfill limits should have a width of 1.5 ft at the bottom of the footing and should
extend upward at a slope rate of 1:4. The wingwalls’ backfill should extend upward at a 1:1
slope from the bottom of the wingwall footings. The structure fabricator will also be required to
show the backfill limits on the shop drawings. The backfill pay limits should be based on the
neat-line limits shown on the plans. The type of structure backfill and the quantities for
excavation and structure backfill should be shown on the plans.
Only the conceptual layout for a precast-concrete three-sided or box structure, or precast
wingwalls and headwalls, should be shown on the plans. The structure centerline, minimum
perpendicular span, minimum structural span, minimum rise, and minimum Q100 hydraulic-
opening area should be shown on the Layout sheet.
Once the work is under contract, the fabricator will design and detail the structure. For each
cast-in-place structure, three-sided structure, or for each box structure of perpendicular span
greater than 12’-0” or of a size not described in ASTM C 1577, the fabricator will provide design
computations and working drawings which are to be checked by, and are subject to the approval
of, the designer.
203-2.07 Documentation
The hydraulic report and necessary software data or input files should be submitted to the Office
of Hydraulics for review and acceptance. All relevant information should be cross referenced if
utilized in other sections of the report. The information in the report should include, but should
be not limited to, the following:
1. project-specific overview, including stating location, purpose, vertical datum used, and
other pertinent information;
2. Topographic Map with drainage area and flow path for Time of Concentration delineated
and labeled, including north arrow and graphic scale bar;
3. aerial photo with drainage area delineated;
4. Summary Table with the information, if applicable, as follows:
a. drainage area;
b. Q100 flow;
c. Q100 water-surface elevation;
d. structure size and type;
e. inlet-edge condition;
f. backwater depth;
g. culvert velocity;
h. headwater elevation;
i. road overflow area;
j. outlet-erosion protection;
k. sump depth;
l. outlet-flowline elevation;
m. minimum low structure elevation;
n. approximate skew; and
o. inlet-depression depth.
5. hydrology calculations which can include the Rational Method, Hydrograph (TR-20,
HEC-HMS, etc.), curve numbers, Manning’s n values, Time of Concentration, etc.
6. HY-8. Only information for the recommended structure, primary alternates, and existing
structure should be included if applicable. The input file, output file, and version of
software used should be included for the reviewer’s use;
7. plans including cross-section of downstream channel, road plan and profile, and layout
sheet if applicable;
8. site photos with key map;
9. backwater calculation with a justification of backwater and its effects, i.e., remains in
channel, below finish floor elevation, or contained within the right of way;
10. other calculations, meeting minutes, local testimony, telephone log, permits, etc., to add
clarity;
11. coordination with county surveyor; and
12. energy-dissipator calculations and files.
203-3.0 BRIDGE
203-3.01 Introduction
FHWA defines a bridge as a structure with a total span of 20 ft or longer, measured along the
centerline of the roadway. For a multiple-pipe structure, this includes the distance between the
pipes. For hydraulic purposes, a structure with a span greater than 20 ft, perpendicular to the
direction of flow, is considered a bridge. Each bridge defined by the Office of Hydraulics should
be modeled using HEC-RAS bridge analysis.
The following define bridge criteria and considerations, including modeling and report-
documentation requirements.
3. The legal requirements of government agencies and their policies and restrictions,
including permits should be considered. See Chapter 201 for a list of the involved
agencies.
6. For a project on new alignment, flood easements should be considered in a rural area, or
where land is inexpensive, as a possible cost-saving measure.
7. The effects of road or bridge realignment altering the flood-elevation location and
potentially causing property damage due to flooding should be considered.
8. Velocity through the structure should not damage the highway facility or adjacent
property.
10. In designing for overtopping, the crest-vertical curve profile location should be
considered as the preferred highway-crossing profile to allow for embankment
overtopping.
11. The downstream conditions should be studied, including those at other bridges or larger
streams that can have the potential to flood back up to the structure. The proposed bridge
should then satisfy the road-serviceability requirements due to the downstream flood
backwater.
12. Side ditches should be checked to ascertain that their elevation is below the water-surface
elevation, and that the flow does not spill over and affect road serviceability in adjacent
watersheds.
14. The location of the opening should account for future stream meandering, floodplain
effects, and possible damage to wetlands or other environmental concerns. An overflow
structure can be required for a very wide floodplain.
15. Pier spacing, pier orientation, and abutments should be designed to minimize flow
disruption and potential scour. Piers should be kept out of the main channel where
possible.
16. Foundation design for new bridges or scour countermeasures for existing bridges should
be provided to avoid failure due to scour.
17. Pier spacing and freeboard at the structure should be designed so that debris or ice can
pass.
18. Minimal disruption of ecosystems and values unique to the floodplain and stream should
be considered.
19. A level of traffic service should be provided that is compatible with that expected for the
class of highway and the projected traffic volume.
20. Choices should be designed that are supported with costs for construction, maintenance,
and operation, including probable repair and reconstruction and potential liability.
21. The proposed structure’s span should be equal to or greater than the existing span unless
prior approval is given from the Office of Hydraulics.
2. Allowable Backwater. This is the difference caused by a bridge between the upstream
water-surface elevation and the natural condition with no bridge at the same location.
The backwater is the maximum proposed bridge value that occurs at a given cross-section
location. The design-storm requirements are shown in Figure 203-2C.
If the existing bridge has a backwater of greater than 1 ft, the proposed bridge has an
allowable backwater equal to or less than 1 ft. If the existing bridge has a backwater less
than or equal to 1 ft., the proposed bridge has an allowable backwater equal to or less
than the backwater of the existing bridge. If the proposed bridge is on new alignment, the
allowable backwater is 0.14 ft. For exceptions, see item 10 below.
FHWA does not require economic justification for a bridge that causes less than 1 ft. of
backwater. Therefore, a formal risk assessment will not be required.
3. Outlet Velocity. The design-storm frequency shown in Figure 203-2C should be used to
determine the appropriate storm event for design. Figure 203-2D should be used to
determine the appropriate riprap size based on outlet velocity.
7. Channel Clearing. This consists of the removal of sediment to enlarge the waterway
opening. Channel clearing should not occur within 1 ft of the Ordinary High Water
elevation. Where the Ordinary High Water elevation is less than 1 ft above the flowline
elevation, channel clearing should not occur within 2 ft of the flowline elevation.
8. Multiple-Opening Structure. A multiple-opening structure is used in a wide floodplain to
pass a portion of the flow once the stream reaches a certain stage. The objectives in
choosing the location of a multiple opening include the following:
The backwater should be determined for the 1% annual EP discharge event. For a
structure requiring an IDNR permit, the backwater at 1% annual EP should not exceed
0.14 ft over existing conditions. IDNR should be contacted for further guidance. For a
structure not requiring an IDNR permit, the backwater from the 1% annual EP event
should not exceed 1 ft below the finished-floor elevations of nearby buildings or
residences. Impacts to crops and yards should be allowed for only a short duration.
10. New-Alignment Bridge. For a new bridge on a new alignment, the maximum backwater
should not exceed 0.14 ft. The 0.14 ft maximum may be modified as follows:
a. the backwater dissipates to 0.14 ft or less at the right-of-way line;
b. the channel is sufficiently deep to contain the increased water height without
overtopping the banks; the backwater is less than or equal to 1 ft; and the
maximum velocity is not excessive; or
c. a flood easement can be purchased upstream of the bridge to allow for greater
than 0.14 ft of backwater.
In a rural area where land costs are minimal, the cost savings may be substantial to
purchase flood easements and reduce the bridge-structure size. The use of flood
easements should be identified early in the design stage so that they can be included in
any land purchasing. However, flood easements are still limited to the maximum 1-ft
backwater requirement.
An exception to the 0.14-ft backwater allowance for a new bridge on a new alignment is
subject to approval of The Office of Hydraulics.
11. Bridge that Requires an IDNR CIF Permit. The water-surface elevation cannot be
increased more than 0.14 ft from existing conditions outside the right of way. The IDNR
Floodplain Guidelines Manual should be checked to determine if a CIF permit is
required, and for the definition of what the existing or base conditions are.
The regulatory agencies require the use of computer hydraulic-modeling software to support
calculations used in flood modeling. The required modeling program is HEC-RAS. The HEC-
RAS procedures are followed as stated in the IDNR manual, General Guidelines for the
Hydrologic-Hydraulic Assessment of Floodplains in Indiana, or Floodplain Guidelines, and the
USACE HEC-RAS manuals. The following should be considered in performing a HEC-RAS
model.
1. Survey Accuracy. A survey is performed for the purpose of bridge or road design.
However, the survey does not always extend far enough up- and downstream to cover the
entire reach used in hydraulic-modeling design. It may be necessary to propagate the last
cross-section up- and downstream as necessary to extend to the full reach length desired.
If available, some county, city, or USGS maps include contours that can be useful in
determining the cross-section shape outside the general project survey area. These tend
to be most useful in sizing the flood plain. Current aerial photography should be used
where current land uses may have changed from the original survey, such as new levees,
structures, etc. Other types of mapping are be available should be discussed with the
Office of Hydraulics prior to use. The hydraulic model should have adjusted the survey
to the NAVD 88 datum. The Floodplain Guidelines Chapters 4 and 5 provide
information on survey and mapping requirements.
2. Cross-Sections and Ineffective Flow. The cross-sections should extend far enough up-
and downstream to include areas that can affect the water surface as it passes through the
bridge of interest. This can include other downstream bridges or structures that can have
potential backwater effects to the bridge of interest. The beginning cross-section should
be the same for natural, existing, and proposed conditions for the same discharge. The
ending cross-section should show a decline in backwater converging back towards the
natural water-surface elevation.
The individual cross-sections should have data points that extend higher than the water-
surface elevation at its extents. Extending the cross-sections beyond the water-surface
elevation can affect the scale of the cross-section so that the channel itself is difficult to
visualize in the model display. The cross-sections should be chosen at appropriate
locations that are perpendicular to the channel. However, the overbank section may have
to be manipulated so that two cross-sections do not overlap. If possible, scour holes and
large sediment mounds near the bridge should be avoided as cross-section locations. If
such a location is necessary, manipulation of the flowline may be necessary to avoid
large rises and drops.
See Floodplain Guidelines Chapter 8 for more information on modeling. For the
appropriate roughness n value, see Figure 203-3A.
3. Bridge. In HEC-RAS, a bridge automatically uses the adjacent cross sections in the
modeling. It may be necessary to investigate the internal cross-sections to make changes
for channel clearing or lowering the channel’s n value through the bridge. The bridge
should be modeled such that is normal to the direction of flow. This can be done
manually or by using the skew function.
203-3.03(03) Scour
Scour is the most common cause of bridge failure. Therefore, potential scour problems should
be recognized. The appropriate countermeasures should be used as necessary to improve bridge
safety. HEC-18 and HEC-20 are FHWA documents that provide information and appropriate
analysis procedure for determining scour. The scour can be computed using hand calculations
from HEC-18, or by using the bridge modeling from HEC-RAS.
The types of scour that are used in bridge-hydraulics calculations include contraction, pier or
local, and abutment. Only contraction and pier scour should be computed. Abutment scour is
accounted for, due to riprap protection required at each abutment. Abutment scour has been
shown to be overestimated.
For a new or replacement bridge, the scour should be computed for both the 1% annual EP and
0.2% annual EP. The 0.2% annual EP discharge should not be computed using the traditional
1.7 multiplier of the 1% annual EP discharge method, as this has typically overestimated scour
and increased foundation costs. The 0.2% annual EP discharge should be determined using the
same methods described in Chapter 202 as used to determine other storm events. Scour
countermeasures are not required, as all bridge pier piles will be driven below the low-scour
elevation. However, the embankment should have appropriately-sized riprap placed on it in a
cone shape around the entire abutment. See Figure 203-3B, Riprap Scour Protection. For a
three-sided or box structure, see the INDOT Standard Drawings for the location of riprap.
In evaluating a bridge, all indications and locations of scour occurrence should be identified.
Bridge-inspection reports should also be checked, along with other historical scour and
geomorphology issues. Scour can be occurring though there are no apparent signs, as scour
holes can fill in prior to the water level sufficiently dropping to allow inspection. If overtopping
occurs before a 1% annual EP event, it is possible that the maximum scour can occur at a lesser
event. Therefore, the scour that occurs just before overtopping should be studied.
If the bridge is a single opening with a wide floodplain and the stream has a high probability of
meandering, guide banks, or spur dikes, should be used to align the approach flow with the
bridge opening and to prevent scour around the abutments. They are usually elliptically shaped
with a major-to-minor-axis ratio of 2.5 to 1. Their length can be determined according to HDS-1
procedures. Guide banks, embankments, and abutments should be protected with rock riprap
with a filter blanket or other approved revetment.
If possible, clearing of vegetation upstream or downstream of the toe of the embankment slope
should be avoided. For more information regarding riprap design and stronger armoring
practices, see Section 203-6.0.
The foundation design for the 1% annual EP should include a geotechnical-design-practice safety
factor of 2.0 to 3.0. The resulting design should then be checked using a superflood, the 0.2%
annual EP, and a geotechnical-design-practice safety factor of at least 1.0. Chapter 18 for more
information.
The hydraulic design model should be obtained. A velocity distribution at the bridge should be
computed that will determine the maximum velocity that occurs. The velocity distribution
should have at least 20 sections in the channel. This distribution is used later in the pier-scour
calculations.
Determine D50 from the geotechnical report. If D50 is unknown or a geotechnical report
does not yet exist at the time of hydraulic modeling, a value of 0.01 mm may be used
which will produce the most conservative result. If using HEC-RAS, D50 should have a
value and it must be at least 0.01 mm. If using a lesser value, HEC-RAS will incorrectly
show contraction scour as 0 ft.
Use the modeling to determine the remaining equation variables. HEC-RAS determines
this, or the equations in HEC-18 may be used for manual use.
Only the contraction scour result from the channel should be used.
2. Pier Local-Scour Analysis. Choose the Maximum V1Y1 method for determining pier
scour. The channel can meander and the highest velocity can occur at the face of the
pier.
Use the modeling to determine the remaining equation variables. HEC-RAS usually
determines this, or the equations in HEC-18 may be used for manual use.
3. Total Scour Analysis. Add the contraction scour and the pier scour for total scour depth.
This should be subtracted from the flowline at the bridge to determine low-scour
elevation. If analyzing an existing bridge, the foundation of the bridge should be checked
against the low-scour elevation to determine if the bridge is scour critical. If an existing
bridge foundation is unknown, the bridge is automatically considered scour critical
With pressure flow, the local scour depth at a pier or abutment is larger than for free-surface flow
with a similar depth and approach velocity. The increase in local scour at a pier subject to
pressure flow results from the flow being directed downward toward the bed by the
superstructure and by increasing the intensity of the horseshoe vortex. The vertical contraction
of the flow is a more significant cause of the increase in scour depth. However, where a bridge
becomes submerged, the average velocity under it is reduced due to a combination of additional
backwater caused by the bridge superstructure impeding the flow, and a reduction of discharge
which must pass under the bridge due to weir flow over the bridge and approach embankments.
As a consequence, an increase in local scour due to pressure flow can be offset by a lesser
velocity through the bridge opening due to increased backwater, and a reduction in discharge due
to overtopping.
In using HEC-RAS in a pressure-flow scenario, the program usually will not determine some
variables, such as the average flow depth at the bridge for contraction scour. They should be
entered manually.
HEC-RAS can be used to determine the discharge through the bridge and the velocity of
approach and depth upstream of the piers where flow impacts the bridge superstructure. These
values should be used to calculate local pier scour. Engineering judgment should then be used to
determine the appropriate multiplier times the calculated pier-scour depth for the pressure-flow
scour depth. This multiplier ranges from 1.0 for a low-approach Froude number Fr = -0.1, to 1.6
for a high-approach Froude number, Fr = 0.6. If the bridge is overtopped, the depth to be used in
the pier-scour equations and for computing the Froude number is the depth to the top of the
bridge deck or guardrail obstructing the flow. Research sponsored by FHWA has a listed
procedure for three separate pressure-flow situations. See FHWA-HRT-09-041 October 2009
for more information on this process.
The method used to determine the hydraulic- and scour-data parameters using HEC-RAS is
described below. The parameters should be shown for both existing and proposed conditions
where applicable.
1. Hydraulic Data.
a. Drainage Area. The drainage area is the delineated area that drains to the
structure in question. See Chapter 202.
e. Gross Waterway Area Opening Below Q100 Elevation. The required area is
determined by using the Q100 natural water surface elevation at the downstream
bridge face. Since this is to be the gross area, the flow-area output from HEC-
RAS, which is net area, should include the piers and adjusted flow-area water-
surface elevation to the Q100 elevation. The gross waterway area should be taken
in a direction parallel to the flow.
f. Road-Overflow Area. This is the actual flow area that will go over the road. This
is not based on the Q100 elevation. It should use the approach-crest elevation
along with the road profile to determine the area.
g. Q100 Velocity. This is the outlet velocity at the downstream face of the bridge as
it exits the structure. This is shown in the HEC-RAS Bridge Output as velocity
for the downstream side of the bridge. No other adjustments should be made, and
the continuity equation should not be used. The outlet velocity is the average
velocity across the whole structure.
i. Skew. The bridge skew is offset from the perpendicular to the roadway
centerline.
a. Q100 Maximum Velocity. The maximum velocity is determined from the highest
value of a HEC-RAS velocity distribution that includes at least 20 subsections
across the channel. The maximum velocity should be the highest value of both
the upstream and downstream bridge sections.
c. Q100 Total Scour. This is the addition of pier scour and contraction scour, but
does not include abutment scour. For multiple piers, use the pier with the highest
scour value.
d. Q100 Low-Scour Elevation. Subtract the total scour from the flowline elevation at
the bridge.
e. Q500. Use the methods described in Chapter 202. Do not use the 1.7 multiplier
method. Repeat the scour data parameters for Q500.
f. Flowline Elevation. This is the lowest point in the channel under the downstream
face of the bridge.
203-3.05 Documentation
The following provides an explanation of what is required in the submittal requirements for a
hydraulics report as it pertains to bridge-hydraulic analysis. The hydrologic requirements appear
in Section 202-4.0.
1. Narrative. The narrative should include a discussion of the thought process used for the
hydraulics or modeling of the bridge. This should also include special features or
conditions that the designer wants the reviewer to consider as a basis for decisions.
Historical flooding issues should be discussed.
4. Plan Sheet. Provide a plan sheet showing the cross-section locations used in the
modeling analysis. Expansion and contraction ineffective-flow-area lines, if using a
HEC-RAS method, should be included.
5. Layout Sheet. A layout sheet should be provided showing the bridge geometry. It should
include the low-structure, Q100, flowline, ordinary-high-water, and channel-clearing
elevations.
6. Site Photos and Aerial Photography. Photos of the site location should be provided that
show both up- and downstream views, and an aerial photograph, so that stream roughness
values, stream morphology, and structure alignment can be verified.
7. HEC-RAS Analysis. A hydraulic model should be provided in the submittal. The model
should be in a single project file. The natural, existing, and proposed plans should be
included within the file. By having the plans in one file, the natural, existing, and
proposed conditions can be compared next to each other.
9. Check-RAS. This should be used to check for modeling warnings. The warnings should
be explained or corrected.
203-4.01 Introduction
This Section provides guidance regarding storm-drain design and analysis policy. A storm-
drainage facility consist of curbs, gutters, storm drains, side ditches or open channels as
appropriate, or culverts. The aspects of storm-drain design such as system planning, pavement
drainage, gutter-flow calculations, inlet spacing, pipe sizing, and hydraulic grade line
calculations are discussed herein. In addition to INDOT policy, local ordinances and legal
constraints should be considered in the final design.
The design of a drainage system should address the needs of the traveling public and as those of
the local community through which it passes. The drainage system for a roadway traversing an
urbanized region can be more complex. This can be attributed to concentrated development
areas and conflicts with existing utilities and drainage systems.
See HEC-22 Urban Drainage Design Manual, Chapters 4 and 7, or LTAP Stormwater Drainage
Manual, Chapter 5 and 7 for more information on storm-drain design.
The placement and hydraulic capacity of a storm-drainage facility should be designed to consider
damage to adjacent property and to secure as low a degree of risk of traffic interruption due to
flooding as is consistent with the importance of the road, the design traffic service requirements,
and available funds.
The Rational Method is used for the design of a storm drain. The storm-drain flow method is
described in Chapter 202. The specific policies for pavement-drainage-system design and
analysis are described in Section 203-4.04.
The type of facility determines allowable pavement spread and the amount of impervious area
that will be intercepted by the storm drainage system. See Figure 203-4A to determine the
allowable spread. If the facility is planned to be expanded as a future project, consideration
should be given to designing the storm sewer to handle the future impervious area. Other
transportation users can utilize the areas between the curb and edge of travel lane, which can
affect the design.
INDOT policy is not generally required to be in accordance with local jurisdictional rules or
regulations. A local jurisdiction can be more restrictive than INDOT drainage requirements. If
so, the local design parameters should be followed as much as practical.
In considering the storm drain, the existing conditions should be evaluated. Off-site drainage
may need to be intercepted by the storm-drain system. This can require earth inlets for drainage
that is blocked by the road. Off-site areas drainage onto the roadway can require additional curb
inlets and storm-sewer capacity. A large concentrated volume of water can be collected more
efficiently in a channel using culvert-type inlets rather than being allowed to flow overland onto
the pavement and into the pavement inlets. Existing utilities should be considered in
determining the storm-drain location and depth.
Where drainage is into an existing system such as a ditch or other storm drain, impacts to the
receiving system should be considered. Possible impacts include, but are not limited to, outlet
velocity, capacity of receiving system, erosion, finished floor elevations, etc. The outlet
structure flow should contain a reasonable outlet velocity and should be protected against scour.
See Figure 203-2D for riprap size based on outlet velocity. Downstream flow conditions include
the following.
1. If the storm drain outlets into a legal drain, the county surveyor should be contacted to
ascertain that the legal drain can handle the additional flow.
2. If the receiving ditch cannot or should not satisfy the necessary capacity requirement, a
detention facility, either above or below ground, should be considered. See Section 203-
5.0.
3. The outlet invert into a ditch should be as high as possible. If the outlet invert has to be
less than 1 ft above the low-flow elevation, high-water analysis of the ditch should be
performed to determine the backwater effects into the storm-drain system.
4. FHWA has developed guidelines for determining the backwater effects through the
storm-drain system during a higher creek flow. See Figure 203-2G for these
requirements. For this situation, a flap gate may be required on the outlet structure.
Some ditches are considered environmentally sensitive. If draining into a sensitive stream,
water-quality improvements can be necessary. A sensitive stream should be identified in the
environmental document. The Office of Environmental Services should be contacted if
questions arise. Sanitary and storm drainage systems should be separate. A storm drain may be
required to tie back into an existing storm-drain system that is a combined sewer. The receiving
wastewater-treatment facility should have sufficient capacity for the additional flow, and that all
EPA requirements are satisfied.
In designing the storm drain, the trunk lines should be placed as shallow as possible while
satisfying cover requirements. This will reduce the cost of excavation and increase safety for the
construction crew. However, this is not always possible due to utility conflicts, slope
requirements, outlet elevations, or other issues. Where there is a slope, the inlets should be
placed on the upstream side of a driveway or intersection. Where practical, manholes should be
placed outside of the pavement limits. If this is not possible, inlets and manholes should be
placed to avoid the wheel path in the roadway mainline, an intersection or a drive. A trunk
mainline may be required on each side of the roadway with few laterals, or only a single trunk
mainline may be required. Such features are a function of economy but can be controlled by
other physical features.
Bridge deck drainage is similar to that for a curbed roadway section. However, it can be less
efficient because cross slopes are flatter, parapets collect large amounts of debris, and small
drainage inlets or scuppers have a higher potential for clogging due to debris. Bridge-deck
construction requires a constant cross slope. Because of the difficulties in providing and
maintaining an adequate deck-drainage system, gutter flow from the roadway should be
intercepted before it reaches a bridge. Runoff should be collected by means of inlets, although
gutter turnouts may be used for a minor flow. The drainage system should prevent water, road
salt, or other corrosives from contacting the structural components. Runoff should be handled in
compliance with applicable stormwater-quality regulations. Deck drainage can be carried
several spans to the bridge end for disposal.
A bridge deck is usually the first segment of a highway to become icy in cold weather. Adequate
deck drainage through use of minimum grades and cross slopes is essential to prevent the
accumulation and spreading of icy spots. Icing on a bridge deck caused due to frost is difficult to
prevent except through surface texture and maintenance practices.
A storm drain is one of the earlier items constructed during the project work. Drainage should be
maintained throughout the construction process. The feasibility of construction should be
considered in designing the storm-drain system. Safety and costs should be analyzed. If the
storm drain is too deep, it may not be able to be constructed without extensive and expensive
safety measures. The storm-drain design should satisfy the specified velocity requirements of
Section 203-4.04(06), so that less maintenance and cleaning will be required.
1. Compatibility of Drainage Structure and Casting. Figure 203-4B shows which casting
may be used with a given type of catch basin, inlet, or manhole. The information shown
in the figure is complementary to that shown on the related INDOT Standard Drawings.
In developing a drainage plan, the designer should refer to the figure to ascertain
structure and casting compatibility. If a structure-casting combination other than that
permitted in the figure is desired, the Office of Hydraulics should be contacted.
2. Pump Station. A pump station may be required to satisfy the grade requirements. The
use of a pump station is not desirable. If the designer is considering the use of a pump
station is considered, the Office of Hydraulics should be contacted for approval.
The first step in the design of a storm-drainage system is to collect initial data about the project
and site location. This includes knowing the purpose of the project, coordinating with local
agencies, and understanding present and future land-use patterns. All possible outlet locations
should be determined. Topographical and aerial mapping is helpful at this point in the process.
Some cities and counties have detailed mapping information of their areas.
An inlet should not be located in the path where a pedestrian is likely to walk.
An inlet will draw an amount of water off the road and into the storm-drain system. Once the
water spreads out a certain distance from the curb onto the road it is desirable to have an inlet
added that will reduce this width of water. This width is known as allowable water spread. The
spread is determined based on the quantity of water and the geometry of the road as it moves
down the gutter, as gutter flow. To determine the amount of water that reaches an inlet, the
Rational Method should be used. The minimum time of concentration should be taken as 5 min.
The design-storm frequency is determined based on the type of facility. The runoff is typically
all impervious unless there is some off-road drainage coming on to the road.
Pavement can have a texture which can affect the friction of the water as it moves across the
road. See Figure 203-4C for Manning’s n value to be used for a street or pavement gutter. The
transverse and longitudinal roadway slopes can be determined from the proposed road design.
The desirable minimum longitudinal gutter grade for a curbed pavement is 0.3%. A minimum
grade in a curbed section can be maintained in flat terrain by rolling the longitudinal-gutter
profile.
The inlet efficiency should be determined to see whether there will be by-pass flow from the
inlet that should be added to the next basin for determining the location of the next inlet. Each
inlet casting has a unique flow-intercept-efficiency coefficient. Manufacturer’s catalogs are a
source of this information.
A curved vane grate should be used for a curb-and-gutter application. Figure 203-4D provides a
hydraulic capacity chart for a curved vane-grate inlet. The chart is based on a roadway cross
section used by the Department. For another inlet type and roadway cross section, the procedure
for determining the hydraulic performance is described below. FHWA has developed computer
software, HY12, which will analyze the flow in a gutter and the interception capacity of a grate
inlet, curb-opening inlet, slotted-drain inlet, or combination inlet on a continuous grade. Both
uniform and composite cross-slopes can be analyzed. The program can analyze a curb-opening,
slotted-drain, or grate inlet in a sag. Enhanced versions by private vendors have made the
program more user-friendly and have improved its usefulness. Not all INDOT grate
configurations have been included in HEC-22. The curved vane grate and the reticuline grate
used in the program are similar to the INDOT grates and can be used by inputting the appropriate
size. Other grate types, such as INDOT casting type 12, 13, or 14, are not included in HEC-22.
However, grate-inlet-capacity curves are available from manufacturers and are recommended for
use.
See HEC-22 Chapter 4 for the spread-equation and inlet by-pass calculations.
The methodology for inlet location and calculating spread is done with a computer program or
on a computer spreadsheet similar to that shown in Figure 203-4E.
A storm-drainage system should be designed so that the 10% annual EP passes through the
system via gravity. Pipe size should not be decreased in a downstream direction regardless of
the available pipe gradient because of potential plugging with debris. See HEC-22 Chapter 7 for
more information.
The storm-drain network should accommodate the 2% annual EP. The system may operate
under pressure, but the hydraulic grade line (HGL) should remain below the rim elevation at
each system manhole, inlet, catch basin, or similar structure. At the outlet, the initial HGL will
be determined based on the tailwater, which will be either the receiving flow depth or halfway
between the crown and critical depth. See HEC-22 Chapter 7 for more information.
Cover is measured from the pipe crown to the bottom of the proposed pavement. The depth of
aggregate base under HMA pavement or subbase under concrete pavement is included in the
cover dimension. The allowable cover depth can vary based on pipe material. For a circular
pipe, the minimum cover should be at least 1 ft., and the maximum cover should be not more
than 100 ft. For a deformed pipe with a corrugated interior designation, the minimum cover
should be at least 1.5 ft. If these requirements cannot be satisfied, it is necessary to consider
other structure types before continuing with the Structure Site Analysis.
The cover depth should be determined for a structure with a precast reinforced-concrete box
section.
A manhole is utilized to provide entry to a continuous underground storm drain for inspection
and cleanout. As a cost-saving measure, the storm drain system should connect inlets together as
much as possible before connecting to a manhole. The inlets or manholes should be placed
within 400 ft of each other so that maintenance can clean them when necessary. The manhole-
bottom elevation should match that of the pipe invert leaving the manhole to avoid
sedimentation.
A manhole should not be located in a traffic lane. However, if this is impossible, it should not be
in the normal vehicle-wheel path. Where practical, a manhole should be located off the roadway.
Figure 203-4F shows the guidelines for a pipe size connection to a particular manhole.
203-4.04(09) Sag Vertical Curve and Flanking Inlets
Two curved vane grates, type 10 or 11, should be installed on one frame casting at the sag point.
Each vane grate is positioned to receive water from each upstream direction. A curb box is
combined with the grate to provide relief if the grate is plugged with debris. The curb box is
ignored in the hydraulic-capacity calculations. A sag grate inlet operates as a weir up to a depth
of about 0.5 ft and as an orifice for a depth greater than 1.5 ft. In a depressed section or
underpass where ponding water can be removed only through the storm-drain system, a higher
design frequency, 2% annual EP, should be considered to design the storm drain which drains
the sag point.
To provide adequate drainage in a sag vertical curve, a minimum slope of 0.3% should be
maintained within 50 ft of the level point in the curve. The location of or need for flanking inlets
should be based on the design spread, design speed, traffic volume, potential for clogging of the
low point inlet, maximum depth of ponding potential at the site, or other considerations that can
be peculiar to the site. Typically, the longer the storm drain reach, the greater the need for
flanking inlets.
The flanking inlets should be placed so that they will limit spread on a low-grade approach to the
level point and act in relief of the sag inlet if it becomes clogged. Figure 203-4G shows the
spacing required for depth-at-curb criteria and vertical curve length defined by K = L/A, where L
is the length of the vertical curve in feet and A is the algebraic percentage difference in approach
grades. The INDOT geometrics specify a maximum K value for the design speed, and a
maximum K value of 170 for considering drainage on a curbed facility. See HEC-22, Chapter
4.4 for design information.
See HEC-22 Chapter 4.4 for more information on designing a slotted drain.
Snow accumulation adjacent to a concrete barrier on the inside or outside shoulder can present a
drainage problem. Therefore, a slotted drain should be used in conjunction with inlet type H-5 or
HA-5 as follows:
1. in a tangent section, at every third inlet;
2. on the low side of a superelevated curve, at all inlet sites; or
3. in a sag vertical curve, three inlets, centered on the low point.
1. Slotted Inlet on Grade. A slotted inlet, which uses a vertical riser, is an effective
pavement-drainage inlet which has a variety of applications. It can be used on a curbed
or uncurbed section, and offers little interference to traffic operations. It can be placed
longitudinally in the gutter or transversely to the gutter. A slotted inlet should be
connected into an inlet structure so that it will be accessible to maintenance forces upon
plugging or freezing.
2. Slotted Inlet in a Sag Location. Except adjacent to a concrete barrier, the use of a slotted-
drain inlet in a sag configuration is discouraged because of the propensity of such an inlet
to collect debris. However, it may be used where it is desirable to supplement an existing
low-point inlet with the use of a slotted drain. A slotted inlet in a sag location performs
as a weir to a depth of about 0.2 ft, dependent on slot width and length. At a depth
greater than about 0.4 ft, it performs as an orifice. Between these depths, flow is in a
transition stage.
203-4.04(11) Underdrains
A roadside ditch is used with an uncurbed roadway section to convey runoff from the highway
pavement and from areas which drain toward the highway. Due to right-of-way limitations, a
roadside ditch should not be used on an urban arterial. It can be used in a cut section, depressed
section, or other location where sufficient right of way is available, and drives or intersections
are infrequent. Where practical, the flow from an area draining toward a curbed highway
pavement should be intercepted behind the curb to prevent flow onto the pavement..
A median area or inside shoulder should be sloped to a center swale to prevent drainage from the
median area from flowing across the pavement. This should be considered for a high-speed
facility, or for one with more than two lanes of traffic in each direction. Where a median barrier
is used, or on a horizontal curve with associated superelevations, it is necessary to provide inlets
and connecting storm drains to collect the water which accumulates against the barrier. A slotted
drain adjacent to the median barrier or weep holes in the barrier can also be used for this
purpose.
A median or roadside ditch can be drained by means of drop inlets similar to those used for
pavement drainage, pipe culverts under one roadway, or cross-drainage culverts which are not
continuous across the median. The type P inlet is used for median ditch drainage. See the
INDOT Standard Drawings for inlet details. See HEC-22 Chapter 4 for additional information
regarding design procedures.
A curb at the outside edge of a pavement is common for a low-speed, urban highway facility. It
contains the surface runoff within the roadway and away from adjacent properties, prevents
erosion, provides pavement delineation, and enables the orderly development of property
adjacent to the roadway. See Section 45-1.05 for a discussion on curb types and usage.
A curb and gutter forms a triangular channel that can be an efficient hydraulic conveyance
facility to convey runoff of a lesser magnitude than the design flow without interruption to
traffic. If a design-storm flow occurs, there is a spread or widening of the conveyed water
surface and the water spreads to include not only the gutter width, but also parking lanes or
shoulders and portions of the traveled surface.
Where practical, runoff should be intercepted from a cut slope or other area draining toward the
roadway before it reaches it. A shallow swale section at the edge of the roadway pavement or
shoulder offers advantages over a curbed section where curbs are not needed for traffic control.
The advantages include a lesser hazard to traffic than a near-vertical curb, and hydraulic capacity
that is not dependent on spread on the pavement.
A shoulder gutter or sloping curb may be appropriate to protect a fill slope from erosion caused
due to water from the roadway pavement. It should be considered for a 2:1 fill slope higher than
20 ft. It should also be considered for a 3:1 fill slope higher than 20 ft if the roadway grade is
steeper than 2%. Where permanent vegetation cannot be established, the height criterion should
be reduced to 10 ft regardless of the grade. Inspection of the existing and proposed site
conditions and contact with maintenance and construction personnel should be made by the
designer to determine if vegetation will survive.
A shoulder gutter or curb, or a riprap turnout should be utilized at a bridge end where
concentrated flow from the bridge deck will otherwise flow down the fill slope. The section of
gutter should be long enough to include the transitions. A shoulder gutter or riprap turnout is not
required on the high side of a superelevated section or adjacent to a barrier wall on a high fill.
The location of an impact-attenuator system should be reviewed to determine the need for a
drainage structure. It is necessary to have a clear or unobstructed opening as traffic approaches
the point of impact to allow a vehicle to impact the system head-on. If the impact attenuator is
placed where superelevation or other grade separation occurs, a grate inlet or a slotted drain can
be needed to prevent water from flowing through the clear opening and crossing the highway
lanes or ramp lanes. A curb, curb-type structure, or swale cannot be used to direct water across
the clear opening because vehicular vaulting can occur once the attenuator system is impacted.
HEC-21 should be referenced for bridge-deck drainage design procedure. The longitudinal slope
of the bridge deck should be steep enough to satisfy the gutter-spread requirements without the
need for gutter inlets on the structure itself. However, this is not always feasible, and runoff
capture may be necessary. All surface drainage should be intercepted before it enters the bridge
section. If inlets are required on the structure, the criteria to be implemented are as follows.
1. For a structure length of less than 170 ft and on grade, or a structure length of less than
250 ft and on a crest vertical curve, inlets are not required. However, hydraulic
calculations for deck drains are required.
2. The gutter spread should be checked to ensure compliance with the design criteria
described in Figure 203-4A.
3. The desirable minimum longitudinal slope for bridge-deck drainage is 0.5%. A flatter
grade will be tolerated where it is not physically or economically desirable to satisfy this
criterion.
4. Fifty percent of the inlets on the bridge should be assumed to be plugged. The end
collectors should be sized accordingly.
6. If deck drainage is required at the ends of the grade-separation structure, deck drains
should discharge into inlets located in the berm or on the slopewall under the bridge as
shown on the INDOT Standard Drawings.
7. A flat grade or sag vertical curve is not allowed on a bridge on a new alignment.
Vertical-curve criteria for an existing structure should be followed for inlet placement.
Because a grate inlet at a sag location is prone to clogging, a safety factor of 2.0 for the
inlet design size should be used if no alternative design is feasible.
a. Grate Type A. This grate fits onto roadway drain type SQ. It is a parallel bar
grate and the most hydraulically-efficient grate in use. The grate is 19 in. square.
Because the width of the openings is 1 in., the grate is not considered bicycle-safe
if placed with the bars parallel to the direction of traffic. However, it is feasible to
use this grate where bicycle traffic is allowed on the bridge if the bars are placed
perpendicular to the direction of travel. The perpendicular arrangement can
substantially reduce the hydraulic capacity of the grate. The outlet fitting is a
circular pipe with diameter of 6 in.
b. Grate Type D. This grate fits onto roadway drain type OS. This is a type C grate
with parallel bars but has two transverse bars which prevent bicycle wheels from
dropping into the inlet. Therefore, it is considered bicycle-safe. The transverse
bars reduce the hydraulic capacity of the grate. The grate dimensions are width of
19 in. by length of 20 in. The outlet fitting is a circular pipe with diameter of 6 in.
d. Curved-Vane Grate. This grate should be used on a curbed roadway where the
inlets are located off the bridge deck.
1. A bridge-drainage pipe beneath the deck is sized larger than necessary for hydraulic
purposes to facilitate maintenance. The minimum pipe diameter is 6 in. The inlet
conditions will control the flow capacity. Entrances, bends, and junctions in the
underdeck pipe system provide opportunities for debris to snag and collect. Smooth
transitions and smooth interior surfaces should be provided. Sharp bends, corner joints,
or bevel joints should be avoided.
3. The INDOT Standard Drawings show details for cast-iron deck drains.
4. Figure 203-4H, Typical Floor Drain Sections, illustrates two alternatives to drains. Its
detail (a) shows a traditional arrangement including a short overhang and a steel beam,
which permits the drain pipe to be located internally with reference to the external beam.
Its detail (b) shows another arrangement including a large overhang and a bulb-tee beam,
which locates the drain pipe to the outside. This is aesthetically less pleasing, therefore
emphasizing the desirability of keeping the number of drains to a minimum.
5. A drainage casting should be positioned such that the outlet pipe is located inside the
exterior beam, if practical. See detail (a). If it cannot be located as such, the casting type
and position should be selected to locate the drainage pipe as close as practical to the
exterior beam. The plans should show the drain location, positioning, and attachment
details.
6. The pipe-conveyance system should not extend below the superstructure until the outfall.
The minimum desirable slope is 1% for a longitudinal pipe between drains or from a
drain to the point of discharge.
7. An open deck drain should not be located over a roadway, sidewalk, or railroad. If a
drain is to be located in one of these areas, a closed drainage system should be provided.
1. The downspout should be extended 6 in. below the beam soffit. The downspout should
be placed approximately 10 ft from the face of a substructure unit, unless a closed
drainage system is to be used. A downspout should not interfere with the required
horizontal or vertical clearances. A pipe system designed to bring water down to ground
level can become clogged with debris and ice and should only be used as the last option.
2. A downspout should not discharge water where such water can be windblown and can
flow down a column or pier.
3. Water should not be discharged openly over a traveled vehicular, railroad, or pedestrian
way, unpaved embankment, or unprotected ground where it can cause erosion or
undermine a structural element. An energy dissipator or riprap should be provided to
prevent erosion.
4. If a free fall is less than 25 ft, riprap or a splash pad will be required to prevent erosion.
A cleanout for maintenance access should be provided at key points within the system to
facilitate the removal of obstructions. A downspout should be located so that a maintenance
crew can access it from underneath the bridge and preferably from the ground. The most
convenient arrangement should be made, as a cleanout that is inaccessible or difficult to reach
will not be cleaned.
Where INDOT constructs a drainage facility outside its right-of-way limits to provide adequate
drainage for a highway, I.C. 8-23-6-2 allows INDOT to assess a proportionate share of the cost
of constructing the drainage facility outside the right of way to beneficiaries of the drainage
structure. Therefore, a municipality or other beneficiary that connects to an INDOT drainage
structure outside INDOT right-of-way limits can be assessed a share of the cost of the drainage
structure in proportion to the amount of drainage discharged. The proportionate share is
calculated as follows:
ܱܴܳ
ܤܣൌ ܨܥ൬ ൰ [Equation 203-4.1]
ܳܶ
By common law, INDOT also has the authority to seek a contribution from the LPA if
stormwater from outside the INDOT right of way discharges into a drainage facility within the
INDOT right of way. For example, if a municipality wants to make a direct discharge into an
INDOT trunkline storm drain, INDOT’s policy will be to request a storm-drainage agreement for
the trunkline-sewer construction. The proportionate share will also be determined from Equation
203-4.1. If the discharge is in the form of sheet flow onto INDOT right of way, INDOT will not
seek a contribution from the municipality involved.
If a particular situation involving sheet flow onto INDOT right of way is increased from existing
conditions, the LPA should agree to the necessary local contribution as a condition for initiating
the State highway improvement. Such an agreement cannot be forced upon an LPA, but must be
pre-arranged through negotiations between the LPA and the Planning Division or Office of
Environmental Services. However, this can occur as late as the design phase.
A situation may arise if INDOT storm-sewer construction results in a request for stormwater
detention or a county assessment for the reconstruction of a regulated drain. If the situation also
involves INDOT conveying city or town stormwater, INDOT should seek a storm-sewer cost-
sharing contribution from the city or town. The procedure for determining the appropriate
contribution by the city or town will be as described above. INDOT cannot cite I.C. 8-23-6-2 as
authority to pass on a portion of a county drainage assessment to the city or town. Only a county
drainage board has the authority to levy a drainage assessment on a municipality or private-
property owner if a regulated drain is involved.
A county drainage assessment does not require a formal agreement to be legally binding on
INDOT. However, if an assessment includes a monetary contribution which relieves INDOT
from providing stormwater detention mandated by the county, the conditions of the assessment
should be formalized in a storm-drainage agreement.
The need for a storm-drainage agreement should be identified during the preliminary-plans
development. Information necessary for the preparation of the formal agreement should be
coordinated with the municipality prior to INDOT design approval. The preliminary cost
estimate of the trunkline sewer and the exact ratio to be used in determining the municipality’s
share should be verbally agreed to with the municipality. The ratio may be based on the sewer’s
cross-sectional area if the discharge of the municipality’s storm sewer cannot be reasonably
determined. The municipality should be notified in writing of the approximate cost of its share
so that it can arrange financing.
After design approval, the formal storm-drainage agreement will be written to bind the LPA and
the State. The Legal Services Division will prepare this document. The agreement must be
signed by all parties concerned before the project may be scheduled for a letting.
INDOT does not limit the designer to particular software design programs. However, the
designer should provide output in a spreadsheet format as explained in Section 203-4.05.
203-4.05 Documentation
The following provides an explanation of the submittal requirements for an INDOT hydraulics
report as it pertains to storm-drain-hydraulics analysis. The hydrologic requirements are
described in Section 202-4.02.
A tabulated summary of spread calculations for inlet spacing should be provided as shown in
Figure 203-4E. Computer software programs may be used for preparation of solutions.
However, the results should still be summarized and referenced in the accepted tabular form.
A storm sewer should be designed to carry the runoff from a 10% annual EP through the system
via gravity. Computer-software methods are available to the user to determine the capacity of a
storm-sewer system. The results from an electronic or manual method should be provided in an
accepted tabular method as shown in Figure 203-4 I.
The final storm-sewer design should be checked to determine its adequacy by analysis using a
2% annual EP through the entire system of the hydraulic gradient. The gradient line should not
exceed the elevation of an opening into the system. A tabular summary or plotted profile should
be provided in the hydraulics-report submittal.
Road plans for a storm-drain project should be submitted so that the appropriate inlet and storm
drain pipe locations can be identified. The plan view should be simplified to show the pipe type,
slope, and size; structure identifier, road grade, and other information necessary to evaluate the
storm-drain system. The plans structure numbers should match the computer and tabular results
in the report submittal. All discrepancies should be addressed prior to report submittal.
Other information that the designer deems necessary toward validation of the design should be
provided in the hydraulics report. Non-traditional methodology requires the approval of the
Office of Hydraulics manager.
203-5.01 Introduction
The traditional design of a storm-drainage system has been to collect and convey storm runoff as
rapidly as possible to a suitable location where it can be discharged. However, the impact of
such a traditional storm-drainage design has not always been favorable. Rapidly conveying
stormwater can cause environmental impacts to karst topography and wetlands downstream,
overwhelm limited outlet capacities, and flood downstream properties, especially where the
amount of impervious area is increased as part of a roadway project. To reduce these impacts,
various forms of stormwater management have been developed, for an open-system or closed-
system facility, as described below.
203-5.02 General Policy
Controlling the quantity of stormwater release using a storage facility can provide the potential
benefits as follows:
Storage can be developed in a depressed area in a parking lot, road embankment, freeway
interchange, or a small lake, pond, or depression. The utility of a storage facility depends on the
amount of storage, its location within the system, and its operational characteristics. An analysis
of such a storage facility should consist of comparing the design flow at a point or points
downstream of the proposed storage site, with or without storage. Other flows in excess of the
design flow that can be expected to pass through the storage facility may be required in the
analysis, i.e., 1% annual EP flood. The design criteria for a storage facility should include the
following:
1. release rate;
2. storage volume;
3. grading and depth requirements;
4. outlet works; and
5. location.
At a minimum, a storage facility should be designed to detain the 1% annual EP, post-
development peak runoff rate, and release it at the 10% annual EP, pre-developed peak runoff
rate. An emergency overflow capable of accommodating the 1% annual EP post-development
discharge may be required.
A local jurisdiction can be more restrictive than INDOT drainage requirements. INDOT
requirements need not be in accordance with local jurisdictional rules and regulations. However,
the local design parameters should be followed as much as practical.
203-5.03 Design Considerations
A pump station may be required to outlet from an infiltration/detention facility. The use of a
pump station to outlet a facility is not desirable. If a pump station is being considered, the Office
of Hydraulics should be contacted for approval.
Dam safety should be considered for a berm or embankment created as part of a detention
facility. An embankment should not be subject to IDNR regulation and inspection requirements.
Per the Indiana Code, IDNR has jurisdiction over all structures, except where the embankment is
lower than 20 ft, the contributing drainage area is less than 1 sq mi, or the storage volume behind
the structure is less than 100 ac-ft. For more information, see Indiana Code 14-27-7.5:
Regulation of Dams.
A detention pond is designed to reduce the peak discharge and detain runoff only for a specific
duration. A detention basin should have a positive outlet that empties all runoff between storms.
The excavation of a detention pond can extend below the water table or outlet level where the
bottom is sealed due to sedimentation. This is a detention pond or wet-bottom detention basin.
The detention pond also has a positive outlet and releases all temporary storage.
A dry-bottom detention facility should be used. A detention basin will require additional right of
way. The basin will require a certain amount of space, and it should be outside the clear-zone for
safety purposes. The pond location and outlet should be considered, especially for flood routing.
The overflow location should avoid impacting nearby property and the roadway.
A retention pond retains runoff for an indefinite time and has no positive outlet. Runoff is
removed only by means of infiltration through a permeable bottom or by means of evaporation.
A retention pond or lake is an example of a retention facility. A retention pond is designed to
drain into the groundwater table.
Soil characteristics are the primary concern in designing a retention pond. A geotechnical report
should be obtained from the Office of Geotechnical Services, county surveyor’s office, etc, to
determine the infiltration capacity of the substratum.
A retention pond will require additional right of way. It should be located outside the clear-zone
for safety purposes.
203-5.03(03) Roadside-Ditch Detention
A roadside ditch detention system takes advantage of the additional capacity of the roadside and
median ditches created by the clear-zone requirements. A roadside ditch detains runoff from the
roadway and discharges it at a restricted rate to a positive outlet.
A roadside ditch is the least expensive open-detention system, since it does not require additional
right of way or significant additional maintenance. Since the ditch is within the right of way,
safety considerations and roadway serviceability should be evaluated.
Underground detention is best suited to an urbanized area where right of way and available land
are constrained. It is desirable for where an underground storage structure is to be located
outside the pavement limits. Coordination with local utilities is required. Conflicts should be
minimized. Clearances should be observed between stormwater and other systems such as
drinking water and sanitary sewers. In considering underground detention, the native soil should
be determined to ensure constructability. All inline detention should have a positive grade to
minimize sedimentation. Access should be provided for cleaning of the underground facility.
The grade should be set to avoid the need for a pump station if possible.
The types of underground detention include underground storage, inline detention, parallel
storage systems, oversize storm-sewer system, and infiltration trench. Underground storage can
be built as one single unit with one inlet and one outlet, under a large area such as a parking lot.
It can also be built as a pipe network or conduit system with multiple inlets and only one outlet,
under a large area such as a parking lot. Inline detention replaces part of a storm-sewer system
with a larger structure near the outlet to detain water within the system. A parallel storage
system runs parallel to the existing storm-sewer system to provide additional storage. An
oversize storm-sewer system increases the pipe sizes as needed in parts of the storm sewer to add
storage to the entire system. An infiltration trench functions like a roadway underdrain, but it
can be used only in sandy soil, where the infiltration rate is high.
An outlet work can take the form of combinations of a drop inlet, pipe, weir, or orifice. An
outlet work selected for a storage facility includes a principal spillway or an emergency
overflow. It should be able to accomplish the design functions of the facility.
A slotted-riser pipe should not be used due to clogging problems. A curb opening can be used
for parking-lot storage. The principal spillway is intended to convey the design storm without
allowing flow to enter an emergency outlet.
An emergency spillway is an outlet provided to allow excess water to exit the pond once the
design storm is exceeded. Usually in the shape of a weir, the emergency outlet should be located
so that the excess stormwater flows to an adequate outlet and does not damage nearby property.
An emergency spillway should be included in a storage-facility design if possible. However, a
viable emergency spillway location may not exist.
203-5.03(06) Maintenance
To ensure acceptable performance and function, a storage facility that requires extensive
maintenance is discouraged. The maintenance problems that are typical of a detention facility
are as follows:
1. weed growth;
2. grass and vegetation maintenance;
3. bank deterioration;
4. standing water or soggy surface;
5. mosquito control;
6. blockage of outlet structures;
7. litter accumulation; or
8. maintenance of fences and perimeter plantings.
1. Both weed growth and grass maintenance can be addressed by constructing side slopes
that can be maintained using available power-driven equipment, such as a tractor mower.
2. Bank deterioration can be controlled with protective lining or by limiting bank slopes.
3. Standing water or soggy surfaces can be eliminated by means of sloping the basin bottom
toward the outlet, or by means of constructing a low-flow pilot channel across the basin
bottom, from the inlet to the outlet.
4. Once the problems listed above are addressed, mosquito control will not be a major
problem.
5. An outlet structure should be selected to minimize the possibility of blockage. A pipe of
diameter of less than 6 in. tends to block easily and should be avoided.
6. The facility should be located for easy access where the maintenance associated with
litter and damage to fences or perimeter plantings can be conducted regularly.
Routine maintenance activities include an annual inspection, preferably during wet weather, and
mowing, as required.
Ponding of water for a significant period of time, at a relatively shallow depth, can introduce an
additional risk factor for property damage, personal injury, or loss of life. Safety considerations
include reducing the chance of drowning by fencing the basin, reducing the maximum depth, or
including ledges or mild slopes to prevent a person from falling in and to facilitate his or her
escape from the basin. A storage facility in a location that is easily accessible to the public
should be provided with fencing adequate to prevent entry onto the site by unauthorized persons.
A storage facility located adjacent to a roadway should be provided with an adequate clear zone
to minimize the accidental entry of an errant vehicle.
Protective treatment is required to prevent entry to a facility that poses a hazard to all persons.
Fences and signs are required for a detention or retention pondwith a locked gate to allow for
maintenance access.
Where a storage facility is located near a roadway, the road should be provided with an adequate
clear zone. The maximum operating-pool depth is limited to 5 ft unless otherwise approved by
the Office of Hydraulics.
A storage facility will require an inflow rate and an outflow rate to determine the necessary
storage volume.
The amount of water flowing into the storage facility should be determined. This inflow rate is
the post-developed 1% annual EP. However, an additional smaller inflow rate should be
considered, if a stricter local ordinance is being followed. The outflow rate should then be
determined. The outflow rate is the pre-developed 10% annual EP. However, additional
smaller outflow rate should be considered, if a stricter local ordinance is being followed.
The required storage volume should be calculated, based on the inflow and outflow rates, and
storm duration. If the watershed draining into a storage facility is greater than 2 ac, the design
should be based on reservoir-routing methods which develop hydrographs for both inflow and
outflow. WinTR-20 and HEC-HMS are available public-domain hydrographic programs. A
basin regulating less than 2 ac can be analyzed using the Rational Method to create a triangular
hydrograph.
203-5.04(01) Detention Pond
For a detention pond, a minimum freeboard of 1 ft above the 1% annual EP storm highwater
elevation should be provided. Other considerations in setting the depth include flood-elevation
requirements, public safety, land availability, land value, present and future land use, water-table
fluctuations, soil characteristics, maintenance requirements, and required freeboard.
The primary outlet should be designed to drain the entire detention volume within 72 h. A
restrictor plate should not be used. See the INDOT Standard Drawings.
An emergency overflow structure should also be added. The emergency overflow structure
should be placed in a location that will accept the extra flow. This may or may not outlet to the
design outfall. Usually, the emergency overflow structure takes the shape of a weir.
The area above the detention pond’s normal high-water elevation should be sloped towards the
pond. The bottom area of the pond should be graded toward the outlet to prevent standing water
conditions. A low-flow or pilot channel constructed across the facility bottom from the inlet to
the outlet should be used to convey low flow. See HEC-22, Chapter 8 for example problems and
more information.
The inflow rate is calculated using the Rational Method, regardless of the size of the drainage
area. Since the pond is retaining all of the runoff from the 1% annual EP, the outflow rate is
almost negligible, because infiltration and evaporation are the only available mechanisms for
drainage. To determine the infiltration rate, soil borings should be obtained to ensure accurate
calculations.
A retention pond also requires an emergency spillway. The emergency spillway should overflow
to an acceptable outlet. The pond should be sized to allow for 1 ft of freeboard below the
emergency spillway. If an acceptable emergency overflow outlet is not available, the pond
should be sized for 1.5 times the total volume required, plus 1 ft of freeboard.
A detention pond detains water from the entire drainage area. A roadside ditch detains water
only from additional pavement being added during construction. However, the methodology for
determining that volume remains the same. To detain the water in a roadside ditch, a berm
should be built upstream of the stream receiving the flow from the ditch. The outlet structure
diameter should not be smaller than 6 in. to prevent clogging. The berm should be constructed
with an overflow weir for a storm event that exceeds the design storm. For more information on
emergency overflow design, see HEC-22, Chapter 8. The capacity of the outfall may not allow
for a normal 1% annual EP inflow and 10% annual EP outflow situation. The release rate should
be considered, since the roadside ditch can be outletting upstream of existing structures.
An oversized storm-sewer system upsizes the pipes near the outlet of the system to provide extra
capacity. An oversized storm-sewer system uses larger round or deformed pipes to provide the
extra capacity, while inline detention uses vaults or boxes to provide the extra capacity.
An oversized storm sewer or inline detention should be designed in accordance with Section
203-4.0 for inlet spacing, water-spread calculations, trunk-line placement, and outlet tailwater
conditions. However, detention-routing calculations should be performed to ensure that a
sufficient amount of water is being detained. Gravity flow should be maintained for the 10%
annual EP. The 2% annual EP hydraulic-grade line should remain below the structure top
casting elevation. If local detention requirements require the 1% annual EP to be detained,
another hydraulic-grade-line check should be made, to ensure that the hydraulic-grade line
remains below the structure top casting elevation at the 1% annual EP. Since the velocity
through the oversized section is likely to be lower than the suggested minimum velocity,
sedimentation is a potential problem. Manholes should be oversized and placed more frequently
through the oversized section, to assist maintenance personnel in removing sediment from the
storm-sewer system.
Since inline detention is usually present near the outlet of the storm-sewer system, an emergency
overflow structure should be placed in the underground storage vault. This consists of a pipe
placed in the upper corner of the storage vault. A pipe of diameter of at least 6 in. should be
used to prevent the emergency overflow structure from clogging.
An infiltration trench is similar to anretention pond, except it is long and narrow and may work
within the right-of-way. An infiltration trench is lined with geotextiles and backfilled with
aggregate. The Rational Method should be used to calculate the inflow rate. The outflow rate
will then be determined based on the infiltration capacity of the soil. Only highly pervious soils
should be considered. The length of the system will depend on the volume required, given the
inflow and outflow rates. Only the volume of the pipe should be considered for storage. The
volume of the voids available in the backfilled trench should be ignored, to provide a factor of
safety. Larger pipes should be used, to allow for maintenance. An infiltration trench should be
constructed in accordance with Section 203-4.0. For additional information, see HEC-22,
Chapter 8 or Chapter 10.
A pump station requires electricity as well as regular maintenance for proper function. It
requires accessibility, monitoring, has limited capacity, and can be expensive. During a large
storm event, it can be prone to flooding and failure. For these reasons, use of a pump station is
discouraged by INDOT. However, because of topography or geometrics, it may become
necessary. If so, the Office of Hydraulics should be contacted and the design guidelines for a
pump station shown in HEC-24 should be followed.
203-5.06 Documentation
203-6.01 Introduction
An open channel is a natural or constructed conveyance for water in which the water surface is
exposed to the atmosphere and the gravity-force component in the direction of motion is the
driving force.
The types of open channels related to a transportation facility are stream channel, or artificial
channel or ditch.
The principles of open-channel-flow hydraulics are applicable to each drainage facility including
a culvert or a storm drain.
1. a natural channel with its size and shape determined by means of natural forces;
2. compound in cross section with a main channel for conveying low flow and a floodplain
to transport flood flow, and
3. shaped geomorphologically due to the long-term history of sediment load and water
discharge which it experiences.
An artificial channel can be a roadside channel, interceptor ditch, or drainage ditch which can be
a constructed channel with regular geometric cross section, and is unlined or lined with artificial
or natural material to protect against erosion.
Although the principles of open-channel flow are the same regardless of the channel type, a
stream channel and an artificial channel, primarily a roadside channel, will be addressed
separately herein.
203-6.02(01) Significance
Channel analysis is necessary for the design of a transportation drainage system to assess the
following:
203-6.02(02) Design
Hydraulic design associated with a natural channel or side ditch is a process which selects and
evaluates alternatives according to established criteria. These criteria are the standards
established to ensure that a highway facility satisfies its intended purpose without endangering
the structural integrity of the facility itself and without undue adverse effects on the environment
or the public welfare.
1. Channel design, or design of a highway facility that impacts a channel, should satisfy the
FHWA policies which are applicable to floodplain management if federal funding is
involved.
2. FEMA floodway regulations and USACE wetland restrictions for permits should be
satisfied.
3. NEPA regulations including the MOU for karst areas or other environmental MOU.
The most important factor in channel design is stability. Channel stability is the result of
controlling the effects of scour and siltation.
Design analysis of a natural or artificial channel should proceed according to the basic principles
of open-channel flow (see Chow, 1970; Henderson, 1966). The basic principles of fluid
mechanics, continuity, momentum, and energy can be applied to open-channel flow with the
additional complication that the position of the free surface is one of the unknown variables. The
determination of this unknown is one of the principal problems of open-channel flow analysis. It
depends on quantification of the flow resistance. A natural channel displays a wider range of
roughness values than an artificial channel.
HEC-20 Stream Stability at Highway Structures, and HDS-6 River Engineering for Highway
Encroachments, should be consulted. Additional references can be obtained through FHWA
hydraulics publications.
1. The hydraulic effects of floodplain encroachment should be evaluated for the 1% annual
EP, and other design-storm events as required, for a major highway facility.
2. If relocation of a stream channel is unavoidable, the cross-sectional shape, meander,
pattern, roughness, sediment transport, and slope should satisfy the existing conditions
insofar as practical. A means of energy dissipation may be necessary where existing
conditions cannot be duplicated. Coordination with the Environmental Services Division
will be necessary for stream channel relocation. See Section 203-3.0.
3. Stream-bank stabilization should be provided, where appropriate, as a result of a stream
disturbance such as encroachment. It should include both upstream and downstream
banks and the local site.
4. Provisions should be incorporated for access by maintenance personnel and equipment to
maintain features such as a dike or a levee.
5. Realignment or change to a natural channel should be minimized. The conditions that
warrant a channel change are as follows:
a. the natural channel crosses the roadway at an extreme skew;
b. the embankment encroaches on the channel; and
c. the location of the natural channel endangers the highway embankment or
adjacent property.
6. For channel clearing, see Section 203-3.03.
The hydraulic analysis of a channel determines the depth and velocity at which a given discharge
will flow in a channel of known geometry, roughness, and slope. The depth and velocity of flow
are necessary for the design or analysis of a channel lining or highway-drainage structure.
The step-backwater method is used to compute the complete water surface profile in a stream
reach to evaluate the unrestricted water-surface elevation for bridge hydraulic design, flood
easement, or a longitudinal encroachment. The step-backwater method is a calculation-intensive
iterative process that is suited for a computer application. HEC-RAS should be used. Other
programs may be used with prior authorization from the Office of Hydraulics.
The step-backwater method should be used for stream-channel analysis. The single-section
method will yield less-reliable results, as it requires more judgment and assumptions than the
step-backwater method. However, the single-section method should be used for analysis of a
standard roadway ditch, culvert, or storm-drain outfall.
A roadside channel is a channel, or side ditch, adjacent to the roadway which intercepts runoff
and groundwater within the right of way and transports its flow to drainage structures or to a
natural waterway. If a property owner has a pipe instead of an open ditch on the property, an
equivalent new pipe should be provided instead of an open ditch.
A median ditch, ditch in a cut section, or other critical ditch section should be checked to verify
that the water surface elevation from a 1% annual EP does not encroach onto the travel lane.
The criteria which apply to a roadside channel or other ditch are as follows.
1. Safety. Clear-zone requirements should be satisfied (see Chapter 49). Channel side
slopes should not exceed the soil or lining’s angle of repose, and should be 3H:1V or
flatter. See Chapter 49 for more information on the cross section of a roadside channel.
2. Design Discharge. The design discharge for a permanent roadside channel or channel
lining should be based on a 10% annual EP. If a natural stream or drainage ditch enters
the side ditch, the design should be for a 1% annual EP. A temporary lining should be
designed for a 50% annual EP.
5. Velocity. Figure 203-6A provides guidance regarding maximum allowable velocity for
natural stream-bed materials.
There can be a location where a stage-discharge relationship has already been measured in a
channel. This exists at a gaging station on a stream monitored by the USGS. Measured stage-
discharge curves will yield more accurate estimates of water-surface elevation, and should take
precedence over the analytical methods described below.
1. Cross Sections. Cross-sectional geometry of a stream is defined by coordinates of lateral
distance and ground elevation which locate individual ground points. The cross section is
taken normal to the flow direction along a single straight line where possible. In a wide
floodplain or bend, it may be necessary to use a section along intersecting straight lines,
i.e., a dog-leg section. The cross section should be plotted to reveal inconsistencies or
errors.
Cross sections should be subdivided with vertical boundaries where there are abrupt
lateral changes in geometry or roughness, such as in overbank flow. The conveyances of
each subsection are computed separately to determine the flow distribution and ά, and are
then added to determine the total flow conveyance. The subsection divisions should be
chosen so that the distribution of flow or conveyance is nearly uniform in each subsection
(Davidian, 1984). Selection of cross sections and vertical subdivision of a cross section
are shown in Figure 203-6B, Hypothetical Cross Section Showing Reaches, Segments,
and Subsections Used in Determining n Value.
2. Single-Section Analysis. This method, also known as the slope-area method, is a solution
of Manning’s equation for the normal depth of flow given the discharge and cross-section
properties including geometry, slope, and roughness. It assumes the existence of steady,
uniform flow. However, uniform flow rarely exists in either an artificial or natural
stream channel. Nevertheless, the single-section method is used to design an artificial
channel for uniform flow as a first approximation, and to develop a stage-discharge rating
curve in a stream channel for tailwater determination at a culvert or storm-drain outlet.
a. Select the typical cross section at or near the location where the stage-discharge
curve is required.
c. Estimate the water-surface slope. Because uniform flow is assumed, the average
slope of the streambed can be used.
f. After the discharge has been calculated at several incremental elevations, plot the
stage versus discharge. This plot is the stage-discharge curve, and it can be used
to determine the water-surface elevation corresponding to the design discharge or
other discharges of interest.
g. Perform the multi-section analysis using HEC-RAS due to the complexity of the
calculations.
The selection of a roadside-channel lining should reflect both initial costs and long-term
maintenance costs. The channel lining should be selected based on the method of allowable
tractive force. This is discussed in Section 203-6.05 Roadside Channel or Other Ditches. The
following provides the procedure for roadside-channel lining. However, the use of these criteria
should be confirmed using the lining-selection methodology described in Section 203-6.05.
1. Seeded Channel, G < 1%. A seeded channel is protected from erosion by means of fast-
growing permanent seeding. This type of channel has the advantage of being low in
initial cost and maintenance, aesthetically pleasing, and compatible with the natural
environment. The use of an erosion control mat, e.g., straw, coconut fiber, is encouraged
to help establish seed growth.
3. Paved Channel, G ≥ 3%. A paved concrete ditch can be resistant to erosion. Its principal
disadvantages are its high maintenance and initial costs, susceptibility to failure if
undermined by scour, and the tendency for scour to occur downstream due to an
acceleration of flow. A paved channel is less desirable for a rural setting. However, it
can be appropriate in a select urban location. The INDOT Standard Drawings illustrate
the standard paved channels. Type A through H is used where the toe of the ditch is
outside of the clear zone. Type J through M is used where the toe of the ditch is inside
the clear zone. For Type J through M, the 6H:1V side slope should be placed nearest to
the roadway. The INDOT Standard Drawings also indicate the type of paved channel
that should be used based on the diameter of the pipe at the outlet and inlet.
b. Cut-Off Wall. A cut-off wall is required at the beginning and end of each paved
side ditch.
c. Lug. A lug has been proven to prevent sliding on a steep slope. A lug should be
provided at the locations as follows:
4. Riprap-Lined Channel, 3% G 10%. A riprap lining is effective for this slope range,
depending on the design flow of the channel. However, riprap should be used on a slope
steeper than 10% at a bridge cone. It is also appropriate to use riprap in a ditch where the
grade is flatter than 3%. For example, if there is a hill in the ditch watershed, riprap
should be placed to dissipate energy and minimize ditch erosion. A mild slope is
constructed by means of dumping riprap into a prepared channel lined with geotextile
filter cloth and grading to the desired shape. The advantages are low construction and
maintenance costs and self-healing characteristics. Riprap has a limited application on a
steep slope where the flow will tend to displace the lining material.
One of the hazards of placing a highway near a river or stream channel or other water body is the
potential for erosion of the highway embankment due to moving water. If erosion of the
highway embankment is to be prevented, bank protection should be anticipated. The proper type
and amount of protection should be provided in the appropriate locations.
The available methods of protecting a highway embankment from bank erosion are as follows:
This Section provides procedures for the design of revetment to be used as channel-bank
protection, and channel lining on a stream or river with a design discharge greater than 50 cfs.
Procedures are also provided for riprap protection at a bridge pier or abutment. For a small
discharge, the procedures provided in Chapter 202 should be used. Rock riprap revetment
should be used due to its low cost, environmental considerations, flexible characteristics, and
widespread acceptance. Other channel-stabilization methods such as a spur, guide-bank retard
structure, longitudinal dike, and bulkhead are discussed in Hydraulic Engineering Circular No.
20, Stream Stability at Highway Structures and Hydraulic Engineering Circular No. 23, Bridge
Scour and Stream Instability Countermeasures.
Channel and bank stabilization is essential to the design of a structure affected by the water
environment. The identification of the potential for bank erosion, and the subsequent need for
stabilization, is best accomplished through observation. A three-level analysis procedure is
provided in HEC-20. The three-level analysis provides a procedure for determining the
geomorphological characteristics, evaluating the existing conditions through field observations,
and determining the hydraulic and sediment transport properties of the stream. If sufficient
information is obtained at a given level of the analysis to solve the problem, the procedure may
be stopped without proceeding to the other levels.
Observations provide the most positive indication of erosion potential. Observation comparison
can be based on historic information or current site conditions. Aerial photographs, old maps,
surveying notes, bridge-design files, and river-survey data are available from the Office of
Hydraulics and FHWA. Gaging-station records and interviews of long-time residents can
provide documentation of recent and potentially current channel movement or bank instabilities.
Current site conditions can be used to evaluate stability. If historic information indicates that a
bank has been relatively stable in the past, local conditions can indicate more recent instabilities.
Local site conditions which are indicative of instabilities can include tipping and falling of
vegetation along the bank, cracks along the bank surface, the presence of slump blocks, fresh
vegetation lying in the channel near the channel banks, deflection of channel flows in the
direction of the bank due to a recently-deposited obstruction or channel-course change, fresh
vertical face cuts along the bank, locally high velocity along the bank, new bar formation
downstream from an eroding bank, local head-cuts, impending or recent cutoffs, etc. The
presence of one of these conditions does not in itself indicate an erosion problem. Bank erosion
is common in each channel if the channel is stable.
Prior to designing a bank-stabilization scheme, the common erosion mechanisms and revetment-
failure modes, and the causes or driving forces behind bank erosion processes should be known.
Inadequate recognition of potential erosion processes at a particular site can lead to failure of the
revetment system. Many causes of bank erosion and revetment failure have been identified. The
more-common causes include abrasion, debris flows, water flow, eddy action, flow acceleration,
unsteady flow, freeze-and-thaw, human actions on the bank, ice, precipitation, waves, toe
erosion, and subsurface flow. However, a combination of mechanisms can cause bank or
revetment failure. The actual mechanism or cause is difficult to determine. Failures are
classified as follows.
1. Particle Erosion: Particle erosion is the most commonly considered erosion mechanism.
Particle erosion results if the tractive force exerted by the flowing water exceeds the bank
material’s ability to resist movement. If displaced stones are not transported from the
eroded area, a mound of displaced rock will develop on the channel bed. The mound has
been observed to cause flow concentration along the bank, resulting in further bank
erosion.
1. Revetment Types.
f. Soil Cement. Soil cement consists of a dry mix of sand, cement, and admixtures
batched in a central mixing plant. It is transported, placed with equipment
capable of producing the width and thickness required, and compacted to the
required density. Control of the moisture and time after introduction of the
mixing water is critical. Curing is required. This results in a rigid protection.
Soil cement can be placed either as a lining or in stepped horizontal layers. The
stepped horizontal layers are stable, provided that toe scour protection has been
incorporated into the design.
2. Design Discharge. The design flow rate for the design or analysis of a highway structure
in the vicinity of a river or stream has a 10% to 1% annual EP. This discharge level will
also be applicable to the design of a revetment system. However, a lower discharge can
produce hydraulically-worse conditions with respect to riprap stability. Discharge levels
should be evaluated to ensure that the design is adequate for all discharge conditions up
to that selected as the design discharge for a structure associated with the riprap scheme.
The design relationships described herein are based on the assumption of uniform, steady,
subcritical flow. The relationships are also valid for gradually-varying flow conditions.
Although the individual hydraulic relationships are not in themselves applicable to
rapidly-varying, unsteady, or supercritical flow conditions, procedures are provided for
extending their use to these flow conditions. See Section 203-6.06(04) for more
information related to channel design.
5. Flow in Channel Bend. The increased velocity and shear stress that are generated as a
result of non-uniform flow should be considered on the outside of a bend. Superelevation
of flow in a channel bend should be considered in the revetment design. For a channel
with overbank flow, the revetment should extend to top of bank. For a channel where the
flow remains within the banks, the revetment should extend up the banks to provide a
freeboard of at least 1 ft. For guidance in the design of channels in a bend, see HEC-15
and HDS-4.
6. Flow Resistance. The hydraulic analysis performed as a part of the revetment design
process requires the estimation of Manning’s roughness coefficient. Physical
characteristics upon which the resistance equations are based include the channel-base
material, surface irregularities, variations in section geometry, bed form, obstructions,
vegetation, channel meandering, flow depth, and channel slope. Seasonal changes in
these factors should also be considered.
7. Extent of Protection. This refers to the longitudinal and vertical extent of protection
required to adequately protect the channel bank.
Many site-specific factors have an effect on the actual length of bank that should
be protected. The above criteria are difficult to apply on a mildly-curving bend or
on a channel having irregular, non-symmetric bends. Other channel controls such
as bridge abutments can produce a stabilizing effect on the bend so that only a
part of the channel bend should be stabilized. The magnitude or nature of the
flow event can cause erosion problems only in a localized portion of the bend,
requiring that only a short channel length be stabilized. Therefore, the above
criteria should be used only as a starting point. Additional analysis of site-
specific factors is necessary to define the actual extent of protection required.
(1) Design Height. The design height of a riprap installation should be equal
to the design high-water elevation plus an allowance for freeboard.
Freeboard is provided in a causeway situation to ensure that the desired
degree of protection will not be reduced due to unaccounted factors,
including the following:
1. Rock Riprap. Guidelines are provided for bank slope, rock size, rock gradation, riprap
layer thickness, and edge treatment. The guidelines apply equally to rock or rubble
riprap.
b. Rock Size. The stability of a particular riprap particle is a function of its size,
expressed either in terms of its weight or equivalent diameter. See the INDOT
Standard Specifications and Figure 203-2D which relates the required riprap class
to the velocity.
(2) Wave Erosion. See Highway Engineering Circular 23, Volume 2, Design
Guide 17 for guidance if wave erosion is anticipated.
(3) Ice Damage. Ice can affect riprap linings. Moving surface ice can cause
crushing and bending forces and large impact loadings. The tangential
flow of ice along a riprap-lined channel bank can also cause excessive
shearing forces. Quantitative criteria for evaluating the impact ice has on
a channel-protection scheme are unavailable.
c. Rock Gradation. The gradation of stones in riprap revetment affects the riprap’s
resistance to erosion. The stone should be well-graded throughout the riprap-
layer thickness. The gradation limits appear in the INDOT Standard
Specifications.
d. Layer Thickness. All stones should be contained within the riprap-layer thickness
to provide maximum resistance against erosion. For guidance, see the INDOT
Standard Specifications.
f. Edge Treatment. The riprap-revetment flanks, toe, and head require a treatment
to prevent undermining. The flanks should be designed as illustrated in Figure
203-6J. The upstream flank is illustrated in section (a) and the downstream flank
in section (b). A more constructible flank section uses riprap rather than
compacted fill.
Where a toe trench cannot be dug, the riprap blanket should terminate in a thick,
stone toe at the level of the streambed. The toe material should not mound and
form a low dike. A low dike along the toe can result in flow concentration along
the revetment face which can stress the revetment to failure. The channel's design
capability should not be impaired due to placement of too much riprap in a toe
mound.
The size of the toe trench or the alternate stone toe is controlled by the anticipated
depth of scour along the revetment. As scour occurs, the stone in the toe will
launch into the eroded area as illustrated in Figure 203-6L. Observation of the
performance of this type of rock toe indicates that the riprap will launch to a final
slope of approximately 2H:1V.
The volume of rock required for the toe should be equal to or exceed 1.5 times the
volume of rock required to extend the riprap blanket at its design thickness and on
a slope of 2H:1V, to the anticipated depth of scour. Dimensions should be based
on the required volume using the thickness and depth determined from the scour
evaluation. The alternate location can be used if the amount of rock required does
not constrain the channel.
A rock-and-wire-mattress revetment consists of flat wire baskets or units filled with rock
that are laid end to end and side to side on a prepared channel bed or bank. The
individual mattress units are wired together to form a continuous revetment mattress.
A stacked-block gabion revetment consists of rectangular wire baskets which are filled
with stone and stacked in a stepped-back fashion to form the revetment surface. It is
commonly used at the toe of an embankment slope as a toewall, which helps to support
other upper-bank revetments and prevents undermining.
(2) Bank and Foundation Preparation. The channel bank should be graded to
a uniform slope. The graded surface, either on the slope or on the
streambed at the toe of the slope on which the rock-and-wire mattress is to
be constructed, should not deviate from the specified slope line by more
than 6 in. Blunt or sharp objects such as rocks or tree roots protruding
from the graded surface should be removed.
(4) Stone Size. The maximum stone size should not exceed the thickness of
the individual mattress units. The stone should be well-graded within the
sizes available. Seventy percent of the stone, by weight, should be slightly
larger than the wire-mesh opening. For commercially-available units, the
wire-mesh opening sizes are listed in Figure 203-6 O.
(5) Stone Quality. The stone should satisfy the quality requirements for
dumped-rock riprap.
Galvanized wire baskets can be safely used in fresh water or where the pH
of the liquid in contact with it is not greater than 10. For minimum
coating weight, see Figure 203-6Q.
(7) Edge Treatment. The toe, head, and flanks of a rock-and-wire mattress
revetment installation require treatment to prevent damage from
undermining. Figure 203-6M illustrates the possible toe-treatment
configurations. If a toe apron is used, its projection should be 1.5 times
the expected maximum depth of scour in the vicinity of the revetment toe.
Where little toe scour is expected, the apron can be replaced with a single-
course gabion toewall. This helps to support the revetment and prevents
undermining. Where an excessive amount of toe scour is anticipated, both
an apron and a toe wall can be used.
(8) Filter Design. Individual mattress units will act as a crude filter and a
pavement unit if filled with overlapping layers of hand-size stones.
However, the need for a filter should be investigated. If necessary, a layer
of permeable membrane cloth, or geotextile, woven from synthetic fibers,
or a gravel layer of thickness of 4 to 6 in. should be placed between the
silty bank and the rock-and-wire-mattress revetment to further inhibit
washout of fines.
(2) Size and Configuration. The common commercial sizes are listed in
Figure 203-6 O. The most common size used is that of width and depth of
3 ft. A thickness of less than 1 ft is not practical.
(3) Edge Treatment. The upstream and downstream flanks of the revetment
should include counterforts. See Figure 203-6 S detail (a). The
counterforts should be placed 12 to 18 ft from the upstream and
downstream limits of the structure, and should extend a minimum of 12 ft
into the bank.
The toe of the revetment should be protected by means of placing the base
of the gabion wall at a depth below the anticipated scour depth. Where it
is difficult to predict the depth of expected scour, or where channel-bed
fluctuations are common, a mattress apron should be used. The minimum
apron length should be equal to 1.5 times the anticipated scour depth
below the apron. This length can be increased in proportion to the level of
uncertainty in predicting the local toe-scour depth.
(1) Mattress And Block Size. The overall mattress size is dictated by the
longitudinal and vertical extent required of the revetment system. An
articulated block mattress is assembled in sections prior to placement on
the bank. The size of individual blocks is variable. Manufacturers have a
number of standard sizes of a particular block available. Manufacturers’
literature should be consulted in selecting an appropriate block size for a
given hydraulic condition.
(3) Edge Treatment. The toe, head, and flanks require treatment to prevent
undermining. Toe treatment includes an apron as illustrated in Figures
203-6T and 203-6W, or a toe-trench as illustrated in Figures 203-6U and
203-6V. As a minimum, a toe apron should extend 1.5 times the
anticipated scour depth in the vicinity of the bank toe. If a toe trench is
used, the mattress should extend to a depth greater than the anticipated
scour depth in the vicinity of the bank toe.
The edges can be terminated at grade as shown in Figures 203-6T, 203-
6U, and 203-6W, or in a termination trench. A termination trench should
be used in silty or sandy soil, for a high-velocity flow, or where failure of
the revetment results in significant economic loss. A termination trench
provides more protection against failure from undermining and
outflanking than an at-grade termination. However, where upper-bank
erosion or lateral outflanking is not expected to be a problem, a grade
termination can provide an economic advantage.
(4) Filter. Prior to installing the mats, a geotextile filter fabric should be
installed on the bank to prevent bank material from leaching through the
openings in the mattress structure. Although a fabric filter is
recommended, graded filter material can be used if it is properly designed
and installed to prevent movement of the graded material through the
protective mattress.
Partially grouted riprap should extend from below the anticipated channel-bed scour
depth to the design high-water level, plus additional height for freeboard.
a. Bank and Foundation Preparation. The graded surface should not deviate from
the specified slope line by more than 6 in. However, a local depression larger
than this can be accommodated because initial placement of filter material or rock
for the revetment will fill the depression.
b. Bank Slope. The bank slope should not be steeper than 1.5H:1V. The Office of
Geotechnical Services should be consulted for guidance.
c. Edge Treatment. The head, toe, and flanks require treatment to prevent
undermining. The revetment toe should extend to a depth below anticipated scour
depths or to bedrock. The toe should be designed as illustrated in Figure 203-6Y,
Grouted Riprap Sections, detail (a). The grout-free riprap provides extra
protection against undermining at the bank toe. Edge-treatment configurations
are illustrated in Figure 203-6Y.
(1) Type 1. Two layers of nylon fabric are woven together at 5 in. to 10 in.
centers as indicated in Figure 203-6Z. These points of attachment serve as
filter points to relieve hydrostatic uplift caused due to percolation of
groundwater through the underlying soil. The finished revetment has a
deeply-cobbled or quilted appearance. Mat thickness averages from 2 to 6
in.
(2) Type 2. Two layers of nylon or polypropylene woven fabric are joined
together at spaced centers by means of interwoven tie cords, the length of
which controls the thickness of the finished revetment. See Figure 203-
6AA. Plastic tubes can be inserted through the two layers of fabric prior
to grout injection to provide weep holes for relief of hydrostatic uplift.
The finished revetment is of uniform cross section and has a lightly-
pebbled appearance. Mat thickness averages from 2 to 10 in.
(3) Type 3. Two layers of nylon fabric are interwoven into rectangular block
patterns. The points of interweaving serve as hinges to permit articulation
of the hardened concrete blocks. The revetment is reinforced with steel
cables or nylon rope threaded between the two layers of fabric prior to
grout injection and remains embedded in the hardened cast-in-place
blocks. Block thickness is controlled with spacer cords in the center of
each block.
Use of soil-cement does not require further design considerations for the embankment.
Proper embankment design procedures should be followed based on individual project
conditions, to prevent subsidence or other type of embankment distress.
a. Top, Toe, and End Features. All extremities of the facing should be tied into non-
erodible sections or abutments. Adequate freeboard and the carrying of the soil-
cement to the paved roadway, plus a lower section as shown in Figure 203-6BB,
will minimize erosion from behind the crest and under the toe of the facing. The
ends of the facing should terminate smoothly in a flat slope or against a rocky
abutment. A small amount of rock riprap can be placed over and adjacent to the
edges of the soil-cement at its contact with the abutment.
(2) arbitrarily assuming the weight of the facing sufficient to resist uplift
pressures that may develop; and
(3) providing free drainage behind, through, or under the soil-cement facing to
prevent adverse hydrostatic pressure.
203-7.0 REFERENCES
1. AASHTO Highway Drainage Guidelines, Hydraulic Analyses for the Location and
Design of Bridges, AASHTO Task Force on Hydrology and Hydraulics, 2007.
2. AASHTO, Model Drainage Manual, Chapter Ten, Bridges.
3. Abt, S.R., Donnell, C.A., Ruff, J.F., and Doehring, F.K., Culvert Shape and Slope Effects
on Outlet Scour, Transportation Research Record 1017, 1985.
4. ASCE Journal of the Hydraulics Division, Hydraulic Design of Stilling Basins, paper
1406, October 1957.
5. Blaiswell, F.W., SAF Stilling Basin, U.S. Government Printing Office, 1959.
6. Bradley, J.N., Hydraulics of Bridge Waterways, HDS 1, Federal Highway
Administration, 1978.
7. Brater, E. F. and King, H.W., Handbook of Hydraulics, 6th ed., New York: McGraw Hill
Book Company, 1976.
8. Brown, S.A., Design of Riprap Revetment, FHWA, Hydraulic Engineering Circular No.
11 (HEC 11), IP-89-016, Washington, DC 20590, 1989.
9. Bureau of Reclamation, Hydraulic Design of Stilling Basins and Energy Dissipators,
Engineering Monograph No. 25, third printing, 1974.
10. Chow, C. N., Open Channel Hydraulics, New York: McGraw Hill Book Company, 1959.
11. Corry, M.L., Jones, J.S., and Thompson, P.L., The Design of Encroachments on
Floodplains Using Risk Analysis, Hydraulic Engineering Circular No. 17, Federal
Highway Administration, Washington, D.C., 1980.
12. Corry, M.L., Jones, J.S., Thompson, P.L., Watts, F.J., and Richards, D.L., Hydraulic
Design of Energy Dissipators for Culverts and Channels, FHWA, Hydraulic Engineering
Circular Number 14 (HEC-14), Chapter 5, 1983, Revised 2006.
13. Federal Highway Administration, Bridge Scour and Stream Instability Countermeasures:
Experience, Selection, and Design Guidance–Third Edition Hydraulic Engineering
Circular No. 23, September 2009.
14. Federal Highway Administration, Design of Roadside Channels with Flexible Linings,
Hydraulic Engineering Circular No. 15, September 2005.
15. Federal Highway Administration, Evaluating Scour at Bridges, HEC 18, 2012.
16. Federal Highway Administration, Geosynthetic Design and Construction Guidelines,
FHWA-HI-95-038.
17. Federal Highway Administration, Hydraulic Design of Highway Culverts, Hydraulic
Design Series No. 5, FHWA-NHI-01-020, FHWA, Washington, D.C., 2001, Rev. May
2005.
18. Federal Highway Administration, Introduction to Highway Hydraulics, Hydraulic Design
Series No. 4, June 2008.
19. Federal Highway Administration, River Engineering for Highway Encroachments,
Hydraulic Design Series No. 6, December 2001.
20. Federal Highway Administration, Stream Stability at Highway Structures, HEC 20, 2012.
21. Federal Highway Administration, Urban Drainage Design Manual, Hydraulic
Engineering Circular No. 22. FHWA NHI-10-009, U.S. Department of Transportation,
Washington, D. C., 2009.
22. Holtz, R.D., Christopher, B.R., and Berg, R.R., Geosynthetic Design & Construction
Guidelines, Participant Notebook, National Highway Institute, US Department of
Transportation, Federal Highway Administration, July 29, 1994 Draft.
23. Ginsburg, A., HY8 Culvert Analysis Microcomputer Program, Applications Guide,
FHWA, EPD-87-101; and software available from McTrans Center, 512 Weil Hall,
University of Florida, Gainsville, FL 32611.
24. McBridge, M.C., and Sternberg, Y.M., Stormwater Management Infiltration Structures,
Publication No. FHWA-MS-83/04, Baltimore, Md., 1983.
25. Reihsen, G., and Harrison, L.J., Debris Control Structures, FHWA, Hydraulic
Engineering Circular Number 9 (HEC 9), Washington, DC 20590, 1971, Revised 2005.
26. Ruff, J.F., Abt, S.R., Mendosa, C., Shaikh, A., and Kloberdanz, R., Scour at Culvert
Outlets in Mixed Bed Materials, FHWA, RD-82-011, September 1982.
27. Sandvik, A., Proportional Weirs for Stormwater Pond Outlets, Civil Engineering ASCE,
pp. 54-56, March 1985.
28. Schueler, T.R., Controlling Urban Runoff: A Practical Manual for Planning and
Designing Urban BMPs, Washington, D.C., Metropolitan Washington Council of
Governments, 1987.
29. Sowers, G.B. and Sowers, G.F., Introductory Soil Mechanics and Foundations, 3rd ed.,
New York: MacMillan Publishing Company, 1970.
30. Spangler, M.G. and Handy, R.L., Soils Engineering, 4th ed., New York: Harper & Row,
1982.
31. Stevens, M.A. and Simons, D.B., Experimental Programs and Basic Data for Studies of
Scour in Riprap at Culvert Outfalls, Colorado State University, CER 70-7-MAS-DBS-57,
1971.
32. Stormwater Management Manual – Volume 2 Procedures, Metropolitan Government of
Nashville and Davidson County. The EDGE Group, Inc., and CH2M Hill, July 1988.
33. U.S. Army Corps of Engineers, Design of Coastal Revetments, Seawalls, and Bulkheads,
Engineering Manual EM-1110-2-1614., April 1985.
34. U.S. Army Corps of Engineers, HEC-RAS, River Analysis System, User’s Manual, Draft
Version 2.2, September 1998.
35. Wong, S.L. and McCuen, R.H., The Design of Vegetative Buffer Strips for Runoff and
Sediment Control in Stormwater Management in Coastal Areas, Annapolis, Maryland,
Department of Natural Resources, 1982.
36. Wycuff, R.L. and Singh, U.P., Preliminary Hydrologic Design of Small Flood Detention
Reserviors, Water Resources Bulletin, Vol. 12, No. 2, pp. 337-49, 1976.
37. Yim, C.S. and Sternberg, U.M., Development and Testing of Granular Filter Design
Criteria for Stormwater Management Infiltration Structures, Baltimore, Maryland,
Department of Transportation, 1987.
38. Young, G.K. and Krolak J.S., HYDRAIN Integrated Drainage Design Computer System,
Volumes 1-6, FHWA, RD-88-120, 1987.
39. Yu, S.L., Norris, W.K, and Wyant, D.C., Urban BMP Demonstration Project of the
Albemarle/Charlottesville Area, Report No. UDA/530358/CZ88/102, Charlottesville,
University of Virginia, 1987.
Concrete slabs
Clear span
less than 20 ft
less than 20 ft
Clear span
less than 20 ft
X X X
Y Y
X Y X
Figure 203-2A
Back
Structure Minimum Circular- Minimum Deformed-
Application Pipe Size Pipe Area
Drive 15 in. 1.1 ft2
Mainline or Public-Road
15 in. 1.1 ft2
Approach (2 lanes)
Mainline or Public-Road
36 in. 6.7 ft2
Approach (≥ 3 Lanes)
Figure 203-2B
Back
Bridge, Culvert,
Allowable Roadway Service-
Functional Allowable Allowable
Backwater, Serviceability, ability
Classification Velocity, Velocity,
Annual EP Annual EP Freeboard *
Annual EP Annual EP
Freeway 1% 1% 2 ft 1% 2%
Ramp 1% 1% 0 ft 1% 2%
Non-Freeway,
1% 1% 2 ft 1% 2%
4 or More Lanes
Two-Lane Facility,
1% 1% 1 ft 1% 2%
AADT > 3000
Two-Lane Facility,
1000 < AADT ≤ 1% 4% 0 ft 1% 4%
3000
Two-Lane Facility,
1% 10% 0 ft 1% 10%
AADT ≤ 1000
Drive 1% 10% 0 ft 1% 10%
DESIGN-STORM FREQUENCY
FOR BRIDGE OR CULVERT
Figure 203-2C
(Page 1 of 2)
Back
Backwater
Roadway Service- Allowable
Functional Design
Serviceability, ability Velocity,
Classification Storm,
Annual EP Freeboard * Annual EP
Annual EP
Freeway 1% 4% 0 ft 10%
Non-Freeway,
1% 10% 0 ft 10%
4 or More Lanes
Two-Lane Facility,
1% 10% 0 ft 10%
AADT > 3000
Two-Lane Facility,
1000 < AADT ≤ 1% 50% 0 ft 50%
3000
Two-Lane Facility,
1% 50% 0 ft 50%
AADT ≤ 1000
DESIGN-STORM FREQUENCY
FOR TEMPORARY STRUCTURE
Figure 203-2C
(Page 2 of 2)
Back
Erosion-Protection Method Velocity, v (ft/s)
Revetment Riprap 6.5
Class 1 Riprap 6.5 < v < 10
Class 2 Riprap 10 v 13
Energy Dissipator > 13
Note: If clear-zone or other issues prohibit the use of the required erosion-protection method, the
Office of Hydraulics should be contacted for additional instructions.
Figure 203-2D
Back
Structure Sump Required Sump Required Sump Required
Diameter for Stream Bed for Stream Bed for Stream Bed
or Span, S (ft) of Sand (in.) of Other Soil (in.) of Rock or Till (in.)
<4 6 3 3
4 ≤ S < 12 12 6 3
12 ≤ S < 20 18 12 3
Figure 203-2E
Back
Type of Conduit Wall Description Manning’s n
Concrete Pipe Smooth Interior 0.012
Concrete Box Smooth Walls 0.012- 0.015
2.75 in. x 0.5 in Corrugations 0.024
6 in. x 1 in. corrugations 0.022-0.025
Corrugated Metal Pipe or Arch, 5 in. x 1 in. corrugations 0.025-0.026
Annular or Helical Pipe 3 in. x 1 in. corrugations 0.027-0.028
6 in. x 2 in. structural plate 0.033-0.035
9.25 in. x 2.5 in. structural plate 0.033-0.037
Thermoplastic/HDPE Pipe Smooth Interior 0.012
Cured in Place Liner (CIPP) Smooth Interior 0.012
Note: The value indicated in this table is the recommended Manning’s n design value. The
actual field value for an older, existing pipeline may vary depending on the effects of
abrasion, corrosion, deflection and joint conditions. A concrete pipe with poor joints and
deteriorated walls may have an n value of 0.014 to 0.018. A corrugated metal pipe with
joint and wall problems may also have a higher n value, and may experience shape
changes which can adversely affect the general hydraulics characteristics of the culvert.
Figure 203-2F
Back
FREQUENCY FOR COINCIDENTAL OCCURRENCE
AREA 10-Year Design 100-Year Design
RATIO MAIN MAIN
TRIBUTARY TRIBUTARY
STREAM STREAM
1 10 2 100
10 000 to 1
10 1 100 2
2 10 10 100
1000 to 1
10 2 100 10
5 10 25 100
100 to 1
10 5 100 25
10 10 50 100
10 to 1
10 10 100 50
10 10 100 100
1 to 1
10 10 100 100
Source: HEC-22, Table 7-3.
Pipe, Concrete
Mitered to conform to fill slope ...........................................................................0.7
*End-Section conforming to fill slope .................................................................0.5
Projecting from fill, square cut end......................................................................0.5
Headwall or headwall and wingwalls,
Square-edged..................................................................................................0.5
Rounded, radius = 1/12D ...............................................................................0.2
Socket end of pipe, grooved...........................................................................0.2
Projecting from fill, socket end, grooved.............................................................0.2
Beveled edges, 33.7-deg or 45-deg bevels...........................................................0.2
Side- or slope-tapered inlet ..................................................................................0.2
* An end section conforming to the fill slope, made of either metal or concrete, is the section
commonly available from manufacturers. From limited hydraulic tests, it is equivalent in
operation to a headwall in both inlet and outlet control. An end section incorporating a closed
taper in its design may have a superior hydraulic performance. Such a section can be designed
using the information shown for the beveled inlet.
ENTRANCE-LOSS COEFFICIENT
Outlet Control, Full or Partly Full
Figure 203-2H
Back
End-Treatment Type Entrance Type KE
Grated Box End Section, Concrete Pipe, headwall
0.5
Type 1 with square edge
Grated Box End Section, Concrete Pipe, headwall
0.5
Type 2 with square edge
Multiple-Pipes Concrete Concrete Pipe, projecting
0.5
Anchor from fill, square cut end
Multiple-Pipes Concrete Corrugated Metal Pipe,
0.9
Anchor Projecting from fill
Corrugated Metal Pipe,
Metal Pipe End Section end section conforming 0.5
to fill slope
Precast-Concrete End Concrete Pipe, end section
0.5
Section conforming to fill slope
Corrugated Metal Pipe,
Safety Metal End Section mitered to conform 0.7
to fill slope
Corrugated Metal Pipe,
Safety Metal End Section end section conforming 0.5
to fill slope
Corrugated Metal Pipe,
Safety Metal End Section mitered to conform 0.7
to fill slope
Corrugated Metal Pipe,
Safety Metal End Section end section conforming 0.5
to fill slope
Single-Pipe Concrete Corrugated Metal Pipe,
0.9
Anchor projecting from fill
Single-Pipe Concrete Concrete Pipe, projecting
0.5
Anchor from fill, square cut end
Single-Pipe Concrete Corrugated Metal Pipe-Arch,
0.9
Anchor projecting from fill
Multiple-Pipe Concrete Concrete Pipe-Arch, projecting
0.5
Anchor from fill, square cut end
Multiple-Pipe Concrete Corrugated Metal Pipe-Arch,
0.9
Anchor projecting from fill
Figure 203-2 I
Back
4 D0 Min.
or to R/W
D0 3 D0 5 D0
d
0f
n.
boar
ee
See Note A
mi
1.
Top of berm,
r
f
top of riprap See Note B Top of natural
channel
y TW
e
1V
:2H h 2H
s Horiz. 1V:
2d or 2d or
50 50
3d or 1.5d
50 max. 2d or 1.5d 1.5d
50 max. max. Thickened or sloping toe
1.5 ft min.
1.5d optional. Construct if
max. SECTION
downstream channel
A degradation is anticipated.
C B
m
r See Note B
D Be
a
rp
i
frp
po
To
2H
1V:
te
2H
xma
i
o r
1V:
pr e
t
Ap fw
a NOTE:
eo
2H
t dg
o e W = Diameter for pipe
n
1V:
p a
ra n Apron culvert
p ow
i
R sh 1 W = Barrel width for
b
3 1V:2H Symm. box culvert
W
0
D B A
2 C
HALF PLAN
See Note B.
hs Berm
2d or 1.5d
50 max.
2d or 1 W
0
SEC. C-C
50
1.5d 2 2
max.
NOTE A: If exit velocity of basin is specified, extend basin as requried to obtain sufficient cross-sectional
area at Section A-A such that Q / (Cross section area at Sec. A-A) = Specified exit velocity.
des
NOTE B: Warp basin to conform to natural stream channel. Top of riprap in floor of basin should be at
the same elevation or lower than natural channel bottom at Sec. A-A.
D50 15hS
Basin length is the
larger of:
Froude No., Fr 4Wo
hS/D50
2 < hS/D50 < 4
Equivalent depth, dE
TW/dE
DE = (4Ac/π)0.5
Figure 203-2L
Back
Culvert brink
3
0.
=
c
/y
4
0.
NOTE: 2 = h / d = 4
50
s 50
=
d
c
y
=
/
21
50
If TW/Y > 0.75, then
0.
d
0
riprap may be required on
=
2
31
5
0.
banks and channel bottom
0.
=
downstream from basin.
y
c
6
e
s
0.
/
h
50
=
RELATIVE DEPTH OF SCOUR HOLE,
y
c
=
/
41
0.
50
d
.7
=
0
51
=
0.
y
c
/
.2
0
d
5
= 0
=
1
.6
c
/y
1
50
d
1=
0.
1 2 3
v
ave
FROUDE NUMBER =
(g) (Y )
e
Figure 203-2M
Back
1.0
0.9
0.8
0.7
Vave
0.3
0.2
NOTE: For partially full circular section or non-circular brink areas, convert wetted
cross sectional areas to an equivalent circular area with diameter W.
0.1
1 2 3 4 5 6 7 8 9 10 20 30 40 50
W Q V TW
O ave
3
SYM (ft) (ft /s) (ft/s) (ft)
23 15.09 1.61 NOTE: To be used for predicting channel velocities downstream from
1.44
culvert outlets where high tailwater prevails.
1.44 14 10.30 1.61
Figure 203-2 O
Back
Case Freeboard Specified Acceptable Structure Alternates to be Shown on Plans
1 ≥ 1 ft Flat-topped, arch-topped, true-arch
2 < 1 ft Those indicated in hydraulics recommendation letter
DETERMINATION OF ACCEPTABLE
THREE-SIDED-STRUCTURE ALTERNATES
Feet Inches Feet Inches
12 144 24 288
13 156 25 300
14 168 26 312
15 180 27 324
16 192 28 336
17 204 29 348
18 216 30 360
19 228 32 384
20 240 34 408
21 252 36 432
22 264 42 504
23 276 48 576
THREE-SIDED STRUCTURE
PERPENDICULAR-SPAN DESIGNATIONS
Feet Inches Feet Inches
4 48 10’-4” 124
5 60 10’-8” 128
6 72 11’ 132
7 84 11’-4” 136
8 96 11’-8” 140
9 108 12 144
10 120 --- ---
THREE-SIDED-STRUCTURE
RISE DESIGNATIONS
Figure 203-2R
Back
MIN. AVG. MAX. AVG. RIPRAP
RIPRAP BASE-SLAB
STREAM STREAM AT OUTSIDE
AT CONCRETE
VELOCITY VELOCITY CURVED BEND
STR. AT STR.
ft/s ft/s IN CHANNEL
n/a ≤ 6.5 Revetment Class 1 n/a
> 6.5 < 10 Class 1 Class 2 n/a
≥ 10 < 13 Class 2 Base Slab Class B
≥ 13 n/a Base Slab Base Slab Class B
Note: The maximum average stream velocity at the structure can occur at a lesser event
than the design storm if roadway overtopping is present during the design storm.
Figure 203-2S
Back
Type of Channel and Description Minimum Normal Maximum
EXCAVATED OR DREDGED
1. Earth, Straight and Uniform 0.016 0.018 0.020
a. Clean, recently completed 0.018 0.022 0.025
b. Clean, after weathering 0.022 0.025 0.030
c. Gravel, uniform section, clean 0.022 0.027 0.033
2. Earth, Winding and Sluggish
a. No vegetation 0.023 0.025 0.030
b. Grass, some weeds 0.025 0.030 0.033
c. Dense weeds or aquatic plants in deep channel 0.030 0.035 0.040
d. Earth bottom and rubble sides 0.025 0.030 0.035
e. Stony bottom and weedy sides 0.025 0.035 0.045
f. Cobble bottom and clean sides 0.030 0.040 0.050
3. Dragline, Excavated or Dredged
a. No vegetation 0.025 0.028 0.033
b. Light brush on banks 0.035 0.050 0.060
4. Rock Cut
a. Smooth and uniform 0.025 0.035 0.040
b. Jagged and irregular 0.035 0.040 0.050
5. Channel Not Maintained, Weeds and Brush Uncut
a. Dense weeds, high as flow depth 0.050 0.080 0.120
b. Clean bottom, brush on sides 0.040 0.050 0.080
c. Clean bottom, highest stage of flow 0.045 0.070 0.110
d. Dense brush, high stage 0.080 0.100 0.140
NATURAL STREAM
1. Minor Stream (top width at flood stage < 100 ft)
a. Stream on plain
(1) Clean, straight, full stage, no rifts or deep
0.025 0.030 0.033
pools
(2) Same as above, but more stones or weeds 0.030 0.035 0.040
(3) Clean, winding, some pools or shoals 0.033 0.040 0.045
(4) Same as above, but some weeds or stones 0.035 0.045 0.050
(5) Same as above, lower stages, more
0.040 0.048 0.055
ineffective slopes and sections
(6) Same as (4), but more stones 0.045 0.050 0.060
(7) Sluggish reaches, weedy, deep pools 0.050 0.070 0.080
(8) Very weedy reaches, deep pools, or
floodway with heavy stand of timber and 0.075 0.100 0.150
underbrush
Back
Type of Channel and Description Minimum Normal Maximum
NATURAL STREAM (contd.)
1. Minor Stream (contd.)
b. Mountain stream, no vegetation in channel,
banks usually steep, trees and brush along
banks submerged at high stages
(1) Bottom: gravel, cobbles, and few
0.030 0.040 0.050
boulders
(2) Bottom: cobbles with large boulders 0.040 0.050 0.07
2. Floodplain
a. Pasture, no brush
(1) Short grass 0.025 0.030 0.035
(2) High grass 0.030 0.035 0.050
b. Cultivated area
(1) No crop 0.020 0.030 0.040
(2) Mature row crops 0.025 0.035 0.045
(3) Mature field crops 0.030 0.040 0.050
c. Brush
(1) Scattered brush, heavy weeds 0.035 0.050 0.070
(2) Light brush and trees, in winter 0.035 0.050 0.060
(3) Light brush and trees, in summer 0.040 0.060 0.080
(4) Medium to dense brush, in winter 0.045 0.070 0.110
(5) Medium to dense brush, in summer 0.070 0.100 0.160
d. Trees
(1) Dense willows, in summer, straight 0.110 0.150 0.200
(2) Cleared land with tree stumps, no sprouts 0.030 0.040 0.050
(3) Same as above, but with heavy growth of
sprouts 0.050 0.060 0.080
(4) Heavy stand of timber, a few downed
trees, little undergrowth, flood stage 0.080 0.100 0.120
below branches
(5) Same as above, but with flood stage
0.100 0.120 0.160
reaching branches
3. Major Stream (top width at flood stage > 100 ft).
The n value is less than that for a minor stream of
similar description, because banks offer less
effective resistance.
a. Regular section with no boulders or brush 0.025 n/a 0.060
b. Irregular and rough section 0.035 n/a 0.100
Source: Chow, V.T.
Back
VALUES OF MANNING’S n FOR UNIFORM FLOW, Figure 203-3A
Minimum
Type Thickness
Abutment Pier
Riprap-Lay Thickness
Note: The thickness is measured such that the top is at the ground elevation.
Substructure
Lay Width
Type
Sloping The cone is covered top to toe, a square toe trench
Abutment is placed below the riprap, based on lay thickness.
Vertical
2 times the water depth or a minimum of 10 ft
Abutment
2 times the pier width or a minimum of 6 ft. The
Pier lay width is from the outside wall of the pier, all
the way around.
Riprap-Lay Width
Note: For an oversized-box or three-sided structure, see the INDOT Standard Drawings.
Figure 203-3B
Back
Hydraulics QA Checklist
Other______________________
Hydraulics QA Checklist
(Continued) Back
Type of Facility Design Frequency Allowable Spread, T
Freeway 2% Annual EP Edge of travel lane
Non-Freeway, ≥ 4 Lanes 10 % Annual EP Across one-half travel lane
Two-Lane Facility 10 % Annual EP 4 ft onto travel lane
Bridge Deck, Non-
Freeway 10 % Annual EP
Edge of travel lane
V ≥ 50 mph 10% Annual EP
3 ft onto travel lane
V < 50 mph
Ramp
V ≥ 50 mph 10% Annual EP Edge of travel lane
V < 50 mph 10% Annual EP 3 ft onto travel lane
Note:Consideration for a 2% annual EP storm event should be used when in a depressed area.
See Section 203-4.04(10)
E X
J X
K X
S X
W1 X X X
A X X X
B X
C X
D X
E X
F X
G X
Inlet
H, HA X
J X
M X
N X
P X
R X
S X
T X
A X X X
B X X X
C2 X X X
D X X X
E X X X
Manhole
F X X X
G X X X
H X X X
J X X X
K X X X
L X X X
M X X X
N X X X
1
Notes: May be substituted for catch basin type A.
2
May be substituted for manhole type A or B.
Figure 203-4B
Back
Type of Gutter or Pavement Manning’s n
Concrete gutter, troweled finish 0.012
Asphalt Pavement
Smooth texture 0.013
Rough texture 0.016
Concrete gutter-asphalt pavement
Smooth 0.013
Rough 0.015
Concrete pavement
Float finish 0.014
Broom finish 0.016
Notes: 1. For a gutter with a small slope where sediment may accumulate, increase n value by
0.002.
2. Reference: USDOT, FHWA, HDS-3 (1961)
3.53
3.18
3
Q(ft /s)
2.83
8.48
t /s)
3
f
(Q ,
2.47
i
70
.6
INTERCEPTED FLOW
2.12
5% 5.65
ce
incy3
Ef
fi
1.77
4.24
0%
e
incy4
Ef
fc
i
1.41
28
.3
1.06 2.12
c
ie
iny5
c 0%
Ef
f
14
.1
0.71
0%
e
incy6
Ef
fc
i
0.71
Ef
fc
ie
iny7
c 0%
0.35
0.35
0
0 0.005 0.01 0.02 0.03 0.04 0.05 0.06 0.07
Figure 203-4E
Back
Manhole Inside- Maximum Trunkline Minimum Trunkline
Manhole
Dia. Dimension Pipe Size Pipe Size
Type
(in.) (in.) (in.)
A 48 dia. 24 12
B 36 dia. 18 12
C 49 dia. 24 12
D 58 x 74 42 27
E 80 x 74 60 48
F 108 x 74 84 66
G 136 x 74 108 90
H 49 dia. 36 24
J 62 dia. 36 24
K 74 dia. 48 36
L 98 dia. 54 48
M 104 dia. 72 54
N 110 dia. 84 72
MANHOLE TYPES
Notes: 1. x = (200dK)0.5, where x = distance from the low point to flanking inlet, ft, and
d = depth at curb, ft
Maximum K for drainage = 170 (ft/%A) for a curbed facility.
2. K = L/A, where L = length of vertical curve, ft, and A = algebraic difference in approach grades, %.
Reference: HEC 12 Chapter 9 (modified).
FLANKING-INLET LOCATIONS
Figure 203-4G
Back
1"-9" 1’-0" 1’-0" 1"-9"
Beam Concrete
barrier rail
Drain type OS
11
:2 1:
12
Concrete
Steel beam bulb-tee
Drain extension,
Drain extension, beam
6" dia.
6" dia.
Pipe support bracket
6" 6"
(b)
(a)
Drainage
Flow Time Velocity
Runoff Coefficient
Area A (A)(C) Invert Elev.
Rainfall Intensity
0.00278CIA = Q
(min) (ft/s)
Slope of Drain
Diameter Pipe
Total Runoff
Capacity Fill
(ac)
Invert Drop
Manhole
I (in./h)
Length
(ft/ft)
(cfs)
(cfs)
(in.)
(ft)
Station
In Section
Increment
Increment
To Upper
Flowing
Design
Lower
Upper
Total
Total
Flow
Full
End
End
End
STORM DRAIN COMPUTATION SHEET
Figure 203-4 I
Back
Storm Durations for Inflow Rates Outflow Rates Peak Water Surface Peak Volumes
1% Annual EP (cfs) (cfs) Elevations (ft) (ft3)
1% Annual EP - 0.25 hr
1% Annual EP - 0.5 hr
1% Annual EP - 1 hr
1% Annual EP - 2 hr
1% Annual EP - 3 hr
1% Annual EP - 6 hr
1% Annual EP - 12 hr
1% Annual EP - 24 hr
Figure 203-5A
Back
Maximum Allowable
Material Manning’s n
Velocity (ft/s)
Fine Sand 0.20 2.5
Sandy Loam 0.20 2.5
Silty Loam 0.20 3.0
Clay Loam 0.20 3.6
Clay 0.20 5.0
Silty Clay 0.20 5.0
Shale 0.20 6.0
Fine Gravel 0.20 5.0
Coarse Gravel 0.25 6.0
Back
Figure 203-6A
N
AI
PL
EL
10 ft
N
O
WATER SURFACE
AN
O
8
FL
CH
N
AI
WEED & WILLOW
ER
6
PL
SEEDLINGS
AT
D
4
O
-W
IL
FI
FL
W
2
RM
SO
LO
HA
0
AC
0 20 40 60ft
RE
CROSS SECTION 1
CR
OS
S
SE
CT
ION
1
SEGMENTS
OPEN
1 2 3
FIELDS
15’ 25’ 35’
10 ft
WATER SURFACE
8
LE &
BE
B EL
SCATTERED SAND
S
4
C AV
DR
TREES
B
R
OC
G
2
O
K
0
0 20 40 60 80 ft
2
ON
I
CT
REACH B
SE
OS
S CROSS SECTION 2
CR
SUBSECTIONS
1 2 3
OPEN
1000’ 30’ 1000’
FIELDS
10 ft WATER
COTTON SURFACE
FIELDS 8
CROSS
WOODS ECTO
I N3 6
S
REACH C
FIRM SOIL
2
0
(NOT TO SCALE)
CROSS SECTION 3
Figure 203-6B
Back
Grade, G Interval
3% ≤ G < 5% 200 ft
5% ≤ G < 8% 150 ft
8% ≤ G < 10% 100 ft
≥ 10% 50 ft
LUG INTERVAL
Figure 203-6C
Back
Tangent Point
Tangent Point
1.
0
W
W
5
1.
FL
O
W
LONGITUDINAL EXTENT OF REVETMENT PROTECTION
R »¿co
Design swl H
0
d
s
Figure 203-6F
Back
Point of Maximum Runup
R »¿1 : X
H’
0
6.0
5.0
4.0
3.0
R
H’
0
2.0
1.5
1.0
0.1 0.15 0.2 0.4 0.6 0.8 1.0 1.5 2.0 4.0 6.0
»¿X or (cot
h
Toe Dept
Ground
h
pt
De
ng
yi
La
Toe Width
NOTES:
1. Not to Scale.
2. For laying depth, see Standard Specifications.
3. Riprap to be placed on geotextile.
Figure 203-6H
Back
Wrap cloth around
base of armor.
Filter cloth
GEOTEXTILE FILTER
Direction of Flow
3T (min.)
1.5
1 5’-0"
Compacted
Backfill
SECTION: A-A
2T (min.)
3T
SECTION: B-B
Figure 203-6J
Back
Compacted, vegetated fill
Ground
Trenched Toe
Mounded Toe
2T T
Filter layer
Apron
Filter Layer Filter Layer
Toe Wall
Anticipated
Bed Scour Anticipated
Bed Scour
(a) (b)
Anticipated
Bed Scour
Anticipated
Bed Scour
(c) (d)
Bank Paving
Filter Layer
Filter Layer
Flow Direction
Filter Layer
Flow Direction
Toe Mattress
Counterfort
Original River Bed
(a) Training wall with counterforts (b) Stepped back low retaining wall with apron
Armor
Anchor
Filter Layer
MONOSLAB REVETMENT
Figure 203-6T
Back
Varies
Varies
Varies
Cable Tunnels
OPEN CELL GRID
Vegetation
Armorflex
Helix Anchor
Filter Fabric
ARMORFLEX
Figure 203-6U
Back
1’-0"
1’-0"
5"
Petraflex Revetment
Earth Anchor
Continuous Woven
Filter Fabric
PETRAFLEX
Figure 203-6V
Back
Ordinary High Water
POSITION OF BLOCKS
Cable or Rod AFTER SCOUR
PART ELEVATION
PART PLAN
4’-8"
TRI-LOCK REVETMENT
2T Grouted Riprap
(Min.)
Channel-Bed
Filter Layer Scour Depth
T
(a)
Extent of Protection
Desired
Filter Layer
1 4’-0"
Excavated 3
Backfill
(b)
T
2T
Filter Layer
2T
(Min.)
(c)
Figure 203-6Y
Back
Filter Point
Spacing
Figure 203-6Z
Back
Cord Spacing
Thickness
Weep Hole
Assembly
Figure 203-6AA
Back
Ultimate Roadway
Level
3 2
1 1
Normal Water
Surface
Soil Cement
Embankment
Riprap Facing
5
1
Impervious Fill
Not to Scale
Minimum Water 4
1
Surface
Berm
6 Embankment
Soil Cement
1
Not to Scale
Not to Scale
Figure 203-6BB
Back