Primary and Remedial Cementing
Primary and Remedial Cementing
Primary and Remedial Cementing
CEMENTING GUIDELINES
DRILLING AND COMPLETION COMMITTEE ALBERTA
APRIL, 1995
1995
I. INTRODUCTION
This Guide is proposed in response to one of the recommendations set forth by the
DACC Surface Casing Vent Flow Subcommittee where the problem of uncontrolled
gas migration was studied and various recommendations were made to try and
prevent this problem from occurring. The purpose of this Guide is to improve the
probability of getting a good primary cement job and if this is not achieved, to
explain the consequences and remedial courses of action.
A primary cement job has few, but none-the-less, critical purposes. The most
important of which is to provide a continuous, impermeable hydraulic seal in the
annulus, preventing uncontrolled reservoir fluid flow behind the casing. Without
cement behind the pipe, oil or gas may flow to surface and cause a blowout -a very
serious situation which can result in massive environmental damage. Other types of
uncontrolled fluid flow can also occur. In some cases this flow may not even be
visible at surface. Reservoir fluids may commingle or they could migrate upwards,
over- pressurizing other permeable zones, or they may invade a fresh water zone
and contaminate Alberta's useable ground water. Other possibilities include the flow
of gas up the inside or outside of the surface casing, venting into the atmosphere
and/or destroying the near well-bore ecology.
It is clear to see that a good primary cement job is important in order to prevent this
uncontrolled flow. It should also be emphasized that hydraulic isolation is not only
necessary across hydrocarbon bearing reservoirs, but also across aquifers, and
shallow gas zones. Thus, it can be seen that competent cement jobs must be
obtained in all casing strings, including the surface casing, as this often is the string
that will protect usable ground water and prevent shallow gas migration.
The industry must be made aware that good primary cement jobs are necessary to
prevent uncontrolled annular gas and fluid flows. The Guide offers practical tips and
a systematic procedure to obtain an adequate cement job. It also includes a small
glossary of definitions, and a section on tips for remedial repair and well
abandonment. The Guide is intended to help the people that drill oil and gas wells
every day. It is important to recognize that this is only a guide, and there may be
techniques different than those described that can result in good cement jobs. This
Guide is not intended to replace local practices .that have proven successful.
o Well Name
o Location (LSD)
o Type of mud
o Any special well problem (lost circulation, kicks, salt sections, etc.)
3. Determine the required amount of dry cement or blend, total mix water,
pump rates, surface and bottom hole pressures during the job, mixing
time, mud displacement volume cumulative displacement to bump the top
plug, and other relevant information.
6. Whenever possible design the cement job so the spacers, washes, and
cement slurries are displaced in turbulent flow. When this is not possible
use alternate displacement techniques such as effective laminar flow
technology.
8. Cement plugs should be used with the purpose of separating each change
in fluid: mud from wash, wash from spacer, spacer from cement, cement
from mud.
3. Design fluid loss target values using 7 MPa (1,000 psi) differential
pressure. The following general guidelines can serve as a point for design:
Note: In thermal or steam flood wells where high temperatures will be seen
through the entire well-bore, silica may also be required in the surface
casing cement.
5. Use high sulfate resistant cement (HSR)when sulfate content is prominent
in formation water.
9. Use the same mix water, cement, and additives in testing that will be used
on the location for the job. The water should be without contaminants.
10. Check the compatibility of the cement slurry and the drilling mud. Test
also with any washes, and spacers that may be required.
11. When pumping cement bugh coiled tubing, the efkctsof imparting extra
shearing energy into the sluny should obviously be well tested before
pumping the job.
V. PRE-JOB PREPARATION
1. Physically check that all required materials and equipment have been
delivered to the location. Weigh scale tickets should be checked in
addition to loading tickets for the cement blends and additional additives
that may be required.
2. In all cases, when different blends and/or mix water are used, every blend
and tank should be clearly identified. During colder seasons, the mix
water will have to be heated to at least 20 °C. Very cold mix water will
adversely effect the additives in the cement slurry; and thus, the slurry
properties such as thickening time, transition time, rheology, and
sedimentation.
4. Calculate the hydraulic lifting forces that the casing string will see just
before the plug is bumped. This is the moment of maximum differential
pressure.
9. Complete the hookup of all equipment. As soon as the casing is landed, rig
cement head to casing and begin circulation. Computer simulations can
give effective circulation rates for mud conditioning. If simulators are not
used, fluid calipers may be run to measure the volume of mud in
movement. Good mud circulation should displace more than 85 % of the
hole volume. In order to break down the yield pint of stationary mud, it is
imperative that the casing be reciprocated and/or rotated during mud
conditioning.
10. If the rig pumps are to displace, install a pressure transducer to record
displacement pressures from the rig pumps.
11. Calibrate and record all electronic sensors. Compare density readings to
pressurized mud balance measurements. Service company engineer and
drilling company representative should agree in advance on the most
accurate measuring equipment which will remain the reference for the job.
12. Conduct on location pre-job meeting with the cementing crew, drilling
company representative, and rig personnel who would be involved with
the job. The meeting must include safety procedures and contingency
plans.
4. Begin mixing lead slurry. Measure and record the mix water either
through gauged storage tanks, through mixing unit tanks or by metering
methods. Check electronic density measurements against the pressurized
mud balance measurements.
5. Collect samples of the dry blended cement and mix water as mixing
progresses. Samples must be taken in clean, well marked containers, and
stored securely at proper temperatures should they be required for post
job evaluation.
6. Mix entire lead slurry and subsequent slurries as per design densities and
rates. Observe well for returns during the entire cementing process. If
possible record the volume and densities of the returns. Observe the
difference between “full” returns and “partial” returns, which would
indicate losses.
7. Take slurry samples during the job. Do not use the setting of the surface
samples as a guide to cement working time or drill out times. These
samples do not accurately reflect the downhole treatment of cement
during or after placement.
9. Above all, do not sacrifice the slurry density in the last two cubic meters of
slurry mixed to save the expense of the dry cement. As the bulk
equipment empties, cement delivery becomes erratic and density control
10. Drop the top plug in accordance with the equipment operating procedure.
When possible, launch the plug "on the fly" rather than shutting down
pumping operations. Record the total amount of mix water used in the
cementing operation. If not dropping the plug "on the fly" the cement
head valves should be closed as soon as pumping is stopped. This will
keep the air volume below the plug, caused by U-tubing, to a minimum.
Also, if this is the last casing String to be cemented, all cement should be
washed out of the surface treating lines so that cement is not placed on
top of the plug.
11. If displacement is through the cement unit, gauge the displacement fluid
through the displacement tanks -do not rely on flow meters recording
drive shaft rotations, pump strokes or other indirect measure. When
possible, use in-line flow metering equipment --that minimizes the effect
of fluid aeration. For production casing strings displace, when possible,
with fluid of the same or lesser density than the completion fluid. This is
to avoid getting a micro-annulus as mentioned later.
12. If the rig pumps are displacing, flow rate and volume should be measured
and recorded by the stroke rate of the mud pump and a physical backup
of tank gauging to assure correct volumes are being pumped.
13. If the top plug does not land after the calculated displacement volume,
then the previously agreed to contingency plan should be put into effect.
The best practice is not to over displace. Even if some cement has to be
drilled out from above the collar, the cement shoe and bottom of the
casing will be firmly anchored in place. If the plug was "not there" (several
explainable reasons exist for this phenomenon), and additional volumes of
mud are pumped, the slurry will be over displaced resulting in a loss of
good cement bond at the shoe (i.e. a "Wet Shoe").
14. Waiting on Cement (WOC) means just that. There are usually a few
options at this point such as hanging off the casing, or to maintain tension
during the cement hydration. Regardless of the procedure, do not
disturb the setting cement column. Physically jarring or moving the
casing can result in irreversible destruction of the early crystalline
structure that is forming. Also, do not keep pressure on the casing while
the cement is setting. This pressure causes ballooning, increasing the
casing diameter. Later pressure release and casing relaxation to its
original diameter will resulr in a micro annulus between the casing and
cement. This implies that it is essential to use float equipment.
6. Smaller sized tubing as a tail pipe and diverter pipes should be used.
7. Plug length should be no longer than 150 meters. They need only be long
enough to prevent inter-zonal formation fluid contamination.
8. Consider cement blends that work most effectively under the temperature
conditions at plug depth. Minimize cement slurry thickening and transition
times.
2. Conduct API lab tests on the slurry. The lower the viscosity of the slurry
and API fluid loss, the greater the chances of success (in most cases).
Obtain thickening time, theology, and API fluid loss from the lab. On
critical jobs test with the actual products and mix water that will be used
on the job. Modify API test schedule with actual temperatures and
pressures to be encountered.
3. Plan the job with the cementing company. Review material requirements
and assure that adequate cement and additives will be available on
location. The norm is to double or triple required volumes as it may take
several attempts to obtain a successful squeeze. Unless process control
cement mixing equipment is available, batch mixing of the slurry should
be considered. Assure an accurate weigh scale and liquid measuring
device are available on site to measure the exact additive amounts as
detailed in the laboratory.
4. Retain samples of cement and mix water before mixing. Ensure to use
clean (even filtered) mix water. Measure the temperature of the mix water
and have provision to heat the mix water if required. Retain samples of
the final mixture. Density of the cement slurry is critical and should be
within 25 kg/m3 of the lab tested slurry.
6. Ensure well-bore fluids are clean and any fluid used for establishing a feed
rate be solids free. Consider having 15 % HCL acid or Mud Acid (12 %
HCL + 3 % HF) available if a good feed rate cannot be obtained. Avoid
fracturing as this will simply open up a new path for uncontrolled flow.
10. Bleed-off the pressure and check returns. Tools should be retrieved and
the well should be undisturbed during the WOC time.
Surface Casing Vent Problem: A well with a surface casing vent problem is any
well licensed by the AEUB which has a measurable flow which may
contaminate usable ground waters, or create an environmental hazard or
safety concern at surface.
Vent Flow: A vent flow is any measurable flow of gas, water or hydrocarbon liquids
andlor with an attainable pressure build-up.
Migration Problem: Is any well licensed by the AEUB which has a detectable
amount of gas or fluid migration at surface, outside the outer most casing,
which may contaminate usable ground waters, or create an environmental
hazard or safety concern.
Once a vent flow problem has been identified, it must be categorized to determine
the extent and timing of remedial action to be taken:
Is any vent flow where any usable water -zones are not covered by cemented
surface casing and/or cemented production casing.
Is any vent flow with a stabilized gas flow equal to or greater than 300
m3/day, and/or equal to a surface shut-in pressure:
Is any vent flow with H2S present which constitutes danger to public safety or
poses an environmental hazard.
1
…The criterion of 11 kPa/m, or half the known formation leak-off pressure, was
chosen to avoid exceeding the fracture gradient. The surface shut-in pressure
may vary with formation leak-off pressure, density of fluid in annulus, depth
to fluid, lost circulation zones, or other well conditions that would limit the
allowable shut-in pressure
Is any usable water vent flow where the surface shut-in pressure is:
Is any vent flow due the wellhead seal failures or casing failure.
Non-Serious Vent Flows: Is any vent flow that has not been classified as a serious
vent flow.
Serious Migration: Is any gas or fluid migration to surface that constitutes a fire
hazard, public safety hazard, or off-lease environmental damage.
Non-Serious Migration: Is any gas or fluid migration to surface that has not been
classified as serious migration.
Operators with numerous existing vent blows that are categorized as serious
solely based on the criteria outlined in “Serious Vent Blows” shall submit a
repair schedule for AEUB approval
ACKNOWLEDGMENTS
Suggestions and improvement ideas were received from numerous sources. With the
hope that the majority of these contributors will be recognized, gratitude and thanks
are hereby extended to:
Alberta Energy and Utilities Board (AEUB)