Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

INVESTIGATION REPORT eFNCR 076 - BOP Test Plug Stuck in CHH

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Page |1

INVESTIGATION REPORT ON STUCK BOP TEST PLUG ON


WELL ZB-347

Date Prepared By Reviewed By Approved By

25 Feb 2018 Mohammed Jabir Amir Nadeem Mohammed Aljarah

QA/QC Engineer Service Manager - ME Area Manager -Iraq

Subject to contractual terms and conditions to the contrary, this document and all the information contained herein are the confidential and exclusive
Property of TechnipFMC, and may not be reproduced, disclosed, or made public in any manner prior to express written authorization by TechnipFMC.
Page |2

Table of Contents
Section Title Page

1.0  BACKGROUND ............................................................................ 3 


2.0  SEQUENCE OF INCIDENT.......................................................... 3 
3.0  FIELD FIX / CORRECTIVE ACTION ......................................... 3 
4.0  CONTRIBUTING FACTORS ........................................................ 3 
5.0  ROOT CAUSE ............................................................................... 4 
6.0  PREVENTIVE ACTION ................................................................ 4 

Subject to contractual terms and conditions to the contrary, this document and all the information contained herein are the confidential and exclusive
Property of TechnipFMC, and may not be reproduced, disclosed, or made public in any manner prior to express written authorization by TechnipFMC.
Page |3

1.0 BACKGROUND
Main Operation : BOP Test.

Nature of Incident : Could not retrieve BOP Test Plug after BOP test failed.

Location : Iraq - Basra - Zubair oil field ZB-347

Date of Incident : 10th February 2018

2.0 SEQUENCE OF INCIDENT


 Post installation of section A “CHH”, TechnipFMC Engineer ran in Bop test plug
for Bop Test.

 During Testing driller observed a pressure drop.

 TechnipFMC Engineer tried to pull out TP to inspect and change S-seals.

 Gradual over pull up to 15 ton was given but unsuccessful.

 N/D BOP for visual check and found Test plug move vertically up to 10 cms and
stop.

 Tried to rotate and over pull to release.

 Once Test plug released TechnipFMC engineer found CHH bowl area was
scratched.

 Seals of BOP TP found damaged too.

3.0 FIELD FIX / CORRECTIVE ACTION


 Customer resumed further operation as is.

4.0 CONTRIBUTING FACTORS


 TDS misalignment.

 Probable cause of degraded seals due to improper storage.

 TDS was used to rotate the stuck plug

 Inadequate communication of the issue to the base while it happened.

Subject to contractual terms and conditions to the contrary, this document and all the information contained herein are the confidential and exclusive
Property of TechnipFMC, and may not be reproduced, disclosed, or made public in any manner prior to express written authorization by TechnipFMC.
Page |4

5.0 ROOT CAUSE


 Misalignment overlooked considering the operation to be routine.

 Even though the seals were checked and appeared good; possible degradation of
the material due to extended exposure to the atmospheric elements.

6.0 PREVENTIVE ACTION


 Confirm the alignment prior to running of TechnipFMC equipment.

 In field Issues to be communicated back to the base immediately.

 Seals to be checked effectively for any traces of damage or replace when in doubt.

 Storage of elastomeric to be carried out as per procedure and the procedures to


be shared with the customers.

 Use elevators to run BOP Test plugs.

 All service personnel notified of the issue and requested to be extra cautious while
using of customer stored equipment.

Subject to contractual terms and conditions to the contrary, this document and all the information contained herein are the confidential and exclusive
Property of TechnipFMC, and may not be reproduced, disclosed, or made public in any manner prior to express written authorization by TechnipFMC.

You might also like