EOWR CV-5X Combine 08may2008
EOWR CV-5X Combine 08may2008
EOWR CV-5X Combine 08may2008
Table of Contents
Page 1
General Well Data
Final Location:
Latitude Longitude Northing Easting
8° 26’ 31.537”N 102° 39’ 03.306”E 933877.77 m 241384.88 m
Rig: Vicksburg
Drilling Contractor: Atwood
Rig Type: Jack Up
RT-MSL: 34.3 m
Water Depth: 78 m
Hole size Hole MD Hole TVD Casing size Casing MD Casing TVD
12” 310 m 310 m 9-5/8” 310 m 310 m
8-1/2” 1422 m 1402 m 7” 1419 m
6-1/8” 3749 m 3508.6 m
Page 2
AFE depths vs Actual depths Measured Depth True Vertical Depth
12” AFE 305 m 305 m
12” Actual 310 m 310 m
Reason for difference Drill to casing tally
Notes
1 Ca Voi-5X is the third exploration well in 2008 campaign.
The well design is a slim hole type, with the first section riser-less drilling 9-
5/8” casing.
2 Drilling rig Vicksburg (Atwood) was towed from NKL-3X to CV-5X on 15-
Feb-2008. Towing distance to CV-5X location is 19.8 NM (36.7 km).
Page 3
Final Positioning Report
Page 4
Daily Drilling Reports
Page 7
Drilling Morning Report
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
10:00 13:00 Lower conductor deck while Skidding out. Skid in enough to install icon tensioner, install ladder & handrails. Skid out to
drilling position.
Install mud dryer and overboard line. Lower wing valves for wellhead & prepare rig floor for drilling with casing.
13:00 13:30 P/U and M/U 9-5/8" wellhead and rack in derrick.
13:30 14:00 Perform abandon ship drill and help riserless drilling meeting.
14:00 15:30 JSA, R/U BJ equipment. P/U and RIH 12" BBL drill shoe, 9-5/8" float collar & 7 joints 40-ppf 9-5/8" csg to 110m MD. M/U
Baker casing spear to TDS.
15:30 18:00 Tag mudline at 112m. Drill in casing from 112m MD(mudline) to 292m MD. M/U 9 LST wellhead, and drill down the casing
with 9.2 ppg Barazan mud to 310m MD / 310m TVD.
18:00 19:00 Circ. 1050 stks. R/U BJ lines and test to 2000 psi. Pump 78 bbls of 15.5 ppg cement slurry with BJ. Disp. cement with 68.2
bbls of seawater. CIP - 18:50 hrs. Check back flow (OK). L/D landing joints and wellhead running tool.
19:00 21:00 Install test plug. Install side outlet valves and wellhead adaptor spool. Nipple up Bop's. Install bell nipple. Install witches hats.
21:00 21:30 Pressure test connection 250/5000 psi. 3/3 mins
21:30 22:30 M/U test assy. Install landing joint and test annular 300/3500psi. Remove test plug and install wear bushing. Laydown test
assy.
22:30 00:00 JSA. P/U & M/U 19 stands (57 joints) of 4" Drillpipe and rack back in the derrick.
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
Water (Other) 9.20
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
51 14.0 13.000
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
112.40 112.40 310.25 309.89 2.50 79.1
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
2/21/2008 0.00 0.00 0.00 0.00 -6.46 1.47 7.08 0.00
Casing
Casing Description OD (in) Set Depth (mKB) Run Date
Surface 9 5/8 310.25 2/21/2008
05:30 16:30 Directionally drilled 8-1/2" hole from 311.5m MD to intermediate section TD at 1422m MD / 1402m TVD. Top of MMU at
1110m MD / 1108m TVD.
16:30 18:00 Pumped 50bbl 12ppg weighted sweep. Circulated and displaced well to 9.2 ppg gel polymer mud. Circulated bottoms up 3
times. Calculated average hole size: 12.2".
18:00 21:00 Flow checked. Pumped slug. Pulled out of the hole with BHA. Laid down bit and MWD probe.
21:00 00:00 Pulled wear bushing. Held pre-job safety meeting. Rigged up and ran in the hole with 7" 23ppf casing to 725m MD.
00:00 00:00
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
Water (Other) 9.20
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
52 14.0 16.000
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
310.25 309.89 1,422.00 1,402.17 11.50 96.7
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
2/22/2008 317.00 6.20 218.50 316.60 -2.04 -7.20 0.18 0.91
2/22/2008 375.00 7.90 224.70 374.20 0.83 -12.34 -4.17 1.84
2/22/2008 403.00 5.60 228.70 402.01 2.54 -14.61 -6.55 2.51
2/22/2008 432.00 1.70 212.30 430.95 3.46 -15.91 -7.84 4.14
2/22/2008 461.00 0.70 185.90 459.94 3.56 -16.45 -8.09 1.16
2/22/2008 490.00 1.00 61.10 488.94 3.35 -16.50 -7.89 1.57
2/22/2008 519.00 2.50 35.80 517.92 2.94 -15.87 -7.29 1.71
2/22/2008 548.00 2.60 34.00 546.89 2.50 -14.81 -6.56 0.13
2/22/2008 577.00 2.50 40.00 575.87 2.02 -13.78 -5.78 0.29
2/22/2008 606.00 2.50 39.10 604.84 1.49 -12.80 -4.98 0.04
2/22/2008 635.00 2.30 37.00 633.81 1.02 -11.85 -4.23 0.23
2/22/2008 693.00 2.20 36.10 691.77 0.18 -10.02 -2.87 0.05
2/22/2008 722.00 2.20 35.40 720.75 -0.21 -9.12 -2.22 0.03
2/22/2008 752.00 2.00 30.70 750.73 -0.56 -8.20 -1.62 0.26
2/22/2008 780.00 2.30 26.10 778.71 -0.80 -7.27 -1.12 0.37
2/22/2008 809.00 2.40 25.70 807.68 -1.02 -6.20 -0.60 0.10
2/22/2008 838.00 2.20 22.70 836.66 -1.21 -5.14 -0.13 0.24
2/22/2008 867.00 2.70 37.50 865.63 -1.55 -4.09 0.51 0.83
2/22/2008 896.00 2.60 37.70 894.60 -2.06 -3.02 1.32 0.10
2/22/2008 925.00 2.80 41.80 923.57 -2.63 -1.98 2.20 0.29
2/22/2008 954.00 2.70 42.10 952.54 -3.26 -0.94 3.13 0.10
2/22/2008 983.00 2.60 41.40 981.51 -3.87 0.06 4.02 0.11
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
2/22/2008 1,012.00 2.20 45.30 1,010.48 -4.44 0.94 4.85 0.45
2/22/2008 1,041.00 1.70 47.20 1,039.46 -4.95 1.63 5.56 0.52
2/22/2008 1,070.00 1.30 0.40 1,068.45 -5.10 2.25 5.88 1.29
2/22/2008 1,099.00 2.20 314.40 1,097.44 -4.53 2.97 5.48 1.65
2/22/2008 1,128.00 2.60 316.30 1,126.42 -3.48 3.83 4.63 0.42
2/22/2008 1,157.00 5.20 297.80 1,155.35 -1.64 4.92 3.02 2.95
2/22/2008 1,186.00 7.70 287.20 1,184.16 1.58 6.11 0.00 2.85
2/22/2008 1,215.00 11.10 291.10 1,212.77 6.30 7.69 -4.47 3.58
2/22/2008 1,244.00 15.20 287.20 1,241.00 12.88 9.82 -10.70 4.34
2/22/2008 1,273.00 19.50 282.50 1,268.68 21.52 11.99 -19.07 4.68
2/22/2008 1,301.00 23.70 282.80 1,294.71 31.82 14.25 -29.12 4.50
2/22/2008 1,330.00 28.00 284.80 1,320.80 44.45 17.28 -41.39 4.54
2/22/2008 1,359.00 27.80 284.40 1,346.43 58.02 20.70 -54.52 0.28
2/22/2008 1,388.00 27.80 283.70 1,372.08 71.55 23.99 -67.64 0.34
Casing
Casing Description OD (in) Set Depth (mKB) Run Date
Surface 9 5/8 310.25 2/21/2008
Intermediate 7 1,419.46 2/22/2008
17:30 00:00 Drilled 6-1/8" hole from 1425m MD to 1780m MD / 1721m TVD.
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
SBM (Other) 9.20
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
52 15.0 14.000 3.0
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
1,422.00 1,402.17 1,780.00 1,721.28 6.50 55.1
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
2/23/2008 1,447.00 27.90 283.50 1,424.25 99.10 30.47 -94.43 0.07
2/23/2008 1,476.00 27.80 283.40 1,449.89 112.64 33.62 -107.61 0.11
2/23/2008 1,505.00 27.80 283.20 1,475.54 126.16 36.73 -120.77 0.10
2/23/2008 1,534.00 27.50 283.20 1,501.23 139.61 39.80 -133.87 0.31
2/23/2008 1,558.00 27.30 283.00 1,522.54 150.65 42.31 -144.63 0.28
2/23/2008 1,592.00 27.00 282.80 1,552.79 166.16 45.77 -159.75 0.28
2/23/2008 1,621.00 26.90 282.80 1,578.64 179.29 48.68 -172.57 0.10
2/23/2008 1,650.00 26.60 282.60 1,604.54 192.33 51.55 -185.30 0.32
2/23/2008 1,679.00 26.10 282.50 1,630.52 205.19 54.35 -197.87 0.52
2/23/2008 1,708.00 25.60 282.30 1,656.62 217.82 57.07 -210.22 0.53
2/23/2008 1,737.00 26.00 282.50 1,682.73 230.43 59.78 -222.54 0.42
Casing
Casing Description OD (in) Set Depth (mKB) Run Date
Surface 9 5/8 310.25 2/21/2008
Intermediate 7 1,419.46 2/22/2008
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
2/24/2008 2,781.00 25.30 281.20 2,621.95 685.78 158.42 -667.52 0.32
2/24/2008 2,809.00 26.10 281.40 2,647.18 697.89 160.80 -679.42 0.86
2/24/2008 2,837.00 26.50 281.10 2,672.28 710.27 163.22 -691.59 0.45
Casing
Casing Description OD (in) Set Depth (mKB) Run Date
Surface 9 5/8 310.25 2/21/2008
Intermediate 7 1,419.46 2/22/2008
18:00 00:00 Picked up HSFT. Function tested tool and ran in the hole with same. Took total of 22 pressure points from 1445m to 1977m
MD (20 valid, 1 tight, 0 lost/no seal, 1 supercharged, 0 aborted). @ 2400 hrs. (50 Total pressure points planned).
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
SBM (Other) 10.20 196,000
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
55 19.0 14.000 2.2
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
3,748.00 3,507.66 3,749.00 3,508.61 0.50 2.0
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Casing
Casing Description OD (in) Set Depth (mKB) Run Date
Surface 9 5/8 310.25 2/21/2008
Intermediate 7 1,419.46 2/22/2008
08:00 00:00 Picked up RDT tool assy. RIH with same and take samples 10 samples from 1569.8m to 1786.9m, 8 valid, 1 tight, 0 lost or no
seal, 1 aborted, 0 supercharged, including 7 pumpouts and 6 samples.
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
SBM (Other) 10.20 196,000
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
56 19.0 15.000 2.2
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Casing
Casing Description OD (in) Set Depth (mKB) Run Date
Surface 9 5/8 310.25 2/21/2008
Intermediate 7 1,419.46 2/22/2008
10:30 20:00 M/U SWC guns. Rig on radio silence until core guns below 500'. Correlate and take core samples as per program. Get cores
from 3394.9m MD to 1465.5 MD. POOH & lay down CST gun. R/D Halliburton. {42 shots, 28 good, 3 misfire, 11 empty & 0
lost in the hole}.
20:00 22:30 Held jsa, Rig up and P/up and rih with 49 jts 2 7/8" tbg + mule shoe jt to 470m.
22:30 00:00 Make up xo and tih with 4" drill pipe to 1630m, Break circulation every 20 stds to break gels in mud.
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
SBM (Other) 10.20 196,000
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
55 19.0 14.000 2.2
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Casing
Casing Description OD (in) Set Depth (mKB) Run Date
Surface 9 5/8 310.25 2/21/2008
Intermediate 7 1,419.46 2/22/2008
09:30 13:00 Pulled out of hole. Recovered and laid out 10 joints plus 1 ft of tubing of original 50 joints. Pipe parted 1' into 11th joint
leaving 40 joints in well.Top of cement at 2985m MD, top of tubing at 2790m MD. 10 joints recovered were not reusable and
junked.
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
WBM (Modified Polymer) 10.30 24,000
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
54 14.0 18.000
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Casing
Casing Description OD (in) Set Depth (mKB) Run Date
Surface 9 5/8 310.25 2/21/2008
Intermediate 7 1,419.46 2/22/2008
14:00 15:00 Pulled out of hole 5 stands and circulated string clean.
15:00 19:00 Continued to pull out of hole laying out 43 stands of 4" drill pipe. Pressure tested 7" x 9 5/8" annulus while pulling out of hole.
Pumping away at 400 psi.
19:00 21:00 Made up 7" casing cutting assembly and ran in hole to cutting depth at 280m MD. Cut casing and confirmed cut by pumping
through casing annulus. Pulled out of hole and laid down cutting assembly
21:00 00:00 Pulled wear bushing and jetted well head clean. Picked up landing joint and pulled and laid out 12 joints of 7" casing.
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Casing
Casing Description OD (in) Set Depth (mKB) Run Date
Surface 9 5/8 310.25 2/21/2008
Intermediate 7 1,419.46 2/22/2008
04:30 05:00 POH laying down 6 stands of drill pipe and l/down stinger.
05:00 07:00 Nippled sown BOP's and removed 2" side outlet valves
07:00 08:00 Made up 9 5/8" casing cutter and ran in hole and cut casing 5m below mud line at 117m Pulled out of hole and laid down
cutter.
08:00 09:30 Picked up running tool and engaged well head and recovered to rig floor. Laid down well head and laid down 8 joints of 9 5/8"
casing and 2.59m offcut.
09:30 13:30 Laid out remaining 32 stands of 4" drill pipe, 24 joints of 4" HWDP and 6 1/8" BHA.
13:30 15:00 Prepare to move. Remove cuttings drier to deck. Move temporary accomocdation to standby site. Tie down loads.
15:00 15:30 Abandon drill, head count in 7 minutes
15:30 16:30 Standup for safety
16:30 20:30 Held jsa, Cantilever rig in and remove icon tensioner, Raise and secure tensioner deck.Pin and secure drilling package to
stow position. Continue to secure rig and decks for tow.
20:30 23:30 Held jsa, Jackdown to 20' airgap, connect M/V Premaraj tide to tow bridle @ 2120 hrs, Jackdown to 9' draft & connect M/V
Heritage service to stbd qtr @ 2215 while removing leg loop from bow and checking water tight integrity.
23:30 00:00 Begin jetting, port leg free @ 2400 hrs. Rigup to jet bow leg.
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Casing
Casing Description OD (in) Set Depth (mKB) Run Date
Surface 9 5/8 310.25 2/21/2008
Intermediate 7 1,419.46 2/22/2008
Mud Checks
Mud / Brine Type Mud Density (lb/gal) pH Water Phase Chlorides (ppm)
Funnel Viscosity (s/qt) PV Calc (cp) YP Calc (lbf/100ft²) HTHP Filtrate (mL/30min)
Drilling Parameters
Depth Start (mKB) TVD Start (mKB) Depth End (mKB) TVD End (mKB) IADC Drilling Time (hrs) Interval ROP (m/hr)
Survey Data
Date MD (mKB) Incl (°) Azm (°) TVD (mKB) VS (m) NS (m) EW (m) DLS (°/30m)
Casing
Casing Description OD (in) Set Depth (mKB) Run Date
Surface 9 5/8 310.25 2/21/2008
Intermediate 7 1,419.46 2/22/2008
Page 29
BHA Summary
WellView
Well Name: CV-5X
Job Type: Drilling - Original
API/UWI Surface Legal Location Well Configuration Type Ground Elevation (mKB) KB-Casing Flange Distance (m) KB-Tubing Head Distance (m) Total Depth (mKB)
CV-5X Deviated 3,749.00
Bits
Bit BHA Drill Time BHA ROP
Run No. Drill String Name BHA Drill Bit Bit Dull Depth In (mKB) Depth Out (mKB) Drilled (m) (hrs) (m/hr)
1 1 Casing drill BBL Shoe, 9 5/8" float collar, 9 5/8" 40ppf casing, 9 5/8" float collar, 9 12in, BBL Shoe, 16687038 ------- 112.40 310.25 197.85 2.50 79.1
5/8" 40ppf casing
2 2 Motor Build Hycalog HCM 604, 7" sperry Drill Lobe 7/8 - 7.5 Stg, 6 3/4" Float sub, 8 1/2in, HCM 604, 1-1-WT-G-X-0-NO-TD 310.25 1,422.00 1,111.75 11.50 96.7
Non Mag MWD Hang off collar, 6 3/4" Non Mag Screen sun, XO Sub, 7210910
24 HWDP
3 3 Rotary AGS Hycalog DSR516M, 6 1/8" Modular NB Stabilizer, 1ft Extension sub, 6 1/8in, DSR516M, 120627 4-8-WT-GN-X-4-ER-PR 1,422.00 3,197.00 1,775.00 42.50 41.8
Adjustable Gauge stabilizer, 5" Non Mag hang off collar, 6" Integral
blade stabilizer w/ screen, Cross over sub, 24 X 4" HWDP
4 4 Rotary AGS DBS FMH3543ZR, 6 1/8" Modular NB Stabilizer, 1ft Extension sub, 6 1/8in, FMH3543ZR, 1-8-RO-T-X-1-CT-TD 3,197.00 3,749.00 552.00 23.00 24.0
Adjustable Gauge stabilizer, 5" Non Mag hang off collar, 6" Integral 11080326
blade stabilizer w/ screen, Cross over sub, 24 X 4" HWDP
Page 31
WellView Casing Summary
P (collapse)
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Top Thread Top (mKB) Btm (mKB) Len (m) Burst Pres (psi) (psi)
Surface, 310.25mKB
Set Depth (mKB) Set Tension (kips) String Nominal OD (in) String Minimum Drift (in) Centralizers Scratchers
310.25 9 5/8
P (collapse)
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Top Thread Top (mKB) Btm (mKB) Len (m) Burst Pres (psi) (psi)
1 Top of Wellhead to 0.00 15.07 15.07
Rig Floor
1 KOP Wellhead 15.07 18.20 3.13
Assembly
22 9.625" 40# N-80 BTC 9 5/8 8.835 40.00 N-80 BTC 18.20 284.14 265.94
CSG.
1 FLOAT COLLAR 9 9 5/8 8.835 40.00 N-80 BTC 284.14 296.89 12.75
5/8" GRADE 40ppf
1 CASING SHOE 9 5/8" 9 5/8 8.835 40.00 N-80 BTC 296.89 310.25 13.36
GRADE 40ppf
Intermediate, 1,419.46mKB
Set Depth (mKB) Set Tension (kips) String Nominal OD (in) String Minimum Drift (in) Centralizers Scratchers
1,419.46 7
P (collapse)
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Top Thread Top (mKB) Btm (mKB) Len (m) Burst Pres (psi) (psi)
1 RKB to HGR 7 6.276 26.00 L-80 0.00 15.60 15.60
1 Hanger assembly 7 6.276 26.00 L-80 BTC 15.60 17.95 2.35
114 7" 23 ppf BTC casing 7 6.366 23.00 N-80 BTC 17.95 1,394.59 1,376.64
N-80
1 Weatherford Float 7 6.366 23.00 N-80 BTC 1,394.59 1,406.88 12.29
Assy
1 Weatherford Shoe 7 6.366 23.00 N-80 BTC 1,406.88 1,419.46 12.58
Original Hole
Wellbore Name Profile Type Kick Off Depth (mKB) Vertical Section Direction (°)
Original Hole Directional 1,066.80 285.00
Section Size (in) Act Top (mKB) Act Btm (mKB)
Surface 12 1/4 112.40 310.00
Intermediate 8 1/2 310.00 1,421.89
Production 6 1/8 1,421.89 3,749.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
Surface, 310.25mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Surface Original Hole 2/21/2008 310.25 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 Top of Wellhead to Rig Floor 15.07 0.00 15.07
1 KOP Wellhead Assembly 3.13 15.07 18.20
22 9.625" 40# N-80 BTC CSG. 9 5/8 8.835 40.00 N-80 BTC 265.94 18.20 284.14
1 FLOAT COLLAR 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 12.75 284.14 296.89
40ppf
1 CASING SHOE 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 13.36 296.89 310.25
40ppf
Intermediate, 1,419.46mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Intermediate Original Hole 2/22/2008 1,419.46 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 RKB to HGR 7 6.276 26.00 L-80 15.60 0.00 15.60
1 Hanger assembly 7 6.276 26.00 L-80 BTC 2.35 15.60 17.95
114 7" 23 ppf BTC casing N-80 7 6.366 23.00 N-80 BTC 1,376.64 17.95 1,394.59
1 Weatherford Float Assy 7 6.366 23.00 N-80 BTC 12.29 1,394.59 1,406.88
1 Weatherford Shoe 7 6.366 23.00 N-80 BTC 12.58 1,406.88 1,419.46
<Description?>, <Type?>, <Start Date?>
Cementing Start Date Cementing End Date Wellbore
Original Hole
Evaluation Method Cement Evaluation Results
Comment
Top (mKB) Bottom (mKB) Full Return? Cmnt Rtrn (bbl) Top Plug? Bottom Plug?
No No No
Initial Pump Rate (bbl/min) Final Pump Rate (bbl/min) Average Pump Rate (bbl/min) Final Pump Pressure (psi) Plug Bump Pressure (psi)
Pipe Reciprocated? Reciprocation Stroke Length (m) Reciprocation Rate (spm) Pipe Rotated? Pipe RPM (rpm)
No No
Depth tagged (mKB) Tag Method Depth Plug Drilled Out To (mKB) Drill Out Diameter (in) Drill Out Date
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
Original Hole
Wellbore Name Profile Type Kick Off Depth (mKB) Vertical Section Direction (°)
Original Hole Directional 1,066.80 285.00
Section Size (in) Act Top (mKB) Act Btm (mKB)
Surface 12 1/4 112.40 310.00
Intermediate 8 1/2 310.00 1,421.89
Production 6 1/8 1,421.89 3,749.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
Surface, 310.25mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Surface Original Hole 2/21/2008 310.25 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 Top of Wellhead to Rig Floor 15.07 0.00 15.07
1 KOP Wellhead Assembly 3.13 15.07 18.20
22 9.625" 40# N-80 BTC CSG. 9 5/8 8.835 40.00 N-80 BTC 265.94 18.20 284.14
1 FLOAT COLLAR 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 12.75 284.14 296.89
40ppf
1 CASING SHOE 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 13.36 296.89 310.25
40ppf
Intermediate, 1,419.46mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Intermediate Original Hole 2/22/2008 1,419.46 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 RKB to HGR 7 6.276 26.00 L-80 15.60 0.00 15.60
1 Hanger assembly 7 6.276 26.00 L-80 BTC 2.35 15.60 17.95
114 7" 23 ppf BTC casing N-80 7 6.366 23.00 N-80 BTC 1,376.64 17.95 1,394.59
1 Weatherford Float Assy 7 6.366 23.00 N-80 BTC 12.29 1,394.59 1,406.88
1 Weatherford Shoe 7 6.366 23.00 N-80 BTC 12.58 1,406.88 1,419.46
Surface Casing Cement, casing, 2/21/2008 18:22
Cementing Start Date Cementing End Date Wellbore
2/21/2008 2/21/2008 Original Hole
Evaluation Method Cement Evaluation Results
Comment
9-5/8" Casing Cement Job Details¿ planned to mix 395 cuft (269 sxs) of class G (+40% S8C) cement with 6.890 gps seawater + 0.050 gps FP-9LS +
2.000 gps A-7 for 7.050 gps or 45.1 bbls of mixed fluid. Slurry weight was 15.5 ppg and the yield was 1.620 cuft/sx. Total calculated slurry volume = 77.5
bbls. Pumped 0 bbls seawater to break circulation. BJ tested lines to 2,000 psig. Mixed and pumped 78.0 bbls of slurry at 6.5 bpm and 350 psi.
Displaced with 68.2 bbls seawater (planned displacement was 68.2 bbls) at 7.0 bpm and 545 psi. Did not drop plug. No wiper plug used in 9-5/8" section.
Bled back and float held. Cement in place at 18:50 hours. Estimated top of cement at seabed. Total of 4 BBL weld on centralizers run.
1, 112.50-310.00mKB
Top (mKB) Bottom (mKB) Full Return? Cmnt Rtrn (bbl) Top Plug? Bottom Plug?
112.50 310.00 No No No
Initial Pump Rate (bbl/min) Final Pump Rate (bbl/min) Average Pump Rate (bbl/min) Final Pump Pressure (psi) Plug Bump Pressure (psi)
7 7 7 545.0 0.0
Pipe Reciprocated? Reciprocation Stroke Length (m) Reciprocation Rate (spm) Pipe Rotated? Pipe RPM (rpm)
No 0.00 0 No
Depth tagged (mKB) Tag Method Depth Plug Drilled Out To (mKB) Drill Out Diameter (in) Drill Out Date
Cement
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Cement Cement from lot #39488 269 Class G + 78.0
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
112.50 310.00 100.0 1.62 6.89
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
15.50
Cement Fluid Additives
Add Type Conc
A-7 Accelerator or Retarder 2.0
FP-9LS Defoamer 0.05
Seawater
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Seawater Sea Water 68.2
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
8.60
Cement Fluid Additives
Add Type Conc
Original Hole
Wellbore Name Profile Type Kick Off Depth (mKB) Vertical Section Direction (°)
Original Hole Directional 1,066.80 285.00
Section Size (in) Act Top (mKB) Act Btm (mKB)
Surface 12 1/4 112.40 310.00
Intermediate 8 1/2 310.00 1,421.89
Production 6 1/8 1,421.89 3,749.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
Surface, 310.25mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Surface Original Hole 2/21/2008 310.25 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 Top of Wellhead to Rig Floor 15.07 0.00 15.07
1 KOP Wellhead Assembly 3.13 15.07 18.20
22 9.625" 40# N-80 BTC CSG. 9 5/8 8.835 40.00 N-80 BTC 265.94 18.20 284.14
1 FLOAT COLLAR 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 12.75 284.14 296.89
40ppf
1 CASING SHOE 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 13.36 296.89 310.25
40ppf
Intermediate, 1,419.46mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Intermediate Original Hole 2/22/2008 1,419.46 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 RKB to HGR 7 6.276 26.00 L-80 15.60 0.00 15.60
1 Hanger assembly 7 6.276 26.00 L-80 BTC 2.35 15.60 17.95
114 7" 23 ppf BTC casing N-80 7 6.366 23.00 N-80 BTC 1,376.64 17.95 1,394.59
1 Weatherford Float Assy 7 6.366 23.00 N-80 BTC 12.29 1,394.59 1,406.88
1 Weatherford Shoe 7 6.366 23.00 N-80 BTC 12.58 1,406.88 1,419.46
Intermediate Casing String, casing, 2/23/2008 02:30
Cementing Start Date Cementing End Date Wellbore
2/23/2008 2/23/2008 Original Hole
Evaluation Method Cement Evaluation Results
Cement Bond Log
Comment
7" Casing Cement Job Details¿ For tail slurry, planned to mix 682 cuft (495 sxs) of class G (+40% S8C) cement with 5.800 gps seawater + 0.000 gps +
0.050 gps FP-9L + 0.200 gps BJ Ultra + 0.300 gps CD-33L for 6.350 gps or 74.9 bbls of mixed fluid. Tail slurry weight was 15.9 ppg and the yield was
1.530 cuft/sx. Total calculated slurry volume (lead + tail) = 0.0 + 135.0 = 135.0 bbls. Pumped 1 bbls seawater preflush. BJ tested lines to 3,500 psig.
Mixed and pumped 135.0 bbls of 15.9 ppg tail slurry at 6.5 bpm and 460 psi. Actual slurry volume (lead + tail) = 135.0 bbls. Dropped wiper plug.
Displaced with 181.9 bbls seawater (planned displacement was 181.9 bbls) at 7.0 bpm and a final pressure of 2,500 psi. Bumped plug with 2,500 psi.
Bled back and float held. Cement in place at 3:57 hours. Estimated top of cement at 3,281' MD. Total of 25 Spirolizer centralizers run.
1, 1,000.00-1,419.00mKB
Top (mKB) Bottom (mKB) Full Return? Cmnt Rtrn (bbl) Top Plug? Bottom Plug?
1,000.00 1,419.00 Yes 0.0 Yes No
Initial Pump Rate (bbl/min) Final Pump Rate (bbl/min) Average Pump Rate (bbl/min) Final Pump Pressure (psi) Plug Bump Pressure (psi)
6 8 7 2,500.0 0.0
Pipe Reciprocated? Reciprocation Stroke Length (m) Reciprocation Rate (spm) Pipe Rotated? Pipe RPM (rpm)
No 0.00 0 No
Depth tagged (mKB) Tag Method Depth Plug Drilled Out To (mKB) Drill Out Diameter (in) Drill Out Date
Sea Water
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Sea Water 1.0
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
8.60
Cement Fluid Additives
Add Type Conc
Tail
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Tail Cement from lot #VN 495 Class G + 135.0
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
3,281.00 4,657.00 0.0 1.53 5.80
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
15.90
Cement Fluid Additives
Add Type Conc
FP-9L Defoamer 0.05
CD-33L Extender 0.3
BJ Ultra Gas Control Additive/Bonding Agent 0.2
Seawater
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Seawater 181.9
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
8.60
Cement Fluid Additives
Add Type Conc
Original Hole
Wellbore Name Profile Type Kick Off Depth (mKB) Vertical Section Direction (°)
Original Hole Directional 1,066.80 285.00
Section Size (in) Act Top (mKB) Act Btm (mKB)
Surface 12 1/4 112.40 310.00
Intermediate 8 1/2 310.00 1,421.89
Production 6 1/8 1,421.89 3,749.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
Surface, 310.25mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Surface Original Hole 2/21/2008 310.25 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 Top of Wellhead to Rig Floor 15.07 0.00 15.07
1 KOP Wellhead Assembly 3.13 15.07 18.20
22 9.625" 40# N-80 BTC CSG. 9 5/8 8.835 40.00 N-80 BTC 265.94 18.20 284.14
1 FLOAT COLLAR 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 12.75 284.14 296.89
40ppf
1 CASING SHOE 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 13.36 296.89 310.25
40ppf
Intermediate, 1,419.46mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Intermediate Original Hole 2/22/2008 1,419.46 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 RKB to HGR 7 6.276 26.00 L-80 15.60 0.00 15.60
1 Hanger assembly 7 6.276 26.00 L-80 BTC 2.35 15.60 17.95
114 7" 23 ppf BTC casing N-80 7 6.366 23.00 N-80 BTC 1,376.64 17.95 1,394.59
1 Weatherford Float Assy 7 6.366 23.00 N-80 BTC 12.29 1,394.59 1,406.88
1 Weatherford Shoe 7 6.366 23.00 N-80 BTC 12.58 1,406.88 1,419.46
Cement Plug # 1 Openhole, plug, 3/1/2008 04:00
Cementing Start Date Cementing End Date Wellbore
3/1/2008 3/1/2008 Original Hole
Evaluation Method Cement Evaluation Results
Comment
Rig up lines at 04:15.
Pressure test lines to 2500 psi at 04:22. Pump 10 Bbls 10.8 ppg MCS-O SpacerMix ahead. Mix & Pump 55.0 bbls 14.0 ppg cement with 0. 80 gps BJUltra,
0.50 gps CD-33L, 0.04 gps R-21LS, 0.05 gps FP-9L, yield=2.08 ft3/sx, total mix fluid=10.51 gps. Displace cement with 3 Bbls 10.8 ppg MCS-O SpacerMix
behind followed by 92.2 bbls 10.3 ppg WBM. Pipe on vacuum. CIP= 05:10
While pulling back to 2940m MD pipe became stuck at 3166m MD. Attempted to work free. Pipe came free at 430 k weight indicator.Continued to pull out
of hole to 2940m.
Top (mKB) Bottom (mKB) Full Return? Cmnt Rtrn (bbl) Top Plug? Bottom Plug?
No No No
Initial Pump Rate (bbl/min) Final Pump Rate (bbl/min) Average Pump Rate (bbl/min) Final Pump Pressure (psi) Plug Bump Pressure (psi)
Pipe Reciprocated? Reciprocation Stroke Length (m) Reciprocation Rate (spm) Pipe Rotated? Pipe RPM (rpm)
No No
Depth tagged (mKB) Tag Method Depth Plug Drilled Out To (mKB) Drill Out Diameter (in) Drill Out Date
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
Original Hole
Wellbore Name Profile Type Kick Off Depth (mKB) Vertical Section Direction (°)
Original Hole Directional 1,066.80 285.00
Section Size (in) Act Top (mKB) Act Btm (mKB)
Surface 12 1/4 112.40 310.00
Intermediate 8 1/2 310.00 1,421.89
Production 6 1/8 1,421.89 3,749.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
Surface, 310.25mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Surface Original Hole 2/21/2008 310.25 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 Top of Wellhead to Rig Floor 15.07 0.00 15.07
1 KOP Wellhead Assembly 3.13 15.07 18.20
22 9.625" 40# N-80 BTC CSG. 9 5/8 8.835 40.00 N-80 BTC 265.94 18.20 284.14
1 FLOAT COLLAR 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 12.75 284.14 296.89
40ppf
1 CASING SHOE 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 13.36 296.89 310.25
40ppf
Intermediate, 1,419.46mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Intermediate Original Hole 2/22/2008 1,419.46 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 RKB to HGR 7 6.276 26.00 L-80 15.60 0.00 15.60
1 Hanger assembly 7 6.276 26.00 L-80 BTC 2.35 15.60 17.95
114 7" 23 ppf BTC casing N-80 7 6.366 23.00 N-80 BTC 1,376.64 17.95 1,394.59
1 Weatherford Float Assy 7 6.366 23.00 N-80 BTC 12.29 1,394.59 1,406.88
1 Weatherford Shoe 7 6.366 23.00 N-80 BTC 12.58 1,406.88 1,419.46
Cement Plug #2 Openhole, plug, 3/1/2008 16:00
Cementing Start Date Cementing End Date Wellbore
3/1/2008 3/1/2008 Original Hole
Evaluation Method Cement Evaluation Results
Comment
Rig up lines at 20:00.
Pressure tested lines to 2500 psi at 20:07. Pump 10 Bbls 10.8 ppg MCS-O Spacer Mix ahead. Mix & Pump 17.4 bbls 14.0 ppg cement with 0. 80 gps BJ
Ultra, 0.50 gps CD-33L, 0.04 gps R-21LS, 0.05 gps FP-9L, yield=2.08 ft3/sx, total mix fluid=10.51 gps. Displace cement with 4.8 Bbls 10.8 ppg MCS-O
Spacer Mix behind followed by 65 bbls 10.3 ppg WBM. Pipe on vacuums. CIP= 20:51
Top (mKB) Bottom (mKB) Full Return? Cmnt Rtrn (bbl) Top Plug? Bottom Plug?
No No No
Initial Pump Rate (bbl/min) Final Pump Rate (bbl/min) Average Pump Rate (bbl/min) Final Pump Pressure (psi) Plug Bump Pressure (psi)
Pipe Reciprocated? Reciprocation Stroke Length (m) Reciprocation Rate (spm) Pipe Rotated? Pipe RPM (rpm)
No No
Depth tagged (mKB) Tag Method Depth Plug Drilled Out To (mKB) Drill Out Diameter (in) Drill Out Date
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
Original Hole
Wellbore Name Profile Type Kick Off Depth (mKB) Vertical Section Direction (°)
Original Hole Directional 1,066.80 285.00
Section Size (in) Act Top (mKB) Act Btm (mKB)
Surface 12 1/4 112.40 310.00
Intermediate 8 1/2 310.00 1,421.89
Production 6 1/8 1,421.89 3,749.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
Surface, 310.25mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Surface Original Hole 2/21/2008 310.25 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 Top of Wellhead to Rig Floor 15.07 0.00 15.07
1 KOP Wellhead Assembly 3.13 15.07 18.20
22 9.625" 40# N-80 BTC CSG. 9 5/8 8.835 40.00 N-80 BTC 265.94 18.20 284.14
1 FLOAT COLLAR 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 12.75 284.14 296.89
40ppf
1 CASING SHOE 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 13.36 296.89 310.25
40ppf
Intermediate, 1,419.46mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Intermediate Original Hole 2/22/2008 1,419.46 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 RKB to HGR 7 6.276 26.00 L-80 15.60 0.00 15.60
1 Hanger assembly 7 6.276 26.00 L-80 BTC 2.35 15.60 17.95
114 7" 23 ppf BTC casing N-80 7 6.366 23.00 N-80 BTC 1,376.64 17.95 1,394.59
1 Weatherford Float Assy 7 6.366 23.00 N-80 BTC 12.29 1,394.59 1,406.88
1 Weatherford Shoe 7 6.366 23.00 N-80 BTC 12.58 1,406.88 1,419.46
Cement Plug #3 Openhole, plug, 3/2/2008 00:00
Cementing Start Date Cementing End Date Wellbore
3/2/2008 3/2/2008 Original Hole
Evaluation Method Cement Evaluation Results
Comment
Rig up lines at 23:38.
Pressure tested lines to 2500 psi at 23:54. Mix & Pump 17.4 bbls 14.0 ppg cement with 0. 80 gps BJ Ultra, 0.50 gps CD-33L, 0.04 gps R-21LS, 0.05 gps
FP-9L, yield=2.08 ft3/sx, total mix fluid=10.51 gps. Displace cement 65 bbls with 10.3 ppg WBM. Pipe on vacuums. CIP= 00:18
Top (mKB) Bottom (mKB) Full Return? Cmnt Rtrn (bbl) Top Plug? Bottom Plug?
No No No
Initial Pump Rate (bbl/min) Final Pump Rate (bbl/min) Average Pump Rate (bbl/min) Final Pump Pressure (psi) Plug Bump Pressure (psi)
Pipe Reciprocated? Reciprocation Stroke Length (m) Reciprocation Rate (spm) Pipe Rotated? Pipe RPM (rpm)
No No
Depth tagged (mKB) Tag Method Depth Plug Drilled Out To (mKB) Drill Out Diameter (in) Drill Out Date
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
Original Hole
Wellbore Name Profile Type Kick Off Depth (mKB) Vertical Section Direction (°)
Original Hole Directional 1,066.80 285.00
Section Size (in) Act Top (mKB) Act Btm (mKB)
Surface 12 1/4 112.40 310.00
Intermediate 8 1/2 310.00 1,421.89
Production 6 1/8 1,421.89 3,749.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
Surface, 310.25mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Surface Original Hole 2/21/2008 310.25 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 Top of Wellhead to Rig Floor 15.07 0.00 15.07
1 KOP Wellhead Assembly 3.13 15.07 18.20
22 9.625" 40# N-80 BTC CSG. 9 5/8 8.835 40.00 N-80 BTC 265.94 18.20 284.14
1 FLOAT COLLAR 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 12.75 284.14 296.89
40ppf
1 CASING SHOE 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 13.36 296.89 310.25
40ppf
Intermediate, 1,419.46mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Intermediate Original Hole 2/22/2008 1,419.46 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 RKB to HGR 7 6.276 26.00 L-80 15.60 0.00 15.60
1 Hanger assembly 7 6.276 26.00 L-80 BTC 2.35 15.60 17.95
114 7" 23 ppf BTC casing N-80 7 6.366 23.00 N-80 BTC 1,376.64 17.95 1,394.59
1 Weatherford Float Assy 7 6.366 23.00 N-80 BTC 12.29 1,394.59 1,406.88
1 Weatherford Shoe 7 6.366 23.00 N-80 BTC 12.58 1,406.88 1,419.46
Cement Plug #4 Openhole, plug, 3/2/2008 01:00
Cementing Start Date Cementing End Date Wellbore
3/2/2008 3/2/2008 Original Hole
Evaluation Method Cement Evaluation Results
Comment
Rig up lines at 01:10
Pressure tested lines to 2500 psi at 01:20. Mix & Pump 17.8 bbls 14.0 ppg cement with
0. 80 gps BJ Ultra, 0.50 gps CD-33L, 0.04 gps R-21LS, 0.05 gps FP-9L, yield=2.08 ft3/sx, total mix fluid=10.51 gps. Displace cement 59.9 bbls with 10.3
ppg WBM. Pipe on vacuums. CIP= 01:42
Top (mKB) Bottom (mKB) Full Return? Cmnt Rtrn (bbl) Top Plug? Bottom Plug?
No No No
Initial Pump Rate (bbl/min) Final Pump Rate (bbl/min) Average Pump Rate (bbl/min) Final Pump Pressure (psi) Plug Bump Pressure (psi)
Pipe Reciprocated? Reciprocation Stroke Length (m) Reciprocation Rate (spm) Pipe Rotated? Pipe RPM (rpm)
No No
Depth tagged (mKB) Tag Method Depth Plug Drilled Out To (mKB) Drill Out Diameter (in) Drill Out Date
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
Original Hole
Wellbore Name Profile Type Kick Off Depth (mKB) Vertical Section Direction (°)
Original Hole Directional 1,066.80 285.00
Section Size (in) Act Top (mKB) Act Btm (mKB)
Surface 12 1/4 112.40 310.00
Intermediate 8 1/2 310.00 1,421.89
Production 6 1/8 1,421.89 3,749.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
Surface, 310.25mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Surface Original Hole 2/21/2008 310.25 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 Top of Wellhead to Rig Floor 15.07 0.00 15.07
1 KOP Wellhead Assembly 3.13 15.07 18.20
22 9.625" 40# N-80 BTC CSG. 9 5/8 8.835 40.00 N-80 BTC 265.94 18.20 284.14
1 FLOAT COLLAR 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 12.75 284.14 296.89
40ppf
1 CASING SHOE 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 13.36 296.89 310.25
40ppf
Intermediate, 1,419.46mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Intermediate Original Hole 2/22/2008 1,419.46 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 RKB to HGR 7 6.276 26.00 L-80 15.60 0.00 15.60
1 Hanger assembly 7 6.276 26.00 L-80 BTC 2.35 15.60 17.95
114 7" 23 ppf BTC casing N-80 7 6.366 23.00 N-80 BTC 1,376.64 17.95 1,394.59
1 Weatherford Float Assy 7 6.366 23.00 N-80 BTC 12.29 1,394.59 1,406.88
1 Weatherford Shoe 7 6.366 23.00 N-80 BTC 12.58 1,406.88 1,419.46
Cement Plug #5 Openhole, plug, 3/2/2008 02:00
Cementing Start Date Cementing End Date Wellbore
3/2/2008 3/2/2008 Original Hole
Evaluation Method Cement Evaluation Results
Comment
Rig up lines at 02:10
Pressure tested lines to 2500 psi at 02:14. Mix & Pump 17 bbls 14.0 ppg cement with
0. 80 gps BJ Ultra, 0.50 gps CD-33L, 0.04 gps R-21LS, 0.05 gps FP-9L, yield=2.08 ft3/sx, total mix fluid=10.51 gps. Displace cement 55 bbls with 10.3 ppg
WBM. Pipe on vacuums. CIP= 02:37
Top (mKB) Bottom (mKB) Full Return? Cmnt Rtrn (bbl) Top Plug? Bottom Plug?
No No No
Initial Pump Rate (bbl/min) Final Pump Rate (bbl/min) Average Pump Rate (bbl/min) Final Pump Pressure (psi) Plug Bump Pressure (psi)
Pipe Reciprocated? Reciprocation Stroke Length (m) Reciprocation Rate (spm) Pipe Rotated? Pipe RPM (rpm)
No No
Depth tagged (mKB) Tag Method Depth Plug Drilled Out To (mKB) Drill Out Diameter (in) Drill Out Date
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
Original Hole
Wellbore Name Profile Type Kick Off Depth (mKB) Vertical Section Direction (°)
Original Hole Directional 1,066.80 285.00
Section Size (in) Act Top (mKB) Act Btm (mKB)
Surface 12 1/4 112.40 310.00
Intermediate 8 1/2 310.00 1,421.89
Production 6 1/8 1,421.89 3,749.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
Surface, 310.25mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Surface Original Hole 2/21/2008 310.25 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 Top of Wellhead to Rig Floor 15.07 0.00 15.07
1 KOP Wellhead Assembly 3.13 15.07 18.20
22 9.625" 40# N-80 BTC CSG. 9 5/8 8.835 40.00 N-80 BTC 265.94 18.20 284.14
1 FLOAT COLLAR 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 12.75 284.14 296.89
40ppf
1 CASING SHOE 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 13.36 296.89 310.25
40ppf
Intermediate, 1,419.46mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Intermediate Original Hole 2/22/2008 1,419.46 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 RKB to HGR 7 6.276 26.00 L-80 15.60 0.00 15.60
1 Hanger assembly 7 6.276 26.00 L-80 BTC 2.35 15.60 17.95
114 7" 23 ppf BTC casing N-80 7 6.366 23.00 N-80 BTC 1,376.64 17.95 1,394.59
1 Weatherford Float Assy 7 6.366 23.00 N-80 BTC 12.29 1,394.59 1,406.88
1 Weatherford Shoe 7 6.366 23.00 N-80 BTC 12.58 1,406.88 1,419.46
Cement Plug #6 Openhole, plug, 3/2/2008 03:00
Cementing Start Date Cementing End Date Wellbore
3/2/2008 3/2/2008 Original Hole
Evaluation Method Cement Evaluation Results
Comment
Rig up lines at 03:05.
Pressure tested lines to 2500 psi at 03:14. Pump 10 Bbls 10.8 ppg MCS-O Spacer Mix ahead. Mix & Pump 14.2 bbls 14.0 ppg cement with 0. 80 gps BJ
Ultra, 0.50 gps CD-33L, 0.04 gps R-21LS, 0.05 gps FP-9L, yield=2.08 ft3/sx, total mix fluid=10.51 gps. Displace cement with 4.8 Bbls 10.8 ppg MCS-O
Spacer Mix behind followed by 46 bbls 10.3 ppg WBM. Pipe on vacuums. CIP= 03:41
Top (mKB) Bottom (mKB) Full Return? Cmnt Rtrn (bbl) Top Plug? Bottom Plug?
No No No
Initial Pump Rate (bbl/min) Final Pump Rate (bbl/min) Average Pump Rate (bbl/min) Final Pump Pressure (psi) Plug Bump Pressure (psi)
Pipe Reciprocated? Reciprocation Stroke Length (m) Reciprocation Rate (spm) Pipe Rotated? Pipe RPM (rpm)
No No
Depth tagged (mKB) Tag Method Depth Plug Drilled Out To (mKB) Drill Out Diameter (in) Drill Out Date
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
Original Hole
Wellbore Name Profile Type Kick Off Depth (mKB) Vertical Section Direction (°)
Original Hole Directional 1,066.80 285.00
Section Size (in) Act Top (mKB) Act Btm (mKB)
Surface 12 1/4 112.40 310.00
Intermediate 8 1/2 310.00 1,421.89
Production 6 1/8 1,421.89 3,749.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
Surface, 310.25mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Surface Original Hole 2/21/2008 310.25 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 Top of Wellhead to Rig Floor 15.07 0.00 15.07
1 KOP Wellhead Assembly 3.13 15.07 18.20
22 9.625" 40# N-80 BTC CSG. 9 5/8 8.835 40.00 N-80 BTC 265.94 18.20 284.14
1 FLOAT COLLAR 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 12.75 284.14 296.89
40ppf
1 CASING SHOE 9 5/8" GRADE 9 5/8 8.835 40.00 N-80 BTC 13.36 296.89 310.25
40ppf
Intermediate, 1,419.46mKB
Casing Description Wellbore Run Date Set Depth (mKB) Stick Up (mKB) Set Tension (kips)
Intermediate Original Hole 2/22/2008 1,419.46 0.00
Centralizers Scratchers
Top Conn
Jts Item Description OD (in) ID (in) Wt (lbs/ft) Grade Sz (in) Top Thread Len (m) Top (mKB) Btm (mKB)
1 RKB to HGR 7 6.276 26.00 L-80 15.60 0.00 15.60
1 Hanger assembly 7 6.276 26.00 L-80 BTC 2.35 15.60 17.95
114 7" 23 ppf BTC casing N-80 7 6.366 23.00 N-80 BTC 1,376.64 17.95 1,394.59
1 Weatherford Float Assy 7 6.366 23.00 N-80 BTC 12.29 1,394.59 1,406.88
1 Weatherford Shoe 7 6.366 23.00 N-80 BTC 12.58 1,406.88 1,419.46
Cement Squeeze, squeeze, 3/2/2008 18:00
Cementing Start Date Cementing End Date Wellbore
3/2/2008 3/2/2008 Original Hole
Evaluation Method Cement Evaluation Results
Cement Bond Log
Comment
Set 7" EZSV Cement Retainer at 13:00.
Pressure test lines to 2500 psi at 13:24. Pump injection test at 13:27, 1 BPM=890psi, 2 BPM=930psi, 3 BPM=970 psi, 4 BPM=1059 psi, Static = 686 psi.
Sting out of retainer at 13:30, Mix and pump 30 bbls 15.9 ppg cement with 0. 2 gps BJUltra, 0.3 gps CD-33L, 0.05 gps FP-9L, yield=1.53 ft3/sx, total mix
fluid=6.35 gps. Displace cement to stinger with 19.4 bbls 10.3 ppg WBM. Sting into retainer at 13:46, squeeze 20 bbls 10.3 ppg WBM to place 20 bbls
cement below retainer. Sting out of retainer at 13:53 pump 3 bbls 10.3ppg WBM to balance 10 bbls cement on top of retainer. CIP= 13:54
Pipe Reciprocated? Reciprocation Stroke Length (m) Reciprocation Rate (spm) Pipe Rotated? Pipe RPM (rpm)
No No
Depth tagged (mKB) Tag Method Depth Plug Drilled Out To (mKB) Drill Out Diameter (in) Drill Out Date
Fluid Type Fluid Description Amount (sacks) Class Volume Pumped (bbl)
Estimated Top (mKB) Estimated Bottom (mKB) Percent Excess Pumped (%) Yield (ft³/sack) Mix H20 Ratio (gal/sack)
Free Water (%) Density (lb/gal) Plastic Viscosity (cp) Thickening Time (hrs) 1st Compressive Strength (psi)
Page 52
Field: EXPLORATION WELL
Site: CV-5X
Well: CV-5X
Wellpath: CV-5X
0
0° 600
700
400
South(-)/North(+) [200m/in]
1400 7" Csg Actual 7" Csg Actual
200
B (Seis Tg2)
2100
0
D (Seis Tg4)
C (Seis Tg3)
3500
D (Seis Tg4)
-400
Well TD @ 3720 mMD/ 2974 mTVD
-700 0 700
-1000 -800 -600 -400 -200 0 200
Vertical Section at 285.00° [700m/in] West(-)/East(+) [200m/in]
VIETNAM
Map System: Universal Transverse Mercator Map Zone: UTM Zone 48, North 102E to 108E
Geo Datum: INDIAN75 (Everest 1830) Coordinate System: Site Centre
Sys Datum: Mean Sea Level Geomagnetic Model: bggm2007
Site: CV-5X
VIETNAM
Site Position: Northing: 933876.30 m Latitude: 8 26 31.488 N
From: Map Easting: 241377.80 m Longitude: 102 39 3.075 E
Position Uncertainty: 0.00 m North Reference: Grid
Water Depth: 76.20 m Grid Convergence: -0.35 deg
Survey
MD Incl Azim TVD +N/-S +E/-W VS DLS Build Turn Tool/Comment
m deg deg m m m m deg/30m deg/30m deg/30m
0.00 0.00 0.00 0.00 1.47 7.08 -6.46 0.000 0.000 0.000 TIE LINE
112.40 0.00 0.00 112.40 1.47 7.08 -6.46 0.000 0.000 0.000 MWD+SCC
310.61 6.01 218.50 310.25 -6.65 0.62 -2.32 0.909 0.909 0.000 9 5/8" Csg Actual
317.00 6.20 218.50 316.60 -7.18 0.20 -2.05 0.909 0.909 0.000 MWD+SCC
346.00 6.30 218.30 345.43 -9.66 -1.77 -0.79 0.106 0.103 -0.207 MWD+SCC
375.00 7.90 224.70 374.21 -12.32 -4.15 0.82 1.844 1.655 6.621 MWD+SCC
403.00 5.60 228.70 402.01 -14.59 -6.53 2.53 2.514 -2.464 4.286 MWD+SCC
432.00 1.70 212.30 430.95 -15.89 -7.83 3.45 4.136 -4.034 -16.966 MWD+SCC
461.00 0.70 185.90 459.94 -16.43 -8.08 3.55 1.156 -1.034 -27.310 MWD+SCC
490.00 1.00 61.10 488.94 -16.49 -7.87 3.34 1.565 0.310 -129.103 MWD+SCC
519.00 2.50 35.80 517.92 -15.85 -7.28 2.93 1.709 1.552 -26.172 MWD+SCC
548.00 2.60 34.20 546.90 -14.79 -6.54 2.49 0.127 0.103 -1.655 MWD+SCC
577.00 2.50 40.20 575.87 -13.77 -5.76 2.00 0.295 -0.103 6.207 MWD+SCC
606.00 2.50 39.10 604.84 -12.79 -4.96 1.48 0.050 0.000 -1.138 MWD+SCC
635.00 2.30 37.00 633.81 -11.84 -4.21 1.00 0.226 -0.207 -2.172 MWD+SCC
693.00 2.20 36.10 691.77 -10.01 -2.85 0.16 0.055 -0.052 -0.466 MWD+SCC
722.00 2.20 35.40 720.75 -9.10 -2.20 -0.23 0.028 0.000 -0.724 MWD+SCC
751.00 2.00 30.70 749.73 -8.22 -1.62 -0.56 0.273 -0.207 -4.862 MWD+SCC
780.00 2.30 26.10 778.71 -7.26 -1.10 -0.81 0.358 0.310 -4.759 MWD+SCC
809.00 2.40 25.70 807.68 -6.19 -0.59 -1.04 0.105 0.103 -0.414 MWD+SCC
838.00 2.20 22.70 836.66 -5.13 -0.11 -1.22 0.241 -0.207 -3.103 MWD+SCC
867.00 2.70 37.50 865.63 -4.07 0.52 -1.56 0.830 0.517 15.310 MWD+SCC
896.00 2.60 37.70 894.60 -3.01 1.34 -2.07 0.104 -0.103 0.207 MWD+SCC
925.00 2.80 41.80 923.57 -1.96 2.22 -2.65 0.287 0.207 4.241 MWD+SCC
954.00 2.70 42.10 952.54 -0.93 3.15 -3.28 0.105 -0.103 0.310 MWD+SCC
983.00 2.60 41.40 981.51 0.07 4.04 -3.88 0.109 -0.103 -0.724 MWD+SCC
1012.00 2.20 45.30 1010.48 0.96 4.87 -4.46 0.447 -0.414 4.034 MWD+SCC
Halliburton Company
Survey Report
Company: CHEVRON VIETNAM Date: 28/03/2008 Time: 13:27:06 Page: 2
Field: EXPLORATION WELL Co-ordinate(NE) Reference: Site: CV-5X, Grid North
Site: CV-5X Vertical (TVD) Reference: RKB CV-5X 34.4
Well: CV-5X Section (VS) Reference: Site (0.00N,0.00E,285.00Azi)
Wellpath: CV-5X Survey Calculation Method: Minimum Curvature Db: Sybase
Survey
MD Incl Azim TVD +N/-S +E/-W VS DLS Build Turn Tool/Comment
m deg deg m m m m deg/30m deg/30m deg/30m
1041.00 1.70 47.20 1039.46 1.64 5.58 -4.97 0.521 -0.517 1.966 MWD+SCC
1070.00 1.30 0.40 1068.45 2.26 5.90 -5.11 1.290 -0.414 -48.414 MWD+SCC
1099.00 2.20 314.40 1097.44 2.98 5.50 -4.54 1.654 0.931 -47.586 MWD+SCC
1128.00 2.60 316.30 1126.42 3.85 4.65 -3.50 0.422 0.414 1.966 MWD+SCC
1157.00 5.20 297.80 1155.35 4.94 3.03 -1.65 2.954 2.690 -19.138 MWD+SCC
1186.00 7.70 287.20 1184.16 6.12 0.01 1.57 2.854 2.586 -10.966 MWD+SCC
1215.00 11.10 291.10 1212.77 7.70 -4.45 6.29 3.576 3.517 4.034 MWD+SCC
1244.00 15.20 287.20 1241.00 9.83 -10.69 12.87 4.337 4.241 -4.034 MWD+SCC
1273.00 19.50 282.50 1268.68 12.01 -19.05 21.51 4.675 4.448 -4.862 MWD+SCC
1301.00 23.70 282.80 1294.71 14.27 -29.10 31.80 4.502 4.500 0.321 MWD+SCC
1330.00 28.00 284.80 1320.80 17.30 -41.37 44.44 4.538 4.448 2.069 MWD+SCC
1359.00 27.80 284.40 1346.43 20.72 -54.50 58.01 0.283 -0.207 -0.414 MWD+SCC
1388.00 27.80 283.70 1372.08 24.00 -67.62 71.53 0.338 0.000 -0.724 MWD+SCC
1405.00 26.60 283.00 1387.20 25.80 -75.18 79.30 2.192 -2.118 -1.235 MWD+SCC
1419.46 27.05 283.18 1400.11 27.27 -81.54 85.82 0.943 0.928 0.368 7" Csg Actual
1447.00 27.90 283.50 1424.54 30.21 -93.90 98.52 0.943 0.929 0.352 MWD+SCC
1476.00 27.80 283.40 1450.18 33.36 -107.08 112.06 0.114 -0.103 -0.103 MWD+SCC
1505.00 27.80 283.20 1475.83 36.47 -120.24 125.58 0.096 0.000 -0.207 MWD+SCC
1534.00 27.50 283.20 1501.52 39.54 -133.34 139.03 0.310 -0.310 0.000 MWD+SCC
1592.00 27.00 282.80 1553.08 45.52 -159.22 165.57 0.275 -0.259 -0.207 MWD+SCC
1621.00 26.90 282.80 1578.94 48.43 -172.04 178.71 0.103 -0.103 0.000 MWD+SCC
1650.00 26.60 282.60 1604.83 51.30 -184.77 191.75 0.324 -0.310 -0.207 MWD+SCC
1679.00 26.10 282.50 1630.82 54.09 -197.33 204.61 0.519 -0.517 -0.103 MWD+SCC
1708.00 25.60 282.30 1656.92 56.81 -209.68 217.24 0.525 -0.517 -0.207 MWD+SCC
1737.00 26.00 282.50 1683.03 59.52 -222.01 229.85 0.423 0.414 0.207 MWD+SCC
1766.00 26.30 282.60 1709.06 62.30 -234.49 242.62 0.314 0.310 0.103 MWD+SCC
1795.00 25.60 282.50 1735.13 65.06 -246.87 255.30 0.726 -0.724 -0.103 MWD+SCC
1824.00 26.20 282.60 1761.22 67.81 -259.24 267.95 0.622 0.621 0.103 MWD+SCC
1853.00 26.30 282.80 1787.23 70.63 -271.75 280.77 0.138 0.103 0.207 MWD+SCC
1882.00 26.50 283.00 1813.21 73.51 -284.32 293.66 0.226 0.207 0.207 MWD+SCC
1911.00 26.30 283.20 1839.18 76.43 -296.88 306.54 0.226 -0.207 0.207 MWD+SCC
1940.00 25.80 283.20 1865.23 79.34 -309.28 319.27 0.517 -0.517 0.000 MWD+SCC
1969.00 25.50 282.80 1891.38 82.16 -321.51 331.82 0.358 -0.310 -0.414 MWD+SCC
1998.00 25.80 283.00 1917.52 84.96 -333.74 344.36 0.323 0.310 0.207 MWD+SCC
2027.00 25.80 283.20 1943.63 87.82 -346.04 356.98 0.090 0.000 0.207 MWD+SCC
2056.00 25.20 283.20 1969.80 90.68 -358.19 369.46 0.621 -0.621 0.000 MWD+SCC
2085.00 25.40 283.20 1996.02 93.51 -370.26 381.84 0.207 0.207 0.000 MWD+SCC
2114.00 25.20 283.00 2022.24 96.31 -382.33 394.23 0.225 -0.207 -0.207 MWD+SCC
2143.00 25.80 283.00 2048.41 99.12 -394.49 406.71 0.621 0.621 0.000 MWD+SCC
2172.00 25.90 283.00 2074.51 101.97 -406.81 419.34 0.103 0.103 0.000 MWD+SCC
2201.00 25.40 283.00 2100.66 104.79 -419.05 431.89 0.517 -0.517 0.000 MWD+SCC
2230.00 25.60 283.20 2126.83 107.62 -431.21 444.37 0.225 0.207 0.207 MWD+SCC
2259.00 26.20 283.20 2152.92 110.51 -443.54 457.03 0.621 0.621 0.000 MWD+SCC
2288.00 26.10 283.20 2178.95 113.43 -455.98 469.80 0.103 -0.103 0.000 MWD+SCC
2317.00 26.20 282.60 2204.98 116.29 -468.44 482.57 0.292 0.103 -0.621 MWD+SCC
2346.00 25.90 282.50 2231.03 119.05 -480.87 495.30 0.314 -0.310 -0.103 MWD+SCC
2375.00 25.80 282.10 2257.13 121.75 -493.22 507.93 0.208 -0.103 -0.414 MWD+SCC
2404.00 26.60 282.30 2283.15 124.45 -505.74 520.72 0.833 0.828 0.207 MWD+SCC
2433.00 27.00 282.50 2309.04 127.26 -518.51 533.78 0.424 0.414 0.207 MWD+SCC
2462.00 26.70 282.50 2334.91 130.10 -531.30 546.86 0.310 -0.310 0.000 MWD+SCC
2491.00 26.50 282.10 2360.84 132.86 -543.98 559.83 0.278 -0.207 -0.414 MWD+SCC
2520.00 25.90 281.90 2386.86 135.52 -556.51 572.62 0.627 -0.621 -0.207 MWD+SCC
2549.00 25.50 282.10 2412.99 138.14 -568.81 585.18 0.423 -0.414 0.207 MWD+SCC
2578.00 25.40 281.80 2439.18 140.72 -581.00 597.62 0.169 -0.103 -0.310 MWD+SCC
2607.00 25.20 281.60 2465.40 143.23 -593.14 610.00 0.225 -0.207 -0.207 MWD+SCC
2636.00 25.70 281.80 2491.58 145.76 -605.34 622.44 0.525 0.517 0.207 MWD+SCC
2665.00 26.20 281.40 2517.66 148.31 -617.77 635.11 0.548 0.517 -0.414 MWD+SCC
2694.00 25.60 281.40 2543.75 150.81 -630.19 647.75 0.621 -0.621 0.000 MWD+SCC
Halliburton Company
Survey Report
Company: CHEVRON VIETNAM Date: 28/03/2008 Time: 13:27:06 Page: 3
Field: EXPLORATION WELL Co-ordinate(NE) Reference: Site: CV-5X, Grid North
Site: CV-5X Vertical (TVD) Reference: RKB CV-5X 34.4
Well: CV-5X Section (VS) Reference: Site (0.00N,0.00E,285.00Azi)
Wellpath: CV-5X Survey Calculation Method: Minimum Curvature Db: Sybase
Survey
MD Incl Azim TVD +N/-S +E/-W VS DLS Build Turn Tool/Comment
m deg deg m m m m deg/30m deg/30m deg/30m
2723.00 25.60 281.20 2569.90 153.27 -642.48 660.25 0.089 0.000 -0.207 MWD+SCC
2752.00 25.60 281.40 2596.05 155.72 -654.76 672.76 0.089 0.000 0.207 MWD+SCC
2781.00 25.30 281.20 2622.24 158.17 -666.98 685.19 0.323 -0.310 -0.207 MWD+SCC
2809.00 26.10 281.40 2647.47 160.55 -678.89 697.31 0.862 0.857 0.214 MWD+SCC
2838.00 26.50 281.10 2673.47 163.05 -691.49 710.13 0.436 0.414 -0.310 MWD+SCC
2867.00 26.20 280.70 2699.45 165.49 -704.13 722.97 0.361 -0.310 -0.414 MWD+SCC
2896.00 25.60 280.50 2725.54 167.82 -716.58 735.60 0.627 -0.621 -0.207 MWD+SCC
2925.00 25.30 280.40 2751.73 170.08 -728.84 748.02 0.314 -0.310 -0.103 MWD+SCC
2983.00 25.60 280.50 2804.10 174.60 -753.35 772.87 0.157 0.155 0.052 MWD+SCC
3012.00 26.00 280.50 2830.21 176.90 -765.76 785.45 0.414 0.414 0.000 MWD+SCC
3041.00 25.60 280.40 2856.32 179.19 -778.17 798.03 0.416 -0.414 -0.103 MWD+SCC
3070.00 25.60 280.20 2882.47 181.43 -790.50 810.52 0.089 0.000 -0.207 MWD+SCC
3099.00 25.00 279.60 2908.69 183.56 -802.71 822.87 0.675 -0.621 -0.621 MWD+SCC
3128.00 24.70 279.10 2935.00 185.54 -814.73 834.99 0.379 -0.310 -0.517 MWD+SCC
3157.00 23.40 278.20 2961.48 187.32 -826.42 846.74 1.397 -1.345 -0.931 MWD+SCC
3186.00 22.60 277.20 2988.18 188.84 -837.64 857.98 0.921 -0.828 -1.034 MWD+SCC
3215.00 23.10 276.80 3014.90 190.21 -848.82 869.13 0.542 0.517 -0.414 MWD+SCC
3244.00 22.60 276.70 3041.63 191.54 -860.00 880.27 0.519 -0.517 -0.103 MWD+SCC
3302.00 21.90 276.50 3095.31 194.06 -881.82 902.00 0.364 -0.362 -0.103 MWD+SCC
3331.00 21.90 275.90 3122.22 195.23 -892.57 912.69 0.232 0.000 -0.621 MWD+SCC
3389.00 23.70 275.20 3175.68 197.40 -914.94 934.86 0.942 0.931 -0.362 MWD+SCC
3418.00 24.90 275.60 3202.11 198.52 -926.82 946.62 1.253 1.241 0.414 MWD+SCC
3446.00 24.80 275.10 3227.52 199.62 -938.54 958.22 0.249 -0.107 -0.536 MWD+SCC
3475.00 24.30 274.50 3253.90 200.63 -950.55 970.08 0.578 -0.517 -0.621 MWD+SCC
3504.00 23.50 273.80 3280.41 201.48 -962.26 981.62 0.878 -0.828 -0.724 MWD+SCC
3562.00 22.10 273.50 3333.88 202.91 -984.69 1003.66 0.727 -0.724 -0.155 MWD+SCC
3591.00 21.40 272.60 3360.81 203.48 -995.42 1014.17 0.802 -0.724 -0.931 MWD+SCC
3620.00 21.10 272.10 3387.84 203.92 -1005.93 1024.43 0.363 -0.310 -0.517 MWD+SCC
3678.00 20.20 270.80 3442.12 204.44 -1026.37 1044.31 0.522 -0.466 -0.672 MWD+SCC
3707.00 19.70 270.10 3469.37 204.52 -1036.27 1053.89 0.573 -0.517 -0.724 MWD+SCC
3736.00 19.70 270.50 3496.68 204.57 -1046.04 1063.34 0.139 0.000 0.414 MWD+SCC
3749.00 19.70 270.50 3508.92 204.61 -1050.42 1067.59 0.000 0.000 0.000 MWD+SCC
3749.00 19.70 270.50 3508.92 204.61 -1050.42 1067.59 0.068 0.000 0.000 PROJECTED to TD
Casing Points
MD TVD Diameter Hole Size Name
m m in in
310.61 310.25 9.625 12.250 9 5/8" Csg Actual
1419.46 1400.11 7.000 8.500 7" Csg Actual
Client : Chevron Vietnam
Well Name : CV-5X
Field :
Slot :
Rig : Vicksburg
BHA Report Job # : TH-DD-0005691616 BHA# 2
BHA# 2 : Date In :22/02/2008 MD In (m) : 310 TVD In (m) : 310 Date Out: 22/02/2008 MD Out (m): 1422 TVD Out (m): 1402
BIT DATA
Bit # OD (in) MFR Style Serial# Nozzles (/32's) TFA (in²) Dull Condition
1 8.500 Hughes HCM604 7210910 6x14 0.902 1-1-WT-GN-X-I-NO-TD
MOTOR DATA
Run # OD (in) MFR Model Serial# Bend Nzl (/32's) Avg Dif (psi) Cum Circ Hrs
7.000 SSDS SperryDrill 700021 0.00° 194 13.25
COMPONENT DATA
Item Description Serial OD ID Gauge Weight Top Con Length Bit - Center
# # (in) (in) (in) (lbs/ft) (m) Blade (m)
1 HCM604 PDC 7210910 8.500 2.500 8.500 176.66 P 4-1/2" Reg 0.34
2 7" SperryDrill Lobe 7/8 - 7.5 stg 700021 7.000 4.753 70.69 B 4-1/2" IF 8.66
3 6 3/4" Float Sub 10761264 6.750 2.813 100.77 B 4-1/2" IF 0.96
4 MWD Hang Off Collar 231801 6.750 2.813 101.00 B 4-1/2" IF 8.56
5 6 3/4" Non Mag Screen Sub STH0455 6.750 2.813 100.77 B 4-1/2" IF 1.92
6 4" XTF 39 B x 4 1/2 IF P(Chevron) Chevron 6.750 2.813 100.77 B XTF-39 0.56
7 24 x 4" HWDP 4.000 2.563 29.70 B XTF-39 225.41
________
246.41
Parameter Min Max Ave Activity Hrs BHA Weight (lb) Drill String OD(in) Len (m)
WOB (klbs) : 5 15 12 Drilling : 11.50 in Air (Total) : 28142
RPM (rpm) : 20 120 120 Reaming : 0.00 in Mud (Total) :
Flow (gpm) : 550 800 800 Circ-Other : 1.75 in Air (Bel Jars) : 0
SPP (psi) : 2600 3650 3273 Total : 13.25 in Mud (Bel Jars) :
PERFORMANCE
In Out Distance (m) ROP (m/hr) Build (°/100') Turn (°/100') DLS (°/100')
Inclination (deg) 5.99 27.13 Oriented : 261.00 35
Azimuth (deg) 218.50 283.21 Rotated : 851.00 116
Total : 1112.00 97 0.58 1.77 0.69
COMMENTS
Client : Chevron Vietnam
Well Name : CV-5X
Field :
Slot :
Rig : Vicksburg
BHA Report Job # : TH-DD-0005691616 BHA# 3
BHA# 3 : Date In :23/02/2008 MD In (m) : 1422 TVD In (m) : 1402 Date Out: 25/02/2008 MD Out (m): 3197 TVD Out (m): 2998
BIT DATA
Bit # OD (in) MFR Style Serial# Nozzles (/32's) TFA (in²) Dull Condition
2 6.125 Reed Hycalog DSR516M 120627 5x11 0.464 4-8-WT-GN-X-4-ER-ROP
MOTOR DATA
Run # OD (in) MFR Model Serial# Bend Nzl (/32's) Avg Dif (psi) Cum Circ Hrs
COMPONENT DATA
Item Description Serial OD ID Gauge Weight Top Con Length Bit - Center
# # (in) (in) (in) (lbs/ft) (m) Blade (m)
1 PDC DSR516M-C1 120627 6.125 2.500 6.125 83.69 P 3-1/2" Reg 0.21
2 6-1/8" Modular NB Stabilizer 10891415 4.750 2.250 6.125 46.84 B HT-38 0.75 0.58
3 1ft x 5" Extension sub 10715718 5.000 2.250 53.37 B HT-38 0.29
4 Adjustable Gauge Stabilizer 325058 5.000 2.250 5.625 53.37 B HT-38 3.20 2.85
5 5" Non-Mag Hang Off Collar 10961179 5.000 2.250 53.37 B 3-1/2" IF 9.55
6 6'' Integral Blade Stabilizer(w/screen) DOTS-17403 5.000 2.250 6.000 53.37 B 3-1/2" IF 1.23 14.62
7 Cross Over Sub S-56664-9 5.000 2.250 53.37 B XTF-39 0.64
8 24 x 4" HWDP 4.000 2.563 29.70 B XTF-39 225.41
________
241.28
Parameter Min Max Ave Activity Hrs BHA Weight (lb) Drill String OD(in) Len (m)
WOB (klbs) : 8 14 10 Drilling : 42.25 in Air (Total) : 24748
RPM (rpm) : 180 240 214 Reaming : 0.00 in Mud (Total) : 20938
Flow (gpm) : 260 304 288 Circ-Other : 2.25 in Air (Bel Jars) : 0
SPP (psi) : 2460 3390 2943 Total : 44.50 in Mud (Bel Jars) : 0
PERFORMANCE
In Out Distance (m) ROP (m/hr) Build (°/100') Turn (°/100') DLS (°/100')
Inclination (deg) 27.13 22.79 Oriented : 0.00 0
Azimuth (deg) 283.21 277.05 Rotated : 1775.00 42
Total : 1775.00 42 -0.07 -0.11 0.09
COMMENTS
The assembly worked well with 11 undergauge stand sets & 49 full gauge stand sets.
UG sets produced a strong overpowering response to FG.UG build response was about 4x the drop response of FG.
(The MNB & 6" St Stabs used were brand new).
The trajectory was maintained at +/- 25°-26° inclination however when the TD target became un-missable the inclination was allowed to degrade
to reduce the drilled depth. As usual as the bit began to wear LHW increased.
In conclusion
Further confirmation that a 5 blade bit ( whatever company) should be run over these longer 6 1/8" sections due to the generally more inherent
benign directional response.
Client : Chevron Vietnam
Well Name : CV-5X
Field :
Slot :
Rig : Vicksburg
BHA Report Job # : TH-DD-0005691616 BHA# 4
BHA# 4 : Date In :25/02/2008 MD In (m) : 3197 TVD In (m) : 2998 Date Cur: 02/03/2008 MD Cur (m): 3749 TVD Cur (m): 3509
BIT DATA
Bit # OD (in) MFR Style Serial# Nozzles (/32's) TFA (in²) Dull Condition
3 6.125 Security DBS FMH3543ZR 11080326 3x10, 2x12 0.451 1-8-RO-T -X-1-CT-TD
MOTOR DATA
Run # OD (in) MFR Model Serial# Bend Nzl (/32's) Avg Dif (psi) Cum Circ Hrs
COMPONENT DATA
Item Description Serial OD ID Gauge Weight Top Con Length Bit - Center
# # (in) (in) (in) (lbs/ft) (m) Blade (m)
1 PDC FMH3543ZR 11080326 6.125 2.000 6.125 89.71 P 3-1/2" Reg 0.21
2 6-1/8" Modular NB Stabilizer 10891415 4.750 2.250 6.125 46.84 B HT-38 0.75 0.59
3 1ft x 5" Extension sub 10715718 5.000 2.250 53.37 B HT-38 0.29
4 Adjustable Gauge Stabilizer 325058 5.000 2.250 5.625 53.37 B HT-38 3.20 2.85
5 5" Non-Mag Hang Off Collar 10961179 5.000 2.250 53.37 B 3-1/2" IF 9.55
6 6'' Integral Blade Stabilizer(w/screen) DOTS-17403 5.000 2.250 6.000 53.37 B 3-1/2" IF 1.23 14.62
7 Cross Over Sub S-56664-9 5.000 2.250 53.37 B XTF-39 0.64
8 24 x 4" HWDP 4.000 2.563 29.70 B XTF-39 225.41
________
241.29
Parameter Min Max Ave Activity Hrs BHA Weight (lb) Drill String OD(in) Len (m)
WOB (klbs) : 8 12 11 Drilling : 23.00 in Air (Total) : 24753
RPM (rpm) : 150 180 156 Reaming : 0.00 in Mud (Total) : 20943
Flow (gpm) : 250 260 257 Circ-Other : 2.50 in Air (Bel Jars) : 0
SPP (psi) : 2730 3170 2918 Total : 25.50 in Mud (Bel Jars) : 0
PERFORMANCE
In Out Distance (m) ROP (m/hr) Build (°/100') Turn (°/100') DLS (°/100')
Inclination (deg) 22.79 19.70 Oriented : 0.00 0
Azimuth (deg) 277.05 270.68 Rotated : 552.00 24
Total : 552.00 24 -0.17 -0.35 0.21
COMMENTS
Page : 1
Client : Chevron Vietnam Field :
Well Name : CV-5X Slot :
Rig : Vicksburg Job # : TH-DD-0005691616
Survey and Drilling Parameters North Ref : Mag Declination : ° VS Dir : 285.00° (from 1.5N, 7.1E)
0.00 0.00 0.00 0.0 0.0 1.5 7.1 0.00 0.00 0.00 1 Tieon
112.40 0.00 0.00 112.4 0.0 1.5 7.1 0.00 0.00 0.00 6 20 550 1
317.00 6.20 218.50 316.6 4.4 -7.2 0.2 0.92 0.92 0.00 10 120 800 2600 248 2
346.00 6.30 218.30 345.4 5.7 -9.7 -1.8 0.11 0.11 -0.21 10 120 800 2650 290 2
375.00 7.90 224.70 374.2 7.3 -12.3 -4.2 1.87 1.68 6.73 10 120 800 2700 158 2
403.00 5.60 228.70 402.0 9.0 -14.6 -6.5 2.55 -2.50 4.35 5 800 2700 390 403 170R 2
432.00 1.70 212.30 430.9 9.9 -15.9 -7.8 4.20 -4.10 -17.24 10 800 2700 403 407 170R 2
418 432 LS 2
461.00 0.70 185.90 459.9 10.0 -16.4 -8.1 1.17 -1.05 0.00 10 120 800 2750 432 438 LS 204 2
490.00 1.00 61.10 488.9 9.8 -16.5 -7.9 1.59 0.32 0.00 10 120 800 2850 477 483 55m 181 2
519.00 2.50 35.80 517.9 9.4 -15.9 -7.3 1.74 1.58 0.00 800 2990 506 512 35m 156 2
548.00 2.60 34.20 546.9 8.9 -14.8 -6.5 0.13 0.11 -1.68 10 120 800 2990 210 2
577.00 2.50 40.20 575.9 8.5 -13.8 -5.8 0.30 -0.11 6.31 10 120 800 2990 299 2
606.00 2.50 39.10 604.8 7.9 -12.8 -5.0 0.05 0.00 -1.16 10 120 800 3000 287 2
635.00 2.30 37.00 633.8 7.5 -11.8 -4.2 0.23 -0.21 -2.21 10 120 800 3050 299 2
693.00 2.20 36.10 691.8 6.6 -10.0 -2.9 0.06 -0.05 -0.47 15 120 800 3350 296 2
722.00 2.20 35.40 720.7 6.2 -9.1 -2.2 0.03 0.00 -0.74 15 120 800 3350 302 2
752.00 2.00 30.70 750.7 5.9 -8.2 -1.6 0.27 -0.20 -4.78 15 120 800 3400 284 2
780.00 2.30 26.10 778.7 5.6 -7.3 -1.1 0.38 0.33 -5.01 15 120 800 3400 191 2
809.00 2.40 25.70 807.7 5.4 -6.2 -0.6 0.11 0.11 -0.42 15 120 800 3400 219 2
838.00 2.20 22.70 836.7 5.2 -5.1 -0.1 0.25 -0.21 -3.15 15 120 800 3500 219 2
867.00 2.70 37.50 865.6 4.9 -4.1 0.5 0.84 0.53 15.56 15 120 800 3450 854 858 110m 100 2
896.00 2.60 37.70 894.6 4.4 -3.0 1.3 0.11 -0.11 0.21 15 120 800 3450 147 2
925.00 2.80 41.80 923.6 3.8 -2.0 2.2 0.29 0.21 4.31 15 120 800 3450 191 2
954.00 2.70 42.10 952.5 3.2 -0.9 3.1 0.11 -0.11 0.32 15 120 800 3450 218 2
983.00 2.60 41.40 981.5 2.6 0.1 4.0 0.11 -0.11 -0.74 15 120 800 3450 190 2
1012.00 2.20 45.30 1010.5 2.0 1.0 4.9 0.45 -0.42 4.10 15 120 800 3450 998 1001 255m 130 2
1041.00 1.70 47.20 1039.5 1.5 1.6 5.6 0.53 -0.53 2.00 15 120 800 3450 1027 1030 225m 110 2
1070.00 1.30 0.40 1068.5 1.3 2.3 5.9 1.31 -0.42 -49.19 5 800 3450 1067 1070 285m 79 2
1099.00 2.20 314.40 1097.4 1.9 3.0 5.5 1.68 0.95 -48.35 5 800 3450 1070 1077 285m 74 2
Page : 2
Client : Chevron Vietnam Field :
Well Name : CV-5X Slot :
Rig : Vicksburg Job # : TH-DD-0005691616
Survey and Drilling Parameters North Ref : Mag Declination : ° VS Dir : 285.00° (from 1.5N, 7.1E)
Drilling 79.25 50
Miscellaneous 27.75 30
Tripping 23.75
20 17
PU/LD BHA 9.75
120
200
110
96.7
100
400
90
600 80
ROP (m/hr)
70
800
60
50
1000 42.0
40
1200 30 24.0
20
1400
10
0
1600
Measured Depth (m)
1 2 3 4
2000
Footage per BHA
2200 1775
1800
2400 1600
2600 1400
Footage Drilled (m)
1200 1112
2800
1000
3000
800
3200 600 552
200
3600
0
3800 1 2 3 4
0 2 4 6 8 10 12 14 16 BHA Number
Day Rotated Oriented
Well Summary:
Drilling Fluids
Page 66
12-1/4” Section
Details of operation:
After towing and waiting on weather to preload, the well was Spudded on
February 21-08. The 9 5/8” casing was drilled to 310mTD using 9.8 ppg WBM and
seawater. The WBM / seawater combination gave 9.2 ppg at the bit. The casing
was cemented and preparations made for next section.
The mud for this section was Xantham (Duovis) 9.8-10.0 ppg. It was pumped to
the hole as split stream with seawater to maintain 9.2 ppg in the hole.
Hole Problems:
None
Other Problems:
None
Cost Comments:
The cost for this section was $ 12,120.00. The cost included the mud built for the
end of the 8.5” section. This mud has to be prepared ahead of time for speed of
operation.
Page 67
8-1/2” Section
Details of operation:
7” casing @ 1419.25 m MD
8 ½ ” hole drilled from 310 m
8 ½” hole drilled to 1422 m
Cost for section $ 7,105.00
Cost / m $ 4.99
Cost / bbl $9.60
Volume built 782 bbl
Volume used 740 bbl
The 8.5” BHA was run in the hole and cement was tagged at 280m. The float
collar and shoe were drilled out at 298 and 310m. 1.5m of new hole was drilled
and a LOT test performed – 12.7 ppg EMW at 220psi. drilling then continued to
1422mTD , 1402m TVD. A 52 bbls 12 ppg HiWt pill was pumped and circulated
round. Circulation continued till the shakers were clean. The hole was then
displaced to 9.2 ppg PHPA WBM. A slug was pumped after a flow check and the
drill string pulled from the hole. Casing was run in to 1419.25m with no problems
recorded and BJ performed the cement job. The string was pulled to rig up 6.125”
BHA.
The section was drilled with seawater to TD and a 12 ppg HiWt pill circulated
round. This pill brought a large increase in cuttings at the shakers – all dumped
overboard. The hole was then displaced to 9.2ppg WBM/PHPA. Any remaining
WBM from this section was saved in nthe surface pits for the plug and abandon
operation.
Hole Problems:
None
Other Problems:
None
Page 68
Solids Control Equipment Performance:
Solid control equipment which has used in this section was 4 ea Derrick/Super G
4 Panel shale shakers, All shale shaker were ran all the time while drilling with
seawater. The shakers were on to collect samples from this section.
Cost Comments:
The practices above mentioned proved to be sufficient and effective and could be
continued for similar wells in this area.
Page 69
6-1/8” Section
Details of operation:
3 ½” liner @ N/a
6 ⅛ ” hole drilled from 1422 m
6 ⅛” hole drilled to 3749 m
Cost for section (incl P $ 177,601.70
and A)
Cost / m $ 76.32
Cost / bbl $ 215.80
Volume built 593 bbl
Volume used 823 bbl
After nipple up and testing the BOPs, the 6.125” BHA was picked up and run in
the hole, tagging the top of the cement at 1375m. The cement was drilled
out while displacing the well to 9.2 ppg SBM. Three meters of new formation was
drilled to 1425m. A bottoms up was circulated round and an LOT test was
performed to 17 ppg EMW. The hole was directionally drilled to 3197m where it
was decided to change the bit. Seepage losses to this point averaged 4-5 bbls/hr.
In addition to chemicals added to maintain mud properties, 5 sx/hr of vinseal was
added for loss control. The shaker screens were screened up as soon as the mud
heated up to 200 mesh on the first 3 screens and a 180 mesh on the end. This
seemed to work well and the Vortex could handle the volume of cuttings. The mud
weight was increased according to the weight up schedule from 9.2 ppg to 10.2
ppg at TD of section.
The new bit was run in and drilling continued to TD – 3749m – 3509 TVD. A
flow check was done and then a swab test performed. A bottoms up was
circulated till the shakers were clean, a slug was pumped and the string was
pulled from the hole.
Halliburton rigged up to run logs and in this time mud for the plug and
abandonment section was prepared.
When logging was finished a 2 7/8” stinger was run in the hole to the cementing
point at 3365m. The SDF was displaced with 10.3 ppg WBM and BJ equipment
was rigged up. The 1st plug – 3365-2985m 14 ppg cement slurry was set. While
pulling up there was a 370K overpull at 3166m. A bottoms up was circulated and
the string was pulled to 2202m. Here a carbide sample was dropped and
circulated round. Gas came to surface at 1400 stks. The string was pulled to
surface for observation. 40 stands of tubing were left in the hole. The string was
Page 70
run in to 2208m and the 2nd plug was set. The string was pulled to 2063m and
plug #3 was set.
While the plugs were being set Brandt was centrifuging the OBM in the surface
pits to 9.1 ppg for backloading to the boat.
Four more plugs were set at 1918m, 1773m, 1628m, and 1454m. There were no
problems encountered setting any of these plugs.
The string was pulled and the 7” EZSV was run and set at 1389m – the 7” shoe.
Cement was pumped below and above the retainer then the 7” casing was cut at
281m. The string was pulled and the 9 5/8” retainer was run in and set at 275m.
The casing was pressure tested to 1000psi and cement was pumped below and
above this retainer as well. The casing was cut at 117m and the string was pulled
from the hole. The OBM pits were backloaded to the boat and the WBM pits were
dumped and cleaned for rig mobilization. The rig was prepared for skidding to new
location – B-VD-2X.
The mud for this section was Synthetic based mud system with Saraline 200 base
oil and 10 ppb Versacoat. We received 890 bbl of SBM from the previous well and
built additional volume as needed.
Initial mud weight was 9.2 ppg when drilling out the cement and shoe track. After
the LOT was done, the mud weight was gradually increased to 10.2 ppg prior to
TD.
During drilling, properties and volume in active system were maintained by
transferring premixed mud. All the chemicals were premixed prior to transfer to
active. The Rheology was controlled with Bentone 38 as primary viscosifier to
have 6 rpm reading between 6 and 10. Oil water ratio was maintained as between
79/21 and 80/20 with Saraline 200 as base oil. Versacoat was the primary
emulsifier in this system. The Electrical stability (ES) was maintained between 520
- 890 V. The premix mud was built with 10 ppb of Versacoat which was enough to
maintain the ES in active.
Lime was used to activate the emulsifier in the system, also to maintain the
alkalinity of the mud. While drilling, additions were made to the active to maintain
properties. Prior to logging 2ppb additional lime was added to the active.
Salinity was controlled with CaCl2 to have the WPS around 200,000 ppm in the
active system.
Hole Problems:
None
Other Problems:
The 2 7/8” stinger was snapped off at 3166m. 40 stands of tubing were left in the
hole.
Page 71
Solids Control Equipment Performance:
Solid control equipment which has used in this section was 4 ea Derrick/Super G
4 panel shale shakers, 2 ea Brandt HS2172 centrifuge and Brandt Vortex Dryer.
All shale shakers were run as needed with end configuration of 200,200,200,180
mesh on each shaker.
The centrifuges were run as needed to keep LGS in the desired range and
maintained the mud weight. One centrifuge was allocated to the vortex dryer and
one to the active system. The Brandt Vortex Dryer proved a valuable piece of
equipment. It was run to reduce surface losses at the shakers and saved SBM by
pumping it back into the system instead of into the ocean.
Cost Comments:
The cost for this section was $177,601.70. Seepage losses contributed to mud
lost costs. The solids control equipment contributed to saving whole mud costs.
9 It was found if we built higher weight mud in the slug pit and used this to
bleed into the active system, it was freeing up the barite line to build premix
when needed.
9 Adding excess emulsifier, lime and HTHP filtration control prior to logging
would give stable mud properties during this period.
Page 72
Solid Control Report on Vicksburg
GENERAL INFORMATION
COUNTRY Vietnam REPORT NO. -
LOCATION Vietnam DATE 23 Feb 08
OPERATOR Chevron MUD TYPE SBM
CONTRACTOR Vicksburg BIT SIZE Exploration 6-1/8"
WELL NO. CV-5X BIT TYPE
ENGINEER ONBOARD 3 LITHOLOGY
SCREEN USAGE 0 MIDNIGHT DEPTH 1787 METRE
DAILY SAFETY CARD 1 TOTAL DRILLED 364.98 METRE
EQUIPMENT OPERATION
Cent#1 AM Cent#2 AM Cent#1 PM Cent#2 PM Dryer AM Dryer PM
MODEL 2172 2172 2172 2172 Vortex Vortex
OPERATION HOURS 0 0 7 6.3 0 7
OPERATION TYPE Standby Standby Drill Drill Drill
SCROLL SPEED (RPM) 400 800
BOWL SPEED (RPM) 1500 2300
FEED RATE GPM 10 60
MAIN DRIVE TORQUE % MAX. 8 28
MUD WEIGHT IN PPG 12.6 9.2 15
MUD WEIGHT OUT PPG 9.2 8.9 12.6
DISCHARGE WEIGHT PPG 17.6 17.6 13.9
CUT POINT 3.4 0.3 2.4
CENTRATE - RETORTING RESULT
Cent#1 AM Cent#2 AM Cent#1 PM Cent#2 PM Dryer AM Dryer PM
SAMPLE TIME 19.00 19.00
SAMPLE DEPTH 1486.00 1486.00
CENTRATE WEIGHT PPG 9.21 8.91
RETORTED OIL % vol. 71.00 74.00
RETORTED WATER % vol. 18.00 18.00
SOLIDS DISCHARGE - RETORTING RESULT
Cent#1 AM Cent#2 AM Cent#1 PM Cent#2 PM Dryer AM Dryer PM
SAMPLE TIME 19.00 19.00 19.00
SAMPLE DEPTH 1486.00 1486.00 1486.00
RETORT WT - EMPTY (50 ML) A 843.10 840.00 841.20
RETORT WT + SAMPLE B 953.40 955.10 909.50
RETORT WT + DRY CUTTINGS C 935.20 938.20 897.80
GRAD. CYL. WT - EMPTY D 63.30 63.50 63.40
GRAD. CYL. WT + CONDENSATE E 81.10 80.10 74.80
VOLUME OF WATER F 8.00 8.00 9.00
VOLUME OF OIL G 15.00 13.00 3.00
RESULT
OOC% (Discharge) 8.88 7.47 3.51
Sampling Error (0.95 to 1.05) 1.00 1.00 1.00
O.O.C. (Gms/Kg) DRY 109.34 90.81 35.31
Daily Base Fluid Discharged, Kg.
COMMENTS
Cement job 7" CSG, WOC. M/U BHA, RIH. @17:00 Start drilling CV-5X on 6-1/8" section. Run 1xcentrifuge cut back mud weight from
dryer and 1xcentrifuge from sandtrap. Dryer running with slightly vibration. Check screen conditions.
9 At Centifuges
At Dryer
8
6
% OOC
0
23-Feb 24-Feb 25-Feb 26-Feb
Day
Abandonment Schematic
Page 78
CHEVRON VIETNAM
WELL ABANDONMENT SCHEMATIC
plug 6 1512-1628m
plug 5 1628-1773m
plug 4 1773-1918m
plug 3 1918-2063m
plug 2 2063-2208m
plug 1 TOC-2985 m
BOC-3365 m
displace from SBM to 10.3 ppg WBM
4/10/20083-3_PA Schematic_final_actual.xlsCV-5X
Time vs Depth, and Cost Summaries
Page 80
Rig on tow: 07:00 15 Feb 08 Time vs. Depth & Cost Rig released: 02:45 4 Mar 08
0 Well 52-CV-5X $7.00
$6.55
WOW
$6.27
500
$6.00
$5.53
$5.20
1,000
$4.88
$5.00
$4.65
$4.55
1,500
$4.24
TVD
(m) $3.96 $4.00
$3.89
Cost
2,000 $3.54
(MM)
Planned Depth $3.19
Actual Depth
$3.00
AFE $3.07
Actual Cost
2,500 $2.56
$2.20
Bit trip
$2.01 $2.00
$1.82
3,000 $1.74
$1.52
$1.21
$1.21
$1.00
3,500 $0.90
$0.60
$0.29
4,000 $0.07
$-
0 1 2 3 4 5 6 7 8 9 Days10 11 12 13 14 15 16 17 18 19 20
NPT Summaries
Page 82
Well CV-5X
NPT by Major Category
80
70
70
60
50
Hour 40
30
20 11.5
10 3
0 0 0
0
0
Cement Downhole Fluids Rig Repairs Surface Wait On Wellbore
Failures Equipment Problems
Failure
Category
This is the last page of this EOWR.
Page 84