Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Analysis, Design and Construction of Tie-Back Anchor For Coffer Dam

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

International Journal of Civil Engineering and Technology (IJCIET)

Volume 7, Issue 6, November-December 2016, pp. 371–377, Article ID: IJCIET_07_06_040


Available online at http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=7&IType=6
ISSN Print: 0976-6308 and ISSN Online: 0976-6316
© IAEME Publication

ANALYSIS, DESIGN AND CONSTRUCTION OF


TIE-BACK ANCHOR FOR COFFER DAM
H.P. Santhosh
Assistant Professor, Department of Civil Engineering,
MSRUAS, Bengaluru, Karnataka. India

R.K. Chethan Gowda


Assistant Professor, Department of Civil Engineering,
MSRUAS, Bengaluru, Karnataka, India

Dr. H.M. Rajashekhara Swamy


Professor & Head, Department of Civil Engineering,
MSRUAS, Bengaluru, Karnataka, India

ABSTRACT
The concept of a rock anchor system is to create an internally stable mass of soil and also to
stabilize the cofferdam that will resist external forces at an adequate level of serviceability. The
analysis and design of rock anchor concentrates on achieving secure against a range of potential
failure conditions of cofferdam. The design should limit movements of the soil and the cofferdam
while providing a practical and economical basis for construction. The design should consider the
mobilization of resistance by both anchors and cofferdam elements in response to loads applied to
the cofferdam particularly sea water [3].
This paper deals with the analysis, design and installation of cement grouted rock/ground
anchors and anchored systems. The analysis, design and construction procedure have been
demonstrated through a series of numerical analyse sand a parametric study has also been carried
out based on different anchorage capacity. It is concluded that 150 ton anchor capacity is effective
in controlling horizontal displacement of cofferdam at different levels. Also this paper deals with
the step by step analysis, design and construction procedure implemented at construction site.
Key words: Coffer dam, Pre-stressed Anchor, Grout, Bond length, Free length
Cite this Article: H.P. Santhosh, R.K. Chethan Gowda and Dr. H.M. Rajashekhara Swamy,
Analysis, Design and Construction of Tie-Back Anchor for Coffer Dam. International Journal of
Civil Engineering and Technology, 7(6), 2016, pp.371–377.
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=7&IType=6

1. INTRODUCTION
The concept of a rock anchor system is to create an internally stable mass of soil and also to stabilize the
cofferdam that will resist external forces at an adequate level of serviceability. The analysis and design of
rock anchor walls concentrates on achieving a final constructed cofferdam that is secure against a range of
potential failure conditions [6]. The design should limit movements of the soil and the cofferdam while

http://www.iaeme.com/IJCIET/index.asp 371 editor@iaeme.com


H.P. Santhosh, R.K. Chethan Gowda and Dr. H.M. Rajashekhara Swamy

providing a practical and economical basis for construction. The design should consider the mobilization
of resistance by both anchors and cofferdam elements in response to loads applied to the cofferdam.
A rock anchor is a long, high capacity reinforcement comprising a tube fixed into rock and tensioned to
a predetermined load. Rock anchors are used widely to improve the stability and load bearing
characteristics of a rock mass [4]. Cable rock anchors utilize bundles of steel wires to form a fixed
anchorage depth. In general the anchor length should under no circumstances should be less than either
2.5m or the free length less than 5m.
This paper deals mainly, but not exclusively, with the analysis and design of large anchors of the type
shown in Fig. 1 and with their application in cofferdam engineering, particularly for concrete gravity,
buttress and arch dams using STAAD Pro.

Figure 1 Brief Details of Rock Anchor

2. DESIGN BASICS
For designing 137 Ton capacity Rock Anchor
Taking total stress losses to 15% the anchor is designed for=137+20.55=157.55 Tons.
The following are to be evaluated
• Number of 15.2mm dia strands
• Bond length of anchor

3. MATERIAL PROPERTIES
3.1. Pre-stressing Strands
15.2 mm diameter seven wire pre-stressed strands

Table 1 Design parameters assumed in calculations


Components Assumed Parameters Remarks
Bond strength at Ultimate bond As per BS 8081/ IS:
Soil/Grout interface stress=0.4N/mm2 1343-1980
Bond strength at Ultimate bond As per BS 8081/ IS:
rout/Strand interface stress=0.4N/mm2 1343-1980

http://www.iaeme.com/IJCIET/index.asp 372 editor@iaeme.com


Analysis, Design and Construction of Tie-Back Anchor for Coffer Dam

Table 2 Safety factors used in design


Components Required F.O.S Remarks
Strand 2 As per BS 8081/ IS:
1343-1980
Rock/Grout Interface 2 As per BS 8081/ IS:
1343-1980
Grout/Strand Interface 2 As per BS 8081/ IS:
1343-1980

4. DESIGN FOR 157.55 TON ANCHOR FORCE


4.1. Design Parameters
Working load =157.55 Ton
Free length =variable
Drill hole dia. =150mm

4.2. Strand Properties


7 wires pre-stressing strands conforming to ASTM standards
Diameter =15.2 mm
Nominal Area=181mm2
Ultimate strength =260kN=26.0 Ton

4.3. Calculations

Number of strands required



=

157.55 ∗ 2
= = 12.119 ~12
26

Bond length required at Ground/Rock Interface



=
"∗# .∗ $
157.55 ∗ 9.81 ∗ 2
= = 16.399~17
" ∗ 150 ∗ 0.4

http://www.iaeme.com/IJCIET/index.asp 373 editor@iaeme.com


H.P. Santhosh, R.K. Chethan Gowda and Dr. H.M. Rajashekhara Swamy

Table 3 Anchor Design Details [1]

Sr. No. Description Quantity


1 No. of strands of 15.2 mm 12 Nos.

2 Bottom Cone-Length 30cm-dia 110mm 1 Nos.

3 Fixed length 17m


4 No of spacers in fixed length 14 Nos.

5 Free length 24m


6 Spacers in free length 8 Nos.

7 Separator Plate 1 Nos.


8 Sheathing Pipe-110mm dia. 23.5m

9 Thrust Plate 400x400x25


10 Bearing Plate 12T 15 dynamic prestress

11 Trumpet pipe with bursting 1Nos.


reinforcement and top plate of 10mm
of 400x400mm

5. GROUTING
The purpose of grouting is to provide permanent bond in the fixed length of the tendon. This also helps in
stabilizing drilled holes. Grout also fills up void spaces, expelling the water collection therein, if any.

5.1. Grout Properties [1]


• The cement grout is prepared based on a w/c ratio of 0.45 with 22.5 liters of water, 50kG of cement and
admixtures will be added as per requirement
• 100mm cube samples shall be taken from the grout mix at the mixer for the subsequent test
• The cement to be used for grouting is OPC (Grade-43) obtained from approved manufacturer/supplier
• The admixture CONBEX 100/equivalent will be used as 225 gm per cement bag

6. CONSTRUCTION PROCEDURE OF ANCHORING FOR COFFER DAM


• On completion of cofferdam, temporary earth filling will be carried out around the cofferdam. The width of
the temporary fill in the docks shall be 8m width at the top level with natural slope so that the Wagon driller
can hae sufficient space to move and anchor the anchors
• Depending on the site conditions provide proper slope to reach the anchoring level from the top of the
cofferdam to the anchor level.
• The Wagon driller will be positioned in the location and start the inclined boring at required level. Placing
and fixing of anchors, as per specifications including grouting will be carried out.
• On completion of inclined anchoring, excavation of soil up to required level will be done for full length. Fig.
2 shows the sectional elevation of 150 Ton Tie-Back Anchor.
The procedure adopted will be same for remaining anchors also. Care should be taken that excavation
should not start before completion of anchorage. Table 4 shows the time cycle for anchorage works.

http://www.iaeme.com/IJCIET/index.asp 374 editor@iaeme.com


Analysis, Design and Construction of Tie-Back Anchor for Coffer Dam

Figure 2 150 Ton Tie-Back Anchor for Cofferdam Support

Table 4 Time Cycle for Anchorage works


Description Quantity Rate of Wagon
Sr. unit Production Driller
No. Unit Hrs
1 Survey, Shifting, & Positioning 1 1 day 0.5
2 Drilling through diaphragm wall - 5 Mtrs 5
3 Placing of MS Pipe for free length 5 10 Mtrs
4 Rock drilling 10 30 Mtrs 6
5 Primary Grouting 6 30 Mtrs
6 Re-drilling & Flushing - 30 Mtrs 5
7 Homing of Cables --
8 Secondary Grouting 10 30 Mtrs
Total 16.5
Add 10% of Misc 1.65
Total time taken for 1 Anchor 19
Total time duration required for one Anchor (20hrs/day) 1

7. ANALYTICAL RESULTS
Static analysis was performed for cofferdam using STAAD Pro software to obtain displacement response
at different level. Fig. 3 shows the STAAD Pro modelling of pre-stressed anchor to the cofferdam. The
comparative result of displacement versus various prestressed force forcofferdam is shown in Fig. no. 4.

http://www.iaeme.com/IJCIET/index.asp 375 editor@iaeme.com


H.P. Santhosh, R.K. Chethan Gowda and Dr. H.M. Rajashekhara Swamy

Figure 3 STAAD Pro modelling of pre-stressed anchor

Figure 4 Variation of Displacement versus Pre-stressed Force

8. RESULTS AND DISCUSSION


The main application of geotechnical ground anchors is to prevent horizontal movement and ensure
stability of retaining structures including sheet pile, bored concrete pile and steel tubular pile walls. In
addition anchors are used to prevent additional movement or stabilize existing retaining walls, bridge
abutments, diaphragm walls and also cofferdams [5]. Cofferdams provides economical and practical
alternative to propping and all anchorages are post-tensioned to 110% working load. A series of numerical
analysis and parametric study shows that 150 tonne anchor capacity is effective in controlling horizontal
displacement of cofferdam at different levels.

REFERENCE
[1] IS: 1343-1980.Indian Standard Code of Practice for Prestressed Concrete, Bureau of Indian Standards,
Manak Bhavan, 9 Bahadur Shah Zafar Marg, New Delhi 110002.
[2] BS: 8081-1989.Code of Practice for Ground Anchorages, British Standards Institution, London,
England, 1989.
[3] Santhosh H.P., Dr. H.M. Rajashekhara Swamy, and Dr. D.L. Prabhakara.(2014) Construction of
Cofferdam-A Case Study, IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE), e-
ISSN:2278-1684, P-ISSN:2320-334X, PP45-50.

http://www.iaeme.com/IJCIET/index.asp 376 editor@iaeme.com


Analysis, Design and Construction of Tie-Back Anchor for Coffer Dam

[4] Monali Bhakare and A. R. Rajan.(2015)Case Study of Active Rock Anchor in Basement, International
Journal of Innovative Research in Science, Engineering and Technology, ISSN(Online) : 2319 – 8753,
Vol. 4, Issue 3, March 2015
[5] Peter George Fookes and Michael Sweeney, Stabilization and control of local rock falls and degrading
rock slopes, Quarterly Journal of Engineering Geology and Hydrology 1976, V.9 P37-55.
[6] E.T. Brown. (2015) Rock engineering design of post-tensioned anchors for dams – A review, Journal of
Rock Mechanics and Geotechnical Engineering, Volume 7, Issue 1, February 2015, Pages 1–13.
[7] Mohammed Y. Fattah, Hasan H. Joni and Ahmed S. A. Al - Dulaimy , Bearing Capacity of Strip
Footing Resting on Dune Sands Stabilized by Grouting with Lime – Silica Fume Mix , International
Journal of Civil Engineering an d Technology (IJCIET) , 7( 2 ), 2016, pp. 01 - 21 .
[8] Akshayakumar V. Hanagodimath, Dr. H. M. Rajashekar Swamy and Harshad R. Parate, Project
Performance in Real Time Construction Industry - A Case Study. International Journal of Civil
Engineering and Technology (IJCIET) , 7(5), 2016, pp.93–102.

http://www.iaeme.com/IJCIET/index.asp 377 editor@iaeme.com

You might also like