Eo T
Eo T
Contract time extensions are based on the ability to demonstrate that delays
have occurred in the construction scheduleaffecting project completion date.
All-time extensions are due to delays beyond the Contractor’s control, many of
them as part of change order requests. Time extension requests are normally
specified in contract’s provision and requesting time extensions should be
made following all steps and documentation under the contract guideline.
It is also important to highlight that time extensions will be denied for the
following reasons:
The time extension when properly presented must contain the following
supporting documents:
Your letter should be concise and must reference the contract clause that
allows the request, a schedule that can prove the delay reasons and the
proposed recovery plan.
It shall also include the damages if any, the amount of calendar or working
days being requested and the impacted activities delayed by the changes.
Sample Letter Approving a Time Extension:
The Contractor,
Contractor Address
Contract Name
Contract Number
Extension of time
I refer to your extension of time claim dated (insert date of the Claim).In
accordance with clause (insert the contract clause) of the General Conditions
of Contract, the Principal grants extension/s of time:
Insert number of days requested and reasons for the time extension.
Signed by
Authorized Person