MCGG Over Current Relay
MCGG Over Current Relay
MCGG Over Current Relay
Service Manual
R8054K
HANDLING OF ELECTRONIC EQUIPMENT
A person’s normal movements can easily generate electrostatic potentials of several
thousand volts. Discharge of these voltages into semiconductor devices when
handling circuits can cause serious damage, which often may not be immediately
apparent but the reliability of the circuit will have been reduced.
The electronic circuits of AREVA T&D products are immune to the relevant levels of
electrostatic discharge when housed in their cases. Do not expose them to the risk of
damage by withdrawing modules unnecessarily.
Each module incorporates the highest practicable protection for its semiconductor
devices. However, if it becomes necessary to withdraw a module, the following
precautions should be taken to preserve the high reliability and long life for which the
equipment has been designed and manufactured.
1. Before removing a module, ensure that you are a same electrostatic potential
as the equipment by touching the case.
2. Handle the module by its front-plate, frame, or edges of the printed circuit
board. Avoid touching the electronic components, printed circuit track or
connectors.
3. Do not pass the module to any person without first ensuring that you are both
at the same electrostatic potential. Shaking hands achieves equipotential.
4. Place the module on an antistatic surface, or on a conducting surface which is
at the same potential as yourself.
5. Store or transport the module in a conductive bag.
More information on safe working procedures for all electronic equipment can be
found in BS5783 and IEC 60147-0F.
If you are making measurements on the internal electronic circuitry of an equipment
in service, it is preferable that you are earthed to the case with a conductive wrist
strap.
Wrist straps should have a resistance to ground between 500k – 10M ohms. If a
wrist strap is not available you should maintain regular contact with the case to
prevent the build up of static. Instrumentation which may be used for making
measurements should be earthed to the case whenever possible.
AREVA T&D strongly recommends that detailed investigations on the electronic
circuitry, or modification work, should be carried out in a Special Handling Area such
as described in BS5783 or IEC 60147-0F.
TYPES: MCGG22
MCGG42*
MCGG52*
MCGG53
MCGG62*
MCGG63
MCGG82*
CONTENTS
SAFETY SECTION 5
1. DESCRIPTION 9
2. SETTINGS 10
2.1 Time delayed element settings 10
3. INSTALLATION 13
3.1 General considerations 13
3.2 Relay mounting 13
3.3 Unpacking 13
3.4 Storage 14
4. COMMISSIONING 14
4.1 Commissioning preliminaries 14
4.2 Instructions for commissioning the relay on any setting or curve 16
4.3 Instructions for commissioning the relay at settings calculated for a
particular application 18
5. MAINTENANCE 22
5.1 Power supply healthy test 22
6. PROBLEM ANALYSIS 23
6.1 General 23
6.2 Procedure 23
7. COMMISSIONING TEST RECORD 27
REPAIR FORM 29
Page 4
CONTENT
1. SAFETY SECTION 3
1.1 Health and safety 3
1.2 Explanation of symbols and labels 3
4. OLDER PRODUCTS 5
6. TECHNICAL SPECIFICATIONS 6
1. SAFETY SECTION
This Safety Section should be read before commencing any work on the
equipment.
1.1 Health and safety
The information in the Safety Section of the product documentation is intended to
ensure that products are properly installed and handled in order to maintain them in
a safe condition. It is assumed that everyone who will be associated with the
equipment will be familiar with the contents of the Safety Section.
1.2 Explanation of symbols and labels
The meaning of symbols and labels may be used on the equipment or in the product
documentation, is given below.
*NOTE: THE TERM EARTH USED THROUGHOUT THE PRODUCT DOCUMENTATION IS THE
DIRECT EQUIVALENT OF THE NORTH AMERICAN TERM GROUND.
4. OLDER PRODUCTS
Electrical adjustments
Equipments which require direct physical adjustments to their operating mechanism
to change current or voltage settings, should have the electrical power removed
before making the change, to avoid any risk of electrical shock.
Mechanical adjustments
The electrical power to the relay contacts should be removed before checking any
mechanical settings, to avoid any risk of electric shock.
Draw out case relays
Removal of the cover on equipment incorporating electromechanical operating
elements, may expose hazardous live parts such as relay contacts.
Insertion and withdrawal of extender cards
When using an extender card, this should not be inserted or withdrawn from the
equipment whilst it is energised. This is to avoid possible shock or damage hazards.
Hazardous live voltages may be accessible on the extender card.
Insertion and withdrawal of heavy current test plugs
When using a heavy current test plug, CT shorting links must be in place before
insertion or removal, to avoid potentially lethal voltages.
The MCGG 22, 42, 52, 62 and 82 are single, two, three or four pole overcurrent
relays, with separate measuring boards for each phase or earth fault input.
The MCGG 53 and 63 are three pole versions, having their phase inputs combined
onto one measuring board.
Each pole of the relay provides a choice of four IDMT characteristics and three
definite time characteristics. Additionally, each pole is provided with an
instantaneous high-set element which can be disabled if not required.
The seven versions of the relay covered by this manual are as follows :
MCGG 22 Single phase with instantaneous element
MCGG 42* Two phase with instantaneous elements
MCGG 52* Two phase plus earth fault with instantaneous element
MCGG 53 Two phase (with polyphase measurement) plus earth fault with
instantaneous elements
MCGG 62* Three phase with instantaneous elements
MCGG 63 Three phase (with polyphase measurement) with instantaneous
element
MCGG 82* Three phase plus earth fault with instantaneous elements
The rated current of the relay (In) is either 1A or 5A and appears on the module
rating label.
The relay comprises a case and single plug-in module, which utilises either one or
two 28 way terminal blocks. The module is designed with ease of assembly and
maintenance in mind, with a switch mode dc-dc converter on a mother-board at the
back of the module. This board carries connectors so that printed circuit boards
carrying timing/measuring circuitry which can derive IDMT and definite time
characteristics can be plugged in.
* Refer to AREVA T&D for manual applicable to MCGG 42, 52, 62 and 82 relays
with the last four model number digits 0501, 0751 or 1001.
Page 9
Section 2. SETTINGS
These settings are determined by positioning miniature switches on the relay front
panel. There are two groups of switches on each relay pole, the upper group sets the
time delayed element, the lower group sets the instantaneous element.
Normally, switch settings are only altered during commissioning. If switch setting
changes under load are unavoidable, follow the procedure outlined in Section 2.1.6
to minimise the possibility of accidental tripping.
2.1 Time delayed element settings
The upper group of switches is sub-divided into three sub-groups which enable the
time delayed element to be set.
2.1.1 Time delayed current setting switches, I = ∑ x In
The upper seven blue switches are used to set the required current sensitivity setting.
Each switch may be positioned to the left or right, the setting level being indicated at
the same horizontal level as the switch, to the left or right of the switches or bank of
switches.
The overall setting is obtained by adding the indicated values of the individual switch
settings, and may be set in steps of 5% over the range 0.05 to 2.4 x In.
2.1.2 Curve selection switches
The three black switches positioned in the upper group of switches are used to select
the required time curve from the choice of four inverse time and three definite time
curves. The characteristic curve equations are listed below. The eighth switch
combination sets the relay into the ‘trip test’ mode.
Switch
Position
0 1
0.14
SI Standard inverse t= s 0 <- - -
(I0.02 – 1)
0 <- - -
0 <- - -
13.5
VI Very inverse t= s 1 - - ->
(I – 1)
0 <- - -
0 <- - -
80
EI Extremely inverse t= s 0 <- - -
(I2– 1)
1 - - ->
0 <- - -
120
LTI Long time inverse t= s 1 - - ->
(I – 1)
1 - - ->
0 <- - -
Page 10
Where I is the ratio of the applied current to the setting current Is.
Page 11
2.1.5 Relay setting example
In this case:–
0.1 <- - 0.05 Is = (0.1 + 0.1 + 0.2 + 0.8) x In
0.1 <- - 0
Current 0.2 <- - 0 = 1.2 x In
setting 0.4 - -> 0 Is = ∑ x In
switches 0.4 - -> 0
0.4 - -> 0
0.8 <- - 0
Curve 0 <- - 1
select 0 <- - 1 Standard inverse curve
switches 0 <- - 1
0.025 - -> 0.05
0 - -> 0.05
TMS 0 <- - 0.1 TMS = (0.05 + 0.05 + 0.4)x
switches 0 <- - 0.2 xt=∑
0 <- - 0.2 = 0.5x
0 - -> 0.4
Instant- 0 <- - 1 Iinst = (8 + 2) x Is
aneous 0 - -> 2
current 0 <- - 4 Iinst = ∑ x Is = 10 x 1.2 x In
setting 0 - -> 8
switches 0 <- - 16 = 12 x In
0 <- - ∞
If the above settings were applied to a 1A relay
Current setting = 1.2A
Curve = Standard Inverse
TMS = 0.5 x
Instantaneous
current setting = 12A
(Currents are secondary values.)
2.1.6 Procedure for resetting the MCGG DIL switches in service
Normally settings are changed with the ac input and/or the dc auxiliary supply
disconnected during commissioning at the required setting.
If either the current setting (Is) or the highset threshhold setting (Iinst) has to be altered
in service then, to minimise the likelihood of any resultant tripping, the following
procedure should be adopted:
1. Temporarily disable the highset element by moving the Iinst 0/∞ switch from the
left (0) to the right (infinity) position.
2. Increase the Is current setting to the maximum by moving all Is switches to left
hand positions. Set the new setting current by moving to the right the switches
required to achieve the new setting. This ensures that an intermediate Is value
lower than the load current is not accidentally applied, resulting in operation of
either the highset or the IDMT element.
Page 12
3. Move the highset (Iinst) switches to the new setting required.
4. Re-enable the highset element by moving the Iinst 0/∞ switch from the infinity
(right) to the 0 (left) position.
Note that the TMS switches and the black curve select switches can be moved at
any time when the load current is less than the setting current (ie. when the green
LED is off) without affecting operation.
Section 3. INSTALLATION
(1) Test facilities: MMLG test block should be positioned at the right of
the tier.
(2) Current relays: MCGG overcurrent relay should be adjacent to test block.
(3) Directional control: METI directional relay should be adjacent to, and to the left
of the MCGG relay it is controlling.
(4) Other relays: Any other relays required for the relay scheme, should be
positioned to the left of the tier viewed from the front.
3.2.2 For individually mounted relays, an outline diagram is normally supplied
showing panel cut-outs and hole centres, these dimensions will also be found
in Publication R6054.
3.3 Unpacking
Care must be taken when unpacking and installing the relays so that none of the
parts is damaged or their settings altered and they must at all times be handled by
skilled persons only. The installation should be clean, dry and reasonably free from
dust and excessive vibration. The site should be well lit to facilitate inspection.
Page 13
Relays which have been removed from their cases should not be left in situations
where they are exposed to dust or damp. This particularly applies to installations
which are being carried out at the same time as constructional work.
3.4 Storage
If relays are not installed immediately upon receipt they should be stored in a place
free from dust and moisture in their original cartons and where de-humidifier bags
have been included in the packing they should be retained. The action of the
de-humidifier crystals will be impaired if the bag has been exposed to ambient
conditions and may be restored by gently heating the bag for about an hour, prior to
replacing it in the carton.
Dust which collects on a carton may, on subsequent unpacking, find its way into the
relay; in damp conditions the carton and packing may become impregnated with
moisture and the de-humidifying agent will lose its efficiency.
Storage temperature –25° to +70°C.
Section 4. COMMISSIONING
Page 14
4.1.6 Main current transformers
DO NOT OPEN THE SECONDARY CIRCUIT OF A LIVE CT SINCE THE HIGH
VOLTAGE PRODUCED MAY BE LETHAL TO PERSONNEL AND COULD DAMAGE
INSULATION.
4.1.7 Test block type MMLG
If test block type MMLG is provided, the connections should be checked to the
scheme diagram, particularly that the supply connections are to the ‘live’ side of the
test block (coloured orange) and with terminals allocated with odd numbers (1, 3, 5,
7 etc.) and also that the dc connection is routed via test block terminals 13 and 15.
4.1.8 Terminal allocation
Reference should be made to the diagram supplied with every relay.
4.1.9 Test equipment required:
Overcurrent test set with timing facilities
Multifinger test plug type MMLB 01 for use with test block type MMLG when required
Calibrated multimeter 0 – 10A ac 0 – 250V dc
4.1.10 General
Secondary injection commissioning tests should be carried out using a portable single
phase overcurrent test equipment, preferably injected via test block type MMLG. It is
most important that the test equipment is capable of injecting an undistorted
sinusoidal current waveform.
4.1.11 DC supply
Remove the relay module from its case. The incoming supply should be checked at
the relay case terminals. Relay case terminal 13 should be positive with respect to
terminal 14 and the incoming voltage must be within the operative range specified
below.
DC rating (V) Operative range (V)
24/54 19 – 60
48/125 37.5 – 150
110/250 87.5 – 300
CAUTION: The relay is designed to withstand an ac ripple component of up to
±12% of the nominal dc auxiliary supply voltage. However, in all cases
the peak value of the dc supply must not exceed the maximum specified
operating limit.
Operation of the supply battery charger with the batteries disconnected could cause
damage due to overvoltage.
4.1.12 Relay CT shorting switches
With the relay removed from its case, check that each CT shorting switch is closed by
injecting rated current into each phase circuit. The rated current of the relay (In) is
either 1A or 5A and appears on the module rating label.
Page 15
4.1.13 Energise relay
For secondary injection testing using test block type MMLG, insert test plug type
MMLB 01 with the required main CT shorting links fitted. It may then be necessary to
link across the front of the test plug to restore the dc supply to the relay.
Isolate the relay trip contacts and insert the module. Ensure that the curve selection
switches on each pole are set to any position except 111. Connect the dc supply to
the relay. The relay has a non-volatile memory which remembers the state (ON or
OFF) of the LED trip indicators when the relay was last powered, and therefore some
or all of the indicators may be illuminated.
Press the RESET button and check that the LEDs on all of the poles are illuminated.
Release the RESET button and check that the LEDs reset.
Note: To commission the relay with the settings and curve required for the
particular application, omit Section 4.2 and proceed directly to Section 4.3.
If the settings/curve will be altered by the user without re-commissioning the
relay, complete the tests in both Sections 4.2 and 4.3.
4.2 Instructions for commissioning the relay on any setting or curve
4.2.1 Current sensitivity switches (Is = ∑ x In)
This test checks that each of the front panel current selector switches operates
correctly. The green relay start LED provided on the front panel gives indication when
the input current exceeds the setting current Is.
Inject single phase current into a phase circuit and slowly increase the current until
the start LED lights. Repeat the test for each switch in turn and check that the pick up
current is within the range shown in Table 4.1
Switch selections: Current (Is = ∑ x In) : as shown
Curve ( ) : any
TMS (x t = ∑) : any
Instantaneous (Iinst = ∑ x Is) : any
Is AC current operate level (amps)
( x In) In = 1A In = 5A
0.05 0.05 - 0.055 0.25 - 0.275
0.10 0.10 - 0.110 0.50 - 0.550
0.15 0.15 - 0.165 0.75 - 0.825
0.25 0.25 - 0.275 1.25 - 1.375
0.45 0.45 - 0.495 2.25 - 2.475
0.45 0.45 - 0.495 2.25 - 2.475
0.45 0.45 - 0.495 2.25 - 2.475
0.85 0.85 - 0.935 4.25 - 4.675
Table 4.1
Note: 1. The above current levels make no allowance for errors in measurement of
the ac current amplitude
2. The reference range for MCGG 22, 42, 52, 62 and 82 relays is 0.05In
to 2.4In
3. The reference range for MCGG 53, 63 relays is 0.2In to 2.4In
These tests should be repeated for each pole of the relay.
Page 16
4.2.2 Curve selection switches ( )
Connect the relay time delayed output contacts to both trip the test set, and to stop
a timer. Inject single phase current into the pole under test at a current level of 10 x
rated current.
Check that the operating time for the relay for each curve setting is within the range
shown in Table 4.2.
Switch selections: Current (Is = ∑ x In) : 1 x In
Curve ( ) : as shown
TMS (x t = ∑) : 1xt
Instantaneous (Iinst = ∑ x Is) : ∞
Selected curve Operating time range at 10 x Is (seconds)
Nominal Range
SI Standard inverse 2.97 2.82 – 3.12
VI Very inverse 1.50 1.42 – 1.58
EI Extremely inverse 0.808 0.747 – 0.869
LTI Long time inverse 13.3 12.6 – 14.0
D2 Definite time 2s 2.00 1.94 – 2.06
D4 Definite time 4s 4.00 3.88 – 4.12
D8 Definite time 8s 8.00 7.76 – 8.24
Table 4.2
Note: The above operating time ranges make no allowance for errors in
measurement of the ac current amplitude.
These tests should be repeated for each pole of the relay.
4.2.3 Time multiplier setting switches (x t = ∑)
Connect relay time delayed output contacts to both trip the test set and to stop a
timer. Inject single phase current into the pole under test at a current level of 10 x
rated current.
Measure the operating time on the SI curve at the TMS switch positions shown in
Table 4.3.
Switch Selections: Current (Is = ∑ x In) : 1 x In
Curve ( ) : SI standard inverse
TMS (x t = ∑) : as shown
Instantaneous (Iinst = ∑ x Is) : ∞
TMS value Operating time range at 10 x In (seconds)
Nominal Range
0.125 x t 0.371 0.322 – 0.42
0.2 x t 0.594 0.534 – 0.654
0.9 x t 2.67 2.48 – 2.87
Table 4.3
Note: The above operating time ranges make no allowance for errors in
measurement of the ac current amplitude.
These tests should be repeated for each pole of the relay.
Page 17
4.2.4 Instantaneous current setting switches (Iinst = ∑ x Is)
WARNING
THE RELAY MAY BE DAMAGED BY APPLYING EXCESSIVE CURRENT FOR LONG
DURATIONS DURING TESTING. IT IS IMPORTANT TO FOLLOW THE INSTRUCTIONS
PRECISELY.
The following test checks that the instantaneous current switches are operative.
The instantaneous trip output contacts must be connected to trip the test set.
It is recommended that the time delay element is set to operate in 4s and that the time
delay output contacts are also wired to trip the test set, to prevent relay damage if
current is applied for too long.
The current level should be set and then suddenly applied; DO NOT INCREASE THE
CURRENT SLOWLY since this may damage the relay. The test must be repeated for
each of the switch positions shown in Table 4.4 initially at a higher current level to
check that the instantaneous element operates and then at a lower level, at which the
element should not trip.
Switch selections: Current (Is = ∑ x In) : 0.5 x In
Curve ( ) : D4 definite time 4s
TMS (x t = ∑) : 1xt
Instantaneous (Iinst = ∑ x Is) : as shown
Instantaneous Current level (A) Iinst response
value In = 1A In = 5A
1 x Is 0.55 2.75 Trip
0.50 2.5 No trip
2 x Is 1.05 5.25 Trip
0.95 4.75 No trip
4 x Is 2.1 10.5 Trip
1.9 9.5 No trip
8 x Is 4.2 21.0 Trip
3.8 19.0 No trip
16 x Is 8.4 42.0 Trip
7.6 38.0 No trip
Table 4.4
Note: The above current ranges make no allowance for errors in measurement of
the ac current amplitude.
These tests should be repeated for each pole of the relay.
4.3 Instructions for commissioning the relay at settings calculated for a
particular application
4.3.1 General
If there is any possibility that the relay settings are to be changed during the life of
the relay without re-commissioning, then the instructions in Section 4.2 should be
completed initially.
Ensure that the main system current transformers are shorted before isolating the relay
from the current transformers in preparation for secondary injection tests.
Page 18
4.3.2 Relay CT shorting switches
If not previously checked, and with the relay module removed from its case, check
that each CT shorting switch is closed by injecting rated current into each phase
circuit. The rated current of the relay (In) is either 1A or 5A and appears on the
module rating label.
4.3.3 Energise relay
Connect the dc supply to the relay and record the dc voltage at terminals 13 (+ve)
and 14.
4.3.4 Trip test
Set the curve selection switches to 111 (test mode), on one pole of the relay.
Check that the LEDs associated with that pole of the relay flash at a frequency of
approximately once per second.
Press and hold the RESET button. The LEDs of the other poles of the relay should
illuminate continuously, whilst those of the pole under test should continue to flash.
After approximately 6 seconds, the time delayed and instantaneous output elements
associated with the pole under test should trip and at the same time, the LEDs should
then illuminate continuously on that pole.
Release the RESET button. The output elements should reset.
Change the curve selection switches from 111 (test mode) to 101 (4s definite time),
and repeat the test on the other poles of the relay.
4.3.5 Instantaneous current settings (Iinst = ∑ x Is)
WARNING
THE RELAY MAY BE DAMAGED BY APPLYING EXCESSIVE CURRENT FOR LONG
DURATIONS DURING TESTING. IT IS IMPORTANT TO FOLLOW THE INSTRUCTIONS
PRECISELY.
This test is to check that the instantaneous current level as set, is correct.
The instantaneous trip output contacts must be connected to trip the test set.
It is recommended that the time delay element is set to operate in 4s and that the time
delay output contacts are also connected to trip the test set, to prevent relay damage
if current is applied for too long.
The current level should be set and then suddenly applied; DO NOT INCREASE THE
CURRENT SLOWLY since this may damage the relay.
Two tests, shown in Table 4.5 below, are specified for the particular x Is setting
required for the application. Initially the higher current level should be applied to
check that the instantaneous element operates and then the lower current level should
be applied to check that no trip occurs.
Switch selections: Current (Is = ∑ x In) : 0.5 x In
Curve ( ) : D4 definite time 4s
TMS (x t = ∑) : 1xt
Instantaneous (Iinst = ∑ x Is) : As specified for the application
Page 19
Instantaneous Current level (A), In = 1A Current level (A), In = 5A
setting (x Is) No trip Iinst Trip Iinst No trip Iinst Trip Iinst
1 0.50 0.55 2.5 2.75
2 0.95 1.05 4.75 5.25
3 1.4 1.6 7.1 7.9
4 1.9 2.1 9.5 10.5
5 2.3 2.7 11.8 13.2
6 2.8 3.2 14.2 15.8
7 3.3 3.7 16.6 18.4
8 3.8 4.2 19 21
9 4.2 4.8 21 24
10 4.7 5.3 23 27
11 5.2 5.8 26 29
12 5.7 6.3 28 32
13 6.1 6.9 30 35
14 6.6 7.4 33 37
15 7.1 7.9 35 40
16 7.6 8.4 38 42
17 8.0 9.0 40 45
18 8.5 9.5 42 48
19 9.0 10.0 45 50
20 9.5 10.5 47 53
21 9.9 11.1 49 56
22 10.4 11.6 52 58
23 10.9 12.1 54 61
24 11.4 12.6 57 63
25 11.8 13.2 59 66
26 12.3 13.7 61 69
27 12.8 14.2 64 71
28 13.3 14.7 66 74
29 13.7 15.3 68 76
30 14.2 15.8 71 79
31 14.7 16.3 73 82
Table 4.5
Note: The above current levels make no allowance for errors in measurement of the
ac current amplitude.
This test should be repeated for each pole of the relay.
4.3.6 Instantaneous element operating time
It is not recommended that the instantaneous element operating time is checked, due
to the possibility of damage to the relay. The tests of section 4.3.5 and the previous
works tests provide adequate assurance that the operating time is correct.
Page 20
4.3.7 Curve selection ( )
The following test checks the selected curve characteristic at specified points.
WARNING
THE TEST EQUIPMENTS THERMAL LIMIT MAY BE EXCEEDED IF THE LONG TIME
INVERSE CURVE IS SELECTED.
Connect the relay time delayed output contacts to both trip the test set, and to stop a
timer. Inject single phase current into a convenient phase of each separate time delay
element at the current levels specified below for the particular curve selection
specified for the application.
Check that the operating time for the relay is within the range shown in Table 4.6
below.
Table 4.6 details the inverse time operating time curves at 2 x, 5 x, 10 x and
20 x Is. It is recommended that results are recorded at 10 x followed by 2 x Is,
the others are listed in case they are specifically requested by the user.
Definite time characteristics should be checked at 2 x Is only.
Switch selections: Current (Is = ∑ x In) : 1 x In
Curve ( ) : As specified for the application
TMS (x t = ∑) : 1xt
Instantaneous (Iinst = ∑ x Is) : As specified for the application
Curve Operating time at specified current (seconds)
2 x Is 5 x Is 10 x Is 20 x Is
Nom. Range Nom. Range Nom. Range Nom. Range
SI 10.03 9.52 - 10.6 4.28 4.06 - 4.50 2.97 2.82 - 3.12 2.27 2.15 - 2.38
VI 13.50 12.8 - 14.2 3.38 3.20 - 3.55 1.50 1.42 - 1.58 0.711 0.675 - 0.746
EI 26.7 24.6 - 28.7 3.33 3.08 - 3.59 0.808 0.747 - 0.869 0.201 0.170 - 0.231
LTI 120 114 - 126 30.0 28.5 - 31.5 13.3 12.6 - 14.0 6.32 6.00 - 6.64
D2 2.00 1.94 - 2.06
D4 4.00 3.88 - 4.12
D8 8.00 7.76 - 8.24
Table 4.6
Note: The above operating time ranges make no allowance for errors in
measurement of the ac current amplitude.
These tests should be repeated for each pole of the relay.
4.3.8 Current sensitivity setting (Is = ∑ x In)
This test checks the sensitivity of the relay at the selected setting. The green relay start
LED provided on the front panel gives indication when the input current exceeds the
setting current Is.
Switch selections: Current (Is = ∑ x In) : As specified for the application
Curve ( ) : As specified for the application
TMS (x t = ∑) : 1xt
Instantaneous (Iinst = ∑ x Is) : As specified for the application
Slowly increase the applied single phase current until the start LED lights.
The minimum value of current to cause the start LED to light should be recorded.
Page 21
This level should be greater than
1 x Is x In
and less than
1.1 x Is x In
Note: These levels make no allowance for errors in measurement of the ac current
amplitude.
These tests should be repeated for each phase of the relay.
4.3.9 Operating time at final selected settings
The relay switches should be set to the specified settings and the operating time of the
time delay circuit (t) should be measured at 2 x Is.
The measured time should be within ±5% or 40ms of the value computed from the
previous time measured at 2 x Is (in test 4.3.8) multiplied by selected TMS settings.
Switch selection: Current (Is = ∑ x In)
Curve ( ) As specified for
TMS (x t = ∑) the application
Instantaneous (Iinst = ∑ x Is)
Repeat test 4.3.9 for each pole of the relay.
4.3.10 Final check
Carefully check that the LED indicators and relay output contacts are all operating
correctly and that with the relay front cover replaced, the reset button satisfactorily
operates/resets the LEDs.
If required, check that the relay output contacts trip the circuit breaker, connect the
relay through to the main CTs and remove the CT shorts.
Section 5. MAINTENANCE
Page 22
Section 6. PROBLEM ANALYSIS
6.1 General
These instructions enable a fault to be located to sub-assembly level. Fault finding at
component level is not recommended.
The major reasons for this are as follows :
(1) Fault finding on printed circuit boards (pcbs) requires specialised knowledge and
equipment.
(2) Components used in manufacture are subjected to strict quality control procedures
and in certain cases selected for particular characteristics. Metal oxide
semiconductor (MOS) components are used which require very careful handling.
(3) Damage can be caused to printed circuit board track unless extreme care is used
in replacement of components.
(4) Replacement of certain components will require recalibration of the relay.
In the event of a faulty sub-assembly being found, it is recommended that the
relay is returned to AREVA T&D or sent to a competent service centre for the work
to be carried out. However, replacement sub-assemblies can be made available from.
AREVA T&D upon request, provided the relay model number and serial number are
quoted. Recalibration of the relay is not required afterthe replacement of a sub-assembly.
Note: Before fault finding on the relay is commenced, all external connections and
supplies to the relay should be checked to ensure that the fault lies within the
relay.
6.2 Procedure
The following tests should only be carried out under laboratory conditions, when a
faulty relay has been identified and removed from its case.
6.2.1 Gaining access to the relay internal circuitry
The method for removing the frontplate on the Series 2 MCGG varies according to
the date at which the relay was supplied.
The earliest types are identified by the presence of one pozidrive type screw in both
the top and bottom plate of the module towards the left-hand side, adjacent to the
frontplate.
To remove the frontplate on this type, firstly remove the plastic handle strips from the
module handles to expose the two screws which secure the relay frontplate to the
module. These are located to the right-hand side of each handle and are recessed so
that their heads lie flush with the relay frontplate. Remove these two screws, together
with the two pozidrive screws mentioned above to release the frontplate.
Later types are not fitted with the two pozidrive type screws fitted in the top and
bottom plate of the module.
To remove the frontplate on this type, firstly remove the plastic handle strips from the
module handles. Next, remove all the screws which secure the handles to the
frontplate.
With the handles removed, remove the two remaining screws to release the
frontplate.
Page 23
On all versions of the MCGG 22, remove the handle strips followed by the handle
securing screws. Finally, with the handles removed, unscrew the remaining two
screws to release the frontplate.
With the frontplate freed from the rest of the module, tension on the wires to the flag
reset switch should be avoided. If necessary, the switch can be unscrewed from the
frontplate.
The latest types utilize clip-in type moulded handles. The black frontplate securing
screws are of the pozidrive type and are directly accessible without removing the
handles. Removal of these screws will release the frontplate. On these types, the reset
switch is not attached to the frontplate.
The measuring/timing PCBs can now be accessed as required.
6.2.2 DC internal power supply check
This can easily be done by pressing the reset button on the front panel.
All LEDs should illuminate if all measuring boards are operating satisfactorily.
Upon releasing the push-button, all LEDs should be extinguished.
Note: This test may be carried out at any time whilst the relay is in service without
affecting its ability to measure or trip.
6.2.3 Output relay trip test
Set the curve selection switches on each measuring board, in turn, to the ‘111’
position.
This should result in the three LEDs on that measuring board flashing at a rate of one
per second.
If the reset bushbutton is then held pressed for approximately six seconds, both output
relays associated with that measuring board should energise, the LEDs will stop
flashing and remain in the on state until the push button is released.
In this way each measuring board, the associated output relays and their changeover
contacts can each be checked individually without the need for any input current
being applied.
Output miniature relays are an integral part of the module’s mother board, so in the
event of such a unit failing, the whole relay should be returned to AREVA T&D for repair.
Page 24
Relay type Apply 2x rated current Measure 20mA ± 10%
to terminals (2A or 10A) at terminals
MCGG22 27 and 28 23 and 24
MCGG42 21 and 22 49 and 50
25 and 26 45 and 46
MCGG52 21 and 22 49 and 50
25 and 26 45 and 46
27 and 28 43 and 44
MCGG53 21 and 22 49 and 50
27 and 28 43 and 44
MCGG62 21 and 22 49 and 50
23 and 24 47 and 48
25 and 26 45 and 46
MCGG63 21 and 22 49 and 50
MCGG82 21 and 22 49 and 50
23 and 24 47 and 48
25 and 26 45 and 46
27 and 28 43 and 44
If 20mA is not obtained at the directional control terminals, then firstly the relay
wiring must be checked, both at the module contact moulding and at the pcb
connectors. If these are sound, then the input transformer of the faulty pole must be
replaced.
6.2.5 Measuring/timing circuitry tests
In the event that one or more poles of the relay is found to be inoperative and the
power supply and input transformer have been proved to be working correctly, then
the measuring/timing pcb (ZJ0091 on earlier versions, ZJ0161 on later versions)
must be suspected. In order to establish that this pcb is faulty, a ‘known-good’ pcb
should be moved from another position in the module, and tested in the position
where the suspect pcb had failed to work. Section 6.2.1 describes how to gain
access to the measuring boards. The measuring boards to be interchanged should
gently be pulled out from the mother board. When the measuring boards are
replaced, care should be taken to ensure that their connecting pins are correctly
aligned with the rear socket. See notes 1 and 2 below.
If this pcb works satisfactorily in this position, it can be assumed that the suspect pcb
is faulty and should be replaced. If, however, this pcb does not work either, the
mother-board should be suspected necessitating that the whole relay should be
returned to AREVA T&D for repair.
Note 1: Under no circumstances should current be injected into any of the relay
inputs when the corresponding measuring/timing pcb has been removed
from the module.
Note 2: At least one of the measuring/timing pcbs must be located in the module
when the dc auxiliary supply is connected to the module or damage to the
power supply circuitry may result.
Page 25
Page 26
Section 7. COMMISSIONING TEST RECORD
Page 27
Test results
Curve ......................
Phase A Phase B Phase C E.F.
Is ..................................
Phase A Phase B Phase C E.F.
TMS .......................
Phase A Phase B Phase C E.F.
_____________________________________ ______________________________________
Commissioning Engineer Customer Witness
_____________________________________ ______________________________________
Date Date
Page 28
REPAIR FORM
Please complete this form and return it to AREVA T&D with the equipment to be repaired. This
form may also be used in the case of application queries.
AREVA T&D
St. Leonards Works
Stafford
ST17 4LX
England
Date: ___________________
Frequency ___________________
continued overleaf
!
6. What did happen?
Signature Title